You are on page 1of 26

PRODUCTION AND OPERATIONAL MANAGEMENT 1

1. Question Why graphical method of recording is preferred over the descriptive method
during method study?
Correct Answer It segregates effective part form ineffective parts , It reduces effort involved in
writing , Critical examinations easier and more effective
Your Answer Critical examinations easier and more effective , It segregates effective part form
ineffective parts , It reduces effort involved in writing

2. Question Which are the subfactors of community facilities or social infrastructure?


Correct Answer Accomodation , Educational , Entertainment
Your Answer Accomodation , Educational , Entertainment

3. Question The ________ is the probability that a bad lot will be accepted by the sampling
plan.
Correct Answer Consumer's risk
Your Answer Consumer's risk

4. Question Which of the following are examples of consumption of physical effort during
recording for method study?
Correct Answer Bending, Positioning, Unloading
Your Answer Bending, Positioning, Unloading

5. Question How to claculate the producer risk in the OC Curve?


Correct Answer Probability that a good lot will be rejected by the sampling
Your Answer Probability that a good lot will be rejected by the sampling

6. Question The ________ are the definitions of the measurable as well as nonmeasurable
characteristics of the product.
Correct Answer Specifications
Your Answer Specifications

7. Question The ________ is the watch dog which ensures that every element of production
and activities which could affect the quality of end product are regulated to the extent
desirable.
Correct Answer Quality control
Your Answer Quality control

8. Question Process Engineer does not get sufficient time for designing tooling for most
economic production run when
Correct Answer Delivery time is less
Your Answer Delivery time is less

9. Question The ________ includes preventive maintenance activities whose needs are
identified through inspection which requires stoppage of machines.
Correct Answer Shutdown Maintenance
Your Answer Shutdown Maintenance

10. Question The ________ is the maximum percentage defective that for the purpose of
sampling inspection can be considered satisfactory as a process average.
Correct Answer Acceptable quality level
Your Answer Acceptable quality level
11. Question What do you mean by lowest possible direct cost required to complete an
activity within its crashed time?
Correct Answer Crash cost
Your Answer Crash cost

12. Question Which are the first three steps of Critical Path Analysis technique?
Correct Answer Activity relationships, Activity identification, Network construction
Your Answer Activity relationships, Activity identification , Network construction
PRODUCTION AND OPERATIONAL MANAGEMENT 2
13. Question Which of the following can be subtypes of corrective maintenance?
Correct Answer Shutdown Maintenance, Design-out Maintenance, Design-in Maintenance
Your Answer Shutdown Maintenance, Design-out Maintenance, Design-in Maintenance

14. Question The ________ is the maintenance work initiated on a result of knowledge of the
condition of an item from routine or continuous checking.
Correct Answer Condition monitoring
Your Answer Condition monitoring

15. Question The process of changing inputs into outputs thereby adding some value to entity
can be defined as
Correct Answer Operation
Your Answer Production

16. Question The ________ is a set of tools and techniques by which products are made to
comply with the specifications at minimum cost to the firm.
Correct Answer Quality control system
Your Answer Quality control system

17. Question What is the meaning of "Product features" according to J.M.Juran?


Correct Answer Quality of design
Your Answer Quality of design

18. Question Which of the following method can be used to record the facts during the method
study?
Correct Answer Micromotion study, Cyclegraph , Chronocyclegraph
Your Answer Micromotion study , Photograph , Cyclegraph , Chronocyclegraph

19. Question Which of the following are types of sampling plan?


Correct Answer Single sampling plan , Double sampling plan , Multiple sampling plan
Your Answer Single sampling plan , Double sampling plan , Multiple sampling plan

20. Question How many of the following are types of specification?


Correct Answer Material specifications , Dimensional specifications , Performance specifications
Your Answer Material specifications , Dimensional specifications , Performance specifications
21. Question Plant layout facilitates processing of products in most effective manner through
the following
Correct Answer Shortest possible distance , Shortest processing time , Minimum movement
Your Answer Shortest possible distance , Minimum movement
Question Work study is also called ________ study
Correct Answer Time and Motion
Your Answer Time and Motion

Question Plant Layout is concerned with optimum arrangement of the following


Correct Answer Storage space , Machines , Material Handling Equipment
Your Answer Storage space , Machines , Sequence of operation
Question Management often fails to realize the importance of efficient layout due to following
reason
Correct Answer losses resulting from poor layout are not directly shown in the financial
statements
Your Answer losses resulting from poor layout are not directly shown in the financial statements
Question Any premise in which persons are employed for purpose of making any product/s is
called
Correct Answer Factory
Your Answer Factory

Question What is the basic philosophy of statistical process control?


Correct Answer Prevention is better than cure
Your Answer Prevention is better than cure
PRODUCTION AND OPERATIONAL MANAGEMENT 3

Question How does the control chart of statistical quality control helps the operating
personnel?
Correct Answer Identify the presence of an assignable cause before it develops
Your Answer Identify the presence of an assignable cause before it develops

Question Where does the central line is located in case of p-chart?


Correct Answer at p bar
Your Answer at p bar

Question Which of the following may be the objectives of project crashing?


Correct Answer To complete the project in the least possible time , To reduce project cost below
it's normal cost , To achieve uniformity in requirement of resources
Your Answer To complete the project in the least possible time , To reduce project cost below
it's normal cost , To achieve uniformity in requirement of resources

Question The ________ advocates maintenance procedures whereby the condition of the plant
is constantly watched through systematic inspection to unearth unhealthy conditions and
preventive
Correct Answer Preventive Maintenance
Your Answer Preventive Maintenance

Question Which is the ideal place to write a description of an activity in a network?


Correct Answer Above the arrow
Your Answer Above the arrow

Question In case of an OC curve, the risk of rejecting a good quality lot may vary between
________.
Correct Answer 0.01 to 10%
Your Answer 0.01 to 10%

Question Which phase of method study is concerned with analyzing the facts critically,
generating alternatives which form the basis for selection and development of improved
methods?
Correct Answer Critical examination
Your Answer Critical examination

Question Which of the following policies is advisable in case of low product variety and large
volumes?
Correct Answer Low Skilled Labour & Special Purpose Machines
Your Answer Low Skilled Labour & Special Purpose Machines

Question Which kind of inspection is followed in case of product layout?


