You are on page 1of 90

Repair of RCC Bridges (From Km.327 to Km.

357 of NH-715)

ABSTRACT OF COST
(Qty.as per Statement No.1 & Rate as per S.O.R 2013-14 of APWD (NH))

Item No. Item description Unit Qty. Rate (Rs.) Amount (Rs.)

Removal of existing cement concrete wearing


coat including its disposal complete as per
Technical specification without causing any
1/16.1 detrimental effect to any part of the bridge Sqm 1193.25 78.00 93,073.50
structure and removal of dismantled material
with all lifts and lead upto 1000.(Thickness
75mm.)

Removal of existing asphaltic wearing coat


comprising of 50 mm thick asphaltic concrete
2/16.2 Sqm 2376.48 59.00 140,212.32
laid over 12 mm thick mastic asphalt including
disposal with all lift and lead upto 1000m.

Dismantling of existing structures like culverts,


bridges, retaining walls and other structure
comprising of masonry, cement concrete, wood
work, steel work, including T&P and scaffolding
3/2.4(I).II.B wherever necessary, sorting the dismantled cum 8.33 573.00 4,770.23
material,disposal of unserviceable material and
stacking the serviceable material with all lift and
lead of 1000 metres. Reinforced cement
concrete grade M-20 & above

Chipping of deteriorated concrete and removal


of all loose & friable materials and fully exposing
rusted reinforcement followed by proper
cleaning and removing of rusts and other
4/16.24 Sqm 1429.23 134.00 191,516.65
foreign materials using sand blasting/ emery
cloths/ wire brush etc. including formwork as
directed and specified by the department
complete

Providing and inserting nipples with approved


fixing compound after drilling holes for grouting
as per Technical specifications including
5/16.4 each 350.00 178.00 62,300.00
subsequent cutting/removal and sealing of the
hole as necessary of nipples after completion of
grouting with Cement/Epoxy.

Sealing of crack / porous concrete with Epoxy


Grout by injection through nipples complete as
6/16.7 kg 5077.00 1511.00 7,671,347.00
per clause 2803.1. Epoxy Grout material from
Fosroc.

Applying epoxy mortar over leached, honey


combed and spalled concrete surface and
7/16.8 Sqm 1429.23 1035.00 1,479,251.76
exposed steel reinforcement complete as per
Technical specification
Item No. Item description Unit Qty. Rate (Rs.) Amount (Rs.)

Spplying and applying two coats of Nitozinc


Primer a two component epoxy zinc rich primer
on the properly cleaned and prepared steel bars
8/16.26 (B) after the required chipping and cleaning of the Sqm 14.29 594.00 8,489.62
concrete surface as per the manufacturer‟s
specifications as directed and specified by the
department complete.

Providing and applying coating of the cleaned


patches with two part of polymer based bonding
agent Nitobond SBR of Fosroc or equivalent @
0.22 Lit per Sqm prior to application of polymer
9/16.28(B) modified mortar with brush after totally Sqm 1429.23 343.00 490,225.46
saturating the cleaned concrete surface with
clean water for proper bonding of old and new
concrete including formwork as specified and
directed by the department complete.

Concreting of the structure with free flow


nonshrink cementitious microconcrete with
Rendorec RG of Fosroc or equivalent after
10/16.31 proper mixing with cleanwater including cum 12.71 106,484.00 1,353,677.85
formwork followed by proper curing for 28 days
as per manufacturer's specifications complete
and as directed by the Department .

Applying Nitowrap 410 saturant Fosroc


Chemicals or equivalent with wet film thickness
@ 250 microns (0.27Lit per sqm) over a coat of
saturant epoxy primer Nitowrap 30 of Fosroc
Chemicals or equivalent @ 0.11Lit per sqm with
brush followed by fixing carbon fibre composite
11/16.33 (B) sqm 950.47 5794.00 5,507,008.70
system Nitowrap EP (CF) of Fosroc Chemicals
or equivalent by pressing on the saturant and
impregnate the same by applying a final coat of
Nitowrap 410 saturant Fosroc Chemicals or
equivalent as specified and directed by the
department complete including formwork.

Patching in depression of concrete surface


wherever necessary by laying epoxy putty ,
Nitocote VF of Fosroc Chemicals or equivalent
12/16.33 (A) @ 1 Lit per sqm after proper surface preparation sqm 950.47 2301.00 2,187,025.72
and proper scraping of concrete protrusion as
specified and directed by the department
complete including formwork

Applying two coats of UV resistant coating


Nitocote UR 512 (FOSROC) Chemicals or
equivalent over fibre system having wet film
13/16.33 (C) sqm 950.47 391.00 371,632.79
thickness of 100 micron @ 0.11Lit per sqm as
specified and directed by the department
complete including formwork.
Item No. Item description Unit Qty. Rate (Rs.) Amount (Rs.)

Applying 2-coats of anti-carbonation - a


protective coating Techguard 103 of Choksey
Chemicals or equivalent @ 0.275 Lit per sqm
with brush over exposed portion of the concrete
14/16.37 structure of the bridge & other structure works sqm 4462.31 289.00 1,289,606.15
etc. complete as desired to protect the
reinforced concrete by preventing the process of
carbonation and directed by the department
including formwork.

Plastering the surface with high rich polymer


modified mortar 10mm thick with cement sand
mortar in prop. 1:4 mixed with 100% acrylic
polymer Mastercrete M-81 of Chosey chemicals
15/16.29 sqm 660.00 536.00 353,760.00
or equivalent @15% by weight of cement
followed by proper curing as specified and
directed by the department complete including
formwork.

Replacement of Expansion Joints complete as


16/16.17 meter 52.50 3628.00 190,470.00
per drawings

Providing and laying of a strip seal expansion


joint catering to maximum horizontal movement
upto 70 mm, complete as per approved
17/14.22 drawings and standard specifications to be meter 52.50 11804.00 619,710.00
installed by the manufacturer/supplier or their
authorised representative ensuring compliance
to the manufacturer's instruction for installation

Providing & fixing 2 mm thick corrugated copper


18/14.18(i) plate in expansion joint complete as per drawing meter 118.20 1640.00 193,848.00
& Technical Specification.

Providing and fixing in position 20 mm thick


premoulded joint filler in expansion joint for fixed
ends of simply supported spans not exceeding
19/14.18(iii) metre 259.20 317.00 82,166.40
10 m to cater for a horizontal movement upto 20
mm, covered with sealant complete as per
drawing and technical specification.

Providing and filling joint sealing compound as


20/14.18(iv) per drawings and technical specifications with metre 236.40 17.00 4,018.80
coarse sand and 6% bitumen by weight

Mastic Asphalt Wearing course for bridges


'Providing Bituminous wearing course
comprising of tack coat with bitumen emulsion
CSS-1h as per APWD SOR item no 5.2 &
MOSRT&H Specification Nos 503, 6mm thick
mastic asphalt as per APWD SOR item no
21/17.64 14.5& MOSRT&H Specification Nos 515& 2702 Sqm 1183.23 866.00 1,024,677.18
and Asphaltic concrete of close Graded
Premix Surfacing(CGPS) materials with Type -a
aggregate Specification Nos 512 of total
avergare thickness 69mm laid in 2 layers as per
APWD SOR tem no 5.11 & MOSRT&H
including all lead and lift as directed.
Item No. Item description Unit Qty. Rate (Rs.) Amount (Rs.)

Providing and laying Cement concrete wearing


coat M-30 grade including reinforcement
22/14.4 cum 119.81 12993.00 1,556,723.81
complete as per drawing and Technical
Specifications

Providing and laying 12 mm thick mastic asphalt


wearing course on top of deck slab excluding
prime coat with paving grade bitumen meeting
the requirements given in table 500-29,
prepared by using mastic cooker and laid to
required level and slope aftering cleaning the
surface, including providing antiskid surface with
23/14.5 (A) bitumen pre coated fine grained hard stone Sqm 1597.50 329.00 525,577.50
shipping of 9.5mm nominal size at the rate of .
005 cum per 10sqm and at approximate
spaciong of 10cm center to center in both
directions, pressed into surfaces when
temperature of the surfaces not less than 100
degC. , protuding 1mm to 4mm over mastic
surfaces, all complete as per clause 515.

'Labour for replacement of Bearings complete


24/16.15 as per Technical Specification (Cost of bearing each 3.00 3339.00 10,017.00
to be paid extra)
Lifting of superstructure by jack (Cost of
bearing to be paid extra) as per approved
25/16.16. B. (i) drawing and technical specification. each 1.00 18278.00 18,278.00
Cost of lifting of superstucture for span above
10 metre to 16 metre

Supplying, fitting and fixing in position true to


line and level elastomeric bearing conforming to
IRC: 83 (Part-II) section IX and clause 2005 of
26/13.14 ccm. 129024 1.02 131,604.48
MoRTH specifications complete including all
accessories as per drawing and Technical
Specifications.

Greasing of Bearing with ULTRATACK AP3


grease including cleaeing of bearings with steel
27/17.63 brush, removal of dusts and dirt with necessary each 14.00 1284.00 17,976.00
scaffolding etc. complete as directed by the
department.
Drainage Spouts complete as per drawing and
28/14.9 each 110.00 10197.00 1,121,670.00
Technical specification
29/Anna-01 Hanging Platform for repair & painting works each 8.00 256,760.00 2,054,080.00
Extra for construction of auxilary structure above
30/16.16 C(II) 6M height including dismentling and removal of each 1.00 1,328,823.00 1,328,823.00
same for lifting of super structure.
Clearing Grass and Removal of Rubbish
( clearing grasss and removal of rubbish upto a
31/2.2 distance of 50m outside the periphery of the hectre 23.00 8,543.00 196,489.00
bridge area.)

G.Total= Rs. 30,280,026.91

Executive Engineer, P.W.D


Nagaon N.H. Division, Nagaon
Statement No-1
Summary of Quantities for repair of Bridges

Sl. No./SOR Quantity for Br. No.


