I PEKERJAAN ELEKTRIKAL
I.I PEKERJAAN POWER HOUSE
a Pengadaan Transformer 100 kVA/20 kV/50 Hz/380 P 1.00 unit
b Pengadaan dan Pemasangan Pole Travo 2.00 unit
c Pekerjaan Listrik Cadangan / Emergency
1 Pengadaan dan pemasangan Genset 100 kVA type silent 1.00 unit
2 Panel Genset 1.00 unit
3 ATS / AMF 1.00 unit
4 Grounding Genset 1.00 unit
5 Dudukan Mesin, peredam getaran, muffler extension 1.00 unit
6 Tanki BBM kap. 1000 liter termasuk instalasi 1.00 unit
JUMLAH PEKERJAAN POWE
I.2 PEKERJAAN PANEL
a Panel LV-MDP
1 Box panel 1.00 unit
2 Pilot Lamp + Fuse 6.00 unit
3 Voltmeter 0 - 500V 6.00 unit
4 Amperemeter 0 - 200A 2.00 unit
5 Selector Voltage 2.00 unit
6 MCCB 3P 200 A 18KA 1.00 unit
7 MCB 3P 25 A 10KA ( Pen LP B ) 1.00 unit
8 MCCB 3P 30 A 10KA ( Pen LP 1 ) 1.00 unit
9 MCCB 3P 40 A 10KA ( Pen LP 2 + LP 3) 1.00 unit
10 MCCB 3P 20 A 10KA ( PAC - B) 1.00 unit
11 MCCB 3P 40 A 10KA ( PAC -1, 2, 3) 1.00 unit
12 MCB 3P 25 A 10KA ( Pompa Air Bersih ) 1.00 unit
13 MCB 3P 25 A 10KA ( Spare ) 1.00 unit
14 Aresster Protection 3p 65 KA 1.00 unit
15 Grounding 1.00 unit
16 Wiring dan Accessories 1.00 unit
b Panel Penerangan Lantai 1 ( LP-1), terdiri dari:
1 Box panel 1.00 unit
2 Pilot Lamp + Fuse 3.00 unit
3 Ampere meter 1.00 unit
4 Voltmeter 0 - 500 1.00 unit
5 Selector Voltage 1.00 unit
6 CT 40 A/5A 1.00 unit
7 MCCB 3P 30A 10KA 1.00 unit
No. URAIAN PEKERJAAN VOLUME SAT
122,500,000.00 122,500,000.00
8,250,000.00 16,500,000.00
613,792,400.00 613,792,400.00
36,000,000.00 36,000,000.00
42,000,000.00 42,000,000.00
26,000,000.00 26,000,000.00
18,250,000.00 18,250,000.00
4,200,000.00 4,200,000.00
JUMLAH PEKERJAAN POWER HOUSE 879,242,400.00
1,600,000.00 1,600,000.00
43,500.00 261,000.00
290,000.00 1,740,000.00
550,000.00 1,100,000.00
249,500.00 499,000.00
615,000.00 615,000.00
594,000.00 594,000.00
594,000.00 594,000.00
594,000.00 594,000.00
594,000.00 594,000.00
594,000.00 594,000.00
594,000.00 594,000.00
594,000.00 594,000.00
5,124,350.00 5,124,350.00
1,500,000.00 1,500,000.00
1,500,000.00 1,500,000.00
1,600,000.00 1,600,000.00
43,500.00 130,500.00
290,000.00 290,000.00
550,000.00 550,000.00
249,500.00 249,500.00
249,500.00 249,500.00
594,000.00 594,000.00
HARGA SATUAN JUMLAH HARGA
( Rp. ) ( Rp. )
297,000.00 297,000.00
750,000.00 750,000.00
1,500,000.00 1,500,000.00
1,600,000.00 1,600,000.00
43,500.00 130,500.00
290,000.00 290,000.00
550,000.00 550,000.00
249,500.00 249,500.00
249,500.00 249,500.00
594,000.00 594,000.00
297,000.00 297,000.00
750,000.00 750,000.00
1,500,000.00 1,500,000.00
1,600,000.00 1,600,000.00
43,500.00 130,500.00
290,000.00 290,000.00
550,000.00 550,000.00
249,500.00 249,500.00
249,500.00 249,500.00
594,000.00 594,000.00
297,000.00 297,000.00
750,000.00 750,000.00
1,500,000.00 1,500,000.00
1,600,000.00 1,600,000.00
43,500.00 130,500.00
290,000.00 290,000.00
550,000.00 550,000.00
249,500.00 249,500.00
249,500.00 249,500.00
594,000.00 594,000.00
297,000.00 297,000.00
750,000.00 750,000.00
1,500,000.00 1,500,000.00
JUMLAH PEKERJAAN PANEL 42,939,350.00
290,520.00 39,220,200.00
290,520.00 9,877,680.00
76,500.00 1,147,500.00
51,360.00 3,081,600.00
51,360.00 1,284,000.00
51,360.00 1,438,080.00
51,360.00 1,232,640.00
HARGA SATUAN JUMLAH HARGA
( Rp. ) ( Rp. )
51,360.00 1,232,640.00
JUMLAH PEKERJAAN PENGKABELAN 58,514,340.00
268,000.00 34,840,000.00
268,000.00 12,864,000.00
JUMLAH PEKERJAAN KABEL TRAY 47,704,000.00
260,000.00 69,680,000.00
780,000.00 14,040,000.00
260,000.00 18,200,000.00
30,900.00 2,163,000.00
30,900.00 1,792,200.00
30,900.00 1,050,600.00
49,000.00 4,410,000.00
450,000.00 6,750,000.00
350,000.00 4,200,000.00
1,400,000.00 5,600,000.00
880,000.00 72,160,000.00
660,000.00 13,200,000.00
665,000.00 26,600,000.00
330,000.00 4,620,000.00
262,000.00 6,288,000.00
5,800,000.00 278,400,000.00
10,500,000.00 105,000,000.00