Correct Answer Pilot inspection
Your Answer Pilot inspection

Question MRP is based on the concept of inventory demand which is of following type
Correct Answer Dependent and independent
Your Answer Dependent and independent

Question Main objective of a good plant layout is


Correct Answer Reduce material handling cost
Your Answer Reduce material handling cost

Question The ________ is the probability that a good lot will be rejected by the sampling plan.
Correct Answer Producer's risk
Your Answer Producer's risk
PRODUCTION AND OPERATIONAL MANAGEMENT 4
Question Which of the following are important considerations concerning activity times?
Correct Answer Activity time should be obtained from the person responsible for the completion
of an activity , Activity time must be independent of any influence which the preceding or
succeeding activity may have on it. , Activity time may assume that just the normal quantity of
resources required to carry out the activity are available.
Your Answer Activity time should be obtained from the person responsible for the completion of
an activity , Activity time must be independent of any influence which the preceding or
succeeding activity may have on it. , Activity time may assume that just the normal quantity of
resources required to carry out the activity are available.

Question The ________ pertain to the climatic conditions which the component , product or
material should withstand.
Correct Answer Environmental specifications
Your Answer Environmental specifications

Question Following are some of the factors considered for evaluation of alternative layouts
Correct Answer Flow of Material , Equipment utilization , Ease of supervision
Your Answer Flow of Material , Ease of supervision , Delivery performance

Question Which of the following are assignable cause?


Correct Answer Large varaitions in hardness of material , Tool wear , Errors in setting
Your Answer Large varaitions in hardness of material , Tool wear , Errors in setting

Question In case of an OC curve, the risk of rejecting a good quality lot may vary between
________.
Correct Answer 0.01 to 10%
Your Answer 0.01 to 10%

Question What is the base for considering activity time as single time estimate or three time
estimate?
Correct Answer Level of uncertainty
Your Answer Availability of labour

Question What do you mean by lowest possible direct cost required to complete an
activity within it's normal time?
Correct Answer Normal cost
Your Answer Normal cost

Question A good maintenance system is not a luxary but a ________.


Correct Answer Necessity
Your Answer Necessity

Question A ________helps to avoid crowding of jobs at a particular machine by change of


route of some of the jobs or by diverting work to other machine.
Correct Answer Control board
Your Answer Move order

Question Any premise in which persons are employed for purpose of making any product/s is
called
Correct Answer Factory
Your Answer Factory

Question A ________ is another form of subcontracting.


Correct Answer Hiring capacity
Your Answer Hiring capacity

Question In an organization there may not be a formal PPC department if


Correct Answer Work is highly repetitive in nature , Planning activities are performed by the
line staff , Number of workmen is not very large
Your Answer Work is highly repetitive in nature , Planning activities are performed by the line
PRODUCTION AND OPERATIONAL MANAGEMENT 5
staff , Number of workmen is not very large

Question Which of the following cases can be treated as delay during recording of method
study?
Correct Answer Operators awaiting instructions from supervisor , Worker waiting for his turn at
tools stores , Jobs awaiting at the machines for their turn
Your Answer Operators awaiting instructions from supervisor , Worker waiting for his turn at
tools stores , Jobs awaiting at the machines for their turn

Question Order preparation process for products manufatured to order requires following
documents
Correct Answer Sales Order, Work order, Shop order
Your Answer Sales Order, Work order, Purchase order

Question Technique of Value Engineering can be effectively employed in design of a product to


Correct Answer To meet the intended function at lowest cost
Your Answer Reduce lead time

Question Scale model used for layout analysis have following advantages
Correct Answer Nontechnical person finds it easy to comprehend , Ovehead facilities can be
shown , Models can be shifted easily
Your Answer Nontechnical person finds it easy to comprehend , Ovehead facilities can be shown
, Models can be shifted easily

Question Which of the following technique is event oriented ?


Correct Answer Project Evaluation & Review Technique
Your Answer Project Evaluation & Review Technique

Question What are uses of diagrams in method study?


Correct Answer Study different plant layouts and select the most optimum one , Study the
extent of traffic over the different routes of the plant , Identify the extent of backtracking, cross
traffic and obstacles encountered during the movement of material.
Your Answer Study different plant layouts and select the most optimum one , Study the extent
of traffic over the different routes of the plant , Identify the extent of backtracking, cross traffic
and obstacles encountered during the movement of material.

Question Route Sheet generally contains following information


Correct Answer Material Specification , Sequence of operation , Skill of Labour
Your Answer Material Specification , Sequence of operation , Skill of Labour
Question Which varaible is taken along the abscissa or X axis?
Correct Answer Time
Your Answer Standard deviation
Question Which are the advantages of suburban location?
Correct Answer Avaialability of adequate land at lower cost , Both skilled and unskilled labour
can be available , Plant expansion is easier due to less or no restriction for building and
construction
Your Answer Avaialability of adequate land at lower cost , Both skilled and unskilled labour can
be available , Plant expansion is easier due to less or no restriction for building and construction

Question The ________ is the maintenance work initiated on a result of knowledge of the
condition of an item from routine or continuous checking.
Correct Answer Condition monitoring
Your Answer Condition monitoring

Question Expediting function is concerned with following activities


Correct Answer Progress chasing to identify delays which may hold up production ,
Communicating possible delays in delivery date commitment to sales department , Devising
cures to keep rate of production in line with schedule
Your Answer Recording progress of work , Progress chasing to identify delays which may hold
up production , Communicating possible delays in delivery date commitment to sales
PRODUCTION AND OPERATIONAL MANAGEMENT 6
department
Question Production control work is ________ in case of floor inspection as compared with the
centralised inspection.
Correct Answer easier
Your Answer time consuming

Question The easiest way to bring the delayed job within the promised delivery time by using
extra shift or weekly holiday is ________.
Correct Answer Overtime working
Your Answer Overtime working

Question What is represented by an arrow in a network?