Item description Unit
Item ref. 328/1 335/1 336/1 339/1 348/1 352/1 352/2 353/1 355/1 357/1
1/16.1 Removal of existing cc wearing coat Sqm 0.00 0.00 112.50 742.50 338.25 0.00 0.00 0.00 0.00 0.00
2/16.2 Removal of asphaltic/mastic wearing coat Sqm 142.50 266.25 112.50 742.50 338.25 211.70 211.70 135.00 216.08 138.00
3/2.4(I).II.B Dismantling of RCC 0.00 0.00 2.70 3.38 2.25 0.00 0.00 0.00 0.00 0.00
4/16.24 Chipping & removal of deteriorated concrete 115.60 163.41 69.65 255.06 278.35 170.37 164.87 110.45 101.48 115.60
5/16.4 Providing and inserting nipples each 29.00 41.00 35.00 64.00 46.00 41.00 41.00 28.00 25.00 29.00
6/16.7 Epoxy grouting kg 580.00 615.00 525.00 640.00 552.00 615.00 615.00 560.00 375.00 435.00
7/16.8 Epoxy mortar Sqm 115.60 163.41 69.65 255.06 278.35 170.37 164.87 110.45 101.48 115.60
8/16.26 (B) Primer coat on steel re-bars Sqm 1.16 1.63 0.70 2.55 2.78 1.70 1.65 1.10 1.01 1.16
9/16.28(B) Polymer base bonding Sqm 115.60 163.41 69.65 255.06 278.35 170.37 164.87 110.45 101.48 115.60
10/16.31 Micro concrete cum -- -- 7.09 3.38 2.25 -- -- -- -- --
11/16.33 (B) Fixing carbon fibre composite system sqm 92.63 173.06 178.74 0.00 0.00 138.48 138.48 87.75 141.34 89.70
12/16.33 (A) Patching in concreate by epoxy putty sqm 92.63 173.06 178.74 0.00 0.00 138.48 138.48 87.75 141.34 89.70
13/16.33 (C) UV resistant coating 92.63 173.06 178.74 0.00 0.00 138.48 138.48 87.75 141.34 89.70
14/16.37 Anti-carbonation-a protective coating 63.00 148.13 205.35 1700.40 1855.66 148.88 138.95 63.00 138.95 63.00
15/16.29 Plastering with polymer modified mortar sqm 110.00 110.00 0.00 0.00 0.00 110.00 110.00 110.00 110.00 110.00
16/16.17 Replacement of expansion Joint meter 0.00 0.00 15.00 22.50 15.00 0.00 0.00 0.00 0.00 0.00
17/14.22 New Strip Seal Expansion Joint meter 0.00 0.00 15.00 22.50 15.00 0.00 0.00 0.00 0.00 0.00
18/ 14.18 (i) 2 mm thick corrugated copper plate meter 15.00 22.50 0.00 0.00 0.00 21.90 21.90 15.00 21.90 15.00
19/ 14.18 (iii) 20 mm thick premoulded joint filler meter 32.40 48.60 0.00 0.00 0.00 48.60 48.60 32.40 48.60 32.40
20/ 14.18 (iv) Joint sealing Compound meter 30.00 45.00 0.00 0.00 0.00 43.80 43.80 30.00 43.80 30.00
21/17.64 Bituminous wearing coat Sqm 142.50 266.25 0.00 0.00 0.00 211.70 211.70 135.00 216.08 138.00
22/14.4 Cement concrete wearing coat M-30 grade cu.m 0.00 0.00 8.44 55.69 55.69 0.00 0.00 0.00 0.00 0.00
23/14.5 (A) Mastic Wearing Coat-12 mm Sqm 0.00 0.00 112.50 742.50 742.50 0.00 0.00 0.00 0.00 0.00
Sl. No./SOR Quantity for Br. No.
Item description Unit
Item ref. 328/1 335/1 336/1 339/1 348/1 352/1 352/2 353/1 355/1 357/1
24/16.15 Labour for replacement of bearing each 0.00 0.00 3.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
25/16.16 Lifting of superstructure by jack each 0.00 0.00 1.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
26/13.14 New Elastomeric bearing ccm. 0.00 0.00 129024 0.00 0.00 0.00 0.00 0.00 0.00 0.00
27/17.63 Greasing of Bearing each 0.00 0.00 0.00 8.00 6.00 0.00 0.00 0.00 0.00 0.00
28/14.9 Drainage spout each 10.00 20.00 12.00 32.00 6.00 8.00 8.00 6.00 8.00 6.00
29/Anna-01 Hanging Platform each 1.00 1.00 0.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00
Extra for construction of auxilary structure
30/16.16 C(II) each 0.00 0.00 1.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
above 6M height

Executive Engineer, PWD


Nagaon NH Division, Nagaon
Statement No-1
of Bridges

Quantity for Br. No.


Total
1193.25
2376.48
8.33
1429.23
350.00
5077.00
1429.23
14.29
1429.23
12.71
950.47
950.47
950.47
4462.31
660.00
52.50
52.50
118.20
259.20
236.40
1183.23
119.81
1597.50
Quantity for Br. No.
Total
3.00
1.00
129024
14.00
110.00
8.00

1.00
Statement No-2
Quantity Statement for Repair of Br.No. 328/1

Br.No. : 328/1
NH No. : NH-715 (Old NH-37)
Name of Br. location : Bordolong
Type of Superstructure : Soild Slab without footpath
Span (exp. Jt. to exp. Jt) : 01 x 9.5 m
Overall width : 8.45m
Carriageway : 7.5m

Sl. No./SOR SA
Item description Unit Nos. L (m) B (m) H/t (m) Qty. Remark
Item ref. (sq.m)
1/16.1 Removal of existing cc wearing coat Sqm
2/16.2 Removal of asphaltic/mastic wearing coat Sqm 02 9.5 7.5 142.5 142.500 02 layers.
3/2.4(I).II.B Dismantling of RCC
4/16.24 Chipping & removal of deteriorated concrete SA= damaged concrete surface area
Super-structure Sqm 01 9.5 8.45 0.925 97.85 97.850 SA=9.5*(8.45+2*0.925)=97.850
Sub-structure- Abutment Sqm 02 8.45 3.5 17.745 17.745 SA=0.3*02*(8.45*3.5)=17.745
Sub-structure- Pier Sqm 0.000
Total Area= 115.595
5/16.4 Providing and inserting nipples each 29.000 57.7975 29.000 @ 01 Nipple per 02 sq.m of SA
6/16.7 Epoxy grouting kg 580.000 @ 20 Kg. per nipple
7/16.8 Epoxy mortar Sqm 115.595 115.595
8/16.26 (B) Primer coat on steel re-bars Sqm 115.595 1.156 @ 1% sq.m of SA
9/16.28(B) Polymer base bonding Sqm 115.595 115.595
10/16.31 Micro concrete cum --
11/16.33 (B) Fixing carbon fibre composite system sqm 01 9.5 8.45 0.65 92.625 92.625 A= 9.5 * (8.45+2*0.65)=92.625 sq.m
12/16.33 (A) Patching in concreate by epoxy putty sqm 92.625 for superstructure solid slab
13/16.33 (C) UV resistant coating 92.625
14/16.37 Anti-carbonation-a protective coating
Sub-structure-Abutment sqm 2 9.00 3.50 63.00 63.000 for substrcutre. L=8.1+2*0.45=9.0m
Sl. No./SOR SA
Item description Unit Nos. L (m) B (m) H/t (m) Qty. Remark
Item ref. (sq.m)
Sub-structure-Pier sqm
Total Area= 63.000
15/16.29 Plastering with polymer modified mortar sqm 4 10 2.75 110.0 110.000 for wing wall. H=(4.5+1)/2=2.75m
16/16.17 Replacement of expansion Joint meter
17/14.22 New Strip Seal Expansion Joint meter
18/ 14.18 (i) 2 mm thick corrugated copper plate meter 2 7.5 15.000 for expansion joint
19/ 14.18 (iii) 20 mm thick premoulded joint filler meter 2x2 8.1 32.400 for expansion joint l=4*8.1=32.4m
20/ 14.18 (iv) Joint sealing Compound meter 4 7.5 30.000 for expansion joint
21/17.64 Bituminous wearing coat Sqm 2 9.5 7.5 142.500 In 02 layers, Avg.69mm thk.
22/14.4 Cement concrete wearing coat M-30 grade cu.m
23/14.5 (A) Mastic Wearing Coat-12 mm Sqm
24/16.15 Labour for replacement of bearing each
25/16.16 Lifting of superstructure by jack each
26/13.14 New Elastomeric bearing ccm.
27/17.63 Greasing of Bearing each
28/14.9 Drainage spout each 02 x 05 10
29/Anna-01 Hanging Platform each 01 01
30/16.16 C(II) Extra for construction of auxilary structure
above 6M height each

Executive Engineer, PWD


Nagaon NH Division, Nagaon
D kerb T
97.85 0.65 0.275 0.925
17.745

115.595
28.89875 580 876380

0.01

92.625
45
Statement No-3
Quantity Statement for Repair of Br.No. 335/1

Br.No. : 335/1
NH No. : NH-715 (Old NH-37)
Name of Br. location : Gurakhati
Type of Superstructure : Soild Slab without footpath
Span (exp. Jt. to exp. Jt) : 02 x 8.875 m
Overall width : 8.45 m
Carriageway : 7.5 m

Sl. No./SOR SA
Item description Unit Nos. L (m) B (m) H/t (m) Qty. Remark
Item ref. (sq.m)
1/16.1 Removal of existing cc wearing coat Sqm
2/16.2 Removal of asphaltic/mastic wearing coat Sqm 04 8.875 7.5 266.25 266.250 02 layers
3/2.4(i).I.C Dismantling of RCC
4/16.24 Chipping & removal of deteriorated concrete SA= damaged concrete area
Super-structure Sqm 02 8.875 8.45 0.925 91.4125 91.413 SA=50%*02*8.875*(8.45+2*0.925)=91.413
Sub-structure-Abutment Sqm 02 8.45 3.75 31.6875 31.688 SA=50%*02*(8.45*3.75)=31.688
Sub-structure-Pier Sqm 01 9.5 1.25 3.75 40.3125 40.313 SA=50%*2*(9.5+1.25)*3.75=40.313 sq.m
Total Area= 163.413
5/16.4 Providing and inserting nipples each 41 81.7063 41.000 @ 01 Nipple per 02 sq.m of SA
6/16.7 Epoxy grouting kg 615.000 @ 15 Kg. per nipple
7/16.8 Epoxy mortar Sqm 163.413 163.413
8/16.26 (B) Primer coat on steel re-bars Sqm 163.413 1.634 @ 1% sq.m of SA
9/16.28(B) Polymer base bonding Sqm 163.413 163.413
10/16.31 Micro concrete cum --
11/16.33 (B) Fixing carbon fibre composite system sqm 02 8.875 8.45 0.65 173.063 173.063 A= 02*8.875* (8.45+2*0.65)=173.063 sq.m
12/16.33 (A) Patching in concreate by epoxy putty sqm 173.063 for superstructure solid slab
13/16.33 (C) UV resistant coating sqm 173.063
14/16.37 Anti-carbonation-protective coating
Sub-structure-Abutment sqm 2 9.00 3.75 67.5 67.500 for substrcutre. L=8.1+2*0.45=9.0m
Sub-structure-Pier sqm 1 9.5 1.25 3.75 80.625 80.625 A=2*(9.5+1.25)*3.75=80.625 sq.m
Total Area= 148.125
15/16.29 Plastering with polymer modified mortar sqm 4 10 2.75 110.0 110.000 for wing wall. H=(4.5+1)/2=2.75m
16/16.17 Replacement of expansion Joint meter
17/14.22 New Strip Seal Expansion Joint meter
18/ 14.18 (i) 2 mm thick corrugated copper plate meter 3 7.5 22.500 for expansion joint
19/ 14.18 (iii) 20 mm thick premoulded joint filler meter 3 x 2 8.1 48.600 for expansion joint l=6*8.1=48.6 m
20/ 14.18 (iv) Joint sealing Compound meter 6 7.5 45.000 for expansion joint
21/17.64 Bituminous wearing coat Sqm 4 8.875 7.5 266.250 In 02 layers, Avg.69mm thk.
22/14.4 Cement concrete wearing coat M-30 grade cu.m
23/14.5 (A) Mastic Wearing Coat-12 mm Sqm
24/16.15 Labour for replacement of bearing each
25/16.16 Lifting of superstructure by jack each
26/13.14 New Elastomeric bearing ccm.
27/17.63 Greasing of Bearing each
28/14.9 Drainage spout each 4 x 5 20
29/Anna-01 Hanging Platform each 01 01
30/16.16 C(II) Extra for construction of auxilary structure
above 6M height each

