Rev : 0.0
FIRE FIGHTING – FIRE PUMPS
Date : NOV-14
Pages : 1 of 7
PROJECT
EMPLOYER
ARCHITECT
PMC
CONTRACTOR
AMMENDMENT RECORD
Recommended
Rev Date Description Prepared By: Reviewed By Approved By:
By
CONTENTS
PROJECT:
Doc Ref : FF MS-01
Rev : 0.0
FIRE FIGHTING – FIRE PUMPS
Date : NOV-14
Pages : 2 of 7
01 Objective 3
02 Scope 3
03 Material 3
04 Reference 3
05 Responsibilities 3
07 Procedure 6
08 Records 7
1.0 Objective
The objective of this method statement is to define the procedure step by step to implement
the correct practices for installation of Fire Pumps & pump valve package.
PROJECT:
Doc Ref : FF MS-01
Rev : 0.0
FIRE FIGHTING – FIRE PUMPS
Date : NOV-14
Pages : 3 of 7
2.0 Scope
This method statement refers to various work procedures contained within Design / Drawing /
Contractual specifications / Customer Quality Requirements which explains and covers the
installation of Fire Pumps & pump valve package.
3.0 Material
1. Electrical Driven Main Pump
3. Jockey Pump
4. Booster Pump
5. Valve Packages
4.0 Reference
4.1 Contract Technical Specifications
4.2 Approved Technical Data Sheets
4.3 Design Intent Drawings & Approved Shop Drawings
4.4 Manufacturers Catalogues & Recommendations
5.0 Responsibilities
5.1 Project Manager:
a) Ensure all required submittals area made and required plant/ tools/ material and manpower
is available in timely manner.
b) Ensure all execution of works area carried out according to approvals, contract specifications,
and approved shop drawings, MS, ITP, ICL and CCL.
c) Ensure necessary coordination with all involved for timely completion of job.
PROJECT:
Doc Ref : FF MS-01
Rev : 0.0
FIRE FIGHTING – FIRE PUMPS
Date : NOV-14
Pages : 4 of 7
a) Identified Site Quality Engineer is responsible for preparation of project specific quality
documents in consultation and support from regional quality representative.
b) Regional quality representative will assist site quality responsible engineer in effective
implementation of approved quality plans and quality control procedures.
c) Responsible for communicating with all site staff about Quality requirements and
responsible for reviewing all related subjects.
d) Regional Quality Representative will be responsible for organizing Quality Audits with
coordination with site and project management.
e) Responsible for all corrective actions in consultation with project management and close
the non-conformity identified during quality audits.
PROJECT:
Doc Ref : FF MS-01
Rev : 0.0
FIRE FIGHTING – FIRE PUMPS
Date : NOV-14
Pages : 5 of 7
b) To ensure that all project personnel / site execution team is fully aware of their
responsibilities and have full understanding of related safety rules, procedures.
c) To advise the involved personnel about the risks involved and necessary HSE precautions /
measures to prevent it.
d) To maintain a continuous inspection / surveillance of site activities, implementation of HSE
policies, advise, train site personnel including workmen regarding safety at works.
7.0 Procedure
7.1 Method of Pump Storage
PROJECT:
Doc Ref : FF MS-01
Rev : 0.0
FIRE FIGHTING – FIRE PUMPS
Date : NOV-14
Pages : 6 of 7
7.1.1 On arrival at site, receiving and unloading of pumps shall be done as per manufacturer’s
recommendation. Manufacturer’s hoisting provisions like lifting legs etc. shall be used for
hoisting and unloading. Unloading equipment like cranes, fork lift, and trolleys shall be
used if required.
7.1.2 Ensure that before pump storage should be calculate tonnage of capacity.
7.1.3 Visual inspections shall be carried out on arrival of pump with transporter; supplier and
any physical damages shall be reported immediately to manufacturer.
7.1.4 Check the pump for receipt of accessories like vibration pads / isolators, mating
couplings / flanges, etc.
7.1.5 Pumps will be segregated Model/size wise and stored accordingly for easy retrieval
7.1.6 Pumps shall be stored on a flat surface in well ventilated and covered storage area.
7.1.7 Inlet and outlet flange blanks shall not be removed until ready for connection to pipe work.
PROJECT:
Doc Ref : FF MS-01
Rev : 0.0
FIRE FIGHTING – FIRE PUMPS
Date : NOV-14
Pages : 7 of 7
7.3.2 Water level the pump assembly by placing the shim plates below the base frame as
required. Check the alignment of the coupling between motor and pumps with thread or
dial gauge.
7.3.3 Alignment of coupling arrangement between motor and pumps, after pump installation
shall be rechecked by the pump supplier before testing.
7.3.4 Ensure proper coupling guards are provided.
7.3.5 Complete the piping and valve package installation as per approved drawings. Following
care should be taken while carrying out the valve package.
1. Install the flexible connectors in the horizontal section of the piping. If installed in
the vertical line, use spring support for the dropping elbows at the suction.
2. Use eccentric reducers at pump suction to prevent air pocket in the suction and
concentric reducers at the discharge of the pump.
3. Do not install horizontal elbow at the pump inlet.
4. Ensure sufficient straight length of pipe is available at upstream and downstream
of balancing valves (DRV) as per manufacturer’s recommendations.
7.3.6 Install the electrical power connections as per approved drawings.
7.3.7 Provide grounding wiring as per approved drawings/manufacturers instruction.
7.3.8 After completion of the installation and complete filling of the water system, deflections
and spring tension in the rubber bellow to be adjusted as per manufacturer’s
recommendations.
7.3.9 Finally levelled the pumps and grouting to be done.
8.0 Records
8.1 Signed off Material Inspection Report.
8.2 Signed off with installation Check list
8.3 Attached manufacturer Test Report.
************************
PROJECT: