Professional Documents
Culture Documents
______________________________________
______________________________________
A H Gray1
ABSTRACT
The InLine Pressure Jig represents a breakthrough in jigging technology.
Its design incorporates a unique combination of features previously
utilised in conventional jig design. In particular, a moveable screen and
circular bed are used to excellent effect. However, a major design
innovation is the encapsulation of the circular bed within a vessel —
allowing the equipment to operate under pressure. This innovation
eliminates free water surface, improves the dynamics within the
separation layer (crossflow) and provides significant cost savings in the
handling of slurries. Recent research results have indicated its capacity to
achieve high recoveries and upgrade ratios in the gravity separation of
minerals.
INTRODUCTION
2. The particles are lifted to the same height during each cycle
regardless of their relative density. At the top of the stroke
the ‘rug is pulled out’ from underneath the particles. This
ensures that the bed porosity remains even and no boil holes
occur.
Drive — pulse
Circular bed
The IPJ has a true circular bed design. The bed overlies a single
hutch. Because no radial partitioning exists in the hutch, walling
effects are eliminated resulting in increased overall performance
of the screen area.
Walling effect in conventional jigs is caused by drag from the
slurry running along the wall of the jig. Eddy currents and
turbulence are created which reduce the relative density of the
bed. This in turn allows excess hutch water flow to pass up along
the wall of the jig. The inverse can also occur with the drag
created by the wall decreasing the flow to such an extent that
settling occurs and solids deposit against the wall. These two
situations reduce effective screen area and overall efficiencies.
In the IPJ, slurry radiates across the radius of the circular bed.
Accordingly, slurry velocity declines as it passes across the
screen from the feed distributor creating a changing environment
for enhanced mineral recovery. FIG 5 - Typical pulse plot for the IPJ.
OPERATIONAL VARIABLES
Hutch water addition
Pulse
Water addition to the jig occurs through the hutch. Hutch water is
The pulse is varied by adjusting the hydraulic drive unit. The essential for three reasons:
pulse plot (Figure 5) shows a typical stroke curve for the IPJ and
the direction changes of the stroke and illustrates the rapid 1. Positive water flow through bed to enhance the bed dilation.
acceleration phase. The curve represents the motion of the screen.
The upward movement is the suction stroke, while the downward 2. Reduce the total suction created during the up stroke.
movement is the dilation (separation) stroke. These two (Suction = Velocity of rising screen - Velocity of rising
movements are variable to about 1.5 x 102 mm/sec maximum water.)
velocity. The acceleration rate is also variable up to 8.3 x 103
mm/sec/sec (Figure 5). 3. Addition of water for concentrate water flow.
The drive will allow for varying load conditions within the jig
bed and maintain a constant cycle rate (pulse). The total balance of the water added through the hutch is: (Tail
Water Dilution = Total hutch water addition - Concentrate water
In order to loosen the bed fully and stratify the bed flow.)
according to density, the following conditions must be This water flow is typically 0.2 m3 water/t/h treated to tail.
met: Control of this flow provides control of the recovery curve
(Figure 6). High water flow to tail increases concentrate grades
• time conditions: the speed and acceleration of the but decreases recovery and causes a loss of fine particles.
moveable screen must be greater than that of the The minimum water addition is balanced to compensate for the
particles in the bed; and excess suction created during the period of the suction stroke
through which the bed is fully compacted. The balance can be
• space conditions: particles must have enough space to achieved through observation of the load gauge on the pulse
move in the period that the particle bed loosens. mechanism and can be set with consideration of concentrate grade
and mass flow. Low water flows will cause excessive load on the
drive mechanism and produce a low grade, dirty concentrate.
It is because the sine wave jig cycle cannot satisfy the two
conditions simultaneously that the separation with the sin
wave jig cycle is very poor (Sun and Sun, 1993).
TABLE 1
DML Resources Limited comparative testwork IPJ 1500 versus YUBA jigs.
Feed Rate Pulp Hutchwater Stroke Stroke Rate Head Grade Tails Grade Overall Conc Rate Recovery
t/h Density (m3/h) per Length (cyc/min) (mg/t) (mg/t) Head Grade (%)
(% sol) t/h of feed (mm) (mg/t)
Test 1
YUBA 4 41.2 31.1 3.4 20 146 419 2.6 08:01 99
IPJ 1 10.9 31.8 1.7 10 120 1461 15 637 36:1 99
Test 2
YUBA 1 39 33.1 2.7 20 146 336 48 11:01 87
IPJ 1 17.6 41.9 1.1 10 120 527 23 395 59:1 96
Test 3
YUBA 1 30.1 29.7 2.3 20 146 375 47 12:01 88
IPJ 1 20.1 32.7 0.9 10 120 592 41 462 106:1 93
Test 5
IPJ 1 83 49 0.2 10 150 68 27 68 307:1 91
The IPJ concentrate was fed to a 30” Knelson and the IPJ tail was
fed to the Mill discharge sump. The Knelson feed was
approximately 0.8 t/hr of high grade concentrate only. Samples
were taken from IPJ feed, concentrate, tail and Knelson tail
(Table 3).
The table reveals the ability of the IPJ to consistently recover
gold to a high grade concentrate. It also demonstrates the ability
of the IPJ to recover a high proportion of gold which the Knelson
Concentrator is unable to recover to concentrate.
The work at SGM was carried out with a single IPJ 1500.sl -
running on 30 tph feed. The re-circulating load of the mill circuit
is up to 600 per cent (Figure 9). Further work carried out on
Pyrite recoveries showed the average mill feed of 3800 ppm
Arsenic (As) with the average IPJ concentrate grade running at
77000 ppm As.
Preliminary results from research work carried out at
Pasminco’s Rosebery Plant (Tasmania), indicate similar results
(Table 3). The object of the program was to split as much gold as
possible from the recirculating load to the Knelson feed. The
IPJ1500sl. was installed in the primary ball mill circuit and
FIG 8 - Ballarat University size by size recoveries (S Thomson, 1995). received unscreened feed directly from the mill discharge pump.
The IPJ was fed from one of the two parallel ball mills and so had
access to only half of the mill feed (Figure 9).
(*Note: The Pasminco results are derived from an average of
the optimisation work carried out. The unit was not running at
optimum for a large proportion of the period.)
Device Process Dilution Water Feed Dilution Water Feed Density Max Particle Size Possible % Recirc Load Treated
(cum water/t treated) (cum water/t treated) (% Cw) (mm) (%)
TABLE 3
IPJ recoveries at Stawell and Rosebery.
Galena recoveries
Work carried out by Reilly (1995) indicates the ability of the IPJ
to recover galena. The work was carried out with an IPJ600 Pilot
scale jig at a feed rate of between 1.5 and 2.2 t/h. and slurry feed
density of 30 per cent by weight. High recoveries were achieved,
and the potential to optimise jig recoveries through the adjustment FIG 10 - Recovery versus Cyc/Min for the 1PJ600 (P Reilley, 1995)
of various operating parameters was illustrated (Figures 10 and
11).
It is expected that the IPJ will have positive benefits in the
removal of galena and other soft heavy minerals from the grinding
circuit before overgrmnding occurs.
POTENTIAL APPLICATIONS
REFERENCES