Executive Engineer, PWD


Nagaon NH Division, Nagaon
17.75

D kerb T
91.413 0.65 0.275 0.925
31.6875
40.313
123.1
40.85313 580 876380

0.01

173.0625
45

48.6
Statement No-4
Quantity Statement for Repair of Br.No. 336/1

Br.No. : 336/1
NH No. : NH-715 (Old NH-37)
Name of Br. location : Phullaguri Sang
Type of Superstructure : T-beam Slab
Span (exp. Jt. to exp. Jt) : 01 x15 m
Overall width : 8.5 m
Carriageway : 7.5 m

Sl. No./SOR SA
Item description Unit Nos. L (m) B (m) H/t (m) Qty. Remark
Item ref. (sq.m)
1/16.1 Removal of existing cc wearing coat Sqm 01 15.0 7.5 112.5 112.500
2/16.2 Removal of asphaltic/mastic wearing coat Sqm 01 15.0 7.5 112.5 112.500
3/2.4(i).I.C Dismantling of RCC cum 04 7.5 0.3 0.3 2.700 For repalcement of Exp. Joint
4/16.24 Chipping & removal of deteriorated concrete SA= damaged concrete surface area
T-beam Slab Area=232.17 sq.m
Super-structure Sqm 01 69.651 69.651
SA=30%* 232.17= 69.651 sq.m
Sub-structure- Abutment Sqm
Sub-structure- Pier Sqm
Total Area= 69.651
5/16.4 Providing and inserting nipples each 35.00 69.651 35.000 @ 01 Nipple per 02 sq.m of SA
6/16.7 Epoxy grouting kg 525.000 @ 15 Kg. per nipple
7/16.8 Epoxy mortar Sqm 69.651 69.651
8/16.26 (B) Primer coat on steel re-bars Sqm 69.651 0.697 @ 1% sq.m of SA
9/16.28(B) Polymer base bonding Sqm 69.651 69.651
Damaged Girder End over bearing
10/16.31 Micro concrete cum 7.088 = 03*2.5*0.45*1.3=4.3875 cu.m
for grouting Exp. Joint= 2.70 cu.m

L.Girder= 03*15*(2*1.5+0.3)=148.5
11/16.33 (B) Fixing carbon fibre composite system sqm 178.74 178.740 C.G = 03*02*(2*1.0*2.24+2.24*0.25)
=30.24 sq.m
12/16.33 (A) Patching in concreate by epoxy putty sqm 178.740
13/16.33 (C) UV resistant coating 178.740
14/16.37 Anti-carbonation-a protective coating
Superstrcuture slab soffit sqm 118.20 118.200 A= 02*(1.7+2.24)*15 =118.20 sq.m
Sub-structure-Abutment 87.15 87.150 A= 02*(8.45+2*2.0)*3.5 =87.15
Total Area= 205.350
15/16.29 Plastering with polymer modified mortar sqm
16/16.17 Replacement of expansion Joint meter 2 7.5 15.000
17/14.22 New Strip Seal Expansion Joint meter 2 7.5 15.000
18/ 14.18 (i) 2 mm thick corrugated copper plate meter
19/ 14.18 (iii) 20 mm thick premoulded joint filler meter
20/ 14.18 (iv) Joint sealing Compound meter
21/17.64 Bituminous wearing coat Sqm
22/14.4 Cement concrete wearing coat M-30 grade cu.m 1 15 7.5 0.075 8.438
23/14.5 (A) Mastic Wearing Coat-12 mm Sqm 1 15 7.5 112.5 112.500
24/16.15 Labour for replacement of bearing each 3 3.0
25/16.16 B.I) Lifting of superstructure by jack each 1 1.0
26/13.14 New Elastomeric bearing ccm. 6 129024 Qty=03*02*56*40*9.6=129024
27/17.63 Greasing of Bearing each
28/14.9 Drainage spout each 02 x 06 12
29/Anna-01 Hanging Platform each
30/16.16 C(II) Extra for construction of auxilary structure
above 6M height each 01 1.000

Executive Engineer, PWD


Nagaon NH Division, Nagaon
D kerb T

97.85 0.65 0.275 0.925

17.745

115.595
34.8255 580 876380

0.01

4.3875

148.5 30.24 178.74


118.2
87.15

129024
Statement No-5
Quantity Statement for Repair of Br.No. 339/1

Br.No. : 339/1
NH No. : NH-715 (Old NH-37)
Name of Br. location : Deosur
Type of Superstructure : RCC Box Girder without footpath
Span (exp. Jt. to exp. Jt) : 02 x 49.5
Overall width : 8.45 m
Carriageway : 7.5 m

Sl. No./SOR SA
Item description Unit Nos. L (m) B (m) H/t (m) Qty. Remark
Item ref. (sq.m)
1/16.1 Removal of existing cc wearing coat Sqm 01 99.0 7.5 742.5 742.500
2/16.2 Removal of asphaltic/mastic wearing coat Sqm 01 99.0 7.5 742.5 742.500 Top mastic layer
3/2.4(i).I.C Dismantling of RCC cum 06 7.5 0.3 0.25 3.375 For repalcement of Exp. Joint
4/16.24 Chipping & removal of deteriorated concrete SA= damaged concrete surface area
Br. Surface Area=1700.4 sq.m
Super-structure Sqm 255.06 255.060
Damaged surface @ 15%
Sub-structure- Abutment Sqm
Sub-structure- Pier Sqm
Total Area= 255.060
5/16.4 Providing and inserting nipples each 127.530 64.00 @ 01 Nipple per 02 sq.m of SA
6/16.7 Epoxy grouting kg 640.000 @ 10 Kg. per nipple
7/16.8 Epoxy mortar Sqm 255.060 255.060
8/16.26 (B) Primer coat on steel re-bars Sqm 255.060 2.551 @ 1% sq.m of SA
9/16.28(B) Polymer base bonding Sqm 255.060 255.060
10/16.31 Micro concrete cum 3.375 for grouting Exp. Joint= 3.375 cu.m
11/16.33 (B) Fixing carbon fibre composite system sqm
12/16.33 (A) Patching in concreate by epoxy putty sqm
13/16.33 (C) UV resistant coating
14/16.37 Anti-carbonation-a protective coating
Superstrcuture slab soffit sqm 1700.40 1700.400 Superst. Surface Area=1700.4 sq.m
Sub-structure-Abutment
Total Area= 1700.400
15/16.29 Plastering with polymer modified mortar sqm
16/16.17 Replacement of expansion Joint meter 3 7.5 22.500
17/14.22 New Strip Seal Expansion Joint meter 3 7.5 22.500
18/ 14.18 (i) 2 mm thick corrugated copper plate meter
19/ 14.18 (iii) 20 mm thick premoulded joint filler meter
20/ 14.18 (iv) Joint sealing Compound meter
21/17.64 Bituminous wearing coat Sqm
22/14.4 Cement concrete wearing coat M-30 grade cu.m 1 99 7.5 0.075 55.688
23/14.5 (A) Mastic Wearing Coat-12 mm Sqm 1 99 7.5 742.5 742.500
24/16.15 Labour for replacement of bearing each
25/16.16 B.I) Lifting of superstructure by jack each
26/13.14 New Elastomeric bearing ccm.
27/17.63 Greasing of Bearing each 08 8.0
28/14.9 Drainage spout each 32 32.0
29/Anna-01 Hanging Platform each 01 1.0
30/16.16 C(II) Extra for construction of auxilary structure
above 6M height each

Executive Engineer, PWD


Nagaon NH Division, Nagaon
Statement No-6
Quantity Statement for Repair of Br.No. 348/1

Br.No. : 348/1
NH No. : NH-715 (Old NH-37)
Name of Br. location : Deopani
Type of Superstructure : RCC T-beam Girder Slabwithout footpath
Span (exp. Jt. to exp. Jt) : 01 X 45.1
Overall width : 8.5m
Carriageway : 7.5m

Sl. No./SOR SA
Item description Unit Nos. L (m) B (m) H/t (m) Qty. Remark
Item ref. (sq.m)
1/16.1 Removal of existing cc wearing coat Sqm 01 45.1 7.5 338.25 338.250
2/16.2 Removal of asphaltic/mastic wearing coat Sqm 01 45.1 7.5 338.25 338.250 Top mastic layer
3/2.4(i).I.C Dismantling of RCC cum 04 7.5 0.3 0.25 2.250 For repalcement of Exp. Joint
4/16.24 Chipping & removal of deteriorated concrete
Br. Surface Area=1855.655 sq.m
Super-structure Sqm 278.348 278.348
Damaged surface @ 15%
Sub-structure- Abutment Sqm
Sub-structure- Pier Sqm
Total Area= 278.348
5/16.4 Providing and inserting nipples each 92.783 46.000 @ 01 Nipple per 02 sq.m of SA
6/16.7 Epoxy grouting kg 552.000 @ 12 Kg. per nipple
7/16.8 Epoxy mortar Sqm 278.348
8/16.26 (B) Primer coat on steel re-bars Sqm 278.348 2.783 @ 1% sq.m of SA
9/16.28(B) Polymer base bonding Sqm 278.348 278.348
10/16.31 Micro concrete cum 2.250 for grouting Exp. Joint= 2.25 cu.m
11/16.33 (B) Fixing carbon fibre composite system sqm
12/16.33 (A) Patching in concreate by epoxy putty sqm
13/16.33 (C) UV resistant coating
14/16.37 Anti-carbonation-a protective coating
Superstrcuture slab soffit sqm 1855.66 1855.655 Superst. SA=1855.655 sq.m
Sub-structure-Abutment
Total Area= 1855.655
15/16.29 Plastering with polymer modified mortar sqm
16/16.17 Replacement of expansion Joint meter 2 7.5 15.000
17/14.22 New Strip Seal Expansion Joint meter 2 7.5 15.000
18/ 14.18 (i) 2 mm thick corrugated copper plate meter
19/ 14.18 (iii) 20 mm thick premoulded joint filler meter
20/ 14.18 (iv) Joint sealing Compound meter
21/17.64 Bituminous wearing coat Sqm
22/14.4 Cement concrete wearing coat M-30 grade cu.m 1 99 7.5 0.075 55.688
23/14.5 (A) Mastic Wearing Coat-12 mm Sqm 1 99 7.5 742.5 742.500
24/16.15 Labour for replacement of bearing each
25/16.16 B.I) Lifting of superstructure by jack each
26/13.14 New Elastomeric bearing ccm.
27/17.63 Greasing of Bearing each 06 6.0
28/14.9 Drainage spout each 6 6.0
29/Anna-01 Hanging Platform each 01 1.0
30/16.16 C(II) Extra for construction of auxilary structure
above 6M height each

Executive Engineer, PWD


Nagaon NH Division, Nagaon
278.3482
1855.655
Statement No-7
Quantity Statement for Repair of Br.No. 352/1

Br.No. : 352/1
NH No. : NH-715 (Old NH-37)
Name of Br. location : Kuthari
Type of Superstructure : R.C.C Soild Slab without footpath
Span (exp. Jt. to exp. Jt) : 02 x 7.25 m
Overall width : 8.25 m
Carriageway : 7.3 m

