RENCANA ANGGARAN BIAYA

PEKERJAAN MEKANIKAL, ELEKTRIKAL, DAN PLU


PROGRAM : PENINGKATAN SARANA & PRASARANA OLAH RAGA
KEGIATAN : PEMBANGUNAN SARANA & PRASARANA OLAH RAGA
PEKERJAAN : PEMBANGUNAN GEDUNG OLAH RAGA (INDOOR) KOMPLEKS STADION BRANTAS
LOKASI : KOTA BATU
TH. ANGGARAN : 2016

No. URAIAN PEKERJAAN VOLUME SAT

I PEKERJAAN ELEKTRIKAL
I.I PEKERJAAN POWER HOUSE
a Pengadaan Transformer 100 kVA/20 kV/50 Hz/380 P 1.00 unit
b Pengadaan dan Pemasangan Pole Travo 2.00 unit
c Pekerjaan Listrik Cadangan / Emergency
1 Pengadaan dan pemasangan Genset 100 kVA type silent 1.00 unit
2 Panel Genset 1.00 unit
3 ATS / AMF 1.00 unit
4 Grounding Genset 1.00 unit
5 Dudukan Mesin, peredam getaran, muffler extension 1.00 unit
6 Tanki BBM kap. 1000 liter termasuk instalasi 1.00 unit
JUMLAH PEKERJAAN POWE
I.2 PEKERJAAN PANEL
a Panel LV-MDP
1 Box panel 1.00 unit
2 Pilot Lamp + Fuse 6.00 unit
3 Voltmeter 0 - 500V 6.00 unit
4 Amperemeter 0 - 200A 2.00 unit
5 Selector Voltage 2.00 unit
6 MCCB 3P 200 A 18KA 1.00 unit
7 MCB 3P 25 A 10KA ( Pen LP B ) 1.00 unit
8 MCCB 3P 30 A 10KA ( Pen LP 1 ) 1.00 unit
9 MCCB 3P 40 A 10KA ( Pen LP 2 + LP 3) 1.00 unit
10 MCCB 3P 20 A 10KA ( PAC - B) 1.00 unit
11 MCCB 3P 40 A 10KA ( PAC -1, 2, 3) 1.00 unit
12 MCB 3P 25 A 10KA ( Pompa Air Bersih ) 1.00 unit
13 MCB 3P 25 A 10KA ( Spare ) 1.00 unit
14 Aresster Protection 3p 65 KA 1.00 unit
15 Grounding 1.00 unit
16 Wiring dan Accessories 1.00 unit
b Panel Penerangan Lantai 1 ( LP-1), terdiri dari:
1 Box panel 1.00 unit
2 Pilot Lamp + Fuse 3.00 unit
3 Ampere meter 1.00 unit
4 Voltmeter 0 - 500 1.00 unit
5 Selector Voltage 1.00 unit
6 CT 40 A/5A 1.00 unit
7 MCCB 3P 30A 10KA 1.00 unit
No. URAIAN PEKERJAAN VOLUME SAT

8 MCB 1P 16A 4,5 KA 1.00 unit


9 Grounding 1.00 unit
10 Wiring dan Accessories 1.00 unit
c Panel Penerangan Tribun, terdiri dari:
1 Box panel 1.00 unit
2 Pilot Lamp + Fuse 3.00 unit
3 Ampere meter 1.00 unit
4 Voltmeter 0 - 500 1.00 unit
5 Selector Voltage 1.00 unit
6 CT 40 A/5A 1.00 unit
7 MCCB 3P 30A 10KA 1.00 unit
8 MCB 1P 16A 4,5 KA 1.00 unit
9 Grounding 1.00 unit
10 Wiring dan Accessories 1.00 unit
d Panel Penerangan Lansekap
1 Box panel 1.00 unit
2 Pilot Lamp + Fuse 3.00 unit
3 Ampere meter 1.00 unit
4 Voltmeter 0 - 500 1.00 unit
5 Selector Voltage 1.00 unit
6 CT 40 A/5A 1.00 unit
7 MCCB 3P 30A 10KA 1.00 unit
8 MCB 1P 16A 4,5 KA 1.00 unit
9 Grounding 1.00 unit
10 Wiring dan Accessories 1.00 unit
e Panel Pompa
1 Box panel 1.00 unit
2 Pilot Lamp + Fuse 3.00 unit
3 Ampere meter 1.00 unit
4 Voltmeter 0 - 500 1.00 unit
5 Selector Voltage 1.00 unit
6 CT 40 A/5A 1.00 unit
7 MCCB 3P 30A 10KA 1.00 unit
8 MCB 1P 16A 4,5 KA 1.00 unit
9 Grounding 1.00 unit
10 Wiring dan Accessories 1.00 unit
JUMLAH PEKERJAA
I.3 PEKERJAAN PENGKABELAN
1 NYFGBY 4x70 mm, Trafo ke MDP 135.00 m1
2 NYFGBY 4x70 mm, Genset ke MDP 34.00 m1
3 NYY 4x10 mm + BC 6 mm, MDP ke SDP A 15.00 m1
4 NYY 4x6 mm + BC 6 mm, MDP ke SDP B 60.00 m1
5 NYY 4x6 mm + BC 6 mm, MDP ke SDP C 25.00 m1
6 NYY 4x6 mm + BC 6 mm, MDP ke SDP Lansekap 28.00 m1
7 NYY 4x6 mm + BC 6 mm, MDP ke SDP Pompa 24.00 m1
No. URAIAN PEKERJAAN VOLUME SAT

8 NYY 4x6 mm + BC 6 mm, MDP ke SDP AC 24.00 m1


JUMLAH PEKERJAAN PENGK
I.4 PEKERJAAN KABEL TRAY
1 Kabel Tray Elektrikal 300 x 100 + support 130.00 m1
2 Riser tray 48.00 m1
JUMLAH PEKERJAAN KAB
I.5 INSTALASI ELEKTRIKAL, PENERANGAN, ARMATUR & FIGTURE
1 Instalasi penerangan 268.00 ttk
2 Instalasi lampu sorot lapangan 18.00 ttk
3 Instalasi stop kontak 70.00 ttk
4 Stop kontak 70.00 ttk
5 Saklar tunggal 58.00 ttk
6 Saklar ganda 34.00 ttk
7 Ducting PVC Ø 4" 90.00 m1
8 Exhaust Fan Ceiling ( Closet ) 15.00 unit
9 Exhaust Fan Dinding ( Closet ) 12.00 unit
10 Exhaust Fan Dinding ( R. Genset dan R. Pompa ) 4.00 unit
11 Downlight 16W LED 82.00 unit
12 Downlight 11.5W LED 20.00 unit
13 Recessed Mounted LED 40.00 unit
14 Recessed Mounted Spot LED wastafel 14.00 unit
15 Surface Mounted LED 24.00 unit
16 Pendant lamp tribun 48.00 unit
17 Consol Stadion 10.00 unit
18 Sport Lamp LED Arena 18.00 unit
19 Spotlight Façade LED 8.00 unit
20 Lampu Taman 4.00 unit
21 PJU lengkap dengan tiang, pondasi dan instalasi kabel 4.00 unit
JUMLAH INSTALASI ELEKTRIKAL, PENERANGAN, ARMATUR &
I.6 PEKERJAAN PENYALUR PETIR & PENTANAHAN
1 Head penangkal petir non Radio aktif Radius proteksi 100 m 1.00 unit
2 Down Conductor cable NYA 70 mm 92.00 m'
3 Dudukan tiang penangkal petir 1.00 unit
4 Lightning Strike counter - Analog 1.00 unit
5 Bak kontrol 40x40 Cm 2.00 unit
6 Grounding penangkal petir / Ground rod max. 1 ohm 1.00 ls
7 Grounding Struktur / Rangka Atap 1.00 ls
8 Obstruction Light ( OBL ) 1.00 ls
9 Pipa GIP medium 1 1/2" 3.00 m'
10 Gali tanah 10.00 m³
11 Testing & Commisioning 1.00 Ls
12 Perizinan Depnaker 1.00 ls
JUMLAH PEKERJAAN PENYALUR PETIR & PENT
II PEKERJAAN ELEKTRONIK
II.1 PEKERJAAN SOUND SYSTEM PUBLIC ADDRESS
No. URAIAN PEKERJAAN VOLUME SAT

1 Column Speaker up to 40 watt 8.00 unit


2 Column Speaker up to 20 watt 8.00 unit
3 Ceiling Speaker up to 10 watt 1.00 unit
4 Power Amplifier 240 watt 1.00 unit
5 Power Amplifier 120 watt 2.00 unit
6 Input Music ( MP3 Player, CD Player, etc ) 1.00 unit
7 Audio Processor 1.00 unit
8 Microphone ( Wireless ) 1.00 unit
9 Microphone Desk ( chime ) 2.00 unit
10 Microphone Cord + Stand 2.00 unit
11 Instalasi 1.00 ls
12 Testing dan commissioning 1.00 ls
JUMLAH PEKERJAAN SOUND SYSTEM PUBLIC A
II.2 PEKERJAAN CCTV
1 CCTV Camera 16.00 unit
2 Main unit ( DVR + peripheral ) 1.00 unit
3 Instalasi, testing dan commissioning 1.00 ls
JUMLAH PEKERJA
II.3 PEKERJAAN PAPAN SCORE ( SCORING BOARD )
1 Panel Display LED 2.00 unit
termasuk software & controller, power supply, bracket, dll
2 Pengadaan struktur / rangka 2.00 ls
3 Instalasi dan commisioning 1.00 unit
JUMLAH PEKERJAAN PAPAN SCORE ( SCORING
III PEKERJAAN MEKANIKAL & PLUMBING
III.1 INSTALASI AIR BERSIH
1 Pengadaan Sumur Bor Dangkal s/d 40 m, lengkap dengan perpipaan, - 1.00 unit
dan material / peralatan bantu
2 Pompa Submersible Q= 150 lpm,Head 30 meter, daya 1,1 kw 1.00 unit
3 Pompa Transfer Q= 150 lpm,Head 30 meter, daya 1,1 kw 2.00 unit
Lengkap termasuk pressure switch, check Valve,
foot valve dan aksesories
4 Pompa Booster Q= 2 x 150 lpm,Head 15 meter, daya 1,1 kw 2.00 unit
Lengkap termasuk pressure switch, pressure tank ,check Valve,
dan aksesories
5 Instalasi pompa 2.00 lot
6 Roof Tank Ø 1,5 m3 Stainless 6.00 unit
INSTALASI TANDON AIR ATAS
1 Pipa PPR PN-10 Ø 40 mm ( Dari Ruang Pompa Ke Roof Tank ) 80.00 m1
2 Floating Valve Ø 1" (Katup Pelampung) 4.00 bh
3 Stop Kran Ø 1 1/2" outlet Roof tank 4.00 bh
4 Stop Kran Ø 1" penguras dan pengisi Roof tank 8.00 bh
5 Water Level Control ( WLC ) lengkap dengan stick dan holder 2.00 unit
PERPIPAAN
1 Pipa PPR PN-10 Ø 2" ( 63 mm ) 30.00 m1
2 Pipa PPR PN-10 Ø 1 1/ 2" ( 50 mm ) 44.10 m1
3 Pipa PPR PN-10 Ø 1 1/ 4" ( 40 mm ) 93.20 m1
4 Pipa PPR PN-10 Ø 1" ( 32 mm ) 73.45 m1
No. URAIAN PEKERJAAN VOLUME SAT

5 Pipa PPR PN-10 Ø 3/4 " ( 25 mm ) 72.29 m1


6 Pipa PPR PN-10 Ø 1/2 " ( 20 mm ) 223.82 m1
7 Accesoris pipa (coupling, reducer, elboe, tee) 1.00 ls
SANITAIR
- Stop Kran Ø 1 1/4" 2.00 bh
FIRE FIGHTING
- Pengadaan Alat Pemadam Api Ringan / Fire Extinguiser 3 kg 6.00 bh
JUMLAH INSTALASI A
III.2 INSTALASI AIR KOTOR & AIR BEKAS
PIPA AIR KOTOR
1 Pipa PVC AW Ø 2 " 30.00 m
2 Pipa PVC AW Ø 3 " 75.00 m
3 Pipa PVC AW Ø 4 " 335.10 m
4 Pipa PVC AW Ø 5 " 12.00 m
PIPA VENTING
1 Pipa PVC D Ø 1 1/4 " 44.00 m
2 Pipa PVC D Ø 2 " 82.00 m
3 Pipa PVC D Ø 3 " 24.00 m
SANITAIR
1 Clean Out dia 3" 6.00 unit
2 Clean Out dia 4" 10.00 unit
SEPTICTANK
1 Septic Tank kap. 3 m3 area belakang 2.00 unit
2 Septic Tank kap. 10 m3 area depan 2.00 unit
JUMLAH INSTALASI AIR KOTOR & A
III.3 PEKERJAAN TATA UDARA
1 Pengadaan dan pemasangan AC Wall Mounted 0.5 pk, termasuk instalasi - 5.00 unit
dan sistem drainase
2 Pengadaan dan pemasangan AC Wall Mounted 1.5 pk, termasuk instalasi - 7.00 unit
dan sistem drainase
3 Pengadaan dan pemasangan AC Wall Mounted 2 pk, termasuk instalasi - 2.00 unit
dan sistem drainase
JUMLAH PEKERJAAN TA
A ANGGARAN BIAYA
KAL, ELEKTRIKAL, DAN PLUMBING

RAGA (INDOOR) KOMPLEKS STADION BRANTAS

HARGA SATUAN JUMLAH HARGA


( Rp. ) ( Rp. )

122,500,000.00 122,500,000.00
8,250,000.00 16,500,000.00

613,792,400.00 613,792,400.00
36,000,000.00 36,000,000.00
42,000,000.00 42,000,000.00
26,000,000.00 26,000,000.00
18,250,000.00 18,250,000.00
4,200,000.00 4,200,000.00
JUMLAH PEKERJAAN POWER HOUSE 879,242,400.00

1,600,000.00 1,600,000.00
43,500.00 261,000.00
290,000.00 1,740,000.00
550,000.00 1,100,000.00
249,500.00 499,000.00
615,000.00 615,000.00
594,000.00 594,000.00
594,000.00 594,000.00
594,000.00 594,000.00
594,000.00 594,000.00
594,000.00 594,000.00
594,000.00 594,000.00
594,000.00 594,000.00
5,124,350.00 5,124,350.00
1,500,000.00 1,500,000.00
1,500,000.00 1,500,000.00

1,600,000.00 1,600,000.00
43,500.00 130,500.00
290,000.00 290,000.00
550,000.00 550,000.00
249,500.00 249,500.00
249,500.00 249,500.00
594,000.00 594,000.00
HARGA SATUAN JUMLAH HARGA
( Rp. ) ( Rp. )
297,000.00 297,000.00
750,000.00 750,000.00
1,500,000.00 1,500,000.00

1,600,000.00 1,600,000.00
43,500.00 130,500.00
290,000.00 290,000.00
550,000.00 550,000.00
249,500.00 249,500.00
249,500.00 249,500.00
594,000.00 594,000.00
297,000.00 297,000.00
750,000.00 750,000.00
1,500,000.00 1,500,000.00

