Data: Kontrol η 1. Berat pile cap


N= 1200 ton η= 0.8644 < 1 V = 47.786 m³
MT s.d TK = 25 m (tiang pancang Group Pile) Berat = 114.687 ton
dw = 3m Ukuran Pile Cap 2. Berat Σpile
ɣb = 1.5 t/m³ n= 28 tiang V = 104.832 m³
ɣsat = 1.8 t/m³ D real = 0.4 m Berat = 251.597 ton
ɣw = 1 t/m³ D ekiv. = 0.45 m 3. Beban Lantai kerja
ɣd = 0.8 t/m³ S= 1.81 m (4 D) t LK = 0.1 m
MB = 40 t.m n1 = 4 baris V= 7.964 m³
ML = 60 t.m n2 = 7 baris Beban = 14.336 ton
eo = 1.65 Lg = 11.2 m 4. Beban penutup lantai Qo1
ep = 0.7 Bg = 5.8 m t lantai = 0.03 m
Cc = 0.55 Poer Lx = 12.0 m Berat = 0.078 t/m²
C= 18 t/m² Poer By = 6.6 m Beban = 6.212 ton
Qo1 2600 kg/m³ L pile = 23.4 m 5. Beban berguna Qo2
= 2.6 t/m³ Jumlah Gaya Vertikal Beban = 31.858 ton
Qo2 400 kg/m² 1. Berat pile cap 114.687 ton 6. Beban akibat kons.
= 0.4 t/m² 2. Berat Σpile 251.597 ton N= 1200 ton
ɣb. b = 2.4 t/m³ 3. Beban lantai kerja 14.336 ton
ɣb. tb = 1.8 t/m³ 4. Beban lantai Qo1 6.212 ton
Pile = (40 x 40) cm 5. Beban berguna Qo2 31.858 ton
D real = (0.4 x 0.4) m 6. Beban akibat kons. 1200 ton
T= 0.6 m ΣV = 1618.690 ton
Diketahui: Tegangan Angka Pori
2/3 pile = 15.6 m Δe1 = 0.189
Δh = 9.40 m Δe2 = 0.123
Δh1 = 2.35 m Δe3 = 0.084
Δh2 = 2.35 m Δe4 = 0.059
Δh3 = 2.35 m ΣΔe = 0.454
Δh4 = 2.35 m Settlement of Consolidation
z1 = 1.175 m ΔSc1 = 0.167 m
z2 = 3.525 m ΔSc2 = 0.109 m
z3 = 5.875 m ΔSc3 = 0.074 m
z4 = 8.225 m ΔSc4 = 0.052 m
Settlement (S) dan Waktu (t) ΣΔSc = 0.403 m
Tegangan Efektif Tanah ΣΔSc = 40.291 cm
A1 = σo1 = 15.52 t/m² Waktu Penurunan
A2 = σo2 = 17.4 t/m² Cv = 0.0000015 cm/detik
A3 = σo3 = 19.28 t/m² u= 0.9
A4 = σo4 = 21.16 t/m² Tv = 0.848
Penyebaran Tegangan Tanah H= 940 cm
A1 = 86.78 m² t1 = t9 = 15839.9459 tahun
Δσo1 = 18.65 t/m² t2 = 4751.98376 tahun
A2 = 137.90 m² t total = 20591.930 tahun
Δσo2 = 11.74 t/m² Settlement of Immediate
A3 = 200.06 m² µ= 0.5 (Tabel)
Δσo3 = 8.09 t/m² E= 70 kg/cm²
A4 = 273.27 m² Lg/Bg = 1.93
Δσo4 = 5.92 t/m² Ip = 0.78 (Grafik)
Si = 12.04041 cm
Menghitung Ss
Cα = -0.8689224
Ss = 251.22388 cm
S Total = 303.55491 cm
Beban tiap pancang Daya Dukung (Qgs)
X1 4 tiang α= 0.3 (Grafik)
= 0.00 m F= 5.4 t/m²
X2 8 tiang θ= 25 (Tabel)
= 1.81 m Nc = 20.72 (Tabel)
X3 8 tiang Kedalaman = 23.4 m
= 3.61 m Maka, Qg = 36000.09 ton
X4 8 tiang SF = 3 (Monumental)
= 5.42 m Qgs = 12000.03 ton > ΣV (Aman)
Y1 14 tiang Kapasitas 1 tiang pancang (Qis)
= 0.90 m Qfriction = 179.1284 ton
Y2 14 tiang Qtip = 59.6736 ton
= 2.71 m Qulti = 238.802 ton
ΣX1² = 0.000 m² SF = 3 (Monumental)
ΣX2² = 26.089 m² Qis = 79.601 ton > Qmax (Aman)
ΣX3² = 104.357 m² Kontrol Efisiensi
ΣX4² = 234.803 m² Ø= 14.04 ᵒ
ΣX² = 365.248 m² m= 4
ΣY1² = 11.414 m² n= 7
ΣY2² = 102.726 m² Eg = 0.86
ΣY² = 114.140 m² = 86 %
Qmax= Q7 = 59.650 ton Qall = 1912.3 ton > ΣV (Aman)
Qmin= Q22 = 55.971 ton Kontrol = 18.139 % < 20% (OK)