Sl. No./SOR SA
Item description Unit Nos. L (m) B (m) H/t (m) Qty. Remark
Item ref. (sq.m)
1/16.1 Removal of existing cc wearing coat Sqm
2/16.2 Removal of asphaltic/mastic wearing coat Sqm 04 7.25 7.3 211.7 211.700 02 layers
3/2.4(i).I.C Dismantling of RCC
4/16.24 Chipping & removal of deteriorated concrete SA= damaged concrete area
Super-structure Sqm 02 7.25 8.25 0.925 87.87 87.870 SA=60%*02*7.25*(8.25+2*0.925)=87.87
Sub-structure-Abutment Sqm 02 9.1 3.75 34.125 34.125 SA=50%*02*(9.1*3.75)=34.125
Sub-structure-Pier Sqm 01 9.5 1.25 3.75 48.375 48.375 SA=60%*2*(9.5+1.25)*3.75=48.375 sq.m
Total Area= 170.370
5/16.4 Providing and inserting nipples each 41 85.185 41.000 @ 01 Nipple per 02 sq.m of SA
6/16.7 Epoxy grouting kg 615.000 @ 15 Kg. per nipple
7/16.8 Epoxy mortar Sqm 170.370 170.370
8/16.26 (B) Primer coat on steel re-bars Sqm 170.370 1.704 @ 1% sq.m of SA
9/16.28(B) Polymer base bonding Sqm 170.370 170.370
10/16.31 Micro concrete cum --
11/16.33 (B) Fixing carbon fibre composite system sqm 02 7.25 8.25 0.65 138.475 138.475 A= 02*7.25* (8.25+2*0.65)=138.475 sq.m
12/16.33 (A) Patching in concreate by epoxy putty sqm 138.475 for superstructure solid slab
13/16.33 (C) UV resistant coating sqm 138.475
14/16.37 Anti-carbonation-protective coating
Sub-structure-Abutment sqm 2 9.10 3.75 68.25 68.250 for substrcutre. L=8.1+2*0.5=9.1m
Sub-structure-Pier sqm 1 9.5 1.25 3.75 80.625 80.625 A=2*(9.5+1.25)*3.75=80.625 sq.m
Total Area= 148.875
15/16.29 Plastering with polymer modified mortar sqm 4 10 2.75 110.0 110.000 for wing wall. H=(4.5+1)/2=2.75m
16/16.17 Replacement of expansion Joint meter
17/14.22 New Strip Seal Expansion Joint meter
18/ 14.18 (i) 2 mm thick corrugated copper plate meter 3 7.3 21.900 for expansion joint
19/ 14.18 (iii) 20 mm thick premoulded joint filler meter 3 x 2 8.1 48.600 for expansion joint l=6*8.1=48.6 m
20/ 14.18 (iv) Joint sealing Compound meter 6 7.3 43.800 for expansion joint
21/17.64 Bituminous wearing coat Sqm 4 7.25 7.3 211.700 In 02 layers, Avg.69mm thk.
22/14.4 Cement concrete wearing coat M-30 grade cu.m
23/14.5 (A) Mastic Wearing Coat-12 mm Sqm
24/16.15 Labour for replacement of bearing each
25/16.16 Lifting of superstructure by jack each
26/13.14 New Elastomeric bearing ccm.
27/17.63 Greasing of Bearing each
28/14.9 Drainage spout each 2 x 4 08
29/Anna-01 Hanging Platform each 01 01
30/16.16 C(II) Extra for construction of auxilary structure
above 6M height each

Executive Engineer, PWD


Nagaon NH Division, Nagaon
D kerb T
87.870 0.65 0.275 0.925
34.125
48.375
121.995
42.5925 580 876380

0.01

138.475
45

48.6
Statement No-8
Quantity Statement for Repair of Br.No. 352/2

Br.No. : 352/2
NH No. : NH-715 (Old NH-37)
Name of Br. location : Harmoti
Type of Superstructure : R.C.C Soild Slab without footpath
Span (exp. Jt. to exp. Jt) : 02 x 7.25 m
Overall width : 8.25 m
Carriageway : 7.3 m

Sl. No./SOR SA
Item description Unit Nos. L (m) B (m) H/t (m) Qty. Remark
Item ref. (sq.m)
1/16.1 Removal of existing cc wearing coat Sqm
2/16.2 Removal of asphaltic/mastic wearing coat Sqm 04 7.25 7.3 211.7 211.700 02 layers
3/2.4(i).I.C Dismantling of RCC
4/16.24 Chipping & removal of deteriorated concrete SA= damaged concrete area
Super-structure Sqm 02 7.25 8.25 0.925 87.87 87.870 SA=60%*02*7.25*(8.25+2*0.925)=87.87
Sub-structure-Abutment Sqm 02 9.1 3.5 31.85 31.850 SA=50%*02*(9.1*3.5)=31.85
Sub-structure-Pier Sqm 01 9.5 1.25 3.5 45.15 45.150 SA=60%*2*(9.5+1.25)*3.5=45.150 sq.m
Total Area= 164.870
5/16.4 Providing and inserting nipples each 41 82.435 41.000 @ 01 Nipple per 02 sq.m of SA
6/16.7 Epoxy grouting kg 615.000 @ 15 Kg. per nipple
7/16.8 Epoxy mortar Sqm 164.870 164.870
8/16.26 (B) Primer coat on steel re-bars Sqm 164.870 1.649 @ 1% sq.m of SA
9/16.28(B) Polymer base bonding Sqm 164.870 164.870
10/16.31 Micro concrete cum --
11/16.33 (B) Fixing carbon fibre composite system sqm 02 7.25 8.25 0.65 138.475 138.475 A= 02*7.25* (8.25+2*0.65)=138.475 sq.m
12/16.33 (A) Patching in concreate by epoxy putty sqm 138.475 for superstructure solid slab
13/16.33 (C) UV resistant coating sqm 138.475
14/16.37 Anti-carbonation-protective coating
Sub-structure-Abutment sqm 2 9.10 3.50 63.7 63.700 for substrcutre. L=8.1+2*0.5=9.1m
Sub-structure-Pier sqm 1 9.5 1.25 3.50 75.25 75.250 A=2*(9.5+1.25)*3.5=75.25 sq.m
Total Area= 138.950
15/16.29 Plastering with polymer modified mortar sqm 4 10 2.75 110.0 110.000 for wing wall. H=(4.5+1)/2=2.75m
16/16.17 Replacement of expansion Joint meter
17/14.22 New Strip Seal Expansion Joint meter
18/ 14.18 (i) 2 mm thick corrugated copper plate meter 3 7.3 21.900 for expansion joint
19/ 14.18 (iii) 20 mm thick premoulded joint filler meter 3 x 2 8.1 48.600 for expansion joint l=6*8.1=48.6 m
20/ 14.18 (iv) Joint sealing Compound meter 6 7.3 43.800 for expansion joint
21/17.64 Bituminous wearing coat Sqm 4 7.25 7.3 211.700 In 02 layers, Avg.69mm thk.
22/14.4 Cement concrete wearing coat M-30 grade cu.m
23/14.5 (A) Mastic Wearing Coat-12 mm Sqm
24/16.15 Labour for replacement of bearing each
25/16.16 Lifting of superstructure by jack each
26/13.14 New Elastomeric bearing ccm.
27/17.63 Greasing of Bearing each
28/14.9 Drainage spout each 2 x 4 08
29/Anna-01 Hanging Platform each 01 01
30/16.16 C(II) Extra for construction of auxilary structure
above 6M height each

Executive Engineer, PWD


Nagaon NH Division, Nagaon
D kerb T
87.870 0.65 0.275 0.925
31.85
45.150
119.72
41.2175 580 876380

0.01

138.475
45

48.6
Statement No-9
Quantity Statement for Repair of Br.No. 353/1

Br.No. : 353/1
NH No. : NH-715 (Old NH-37)
Name of Br. location : Harmoti
Type of Superstructure : R.C.C Soild Slab without footpath
Span (exp. Jt. to exp. Jt) : 01 x 9 m
Overall width : 8.45 m
Carriageway : 7.5 m

Sl. No./SOR SA
Item description Unit Nos. L (m) B (m) H/t (m) Qty. Remark
Item ref. (sq.m)
1/16.1 Removal of existing cc wearing coat Sqm
2/16.2 Removal of asphaltic/mastic wearing coat Sqm 02 9 7.5 135 135.000 02 layers.
3/2.4(I).II.B Dismantling of RCC
4/16.24 Chipping & removal of deteriorated concrete SA= damaged concrete surface area
Super-structure Sqm 01 9.00 8.45 0.925 92.7 92.700 SA=9.0*(8.45+2*0.925)=92.70
Sub-structure- Abutment Sqm 02 8.45 3.5 17.745 17.745 SA=0.3*02*(8.45*3.5)=17.745
Sub-structure- Pier Sqm 0.000
Total Area= 110.445
5/16.4 Providing and inserting nipples each 28.000 55.2225 28.000 @ 01 Nipple per 02 sq.m of SA
6/16.7 Epoxy grouting kg 560.000 @ 20 Kg. per nipple
7/16.8 Epoxy mortar Sqm 110.445 110.445
8/16.26 (B) Primer coat on steel re-bars Sqm 110.445 1.104 @ 1% sq.m of SA
9/16.28(B) Polymer base bonding Sqm 110.445 110.445
10/16.31 Micro concrete cum --
11/16.33 (B) Fixing carbon fibre composite system sqm 01 9 8.45 0.65 87.75 87.750 A= 9.0 * (8.45+2*0.65)=87.75 sq.m
12/16.33 (A) Patching in concreate by epoxy putty sqm 87.750 for superstructure solid slab
13/16.33 (C) UV resistant coating 87.750
14/16.37 Anti-carbonation-a protective coating
Sub-structure-Abutment sqm 2 9.00 3.50 63.00 63.000 for substrcutre. L=8.1+2*0.45=9.0m
Sub-structure-Pier sqm
Total Area= 63.000
15/16.29 Plastering with polymer modified mortar sqm 4 10 2.75 110.0 110.000 for wing wall. H=(4.5+1)/2=2.75m
16/16.17 Replacement of expansion Joint meter
17/14.22 New Strip Seal Expansion Joint meter
18/ 14.18 (i) 2 mm thick corrugated copper plate meter 2 7.5 15.000 for expansion joint
19/ 14.18 (iii) 20 mm thick premoulded joint filler meter 2x2 8.1 32.400 for expansion joint l=4*8.1=32.4m
20/ 14.18 (iv) Joint sealing Compound meter 4 7.5 30.000 for expansion joint
21/17.64 Bituminous wearing coat Sqm 2 9 7.5 135.000 In 02 layers, Avg.69mm thk.
22/14.4 Cement concrete wearing coat M-30 grade cu.m
23/14.5 (A) Mastic Wearing Coat-12 mm Sqm
24/16.15 Labour for replacement of bearing each
25/16.16 Lifting of superstructure by jack each
26/13.14 New Elastomeric bearing ccm.
27/17.63 Greasing of Bearing each
28/14.9 Drainage spout each 02 x 03 06
29/Anna-01 Hanging Platform each 01 01
30/16.16 C(II) Extra for construction of auxilary structure
above 6M height each