1,600,000.00 1,600,000.00
43,500.00 130,500.00
290,000.00 290,000.00
550,000.00 550,000.00
249,500.00 249,500.00
249,500.00 249,500.00
594,000.00 594,000.00
297,000.00 297,000.00
750,000.00 750,000.00
1,500,000.00 1,500,000.00

1,600,000.00 1,600,000.00
43,500.00 130,500.00
290,000.00 290,000.00
550,000.00 550,000.00
249,500.00 249,500.00
249,500.00 249,500.00
594,000.00 594,000.00
297,000.00 297,000.00
750,000.00 750,000.00
1,500,000.00 1,500,000.00
JUMLAH PEKERJAAN PANEL 42,939,350.00

290,520.00 39,220,200.00
290,520.00 9,877,680.00
76,500.00 1,147,500.00
51,360.00 3,081,600.00
51,360.00 1,284,000.00
51,360.00 1,438,080.00
51,360.00 1,232,640.00
HARGA SATUAN JUMLAH HARGA
( Rp. ) ( Rp. )
51,360.00 1,232,640.00
JUMLAH PEKERJAAN PENGKABELAN 58,514,340.00

268,000.00 34,840,000.00
268,000.00 12,864,000.00
JUMLAH PEKERJAAN KABEL TRAY 47,704,000.00

260,000.00 69,680,000.00
780,000.00 14,040,000.00
260,000.00 18,200,000.00
30,900.00 2,163,000.00
30,900.00 1,792,200.00
30,900.00 1,050,600.00
49,000.00 4,410,000.00
450,000.00 6,750,000.00
350,000.00 4,200,000.00
1,400,000.00 5,600,000.00
880,000.00 72,160,000.00
660,000.00 13,200,000.00
665,000.00 26,600,000.00
330,000.00 4,620,000.00
262,000.00 6,288,000.00
5,800,000.00 278,400,000.00
10,500,000.00 105,000,000.00
13,900,000.00 250,200,000.00
2,300,000.00 18,400,000.00
1,500,000.00 6,000,000.00
19,200,000.00 76,800,000.00
LASI ELEKTRIKAL, PENERANGAN, ARMATUR & FIGTURE 985,553,800.00

23,741,025.00 23,741,025.00
62,600.00 5,759,200.00
600,000.00 600,000.00
670,000.00 670,000.00
1,750,000.00 3,500,000.00
3,750,000.00 3,750,000.00
1,750,000.00 1,750,000.00
4,200,000.00 4,200,000.00
320,000.00 960,000.00
86,557.50 865,575.00
2,000,000.00 2,000,000.00
2,600,000.00 2,600,000.00
JUMLAH PEKERJAAN PENYALUR PETIR & PENTANAHAN 50,395,800.00
HARGA SATUAN JUMLAH HARGA
( Rp. ) ( Rp. )
968,000.00 7,744,000.00
666,000.00 5,328,000.00
260,000.00 260,000.00
5,650,000.00 5,650,000.00
3,940,000.00 7,880,000.00
4,320,000.00 4,320,000.00
3,600,000.00 3,600,000.00
5,600,000.00 5,600,000.00
1,640,000.00 3,280,000.00
585,000.00 1,170,000.00
12,600,000.00 12,600,000.00
2,600,000.00 2,600,000.00
UMLAH PEKERJAAN SOUND SYSTEM PUBLIC ADDRESS 60,032,000.00

1,450,000.00 23,200,000.00
7,585,000.00 7,585,000.00
8,365,000.00 8,365,000.00
JUMLAH PEKERJAAN CCTV 39,150,000.00

225,000,000.00 450,000,000.00

6,250,000.00 12,500,000.00
36,600,000.00 36,600,000.00
UMLAH PEKERJAAN PAPAN SCORE ( SCORING BOARD ) 499,100,000.00

64,500,000.00 64,500,000.00

18,500,000.00 18,500,000.00
16,500,000.00 33,000,000.00

32,500,000.00 65,000,000.00

3,500,000.00 7,000,000.00
4,357,500.00 26,145,000.00

153,300.00 12,264,000.00
140,000.00 560,000.00
187,000.00 748,000.00
137,000.00 1,096,000.00
1,350,000.00 2,700,000.00

239,600.00 7,188,000.00
153,300.00 6,760,530.00
103,000.00 9,599,600.00
70,100.00 5,148,845.00
HARGA SATUAN JUMLAH HARGA
( Rp. ) ( Rp. )
48,800.00 3,527,752.00
39,500.00 8,840,890.00
196,290.00 196,290.00

162,000.00 324,000.00

1,262,000.00 7,572,000.00
JUMLAH INSTALASI AIR BERSIH 280,670,907.00

46,200.00 1,386,000.00
82,200.00 6,165,000.00
127,000.00 42,557,700.00
185,600.00 2,227,200.00

29,700.00 1,306,800.00
35,900.00 2,943,800.00
57,400.00 1,377,600.00

146,700.00 880,200.00
171,700.00 1,717,000.00

5,732,525.32 11,465,050.64
10,818,353.74 21,636,707.48
JUMLAH INSTALASI AIR KOTOR & AIR BEKAS 93,663,058.13

5,702,100.00 28,510,500.00

5,920,000.00 41,440,000.00

6,137,900.00 12,275,800.00

JUMLAH PEKERJAAN TATA UDARA 82,226,300.00


D E D RE-DESAIN PASAR SAY
PEMERINTAH KOTA BATU
DINAS PEKERJAAN UMUM
CIPTA KARYA DAN TATA RUAN
Jl. Panglima Sudirman No.507, Balai Among Tani Gedun

KEGIATAN
: PERENCANAAN PEMBANGUNAN PASAR KOTA BATU
PEKERJAAN : PERENCANAAN DED
LOKASI : Jl. DEWI SARTIKA, KOTA BATU
TAHUN : 2016
PASAR SAYUR KOTA BATU
MERINTAH KOTA BATU
AS PEKERJAAN UMUM
KARYA DAN TATA RUANG
7, Balai Among Tani Gedung C lantai 2, Kota Batu

AR KOTA BATU
RE-DESAIN PASAR SAYUR KOTA SURABAYA

PEMERINTAH KOTA SURABAYA


DINAS PEKERJAAN UMUM
CIPTA KARYA DAN TATA RUANG
Jl. Pawiyatan No.11, Bubutan, Kota SBY, Jawa Timur 60174

KEGIATAN
: PEMBANGUNAN PASAR UNIT SAYUR KOTA SURABAYA
PEKERJAAN : PEMBANGUNAN PASAR UNIT SAYUR KOTA SURABAYA
LOKASI : JL. GUBENG KERTAJAYA - KOTA SURABAYA
TAHUN : 2018
R SAYUR KOTA SURABAYA

INTAH KOTA SURABAYA


AS PEKERJAAN UMUM
KARYA DAN TATA RUANG
1, Bubutan, Kota SBY, Jawa Timur 60174

NAN PASAR UNIT SAYUR KOTA SURABAYA


REKAPITULASI H P S
PROGRAM : PEMBANGUNAN PASAR UNIT SAYUR KOTA SURABAYA
KEGIATAN : PEMBANGUNAN PASAR UNIT SAYUR KOTA SURABAYA
PEKERJAAN : PERENCANAAN D E D
LOKASI : JL. GUBENG KERTAJAYA - KOTA SURABAYA
TH. ANGGARAN : 2018

No. URAIAN PEKERJAAN JUMLAH

I. PEKERJAAN PERSIAPAN Rp. Err:509


II. PEKERJAAN URUGAN DAN GALIAN Rp. Err:509
III. PEKERJAAN PASANGAN Rp. 2,186,041,464.56
IV. PEKERJAAN BETON Rp. #REF!
V. PEK. KUSEN, JENDELA, PINTU DAN ASSESORIES Rp. 1,608,477,132.17
VI. PEKERJAAN PENGECATAN Rp. 219,250,696.86
VII. PEKERJAAN ELEKTRIKAL Rp. 280,974,606.90
VIII. PEKERJAAN MECHANICAL Rp. Err:509
IX. PEKERJAAN KERAMIK Rp. 1,076,088,108.00
X. PEKERJAAN SANITASI DAN PLUMBING Rp. #REF!
XI. PEKERJAAN LAIN - LAIN Rp. Err:509
TOTAL Rp. Err:509
Ppn 10% Rp. Err:509
Jumlah Rp. Err:509
Pembulatan Rp. Err:509

SEBELAS MILYAR SERATUS TIGA PULUH TIGA JUTA SEMBILAN RATUS


TERBILANG :
DELAPAN PULUH LIMA RIBU RUPIAH

Surabaya, 23 September 2018

Pejabat Pelaksana Teknis Kegiatan Di bantu di Susun oleh


(PPTK) PT. BAGIYO CONSULTANT
Dinas Pekerjaan Umum Cipta Karya dan Selaku Konsultan Perencana
Tata Ruang

MUCHAMMAD NOOR, ST MUHAMMAD FARUQ


NIP. 19710512 200604 1 014 DIREKTUR UTAMA
Pemberi Pertimbangan Teknis
Menetapkan dan Mengesahkan : Penyusunan HPS
Pejabat Pembuat Komitmen ( PPK ) Tim Ahli Bangunan Gedung
Bidang Cipta Karya 2016 Institut Teknologi Sepuluh November
Dinas Cipta Karya Dan Tata Ruang Kota Surabaya
Batu

NUGROHO WIDYANTO, ST,MT. Ir. Achmad Faiz Hadi. P, MT


NIP. 19700805 200312 1 003 NIP. 19630310 198903 1 004
Team Leader
PITULASI H P S

JUMLAH

AR SERATUS TIGA PULUH TIGA JUTA SEMBILAN RATUS


DELAPAN PULUH LIMA RIBU RUPIAH

Surabaya, 23 September 2018

Di bantu di Susun oleh


PT. BAGIYO CONSULTANT
Selaku Konsultan Perencana

MUHAMMAD FARUQ
DIREKTUR UTAMA
HARGA PERKIRAAN SENDIRI ( H
PROGRAM : PEMBANGUNAN PASAR BATU UNIT SAYUR KOTA SURABAYA
KEGIATAN : PEMBANGUNAN PASAR BATU UNIT SAYUR KOTA SURABAYA
PEKERJAAN : PEMBANGUNAN PASAR BATU UNIT SAYUR KOTA SURABAYA
LOKASI : JL. GUBENG KERTAJAYA - KOTA SURABAYA
TH. ANGGARAN : 2018

No. URAIAN PEKERJAAN VOLUME SAT

I. PEKERJAAN PERSIAPAN
1 Papan Nama proyek 1.00 ls
2 Pembuatan bouwplank 294.00 m1
3 Err:509 298.00 m1
4 Pembersihan lokasi awal s/d akhir pekerjaan 432.00 m²
5 Listrik dan Air Kerja 6.00 bln
6 Perbaikan Kembali Akses Jalan dan Saluran 1.00 ls
7 Mobilisasi Demobilisasi Bahan dan Peralatan 1.00 ls
8 Err:509 90.00 Err:509
9 Err:509 18.00 Err:509
10 Err:509 324.00 Err:509
11 Err:509 2,002.00 Err:509
12 Pengganti BPJS 1.00 ls
JUMLAH PEKERJAAN P
II. PEKERJAAN URUGAN DAN GALIAN
1 Galian Tanah 335.66 m³
2 Urugan Pasir , t = 5 cm 8.56 m³
3 Urugan Kembali 584.39 m³
4 Err:509 472.50 m³
JUMLAH PEKERJAAN URUGAN DA
III. PEKERJAAN PASANGAN
1 Pondasi Batu kali, lebar atas = 30 cm 7.92 m³
2 Pasangan Batu Kosong 3.60 m³
3 Err:509 3,751.43 m2
4 Err:509 7,566.86 m2
5 Err:509 7,566.86 m2
6 Err:509 14,489.60 m'
JUMLAH PEKERJAAN P
IV. PEKERJAAN BETON
1 Pondasi footplat
- Pondasi Pile Cap Type A 29.95 m³
- Pondasi Pile Cap Type B 0.70 m³
2 Lantai kerja beton K 150, t = 5 cm
- Lantai kerja beton untuk Pile Cap Type A 7.49 m³
- Lantai kerja beton untuk Pile Cap Type B 0.18 m³
3 Plat lantai beton , t = 13 cm 252.00 m³
No. URAIAN PEKERJAAN VOLUME SAT

4 Beton Sloof
- SLOOF 30 X 50 CM 50.44 m³
5 Beton Kolom
- KOLOM PENDEK 20 X 20 cm 10.30 m³
- KOLOM PENDEK 15 X 15 cm 0.24 m³
- KOLOM STRUKTUR 20 X 20 cm 34.16 m³
6 Err:509
- Err:509 40.35 m³
- Err:509 408.00 m'
7 Beton Balok 2.43 m'
8 Beton Bertulang Plat Atap
- Beton Bertulang Plat atap t = 13 cm 168.12 m³
9 Beton untuk tangga, t = 13 cm 1.39 m³
JUMLAH PEKERJA
No. URAIAN PEKERJAAN VOLUME SAT

V. PEK. KUSEN, JENDELA, PINTU DAN ASSESORIES


1 - 134.00 unit
2 - 15.25 m2
3 Err:509 8.10 Err:509
4 Err:509 27.20 Err:509
5 Pasang kunci tanam biasa 10.00 bh
6 Pasang engsel pintu 10.00 bh
JUMLAH PEKERJAAN KUSEN, JENDELA, PINTU DAN A
VI. PEKERJAAN PENGECATAN
1 Pengecatan Dinding Baru Luar 2,795.43 m²
2 Pengecatan Dinding Baru Dalam 2,795.43 m²
3 Pengecatan dak beton 2,566.58 m²
JUMLAH PEKERJAAN PEN
VII. PEKERJAAN ELEKTRIKAL
1 Panel Bekisting Pile Cap 2.00 buah
2 Instalasi penerangan 229.00 titik
3 Instalasi stop kontak 136.00 titik
4 Stop kontak 136.00 unit
5 Saklar tunggal 136.00 unit
6 Saklar ganda 10.00 unit
7 Rumah dan Fiting Lampu 229.00 titik
8 Lampu LED 13 WATT 83.00 Err:509
9 Err:509 8.00 Err:509
10 Err:509 138.00 Err:509
11 - 75.00 m1
JUMLAH PEKERJAAN EL
VIII. PEKERJAAN MECHANICAL
1 Pemasangan dan Pengadaan Hydrant Pillar (HP) 4.00 titik
2 Pemasangan dan Pengadaan VALVE-VALVE & FIXTURES dia 100 mm 4.00 titik
3 Pemasangan dan Pengadaan Hose Reel Cabinet ( HRC ) 4.00 titik
4 Instalasi Pipa Hydrant 323.40 m'
5 Galian Pipa Hydrant 77.62 m3
JUMLAH PEKERJAAN ME
IX. PEKERJAAN KERAMIK
1 - 2,648.00 m2
2 - 2,392.00 m2
3 - 60.00 m2
4 Pasang Lantai keramik ukuran 40 x 40 cm motif untuk tangga 108.00 m2
JUMLAH PEKERJAAN
X. PEKERJAAN SANITASI DAN PLUMBING
1 Closed Jongkok 8.00 0
2 Kran Air 8.00 0
3 Pipa untuk air bersih 88.00 0
4 Pipa untuk air kotor 575.30 0
5 Pipa untuk kotoran 22.00 0
No. URAIAN PEKERJAAN VOLUME SAT