Correct Answer Activity
Your Answer Activity

Question The document raised by PPC which authorises different functions to take action as
per instruction is called
Correct Answer Work Order
Your Answer Work Order

Question A good layout makes effective use of space. Utilization of space for a department like
Stores can be measured by
Correct Answer Proportion of Cubic volume space utilized
Your Answer Ratio of area utilised to area available

Question The process of changing inputs into outputs thereby adding some value to entity can
be defined as
Correct Answer Operation
Your Answer Operation
PRODUCTION AND OPERATIONAL MANAGEMENT 7
Question MRP is based on the concept of inventory demand which is of following type
Correct Answer Dependent and independent
Your Answer Dependent and independent

Question Main objective of a good plant layout is


Correct Answer Reduce material handling cost
Your Answer Reduce material handling cost

Question The ________ is the probability that a good lot will be rejected by the sampling plan.
Correct Answer Producer's risk
Your Answer Producer's risk

Question Which of the following are important considerations concerning activity times?
Correct Answer Activity time should be obtained from the person responsible for the
completion of an activity , Activity time must be independent of any influence which the
preceding or succeeding activity may have on it. , Activity time may assume that just the
normal quantity of resources required to carry out the activity are available.
Your Answer Activity time should be obtained from the person responsible for the
completion of an activity , Activity time must be independent of any influence which the
preceding or succeeding activity may have on it. , Activity time may assume that just the
normal quantity of resources required to carry out the activity are available.
Question The ________ pertain to the climatic conditions which the component , product
or material should withstand.
Correct Answer Environmental specifications
Your Answer Environmental specifications

Question Following are some of the factors considered for evaluation of alternative layouts
Correct Answer Flow of Material , Equipment utilization , Ease of supervision
Your Answer Flow of Material , Ease of supervision , Delivery performance

Question Which of the following are assignable cause?


Correct Answer Large varaitions in hardness of material , Tool wear , Errors in setting
Your Answer Large varaitions in hardness of material , Tool wear , Errors in setting

Question In case of an OC curve, the risk of rejecting a good quality lot may vary between
________.
Correct Answer 0.01 to 10%
Your Answer 0.01 to 10%

Question What is the base for considering activity time as single time estimate or three time
estimate?
Correct Answer Level of uncertainty
Your Answer Availability of labour

Question What do you mean by lowest possible direct cost required to complete
an activity within it's normal time?
Correct Answer Normal cost
Your Answer Normal cost

Question A good maintenance system is not a luxary but a ________.


Correct Answer NecessityYour Answer Necessity
PRODUCTION AND OPERATIONAL MANAGEMENT 8
Question A ________helps to avoid crowding of jobs at a particular machine by change of
route of some of the jobs or by diverting work to other machine.
Correct Answer Control board
Your Answer Move order

Question Any premise in which persons are employed for purpose of making any product/s
is called
Correct Answer Factory
Your Answer Factory

Question A ________ is another form of subcontracting.


Correct Answer Hiring capacity
Your Answer Hiring capacity

Question In an organization there may not be a formal PPC department if


Correct Answer Work is highly repetitive in nature , Planning activities are performed by the
line staff , Number of workmen is not very large
Your Answer Work is highly repetitive in nature , Planning activities are performed by the
line staff , Number of workmen is not very large

Question Which of the following cases can be treated as delay during recording of method
study?
Correct Answer Operators awaiting instructions from supervisor , Worker waiting for his
turn at tools stores , Jobs awaiting at the machines for their turn
Your Answer Operators awaiting instructions from supervisor , Worker waiting for his turn
at tools stores , Jobs awaiting at the machines for their turn

Question Order preparation process for products manufatured to order requires following
documents
Correct Answer Sales Order , Work order , Shop order
Your Answer Sales Order , Work order , Purchase order

Question Technique of Value Engineering can be effectively employed in design of a


product to
Correct Answer To meet the intended function at lowest cost
Your Answer Reduce lead time

Question Scale model used for layout analysis have following advantages
Correct Answer Nontechnical person finds it easy to comprehend , Ovehead facilities can be
shown , Models can be shifted easily
Your Answer Nontechnical person finds it easy to comprehend , Ovehead facilities can be
shown , Models can be shifted easily

Question Which of the following technique is event oriented ?


Correct Answer Project Evaluation & Review Technique
Your Answer Project Evaluation & Review Technique

Question What are uses of diagrams in method study?


Correct Answer Study different plant layouts and select the most optimum one , Study the
extent of traffic over the different routes of the plant , Identify the extent of backtracking,
cross traffic and obstacles encountered during the movement of material.
Your Answer Study different plant layouts and select the most optimum one , Study the
extent of traffic over the different routes of the plant , Identify the extent of backtracking,
cross traffic and obstacles encountered during the movement of material.
PRODUCTION AND OPERATIONAL MANAGEMENT 9
Question Route Sheet generally contains following information
Correct Answer Material Specification , Sequence of operation , Skill of Labour
Your Answer Material Specification , Sequence of operation , Skill of Labour

Question Which varaible is taken along the abscissa or X axis?


Correct Answer Time
Your Answer Standard deviation

Question Which are the advantages of suburban location?


Correct Answer Avaialability of adequate land at lower cost , Both skilled and unskilled
labour can be available , Plant expansion is easier due to less or no restriction for building
and construction
Your Answer Avaialability of adequate land at lower cost , Both skilled and unskilled labour
can be available , Plant expansion is easier due to less or no restriction for building and
construction
Question The ________ is the maintenance work initiated on a result of knowledge of the
condition of an item from routine or continuous checking.
Correct Answer Condition monitoring
Your Answer Condition monitoring
Question Expediting function is concerned with following activities
Correct Answer Progress chasing to identify delays which may hold up production ,
Communicating possible delays in delivery date commitment to sales department , Devising
cures to keep rate of production in line with schedule
Your Answer Recording progress of work , Progress chasing to identify delays which may
hold up production , Communicating possible delays in delivery date commitment to sales
department
Question Production control work is ________ in case of floor inspection as compared with
the centralised inspection.
Correct Answer easier
Your Answer time consuming
Question The easiest way to bring the delayed job within the promised delivery time by
using extra shift or weekly holiday is ________.
Correct Answer Overtime working
Your Answer Overtime working

Question What is represented by an arrow in a network?


Correct Answer Activity
Your Answer Activity

Question The document raised by PPC which authorises different functions to take action as
per instruction is called
Correct Answer Work Order
Your Answer Work Order

Question A good layout makes effective use of space. Utilization of space for a department
like Stores can be measured by
Correct Answer Proportion of Cubic volume space utilized
Your Answer Ratio of area utilised to area available

Question The process of changing inputs into outputs thereby adding some value to entity
can be defined as
Correct Answer Operation
Your Answer Operation

Question The ________ must ensure that the product satisfy the functional requirements of
it's usage.
Correct Answer Quality of design
Your Answer Quality of design

Question Which of the following information is available in summary of part in a chart during
PRODUCTION AND OPERATIONAL MANAGEMENT 10
methods study?
Correct Answer Frequency of each symbol , Total time for each symbol , Total distance travelled
by the object
Your Answer Frequency of each symbol , Total time for each symbol
Question Which varaible is taken along the ordinate or Y axis?
Correct Answer Quality
Your Answer Quality
Question Which of the following schedules are recommended to prepare and follow as a part of
preventive maintenance system?
Correct Answer Preventive inspection schedule , Cleaning and upkeep schedule , Lubrication
schedule
Your Answer Preventive inspection schedule , Cleaning and upkeep schedule , Lubrication
schedule

Question Which kind of preventive inspection detects some maintenance related characteristics
by making use of human senses, when equipment is in operation?
Correct Answer Extrernal inspection
Your Answer Extrernal inspection

Question Which are different ways to show critical path in a network?