Executive Engineer, PWD


Nagaon NH Division, Nagaon
D kerb T
92.7 0.65 0.275 0.925
17.745

110.445
27.61125 580 876380

0.01

87.75
45
Statement No-10
Quantity Statement for Repair of Br.No. 355/1

Br.No. : 355/1
NH No. : NH-715 (Old NH-37)
Name of Br. location : Harmoti
Type of Superstructure : R.C.C Soild Slab without footpath
Span (exp. Jt. to exp. Jt) : 02 x 7.4 m
Overall width : 8.25 m
Carriageway : 7.3 m

Sl. No./SOR SA
Item description Unit Nos. L (m) B (m) H/t (m) Qty. Remark
Item ref. (sq.m)
1/16.1 Removal of existing cc wearing coat Sqm
2/16.2 Removal of asphaltic/mastic wearing coat Sqm 04 7.4 7.3 216.08 216.080 02 layers
3/2.4(i).I.C Dismantling of RCC
4/16.24 Chipping & removal of deteriorated concrete SA= damaged concrete area
Super-structure Sqm 02 7.4 8.25 0.925 59.792 59.792 SA=40%*02*7.4*(8.25+2*0.925)=59.72
Sub-structure-Abutment Sqm 02 9.1 3.5 19.11 19.110 SA=30%*02*(9.1*3.5)=19.11
Sub-structure-Pier Sqm 01 9.5 1.25 3.5 22.575 22.575 SA=30%*2*(9.5+1.25)*3.5=22.575 sq.m
Total Area= 101.477
5/16.4 Providing and inserting nipples each 41 50.7385 25.000 @ 01 Nipple per 02 sq.m of SA
6/16.7 Epoxy grouting kg 375.000 @ 15 Kg. per nipple
7/16.8 Epoxy mortar Sqm 101.477 101.477
8/16.26 (B) Primer coat on steel re-bars Sqm 101.477 1.015 @ 1% sq.m of SA
9/16.28(B) Polymer base bonding Sqm 101.477 101.477
10/16.31 Micro concrete cum --
11/16.33 (B) Fixing carbon fibre composite system sqm 02 7.4 8.25 0.65 141.34 141.340 A= 02*7.4* (8.25+2*0.65)=141.34 sq.m
12/16.33 (A) Patching in concreate by epoxy putty sqm 141.340 for superstructure solid slab
13/16.33 (C) UV resistant coating sqm 141.340
14/16.37 Anti-carbonation-protective coating
Sub-structure-Abutment sqm 2 9.10 3.50 63.7 63.700 for substrcutre. L=8.1+2*0.5=9.1m
Sub-structure-Pier sqm 1 9.5 1.25 3.50 75.25 75.250 A=2*(9.5+1.25)*3.5=75.25 sq.m
Total Area= 138.950
15/16.29 Plastering with polymer modified mortar sqm 4 10 2.75 110.0 110.000 for wing wall. H=(4.5+1)/2=2.75m
16/16.17 Replacement of expansion Joint meter
17/14.22 New Strip Seal Expansion Joint meter
18/ 14.18 (i) 2 mm thick corrugated copper plate meter 3 7.3 21.900 for expansion joint
19/ 14.18 (iii) 20 mm thick premoulded joint filler meter 3 x 2 8.1 48.600 for expansion joint l=6*8.1=48.6 m
20/ 14.18 (iv) Joint sealing Compound meter 6 7.3 43.800 for expansion joint
21/17.64 Bituminous wearing coat Sqm 4 7.4 7.3 216.080 In 02 layers, Avg.69mm thk.
22/14.4 Cement concrete wearing coat M-30 grade cu.m
23/14.5 (A) Mastic Wearing Coat-12 mm Sqm
24/16.15 Labour for replacement of bearing each
25/16.16 Lifting of superstructure by jack each
26/13.14 New Elastomeric bearing ccm.
27/17.63 Greasing of Bearing each
28/14.9 Drainage spout each 2 x 4 08
29/Anna-01 Hanging Platform each 01 01
30/16.16 C(II) Extra for construction of auxilary structure
above 6M height each

Executive Engineer, PWD


Nagaon NH Division, Nagaon
D kerb T
59.792 0.65 0.275 0.925
19.11
22.575
78.902
25.36925 580 876380

0.01

141.34
45

48.6
Statement No-11
Quantity Statement for Repair of Br.No. 357/1

Br.No. : 357/1
NH No. : NH-715 (Old NH-37)
Name of Br. location : Bagori
Type of Superstructure : Soild Slab without footpath
Span (exp. Jt. to exp. Jt) : 01 x 9.2 m
Overall width : 8.45 m
Carriageway : 7.5 m

Sl. No./SOR SA
Item description Unit Nos. L (m) B (m) H/t (m) Qty. Remark
Item ref. (sq.m)
1/16.1 Removal of existing cc wearing coat Sqm
2/16.2 Removal of asphaltic/mastic wearing coat Sqm 02 9.2 7.5 138 138.000 02 layers.
3/2.4(I).II.B Dismantling of RCC
4/16.24 Chipping & removal of deteriorated concrete SA= damaged concrete surface area
Super-structure Sqm 01 9.2 8.45 0.925 97.85 97.850 SA=9.5*(8.45+2*0.925)=97.850
Sub-structure- Abutment Sqm 02 8.45 3.5 17.745 17.745 SA=0.3*02*(8.45*3.5)=17.745
Sub-structure- Pier Sqm 0.000
Total Area= 115.595
5/16.4 Providing and inserting nipples each 29.000 57.7975 29.000 @ 01 Nipple per 02 sq.m of SA
6/16.7 Epoxy grouting kg 435.000 @ 15 Kg. per nipple
7/16.8 Epoxy mortar Sqm 115.595 115.595
8/16.26 (B) Primer coat on steel re-bars Sqm 115.595 1.156 @ 1% sq.m of SA
9/16.28(B) Polymer base bonding Sqm 115.595 115.595
10/16.31 Micro concrete cum --
11/16.33 (B) Fixing carbon fibre composite system sqm 01 9.2 8.45 0.65 89.7 89.700 A= 9.5 * (8.45+2*0.65)=92.625 sq.m
12/16.33 (A) Patching in concreate by epoxy putty sqm 89.700 for superstructure solid slab
13/16.33 (C) UV resistant coating 89.700
14/16.37 Anti-carbonation-a protective coating
Sub-structure-Abutment sqm 2 9.00 3.50 63.00 63.000 for substrcutre. L=8.1+2*0.45=9.0m
Sub-structure-Pier sqm
Total Area= 63.000
15/16.29 Plastering with polymer modified mortar sqm 4 10 2.75 110.0 110.000 for wing wall. H=(4.5+1)/2=2.75m
16/16.17 Replacement of expansion Joint meter
17/14.22 New Strip Seal Expansion Joint meter
18/ 14.18 (i) 2 mm thick corrugated copper plate meter 2 7.5 15.000 for expansion joint
19/ 14.18 (iii) 20 mm thick premoulded joint filler meter 2x2 8.1 32.400 for expansion joint l=4*8.1=32.4m
20/ 14.18 (iv) Joint sealing Compound meter 4 7.5 30.000 for expansion joint
21/17.64 Bituminous wearing coat Sqm 2 9.2 7.5 138.000 In 02 layers, Avg.69mm thk.
22/14.4 Cement concrete wearing coat M-30 grade cu.m
23/14.5 (A) Mastic Wearing Coat-12 mm Sqm
24/16.15 Labour for replacement of bearing each
25/16.16 Lifting of superstructure by jack each
26/13.14 New Elastomeric bearing ccm.
27/17.63 Greasing of Bearing each
28/14.9 Drainage spout each 02 x 03 06
29/Anna-01 Hanging Platform each 01 01
30/16.16 C(II) Extra for construction of auxilary structure
above 6M height each

Executive Engineer, PWD


Nagaon NH Division, Nagaon
D kerb T
97.85 0.65 0.275 0.925
17.745

115.595
28.89875 580 876380

0.01

92.625
45
BRIDGE DISTRESS PHOTHOGRAPH

BR. No-328/1

BR. No-335/1
BR. No-336/1

BR. No-339/1
BR. No-348/1

BR. No-352/1
BR. No-353/1

BR. No-355/1
BR. No-357/1
Annalysis of Hanging Platform for repair & painting of Bridges

Total
Sl.No Item No Particulars/ Description of Items Unit Rate (Rs)
Quantity

Providing and launching steel struss of structural steel BUG super structure including painting complete
as per section 1900 of MoRTH specification.
14.14 Quantity Calculation
SOR for ISMB250 4x5.0x37.3 = 746 kg
1 mt 0.969 158977.00
SH, MDR ISMB150 5x3.0x14.9 = 223.5 kg
2018-19 ----------------------------------------------
= 969.5 kg

Supplying, fitting and fixing Azar, Nahar or Nageswar woodwork complete, including fixing with MS
Boards, nuts , nails, screws etc. and coal taring two coats with best tar applied hot as per approved
drawings and technical specifications, complete as per direction of Engineer in charge. (a ) In Undressed
woodwork in floor planks, collars, bracing, wheel guards,struts,runner belts,railings,. Railposts, runners
etc....
2 17.7/a Quantity Calculation cum 3.910 26269.00
Runner 4x5.0x0.10x0.10 = 0.2 cum
Decking 55x3.0x0.15x.15 = 3.71 cum
------------------------------------------------------
= 3.91 cum

Total Amount = Rs.


say

Executive Engineer, PWD


Nagaon NH Division, Nagaon
Anexure -1

of Bridges

Amount (Rs.)

154048.71

102711.79

256760.50
256,760.00

Executive Engineer, PWD


Nagaon NH Division, Nagaon
Statement No-11
Quantity Statement for Repair of Br.No. 357/1

Br.No. : 357/1
NH No. : NH-715 (Old NH-37)
Name of Br. location : Harmoti
Type of Superstructure : R.C.C Soild Slab
Span (exp. Jt. to exp. Jt) : 01 x 9.2 m
Overall width : 8.5 m
Carriageway : 7.5 m

Quantity

wing/
Item No. Item description Unit Existing
Super- Substrcu return/ Bearig Exp. Wearing Drainage
wearing others Total
structure tre screen Pedastal Joint Coat spout
coat
wall

1/16.1 Removal of existing cc wearing coat Sqm 0.00


2/16.2 Removal of asphaltic/mastic wearing coat Sqm 69.00 69.00
3/2.4(i).I.C Dismantling of RCC 0.00
4/16.24 Chipping & removal of deteriorated concrete Sqm --- 31.27 15.26 -- -- -- 46.53
5/16.4 Providing and inserting nipples each 16.00 8.00 24.00
6/16.5 A Cement grouting kg 460.00 460.00
7/16.7 Epoxy grouting kg 240.00 240.00
8/16.8 Epoxy mortar Sqm 31.27 7.63 2.50 41.40
9/16.26 (B) Primer coat on steel re-bars Sqm 1.04 0.76 0.13 1.93
10/16.28(B) Polymer base bonding Sqm 31.27 7.63 2.50 41.40
11/16.31 Micro concrete cum -- -- 0.00
12/16.33 (A) Patching in concreate by epoxy putty sqm 89.24 89.24
13/16.33 (B) Fixing carbon fibre composite system sqm 89.24 89.24
14/16.33 (C) UV resistant coating sqm 89.24 89.24
15/16.37 Anti-carbonation-a protective coating sqm 104.24 104.24
16/16.29 Plastering with polymer modified mortar sqm 76.3 76.30
17/14.26 Providing water proofing compound sqm 0.00
18/16.17 Replacement of expansion Joint meter 0.00
19/14.22 New Streap Seal Expansion Joint meter 0.00
20/14.18(i) Corrugated copper plate in expansion joint meter 0.00
21/14.5 (B) Bituminous wearing coat Sqm 69.00 69.00
22/5.14 (ii) Mastic Wearing Coat-40mm Sqm 0.00
23/16.15 Labour for replacement of bearing each 0.00
24/16.16 Lifting of superstructure by jack each 0.00
25/13.14 New Elastomeric bearing ccm. 0.00
26/17.63 Greasing of Bearing each 0.00
27/14.9 Drainage spout each 0.00
28/Anna-01 Hanging Platform each 0.00
29/16.43 NDT with Ultrasonic Pulse Velocity Meter each 0.00