6 ### 28.00 0
7 ### 46.00 0
8 Memasang 1 unit septictank kapasitas 50 orang 2.00 unit
JUMLAH PEKERJAAN SANITASI DAN
PEKERJAAN ATAP BAJA RINGAN
1 ###
2 ###
JUMLAH PEKERJAAN ATAP BAJ
XI. PEKERJAAN LAIN - LAIN
1 Pembuatan Papan Nama "Pasar Sayur" 1.00 ls
2 ### 136.08 m2
3 ### 10.00 unit
4 Pasang Tanggulan Bata Keliling Atap tinggi 10 cm 488.00 m'
5 Pemasangan Bak kontrol uk. 120 X 75 X 100 cm 20.00 0
6 Pemasangan plat beton tutup bak kontrol uk. 120 X 75 X 12 cm 20.00 0
7 ### 286.80 0
8 ### 286.80 0
9 ### 8.60 0
10 ### 163.20 0
11 ### 79.80 0
12 ### 760.50 0
13 ### 1,527.86 m2
14 ### 2,566.58 0
PEKERJAAN L

GRAND TOTA
KIRAAN SENDIRI ( H P S )

HARGA SATUAN
JUMLAH HARGA
( Rp. )

1,500,000.00 Rp 1,500,000.00
33,755.00 Rp 9,923,970.00
Err:509 Rp Err:509
23,850.00 Rp 10,303,200.00
3,500,000.00 Rp 21,000,000.00
28,000,000.00 Rp 28,000,000.00
78,000,000.00 Rp 78,000,000.00
Err:509 Rp Err:509
Err:509 Rp Err:509
Err:509 Rp Err:509
Err:509 Rp Err:509
25,000,000.00 Rp 25,000,000.00
JUMLAH PEKERJAAN PERSIAPAN Rp Err:509

187,965.00 Rp 63,091,805.60
46,770.00 Rp 400,491.51
38,969.10 Rp 22,772,986.08
Err:509 Rp Err:509
JUMLAH PEKERJAAN URUGAN DAN GALIAN Rp Err:509

263,625.00 Rp 2,087,910.00
500,454.00 Rp 1,801,634.40
165,934.00 Rp 622,489,785.62
84,643.00 Rp 640,481,730.98
48,286.00 Rp 365,373,401.96
38,221.00 Rp 553,807,001.60
JUMLAH PEKERJAAN PASANGAN Rp 2,186,041,464.56

Err:509 Rp Err:509
Err:509 Rp Err:509
Rp
311,422.00 Rp 2,331,927.94
311,422.00 Rp 54,498.85
311,422.00 Rp 78,478,344.00
HARGA SATUAN
JUMLAH HARGA
( Rp. )

#REF! Rp #REF!

#REF! Rp #REF!
#REF! Rp #REF!
#REF! Rp #REF!

#REF! Rp #REF!
118,717.00 Rp 48,436,536.00
118,717.00 Rp 288,482.31

4,868,005.00 Rp 818,409,000.60
4,868,005.00 Rp 6,776,262.96
JUMLAH PEKERJAAN BETON Rp #REF!
HARGA SATUAN
JUMLAH HARGA
( Rp. )

11,887,522.50 Rp 1,592,928,015.00
423,621.70 Rp 6,460,230.93
163,185.80 Rp 1,321,804.98
163,185.80 Rp 4,438,653.76
235,655.00 Rp 2,356,550.00
97,187.75 Rp 971,877.50
EKERJAAN KUSEN, JENDELA, PINTU DAN ASSESORIES Rp 1,608,477,132.17

30,400.60 Rp 84,982,749.26
25,040.60 Rp 69,999,244.46
25,040.60 Rp 64,268,703.15
JUMLAH PEKERJAAN PENGECATAN Rp 219,250,696.86

34,254,000.00 Rp 68,508,000.00
460,459.06 Rp 105,445,124.74
422,959.06 Rp 57,522,432.16
28,000.00 Rp 3,808,000.00
18,000.00 Rp 2,448,000.00
51,000.00 Rp 510,000.00
120,000.00 Rp 27,480,000.00
88,000.00 Rp 7,304,000.00
50,000.00 Rp 400,000.00
27,000.00 Rp 3,726,000.00
50,974.00 Rp 3,823,050.00
JUMLAH PEKERJAAN ELEKTRIKAL Rp 280,974,606.90

2,327,775.00 Rp 9,311,100.00
2,634,327.00 Rp 10,537,308.00
3,306,825.00 Rp 13,227,300.00
272,825.00 Rp 88,231,605.00
Err:509 Rp Err:509
JUMLAH PEKERJAAN MECHANICAL Rp Err:509

48,286.00 Rp 127,861,328.00
371,485.00 Rp 888,592,120.00
325,238.00 Rp 19,514,280.00
371,485.00 Rp 40,120,380.00
JUMLAH PEKERJAAN KERAMIK Rp 1,076,088,108.00

698,880.00 Rp 5,591,040.00
175,292.50 Rp 1,402,340.00
49,340.60 Rp 4,341,972.80
86,700.20 Rp 49,878,625.06
124,409.15 Rp 2,737,001.30
HARGA SATUAN
JUMLAH HARGA
( Rp. )
66,255.00 Rp 1,855,140.00
326,000.00 Rp 14,996,000.00
#REF! Rp #REF!
JUMLAH PEKERJAAN SANITASI DAN PLUMBING Rp #REF!

JUMLAH PEKERJAAN ATAP BAJA RINGAN Rp -

30,000,000.00Rp 30,000,000.00
481,247.00Rp 65,488,091.76
11,174,653.20Rp 111,746,532.00
16,593.40Rp 8,097,579.20
301,760.00Rp 6,035,200.00
513,021.04Rp 10,260,420.87
476,077.13Rp 136,538,919.93
848,238.47Rp 243,274,794.15
46,770.00Rp 402,409.08
126,210.00Rp 20,597,472.00
165,934.00Rp 13,241,533.20
Err:509 Rp Err:509
87,165.00 Rp 133,175,813.98
48,286.00 Rp 123,929,881.88
PEKERJAAN LAIN - LAIN Rp Err:509

GRAND TOTAL Rp Err:509


NAMA KEGIATAN : PEMBANGUNAN PASAR UNIT SAYUR KOTA SURABAYA BULAN

LOKASI : JL. GUBENG KERTAJAYA - KOTA SURABAYA DANA DITERIM


BESARAN DANA

Bobot BU
No Uraian Pekerjaan Harga (Rp) Pekerjaan %
M
1

I PEKERJAAN PERSIAPAN Err:509 Err:509 Err:509

II PEKERJAAN URUGAN DAN GALIAN Err:509 Err:509

III PEKERJAAN PASANGAN 2,186,041,464.56 Err:509

IV PEKERJAAN BETON #REF! #REF!

V PEK. KUSEN, JENDELA, PINTU DAN ASS 1,608,477,132.17 Err:509

VI PEKERJAAN PENGECATAN 219,250,696.86 Err:509

VII PEKERJAAN ELEKTRIKAL 280,974,606.90 Err:509

VIII PEKERJAAN MECHANICAL Err:509 Err:509

IX PEKERJAAN LANTAI 1,076,088,108.00 Err:509

X PEKERJAAN SANITASI DAN PLUMBING #REF! #REF!

XI PEKERJAAN LAIN - LAIN Err:509 Err:509


JUMLAH Err:509 Err:509
JUMLAH DIBULATKAN Err:509
Rencana Kemajuan Pekerjaan Mingguan (%) Err:509
Rencana Kemajuan Pekerjaan Komulatif (%) 0 Err:509
Bobot BU
No Uraian Pekerjaan Harga (Rp) Pekerjaan %

Mengetahui ,

Pejabat Pelaksana Teknis Kegiatan


(PPTK)
Dinas Pekerjaan Umum Cipta Karya dan
Tata Ruang

MUCHAMMAD NOOR, ST
NIP. 19710512 200604 1 014
TIME SCHEDULE

: BULAN KE I - BULAN KE V

ANA DITERIMA TANGGAL :


ESARAN DANA Err:509 (DI LUAR PPN)

BULAN I BULAN II BULAN III

MINGGU MINGGU MINGGU


2 3 4 5 6 7 8 9 10 11

Err:509 Err:509 Err:509 Err:509 Err:509 Err:509

Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509

Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509

#REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!

Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509

Err:509 Err:509 Err:509

Err:509 #REF! #REF! Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509
Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509
BULAN I BULAN II BULAN III

Menyetujui ,

Menetapkan dan Mengesahkan :


Pejabat Pembuat Komitmen ( PPK )
Bidang Cipta Karya 2016
Dinas Cipta Karya Dan Tata Ruang Kota Batu

NUGROHO WIDYANTO, ST.,MT.


NIP. 19700805 200312 1 003
N III BULAN IV BULAN V
KET
GU MINGGU MINGGU
12 13 14 15 16 17 18 19 20
100

Err:509 Err:509 Err:509 Err:509 Err:509 Err:509

#REF! #REF! #REF! #REF! #REF! #REF!

Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509

Err:509 Err:509 Err:509 Err:509 Err:509

Err:509 Err:509 Err:509

Err:509 Err:509 Err:509

Err:509 Err:509 Err:509 Err:509 Err:509 Err:509

#REF! #REF! #REF! #REF!

Err:509 Err:509 Err:509 0

Err:509 Err:509 Err:509 Err:509 Err:509 #REF! Err:509 Err:509 Err:509


Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509
N III BULAN IV BULAN V
KET
Surabaya, 23 September 2018
Di bantu di susun oleh

PT.BAGIYO CONSULTANT
Selaku Konsultan Perencana

MUHAMMAD FARUQ
DIREKTUR UTAMA
DAFTAR HARGA SATUAN BAHA
PROGRAM : PEMBANGUNAN PASAR BATU UNIT SAYUR KOTA SURA
KEGIATAN : PEMBANGUNAN PASAR BATU UNIT SAYUR KOTA SURA
PEKERJAAN : PEMBANGUNAN PASAR BATU UNIT SAYUR KOTA SURA
LOKASI : JL. GUBENG KERTAJAYA - KOTA SURABAYA
TH. ANGGARAN : 2018

NO JENIS UPAH, BAHAN, ALAT, SPESIFIKASI, DAN M

A UPAH
1 Pekerja / Pembantu Tukang
2 Mandor
3 Tukang Batu
4 Kepala Tukang batu
5 Tukang Kayu
6 Kepala Tukang Kayu
7 Tukang Besi
8 Kepala Tukang Besi
9 Tukang Cat
10 Kepala Tukang Cat
11 Tukang Pipa
12 Kepala Tukang Pipa
13 Tukang Listrik
14 Kepala Tukang Listrik

B BAHAN PEKERJAAN SIPIL DAN STRUKTUR


1 Pasir Urug
2 Sirtu
3 Pasir Cor / Beton
4 Pasir Pasang
5 Bata Merah
6 Batu Pecah 2/3 ( pecah mesin )
7 Batu Pecah 5/7
8 Batu Kali / Gunung Belah
9 Batu Alam
10 Semen Portland
11 Semen Warna
12 Besi Beton Polos
NO JENIS UPAH, BAHAN, ALAT, SPESIFIKASI, DAN M

13 Besi Beton Ulir


14 Besi Profil ( IWF, CNP, Siku, Plate, Pipa )
15 Pipa Stain less Dia. 4" t = 3,2 mm (Roll)
16 Dynabolt
17 Mur Baut ( HTB )
18 Atap Baja Ringan
19 Penutup Atap Zincalume + Peredam
20 Roofmesh
21 Paku
22 Kawat Beton
23 Kayu Dolken / Galam Ø 10 cm - 4 m
24 Kayu Begesting Kl. IV
25 Papan Begesting Kl. IV
26 Kayu Meranti / Kruing
27 Papan Kayu Kamper
28 Triplek 4 mm
29 Multiplek 9 mm
30 Minyak Begisting
31 Beton Ready Mix K 275
32 Beton Ready Mix K 300
33 Beton Ready Mix K 350
34 Atap Spandek tebal 0,45
35 Plat beton tutup Bak Kontrol uk 120x75x12
36 Plat beton tutup U-ditch uk 68x120x12
37 Saluran U ditch uk 50x50 cm
38 Cover bak kontrol uk. 120X75X10
39 Besi Strip
40 Pipa 4"
41 Pipa 2"
42 Ball joint diameter 3"
43 Paving tebal 8 cm K-500
NO JENIS UPAH, BAHAN, ALAT, SPESIFIKASI, DAN M

C BAHAN PEKERJAAN ARSITEKTUR


1 Keramik Lantai 40 x 40 motif
2 Keramik Lantai40 x 40 polos
3 Keramik Lantai 20 x 25
4 Cat Dasar
5 Cat Dinding Eksterior ( weather shield )
6 Cat Dinding Interior
7 Cat Minyak / Besi
8 Zincromate / Meni Besi
9 Cat Duco
10 Kusen Aluminium 4' Natural
11 ACP ( aluminium composite panel ) Outdoor 4mm tct
12 0.5 mm, PVDF clear coating anti scratch alloy 3003
13 Seng Gelombang
14 Jendela Naco Uk. 15 cm x 90 Cm
15 Kunci Tanam
16 Paku skrup 3,5"
17 Sealant
18 Minyak Cat / Afduner
19 Kertas Gosok
20 Besi Hollow 40/40
21 Besi Hollow 20/40
22 Pintu Rolling Door
23 Pintu PVC
24 Engsel Pintu
D BAHAN PEKERJAAN MEKANIKAL
1 Roof Drain Diecast Iron
2 Coating Sikatop 107
3 Kuas
4 Kloset jongkok
5 Pipa PVC tipe AW Ø 1/2"
6 Pipa PVC tipe AW Ø 4 "
7 Pipa PVC tipe AW Ø 6 "
8 Kran air
9 floor drain
10 Roof Drain Diecast Iron
11 Memasang 1 unit septictank kapasitas 50 orang
NO JENIS UPAH, BAHAN, ALAT, SPESIFIKASI, DAN M

12 Saluran U ditch uk 50x50 cm


13 Kloset Jongkok Teraso

E BAHAN PEKERJAAN ELEKTRIKAL DAN ELEKTRONIK


Kabel Elektrik dan Elektronik
NYY
1 - 4×6 mm2 0,6/1 kV
NYA
2 - 1×2,5 mm2 450/700 V
3 - Lampu led 7 Watt
4 - Lampu Led 4 Watt
5 - Rumah dan Fiting Lampu
6 - Lampu LED 13 watt
Type BC
7 - 1x6 mm2
NYM
8 - 3×2,5 mm2 300/500 V
9 Stop Kontak
10 Saklar Tunggal
11 Saklar Double
12 Isolator
13 Las Doof
14 Konduit dia 20 mm (3/4")
15 Claim conduit
16 Box Panel 50 x 40 x 25 cm dan aksesoris lainnya
17 MCB 40A/3P, 10 kA
NO JENIS UPAH, BAHAN, ALAT, SPESIFIKASI, DAN M

