Contractor Work Instruction


Title: 218729. LEIGH PRIMARY, SPINNING Job Type Civil - Substations Team:
JENNY WAY. LEIGH. EXCAVATIONS /
Issued To: Freedom Sth Civil CIFMS Asset Ref No Package: CIVIL
Address: Job No D.50018543.895
Job Start Date 10/06/2019 Created By
Job End Date 14/06/2019 D McMahon
S74 End Date Project Manager
Substation: 2187290ST001 WI Number 1345401 D McMahon

All work to be carried out in accordance with Electricity North West's Code of Practice.
Carry out site safety checks/ risks in accordance with the safe working practices manual.

All Works Issued In Accordance With The Terms And Conditions As Detailed In XD5 Electricity Networks Project Framework Agreement, Building and Minor
Civil Works

Agreed Order Value

Prime Costs Labour On-Costs Materials On-Costs


Project Labour Total £1,159.00 Turnkey Rate 0.00% £0.00 ENWL Mat Handling 7.50% £0.00
Project Materials Total £0.00 PMC 7.85% £90.98 Cont Mat Supply 7.50% £0.00
Non-Electrical Materials Total £0.00 General OH 4.50% £52.16 Sched20Materials 0.00% £0.00
Directs Total £0.00 Profit 5.00% £57.95 ENWL Mat Supply 0.00% £0.00
Sched 20 0.00% £0.00 Directs 10.00% £0.00
Prime Costs Total £1,159.00

Premium Rate 1 £0.00


Premium Rate 2 £0.00
Sched 20 Turnkey
On-Costs Total £201.09

Prime + On Costs Total £1,360.09

Design Cost Agreed Variations

Labour Total £3,684.04 Labour Total -£2,323.95


Materials Total £0.00 Materials Total £0.00
NEMls Total £0.00 NEMs Total £0.00
Directs Total £0.00 Directs Total £0.00

Total £3,684.04 Total -£2,323.95

Additional Information:
PLEASE SEE ADDITIONAL INFORMATION.
SUPPLY GARIC WELFARE VAN. CRANE WILL BE REQUIRED AND THE CARPARK AREA NEEDS TO BE FREE FROM OBSTRUCTION, HENCE THE VEHICLE.
EXCAVATE FULLY THE SIDE OF THE EXISTING PLINTH WITHIN THE T11 COMPOUND. SEE SKETCH.
STORAGE OF EXCAVATED MATERIALS CAN BE STORED NEATLY ON ONE SIDE OF THE SITE AS DISCUSSED.
REMOVE FENCING BOARDS TO ALLOW THIS.
DE-CONTAMINATE (STEAM CLEAN) THE PLINTH ONCE EXPOSED. CENTRE LINE TO BE MARKED ON THE EXISTING PLINTH.

**cost code changed from 50018343 to 50018543 - AD 10.06.19**

218729. LEIGH PRIMARY, SPINNING JENNY Page 1 of 3 Prepared: 29 Jul 2019


Contractor Work Instruction
Premium Rate 1 (Prime Costs)
# Ref/PIMS Description Premium Rate 2 Unit Q'ty Materials Lab/Dir NEMs
2 DBMCG.7.2 Take down existing fencing and posts: 1800 to 2800 high m
2 .00 £24.83 £0.00

3 DBMCC.1.13 Reduce levels - ne 1.00m deep m3


7.23 .00 £1,016.84 £0.00

6 DBMCC.3.28 Disposal of syringes/needles/sharps including notification to Project Engineer; Site


1 .00 £117.32 £0.00

Total Materials: £0.00 TotalLabour / Dirs: £1,158.99 Total Nems: £0.00

# Ref/PIMS Additional Work - Not Programmed Unit Q'ty Materials Labour NEMs

218729. LEIGH PRIMARY, SPINNING JENNY Page 2 of 3 Prepared: 29 Jul 2019


Contractor Work Instruction

Materials List

Code Description Unit Date Planned Used


Price Priced Quantity Quantity

Labour References too long to display in full above


Item Reference Description
6 DBMCC.3.28 Disposal of syringes/needles/sharps including notification to Project Engineer; transport in suitable metal containers and all PPE
necessary; multiple items

218729. LEIGH PRIMARY, SPINNING JENNY Page 3 of 3 Prepared: 29 Jul 2019