13,900,000.00 250,200,000.00
2,300,000.00 18,400,000.00
1,500,000.00 6,000,000.00
19,200,000.00 76,800,000.00
LASI ELEKTRIKAL, PENERANGAN, ARMATUR & FIGTURE 985,553,800.00
23,741,025.00 23,741,025.00
62,600.00 5,759,200.00
600,000.00 600,000.00
670,000.00 670,000.00
1,750,000.00 3,500,000.00
3,750,000.00 3,750,000.00
1,750,000.00 1,750,000.00
4,200,000.00 4,200,000.00
320,000.00 960,000.00
86,557.50 865,575.00
2,000,000.00 2,000,000.00
2,600,000.00 2,600,000.00
JUMLAH PEKERJAAN PENYALUR PETIR & PENTANAHAN 50,395,800.00
HARGA SATUAN JUMLAH HARGA
( Rp. ) ( Rp. )
968,000.00 7,744,000.00
666,000.00 5,328,000.00
260,000.00 260,000.00
5,650,000.00 5,650,000.00
3,940,000.00 7,880,000.00
4,320,000.00 4,320,000.00
3,600,000.00 3,600,000.00
5,600,000.00 5,600,000.00
1,640,000.00 3,280,000.00
585,000.00 1,170,000.00
12,600,000.00 12,600,000.00
2,600,000.00 2,600,000.00
UMLAH PEKERJAAN SOUND SYSTEM PUBLIC ADDRESS 60,032,000.00
1,450,000.00 23,200,000.00
7,585,000.00 7,585,000.00
8,365,000.00 8,365,000.00
JUMLAH PEKERJAAN CCTV 39,150,000.00
225,000,000.00 450,000,000.00
6,250,000.00 12,500,000.00
36,600,000.00 36,600,000.00
UMLAH PEKERJAAN PAPAN SCORE ( SCORING BOARD ) 499,100,000.00
64,500,000.00 64,500,000.00
18,500,000.00 18,500,000.00
16,500,000.00 33,000,000.00
32,500,000.00 65,000,000.00
3,500,000.00 7,000,000.00
4,357,500.00 26,145,000.00
153,300.00 12,264,000.00
140,000.00 560,000.00
187,000.00 748,000.00
137,000.00 1,096,000.00
1,350,000.00 2,700,000.00
239,600.00 7,188,000.00
153,300.00 6,760,530.00
103,000.00 9,599,600.00
70,100.00 5,148,845.00
HARGA SATUAN JUMLAH HARGA
( Rp. ) ( Rp. )
48,800.00 3,527,752.00
39,500.00 8,840,890.00
196,290.00 196,290.00
162,000.00 324,000.00
1,262,000.00 7,572,000.00
JUMLAH INSTALASI AIR BERSIH 280,670,907.00
46,200.00 1,386,000.00
82,200.00 6,165,000.00
127,000.00 42,557,700.00
185,600.00 2,227,200.00
29,700.00 1,306,800.00
35,900.00 2,943,800.00
57,400.00 1,377,600.00
146,700.00 880,200.00
171,700.00 1,717,000.00
5,732,525.32 11,465,050.64
10,818,353.74 21,636,707.48
JUMLAH INSTALASI AIR KOTOR & AIR BEKAS 93,663,058.13
5,702,100.00 28,510,500.00
5,920,000.00 41,440,000.00
6,137,900.00 12,275,800.00
KEGIATAN
: PERENCANAAN PEMBANGUNAN PASAR KOTA BATU
PEKERJAAN : PERENCANAAN DED
LOKASI : Jl. DEWI SARTIKA, KOTA BATU
TAHUN : 2016
PASAR SAYUR KOTA BATU
MERINTAH KOTA BATU
AS PEKERJAAN UMUM
KARYA DAN TATA RUANG
7, Balai Among Tani Gedung C lantai 2, Kota Batu
AR KOTA BATU
RE-DESAIN PASAR SAYUR KOTA SURABAYA
KEGIATAN
: PEMBANGUNAN PASAR UNIT SAYUR KOTA SURABAYA
PEKERJAAN : PEMBANGUNAN PASAR UNIT SAYUR KOTA SURABAYA
LOKASI : JL. GUBENG KERTAJAYA - KOTA SURABAYA
TAHUN : 2018
R SAYUR KOTA SURABAYA
JUMLAH
MUHAMMAD FARUQ
DIREKTUR UTAMA
HARGA PERKIRAAN SENDIRI ( H
PROGRAM : PEMBANGUNAN PASAR BATU UNIT SAYUR KOTA SURABAYA
KEGIATAN : PEMBANGUNAN PASAR BATU UNIT SAYUR KOTA SURABAYA
PEKERJAAN : PEMBANGUNAN PASAR BATU UNIT SAYUR KOTA SURABAYA
LOKASI : JL. GUBENG KERTAJAYA - KOTA SURABAYA
TH. ANGGARAN : 2018
I. PEKERJAAN PERSIAPAN
1 Papan Nama proyek 1.00 ls
2 Pembuatan bouwplank 294.00 m1
3 Err:509 298.00 m1
4 Pembersihan lokasi awal s/d akhir pekerjaan 432.00 m²
5 Listrik dan Air Kerja 6.00 bln
6 Perbaikan Kembali Akses Jalan dan Saluran 1.00 ls
7 Mobilisasi Demobilisasi Bahan dan Peralatan 1.00 ls
8 Err:509 90.00 Err:509
9 Err:509 18.00 Err:509
10 Err:509 324.00 Err:509
11 Err:509 2,002.00 Err:509
12 Pengganti BPJS 1.00 ls
JUMLAH PEKERJAAN P
II. PEKERJAAN URUGAN DAN GALIAN
1 Galian Tanah 335.66 m³
2 Urugan Pasir , t = 5 cm 8.56 m³
3 Urugan Kembali 584.39 m³
4 Err:509 472.50 m³
JUMLAH PEKERJAAN URUGAN DA
III. PEKERJAAN PASANGAN
1 Pondasi Batu kali, lebar atas = 30 cm 7.92 m³
2 Pasangan Batu Kosong 3.60 m³
3 Err:509 3,751.43 m2
4 Err:509 7,566.86 m2
5 Err:509 7,566.86 m2
6 Err:509 14,489.60 m'
JUMLAH PEKERJAAN P
IV. PEKERJAAN BETON