Executive Engineer, PWD


Nagaon NH Division, Nagaon
15

104.236 76.3 20%

50
10kg/nipple
40%
1%
30%

89.24
Statement No-10
Quantity Statement for Repair of Br.No. 355/1

Br.No. : 355/1
NH No. : NH-715 (Old NH-37)
Name of Br. location : Harmoti
Type of Superstructure : R.C.C Soild Slab
Span (exp. Jt. to exp. Jt) : (01x7.6)+(01 x 7.4) m
Overall width : 8.5m
Carriageway : 7.5m

Quantity

wing/
Item No. Item description Unit Existing
Super- Substrcu return/ Bearig Exp. Wearing Drainage
wearing others Total
structure tre screen Pedastal Joint Coat spout
coat
wall

1/16.1 Removal of existing cc wearing coat Sqm 0.00


2/16.2 Removal of asphaltic/mastic wearing coat Sqm 112.50 112.50
3/2.4(i).I.C Dismantling of RCC 0.00
4/16.24 Chipping & removal of deteriorated concrete Sqm --- 67.98 15.26 -- -- -- 83.24
5/16.4 Providing and inserting nipples each 35.00 8.00 43.00
6/16.5 A Cement grouting kg 750.00 750.00
7/16.7 Epoxy grouting kg 700.00 700.00
8/16.8 Epoxy mortar Sqm 67.98 7.63 4.00 79.61
9/16.26 (B) Primer coat on steel re-bars Sqm 3.40 0.76 0.20 4.36
10/16.28(B) Polymer base bonding Sqm 50.99 7.63 4.00 62.62
11/16.31 Micro concrete cum -- -- 0.00
12/16.33 (A) Patching in concreate by epoxy putty sqm 60.00 60.00
13/16.33 (B) Fixing carbon fibre composite system sqm 60.00 60.00
14/16.33 (C) UV resistant coating sqm 60.00 60.00
15/16.37 Anti-carbonation-a protective coating sqm 169.95 169.95
16/16.29 Plastering with polymer modified mortar sqm 76.3 76.30
17/14.26 Providing water proofing compound sqm 0.00
18/16.17 Replacement of expansion Joint meter 0.00
19/14.22 New Streap Seal Expansion Joint meter 0.00
20/14.18(i) Corrugated copper plate in expansion joint meter 0.00
21/14.5 (B) Bituminous wearing coat Sqm 112.50 112.50
22/5.14 (ii) Mastic Wearing Coat-40mm Sqm 0.00
23/16.15 Labour for replacement of bearing each 0.00
24/16.16 Lifting of superstructure by jack each 0.00
25/13.14 New Elastomeric bearing ccm. 0.00
26/17.63 Greasing of Bearing each 0.00
27/14.9 Drainage spout each 0.00
28/Anna-01 Hanging Platform each 1 1.00
29/16.43 NDT with Ultrasonic Pulse Velocity Meter each 0.00

Executive Engineer, PWD


Nagaon NH Division, Nagaon
15

169.95 76.3 20%

50
10kg/nipple
40%
1%
30%

60
Statement No-9
Quantity Statement for Repair of Br.No. 353/1

Br.No. : 353/1
NH No. : NH-715 (Old NH-37)
Name of Br. location : Harmoti
Type of Superstructure : R.C.C Soild Slab
Span (exp. Jt. to exp. Jt) : 01 x 9 m
Overall width : 8.5m
Carriageway : 7.5m

Quantity

wing/
Item No. Item description Unit Existing
Super- Substrcu return/ Bearig Exp. Wearing Drainage
wearing others Total
structure tre screen Pedastal Joint Coat spout
coat
wall

1/16.1 Removal of existing cc wearing coat Sqm 0.00


2/16.2 Removal of asphaltic/mastic wearing coat Sqm 67.50 67.50
3/2.4(i).I.C Dismantling of RCC 0.00
4/16.24 Chipping & removal of deteriorated concrete Sqm --- 40.79 22.89 -- -- -- 63.68
5/16.4 Providing and inserting nipples each 22.00 12.00 34.00
6/16.5 A Cement grouting kg 730.00 730.00
7/16.7 Epoxy grouting kg 440.00 440.00
8/16.8 Epoxy mortar Sqm 40.79 22.89 3.00 66.68
9/16.26 (B) Primer coat on steel re-bars Sqm 2.04 0.76 0.15 2.95
10/16.28(B) Polymer base bonding Sqm 40.79 22.89 3.00 66.68
11/16.31 Micro concrete cum 2.00 -- 2.00
12/16.33 (A) Patching in concreate by epoxy putty sqm 87.30 87.30
13/16.33 (B) Fixing carbon fibre composite system sqm 87.30 87.30
14/16.33 (C) UV resistant coating sqm 87.30 87.30
15/16.37 Anti-carbonation-a protective coating sqm 101.97 101.97
16/16.29 Plastering with polymer modified mortar sqm 76.3 76.30
17/14.26 Providing water proofing compound sqm 0.00
18/16.17 Replacement of expansion Joint meter 0.00
19/14.22 New Streap Seal Expansion Joint meter 0.00
20/14.18(i) Corrugated copper plate in expansion joint meter 0.00
21/14.5 (B) Bituminous wearing coat Sqm 67.50 67.50
22/5.14 (ii) Mastic Wearing Coat-40mm Sqm 0.00
23/16.15 Labour for replacement of bearing each 0.00
24/16.16 Lifting of superstructure by jack each 0.00
25/13.14 New Elastomeric bearing ccm. 0.00
26/17.63 Greasing of Bearing each 0.00
27/14.9 Drainage spout each 0.00
28/Anna-01 Hanging Platform each 1 1.00
29/16.43 NDT with Ultrasonic Pulse Velocity Meter each 0.00

Executive Engineer, PWD


Nagaon NH Division, Nagaon
101.97 76.3 30%

50
10kg/nipple
40%
1%
30%

87.3
Statement No-8
Quantity Statement for Repair of Br.No. 352/2

Br.No. : 352/2
NH No. : NH-715 (Old NH-37)
Name of Br. location : Kuthari
Type of Superstructure : R.C.C Soild Slab
Span (exp. Jt. to exp. Jt) : 02 x 7.3 m
Overall width : 8.5m
Carriageway : 7.5m

Quantity

wing/
Item No. Item description Unit Existing
Super- Substrcu return/ Bearig Exp. Wearing Drainage
wearing others Total
structure tre screen Pedastal Joint Coat spout
coat
wall

1/16.1 Removal of existing cc wearing coat Sqm 0.00


2/16.2 Removal of asphaltic/mastic wearing coat Sqm 109.50 109.50
3/2.4(i).I.C Dismantling of RCC 0.00
4/16.24 Chipping & removal of deteriorated concrete Sqm --- 49.63 46.17 -- -- -- 95.80
5/16.4 Providing and inserting nipples each 25.00 23.00 48.00
6/16.5 A Cement grouting kg 730.00 730.00
7/16.7 Epoxy grouting kg 250.00 250.00
8/16.8 Epoxy mortar Sqm 49.63 46.17 3.68 4.00 103.47
9/16.26 (B) Primer coat on steel re-bars Sqm 1.65 1.54 0.12 0.20 3.52
10/16.28(B) Polymer base bonding Sqm 49.63 46.17 3.68 4.00 103.47
11/16.31 Micro concrete cum -- -- 0.00
12/16.33 (A) Patching in concreate by epoxy putty sqm 141.62 141.62
13/16.33 (B) Fixing carbon fibre composite system sqm 141.62 141.62
14/16.33 (C) UV resistant coating sqm 141.62 141.62
15/16.37 Anti-carbonation-a protective coating sqm 165.42 165.42
16/16.29 Plastering with polymer modified mortar sqm 202.9 202.90
17/14.26 Providing water proofing compound sqm 0.00
18/16.17 Replacement of expansion Joint meter 0.00
19/14.22 New Streap Seal Expansion Joint meter 0.00
20/14.18(i) Corrugated copper plate in expansion joint meter 0.00
21/14.5 (B) Bituminous wearing coat Sqm 109.50 109.50
22/5.14 (ii) Mastic Wearing Coat-40mm Sqm 0.00
23/16.15 Labour for replacement of bearing each 0.00
24/16.16 Lifting of superstructure by jack each 0.00
25/13.14 New Elastomeric bearing ccm. 0.00
26/17.63 Greasing of Bearing each 0.00
27/14.9 Drainage spout each 0.00
28/Anna-01 Hanging Platform each 0.00
29/16.43 NDT with Ultrasonic Pulse Velocity Meter each 0.00

Executive Engineer, PWD


Nagaon NH Division, Nagaon
165.418 153.9 40%

50
10kg/nipple
40%
1%
30%

141.62
Statement No-7
Quantity Statement for Repair of Br.No. 352/1

Br.No. : 352/1
NH No. : NH-715 (Old NH-37)
Name of Br. location : Kuthari
Type of Superstructure : R.C.C Soild Slab
Span (exp. Jt. to exp. Jt) : 02 x 7.3 m
Overall width : 8.5m
Carriageway : 7.5m

Quantity

wing/
Item No. Item description Unit Existing
Super- Substrcu return/ Bearig Exp. Wearing Drainage
wearing others Total
structure tre screen Pedastal Joint Coat spout
coat
wall

1/16.1 Removal of existing cc wearing coat Sqm 0.00


2/16.2 Removal of asphaltic/mastic wearing coat Sqm 109.50 109.50
3/2.4(i).I.C Dismantling of RCC 0.00
4/16.24 Chipping & removal of deteriorated concrete Sqm --- 66.17 61.56 12.25 -- -- -- 139.98
5/16.4 Providing and inserting nipples each 34.00 31.00 6.00 71.00
6/16.5 A Cement grouting kg 730.00 730.00
7/16.7 Epoxy grouting kg 510.00 510.00
8/16.8 Epoxy mortar Sqm 66.17 61.56 4.90 2.50 135.13
9/16.26 (B) Primer coat on steel re-bars Sqm 1.65 1.54 0.12 0.13 3.44
10/16.28(B) Polymer base bonding Sqm 66.17 61.56 4.90 2.50 135.13
11/16.31 Micro concrete cum -- -- 0.00
12/16.33 (A) Patching in concreate by epoxy putty sqm 141.62 141.62
13/16.33 (B) Fixing carbon fibre composite system sqm 141.62 141.62
14/16.33 (C) UV resistant coating sqm 141.62 141.62
15/16.37 Anti-carbonation-a protective coating sqm 165.42 165.42
16/16.29 Plastering with polymer modified mortar sqm 202.9 202.90
17/14.26 Providing water proofing compound sqm 0.00
18/16.17 Replacement of expansion Joint meter 0.00
19/14.22 New Streap Seal Expansion Joint meter 0.00
20/14.18(i) Corrugated copper plate in expansion joint meter 0.00
21/14.5 (B) Bituminous wearing coat Sqm 109.50 109.50
22/5.14 (ii) Mastic Wearing Coat-40mm Sqm 0.00
23/16.15 Labour for replacement of bearing each 0.00
24/16.16 Lifting of superstructure by jack each 0.00
25/13.14 New Elastomeric bearing ccm. 0.00
26/17.63 Greasing of Bearing each 0.00
27/14.9 Drainage spout each 0.00
28/Anna-01 Hanging Platform each 1 1.00
29/16.43 NDT with Ultrasonic Pulse Velocity Meter each 0.00