Correct Answer Thick Line , Red Line , Double Line
Your Answer Thick Line , Red Line , Double Line

Question What are the benefits of overhauling?


Correct Answer It increases useful life of an equipment and it's parts , Advance planning allows
to attend equipment without disturbing the production programme , Advance planning allows to
prepare and keep ready the list of replacement spares
Your Answer It increases useful life of an equipment and it's parts , Advance planning allows to
attend equipment without disturbing the production programme , Advance planning allows to
prepare and keep ready the list of replacement spares

Question Which of the following factors play important role while selecting or rejecting a
particular site from legislation and taxation point of view?
Correct Answer Labour laws , Building codes , Policies regarding issue of licences
Your Answer Labour laws , Building codes , Policies regarding issue of licences
Question Major contributors in the development of Control Charts, Sampling plan are
Correct Answer F H Dodge , H G Roming , Walter Schewhart
Your Answer F H Dodge , H G Roming , Walter Schewhart

Question The ________ is necessary when the job requires detailed of one or more of the job
characteristics with the help of special equipment which is not available at the producing
company.
Correct Answer Inspection order
Your Answer Job card

Question Which of the following cases can be referred as operation in method study recording?
Correct Answer Change in physical characteristic , Consumption of physical effort , Change in
chemical characteristic
Your Answer Change in physical characteristic , Consumption of physical effort , Change in
chemical characteristic

Question The ________ is the maintenance work initiated on a result of knowledge of the
condition of an item from routine or continuous checking.
Correct Answer Condition monitoring
Your Answer Overhauling

Question Work study is also called ________ study


Correct Answer Time and Motion
Your Answer Method

Question Which are the advantages of suburban location?


PRODUCTION AND OPERATIONAL MANAGEMENT 11
Correct Answer Avaialability of adequate land at lower cost , Both skilled and unskilled labour
can be available , Plant expansion is easier due to less or no restriction for building and
construction
Your Answer Avaialability of adequate land at lower cost , Both skilled and unskilled labour can
be available , Plant expansion is easier due to less or no restriction for building and construction

Question Which of the following is the criteria for the percentage defectives in the zone of the
indecision?
Correct Answer Lots having the percentage defective more than AQL but less than LPTD
Your Answer Lots having the percentage defective less than AQL but more than LPTD

Question The easiest way to bring the delayed job within the promised delivery time by using
extra shift or weekly holiday is ________.
Correct Answer Overtime working
Your Answer Overtime working

Question In case of Batch Production which kind of labour is expected?


Correct Answer Skilled in one specific Manufacturing Process
Your Answer Semiskilled

Question Which three of the following are causes of continuous upward pattern of Xbar-R
control chart?
Correct Answer Wear of tool , Abnormal rise in temperature , Accumulation of dirt
Your Answer Wear of tool , Abnormal rise in temperature , Accumulation of dirt

Question What do you mean by CPM?


Correct Answer Critical Path Method
Your Answer Critical Path Method

Question Which of the following are major inputs to scheduling?


Correct Answer Overlapping of operations , Effective Capacity per work centre , Performance
standards
Your Answer Overlapping of operations , Effective Capacity per work centre , Performance
standards

Question Lack of material planning results in the following


Correct Answer Over ordering , under ordering , stockouts
Your Answer Over ordering , under ordering , stockouts

Question What do you mean by the verification of object against predetermined standards of
quality or quantity or both?
Correct Answer Inspection
Your Answer Inspection

Question What are the advantages of templates over diagrams?


Correct Answer Can be conveniently moved on the graph paper , Less laborious , Saves time
Your Answer Can be conveniently moved on the graph paper , Less laborious , Unskilled person
can do and analyze it

Question The ________ is the probability that a good lot will be rejected by the sampling plan.
Correct Answer Producer's risk
Your Answer Producer's risk

Question Any premise in which persons are employed for purpose of making any product/s is
called
Correct Answer Factory
Your Answer Factory
PRODUCTION AND OPERATIONAL MANAGEMENT 12
Question An Ideal OC curve is ________ shaped curve that accpets all the lots with quality
equal to or better than AQL .
Correct Answer Rectangular
Your Answer Bell

Question Which is the right time to prepare stores issue order?


Correct Answer When route sheet is ready
Your Answer When route sheet is ready

Question Which element of a network represents a task which has got a definite beginning and
definite end?
Correct Answer Activity
Your Answer Activity
Question Which kind of preventive inspection detects some defects in moving parts, internal
cracks, and others , when machine is under preplanned shutdown?
Correct Answer Internal inspection
Your Answer Internal inspection

Question Production Planning is a centralised activity which includes functions such as


________
Correct Answer Scheduling
Your Answer Dispatching

Question Goods after final inspection should accompany ________to enable dispatch
department to identify and draw correct reference.
Correct Answer Forwarding note
Your Answer Forwarding note

Question Who has introduced the useful concept of control chart in 1931?
Correct Answer Walter Shewhart
Your Answer Walter Shewhart

Question Which of the following aspects are essential to ensure quality of purchased items?
Correct Answer Defining right quality for the job , Vendor performance evaluation , Making sure
that suppliers understand the requirements
Your Answer Defining right quality for the job , Vendor performance evaluation , Making sure
that suppliers understand the requirements

Question The ________ breakdowns usually cost more, partly due to damage done to the
adjustment components and partly due to emergency actions.
Correct Answer Unexpected
Your Answer Unexpected

Question MRP is based on the concept of inventory demand which is of following type
Correct Answer Dependent and independent
Your Answer Dependent and independent

Question Any premise in which persons are employed for purpose of making any product/s is
called
Correct Answer Factory
Your Answer Factory

Question Components of Production Management include


Correct Answer Capacity Planning , Job Design , Production Planning
Your Answer Capacity Planning , Job Design , Production Planning

Question Which of the following is the criteria for the percentage defectives in the zone of the
indecision?
Correct Answer Lots having the percentage defective more than AQL but less than LPTD
PRODUCTION AND OPERATIONAL MANAGEMENT 13
Your Answer Lots having the percentage defective more than AQL but less than LPTD
Question Which of the following are examples of addition during recording for method study?
Correct Answer Brazing , Welding , Riveting
Your Answer Brazing , Welding , Riveting

