Weekly Progress Report Card - Balrampur(2nd Week July )

Weekly Asking Rate (WAR) 570 Planned Completion Date


15-Aug-19
Weekly Current Rate (WCR) 188 Expected Completion Date 05-Nov-19
GAP (WAR - WCR) 383 Improvement Delays (in Days) 83

Graphs

BPL(3421 nos)
1200
1140
1000
800

600 570
400 375
270
200
0
July 1st Week July 2nd Week

Desired per week Erection Completion


BCD submission to client for legrization Legrization updation on client portal

July 2nd July 1st


Week Week
Erection Completion 375 270
BCD submission to client for
legrization 0 0
Legrization updation on client
portal 0 0
JMC submission with account
ID to client 0 0
JMC approval from client 0 0
MB Done 0 0
MB Not Done 0 0
MD Office 0 0