Executive Engineer, PWD


Nagaon NH Division, Nagaon
165.418 153.9 40%

50
10kg/nipple
40%
1%
30%

141.62
Statement No-2
Quantity Statement for Repair of Br.No. 328/1

Br.No. : 328/1
NH No. : NH-715 (Old NH-37)
Name of Br. location : Bordolong
Type of Superstructure : Soild Slab
Span (exp. Jt. to exp. Jt) : 01 x 9.5 m
Overall width : 8.5m
Carriageway : 7.5m

Quantity

wing/
Item No. Item description Unit Existing
Super- Substrcu return/ Bearig Exp. Wearing Drainage
wearing others Total
structure tre screen Pedastal Joint Coat spout
coat
wall

1/16.1 Removal of existing cc wearing coat Sqm 0.00


2/16.2 Removal of asphaltic/mastic wearing coat Sqm 71.25 71.25
3/2.4(i).I.C Dismantling of RCC 0.00
4/16.24 Chipping & removal of deteriorated concrete Sqm --- 53.82 30.52 --- -- -- -- 84.34
5/16.4 Providing and inserting nipples each 27.00 16.00 43.00
6/16.5 A Cement grouting kg 475.00 475.00
7/16.7 Epoxy grouting kg 540.00 540.00
8/16.8 Epoxy mortar Sqm 43.05 30.52 1.50 75.07
9/16.26 (B) Primer coat on steel re-bars Sqm 1.08 0.76 0.08 1.91
10/16.28(B) Polymer base bonding Sqm 43.05 30.52 1.50 75.07
11/16.31 Micro concrete cum -- -- 0.00
12/16.33 (A) Patching in concreate by epoxy putty sqm 92.15 92.15
13/16.33 (B) Fixing carbon fibre composite system sqm 92.15 92.15
14/16.33 (C) UV resistant coating sqm 92.15 92.15
15/16.37 Anti-carbonation-a protective coating sqm 107.64 107.64
16/16.29 Plastering with polymer modified mortar sqm 76.3 76.30
17/14.26 Providing water proofing compound sqm 0.00
18/16.17 Replacement of expansion Joint meter 0.00
19/14.22 New Streap Seal Expansion Joint meter 0.00
20/14.18(i) Corrugated copper plate in expansion joint meter 0.00
21/14.5 (B) Bituminous wearing coat Sqm 71.25 71.25
22/5.14 (ii) Mastic Wearing Coat-40mm Sqm 0.00
23/16.15 Labour for replacement of bearing each 0.00
24/16.16 Lifting of superstructure by jack each 0.00
25/13.14 New Elastomeric bearing ccm. 0.00
26/17.63 Greasing of Bearing each 0.00
27/14.9 Drainage spout each 0.00
28/Anna-01 Hanging Platform each 1 1.00
29/16.43 NDT with Ultrasonic Pulse Velocity Meter each 0.00

Executive Engineer, PWD


Nagaon NH Division, Nagaon
107.635 76.3 40%

50 74575
10kg/nipple 815940
30% 5.75 890515
1%
30%

92.15
Statement No-3
Quantity Statement for Repair of Br.No. 335/1

Br.No. : 335/1
NH No. : NH-715 (Old NH-37)
Name of Br. location : Gurakhati
Type of Superstructure : Soild Slab
Span (exp. Jt. to exp. Jt) : 02 x 8.875 m
Overall width : 8.5m
Carriageway : 7.5m

Quantity

wing/
Item No. Item description Unit Existing
Super- Substrcu return/ Bearig Exp. Wearing Drainage
wearing others Total
structure tre screen Pedastal Joint Coat spout
coat
wall

1/16.1 Removal of existing cc wearing coat Sqm 0.00


2/16.2 Removal of asphaltic/mastic wearing coat Sqm 133.13 133.13
3/2.4(i).I.C Dismantling of RCC 0.00
4/16.24 Chipping & removal of deteriorated concrete Sqm --- 60.33 43.26 --- -- -- -- 103.59
5/16.4 Providing and inserting nipples each 31.00 22.00 53.00
6/16.5 A Cement grouting kg 887.50 887.50
7/16.7 Epoxy grouting kg 465.00 465.00
8/16.8 Epoxy mortar Sqm 60.33 43.26 5.00 108.59
9/16.26 (B) Primer coat on steel re-bars Sqm 2.01 1.44 0.25 3.70
10/16.28(B) Polymer base bonding Sqm 60.33 28.84 5.00 94.17
11/16.31 Micro concrete cum -- -- 0.00
12/16.33 (A) Patching in concreate by epoxy putty sqm 172.18 172.18
13/16.33 (B) Fixing carbon fibre composite system sqm 172.18 172.18
14/16.33 (C) UV resistant coating sqm 172.18 172.18
15/16.37 Anti-carbonation-a protective coating sqm 201.11 201.11
16/16.29 Plastering with polymer modified mortar sqm 144.2 144.20
17/14.26 Providing water proofing compound sqm 0.00
18/16.17 Replacement of expansion Joint meter 0.00
19/14.22 New Streap Seal Expansion Joint meter 0.00
20/14.18(i) Corrugated copper plate in expansion joint meter 0.00
21/14.5 (B) Bituminous wearing coat Sqm 133.13 133.13
22/5.14 (ii) Mastic Wearing Coat-40mm Sqm 0.00
23/16.15 Labour for replacement of bearing each 0.00
24/16.16 Lifting of superstructure by jack each 0.00
25/13.14 New Elastomeric bearing ccm. 0.00
26/17.63 Greasing of Bearing each 0.00
27/14.9 Drainage spout each 0.00
28/Anna-01 Hanging Platform each 0.00
29/16.43 NDT with Ultrasonic Pulse Velocity Meter each 0.00

Executive Engineer, PWD


Nagaon NH Division, Nagaon
slab abut
201.1075 144.2 30%

50
10kg/nipple
30%
1%
30%

172.175
Statement No-5
Quantity Statement for Repair of Br.No. 339/1

Br.No. : 339/1
NH No. : NH-715 (Old NH-37)
Name of Br. location : Deosur
Type of Superstructure : RCC Box Girder
Span (exp. Jt. to exp. Jt) : 02 x49.5
Overall width : 8.5m
Carriageway : 7.5m

Quantity
wing/
Item No. Item description Unit Existing
Super- Substrcu return/ Bearig Exp. Wearing Drainage
wearing others Total
structure tre screen Pedastal Joint Coat spout
coat
wall

1/16.1 Removal of existing cc wearing coat Sqm 75 75.00


2/16.2 Removal of asphaltic/mastic wearing coat Sqm 742.50 742.50
3/2.4(i).I.C Dismantling of RCC 2.03 2.03
4/16.24 Chipping & removal of deteriorated concrete Sqm --- --- -- -- -- 0.00
5/16.4 Providing and inserting nipples each 0.00
6/16.5 A Cement grouting kg 0.00
7/16.7 Epoxy grouting kg 0.00
8/16.8 Epoxy mortar Sqm 22.50 8.00 30.50
9/16.26 (B) Primer coat on steel re-bars Sqm 0.40 0.40
10/16.28(B) Polymer base bonding Sqm 6.75 8.00 14.75
11/16.31 Micro concrete cum -- -- 3.46 3.46
12/16.33 (A) Patching in concreate by epoxy putty sqm 0.00
13/16.33 (B) Fixing carbon fibre composite system sqm 0.00
14/16.33 (C) UV resistant coating sqm 0.00
15/16.37 Anti-carbonation protective coating sqm 1700.40 1700.40
16/16.29 Plastering with polymer modified mortar sqm 0.00
17/14.26 Providing water proofing compound sqm 0.00
18/16.17 Replacement of expansion Joint meter 45.00 45.00
19/14.22 New Streap Seal Expansion Joint meter 45.00 45.00
20/14.18(i) Corrugated copper plate in expansion joint meter 22.50 22.50
21/14.5 (B) Bituminous wearing coat Sqm 0.00
22/5.14 (ii) Mastic Wearing Coat-40mm Sqm 825.00 825.00
23/16.15 Labour for replacement of bearing each 0.00
24/16.16 Lifting of superstructure by jack each 0.00
25/13.14 New Elastomeric bearing ccm. 0.00
26/17.63 Greasing of Bearing each 8.00 8 16.00
27/14.9 Drainage spout each 32.00 32 64.00
28/Anna-01 Hanging Platform each 1 1.00
29/16.43 NDT with Ultrasonic Pulse Velocity Meter each 0.00

Executive Engineer, PWD


Nagaon NH Division, Nagaon
slab abut
1700.4 170

50
Statement No-4
Quantity Statement for Repair of Br.No. 336/1

Br.No. : 336/1
NH No. : NH-715 (Old NH-37)
Name of Br. location : Fullaguri Sang
Type of Superstructure : Soild Slab
Span (exp. Jt. to exp. Jt) : 01 x15
Overall width : 8.5m
Carriageway : 7.5m

Quantity

wing/
Item No. Item description Unit Existing
Super- Substrcu return/ Bearig Exp. Wearing Drainage
wearing others Total
structure tre screen Pedastal Joint Coat spout
coat
wall

1/16.1 Removal of existing cc wearing coat Sqm 0.00


2/16.2 Removal of asphaltic/mastic wearing coat Sqm 112.50 112.50
3/2.4(i).I.C Dismantling of RCC 0.00
4/16.24 Chipping & removal of deteriorated concrete Sqm --- 69.65 22.89 --- -- -- -- 92.54
5/16.4 Providing and inserting nipples each 35.00 12.00 47.00
6/16.5 A Cement grouting kg 750.00 750.00
7/16.7 Epoxy grouting kg 525.00 525.00
8/16.8 Epoxy mortar Sqm 69.65 22.89 5.00 97.54
9/16.26 (B) Primer coat on steel re-bars Sqm 2.32 0.76 0.25 3.33
10/16.28(B) Polymer base bonding Sqm 69.65 22.89 5.00 97.54
11/16.31 Micro concrete cum 4.00 -- 4.00
12/16.33 (A) Patching in concreate by epoxy putty sqm 145.50 145.50
13/16.33 (B) Fixing carbon fibre composite system sqm 145.50 145.50
14/16.33 (C) UV resistant coating sqm 145.50 145.50
15/16.37 Anti-carbonation-a protective coating sqm 232.17 232.17
16/16.29 Plastering with polymer modified mortar sqm 76.3 76.30
17/14.26 Providing water proofing compound sqm 0.00
18/16.17 Replacement of expansion Joint meter 0.00
19/14.22 New Streap Seal Expansion Joint meter 0.00
20/14.18(i) Corrugated copper plate in expansion joint meter 0.00
21/14.5 (B) Bituminous wearing coat Sqm 112.50 112.50
22/5.14 (ii) Mastic Wearing Coat-40mm Sqm 0.00
23/16.15 Labour for replacement of bearing each 1 1.00
24/16.16 Lifting of superstructure by jack each 1 1.00
25/13.14 New Elastomeric bearing ccm. 56320 56320.00
26/17.63 Greasing of Bearing each 0.00
27/14.9 Drainage spout each 0.00
28/Anna-01 Hanging Platform each 1 1.00
29/16.43 NDT with Ultrasonic Pulse Velocity Meter each 0.00

