CONTENTS
1. SCOPE ...............................................................................................................3
2. REFERENCE DOCUMENTS ..............................................................................3
2.1 Codes and Standards .........................................................................................3
2.2 Company Specifications......................................................................................3
2.3 Conflict and Clarification .....................................................................................3
3. QUALITY REQUIREMENTS ...............................................................................4
4. GENERAL...........................................................................................................4
5. MARKERS ..........................................................................................................4
5.1 Kilometer Markers ...............................................................................................4
5.2 Pipeline Warning Sign.........................................................................................4
5.3 ROU Boundary Marker .......................................................................................5
5.4 Navigable Waterway Pipeline Crossing Warning Sign ........................................5
DNEP000-P30-J00-504_00 Page 2 of 5
RELIANCE GAS PIPELINES LIMITED
DAHEJ NAGOTHANE ETHANE PIPELINE
SPECIFICATION FOR MARKERS
1. SCOPE
This specification covers the minimum requirements for supply, fabrication and
erection of pipeline markers to be installed by CONTRACTOR at various locations
along the route of a cross-country pipeline.
This specification shall be read in conjunction with the conditions of all
specifications and documents included in the CONTRACT between COMPANY and
CONTRACTOR.
2. REFERENCE DOCUMENTS
DNEP000-P30-J00-504_00 Page 3 of 5
RELIANCE GAS PIPELINES LIMITED
DAHEJ NAGOTHANE ETHANE PIPELINE
SPECIFICATION FOR MARKERS
3. QUALITY REQUIREMENTS
4. GENERAL
CONTRACTOR shall supply, fabricate and install the Pipeline Markers along the
pipeline route. The location of markers as indicated in the approved drawings shall
be treated for guidance purpose only and the exact location of the markers shall be
based on AS BUILT drawings and as directed by COMPANY.
The pipeline markers shall be fabricated and installed in accordance with the
standard drawings included herein. Before start of fabrication of the markers, the
CONTRACTOR shall prepare and submit for COMPANY’s approval, the detailed
scheme for the marker plates as applicable for the project. All the markers shall be
painted in accordance with the requirements of Specification for Painting
(Specification No. DNEP000-P30-J00-514). The painting scheme shall be suitable
for Normal Corrosive Environment unless otherwise stated in the scope document..
The pipeline markers shall be installed, as far as possible, at locations such that
they do not cause any hindrance to the regular use of the land or to the traffic.
5. M ARKERS
DNEP000-P30-J00-504_00 Page 4 of 5
RELIANCE GAS PIPELINES LIMITED
DAHEJ NAGOTHANE ETHANE PIPELINE
SPECIFICATION FOR MARKERS
- And or any other location as shown in the approved drawings and as directed by the
COMPANY.
Each post shall be fitted with two number warning plates. One warning plate shall
be inscribed with text in English and the other with text in local language.
Where warning sign is within 200 m of KP point, the same shall be provided with KP
post with warning plate indicating crossing chainage.
Pipeline Warning Sign shall identify the existence of the pipeline and display the
name of the COMPANY, with an emergency telephone number, as shown in
Standard Drawing No. DNEP000-P14-J45-511.
DNEP000-P30-J00-504_00 Page 5 of 5