18 MCB 16A/1P, 6kA


19 Pilot Lamp RST+Fuse
20 Volt Meter
21 SSV
22 Ampere Meter
23 Shunt Trip
24 CT
25 Busbar
26 Pipa Diameter 100 mm
27 VALVE-VALVE & FIXTURES dia 100 mm
28 Hose Reel Cabinet ( HRC )
29 Hydrant Pillar (HP)
30 Flange
31 Inbow doos

E PERALATAN MEKANIK
1 Dozer
2 Excavator
3 Wheel Loader
4 Motor Grader
5 Vibro Roller
6 Water Tanker
7 Dump Truck
8 Crane
9 Jack In pile
10 Genset type Silent
11 Pompa Air Mesin
12 Throwel
13 Vibrator
14 Molen
15 Survey ( Waterpass, Theodolit, dan Total Station )
16 PDA test
R HARGA SATUAN BAHAN DAN UPAH
UNAN PASAR BATU UNIT SAYUR KOTA SURABAYA
UNAN PASAR BATU UNIT SAYUR KOTA SURABAYA
UNAN PASAR BATU UNIT SAYUR KOTA SURABAYA
G KERTAJAYA - KOTA SURABAYA

HARGA SATUAN
BAHAN, ALAT, SPESIFIKASI, DAN MERK SATUAN
( Rp. )

Hari 150,000.00
Hari 177,000.00
Hari 161,000.00
Hari 177,000.00
Hari 161,000.00
Hari 177,000.00
Hari 161,000.00
Hari 177,000.00
Hari 161,000.00
Hari 177,000.00
Hari 161,000.00
Hari 177,000.00
Hari 161,000.00
Hari 177,000.00

PIL DAN STRUKTUR


ex. Lokal terbaik m³ 183,000.00
ex. Lokal terbaik m³ 212,000.00
ex. Lokal terbaik m³ 281,000.00
ex. Lokal terbaik m³ 281,000.00
ex. Lokal terbaik buah 1,000.00
ex. Lokal terbaik m³ 284,000.00
ex. Lokal terbaik m³ 284,000.00
ex. Lokal terbaik m³ 466,000.00
ex. Lokal terbaik m² 114,000.00
ex. Semen Indonesia,Tiga Roda, Gresik, Holcim kg 2,000.00
ex. Semen Indonesia,Tiga Roda, Gresik, Holcim kg 3,000.00
ex. Bhirawa, Hanil, Master Steel, setara kg 14,000.00
HARGA SATUAN
BAHAN, ALAT, SPESIFIKASI, DAN MERK SATUAN
( Rp. )
ex. Bhirawa, Hanil, Master Steel, setara kg 15,000.00
ex. KS, Gunung Garuda kg 13,000.00
ex. Lokal terbaik kg 21,000.00
ex. KS, Gunung Garuda kg 27,000.00
ex. KS, Gunung Garuda kg 38,000.00
ex. Smart Truss, Pryda kg 25,000.00
m2 326,000.00
m2 134,000.00
ex. Lokal terbaik kg 16,000.00
ex. Lokal terbaik kg 28,000.00
ex. Lokal terbaik batang 12,000.00
ex. Lokal terbaik m³ -
ex. Lokal terbaik m³ 4,324,000.00
ex. Lokal terbaik m³ 3,459,000.00
ex. Lokal terbaik m³ 9,762,000.00
ex. Lokal terbaik lembar 66,000.00
ex. Lokal terbaik lembar 166,000.00
ex. Lokal terbaik ltr 31,000.00
ex. Lokal terbaik m³ 890,000.00
ex. Lokal terbaik m³ 899,000.00
ex. Lokal terbaik m³ 946,000.00
ex. Lokal terbaik lembar 77,000.00
ex. Lokal terbaik bh 523,000.00
ex. Lokal terbaik bh 482,000.00
ex. Lokal terbaik bh 895,000.00
ex. Lokal terbaik bh 243,000.00
ex. Lokal terbaik kg 18,000.00
330,000.00
60,000.00
232,000.00
99,000.00
HARGA SATUAN
BAHAN, ALAT, SPESIFIKASI, DAN MERK SATUAN
( Rp. )

ex. KIA, Platinum, Roman m² 146,000.00


ex. KIA, Platinum, Roman m² 95,000.00
ex. KIA, Platinum, Roman m² 67,000.00
ex. Dulux, Jotun, Mowilex kg 28,000.00
ex. Dulux, Jotun, Mowilex kg 45,000.00
ex. Dulux, Jotun, Mowilex kg 29,000.00
ex. Nippon Paint, Emco, Avian kg 65,000.00
ex. Nippon Paint, Emco, Avian kg 43,000.00
kg 34,000.00
ex. Indal, Alexindo m' 131,000.00
ex. Seven, Alcopanel, Alucopan m² 361,000.00
-
ex. Lokfom, Fumira, setara lembar 65,000.00
Bh 43,000.00
Bh 151,000.00
bh 1,000.00
tube 43,000.00
liter 8,000.00
lembar 21,000.00
m' 100,000.00
m' 72,000.00
unit 9,204,000.00
bh 342,000.00
bh 68,000.00

ex. Antasan, SanEi, setara 316,000.00


kg 93,000.00
bh 36,000.00
bh 459,000.00
m' 7,000.00
m' 21,000.00
m' 37,000.00
bh 155,000.00
bh 46,000.00
bh 316,000.00
unit 13,679,000.00
HARGA SATUAN
BAHAN, ALAT, SPESIFIKASI, DAN MERK SATUAN
( Rp. )
bh 924,000.00
bh 213,000.00

EKTRIKAL DAN ELEKTRONIK

ex. Supreme, Kabelindo, Kabel Metal, Jembo m' 31,000.00


-
ex. Supreme, Kabelindo, Kabel Metal, Jembo m' -
ex. Philip, Artolite, Saka, Osram, setara unit 50,000.00
ex. Philip, Artolite, Saka, Osram, setara unit 27,000.00
unit 120,000.00
unit 88,000.00
-
ex. Supreme, Kabelindo, Kabel Metal, Jembo m' 7,000.00
-
ex. Supreme, Kabelindo, Kabel Metal, Jembo m' 16,000.00
ex. Clipsal, Panasonic, Berker, Legrand, setara unit 28,000.00
ex. Clipsal, Panasonic, Berker, Legrand, setara unit 18,000.00
ex. Clipsal, Panasonic, Berker, Legrand, setara unit 51,000.00
m' 8,000.00
bh 13,000.00
ex. Clipsal, Panasonic, Berker, Legrand, setara m' 4,000.00
bh 400.00
bh 29,363,000.00
bh 737,000.00
HARGA SATUAN
BAHAN, ALAT, SPESIFIKASI, DAN MERK SATUAN
( Rp. )
bh 108,000.00
bh 50,000.00
bh 300,000.00
bh 186,000.00
bh 262,000.00
bh 462,000.00
bh 234,000.00
m 178,000.00
m' 214,000.00
bh 2,560,000.00
lot 3,248,000.00
bh 2,200,000.00
bh 105,000.00
bh 6,000.00

jam -
PC 300 jam 1,267,000.00
hari 5,229,000.00
hari 2,514,000.00
hari 1,234,000.00
hari 1,567,000.00
Light Truck hari -
25 s/d 30 ton jam -
jam -
25 -50 kVA hari -
hari -
hari -
hari -
hari -
hari -
titik -
DAFTAR HARGA SATUAN BAHAN DAN UPAH
PROGRAM : PEMBANGUNAN PASAR KOTA BATU TAHAP I
KEGIATAN : PEMBANGUNAN PASAR KOTA BATU TAHAP I
PEKERJAAN : PEMBANGUNAN PASAR KOTA BATU TAHAP I
LOKASI : Jl. Dewi Sartika , kota Batu
TH. ANGGARAN : 2016

HARGA SURVEI
NO JENIS UPAH, BAHAN, ALAT, SPESIFIKASI, DAN MERK SATUAN
TERTINGGI

A UPAH ssh kota batu


1 Pekerja / Pembantu Tukang Hari 73,295.00
2 Mandor Hari 94,160.00
3 Tukang Batu Hari 73,295.00
4 Kepala Tukang batu Hari 85,600.00
5 Tukang Kayu Hari 80,250.00
6 Kepala Tukang Kayu Hari 85,600.00
7 Tukang Besi Hari 80,250.00
8 Kepala Tukang Besi Hari 85,600.00
9 Tukang Cat Hari 73,295.00
10 Kepala Tukang Cat Hari 85,600.00
11 Tukang Pipa Hari 80,250.00
12 Kepala Tukang Pipa Hari 85,600.00
13 Tukang Listrik Hari 80,250.00
14 Kepala Tukang Listrik Hari 85,600.00

B BAHAN PEKERJAAN SIPIL DAN STRUKTUR


1 Pasir Urug m³ 210,000.00
2 Sirtu m³ 170,000.00
3 Pasir Cor / Beton m³ 300,000.00
4 Pasir Pasang m³ 245,000.00
5 Bata Merah buah 1,100.00
6 Batu Pecah 2/3 ( pecah mesin ) m³ 285,000.00
7 Batu Pecah 5/7 m³ 254,400.00
8 Batu Kali / Gunung Belah m³ 250,000.00
9 Batu Alam m² 145,000.00
10 Semen Portland kg 1,400.00
11 Semen Warna kg 2,250.00
HARGA SURVEI
NO JENIS UPAH, BAHAN, ALAT, SPESIFIKASI, DAN MERK SATUAN
TERTINGGI

12 Besi Beton Polos kg 14,100.00


13 Besi Beton Ulir kg 14,500.00
14 Besi Profil ( IWF, CNP, Siku, Plate, Pipa ) kg 12,100.00
15 Pipa Stain less Dia. 4" t = 3,2 mm (Roll) kg 17,500.00
16 Dynabolt kg 22,800.00
17 Mur Baut ( HTB ) kg 32,000.00
18 Baut D16 bh 22,000.00
19 Angkur D16 bh 125,000.00
20 Paku kg 18,000.00
21 Kawat Beton kg 19,000.00
22 Kayu Dolken / Galam Ø 10 cm - 4 m batang 14,000.00
23 Kayu Begesting Kl. IV m³ 1,850,000.00
24 Papan Begesting Kl. IV m³ 2,050,000.00
25 Kayu Meranti / Kruing m³ 4,500,000.00
26 Papan Kayu Kamper m³ 5,050,000.00
27 Multiplek 9 mm lembar 165,000.00
28 Minyak Begisting ltr 14,000.00
29 Beton Ready Mix K 275 m³ 714,000.00
30 Beton Ready Mix K 300 m³ 790,000.00
31 Beton Ready Mix K 350 m³ 882,000.00
32 Plat beton tutup Bak Kontrol uk 120x75x12 bh 459,360.00
33 Plat beton tutup U-ditch uk 68x120x12 bh 423,360.00
34 Saluran U ditch uk 50x50 cm bh 786,240.00
35 Kaca tempered 8 mm m² 550,000.00
36 Paving tebal 8 cm K-500 m² 137,000.00

C BAHAN PEKERJAAN ARSITEKTUR


HARGA SURVEI
NO JENIS UPAH, BAHAN, ALAT, SPESIFIKASI, DAN MERK SATUAN
TERTINGGI

1 Keramik Lantai40 x 40 m² 131,500.00


Keramik Lantai40 x 40 polos m² 52,500.00
Keramik Lantai 20 x 25 m² 108,000.00
2 Cat Dasar kg 25,000.00
3 Cat Dinding Eksterior ( weather shield ) kg 50,000.00
4 Cat Dinding Interior kg 24,150.00
5 Cat Minyak / Besi kg 54,700.00
6 Zincromate / Meni Besi kg 24,600.00
7 Kusen Aluminium 4' Natural m' 110,000.00
8 ACP ( aluminium composite panel ) Outdoor 4mm tct m² 688,800.00
0.5 mm, PVDF
9 Seng Gelombang lembar 48,000.00
10 Paku skrup 3,5" bh 600.00
11 Sealant tube 37,050.00
12 Minyak Cat / Afduner liter 6,960.00
13 Kertas Gosok lembar 9,600.00
14 Coating Sikatop 107 kg 87,200.00
15 Kuas bh 13,200.00
16 Besi Hollow 40/40/2.3 kg 20,000.00
17 Besi Hollow 20/40/1.0 kg 20,000.00
18 Besi Hollow 50/50/3.2 kg 20,000.00
19 Pintu Rolling Door (2.65 x 3.00 m) termasuk cover Unit 7,791,000.00
20 Pintu PVC bh 250,000.00

D BAHAN PEKERJAAN MEKANIKAL


1 PVC AW 6.00" m' 208,725.00
2 Roof Drain Diecast Iron bh 288,000.00

E BAHAN PEKERJAAN ELEKTRIKAL DAN ELEKTRONIK


Kabel Elektrik dan Elektronik
NYY
- 4×6 mm2 0,6/1 kV m' 26,400.00
NYA
1 - 1×2,5 mm2 450/700 V m' 3,600.00
2 - Lampu LED 7 Watt unit 44,500.00
3 - Lampu LED 4 Watt unit 27,000.00
4 - Lampu LED 13 watt unit 79,000.00
HARGA SURVEI
NO JENIS UPAH, BAHAN, ALAT, SPESIFIKASI, DAN MERK SATUAN
TERTINGGI

5 - Rumah dan Fiting Lampu unit 105,000.00


6 - Lampu Spot LED 12 watt unit 127,000.00

7 Type BC
- 1x6 mm2 m' 6,699.00
8 NYM
- 3×2,5 mm2 300/500 V m' 13,650.00
9 Stop Kontak unit 23,000.00
10 Saklar Tunggal unit 15,000.00
11 Saklar Double unit 21,700.00
12 Isolator m' 500.00
13 Las Doof bh 10,800.00
14 Konduit dia 20 mm (3/4") m' 3,312.00
15 Claim conduit bh 500.00
16 Pipa Diameter 100 mm m' 181,400.00
Bahan Pipa : BSP , Schedule -40
ASTM-53A
17 VALVE-VALVE & FIXTURES dia 100 mm bh 2,442,960.00
Jenis : Gate Valve
WP : 16 Kg/cm² atau 250 psi
18 Hose Reel Cabinet ( HRC ) lot 3,110,250.00
Kelengkapan
Fire Hose with Machino Coupling size 1,5 ", 30 M
Branch Pipe with straight tip nozzle size 1,5", 1pcs
Hydrant Valve 10K size 1,5", 1pcs
Landing valve 10K, VDH size 2,5", 1 pcs