Question The easiest way to bring the delayed job within the promised delivery time by using
extra shift or weekly holiday is ________.
Correct Answer Overtime working
Your Answer Overtime working

Question An Ideal OC curve is ________ shaped curve that accpets all the lots with quality
equal to or better than AQL .
Correct Answer Rectangular
Your Answer Rectangular

Question Which of the following causes can be responsible for derailing the production
schedule in a factory?
Correct Answer Errors in drawings , Delay in receipt of material from vendor , Excessive
absenteeism
Your Answer Errors in drawings , Delay in receipt of material from vendor , Excessive
absenteeism

Question Which of the following situations demand the economic consideration while selecting
a job for method study?
Correct Answer Unorderly movement of men and materials , Excessive process defectives , Too
many suggestions received for improvement from a department or section
Your Answer Unorderly movement of men and materials , Excessive process defectives ,
Inconsistent quality

Question Which of the following are the basic requirements of quality standard?
Correct Answer Deifinite , Undesrstandable , Economically viable
Your Answer Absolute uniformity , Undesrstandable , Economically viable

Question The ________ is the defect level for which lots are regarded as bad lots.
Correct Answer Lot Tolerance Percentage Defective
Your Answer Acceptable quality level

Question The document which incorporates details of process planning for a job is called
Correct Answer Route Sheet
Your Answer Route Sheet

Question Which of the following is the most popular technique for Project Production?
Correct Answer PERT & CPM
Your Answer PERT & CPM

Question Technique of Value Engineering can be effectively employed in design of a product to


Correct Answer To meet the intended function at lowest cost
Your Answer To meet the intended function at lowest cost

Question What can be the worst effect due to excessive vibration?


Correct Answer Breakdown
Your Answer Breakdown

Question What is the relation between duration of an activity and length of an arrow?
Correct Answer No relation
Your Answer No relation

Question What is the nature of the sampling plan for critical defects?
Correct Answer Tight
PRODUCTION AND OPERATIONAL MANAGEMENT 14
Your Answer Tight

Question The ________ is the maintenance work initiated on a result of knowledge of the
condition of an item from routine or continuous checking.
Correct Answer Condition monitoring
Your Answer Condition monitoring

Question Which of the following are important considerations concerning activity times?
Correct Answer Activity time should be obtained from the person responsible for the completion
of an activity , Activity time must be independent of any influence which the preceding or
succeeding activity may have on it. , Activity time may assume that just the normal quantity of
resources required to carry out the activity are available.
Your Answer Activity time should be obtained from the person responsible for the completion of
an activity , Activity time must be independent of any influence which the preceding or
succeeding activity may have on it. , Activity time may assume that just the normal quantity of
resources required to carry out the activity are available.

Question Which of the following techniques is used by industrial engineering department to


obtain the utilisation index?
Correct Answer Work Sampling Studies
Your Answer Break Even Analysis

Question Which of the following factors play important role while selecting or rejecting a
particular site from legislation and taxation point of view?
Correct Answer Labour laws , Building codes , Policies regarding issue of licences
Your Answer Labour laws , Building codes , Policies regarding issue of licences

Question Which of the following cases can be referred as operation in method study recording?
Correct Answer Change in physical characteristic , Consumption of physical effort , Change in
chemical characteristic
Your Answer Change in physical characteristic , Consumption of physical effort , Movement of
material

Question The ________ must ensure that the product satisfy the functional requirements of
it's usage.
Correct Answer Quality of design
Your Answer Quality of design

Question Which of the following are examples of pure materials?


Correct Answer Bakeries , Ice factories , Woolen
Your Answer Bakeries , Ice factories , Woolen

Question Site factors for plant location include


Correct Answer Suitability of land
Your Answer Suitability of land

Question The ________ is the probability that a good lot will be rejected by the sampling plan.
Correct Answer Producer's risk
Your Answer Producer's risk

Question Which of the following defects can be observed during preventive inspection by using
human senses?
Correct Answer Deviation from normal sound , Excessive Vibration , Leakage of a gas
Your Answer Deviation from normal sound , Excessive Vibration , Leakage of a gas

Question Lack of material planning results in the following


Correct Answer Over ordering , under ordering , stockouts
Your Answer Over ordering , under ordering , stockouts

Question Work study is also called ________ study


PRODUCTION AND OPERATIONAL MANAGEMENT 15
Correct Answer Time and Motion
Your Answer Time and Motion

Question Following is one of the techniques used for Material Planning for high value material
Correct Answer MRP
Your Answer MRP

Question What do you understand by totality of features and characteristics of a product or


service that bears on it's ability to satisfy the customer?
Correct Answer Quality
Your Answer Quality

Question One detachable ticket is prepared for each ________.


Correct Answer Operation
Your Answer Worker

Question Which of the following are minimum requirement for a good quality of design?
Correct Answer Resonable cost , Resonable procurement time , Resonable manufacturing time
Your Answer Resonable manufacturing time , Resonable cost , Resonable procurement time

Question Where does the central line is located in case of p-chart?


Correct Answer at p bar
Your Answer at median

Question Any premise in which persons are employed for purpose of making any product/s is
called
Correct Answer Factory
Your Answer Factory

Question Technique of Value Engineering can be effectively employed in design of a product to

Correct Answer To meet the intended function at lowest cost


Your Answer To meet the intended function at lowest cost

Question The ________ is the probability that a good lot will be rejected by the sampling plan.
Correct Answer Producer's risk
Your Answer Producer's risk

Question Material Requirement Planning is very useful in following situations


Correct Answer Long Lead time for procurement , Several levels of assemblies in product , Long
manufacturing cycle
Your Answer Long Lead time for procurement , Long manufacturing cycle , Demand for the
product is not known

Question The ________ is the process of withdrawing the equipment from the production line,
dismantling it unitwise, visualising defects, effecting adjustments, replacing worn-out parts and
finally building it up to get desired accuracies.
Correct Answer Reconditioning
Your Answer Overhauling

Question The ratio of output to input of a production system is commonly known as


Correct Answer Productivity
Your Answer Productivity

Question Which of the following factors play important role while selecting or rejecting a
particular site from legislation and taxation point of view?
Correct Answer Labour laws , Building codes , Policies regarding issue of licences
Your Answer Labour laws , Building codes , Policies regarding issue of licences
PRODUCTION AND OPERATIONAL MANAGEMENT 16

Question What do you mean by the study of repetitive short cycle operations which involve
quick hand / feet motions?
Correct Answer Micromotion study
Your Answer Macromotion study

Question Which of the following products should be produced by using mass production?
Correct Answer Refrigerator , Tyre for automobile , Television Set
Your Answer Refrigerator , Tyre for automobile , Television Set

Question What does the points falling outside the control limits indicate?
Correct Answer Presence of assignable causes
Your Answer Mean = Standard deviation

Question Which industry out of the following industries require maximum consideration for
safety factor while selecting plant location?
Correct Answer Nuclear power plant
Your Answer Nuclear power plant

Question Which of the following are assignable cause?