Executive Engineer, PWD


Nagaon NH Division, Nagaon
slab abut
232.17 76.3 30%

50

8.5

145.5
Statement No-6
Quantity Statement for Repair of Br.No. 348/1

Br.No. : 348/1
NH No. : NH-715 (Old NH-37)
Name of Br. location : Deopani
Type of Superstructure : RCC T-beam Girder Slab
Span (exp. Jt. to exp. Jt) : 01 X 45.1
Overall width : 8.5m
Carriageway : 7.5m

Quantity

wing/
Item No. Item description Unit Existing
Super- Substrcu return/ Bearig Exp. Wearing Drainage
wearing others Total
structure tre screen Pedastal Joint Coat spout
coat
wall

1/16.1 Removal of existing cc wearing coat Sqm 0.00


2/16.2 Removal of asphaltic/mastic wearing coat Sqm 338.25 338.25
3/2.4(i).I.C Dismantling of RCC 1.35 1.35
4/16.24 Chipping & removal of deteriorated concrete Sqm --- --- -- -- -- 0.00
5/16.4 Providing and inserting nipples each 0.00
6/16.5 A Cement grouting kg 0.00
7/16.7 Epoxy grouting kg 0.00
8/16.8 Epoxy mortar Sqm 15.00 11.50 26.50
9/16.26 (B) Primer coat on steel re-bars Sqm 0.58 0.58
10/16.28(B) Polymer base bonding Sqm 4.50 11.50 16.00
11/16.31 Micro concrete cum -- -- 0.00
12/16.33 (A) Patching in concreate by epoxy putty sqm 0.00
13/16.33 (B) Fixing carbon fibre composite system sqm 0.00
14/16.33 (C) UV resistant coating sqm 0.00
15/16.37 Anti-carbonation protective coating sqm 1855.65 1855.65
16/16.29 Plastering with polymer modified mortar sqm 0.00
17/14.26 Providing water proofing compound sqm 0.00
18/16.17 Replacement of expansion Joint meter 30.00 30.00
19/14.22 New Streap Seal Expansion Joint meter 30.00 30.00
20/14.18(i) Corrugated copper plate in expansion joint meter 15.00 15.00
21/14.5 (B) Bituminous wearing coat Sqm 338.25 338.25
22/5.14 (ii) Mastic Wearing Coat-40mm Sqm 75.00 75.00
23/16.15 Labour for replacement of bearing each 0.00
24/16.16 Lifting of superstructure by jack each 0.00
25/13.14 New Elastomeric bearing ccm. 0.00
26/17.63 Greasing of Bearing each 6 6.00
27/14.9 Drainage spout each 0.00
28/Anna-01 Hanging Platform each 1 1.00
29/16.43 NDT with Ultrasonic Pulse Velocity Meter each 0.00

Executive Engineer, PWD


Nagaon NH Division, Nagaon
slab abut
1855.655

50

22.55
STATEMENT-L
RETAINING WALL AT CH.337/200 AT L/S OF NH-715

CC Masonary in C.M 1:3


0.75 m
x
0.6 m
Shoulder
1.0 m x
Granular Back fill 1.0 m

1.5 m x 1.0 m

Weep Hole

2.0 m x 1.0 m

2.5 m x 1.5 m

1.5 m 1.0 m
N.G.L

TYPICAL CROSS-SECTION OF BOULDER RETAINING WALL IN WIRE CRATES

Quantity Statement

Qty.
Sl. No. Items Unit L (m) B (m) H (m) (cu.m)
1) PCC 1:3:6 in foundation cu.m 12.00 3.00 0.10 3.60
2) Boulder Apron in Wire Crates cu.m
1st. Layer cu.m 12.00 2.50 1.25 37.50
2nd. Layer cu.m 12.00 2.50 1.50 45.00
3rd. Layer cu.m 12.00 2.00 1.00 24.00
4th. Layer cu.m 12.00 1.50 1.00 18.00
5th. Layer cu.m 12.00 1.00 1.00 12.00
Total= cu.m 136.50
3) PCC Grade M15 in head wall cu.m 12.00 0.60 0.75 5.40
4) Plaster in head wall sq.m 12.00 2.1 25.2
5) Painting in head wall sq.m 12.00 2.1 25.2
6) Weep Hole each 20

Executive Engineer, PWD


Nagaon NH Division, Nagaon
ESTIMATE BOULDER RETAINING WALL

Rate
Item No. Item description Unit Qty. Amount (Rs.)
(Rs.)
1/12.1/304
Excavation for Structures (Earth work in
excavation of foundation of structures as
per drawing and technical specification,
including setting out, construction of
shoring and bracing, removal of stumps
and other deleterious matter, dressing of
sides and bottom and backfilling with
approved material.

A. Manual Means
(I) Without dewatering
(i) upto 3 m depth cum 48.6 65.00 3,159.00
2/12.4/2100 PCC 1:3:6 in Foundation (Plain cement
concrete 1:3:6 nominal mix in foundation
with crushed stone aggregate 40 mm
nominal size mechanically mixed, placed cum 3.60 4964.00 17,870.40
in foundation and compacted by vibration
including curing for 14 days.)

3/15.2/2503 Boulder apron laid in wire crates (Providing


and laying of boulder apron laid in wire
crates made with 4mm dia GI wire
conforming to IS: 280 & IS:4826 in 100mm
x 100mm mesh (weaved diagonally) cum 136.50 2916.00 398,034.00
including 10% extra for laps and joints laid
with stone boulders weighting not less
than 40Kg each.)

4/13.5 Plain/Reinforced cement concrete, in sub


(N)/1500,17 structure complete as per drawing and
00, 2200 technical specification and steel shuttering
formwork

(N) Without plasticiser


A PCC Grade M15 Height upto 5m cum 5.40 6048.00 32,659.20
5/ 13.3/1300 Plastering with cement mortar (1:3 ) on
-2200 brick work in sub-structure as per sqm 25.2 126.00 3,175.20
Technical specifications
14.16 Painting on concrete surface (Providing
and applying 2 coats of water based
cement paint to unplastered concrete
surface after cleaning the surface of dirt,
dust, oil, grease, efflorescence and
applying paint @ of 1 litre for 2 Sq.m. )

(A) For Plain surface sqm 25.2 45.00 1,134.00


6/13.8 Providing weep holes in Brick
masonry/Plain/Reinforced concrete
abutment, wing wall/return wall with 100
mm dia AC pipe, extending through the full each 20 204.00 4,080.00
width of the structure with slope of 1V :20H
towards drawing foce. Complete as per
drawing and Technical specification.

Total Cost= 460,111.80

Executive Engineer, PWD


Nagaon NH Division, Nagaon
Executive Engineer, PWD
Nagaon NH Division, Nagaon
Sl No Item Unit PWD SOR Rate Current rate

16.1 Removal of existing cement concrete wearing Sqm 99 150


coat including its disposal complete as per
technical specification without causing any
detrimental effect to any part of the bridge
structure and removal of dismantled material
with all lifts and lead up to 1000(Thickness
75mm)

16.5 Sealing of cracks/porous concrete by


injection process through nipples/grouting
complete as per Technical specification
A.cement grout kg 123 123

16.7 Sealing crack /Porus concrete with epoxy kg 1084 1800


grout by injecton through nipple complete as
per clause 2803.1
16.8 Applying epoxy mortar over leched, Sqm 734 1500
honeycombed and spalled concrete surface
and exposed steel reinforcement complete as
per Technical specification

16.26 (B) Supplying and applying two coats of Nitozinc Sqm 183 220
Primer a two component epoxy zinc rich
primer on the properly cleaned and prepared
steel bars after the required chipping and
cleaning of the concrete surface as per the
manufactures specification as directed and
specified by the department complete

16.28(B) B. Proving and applying coating of the Sqm 292 350


cleaned patches with two part of polymer
base bonding agent nitobond SBR or fosroc
or equivalent @0.2 lit per sqm prior to
application of polymer modified mortar with
brush after totally saturating the cleaned
concreate surface with clean water for
proper bonding of old and new concreate
including formwork as specified and directed
by the departmental complete

16.31 Concreting of the structure with free flow cum 104861 104861
nonshrink cementitious micro concrete with
renderoc RG of fosroc or equivalent after
proper mixing with clean water including
formwork followed by proper curing for 28
days as per manufacture's specification
complete and as directed by the Department
16.33 A. Patching in depression of concreate surface sqm 1751 1751
wherever necessary by laying epoxy putty ,
nitocote VF of fosroc Chemicals or
equivalent@1 lit per sqm after proper surface
preparation and proper scraping of concreate
protrusion as specified and directed by the
department complete including formwork

B. Applying Nitobond 410 saturant Fosroc sqm 4892 4892


Chemicals or equivalent with wet film
thickness @250 microns (0.27 lit per sqm )
over a coat of saturant epoxy primer
Nitowrap 30 of fosroc Chemicals or
equivalent @0.11 lit per sqm with brush
followed by fixing carbon fibre composite
system Nitowarp EP(CF) of fosroc chemicals
or equivalent by pressing on the saturant and
impregnate the same by applying a final coat
of Nitowarp 410 saturant Fosroc chemicals or
equivalent as specified and directed by the
department complete including formwork.

C. Applying two coats of UV resistant coating sqm 422 422


Nitocote UR 512(FOSROC)Chemicals or
equivalent over fibre system having wet film
thickness of 100 micron@0.11 lit per sqm as
specified and directed by the department
complete including formwork

16.37 Applying 2-coats of anti-carbonation-a sqm 260 395


protective coating deckguard or equivalent
@0.275 Lit per sqm with brush over exposed
protection of the concrete structure of the
bridge& other structure work etc. complete
as desired to protect the reinforced concrete
by preventing the process of carbonation and
directed by the department including
formwork.
30% of the surface
area of bridge

1000 kg
cement/20m span
Aprox 0.5kg/ Sqm of
the Bridge area

20 % of the bridge
surface area

0.5 % of the bridge


area

20 % of the bridge
surface area

Depend upon the


bridge situation
As per actual
mesurement

As per actual Applying Nitowrap 410 saturant Fosroc Chemicals or equivalent


mesurement with wet film thickness @ 250 microns (0.27Lit per sqm) over a
coat of saturant epoxy primer Nitowrap 30 of Fosroc Chemicals
or equivalent @ 0.11Lit per sqm with brush followed by fixing
carbon fibre composite system Nitowrap EP (CF) of Fosroc
Chemicals or equivalent by pressing on the saturant and
impregnate the same by applying a final coat of Nitowrap 410
saturant Fosroc Chemicals or equivalent as specified and
directed by the department complete including formwork.

As per actual
mesurement

Total surface area of


bridges