19 Hydrant Pillar (HP) Buah 1,980,000.00


20 Flange Buah 700,000.00
HARGA SURVEI
NO JENIS UPAH, BAHAN, ALAT, SPESIFIKASI, DAN MERK SATUAN
TERTINGGI

F PERALATAN MEKANIK
1 Dozer jam 225,000.00
2 Excavator jam 240,000.00
3 Dump Truck hari 340,000.00
4 Crane jam 120,000.00
5 Jack In pile jam 160,000.00
6 Genset type Silent hari 60,000.00
7 Pompa Air Mesin hari 40,000.00
8 Throwel hari 60,000.00
9 Vibrator hari 120,000.00
10 Molen hari 80,000.00
11 Survey ( Waterpass, Theodolit, dan Total Station ) hari 40,000.00
12 PDA test titik 12,500,000.00
RGA SATUAN BAHAN DAN UPAH

HARGA SURVEI OVER HEAD &


TERENDAH PROFIT 15%

1.15
70,000.00
90,000.00
70,000.00
85,000.00
80,000.00
85,000.00
80,000.00
85,000.00
70,000.00
85,000.00
80,000.00
85,000.00
80,000.00
85,000.00

STRUKTUR
120,000.00 189,750.00
125,000.00 169,625.00
275,000.00 330,625.00
210,000.00 261,625.00
700.00 1,035.00
220,000.00 290,375.00
254,400.00 292,560.00
210,000.00 264,500.00
130,000.00 158,125.00
1,250.00 1,523.75
2,250.00 2,587.50
HARGA SURVEI OVER HEAD &
TERENDAH PROFIT 15%

10,100.00 13,915.00
11,500.00 14,950.00
12,100.00 13,915.00
17,500.00 20,125.00
22,000.00 25,760.00
32,000.00 36,800.00
20,500.00 24,437.50
117,000.00 139,150.00
11,000.00 16,675.00
17,500.00 20,987.50
14,000.00 16,100.00
1,125,000.00 1,710,625.00
2,050,000.00 2,357,500.00
4,050,000.00 4,916,250.00
4,950,000.00 5,750,000.00
115,000.00 161,000.00
13,000.00 15,525.00
700,000.00 813,050.00
714,500.00 865,087.50
742,000.00 933,800.00
421,080.00 506,253.00
388,080.00 466,578.00
720,720.00 866,502.00
540,000.00 626,750.00
125,000.00 150,650.00
HARGA SURVEI OVER HEAD &
TERENDAH PROFIT 15%

120,900.00 145,130.00
39,500.00 52,900.00
52,500.00 92,287.50
21,620.00 26,806.50
25,000.00 43,125.00
24,150.00 27,772.50
54,700.00 62,905.00
23,000.00 27,370.00
110,000.00 126,500.00
580,000.00 729,560.00

45,000.00 53,475.00
600.00 690.00
35,000.00 41,428.75
6,960.00 8,004.00
9,600.00 11,040.00
70,200.00 90,505.00
13,200.00 15,180.00
19,500.00 22,712.50
19,500.00 22,712.50
19,500.00 22,712.50
7,711,500.00 8,913,937.50
210,000.00 264,500.00

L
189,750.00 229,123.13
244,000.00 305,900.00

AL DAN ELEKTRONIK

26,400.00 30,360.00

3,780.00 4,243.50
40,500.00 48,875.00
19,000.00 26,450.00
70,000.00 85,675.00
HARGA SURVEI OVER HEAD &
TERENDAH PROFIT 15%

97,500.00 116,437.50
120,000.00 142,025.00

5,699.00 7,128.85

13,000.00 15,323.75
23,000.00 26,450.00
15,000.00 17,250.00
21,700.00 24,955.00
500.00 575.00
10,800.00 12,420.00
3,312.00 3,808.80
250.00 431.25
178,500.00 206,942.50

1,975,000.00 2,540,327.00

2,360,000.00 3,145,393.75

1,700,000.00 2,116,000.00
350,000.00 603,750.00
HARGA SURVEI OVER HEAD &
TERENDAH PROFIT 15%

220,000.00 255,875.00
230,000.00 270,250.00
330,000.00 385,250.00
110,000.00 132,250.00
180,000.00 195,500.00
60,000.00 69,000.00
40,000.00 46,000.00
60,000.00 69,000.00
120,000.00 138,000.00
80,000.00 92,000.00
40,000.00 46,000.00
13,000,000.00 14,662,500.00
DAFTAR ANALISA
PROGRAM :
KEGIATAN :
PEKERJAAN :
LOKASI :
TH. ANGGARAN :

No URAIAN PEKERJAAN

A Analisa Biaya Konstruksi Pekerjaan Persiapan


1 Err:509
2 Pengukuran dan Pemasangan Bouwplank / M1
3 Err:509
4 Err:509
5 Membersihkan Lapangan dan Peralatan / M2
6 Err:509
7 Err:509
B Analisa Biaya Konstruksi Pekerjaan Tanah
8 Galian Tanah
9 Err:509
10 Urugan Kembali
11 Urugan Pasir / M3
12 Err:509
13 Err:509
C Analisa Biaya Konstruksi Pekerjaan Pondasi
14 Pasang Pondasi Batu Kali 1 Pc : 3 Pasir Pasang / M3
15 Pemancangan
D Analisa Biaya Konstruksi Pekerjaan Beton
16 Membuat 1 M3 Beton Ready Mix K-225 Pile Cap
17 Err:509
18 Membuat Sloof Beton Bertulang (200 Kg Besi + Bekistin
19 Membuat Kolom Beton Bertulang (250 Kg Besi + Bekis
20 Membuat Balok Beton Bertulang (250 Kg Besi + Bekisti
21 Membuat Kolom Praktis (15x15) CM / M1
22 Membuat Plat Lantai Beton Bertulang (125 Kg Besi + B
23 Membuat Sloof Beton Bertulang (150 Kg Besi + Bekistin
E Analisa Biaya Konstruksi Pekerjaan Dinding dan Ples
24 Pasangan Bata Merah Tebal 1/2 Bata, 1 Pc : 6 Ps / M2
25 Plesteran 1 Pc : 2 Ps, Tebal 15 mm / M2
26 Memasang Acian / M2
No URAIAN PEKERJAAN

27 Benangan
F Analisa Biaya Konstruksi Pekerjaan Lantai
28 Pasang Lantai Keramik 40 x 40 cm Motif untuk Los Te
29 Pasang Keramik Dinding 20 x 25 cm
G Analisa Biaya Konstruksi Pekerjaan Pengecatan
30 Pengecatan Tembok Baru dalam (1 Lapis Plamir, 1 Lapis Cat Das
31 Pengecatan Tembok Baru Luar (1 Lapis Alkali Sealer, 1 Lapis Ca
H Analisa Biaya Konstruksi Pekerjaan Kusen, Pintu, Jen
32 Pasang Rolling Door Almunium / 1 unit
33 Memasang Kusen Alumunium
34 Memasang Daun Pintu PVC
35 Pasang kunci tanam biasa
36 Pasang engsel pintu
I Analisa Biaya Konstruksi Pekerjaan Elektrikal
37 Pemasangan Panel / Unit
38 Memasang NYY 4x6 mm²
39 Instalasi penerangan/ ttk
40 Instalasi Stop Kontak/ ttk
J Analisa Biaya Konstruksi Pekerjaan Mekanikal
41 Pemasangan dan Pengadaan Hydrant Pillar (HP)
42 Pemasangan dan Pengadaan VALVE-VALVE & FIXTU
43 Pemasangan dan Pengadaan Hose Reel Cabinet ( HRC
44 Instalasi Pipa Hydrant
No URAIAN PEKERJAAN

K Analisa Biaya Konstruksi Pekerjaan Sanitasi dan Plu


45 Pasang kloset jongkok porselin
46 Pasang kran diameter 1/2"
47 Pasang pipa PVC tipe AW, diameter 1/2"
48 Pasang pipa PVC tipe AW, diameter 4"
49 Pasang pipa PVC tipe AW, diameter 6"
50 Memasang 1 unit septictank kapasitas 50 orang
51 Memasang 1 Bh Floor Drain
52 Memasang 1 Bh Roof Drain
L Analisa Biaya Konstruksi Pekerjaan Lain - Lain
53 Aluminium Composite Panel ( Standart )+Aksesories
54 PEMASANGAN BAK KONTROL UKURAN 120 X 75
55 PEMASANGAN TUTUP BAK KONTROL UKURAN 1
56 PEMASANGAN PLAT BETON TUTUP U-DITCH UK
57 PEMASANGAN SALURAN U DITCH UK. 50X50X120
58 Pasang Paving Stone TB.8 cm K500 dengan Penebaran Pasir Pasa
59 PEMASANGAN JALUSI BESI HOLLOW 0.8 X 5.75 M/
DAFTAR ANALISA HARGA SATUAN
-
-
-
KOTA SURABAYA
2018

URAIAN PEKERJAAN HARGA SAT

Analisa Biaya Konstruksi Pekerjaan Persiapan


Rp.
Pengukuran dan Pemasangan Bouwplank / M1 Rp.
Rp.
Rp.
Membersihkan Lapangan dan Peralatan / M2 Rp.
Rp.
Err:509 Rp.
Analisa Biaya Konstruksi Pekerjaan Tanah
Rp.
Rp.
Urugan Kembali Rp.
Urugan Pasir / M3 Rp.
Err:509 Rp.
Rp.
Analisa Biaya Konstruksi Pekerjaan Pondasi
Pasang Pondasi Batu Kali 1 Pc : 3 Pasir Pasang / M3 Rp.
Rp.
Analisa Biaya Konstruksi Pekerjaan Beton
Membuat 1 M3 Beton Ready Mix K-225 Pile Cap Rp.
Rp.
Membuat Sloof Beton Bertulang (200 Kg Besi + Bekisting) / M3 Rp.
Membuat Kolom Beton Bertulang (250 Kg Besi + Bekisting) / M3 Rp.
Membuat Balok Beton Bertulang (250 Kg Besi + Bekisting) / M3 Rp.
Membuat Kolom Praktis (15x15) CM / M1 Rp.
Membuat Plat Lantai Beton Bertulang (125 Kg Besi + Bekisting) / M3 Rp.
Membuat Sloof Beton Bertulang (150 Kg Besi + Bekisting) / M3 ( Los Terbuka ) Rp.
Analisa Biaya Konstruksi Pekerjaan Dinding dan Plesteran
Pasangan Bata Merah Tebal 1/2 Bata, 1 Pc : 6 Ps / M2 Rp.
Plesteran 1 Pc : 2 Ps, Tebal 15 mm / M2 Rp.
Memasang Acian / M2 Rp.
URAIAN PEKERJAAN HARGA SAT

Benangan Rp.
Analisa Biaya Konstruksi Pekerjaan Lantai
Pasang Lantai Keramik 40 x 40 cm Motif untuk Los Tengah/ M2 Rp.
Pasang Keramik Dinding 20 x 25 cm Rp.
Analisa Biaya Konstruksi Pekerjaan Pengecatan
Pengecatan Tembok Baru dalam (1 Lapis Plamir, 1 Lapis Cat Dasar, 2 Lapis Cat Penutup) / M2 Rp.
Pengecatan Tembok Baru Luar (1 Lapis Alkali Sealer, 1 Lapis Cat Dasar, 2 Lapis Cat Penutup) / M2 Rp.
Analisa Biaya Konstruksi Pekerjaan Kusen, Pintu, Jendela dan Aksesories
Pasang Rolling Door Almunium / 1 unit
Memasang Kusen Alumunium
Memasang Daun Pintu PVC
Pasang kunci tanam biasa
Pasang engsel pintu
Analisa Biaya Konstruksi Pekerjaan Elektrikal
Pemasangan Panel / Unit Rp.
Memasang NYY 4x6 mm² Rp.
Instalasi penerangan/ ttk Rp.
Instalasi Stop Kontak/ ttk Rp.
Analisa Biaya Konstruksi Pekerjaan Mekanikal
Pemasangan dan Pengadaan Hydrant Pillar (HP) Rp.
Pemasangan dan Pengadaan VALVE-VALVE & FIXTURES dia 100 mm Rp.
Pemasangan dan Pengadaan Hose Reel Cabinet ( HRC ) Rp.
Instalasi Pipa Hydrant Rp.
URAIAN PEKERJAAN HARGA SAT

Analisa Biaya Konstruksi Pekerjaan Sanitasi dan Plumbing


Pasang kloset jongkok porselin Rp.
Pasang kran diameter 1/2" Rp.
Pasang pipa PVC tipe AW, diameter 1/2" Rp.
Pasang pipa PVC tipe AW, diameter 4" Rp.
Pasang pipa PVC tipe AW, diameter 6" Rp.
Memasang 1 unit septictank kapasitas 50 orang Rp.
Memasang 1 Bh Floor Drain Rp.
Memasang 1 Bh Roof Drain Rp.
Analisa Biaya Konstruksi Pekerjaan Lain - Lain
Aluminium Composite Panel ( Standart )+Aksesories Rp.
PEMASANGAN BAK KONTROL UKURAN 120 X 75 X 100 CM/ BH Rp.
PEMASANGAN TUTUP BAK KONTROL UKURAN 120 X 75 X 12 CM/ BH Rp.
PEMASANGAN PLAT BETON TUTUP U-DITCH UK. 50x60x12 CM /M' Rp.
PEMASANGAN SALURAN U DITCH UK. 50X50X120 CM/ M' Rp.
Pasang Paving Stone TB.8 cm K500 dengan Penebaran Pasir Pasang Pengunci (Warna Abu-abu)/ m2 Rp.
PEMASANGAN JALUSI BESI HOLLOW 0.8 X 5.75 M/ UNIT Rp.
ISA HARGA SATUAN

HARGA SATUAN

Err:509
33,755.00
Err:509
Err:509
23,850.00
Err:509
Err:509

187,965.00
Err:509
38,969.10
46,770.00
Err:509
Err:509

263,625.00
500,454.00

311,422.00
Err:509
#REF!
#REF!
#REF!
118,717.00
4,868,005.00
4,110,939.38

165,934.00
84,643.00
48,286.00
HARGA SATUAN

38,221.00

371,485.00
325,238.00

25,040.60
30,400.60

11,887,522.50
163,185.80
423,621.70
235,655.00
97,187.75

34,254,000.00
50,974.00
460,459.06
422,959.06

2,327,775.00
2,634,327.00
3,306,825.00
272,825.00
HARGA SATUAN

698,880.00
175,292.50
49,340.60
86,700.20
124,409.15
#REF!
66,255.00
326000

481,247.00
301,760.00
513,021.04
476,077.13
848,238.47
126,210.00
11,174,653.20
ANALISA HARGA SATUAN PEKERJAA
PROGRAM :
KEGIATAN :
PEKERJAAN :
LOKASI :
TH. ANGGARAN : 2018