1 Pondasi footplat
- Pondasi Pile Cap Type A 29.95 m³
- Pondasi Pile Cap Type B 0.70 m³
2 Lantai kerja beton K 150, t = 5 cm
- Lantai kerja beton untuk Pile Cap Type A 7.49 m³
- Lantai kerja beton untuk Pile Cap Type B 0.18 m³
3 Plat lantai beton , t = 13 cm 252.00 m³
No. URAIAN PEKERJAAN VOLUME SAT
4 Beton Sloof
- SLOOF 30 X 50 CM 50.44 m³
5 Beton Kolom
- KOLOM PENDEK 20 X 20 cm 10.30 m³
- KOLOM PENDEK 15 X 15 cm 0.24 m³
- KOLOM STRUKTUR 20 X 20 cm 34.16 m³
6 Err:509
- Err:509 40.35 m³
- Err:509 408.00 m'
7 Beton Balok 2.43 m'
8 Beton Bertulang Plat Atap
- Beton Bertulang Plat atap t = 13 cm 168.12 m³
9 Beton untuk tangga, t = 13 cm 1.39 m³
JUMLAH PEKERJA
No. URAIAN PEKERJAAN VOLUME SAT
6 ### 28.00 0
7 ### 46.00 0
8 Memasang 1 unit septictank kapasitas 50 orang 2.00 unit
JUMLAH PEKERJAAN SANITASI DAN
PEKERJAAN ATAP BAJA RINGAN
1 ###
2 ###
JUMLAH PEKERJAAN ATAP BAJ
XI. PEKERJAAN LAIN - LAIN
1 Pembuatan Papan Nama "Pasar Sayur" 1.00 ls
2 ### 136.08 m2
3 ### 10.00 unit
4 Pasang Tanggulan Bata Keliling Atap tinggi 10 cm 488.00 m'
5 Pemasangan Bak kontrol uk. 120 X 75 X 100 cm 20.00 0
6 Pemasangan plat beton tutup bak kontrol uk. 120 X 75 X 12 cm 20.00 0
7 ### 286.80 0
8 ### 286.80 0
9 ### 8.60 0
10 ### 163.20 0
11 ### 79.80 0
12 ### 760.50 0
13 ### 1,527.86 m2
14 ### 2,566.58 0
PEKERJAAN L
GRAND TOTA
KIRAAN SENDIRI ( H P S )
HARGA SATUAN
JUMLAH HARGA
( Rp. )
1,500,000.00 Rp 1,500,000.00
33,755.00 Rp 9,923,970.00
Err:509 Rp Err:509
23,850.00 Rp 10,303,200.00
3,500,000.00 Rp 21,000,000.00
28,000,000.00 Rp 28,000,000.00
78,000,000.00 Rp 78,000,000.00
Err:509 Rp Err:509
Err:509 Rp Err:509
Err:509 Rp Err:509
Err:509 Rp Err:509
25,000,000.00 Rp 25,000,000.00
JUMLAH PEKERJAAN PERSIAPAN Rp Err:509
187,965.00 Rp 63,091,805.60
46,770.00 Rp 400,491.51
38,969.10 Rp 22,772,986.08
Err:509 Rp Err:509
JUMLAH PEKERJAAN URUGAN DAN GALIAN Rp Err:509
263,625.00 Rp 2,087,910.00
500,454.00 Rp 1,801,634.40
165,934.00 Rp 622,489,785.62
84,643.00 Rp 640,481,730.98
48,286.00 Rp 365,373,401.96
38,221.00 Rp 553,807,001.60
JUMLAH PEKERJAAN PASANGAN Rp 2,186,041,464.56
Err:509 Rp Err:509
Err:509 Rp Err:509
Rp
311,422.00 Rp 2,331,927.94
311,422.00 Rp 54,498.85
311,422.00 Rp 78,478,344.00
HARGA SATUAN
JUMLAH HARGA
( Rp. )
#REF! Rp #REF!
#REF! Rp #REF!
#REF! Rp #REF!
#REF! Rp #REF!
#REF! Rp #REF!
118,717.00 Rp 48,436,536.00
118,717.00 Rp 288,482.31
4,868,005.00 Rp 818,409,000.60
4,868,005.00 Rp 6,776,262.96
JUMLAH PEKERJAAN BETON Rp #REF!
HARGA SATUAN
JUMLAH HARGA
( Rp. )
11,887,522.50 Rp 1,592,928,015.00
423,621.70 Rp 6,460,230.93
163,185.80 Rp 1,321,804.98
163,185.80 Rp 4,438,653.76
235,655.00 Rp 2,356,550.00
97,187.75 Rp 971,877.50
EKERJAAN KUSEN, JENDELA, PINTU DAN ASSESORIES Rp 1,608,477,132.17
30,400.60 Rp 84,982,749.26
25,040.60 Rp 69,999,244.46
25,040.60 Rp 64,268,703.15
JUMLAH PEKERJAAN PENGECATAN Rp 219,250,696.86
34,254,000.00 Rp 68,508,000.00
460,459.06 Rp 105,445,124.74
422,959.06 Rp 57,522,432.16
28,000.00 Rp 3,808,000.00
18,000.00 Rp 2,448,000.00
51,000.00 Rp 510,000.00
120,000.00 Rp 27,480,000.00
88,000.00 Rp 7,304,000.00
50,000.00 Rp 400,000.00
27,000.00 Rp 3,726,000.00
50,974.00 Rp 3,823,050.00
JUMLAH PEKERJAAN ELEKTRIKAL Rp 280,974,606.90
2,327,775.00 Rp 9,311,100.00
2,634,327.00 Rp 10,537,308.00
3,306,825.00 Rp 13,227,300.00
272,825.00 Rp 88,231,605.00
Err:509 Rp Err:509
JUMLAH PEKERJAAN MECHANICAL Rp Err:509
48,286.00 Rp 127,861,328.00
371,485.00 Rp 888,592,120.00
325,238.00 Rp 19,514,280.00
371,485.00 Rp 40,120,380.00
JUMLAH PEKERJAAN KERAMIK Rp 1,076,088,108.00
698,880.00 Rp 5,591,040.00
175,292.50 Rp 1,402,340.00
49,340.60 Rp 4,341,972.80
86,700.20 Rp 49,878,625.06
124,409.15 Rp 2,737,001.30
HARGA SATUAN
JUMLAH HARGA
( Rp. )
66,255.00 Rp 1,855,140.00
326,000.00 Rp 14,996,000.00
#REF! Rp #REF!
JUMLAH PEKERJAAN SANITASI DAN PLUMBING Rp #REF!
