Professional Documents
Culture Documents
BPD 31003
CONSTRUCTION
COST
ESTIMATION
Ts. Dr. Norliana Sarpin
norliana@uthm.edu.my
BRICK WORK
+
BRICKWORKS AND BLOCKWORKS
+
CONTENT
1. Introduction
2. Brickworks & Blockworks
3. Materials
• Brick
• Mortar
• Wire mesh
• Damp Proof Membrane
• Cutting & Waste
4. Labour
+
CONTENT
5. Blockworks
6. Sub-contractors’ Responsibilities
7. Calculation :
• Example 1 – Cement Mortar Mix
• Example 2 – Mortar
• Example 3 - Brickworks
+
INTRODUCTION
The following are the items which normally states that prices
are included for:
1m
65mm + 10mm
215mm + 10mm
+
Material (Brick)
1m
Wire mesh
CALCULATION
+
Example 1: Cement Mortar Mix
Question:
Find the unit rate per m 3 for cement mortar mix (1:3).
(using a 5/3½ runner, continuously). A 5/3½ mixer takes 5 cubic feet
of dry materials and produces 3½ cubic feet of concrete per mix (i.e.
0.099m3) (1 cubic feet = 0.0283 cubic metre). Working continuously
at the rate of 12 mixes per hour, this produces approximately 1.20m3
of mixed concrete in an hour.
Assumption:
Cost of mixer (rental) = RM 100.00 per day
Cost of diesel for = RM 24.00 per day
mixer
Labour wages = RM 40.00 per day
No. of labour = 3 persons (1 filler, 2
wheelers)
+
Example 1: Cement Mortar Mix
Assumption:
Cost of Ordinary Portland Cement =RM 18.00 per bag
(50kg)
inclusive unloading cost
Cost of sand = RM 120.00 per tonne
Density of Ordinary Portland Cement = 1420kg/m3
Density of sand = 1600kg/m3
Working hour per day = 8 hours
Shrinkage and wastage = 33.33%
+ Example 1: Cement Mortar Mix
RM RM/
m3
Material Cost
(a) 1 m3 Ordinary Portland Cement
Cement per tonne = 1000kg = (1000kg/50kg) =
20bag
Cement price per tonne =(RM18.00 x 20bags)=
RM360.00
1m3 cement = 1420kg/m3 at RM360.00 per tonne
= [(1m3 x 1420kg/m3) /1000kg ] x RM360.00/tonne = 511.20
(b) 3 m3 Sand
1 m3 sand = 1600 kg/m3 at RM120.00 per tonne
= [(3m3 x 1600kg/m3) / 1000kg ] x RM120.00/tonne = 576.00
Labour Cost
(e) 3 labours at RM40.00 per day
= 3 x (RM40.00 / 8 hour)
= RM15.00 per hour
Assumption:
Cost of cement = RM 10.50 per bag
Cost of sand = RM 30.00 per m 3
(b) 3 m3 Sand
3m3 x RM30.00 = 90.00
= 384.00
(c) Add shrinkage and wastage 1/3 = 128.00
Total Material Cost for 4m3 = 512.00
Labour Cost
(e) labour at RM40.00 per day
= 2 x (RM40.00 / 8 hour) = 10.00
= 138.00
Cost of mortar per m3
+ Example 3: Brickworks
Question:
110mm thick brickwall in strip foundations, in cement mortar 1:3
mix, laid in stretcher Bond. Determine the unit rate in m 2.
Assumption:
No. of brick required per m2 = 63 pieces
Cost of brick = RM 0.30 per
piece
Mortar required per m2 (inclusive = 0.025m3
wastage)
Cost of cement mortar mix (1:3) = RM 387.81
per m3
+
Example 3: Brickworks
Assumption:
Wages per day (Bricklayer) =RM 60.00
(General worker) = RM 40.00
Gang of labour = 1 + 1 (1 bricklayer, 1 labourer/general
worker)
Output of bricklayer = 120 pieces per hour
Allow 8 hour working per day
Profit and Overhead = 10%
+Example 3: Brickworks
RM RM/m2
Material Cost
(a) 1m2 of common brick = (63 pieces x = 18.90
RM0.30/piece)
(b) Mortar inclusive wastage = (0.025m3 x = 9.70
RM387.81/m3)
(c) Add Wire Mesh/exmet = 3.50m x RM 0.80 = 2.80
Cost of materials per m2 = 31.40
Labour Cost
(e) Cost of labours per hour;
1 bricklayer = (RM60.00 per day / 8 hours) = 7.50
1 labourer = (RM40.00 per day / 8 hours) = 5.00
Total cost of gang of labour per hour = 12.50
RM RM/m2
Labour Cost
Cost of Labour per m2 = 6.25
Thank you
norliana@uthm.edu.my
+
NEXT LECTURE
Finishes
+ Example 4: Cement Sand Block
Question:
Determine the unit rate in m2 for:
150mm thick wall in cement and sand blocks size 400mm x 100mm x 100mm thick for partition walling in
cement mortar (1:3) mix.
Assumption:
No. of block required per m2 = 22 pieces
Cost of block = RM 1.30 per piece
Wastage on material = 5%
Mortar required per m2 (inclusive wastage) = 0.011m3
Cost of cement mortar mix (1:3) per mix3 = RM 387.81
Wages per day (Blocklayer) = RM 60.00
Overhead = 10%
+
Example 4: Cement Sand Block
RM RM/m2
Material Cost
(a) Cement and sand hollow block
1m2 = 22 pieces x RM1.30 per piece = 28.60
(b) Waste on material 5% = (RM28.60 x 5%) = 1.43
(c) Mortar inclusive wastage = (0.011m3 x = 4.27
RM387.81/m3)
Cost of materials per m2 = 34.30
Labour Cost
(d) Cost of 1 blocklayer = (RM60.00 per day / 8 hour) = 7.50
Cost of 1 labourer = (RM40.00 per day / 8 hour) = 5.00
Total cost of gang of labour per hour = 12.50
+
Example 4: Cement Sand Block
RM RM/m2
Labour Cost
(e) Cost of labour per m2 = 0.45 hours
1m2 = (0.45 hours x RM12.50 per hour) = 5.63