ANALISA PEKERJAAN STRUKTUR DAN ARSITEKTUR

No Indeks Sat Uraian Harga Satuan Upah


A Analisa Biaya Konstruksi Pekerjaan Persiapan
1 Pengukuran dan Pemasangan Bouwplank / M1
0.0050 oh Mandor 177,000.00 885.00
0.0100 oh Kepala Tukang 177,000.00 1,770.00
0.1000 oh Tukang Kayu 161,000.00 16,100.00
0.1000 oh Pekerja 150,000.00 15,000.00
0.0120 M3 Kayu 5/7 (Kayu Klas.IV) 4,188,000.00
0.0200 Kg Paku Biasa 2"-5" 29,100.00
0.0070 M3 Kayu Papan 3/20 (Klas IV) 4,188,000.00
33,755.00
5 Membersihkan Lapangan dan Peralatan / M2
0.0500 oh Mandor 177,000.00 8,850.00
0.1000 oh Pekerja 150,000.00 15,000.00
23,850.00
No Indeks Sat Uraian Harga Satuan Upah
B Analisa Biaya Konstruksi Pekerjaan Galian & Urugan

8 Galian Tanah
0.0450 oh Mandor 177,000.00 7,965.00
1.2000 oh Pekerja 150,000.00 180,000.00
187,965.00
10 Urugan Kembali m3
0.0083 oh Mandor 177,000.00 1,469.10
0.2500 oh Pekerja 150,000.00 37,500.00
38,969.10
11 Urugan Pasir / M3
0.0100 oh Mandor 177,000.00 1,770.00
0.3000 oh Pekerja 150,000.00 45,000.00
1.2000 M3 Pasir Urug 177,000.00
46,770.00

C Analisa Biaya Konstruksi Pekerjaan Pondasi

14 Pasang Pondasi Batu Kali 1 Pc : 3 Pasir Pasang / M3


0.0750 oh Mandor 177,000.00 13,275.00
0.0750 oh Kepala Tukang 177,000.00 13,275.00
0.0750 oh Tukang 161,000.00 12,075.00
1.5000 oh Pekerja 150,000.00 225,000.00
1.2000 M3 Batu Kali 466,000.00
202.0000 Kg Semen Portland 2,000.00
0.4850 M3 Pasir Pasang 281,000.00
263,625.00
15 Pemancangan
0.3900 oh Tukang 161,000.00 62,790.00
1.0000 Batang Tiang Pancang 155,500.00
0.2180 Jam Sewa Crane 30 ton 146,500.00
0.2180 Jam Sewa Hammer Tiang Pancang 204,700.00 62,790.00
125,580.00
D Analisa Biaya Konstruksi Pekerjaan Beton - SNI 7394 2008
16 Membuat 1 M3 Beton Ready Mix K-225 Pile Cap
0.0830 oh Mandor 177,000.00 14,691.00
0.0280 oh Kepala Tukang 177,000.00 4,956.00
0.2750 oh Tukang 161,000.00 44,275.00
1.6500 oh Pekerja 150,000.00 247,500.00
1.02 m3 Ready mix 875,000.00
311,422.00
16 Membuat 1 M3 Beton Ready Mix K-225 Sloof
0.0830 oh Mandor 177,000.00 14,691.00
0.0280 oh Kepala Tukang 177,000.00 4,956.00
0.2750 oh Tukang 161,000.00 44,275.00
1.6500 oh Pekerja 150,000.00 247,500.00
1.02 m3 Ready mix 938,000.00
311,422.00
No Indeks Sat Uraian Harga Satuan Upah
16 Membuat 1 M3 Beton Ready Mix K-225 Lantai Kerja
0.0830 oh Mandor 177,000.00 14,691.00
0.0280 oh Kepala Tukang 177,000.00 4,956.00
0.2750 oh Tukang 161,000.00 44,275.00
1.6500 oh Pekerja 150,000.00 247,500.00
1.02 m3 Ready mix 875,000.00
311,422.00
16 Membuat 1 M3 Beton Ready Mix K-225 Plat Lantai
0.0830 oh Mandor 177,000.00 14,691.00
0.0280 oh Kepala Tukang 177,000.00 4,956.00
0.2750 oh Tukang 161,000.00 44,275.00
1.6500 oh Pekerja 150,000.00 247,500.00
1.02 m3 Ready mix 938,000.00
311,422.00
16 Membuat 1 M3 Beton Ready Mix K-225 Plat Kolom
0.0830 oh Mandor 177,000.00 14,691.00
0.0280 oh Kepala Tukang 177,000.00 4,956.00
0.2750 oh Tukang 161,000.00 44,275.00
1.6500 oh Pekerja 150,000.00 247,500.00
1.02 m3 Ready mix 938,000.00
311,422.00
16 Membuat 1 M3 Beton Ready Mix K-225 Balok
0.0830 oh Mandor 177,000.00 14,691.00
0.0280 oh Kepala Tukang 177,000.00 4,956.00
0.2750 oh Tukang 161,000.00 44,275.00
1.6500 oh Pekerja 150,000.00 247,500.00
1.02 m3 Ready mix 938,000.00
311,422.00
16 Membuat 1 M3 Beton Ready Mix K-225 Plat Atap
0.0830 oh Mandor 177,000.00 14,691.00
0.0280 oh Kepala Tukang 177,000.00 4,956.00
0.2750 oh Tukang 161,000.00 44,275.00
1.6500 oh Pekerja 150,000.00 247,500.00
1.02 m3 Ready mix 938,000.00
311,422.00
16 Membuat 1 M3 Beton Ready Mix K-225 Plat Tangga dan Bordes
0.0830 oh Mandor 177,000.00 14,691.00
0.0280 oh Kepala Tukang 177,000.00 4,956.00
0.2750 oh Tukang 161,000.00 44,275.00
1.6500 oh Pekerja 150,000.00 247,500.00
1.02 m3 Ready mix 938,000.00
311,422.00
E Analisa Biaya Konstruksi Pekerjaan Bekisting
16 Membuat 1m3 Bekisting Pile Cap
0.0300 oh Mandor 177,000.00 5,310.00
0.0300 oh Kepala Tukang 177,000.00 5,310.00
0.3000 oh Tukang Kayu 161,000.00 48,300.00
0.3000 oh Pekerja 150,000.00 45,000.00
No Indeks Sat Uraian Harga Satuan Upah
0.1280 lembar Multiflex 18 mm 150,000.00
0.0060 M3 Kaso 5/7 cm 155,000.00
0.2800 Kg Paku 7 cm dan 12 cm 12,500.00
0.2500 Liter Minyak Bekisting 40,000.00
103,920.00
16 Membuat 1m3 Bekisting Sloof
0.0300 oh Mandor 177,000.00 5,310.00
0.0300 oh Kepala Tukang 177,000.00 5,310.00
0.3000 oh Tukang Kayu 161,000.00 48,300.00
0.3000 oh Pekerja 150,000.00 45,000.00
0.1280 lembar Multiflex 18 mm 150,000.00
0.0060 M3 Kaso 5/7 cm 155,000.00
0.2800 Kg Paku 7 cm dan 12 cm 12,500.00
0.2500 Liter Minyak Bekisting 40,000.00
103,920.00
16 Membuat 1m3 Bekisting Kolom
0.0300 oh Mandor 177,000.00 5,310.00
0.0300 oh Kepala Tukang 177,000.00 5,310.00
0.3000 oh Tukang Kayu 161,000.00 48,300.00
0.3000 oh Pekerja 150,000.00 45,000.00
0.1280 lembar Multiflex 18 mm 150,000.00
0.0060 M3 Kaso 5/7 cm 155,000.00
0.2800 Kg Paku 7 cm dan 12 cm 12,500.00
0.2500 Liter Minyak Bekisting 40,000.00
103,920.00
16 Membuat 1m3 Bekisting Balok
0.0300 oh Mandor 177,000.00 5,310.00
0.0300 oh Kepala Tukang 177,000.00 5,310.00
0.3000 oh Tukang Kayu 161,000.00 48,300.00
0.3000 oh Pekerja 150,000.00 45,000.00
0.1280 lembar Multiflex 18 mm 150,000.00
0.0060 M3 Kaso 5/7 cm 155,000.00
0.2800 Kg Paku 7 cm dan 12 cm 12,500.00
0.2500 Liter Minyak Bekisting 40,000.00
103,920.00
16 Membuat 1m3 Bekisting pelat
0.0300 oh Mandor 177,000.00 5,310.00
0.0300 oh Kepala Tukang 177,000.00 5,310.00
0.3000 oh Tukang Kayu 161,000.00 48,300.00
0.3000 oh Pekerja 150,000.00 45,000.00
0.1280 lembar Multiflex 18 mm 150,000.00
0.0060 M3 Kaso 5/7 cm 155,000.00
0.2800 Kg Paku 7 cm dan 12 cm 12,500.00
0.2500 Liter Minyak Bekisting 40,000.00
103,920.00
No Indeks Sat Uraian Harga Satuan Upah
18 Membuat Sloof Beton Bertulang (200 Kg Besi + Bekisting) / M3
0.2830 oh Mandor 177,000.00 50,091.00
0.3230 oh Kepala Tukang 177,000.00 57,171.00
1.4000 oh Tukang Besi 161,000.00 225,400.00
0.2750 oh Tukang Batu 161,000.00 44,275.00
1.5600 oh Tukang Kayu 161,000.00 251,160.00
5.6500 oh Pekerja 150,000.00 847,500.00
0.2700 M3 Kayu Klas III -
2.0000 Kg Paku 5 cm - 12 cm 16,000.00
0.6000 Ltr Minyak Bekisting 31,000.00
210.0000 Kg #REF! #REF!
3.0000 Kg Kawat Beton 28,000.00
1.0500 M3 Readymix K-275 890,000.00
1,475,597.00
19 Membuat Kolom Beton Bertulang (250 Kg Besi + Bekisting) / M3
0.3180 oh Mandor 177,000.00 56,286.00
0.3330 oh Kepala Tukang 177,000.00 58,941.00
1.4000 oh Tukang Besi 161,000.00 225,400.00
0.2750 oh Tukang Batu 161,000.00 44,275.00
1.6500 oh Tukang Kayu 161,000.00 265,650.00
6.3500 oh Pekerja 150,000.00 952,500.00
0.3200 M3 Kayu Klas III -
3.2000 Kg Paku 5 cm - 12 cm 16,000.00
1.6000 Ltr Minyak Bekisting 31,000.00
262.5000 Kg #REF! #REF!
3.0000 Kg Kawat Beton 28,000.00
1.0500 M3 Readymix K-275 890,000.00
0.1400 M3 Kayu Beton Klas II 3,459,000.00
2.8000 Lbr Plywood 9 mm 166,000.00
16.0000 Btg Dolken Ø-8 cm / 4 m 12,000.00
1,603,052.00
20 Membuat Balok Beton Bertulang (250 Kg Besi + Bekisting) / M3
0.3180 oh Mandor 177,000.00 56,286.00
0.3330 oh Kepala Tukang 177,000.00 58,941.00
1.4000 oh Tukang Besi 161,000.00 225,400.00
0.2750 oh Tukang Batu 161,000.00 44,275.00
1.6500 oh Tukang Kayu 161,000.00 265,650.00
6.3500 oh Pekerja 150,000.00 952,500.00
0.3200 M3 Kayu Klas III -
3.2000 Kg Paku 5 cm - 12 cm 16,000.00
1.6000 Ltr Minyak Bekisting 31,000.00
262.5000 Kg #REF! #REF!
3.0000 Kg Kawat Beton 28,000.00
1.0500 M3 Readymix K-275 890,000.00
0.1400 M3 Kayu Beton Klas II 3,459,000.00
2.8000 Lbr Plywood 9 mm 166,000.00
16.0000 Btg Dolken Ø-8 cm / 4 m 12,000.00
1,603,052.00
No Indeks Sat Uraian Harga Satuan Upah
21 Membuat Kolom Praktis (15x15) CM / M1
0.0090 oh Mandor 177,000.00 1,593.00
0.0060 oh Kepala Tukang 177,000.00 1,062.00
0.0200 oh Tukang Besi 161,000.00 3,220.00
0.0200 oh Tukang Kayu 161,000.00 3,220.00
0.0200 oh Tukang Batu 161,000.00 3,220.00
0.1800 oh Pekerja 150,000.00 27,000.00
0.0020 M3 Kayu Klas III -
0.0100 Kg Paku 5 cm - 12 cm 16,000.00
0.4000 Ltr Minyak Bekisting 31,000.00
3.0000 Kg Besi Beton Polos 14,000.00
0.4500 Kg Kawat Beton 28,000.00
4.0000 Kg Semen Portland 2,000.00
0.0060 M3 Pasir Beton 281,000.00
0.0090 M3 Kerikil 284,000.00
39,315.00
22 Membuat Plat Lantai Beton Bertulang (125 Kg Besi + Bekisting) / M3
0.1650 oh Mandor 177,000.00 29,205.00
0.2450 oh Kepala Tukang 177,000.00 43,365.00
1.0500 oh Tukang Besi 161,000.00 169,050.00
0.3500 oh Tukang Kayu 161,000.00 56,350.00
1.0400 oh Tukang Batu 161,000.00 167,440.00
3.9000 oh Pekerja 150,000.00 585,000.00
0.2000 M3 Kayu Terentang / Klas IV -
1.5000 Kg Paku Biasa 2" - 5" 16,000.00
0.4000 Ltr Minyak Bekisting 31,000.00
131.2500 Kg Besi Beton (Polos U-24) 14,000.00
2.2500 Kg Kawat Beton 28,000.00
1.0500 M3 Readymix K-275 890,000.00
0.1050 M3 Kayu Beton Klas II 3,459,000.00
2.5000 Lbr Plywood 9 mm 166,000.00
14.0000 Btg Dolken Ø-8 cm / 4 m 12,000.00
1,050,410.00
No Indeks Sat Uraian Harga Satuan Upah
23 Membuat Sloof Beton Bertulang (150 Kg Besi + Bekisting) / M3 ( Los Terbuka )
0.2650 oh Mandor 90,000.00 23,850.00
0.2620 oh Kepala Tukang 85,000.00 22,270.00
1.0500 oh Tukang Besi 80,000.00 84,000.00
0.2750 oh Tukang Batu 70,000.00 19,250.00
1.3000 oh Tukang Kayu 80,000.00 104,000.00
5.3000 oh Pekerja 70,000.00 371,000.00
0.2000 M3 Kayu Klas III 1,710,625.00
1.5000 Kg Paku 5 cm - 12 cm 16,675.00
0.4000 Ltr Minyak Bekisting 15,525.00
157.5000 Kg Besi Beton polos 14,000.00
2.2500 Kg Kawat Beton 20,987.50
1.0500 M3 Readymix K-275 820,000.00
624,370.00

