CONSTRUCTION TECHNOLOGY
AND ESTIMATING
Bricks
Brick
Mortar
Wire mesh
2018/1/3
MATERIAL: BRICK
1) To find brick quantity in 1m2 brickwall:
• 225mm x 113mm x 75mm (Work size)
• Allow 5% of wastage
2018/1/3
MATERIAL: BRICK
1) Brick Quantity in 1m2 brickwall
– standard size of brick 225mm x 113mm x 75mm
2018/1/3
MATERIAL
2) Mortar
A lot of types for mixture, eg:
mixture of cement : lime : sand (1:1:6)
mixture of cement : sand (1:3)
Add 1/3 for shrinkage
Mortar output
mortar output in 1m2 half brick wall 0.025m3
mortar output in 1m2 one brick wall 0.050m3
3) Wire mesh
Every 4 layers need to put
1m2 consist of 3.50m length of
wire mesh
2018/1/3
LABOUR
Mixing mortar – general worker output 2.00hr/m3
Brick bonding – bricklayer & general worker output
(Refer toTable)
Description Bricklayer (Hr/m2) General Worker
(Hr/m2)
2018/1/3
BRICKWALL
Build up rate for 1 m2 half brickwall of common clay
bricks in cement and sand (1:3).
Assumption:
Clay Bricks = RM 0.25/no
Wire mesh = 3.50m x RM 0.60
1m3 cement = 28 bag (RM 13.00/bag)
1m3 sand = RM 16.50/m3
Mortar output in 1m2 half brick wall 0.025m3
Mortar output in 1m2 one brick wall 0.050m3
General Workers to mix the mortar is 2.00hr/m3
Allow 20% profit and overhead (Applicable to all build up rate)
2018/1/3
BRICKWALL
Material cost
Mortar
1m3 cement = 1 x 28 x RM 13.00 = RM 364.00
3m3 sand = 3 x RM 16.50 = RM 49.50
RM 413.50
Add 1/3 shrinkage = RM 137.83
Cost for 4m3 mortar = RM 551.33
4
Cost for 1m3 mortar = RM 137.83
http://www.pavingexpert.com/images/features/wall10.gif
2018/1/3
DAMP PROOF COURSE
Build up rate for 1m of 113mm wide horizontal DPC of
single course bituminous felt lapped 100mm at joints and
bedded in cement and sand mortar (1:3).
(measured net and no allowance made for laps)
Assumption:
DPC = RM 5.00 per m2
Mortar = 0.002m3
Bricklayer = 0.02hr/m
General worker = 0.01hr/m
Allow for 5% overlapping & wastage