30,000,000.00Rp 30,000,000.00
481,247.00Rp 65,488,091.76
11,174,653.20Rp 111,746,532.00
16,593.40Rp 8,097,579.20
301,760.00Rp 6,035,200.00
513,021.04Rp 10,260,420.87
476,077.13Rp 136,538,919.93
848,238.47Rp 243,274,794.15
46,770.00Rp 402,409.08
126,210.00Rp 20,597,472.00
165,934.00Rp 13,241,533.20
Err:509 Rp Err:509
87,165.00 Rp 133,175,813.98
48,286.00 Rp 123,929,881.88
PEKERJAAN LAIN - LAIN Rp Err:509
Bobot BU
No Uraian Pekerjaan Harga (Rp) Pekerjaan %
M
1
Mengetahui ,
MUCHAMMAD NOOR, ST
NIP. 19710512 200604 1 014
TIME SCHEDULE
: BULAN KE I - BULAN KE V
Err:509 #REF! #REF! Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509
Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509
BULAN I BULAN II BULAN III
Menyetujui ,
PT.BAGIYO CONSULTANT
Selaku Konsultan Perencana
MUHAMMAD FARUQ
DIREKTUR UTAMA
DAFTAR HARGA SATUAN BAHA
PROGRAM : PEMBANGUNAN PASAR BATU UNIT SAYUR KOTA SURA
KEGIATAN : PEMBANGUNAN PASAR BATU UNIT SAYUR KOTA SURA
PEKERJAAN : PEMBANGUNAN PASAR BATU UNIT SAYUR KOTA SURA
LOKASI : JL. GUBENG KERTAJAYA - KOTA SURABAYA
TH. ANGGARAN : 2018
A UPAH
1 Pekerja / Pembantu Tukang
2 Mandor
3 Tukang Batu
4 Kepala Tukang batu
5 Tukang Kayu
6 Kepala Tukang Kayu
7 Tukang Besi
8 Kepala Tukang Besi
9 Tukang Cat
10 Kepala Tukang Cat
11 Tukang Pipa
12 Kepala Tukang Pipa
13 Tukang Listrik
14 Kepala Tukang Listrik
E PERALATAN MEKANIK
1 Dozer
2 Excavator
3 Wheel Loader
4 Motor Grader
5 Vibro Roller
6 Water Tanker
7 Dump Truck
8 Crane
9 Jack In pile
10 Genset type Silent
11 Pompa Air Mesin
12 Throwel
13 Vibrator
14 Molen
15 Survey ( Waterpass, Theodolit, dan Total Station )
16 PDA test
R HARGA SATUAN BAHAN DAN UPAH
UNAN PASAR BATU UNIT SAYUR KOTA SURABAYA
UNAN PASAR BATU UNIT SAYUR KOTA SURABAYA
UNAN PASAR BATU UNIT SAYUR KOTA SURABAYA
G KERTAJAYA - KOTA SURABAYA
HARGA SATUAN
BAHAN, ALAT, SPESIFIKASI, DAN MERK SATUAN
( Rp. )
Hari 150,000.00
Hari 177,000.00
Hari 161,000.00
Hari 177,000.00
Hari 161,000.00
Hari 177,000.00
Hari 161,000.00
Hari 177,000.00
Hari 161,000.00
Hari 177,000.00
Hari 161,000.00
Hari 177,000.00
Hari 161,000.00
Hari 177,000.00
jam -
PC 300 jam 1,267,000.00
hari 5,229,000.00
hari 2,514,000.00
hari 1,234,000.00
hari 1,567,000.00
Light Truck hari -
25 s/d 30 ton jam -
jam -
25 -50 kVA hari -
hari -
hari -
hari -
hari -
hari -
titik -
DAFTAR HARGA SATUAN BAHAN DAN UPAH
PROGRAM : PEMBANGUNAN PASAR KOTA BATU TAHAP I
KEGIATAN : PEMBANGUNAN PASAR KOTA BATU TAHAP I
PEKERJAAN : PEMBANGUNAN PASAR KOTA BATU TAHAP I
LOKASI : Jl. Dewi Sartika , kota Batu
TH. ANGGARAN : 2016
HARGA SURVEI
NO JENIS UPAH, BAHAN, ALAT, SPESIFIKASI, DAN MERK SATUAN
TERTINGGI
7 Type BC
- 1x6 mm2 m' 6,699.00
8 NYM
- 3×2,5 mm2 300/500 V m' 13,650.00
9 Stop Kontak unit 23,000.00
10 Saklar Tunggal unit 15,000.00
11 Saklar Double unit 21,700.00
12 Isolator m' 500.00
13 Las Doof bh 10,800.00
14 Konduit dia 20 mm (3/4") m' 3,312.00
15 Claim conduit bh 500.00
16 Pipa Diameter 100 mm m' 181,400.00
Bahan Pipa : BSP , Schedule -40
ASTM-53A
17 VALVE-VALVE & FIXTURES dia 100 mm bh 2,442,960.00
Jenis : Gate Valve
WP : 16 Kg/cm² atau 250 psi
18 Hose Reel Cabinet ( HRC ) lot 3,110,250.00
Kelengkapan
Fire Hose with Machino Coupling size 1,5 ", 30 M
Branch Pipe with straight tip nozzle size 1,5", 1pcs
Hydrant Valve 10K size 1,5", 1pcs
Landing valve 10K, VDH size 2,5", 1 pcs
F PERALATAN MEKANIK
1 Dozer jam 225,000.00
2 Excavator jam 240,000.00
3 Dump Truck hari 340,000.00
4 Crane jam 120,000.00
5 Jack In pile jam 160,000.00
6 Genset type Silent hari 60,000.00
7 Pompa Air Mesin hari 40,000.00
8 Throwel hari 60,000.00
9 Vibrator hari 120,000.00
10 Molen hari 80,000.00
11 Survey ( Waterpass, Theodolit, dan Total Station ) hari 40,000.00
12 PDA test titik 12,500,000.00
RGA SATUAN BAHAN DAN UPAH
1.15
70,000.00
90,000.00
70,000.00
85,000.00
80,000.00
85,000.00
80,000.00
85,000.00
70,000.00
85,000.00
80,000.00
85,000.00
80,000.00
85,000.00
STRUKTUR
120,000.00 189,750.00
125,000.00 169,625.00
275,000.00 330,625.00
210,000.00 261,625.00
700.00 1,035.00
220,000.00 290,375.00
254,400.00 292,560.00
210,000.00 264,500.00
130,000.00 158,125.00
1,250.00 1,523.75
2,250.00 2,587.50
HARGA SURVEI OVER HEAD &
TERENDAH PROFIT 15%
10,100.00 13,915.00
11,500.00 14,950.00
12,100.00 13,915.00
17,500.00 20,125.00
22,000.00 25,760.00
32,000.00 36,800.00
20,500.00 24,437.50
117,000.00 139,150.00
11,000.00 16,675.00
17,500.00 20,987.50
14,000.00 16,100.00
1,125,000.00 1,710,625.00
2,050,000.00 2,357,500.00
4,050,000.00 4,916,250.00
4,950,000.00 5,750,000.00
115,000.00 161,000.00
13,000.00 15,525.00
700,000.00 813,050.00
714,500.00 865,087.50
742,000.00 933,800.00
421,080.00 506,253.00
388,080.00 466,578.00
720,720.00 866,502.00
540,000.00 626,750.00
125,000.00 150,650.00
HARGA SURVEI OVER HEAD &
TERENDAH PROFIT 15%
120,900.00 145,130.00
39,500.00 52,900.00
52,500.00 92,287.50
21,620.00 26,806.50
25,000.00 43,125.00
24,150.00 27,772.50
54,700.00 62,905.00
23,000.00 27,370.00
110,000.00 126,500.00
580,000.00 729,560.00
45,000.00 53,475.00
600.00 690.00
35,000.00 41,428.75
6,960.00 8,004.00
9,600.00 11,040.00
70,200.00 90,505.00
13,200.00 15,180.00
19,500.00 22,712.50
19,500.00 22,712.50
19,500.00 22,712.50
7,711,500.00 8,913,937.50
210,000.00 264,500.00
L
189,750.00 229,123.13
244,000.00 305,900.00
AL DAN ELEKTRONIK
26,400.00 30,360.00
3,780.00 4,243.50
40,500.00 48,875.00
19,000.00 26,450.00
70,000.00 85,675.00
HARGA SURVEI OVER HEAD &
TERENDAH PROFIT 15%
97,500.00 116,437.50
120,000.00 142,025.00
5,699.00 7,128.85
13,000.00 15,323.75
23,000.00 26,450.00
15,000.00 17,250.00
21,700.00 24,955.00
500.00 575.00
10,800.00 12,420.00
3,312.00 3,808.80
250.00 431.25
178,500.00 206,942.50
1,975,000.00 2,540,327.00
2,360,000.00 3,145,393.75
1,700,000.00 2,116,000.00
350,000.00 603,750.00
HARGA SURVEI OVER HEAD &
TERENDAH PROFIT 15%
220,000.00 255,875.00
230,000.00 270,250.00
330,000.00 385,250.00
110,000.00 132,250.00
180,000.00 195,500.00
60,000.00 69,000.00
40,000.00 46,000.00
60,000.00 69,000.00
120,000.00 138,000.00
80,000.00 92,000.00
40,000.00 46,000.00
13,000,000.00 14,662,500.00
DAFTAR ANALISA
PROGRAM :
KEGIATAN :
PEKERJAAN :
LOKASI :
TH. ANGGARAN :
No URAIAN PEKERJAAN
27 Benangan
F Analisa Biaya Konstruksi Pekerjaan Lantai
28 Pasang Lantai Keramik 40 x 40 cm Motif untuk Los Te
29 Pasang Keramik Dinding 20 x 25 cm
G Analisa Biaya Konstruksi Pekerjaan Pengecatan
30 Pengecatan Tembok Baru dalam (1 Lapis Plamir, 1 Lapis Cat Das
31 Pengecatan Tembok Baru Luar (1 Lapis Alkali Sealer, 1 Lapis Ca
H Analisa Biaya Konstruksi Pekerjaan Kusen, Pintu, Jen
32 Pasang Rolling Door Almunium / 1 unit
33 Memasang Kusen Alumunium
34 Memasang Daun Pintu PVC
35 Pasang kunci tanam biasa
36 Pasang engsel pintu
I Analisa Biaya Konstruksi Pekerjaan Elektrikal
37 Pemasangan Panel / Unit
38 Memasang NYY 4x6 mm²
39 Instalasi penerangan/ ttk
40 Instalasi Stop Kontak/ ttk
J Analisa Biaya Konstruksi Pekerjaan Mekanikal
41 Pemasangan dan Pengadaan Hydrant Pillar (HP)
42 Pemasangan dan Pengadaan VALVE-VALVE & FIXTU
43 Pemasangan dan Pengadaan Hose Reel Cabinet ( HRC
44 Instalasi Pipa Hydrant
No URAIAN PEKERJAAN
Benangan Rp.
Analisa Biaya Konstruksi Pekerjaan Lantai
Pasang Lantai Keramik 40 x 40 cm Motif untuk Los Tengah/ M2 Rp.
Pasang Keramik Dinding 20 x 25 cm Rp.
Analisa Biaya Konstruksi Pekerjaan Pengecatan
Pengecatan Tembok Baru dalam (1 Lapis Plamir, 1 Lapis Cat Dasar, 2 Lapis Cat Penutup) / M2 Rp.
Pengecatan Tembok Baru Luar (1 Lapis Alkali Sealer, 1 Lapis Cat Dasar, 2 Lapis Cat Penutup) / M2 Rp.
Analisa Biaya Konstruksi Pekerjaan Kusen, Pintu, Jendela dan Aksesories
Pasang Rolling Door Almunium / 1 unit
Memasang Kusen Alumunium
Memasang Daun Pintu PVC
Pasang kunci tanam biasa
Pasang engsel pintu
Analisa Biaya Konstruksi Pekerjaan Elektrikal
Pemasangan Panel / Unit Rp.
Memasang NYY 4x6 mm² Rp.
Instalasi penerangan/ ttk Rp.
Instalasi Stop Kontak/ ttk Rp.
Analisa Biaya Konstruksi Pekerjaan Mekanikal
Pemasangan dan Pengadaan Hydrant Pillar (HP) Rp.
Pemasangan dan Pengadaan VALVE-VALVE & FIXTURES dia 100 mm Rp.
Pemasangan dan Pengadaan Hose Reel Cabinet ( HRC ) Rp.
Instalasi Pipa Hydrant Rp.
URAIAN PEKERJAAN HARGA SAT
HARGA SATUAN
Err:509
33,755.00
Err:509
Err:509
23,850.00
Err:509
Err:509
187,965.00
Err:509
38,969.10
46,770.00
Err:509
Err:509
263,625.00
500,454.00
311,422.00
Err:509
#REF!
#REF!
#REF!
118,717.00
4,868,005.00
4,110,939.38
165,934.00
84,643.00
48,286.00
HARGA SATUAN
38,221.00
371,485.00
325,238.00
25,040.60
30,400.60
11,887,522.50
163,185.80
423,621.70
235,655.00
97,187.75
34,254,000.00
50,974.00
460,459.06
422,959.06
2,327,775.00
2,634,327.00
3,306,825.00
272,825.00
HARGA SATUAN
698,880.00
175,292.50
49,340.60
86,700.20
124,409.15
#REF!
66,255.00
326000
481,247.00
301,760.00
513,021.04
476,077.13
848,238.47
126,210.00
11,174,653.20
ANALISA HARGA SATUAN PEKERJAA
PROGRAM :
KEGIATAN :
PEKERJAAN :
LOKASI :
TH. ANGGARAN : 2018
8 Galian Tanah
0.0450 oh Mandor 177,000.00 7,965.00
1.2000 oh Pekerja 150,000.00 180,000.00
187,965.00
10 Urugan Kembali m3
0.0083 oh Mandor 177,000.00 1,469.10
0.2500 oh Pekerja 150,000.00 37,500.00
38,969.10
11 Urugan Pasir / M3
0.0100 oh Mandor 177,000.00 1,770.00
0.3000 oh Pekerja 150,000.00 45,000.00
1.2000 M3 Pasir Urug 177,000.00
46,770.00
30 Pengecatan Tembok Baru dalam (1 Lapis Plamir, 1 Lapis Cat Dasar, 2 Lapis Cat Penutup) / M2
0.0025 oh Mandor 177,000.00 442.50
0.0063 oh Kepala Tukang 177,000.00 1,115.10
0.0630 oh Tukang Cat 161,000.00 10,143.00
0.0200 oh Pekerja 150,000.00 3,000.00
0.1000 Kg Cat Dasar 28,000.00
0.2600 Kg Cat Penutup 2 Kali (Cat Air Setara Matex) 29,000.00
14,700.60
No Indeks Sat Uraian Harga Satuan Upah
31 Pengecatan Tembok Baru Luar (1 Lapis Alkali Sealer, 1 Lapis Cat Dasar, 2 Lapis Cat Penutup) / M2
0.0025 oh Mandor 177,000.00 442.50
0.0063 oh Kepala Tukang 177,000.00 1,115.10
0.0630 oh Tukang Cat 161,000.00 10,143.00
0.0280 oh Pekerja 150,000.00 4,200.00
0.1000 Kg Cat Dasar 28,000.00
0.2600 Kg Cat Penutup 2 Kali (Cat Weather Shield) 45,000.00
15,900.60
SITEKTUR
Jumlah Bahan Jumlah Upah & Keuntungan Harga Yang
Kebutuhan Harga Total
Bahan dan Pajak Harus Dibayar
1
2
20
20
3
4
2
- 33,755.00 115% Rp 27,807,400 Rp 31,978,510
1
2
- 23,850.00 115% Rp 477,000 Rp 548,550
Jumlah Bahan Jumlah Upah & Keuntungan Harga Yang
Kebutuhan Harga Total
Bahan dan Pajak Harus Dibayar
1
26.6666666667
- 187,965.00 115% Rp 4,177,000 Rp 4,803,550
1
30.1204819277
38,969.10 115% Rp 4,695,072 Rp 5,399,333
1
30
1
1
1
20
1
155,500.00 3.0
31,937.00 1.0
187,437.00 1.0
374,874.00 500,454.00 115% Rp 978,700 Rp 1,125,505
1
1
4
20
1
1
4
20
1
1
4
20
9.04
311,422.00 115% Rp 3,998,000 Rp 4,597,700
1
1
4
20
80.63
311,422.00 115% Rp 3,998,000 Rp 4,597,700
1
1
4
20
24.42
311,422.00 115% Rp 3,998,000 Rp 4,597,700
1
1
4
20
54.81
311,422.00 115% Rp 3,998,000 Rp 4,597,700
1
1
4
20
80.63
311,422.00 115% Rp 3,998,000 Rp 4,597,700
1
1
4
20
5.1
311,422.00 115% Rp 3,998,000 Rp 4,597,700
1
1
10
10
Jumlah Bahan Jumlah Upah & Keuntungan Harga Yang
Kebutuhan Harga Total
Bahan dan Pajak Harus Dibayar
1
1
10
10
1
1
10
10
1
1
10
10
1
1
10
10
-
32,000.00
18,600.00
#REF!
84,000.00
934,500.00
#REF! #REF!
-
51,200.00
49,600.00
#REF!
84,000.00
934,500.00
484,260.00
464,800.00
192,000.00
#REF! #REF!
-
51,200.00
49,600.00
#REF!
84,000.00
934,500.00
484,260.00
464,800.00
192,000.00
#REF! #REF!
Jumlah Bahan Jumlah Upah & Keuntungan Harga Yang
Kebutuhan Harga Total
Bahan dan Pajak Harus Dibayar
oh
oh
oh
oh
oh
oh
- M3
160.00 Kg
12,400.00 Ltr
42,000.00 Kg
12,600.00 Kg
8,000.00 Kg
1,686.00 M3
2,556.00 M3
79,402.00 118,717.00
-
24,000.00
12,400.00
1,837,500.00
63,000.00
934,500.00
363,195.00
415,000.00
168,000.00
3,817,595.00 4,868,005.00
Jumlah Bahan Jumlah Upah & Keuntungan Harga Yang
Kebutuhan Harga Total
Bahan dan Pajak Harus Dibayar
342,125.00
25,012.50
6,210.00
2,205,000.00
47,221.88
861,000.00
3,486,569.38 4,110,939.38
70,000.00
16,640.00
13,769.00
100,409.00 165,934.00
20,448.00
5,620.00
26,068.00 84,643.00
6,500.00
6,500.00 48,286.00
13,000.00
5,901.00
18,901.00 38,221.00
Jumlah Bahan Jumlah Upah & Keuntungan Harga Yang
Kebutuhan Harga Total
Bahan dan Pajak Harus Dibayar
160,600.00
20,000.00
12,645.00
4,500.00
197,745.00 371,485.00
73,700.00
18,600.00
5,058.00
4,500.00
101,858.00 325,238.00
2,800.00
7,540.00
10,340.00 25,040.60
Jumlah Bahan Jumlah Upah & Keuntungan Harga Yang
Kebutuhan Harga Total
Bahan dan Pajak Harus Dibayar
enutup) / M2
2,800.00
11,700.00
14,500.00 30,400.60
9,204,000.00
9,204,000.00 11,887,522.50
163,185.80
423,621.70
151,000.00
151,000.00 235,655.00
Jumlah Bahan Jumlah Upah & Keuntungan Harga Yang
Kebutuhan Harga Total
Bahan dan Pajak Harus Dibayar
68,000.00
68,000.00 97,187.75
29,363,000.00
737,000.00
108,000.00
150,000.00
900,000.00
186,000.00
786,000.00
462,000.00
234,000.00
178,000.00
1,150,000.00
34,254,000.00 34,254,000.00
34,100.00
7,700.00
41,800.00 50,974.00
Jumlah Bahan Jumlah Upah & Keuntungan Harga Yang
Kebutuhan Harga Total
Bahan dan Pajak Harus Dibayar
269,723.25
67,430.81
480.00
6,000.00
32,000.00
26,000.00
401,634.06 460,459.06
269,723.25
67,430.81
480.00
6,000.00
32,000.00
26,000.00
401,634.06 422,959.06
2,200,000.00
76,000.00
2,276,000.00 2,327,775.00
2,540,327.00
66,000.00
2,606,327.00 2,634,327.00
Jumlah Bahan Jumlah Upah & Keuntungan Harga Yang
Kebutuhan Harga Total
Bahan dan Pajak Harus Dibayar
3,248,000.00
76,000.00
2,166,500.00
3,248,000.00 3,306,825.00
214,000.00
12,000.00
76,000.00
214,000.00 272,825.00
213,000.00
7,000.00
12,000.00
2,810.00
234,810.00 698,880.00
Jumlah Bahan Jumlah Upah & Keuntungan Harga Yang
Kebutuhan Harga Total
Bahan dan Pajak Harus Dibayar
155,000.00
37.50
155,037.50 175,292.50
8,400.00
24,500.00
32,900.00 49,340.60
25,200.00
24,500.00
49,700.00 86,700.20
44,400.00
24,500.00
68,900.00 124,409.15
Jumlah Bahan Jumlah Upah & Keuntungan Harga Yang
Kebutuhan Harga Total
Bahan dan Pajak Harus Dibayar
#REF!