E Analisa Biaya Konstruksi Pekerjaan Dinding dan Plesteran


24 Pasangan Bata Merah Tebal 1/2 Bata, 1 Pc : 6 Ps / M2
0.0150 OH Mandor 177,000.00 2,655.00
0.0100 OH Kepala Tukang 177,000.00 1,770.00
0.1000 OH Tukang Batu 161,000.00 16,100.00
0.3000 OH Pekerja 150,000.00 45,000.00
70.0000 Bh Bata Merah 5 x 11 x 22 cm 1,000.00
8.3200 Kg Semen Portland 2,000.00
0.0490 M3 Pasir Pasang 281,000.00
65,525.00
25 Plesteran 1 Pc : 2 Ps, Tebal 15 mm / M2
0.0100 OH Mandor 177,000.00 1,770.00
0.0150 OH Kepala Tukang 177,000.00 2,655.00
0.1500 OH Tukang Batu 161,000.00 24,150.00
0.2000 OH Pekerja 150,000.00 30,000.00
10.2240 Kg Semen Portland 2,000.00
0.0200 M3 Pasir Pasang 281,000.00
58,575.00
26 Memasang Acian / M2
0.0080 OH Mandor 177,000.00 1,416.00
0.0100 OH Kepala Tukang 177,000.00 1,770.00
0.1000 OH Tukang Batu 161,000.00 16,100.00
0.1500 OH Pekerja 150,000.00 22,500.00
3.2500 Kg Semen Portland 2,000.00
41,786.00
27 Benangan m'
0.1200 OH Tukang Batu 161,000.00 19,320.00
6.5000 kg Semen Portland 2,000.00
0.0210 m3 Pasir Pasang 281,000.00
19,320.00

F Analisa Biaya Konstruksi Pekerjaan Lantai


28 Pasang Lantai Keramik 40 x 40 cm Motif untuk Los Tengah/ M2
No Indeks Sat Uraian Harga Satuan Upah
0.0350 OH Mandor 177,000.00 6,195.00
0.0350 OH Kepala Tukang 177,000.00 6,195.00
0.3500 OH Tukang Batu 161,000.00 56,350.00
0.7000 OH Pekerja 150,000.00 105,000.00
1.1000 m2 Ubin keramik 40x40 146,000.00
10.0000 Kg Semen Portland 2,000.00
0.0450 M3 Pasir Pasang 281,000.00
1.5000 Kg Semen Warna 3,000.00
173,740.00
29 Pasang Keramik Dinding 20 x 25 cm
0.9000 OH Pekerja 150,000.00 135,000.00
0.4500 OH Tukang Batu 161,000.00 72,450.00
0.0450 OH Kepala Tukang Batu 177,000.00 7,965.00
0.0450 OH Mandor 177,000.00 7,965.00

1.1000 m2 Keramik Dinding 20 x 25 cm 67,000.00


9.3000 kg Portland Cement (PC) 2,000.00
0.0180 m³ Pasir Pasang 281,000.00
1.5000 kg Portland Cement (PC) Warna 3,000.00
223,380.00

G Analisa Biaya Konstruksi Pekerjaan Pengecatan

30 Pengecatan Tembok Baru dalam (1 Lapis Plamir, 1 Lapis Cat Dasar, 2 Lapis Cat Penutup) / M2
0.0025 oh Mandor 177,000.00 442.50
0.0063 oh Kepala Tukang 177,000.00 1,115.10
0.0630 oh Tukang Cat 161,000.00 10,143.00
0.0200 oh Pekerja 150,000.00 3,000.00
0.1000 Kg Cat Dasar 28,000.00
0.2600 Kg Cat Penutup 2 Kali (Cat Air Setara Matex) 29,000.00
14,700.60
No Indeks Sat Uraian Harga Satuan Upah
31 Pengecatan Tembok Baru Luar (1 Lapis Alkali Sealer, 1 Lapis Cat Dasar, 2 Lapis Cat Penutup) / M2
0.0025 oh Mandor 177,000.00 442.50
0.0063 oh Kepala Tukang 177,000.00 1,115.10
0.0630 oh Tukang Cat 161,000.00 10,143.00
0.0280 oh Pekerja 150,000.00 4,200.00
0.1000 Kg Cat Dasar 28,000.00
0.2600 Kg Cat Penutup 2 Kali (Cat Weather Shield) 45,000.00
15,900.60

H Analisa Biaya Konstruksi Pekerjaan Kusen, Pintu, Jendela dan Aksesories


32 Pasang Rolling Door Almunium / 1 unit
7.9500 OH Pekerja 150,000.00 1,192,500.00
7.9500 OH Tukang Besi 161,000.00 1,279,950.00
0.7950 OH Kepala Tukang Besi 177,000.00 140,715.00
0.3975 OH Mandor 177,000.00 70,357.50
1.0000 unit Rolling Door 9,204,000.00
2,683,522.50
33 Memasang Kusen Alumunium
0.0430 OH Pekerja 150,000.00 6,450.00
0.0430 OH Tukang Besi/Baja 161,000.00 6,923.00
0.0043 OH Kepala Tukang Besi 177,000.00 761.10
0.0021 OH Mandor 177,000.00 371.70
1.1000 M' Profil Aluminium Coklat 131,000.00 144,100.00
2.0000 bh Sekrup segala ukuran 1,000.00 2,000.00
0.0600 tube Sealant 43,000.00 2,580.00

34 Memasang Daun Pintu PVC


0.0021 OH Mandor 177,000.00 371.70
0.5000 OH Tukang 161,000.00 80,500.00
0.0050 OH Pekerja 150,000.00 750.00
1.0000 bh Pintu PVC 342,000.00 342,000.00

35 Pasang kunci tanam biasa

0.01 OH Pekerja 150,000.00 1,500.00


0.5 OH Tukang Kayu 161,000.00 80,500.00
0.01 OH Kepala Tukang Kayu 177,000.00 1,770.00
0.005 OH Mandor 177,000.00 885.00

1.0000 bh Kunci Tanam 151,000.00


84,655.00
36 Pasang engsel pintu

0.0150 OH Pekerja 150,000.00 2,250.00


0.1500 OH Tukang Kayu 161,000.00 24,150.00
0.0150 OH Kepala Tukang Kayu 177,000.00 2,655.00
0.0008 OH Mandor 177,000.00 132.75
No Indeks Sat Uraian Harga Satuan Upah
1.0000 BH Engsel Pintu 68,000.00
29,187.75

I Analisa Biaya Konstruksi Pekerjaan Elektrikal

37 Pemasangan Panel / Unit


1.0000 bh Box Panel 50 x 40 x 25 cm dan aksesoris lainnya 29,363,000.00
1.0000 bh MCB 40A/3P, 10 kA 737,000.00
1.0000 bh MCB 16A/1P, 6kA 108,000.00
3.0000 bh Pilot Lamp RST+Fuse 50,000.00
3.0000 bh Volt Meter 300,000.00
1.0000 bh SSV 186,000.00
3.0000 bh Ampere Meter 262,000.00
1.0000 bh Shunt Trip 462,000.00
1.0000 bh CT 234,000.00
1.0000 m Busbar 178,000.00
1.0000 ls assesories & installasi 1,150,000.00

38 Memasang NYY 4x6 mm²


1.1000 m' NYY 4x6 mm² 31,000.00
1.1000 m' Kabel BC 6 mm² 7,000.00
0.0120 OH Mandor 177,000.00 2,124.00
0.0180 OH Kepala Tukang listrik 177,000.00 3,186.00
0.0240 OH Tukang 161,000.00 3,864.00
9,174.00
No Indeks Sat Uraian Harga Satuan Upah
39 Instalasi penerangan/ ttk
0.0250 OH Mandor 177,000.00 4,425.00
0.0500 OH Kepala Tukang listrik 177,000.00 8,850.00
0.0500 OH Tukang 161,000.00 8,050.00
0.2500 OH Pekerja 150,000.00 37,500.00

16.8577 m' Kabel NYM 3×2,5 mm2 300/500 V 16,000.00


16.8577 m' Konduit dia 20 mm (3/4") 4,000.00
1.2000 m' Claim conduit 400.00
1.0000 bh Inbow Doos 6,000.00
4.0000 m' Isolator 8,000.00
2.0000 bh Las Doof 13,000.00
58,825.00
40 Instalasi Stop Kontak/ ttk
0.0250 OH Mandor 177,000.00 4,425.00
0.0500 OH Kepala Tukang listrik 177,000.00 8,850.00
0.0500 OH Tukang 161,000.00 8,050.00
OH Pekerja 150,000.00 0.00
16.8577 m' Kabel NYM 3×2,5 mm2 300/500 V 16,000.00
16.8577 m' Konduit dia 20 mm (3/4") 4,000.00
1.2000 m' Claim conduit 400.00
1.0000 bh Inbow Doos 6,000.00
4.0000 m' Isolator 8,000.00
2.0000 bh Las Doof 13,000.00
21,325.00

J Analisa Biaya Konstruksi Pekerjaan Mekanikal

41 Pemasangan dan Pengadaan Hydrant Pillar (HP)


0.0250 OH Mandor 177,000.00 4,425.00
0.0500 OH Tukang Pipa 31,000.00 1,550.00
0.0500 OH Multiplek 9 mm 166,000.00 8,300.00
0.2500 OH Pekerja 150,000.00 37,500.00

1.0000 0 Hydrant Pillar (HP) 2,200,000.00


2.0000 0 Flange 105,000.00
1.0000 lot Peralatan Bantu 76,000.00
51,775.00
42 Pemasangan dan Pengadaan VALVE-VALVE & FIXTURES dia 100 mm
0.0250 OH Mandor 90,000.00 2,250.00
0.0500 OH Kepala Tukang Pipa 85,000.00 4,250.00
0.0500 OH Tukang Pipa 80,000.00 4,000.00
0.2500 OH Pekerja 70,000.00 17,500.00

1.0000 Buah VALVE-VALVE & FIXTURES dia 100 mm 2,540,327.00


1.0000 lot Peralatan Bantu 66,000.00
28,000.00
No Indeks Sat Uraian Harga Satuan Upah
43 Pemasangan dan Pengadaan Hose Reel Cabinet ( HRC )
0.0250 OH Mandor 177,000.00 4,425.00
0.0500 OH Kepala Tukang Pipa 177,000.00 8,850.00
0.0500 OH Tukang Pipa 161,000.00 8,050.00
0.2500 OH Pekerja 150,000.00 37,500.00

1.0000 lot Hose Reel Cabinet ( HRC ) 3,248,000.00


1.0000 ls Peralatan Bantu 76,000.00
1.0000 ls Pondasi dan bak kontrol 2,166,500.00
58,825.00
44 Instalasi Pipa Hydrant
0.0250 OH Mandor 177,000.00 4,425.00
0.0500 OH Kepala Tukang Pipa 177,000.00 8,850.00
0.0500 OH Tukang Pipa 161,000.00 8,050.00
0.2500 OH Pekerja 150,000.00 37,500.00

1.0000 m' Pipa Diameter 100 mm 214,000.00


1.0000 ls Cat Dasar, Flinkote. 12,000.00
1.0000 lot Peralatan Bantu 76,000.00
58,825.00

K Analisa Biaya Konstruksi Pekerjaan Sanitasi dan Plumbing

45 Pasang kloset jongkok porselin


1.0000 OH Pekerja 150,000.00 150,000.00
1.5000 OH Tukang Batu 161,000.00 241,500.00
0.3000 OH Kepala Tukang Batu 177,000.00 53,100.00
0.1100 OH Mandor 177,000.00 19,470.00

1.0000 bh Kloset Jongkok Teraso 213,000.00


7.0000 bh Bata Merah 1,000.00
6.0000 kg Portland Cement (PC) 2,000.00
0.0100 m³ Pasir Pasang 281,000.00
464,070.00
No Indeks Sat Uraian Harga Satuan Upah
46 Pasang kran diameter 1/2"
0.0100 OH Pekerja 150,000.00 1,500.00
0.1000 OH Tukang Pipa 161,000.00 16,100.00
0.0100 OH Kepala Tukang Batu 177,000.00 1,770.00
0.0050 OH Mandor 177,000.00 885.00

1.0000 bh Kran Air 1/2 " 155,000.00


0.0250 bh Seal Tape / TBA 1,500.00
20,255.00
47 Pasang pipa PVC tipe AW, diameter 1/2"
0.0360 OH Pekerja 150,000.00 5,400.00
0.0600 OH Tukang Pipa 161,000.00 9,660.00
0.0060 OH Kepala Tukang Pipa 177,000.00 1,062.00
0.0018 OH Mandor 177,000.00 318.60

1.2000 M' Pipa PVC tipe AW Ø 1/2" 7,000.00


0.3500 Perlengkapan 70,000.00
16,440.60
48 Pasang pipa PVC tipe AW, diameter 4"
0.0810 OH Pekerja 150,000.00 12,150.00
0.1350 OH Tukang Pipa 161,000.00 21,735.00
0.0135 OH Kepala Tukang Pipa 177,000.00 2,389.50
0.0041 OH Mandor 177,000.00 725.70

1.2000 M' Pipa PVC tipe AW Ø 4 " 21,000.00


0.3500 Perlengkapan 70,000.00
37,000.20
49 Pasang pipa PVC tipe AW, diameter 6"
0.1215 OH Pekerja 150,000.00 18,225.00
0.2025 OH Tukang Pipa 161,000.00 32,602.50
0.0203 OH Kepala Tukang Pipa 177,000.00 3,593.10
0.0062 OH Mandor 177,000.00 1,088.55

1.2000 M' Pipa PVC tipe AW Ø 6 " 37,000.00


0.3500 Perlengkapan 70,000.00
55,509.15
50 Memasang 1 unit septictank kapasitas 50 orang
15.6100 M3 Galian Tanah Biasa Sedalam 2 meter #REF! #REF!
5.3300 M3 Urugan Bekas Galian #REF! #REF!
1.5700 M3 Pasangan Batu Bata 1:6 165,934.00 260,516.38
0.6600 M 3
Beton Tumbuk 1:3:5 (Split 2/3) 311,422.00 205,538.52
30.6100 M 2
Plesteran 1:2 tebal 15 mm 84,643.00 2,590,922.23
0.5000 M 3
Beton Bertulang Plat Lantai (besi = 125 kg) 4,868,005.00 2,434,002.50
3.0000 M 3
Kerekel Saringan 260,000.00 780,000.00
4.0000 M 3
Pasir Saringan 156,000.00 624,000.00
2.0000 M '
Memasang Pipa Besi dia. 2" 35,000.00 70,000.00
5.0000 M 3
Memasang Pipa PVC dia. 4" 86,700.20 433,501.00
No Indeks Sat Uraian Harga Satuan Upah
30.0000 Kg Ijuk Saringan 87,277.50 2,618,325.00
12.0000 m2 Plastik Hitam 7,500.00 90,000.00

51 Memasang 1 Bh Floor Drain


0.0050 OH Mandor 177,000.00 885.00
0.0100 OH Kepala Tukang 177,000.00 1,770.00
0.1000 OH Tukang 161,000.00 16,100.00
0.0100 OH Pekerja 150,000.00 1,500.00
1.0000 bh Floor Drain 46,000.00 46,000.00

52 Memasang 1 Bh Roof Drain


0.0050 OH Mandor 90,000.00 450.00
0.0100 OH Kepala Tukang 85,000.00 850.00
0.1000 OH Tukang 80,000.00 8,000.00
0.0100 OH Pekerja 70,000.00 700.00
1.0000 bh Roof Drain 316,000.00 316,000.00