Correct Answer Large varaitions in hardness of material , Tool wear , Errors in settingYour
Answer
Large varaitions in hardness of material , Play in guide rods , Errors in setting

Question A good plant layout helps in


Correct Answer Reducing handling costs
Your Answer Reducing handling costs

Question Which of the following are examples of addition during recording for method study?
Correct Answer Brazing , Welding , Riveting
Your Answer Brazing , Welding , Riveting

Question Work study is also called ________ study


Correct Answer Time and Motion
Your Answer Time and Motion

Question Which kind of gauge consists of electrical contacts operating a series of colloured
signal lamps which indicate whether the dimension is correct, oversize or undersize?
Correct Answer Multiple gauging
Your Answer Multiple gauging

Question Components of Production Management include


Correct Answer Capacity Planning , Job Design , Production Planning
Your Answer Capacity Planning , Job Design , Production Planning

Question Which are major benefits of identifying the critical path?


Correct Answer It helps to identify the set of activities and events which are critical and as such
must be carefully controlled and monitored , It identifies activities to be given preference in
allocation of resources. , It helps to exercise "control by exception".
Your Answer It helps to identify the set of activities and events which are critical and as such
must be carefully controlled and monitored , It reduces the paperwork , It identifies activities to
be given preference in allocation of resources.

Question Which are reason due to which the progress of work is rarely in line with it's plan?
Correct Answer Absenteeism , Machine breakdowns , Substandard performance against prefixed
production standards
Your Answer Absenteeism , Machine breakdowns , Substandard performance against prefixed
production standards

Question The ________ is necessary when the job requires detailed of one or more of the job
PRODUCTION AND OPERATIONAL MANAGEMENT 17
characteristics with the help of special equipment which is not available at the producing
company.
Correct Answer Inspection order
Your Answer Inspection order

Question Which of the following are important considerations concerning activity times?
Correct Answer Activity time should be obtained from the person responsible for the completion
of an activity , Activity time must be independent of any influence which the preceding or
succeeding activity may have on it. , Activity time may assume that just the normal quantity of
resources required to carry out the activity are available.
Your Answer Activity time should be obtained from the person responsible for the completion of
an activity , Activity time must be independent of any influence which the preceding or
succeeding activity may have on it. , Activity time may assume that just the normal quantity of
resources required to carry out the activity are available.

Question Capacity decisions have a direct influence on performance of production system in


respect of ________
Correct Answer Delivery performance
Your Answer Delivery performance

Question The process of changing inputs into outputs thereby adding some value to entity can
be defined as
Correct Answer Operation
Your Answer Operation

Question Which of the following possibilities can be explored by using flow process chart?
Correct Answer Eliminating the operations or combining the operations with another , Reducing
the distance traveled by the workmen or materials , Avoiding the waiting time and thereby
reduce production losses
Your Answer Eliminating the operations or combining the operations with another , Reducing
the distance traveled by the workmen or materials , Avoiding the waiting time and thereby
reduce production losses

Question The document raised by PPC which authorises different functions to take action as
per instruction is called
Correct Answer Work Order
Your Answer Work Order

Question Production control work is ________ in case of floor inspection as compared with the
centralised inspection.
Correct Answer easier
Your Answer easier

Question A ________ is another form of subcontracting.


Correct Answer Hiring capacity
Your Answer Hiring capacity

Question The ________ breakdowns usually cost more, partly due to damage done to the
adjustment components and partly due to emergency actions.
Correct Answer Unexpected
Your Answer Unexpected

Question Production Planning is a centralised activity which includes functions such as


________
Correct Answer Scheduling
Your Answer Scheduling

Question Which is the zone beyond LTPD in case of Oc curve of a general plan?
Correct Answer Zone of rejection
Your Answer Zone of rejection
PRODUCTION AND OPERATIONAL MANAGEMENT 18

Question Where the ignorance towards the degradation of machine leads to?
Correct Answer Eventual breakdown
Your Answer Eventual breakdown

Question Following are some of the factors which influence process planning
Correct Answer Order Quantity , Process capability of machine , Delivery Dates
Your Answer Process capability of machine , Delivery Dates , Order Quantity

Question Gross requirement of products is determined on the basis of


Correct Answer Both forecast and pending orders
Your Answer Both forecast and pending orders

Question In exponential smoothing method,for a stable demand pattern and better smoothing
effect, value of fraction( Alpha) selected is
Correct Answer 0.05 to 0.10
Your Answer 0.05 to 0.10
Question Which of the following may be the objectives of project crashing?
Correct Answer To complete the project in the least possible time , To reduce project cost below
it's normal cost , To achieve uniformity in requirement of resources
Your Answer To complete the project in the least possible time , To reduce project cost below
it's normal cost , To achieve uniformity in requirement of resources

Question Which is the next stage to the inspection based quality control in the historical
development of quality management.
Correct Answer Quality assurance
Your Answer Total Quality management

Question Inadequate production capacity ultimately leads to


Correct Answer Poor Customer Service
Your Answer Low Productivity

Question The ________ is the maintenance work initiated on a result of knowledge of the
condition of an item from routine or continuous checking.
Correct Answer Condition monitoring
Your Answer Condition monitoring

Question Production Planning includes


Correct Answer Predetermination of manufacturing requirements
Your Answer Predetermination of manufacturing requirements

Question Expediting function is concerned with following activities


Correct Answer Progress chasing to identify delays which may hold up production ,
Communicating possible delays in delivery date commitment to sales department , Devising
cures to keep rate of production in line with schedule
Your Answer Progress chasing to identify delays which may hold up production , Communicating
possible delays in delivery date commitment to sales department , Devising cures to keep rate
of production in line with schedule

Question Production Planning is a centralised activity which includes functions such as


________
Correct Answer Scheduling
Your Answer Scheduling

Question A set of activities to keep an equipment in the specified condition is called as