66,255.00
326,000.00
397,100.00
36,100.00
433,200.00 481,247.00
243,000.00
17,010.00
260,010.00 301,760.00
Jumlah Bahan Jumlah Upah & Keuntungan Harga Yang
Kebutuhan Harga Total
Bahan dan Pajak Harus Dibayar
435,833.33
35,437.71
471,271.04 513,021.04
401,666.67
32,660.46
434,327.13 476,077.13
745,833.33
60,655.14
806,488.47 848,238.47
99,000.00
2,810.00
101,810.00 126,210.00
L27
L11
L05
L01
5,431,500.00
2,754,100.80
84,065.00
23,920.00
Jumlah Bahan Jumlah Upah & Keuntungan Harga Yang
Kebutuhan Harga Total
Bahan dan Pajak Harus Dibayar
2,097.60
96,600.00 M126
8,392,283.40 11,174,653.20 M148.c
Produktivitas
Waktu (Hari)
(m2)
947.3710561398 1.000
23 27
Produktivitas
Waktu (Hari)
(m2)
26 5.00
139 1.00
115 1.00
15 2.000
2.25
14.76 6.0000
14.76 3.00
Produktivitas
Waktu (Hari)
(m2)
14.7635684056 1.0000
14.7635684056 6.00
14.7635684056 0
14.7635684056 3.712517
14.7635684056 5.4614167649
14.7635684056 0.3454449399
Produktivitas
Waktu (Hari)
(m2)
38.3333333333 0.2086956522
38.3333333333 6.7262608696
38.3333333333 6.3709565217
38.3333333333 22.9630434783
38.3333333333 0.6944347826
Produktivitas
Waktu (Hari)
(m2)
Produktivitas
Waktu (Hari)
(m2)
Produktivitas
Waktu (Hari)
(m2)
Produktivitas
Waktu (Hari)
(m2)
Produktivitas
Waktu (Hari)
(m2)
BACK
PROGRAM : -
KEGIATAN : -
PEKERJAAN : -
LOKASI : -
TH. ANGGARAN : -
I. PEKERJAAN PERSIAPAN
1 Pengukuran
2 Pembersihan lokasi awal s/d akhir pekerjaan
3 Mobilisasi Demobilisasi Bahan dan Peralatan
3 Urugan Kembali
4 Tulangan Plat
P1 Y Total Panjang Unit Satuan (Kg/m)
1 Ф10 165 0.617
2 Ф10 569.5 0.617
3 Ф10 38 0.617
4 Ф10 569.5 0.617
5 Ф10 541.5 0.617
P1
P1 X Total Panjang Unit Satuan (Kg/m)
1 Ф10 105 0.617
2 Ф10 329.5 0.617
3 Ф10 105 0.617
4 Ф10 329.5 0.617
5 Ф10 301.5 0.617
P2 Y Total Panjang Unit Satuan (Kg/m)
1 Ф10 174.5 0.617
2 Ф10 633.4 0.617
3 Ф10 174.5 0.617
4 Ф10 633.4 0.617
5 Ф10 605.4 0.617
P2
P2 X Total Panjang Unit Satuan (Kg/m)
1 Ф10 112 0.617
2 Ф10 329.5 0.617
3 Ф10 112 0.617
4 Ф10 329.5 0.617
5 Ф10 301.5 0.617
P3 Y Total Panjang Unit Satuan (Kg/m)
1 Ф10 131 0.617
2 Ф10 395.5 0.617
3 Ф10 131 0.617
4 Ф10 395.5 0.617
5 Ф10 381.5 0.617
P3
P3 X Total Panjang Unit Satuan (Kg/m)
P3
116.59
1.80 2.60 1.00 6.00 28.08
1.80 1.80 1.00 18.00 58.32
1.00 1.00 1.50 4.00 6.00
43.20
1.000 -
1.80 2.60 0.50 6.00 14.04
1.80 1.80 0.50 18.00 29.16
1.000 116.59
JUMLAH PEKERJAAN TANAH
86.40
1.80 2.60 1.00 6.00 28.08
1.80 1.80 1.00 18.00 58.32
9.04
1.80 2.60 0.10 6.00 2.81
1.80 1.80 0.10 18.00 5.83
1.00 1.00 0.10 4.00 0.40
31.50 19.69 0.13 80.63
12 1,314.92
12 353.68
12 337.01
12 45.64
72 62.19
19 2,230.38
19 608.22
19 583.07
19 78.48
80 88.85
9 493.09
9 265.26
9 252.76
9 34.23
72 62.19
12 227.64
12 84.11
21 10.37
6 234.98
6 114.34
6 170.77
6 14.75
48 32.58
2 32.91
2 29.82
47 31.90
10 1,173.88
10 320.12
10 306.88
10 41.31
80 54.30
Jumlah Total Berat
24 172.99
24 21.18
24 116.49
24 21.18
Jumlah Total Berat(Kg)
32 1,651.69
165 142.53
64 5,999.25
298 257.41
32 1,283.42
128 110.57
16 146.27
30 25.91
64 1,732.79
87 75.15
32 731.70
74 63.92
1,008.44
10 122.56
10 86.11
10 122.56 417.33
10 86.11
8.00 2.00
1.80 2.60 0.50 4.40
1.80 1.80 0.50 3.60
198.34 0.30 0.50 257.84
0.40 0.40 6.36 24.00 244.22
880.25 -
64.80 0.30 0.50 168.48
114.57 0.40 0.60 366.62
48.74 0.30 0.50 126.71
18.18 0.20 0.30 29.09
18.09 0.25 0.40 37.99
6.03 0.25 0.40 12.66
60.30 0.25 0.45 138.69
31.50 19.69 0.13 2.00 26.62
0.30 3.50 0.13 64.00 8.74
m1
m²
ls
PEKERJAAN PERSIAPAN
m³
m³
m³
m³
m³
m³
m³
AH PEKERJAAN TANAH
m³
m³
PEKERJAAN PASANGAN
m³
m³
m³
m³
m³
m³
m³
m³
m³
m³
m³
m³
m³
m³
m³
m³
m³
m³
m²
m²
m²
m²
m²
