Detailed activity sheet

Work Activity Investigators Proposed


Proposed date of Status /
Package (Overarching Objectives involved in the date of
completion Remark
(WP) / Targeted Deliverables) activity start
WP1 Finalization of syngas to Tirupathi Naidu Ch, 01.10.2017 30.11.2017 Completed
methanol process scheme I Nagamohan
& K Rasesh
WP2 Final Process Flow Tirupathi Naidu Ch, 15.11.2017 15.12.2017 Completed
Diagram (PFD) and I Nagamohan,
Process & Instrumentation C Thirugnanam
Diagram (P&ID) & K Rasesh
WP3 Finalization of Tirupathi Naidu Ch, 1.12.2017 30.01.2018 Completed
Specifications of all the I. Nagamohan,
equipment’s and materials A. Gunasekaran,
N. Sivarama Krishna,
AK Pandey
& K Rasesh
WP4 Indenting and Tirupathi Naidu Ch, 15.12.2017 31.12.2019 Received all
procurement of I. Nagamohan, items except
equipment’s and materials A. Gunasekaran, syngas to
N. Sivarama Krishna, methanol
AK Pandey module. Partly
& K Rasesh supplied in
syngas to
methanol
module. Balance
items expected
by 31.12.2019
WP5 Modifications have been D Satya Mohan Rao 1.06.2018 31.12.2018 Completed
carried out in existing &
gasification facility N. Sivarama Krishna
WP6 Erection, Commissioning I. Nagamohan, 1.10.2018 15.05.2019 Completed
and integration of O2 D Satya Mohan Rao,
plant and Liquid CO2 tank A. Gunasekaran,
with existing gasification &
plant N. Sivarama Krishna
WP7 Preparation of control K Rasesh, 01.04.2018 31.05.2018 Completed
logics, startup and Tirupathi Naidu Ch,
shutdown procedures for &
I. Nagamohan.
syngas to methanol plant

WP8 Hazardous and K Rasesh, 1.10.2018 31.12.2018 Completed


Operability (HAZOP)
study for safety aspects
WP9 Consultancy agreement K Rasesh, 15.01.2019 15.03.2019 Completed
has been made with I. Nagamohan,
Gujarat Narmada Valley &
AK Pandey
Fertilizers & Chemicals
Limited (GNFC)
WP10 Civil foundation for D Satya Mohan Rao, 01.04.2019 15.07.2019 Completed
syngas to methanol A. Gunasekaran,
module structure and &
N. Sivarama Krishna
constructed control room.
Erection

WP11 Erection of syngas to D Satya Mohan Rao, 15.07.2019 31.12.2019 All structural
methanol plant. & columns, stair
N. Sivarama Krishna cases and
equipment’s
erected. Piping
work under
progress.
Integration Commissioning and Tirupathi Naidu Ch, 01.12.2019 31.01.2020 Yet to start
of all work integration of syngas to I. Nagamohan,
packages methanol plant A. Gunasekaran,
N. Sivarama Krishna,
AK Pandey,
D Satya Mohan Rao,
C Thirugnanam
& K Rasesh
WP12 Operation and Tirupathi Naidu Ch, 01.02.2020 31.03.2020 Yet to start
Performance Evaluation I. Nagamohan,
of the Coal to methanol A. Gunasekaran,
N. Sivarama Krishna,
plant AK Pandey,
D Satya Mohan Rao,
C Thirugnanam
& K Rasesh