________.
Correct Answer Maintenance
Your Answer Maintenance
Question A good plant layout helps in
PRODUCTION AND OPERATIONAL MANAGEMENT 19
Correct Answer Reducing handling costs
Your Answer Reducing handling costs
Question The ________ is the probability that a good lot will be rejected by the sampling plan.
Correct Answer Producer's risk
Your Answer Producer's risk

Question Components of Production Management include


Correct Answer Capacity Planning , Job Design , Production Planning
Your Answer Capacity Planning , Job Design , Production Planning

Question Technique of Value Engineering can be effectively employed in design of a product to


Correct Answer To meet the intended function at lowest cost
Your Answer To meet the intended function at lowest cost

Question Which are the subtasks of the maintenance phase of the method study?
Correct Answer Monitoring and control , Performance appraisal , Audit on savings
Your Answer Monitoring and control , Performance appraisal , Audit on savings

Question The ________ is a set of tools and techniques by which products are made to comply
with the specifications at minimum cost to the firm.
Correct Answer Quality control system
Your Answer Quality control system

Question Need for change in layout can occur due to following reason
Correct Answer introduction of new product
Your Answer improve quality

Question Goods after final inspection should accompany ________to enable dispatch
department to identify and draw correct reference.
Correct Answer Forwarding note
Your Answer Forwarding note

Question Which are the different methods of recording actual progress of work?
Correct Answer Display boards , Progress cards , Network updating
Your Answer Display boards , Progress cards , Network updating

The term ________ emplies the foregone profit due to inability of company to produce.
Correct Answer Opportunity cost
Your Answer Opportunity cost

Question Any premise in which persons are employed for purpose of making any product/s is
called
Correct Answer Factory
Your Answer Factory

Question The process of changing inputs into outputs thereby adding some value to entity can
be defined as
Correct Answer Operation
Your Answer Operation

Question What do you mean by the selection of the job for the method study on the basis of
manufacturing difficulties?
Correct Answer Technical consideration
Your Answer Economic consideration

Question Which of the following are examples of addition during recording for method study?
Correct Answer Brazing , Welding , Riveting
Your Answer Brazing , Welding , Riveting
PRODUCTION AND OPERATIONAL MANAGEMENT 20

Question The ratio of output to input of a production system is commonly known as


Correct Answer Productivity
Your Answer Productivity

Question In case of Batch Production which kind of labour is expected?


Correct Answer Skilled in one specific Manufacturing Process
Your Answer Skilled in all Manufacturing Processes

Question The ________ is necessary when the job requires detailed of one or more of the job
characteristics with the help of special equipment which is not available at the producing
company.
Correct Answer Inspection order
Your Answer Inspection order

Question Which are the factors on which the structure of the transportation cost depends?
Correct Answer Average distance of shipment , Characteristics of the commodity , Medium of
shipment
Your Answer Average distance of shipment , Characteristics of the commodity , Medium of
shipment

Question Which is the ideal place to inspect jigs and fixtures in a mass manufacturing unit?
Correct Answer Separate inspection room
Your Answer Separate inspection room

Question Expediting action is necessary if the delays and interruptions are abnormal and
hence any subsequent delay is bound to extend the promised delivery date.
Correct Answer True
Your Answer True

Question Breakdown of machines, absenteeism of worker does not dislocate the manufacturing
activity in process layout
Correct Answer True
Your Answer True

Question Dust gets mixed with lubricants, forms an abrasive substance and causes pre-mature
failure of machinery.
Correct Answer True
Your Answer True

Question All activities must not be tied up into the network


Correct Answer False
Your Answer False

Question Operation Process Chart provides information on time and distances


Correct Answer False
Your Answer False

Question Inspection order is must even for simple jobs which can be inspected by shop
inspector with the tooling available on shop.
Correct Answer False
Your Answer True

Question Feasibility of time schedule requires that an activity be scheduled before any of it's
predecessors are scheduled.
Correct Answer False
Your Answer True

Question Planned lubrication is said to be the nervous system of the equipment.


Correct Answer True
Your Answer True
PRODUCTION AND OPERATIONAL MANAGEMENT 21

Question A network should be progression of activities always moving forward.


Correct Answer True
Your Answer True

Question For p-chart, the central line of fraction defectives is determined by average
percentage defectives.
Correct Answer True
Your Answer True

Question As a general rule, the number of tail event of an activity is more than that of it's
head event.
Correct Answer False
Your Answer False

Question All activities must not be tied up into the network


Correct Answer False
Your Answer False

Question In case of X bar, if the process is not under control indicated by some points falling
outside the control limits, such points outside the control limits are eliminated and new trial
control limits for the remaining points are computed.
Correct Answer True
Your Answer True

Question Inspection order is must even for simple jobs which can be inspected by shop
inspector with the tooling available on shop.
Correct Answer False
Your Answer False

Question Cent percent inspection is often more practical and economical than sampling
inspection.
Correct Answer False
Your Answer False

Question A load chart specifies the work to be carried out by each person of company during
shift hours.
Correct Answer False
Your Answer True

Question Cellular layout is based on the concept of Group Technology


Correct Answer True
Your Answer True

Question In case of forward pass computation, the earliest event time of the first event is
zero.
Correct Answer True
Your Answer True

Question As a general rule, a site five times the actual plant size is considered minimum for
parking, access facilities and future expansion.
Correct Answer True
Your Answer True

Question Independent float either affects the float of preceding activities or that of succeeding
activities.
Correct Answer False
Your Answer False

Question As a general rule, the number of tail event of an activity is more than that of it's
PRODUCTION AND OPERATIONAL MANAGEMENT 22
head event.
Correct Answer False
Your Answer False

Question All activities must not be tied up into the network


Correct Answer False
Your Answer False

Question In case of X bar, if the process is not under control indicated by some points falling
outside the control limits, such points outside the control limits are eliminated and new trial
control limits for the remaining points are computed.
Correct Answer True
Your Answer True

Question Inspection order is must even for simple jobs which can be inspected by shop
inspector with the tooling available on shop.
Correct Answer False
Your Answer False

Question Cent percent inspection is often more practical and economical than sampling
inspection.
Correct Answer False
Your Answer False

Question A load chart specifies the work to be carried out by each person of company during
shift hours.
Correct Answer False
Your Answer True

Question Cellular layout is based on the concept of Group Technology


Correct Answer True
Your Answer True

Question In case of forward pass computation, the earliest event time of the first event is
zero.
Correct Answer True
Your Answer True