m²
m²
m²
m²
EKERJAAN ELEKTRIKAL
BACK UP
PROGRAM : -
KEGIATAN : -
PEKERJAAN : -
LOKASI : -
TH. ANGGARAN : -
tinggi
No. URAIAN PEKERJAAN panjang lebar
I. PEKERJAAN PERSIAPAN
1 Pembuatan bouwplank 31.50 19.69
- Kepala tukang / Mandor
3 Urugan Kembali
3 Tulangan Sloof
- D16
4 Tulangan Plat
- Ф10
- Ф8
5 Tulangan Tangga
- D12
- Ф8
jumlah luas
KOEF VOLUME SAT
102.38 m1
620.24 m²
1.00 ls
JUMLAH PEKERJAAN PERSIAPAN
116.59
6.00 28.08 m³
18.00 58.32 m³
4.00 6.00 m³
43.20 m³
1.000 - m³
6.00 14.04 m³
18.00 29.16
1.000 116.59 m³
JUMLAH PEKERJAAN TANAH
4.00 21.60 m³
1.08 m³
936.000 13,665.60 m1
JUMLAH PEKERJAAN PASANGAN
6.00 28.08 m³
18.00 58.32 m³
6.00 2.81 m³
18.00 5.83 m³
4.00 0.40 m³
80.63 m³
29.75 m³
24.00 24.42 m³
9.72 m³
27.50 m³
7.31 m³
1.09 m³
1.81 m³
0.60 m³
6.78 m³
267.14 m³
64.00 4.37 m³
2.00 0.68 m³
8.00
2.00
8.00
2.00
- m²
2.00 titik
4.40 m²
3.60 m²
257.84
24.00 244.22 m²
-
168.48 m²
366.62 m²
126.71 m²
29.09 m²
37.99 m²
12.66 m²
138.69 m²
26.62 m²
64.00 -----
tinggi
No. URAIAN PEKERJAAN panjang lebar
I. PEKERJAAN PERSIAPAN
1 Papan Nama proyek
2 Pembuatan bouwplank 75.00 72.00
3 Pagar sementara setinggi 2 m 76.00 73.00
4 Pembersihan lokasi awal s/d akhir pekerjaan 6.00 72.00
5 Listrik dan Air Kerja
6 Perbaikan Kembali Akses Jalan dan Saluran
7 Mobilisasi Demobilisasi Bahan dan Peralatan 90.00
8 Pembuatan direksi keet 18.00 5.00
9 Pembuatan gudang bahan 3.00 6.00
10 Pembuatan Bedeng Relokasi Pedagang (Tidak Permanen)
2.00 3.00
3.00 5.00
12 Pembongkaran bangunan eksisting LOS 1 - 18 7.15 48.65
DOK 1 & 2 12.00 8.00
DOK 3 15.00 12.50
LOS 21 10.00 5.00
LOS 19 76.50 10.50
LOS 23 30.10 7.00
13 Pengganti BPJS
3 Urugan Kembali
4 Cutting tanah 72.00 17.50 0.75
5 Pekerjaan Plesteran
6 Pekerjaan Acian
7 Benangan
Plat liufel 66.00 13.00
57.00 7.50
55.50 7.00
Kolom 20 x 20 cm 3.65
jumlah luas
KOEF VOLUME SAT
1.00 ls
294.00 m1
298.00 m1
432.00 m²
6.00 bln
1.00 ls
1.00 ls
90.00 m²
18.00 m²
324.00 m²
49.00 294.00
2.00 30.00
347.85 m²
2.00 192.00 m²
187.50
50.00
803.25 m²
2.00 421.40
2,002.00
1.00 ls
JUMLAH PEKERJAAN PERSIAPAN
335.66 m³
20.70 m³
234.00 134.78 m³
14.00 1.75 m³
174.64 m³
6.00 3.78 m³
8.56 m³
1.000 0.90 m³
234.00 7.49 m³
14.00 0.18
1.000 584.39 m³
472.50 m³
JUMLAH PEKERJAAN TANAH
7.92 m³
3.60 m³
3,751.43 m2
672.49
4,034.94
64.00
-
-
-
-
7,566.86 m2
7,566.86 m2
14,489.60 m1
4.00 316.00 m1
4.00 258.00
4.00 250.00
936.000 13,665.60 m1
JUMLAH PEKERJAAN PASANGAN
234.00 29.95 m³
14.00 0.70 m³
234.00 7.49 m³
14.00 0.18 m³
252.00 m³
119.60 m³
50.44 m³
28.44
8.00 13.44
10.00 15.00
234.00 10.30 m³
14.00 0.24 m³
m'
m'
m'
234.00 34.16 m³
40.35 m³
408.00 m³
2.43 m³
168.12 m³
858.00 68.64 m³
2.00 855.00 68.40 m³
388.50 31.08 m³
1.39 m³
JUMLAH PEKERJAAN BETON
64.00 1,020.00 134.00 unit
15.25
2.00 4.05 m2
8.00 11.20 m2
2.00 8.10 m'
8.00 27.20 m'
JUMLAH PEKERJAAN KUSEN
2,795.43 m²
2,795.43 m²
2.00 titik
229.00 titik
136.00 titik
136.00 unit
136.00 unit
10.00 unit
229.00 unit
83.00 buah
8.00 buah
138.00 buah
75.00 m1
JUMLAH PEKERJAAN ELEKTRIKAL
4.00 titik
4.00 titik
4.00 titik
323.40 m'
77.62 m3
JUMLAH PEKERJAAN ELEKTRIKAL
256.00 m2
2,648.00 m2
2,392.00
60.00 m2
108.00 m2
JUMLAH PEKERJAAN LANTAI
8 unit
8 unit
88 m'
575.30 m'
22 m'
28 unit
2 46.00 unit
JUMLAH PEKERJAAN LANTAI
- m²
- m²
PEKERJAAN ATAP BAJA RINGAN
1.00 1.00 ls
136.08 m2
12.00 32.40
12.00 103.68
10 10 unit
488 m'
20 unit
20 unit
286.80 m'
286.80 m'
8.604 m3
163.2 m2
m2
115.2 m2
2.00 48 m2
p.tot 79.80 m2
120 18
108 16.2
144 21.6
160 24
-
m3
2.00 43.2
2.00 37.8
2.00 54
2.00 90
760.50 m3
1,527.86 m2
919.38 m2
2 896.00
432.00
2,566.58 m2
319.20