Question Independent float either affects the float of preceding activities or that of succeeding
activities.
Correct Answer False
Your Answer False

Question The event numbers as far as possible reflect the logical relationships of the activities.
Correct Answer True
Your Answer False

Question Skill of labour force in a product type layout is usually higher than in the process
type of layout
Correct Answer False
Your Answer True

Question Repetitive movements between work stations which are difficult to be traced on
string diagrams can be conveniently shown on flow diagrams.
Correct Answer False
Your Answer True

Question All activities lying on the non-critical paths must have total float and free float.
Correct Answer False
Your Answer False
PRODUCTION AND OPERATIONAL MANAGEMENT 23

Question In case of X bar-R charts,it is ensured that the assignable causes are detected before
the tolerances are violated, upper and lower statistical limits are worked out and inserted into a
chart.
Correct Answer True
Your Answer False

Question Root cause of most of the breakdowns is failure of the lubrication system.
Correct Answer True
Your Answer True

Question It is not necessary to know spare time available on the non-critical path to allow a
little delay for noncritical activity.
Correct Answer False
Your Answer False

Question MRP software generates time periodwise requiremetn of subassemblies


Correct Answer True
Your Answer True

Question In case of two handed process chart, the simultaneous activities of both hands are
recorded opposite to each other on the chart.
Correct Answer True
Your Answer True

Question It would not affect the project completion time if non-critical activities take little
loner time than planned.
Correct Answer True
Your Answer True

Question After goods have been manufactured, route sheets and operation layouts should not
be collected back.
Correct Answer False
Your Answer False

Question In case of centralised inspection, inspection rooms generally become bottleneck and
cause delay in taking action regarding rejection or rework.
Correct Answer True
Your Answer True

Question During set up of X bar-R control chart, control limts should be practically revised
from time to time as additional data is accumulated.
Correct Answer True
Your Answer False

Question Floor inspection delays the identification of faults which can not be rectified
immediately before large lots are spoiled.
Correct Answer False
Your Answer False

Question Cent percent inspection is required on WIP prior to the key, critical or costly
operation.
Correct Answer True
Your Answer True

Question Repetitive movements between work stations which are difficult to be traced on
string diagrams can be conveniently shown on flow diagrams.
Correct Answer False
Your Answer True

Question An activity can share the same tail event and same head event with any other
PRODUCTION AND OPERATIONAL MANAGEMENT 24
activity.
Correct Answer False
Your Answer True

Question F W Taylor devised a system for classifying motions into basic divisions called
Therbligs
Correct Answer False
Your Answer False

Question In case of two handed process chart, the simultaneous activities of both hands are
recorded opposite to each other on the chart.
Correct Answer True
Your Answer True

Question An activity should represent an operation or set of operations which can be


performed using a particular kind of equipment or a special skill.
Correct Answer True
Your Answer True

Question In case of X bar, if the process is not under control indicated by some points falling
outside the control limits, such points outside the control limits are eliminated and new trial
control limits for the remaining points are computed.
Correct Answer True
Your Answer True

Question After goods have been manufactured, route sheets and operation layouts should not
be collected back.
Correct Answer False
Your Answer False

Question Planned lubrication is said to be the nervous system of the equipment.


Correct Answer True
Your Answer True

Question An activity can share the same tail event and same head event with any other
activity.
Correct Answer False
Your Answer True

Question Only skilled worker can use the fixed limit gauge.
Correct Answer False
Your Answer False

Question Breakdown of machines, absenteeism of worker does not dislocate the manufacturing
activity in process layout
Correct Answer True
Your Answer True

Question Dust gets mixed with lubricants, forms an abrasive substance and causes pre-mature
failure of machinery.
Correct Answer True
Your Answer True

Question Operation process charts though indicates the sequence of events but do not show
movements.
Correct Answer True
Your Answer True

Question The problems of congestion, bottlenecks and backtracking can not be visualized by
using templates and models.
PRODUCTION AND OPERATIONAL MANAGEMENT 25
Correct Answer False
Your Answer False

Question Skill of labour force in a product type layout is usually higher than in the process
type of layout
Correct Answer False
Your Answer True

Question Recording of movement is not necessary in case of method study in any form.
Correct Answer False
Your Answer True

Question Inspection should be conducted on all incoming materials, semifinished items,


bought out components, subcontract items prior to any operation, assembly.
Correct Answer True
Your Answer True

Question A load chart specifies the work to be carried out by each person of company during
shift hours.
Correct Answer False
Your Answer False

Question Breakdown is inversly proportional to the investment in W.I.P.


Correct Answer False
Your Answer True

Question short cycle job should be studied for macroscopic motions.


Correct Answer False
Your Answer True

Question Inspection Order can be a verbal order


Correct Answer True
Your Answer False

Question In case of backward pass computation, the latest event time of the end event equals
to the earliest event time minus duration of that activity.
Correct Answer False
Your Answer True

Question In Gantt chart, the horizontal lines devide vertical lines into sections which represent
either operations or work centres.
Correct Answer True
Your Answer True

POA MATCHING QUESTION

Question Correct Answer Your Answer


Toung Sweet Sweet
Eye Crack Crack
Nose Burnout Burnout
Ear Impact Impact

Question Correct Answer Your Answer


Emerson Efficiency Plan Wage Payment Wage Payment
Craft Facilities Planning Facilities Planning
Work Sampling Machine utilization Machine utilization
Gantt Chart Production Scheduling Production Scheduling
PRODUCTION AND OPERATIONAL MANAGEMENT 26
Question Correct Answer Your Answer
Crash cost of an activity Cc Cc
Normal time of an activity Tn Tn
Crash time of activity Tc Tc
Normal cost of an activity Cn Cn

Question Correct Answer Your Answer


Combined Layout Mixed Layout Mixed Layout
Fixed Position Layout Project Layout Line Layout
Product Layout Line Layout Shop layout
Process Layout Functional Layout Functional Layout

Question Correct Answer Your Answer


Factor Analysis Method to evaluate layouts Technique for evolving and analysis of layouts
Minimization of production delays Objective of good layout Objective of good layout
Maximum visibility Principles of good layout Principles of good layout
Scale model Layout analysis Method to evaluate layouts

Question Correct Answer Your Answer


Draining and refilling of oil reserviors of plunger pump Yearly Yearly
Parts lubricated with oil nipple Daily Daily
Tools and slideways two to three times a day two to three times a day
Table lubrication Weekly Weekly

Question Correct Answer Your Answer


Pessimistic time b b
Expected time Te Te
Optimistic time a a
Most likely time m m

You might also like