L Analisa Biaya Konstruksi Pekerjaan Lain - Lain

53 Aluminium Composite Panel ( Standart )+Aksesories


0.0010 oh Mandor 177,000.00 177.00
0.0100 oh Kepala Tukang 177,000.00 1,770.00
0.1000 oh Tukang Kayu 161,000.00 16,100.00
0.2000 oh Pekerja 150,000.00 30,000.00
1.1000 m2 Aluminium Composite Panel 361,000.00
10.0000 % Aksesories
48,047.00
54 PEMASANGAN BAK KONTROL UKURAN 120 X 75 X 100 CM/ BH
0.2000 OH Pekerja biasa 150,000.00 30,000.00
0.0400 OH Tukang batu 161,000.00 6,440.00
0.0200 OH Kepala Tukang batu 177,000.00 3,540.00
0.0100 OH Mandor 177,000.00 1,770.00

1.0000 bh Cover bak kontrol uk. 120X75X10 243,000.00


1.0000 ls Alat bantu 17,010.00
41,750.00
No Indeks Sat Uraian Harga Satuan Upah
55 PEMASANGAN TUTUP BAK KONTROL UKURAN 120 X 75 X 12 CM/ BH
0.2000 OH Pekerja biasa 150,000.00 30,000.00
0.0400 OH Tukang batu 161,000.00 6,440.00
0.0200 OH Kepala Tukang batu 177,000.00 3,540.00
0.0100 OH Mandor 177,000.00 1,770.00

0.8333 bh Plat beton tutup Bak Kontrol uk 120x75x12 523,000.00


1.0000 ls Alat bantu 35,437.71
41,750.00
56 PEMASANGAN PLAT BETON TUTUP U-DITCH UK. 50x60x12 CM /M'
0.2000 OH Pekerja biasa 150,000.00 30,000.00
0.0400 OH Tukang batu 161,000.00 6,440.00
0.0200 OH Kepala Tukang batu 177,000.00 3,540.00
0.0100 OH Mandor 177,000.00 1,770.00

0.8333 bh Plat beton tutup U-ditch uk 68x120x12 482,000.00


1.0000 ls Alat bantu 32,660.46
41,750.00
57 PEMASANGAN SALURAN U DITCH UK. 50X50X120 CM/ M'
0.2000 OH Pekerja biasa 150,000.00 30,000.00
0.0400 OH Tukang batu 161,000.00 6,440.00
0.0200 OH Kepala Tukang batu 177,000.00 3,540.00
0.0100 OH Mandor 177,000.00 1,770.00

0.8333 bh Saluran U ditch uk 50x50 cm 895,000.00


1.0000 ls Alat bantu 60,655.14
41,750.00
58 Pasang Paving Stone TB.8 cm K500 dengan Penebaran Pasir Pasang Pengunci (Warna Abu-abu)/ m2

0.0250 OH Mandor 177,000.00 4,425.00


0.0250 OH Kepala tukang 177,000.00 4,425.00
0.0500 OH Pekerja 150,000.00 7,500.00
0.0500 OH Tukang batu 161,000.00 8,050.00

1.0000 m2 Paving Stone abu-abu TB.8 cm 99,000.00


0.0100 m3 Pasir Pasang 281,000.00
24,400.00
59 PEMASANGAN JALUSI BESI HOLLOW 0.8 X 5.75 M/ UNIT
0.3818 OH Mandor 177,000.00 67,578.60
0.7682 OH Kepala Tukang Besi 177,000.00 135,971.40
7.6820 OH Tukang Besi 161,000.00 1,236,802.00
6.7781 OH Kepala Tukang Cat 177,000.00 1,199,723.70
0.0331 OH Tukang Cat 161,000.00 5,329.10
0.9131 OH Pembantu Tukang 150,000.00 136,965.00
54.3150 m1 Besi Hollow 40/40 100,000.00
38.2514 m1 Besi Hollow 20/40 72,000.00
1.9550 Kg Cat Zincromate 43,000.00
0.3680 Kg Cat Minyak / Besi 65,000.00
No Indeks Sat Uraian Harga Satuan Upah
0.2622 Liter Minyak Cat / Afduner 8,000.00
4.6000 Lembar Kertas Gosok 21,000.00
2,782,369.80
EKERJAAN

SITEKTUR
Jumlah Bahan Jumlah Upah & Keuntungan Harga Yang
Kebutuhan Harga Total
Bahan dan Pajak Harus Dibayar

1
2
20
20
3
4
2
- 33,755.00 115% Rp 27,807,400 Rp 31,978,510

1
2
- 23,850.00 115% Rp 477,000 Rp 548,550
Jumlah Bahan Jumlah Upah & Keuntungan Harga Yang
Kebutuhan Harga Total
Bahan dan Pajak Harus Dibayar

1
26.6666666667
- 187,965.00 115% Rp 4,177,000 Rp 4,803,550

1
30.1204819277
38,969.10 115% Rp 4,695,072 Rp 5,399,333

1
30

- 46,770.00 115% Rp 4,677,000 Rp 5,378,550

1
1
1
20

- 263,625.00 115% Rp 3,515,000 Rp 4,042,250

1
155,500.00 3.0
31,937.00 1.0
187,437.00 1.0
374,874.00 500,454.00 115% Rp 978,700 Rp 1,125,505

1
1
4
20

311,422.00 115% Rp 3,998,000 Rp 4,597,700

1
1
4
20

311,422.00 115% Rp 3,998,000 Rp 4,597,700


Jumlah Bahan Jumlah Upah & Keuntungan Harga Yang
Kebutuhan Harga Total
Bahan dan Pajak Harus Dibayar

1
1
4
20
9.04
311,422.00 115% Rp 3,998,000 Rp 4,597,700

1
1
4
20
80.63
311,422.00 115% Rp 3,998,000 Rp 4,597,700

1
1
4
20
24.42
311,422.00 115% Rp 3,998,000 Rp 4,597,700

1
1
4
20
54.81
311,422.00 115% Rp 3,998,000 Rp 4,597,700

1
1
4
20
80.63
311,422.00 115% Rp 3,998,000 Rp 4,597,700

1
1
4
20
5.1
311,422.00 115% Rp 3,998,000 Rp 4,597,700

1
1
10
10
Jumlah Bahan Jumlah Upah & Keuntungan Harga Yang
Kebutuhan Harga Total
Bahan dan Pajak Harus Dibayar

103,920.00 115% Rp 3,464,000 Rp 3,983,600

1
1
10
10

103,920.00 115% Rp 3,464,000 Rp 3,983,600

1
1
10
10

103,920.00 115% Rp 3,464,000 Rp 3,983,600

1
1
10
10

103,920.00 115% Rp 3,464,000 Rp 3,983,600

1
1
10
10

103,920.00 115% Rp 3,464,000 Rp 3,983,600


Jumlah Bahan Jumlah Upah & Keuntungan Harga Yang
Kebutuhan Harga Total
Bahan dan Pajak Harus Dibayar

-
32,000.00
18,600.00
#REF!
84,000.00
934,500.00
#REF! #REF!

-
51,200.00
49,600.00
#REF!
84,000.00
934,500.00
484,260.00
464,800.00
192,000.00
#REF! #REF!

-
51,200.00
49,600.00
#REF!
84,000.00
934,500.00
484,260.00
464,800.00
192,000.00
#REF! #REF!
Jumlah Bahan Jumlah Upah & Keuntungan Harga Yang
Kebutuhan Harga Total
Bahan dan Pajak Harus Dibayar

oh
oh
oh
oh
oh
oh
- M3
160.00 Kg
12,400.00 Ltr
42,000.00 Kg
12,600.00 Kg
8,000.00 Kg
1,686.00 M3
2,556.00 M3
79,402.00 118,717.00

-
24,000.00
12,400.00
1,837,500.00
63,000.00
934,500.00
363,195.00
415,000.00
168,000.00
3,817,595.00 4,868,005.00
Jumlah Bahan Jumlah Upah & Keuntungan Harga Yang
Kebutuhan Harga Total
Bahan dan Pajak Harus Dibayar

342,125.00
25,012.50
6,210.00
2,205,000.00
47,221.88
861,000.00
3,486,569.38 4,110,939.38

70,000.00
16,640.00
13,769.00
100,409.00 165,934.00

20,448.00
5,620.00
26,068.00 84,643.00

6,500.00
6,500.00 48,286.00

13,000.00
5,901.00
18,901.00 38,221.00
Jumlah Bahan Jumlah Upah & Keuntungan Harga Yang
Kebutuhan Harga Total
Bahan dan Pajak Harus Dibayar

160,600.00
20,000.00
12,645.00
4,500.00
197,745.00 371,485.00

73,700.00
18,600.00
5,058.00
4,500.00
101,858.00 325,238.00

2,800.00
7,540.00
10,340.00 25,040.60
Jumlah Bahan Jumlah Upah & Keuntungan Harga Yang
Kebutuhan Harga Total
Bahan dan Pajak Harus Dibayar
enutup) / M2

2,800.00
11,700.00
14,500.00 30,400.60

9,204,000.00
9,204,000.00 11,887,522.50

163,185.80

423,621.70

151,000.00
151,000.00 235,655.00
Jumlah Bahan Jumlah Upah & Keuntungan Harga Yang
Kebutuhan Harga Total
Bahan dan Pajak Harus Dibayar
68,000.00
68,000.00 97,187.75

29,363,000.00
737,000.00
108,000.00
150,000.00
900,000.00
186,000.00
786,000.00
462,000.00
234,000.00
178,000.00
1,150,000.00
34,254,000.00 34,254,000.00

34,100.00
7,700.00

41,800.00 50,974.00
Jumlah Bahan Jumlah Upah & Keuntungan Harga Yang
Kebutuhan Harga Total
Bahan dan Pajak Harus Dibayar

269,723.25
67,430.81
480.00
6,000.00
32,000.00
26,000.00
401,634.06 460,459.06

269,723.25
67,430.81
480.00
6,000.00
32,000.00
26,000.00
401,634.06 422,959.06

2,200,000.00

76,000.00
2,276,000.00 2,327,775.00

2,540,327.00
66,000.00
2,606,327.00 2,634,327.00
Jumlah Bahan Jumlah Upah & Keuntungan Harga Yang
Kebutuhan Harga Total
Bahan dan Pajak Harus Dibayar

3,248,000.00
76,000.00
2,166,500.00
3,248,000.00 3,306,825.00

214,000.00
12,000.00
76,000.00
214,000.00 272,825.00

213,000.00
7,000.00
12,000.00
2,810.00
234,810.00 698,880.00
Jumlah Bahan Jumlah Upah & Keuntungan Harga Yang
Kebutuhan Harga Total
Bahan dan Pajak Harus Dibayar

155,000.00
37.50
155,037.50 175,292.50

8,400.00
24,500.00
32,900.00 49,340.60

25,200.00
24,500.00
49,700.00 86,700.20

44,400.00
24,500.00
68,900.00 124,409.15
Jumlah Bahan Jumlah Upah & Keuntungan Harga Yang
Kebutuhan Harga Total
Bahan dan Pajak Harus Dibayar

#REF!

66,255.00

326,000.00

397,100.00
36,100.00
433,200.00 481,247.00

243,000.00
17,010.00
260,010.00 301,760.00
Jumlah Bahan Jumlah Upah & Keuntungan Harga Yang
Kebutuhan Harga Total
Bahan dan Pajak Harus Dibayar

435,833.33
35,437.71
471,271.04 513,021.04

401,666.67
32,660.46
434,327.13 476,077.13

745,833.33
60,655.14
806,488.47 848,238.47

99,000.00
2,810.00
101,810.00 126,210.00

L27
L11
L05
L01
5,431,500.00
2,754,100.80
84,065.00
23,920.00
Jumlah Bahan Jumlah Upah & Keuntungan Harga Yang
Kebutuhan Harga Total
Bahan dan Pajak Harus Dibayar
2,097.60
96,600.00 M126
8,392,283.40 11,174,653.20 M148.c
Produktivitas
Waktu (Hari)
(m2)

947.3710561398 1.000

23 27
Produktivitas
Waktu (Hari)
(m2)

26 5.00

139 1.00

115 1.00

15 2.000

2.25

14.76 6.0000

14.76 3.00
Produktivitas
Waktu (Hari)
(m2)

14.7635684056 1.0000

14.7635684056 6.00

14.7635684056 0

14.7635684056 3.712517

14.7635684056 5.4614167649

14.7635684056 0.3454449399
Produktivitas
Waktu (Hari)
(m2)

38.3333333333 0.2086956522

38.3333333333 6.7262608696

38.3333333333 6.3709565217

38.3333333333 22.9630434783

38.3333333333 0.6944347826
Produktivitas
Waktu (Hari)
(m2)
Produktivitas
Waktu (Hari)
(m2)
Produktivitas
Waktu (Hari)
(m2)
Produktivitas
Waktu (Hari)
(m2)
Produktivitas
Waktu (Hari)
(m2)
BACK
PROGRAM : -
KEGIATAN : -
PEKERJAAN : -
LOKASI : -
TH. ANGGARAN : -

No. URAIAN PEKERJAAN

I. PEKERJAAN PERSIAPAN
1 Pengukuran
2 Pembersihan lokasi awal s/d akhir pekerjaan
3 Mobilisasi Demobilisasi Bahan dan Peralatan

II. PEKERJAAN TANAH


1 Galian Tanah
Galian Pile Cap Tipe A
Galian Pile Cap Tipe B
Galian Batu Kali
2 Urugan Pasir , t = 5 cm
-Dibawah Pondasi Batu Kali
-Dibawah footplat 1
-Dibawah footplat 2

3 Urugan Kembali

III. PEKERJAAN PASANGAN


1 Pondasi Batu kali, lebar atas = 30 cm
2 Pasangan Batu Kosong

IV. PEKERJAAN BETON


1 Pondasi Pile Cap
- Pondasi Pile Cap Type A
- Pondasi Pile Cap Type B
2 Lantai kerja beton t = 10 cm
- Lantai kerja beton untuk Pile Cap Type A
- Lantai kerja beton untuk Pile Cap Type B
- Lantai Kerja Pondasi Batu Kali
3 Plat lantai beton , t = 13 cm
4 Beton Sloof
- SLOOF 30 X 50 CM
5 Beton Kolom
- KOLOM STRUKTUR 40 x 40 cm
7 Beton Balok
- Balok B1
- Balok B2
- Balok B3
- Balok B4
- Balok B5
- Balok B6
- Balok B7
8 Beton Bertulang Plat Atap
- Beton Bertulang Plat atap t = 13 cm
9 Beton untuk tangga, t = 13 cm
10 Beton Bordes
V. PEKERJAAN PEMANCANGAN
1 Tiang Pancang
- Tiang Pancang Diamter 30cm
- Tiang Pancang Diamter 40cm
- Potong Tiang Pancang

VI. PEKERJAAN TULANGAN


1 Tulangan Balok
- Tulangan Balok B1 Total Panjang Unit Satuan (Kg/m)
Tumpuan
- D22 25248 4.34
Lapangan
P1 D22 6791 4.34
P2 D22 6471 4.34
Tengah D10 6791 0.56
Sengkang Ф10 1400 0.617
- Tulangan Balok B2 Total Panjang
Tumpuan D22 27048 4.34
Lapangan
P1 D22 7376 4.34
P2 D22 7071 4.34
Tengah D10 7376 0.56
Sengkang Ф10 1800 0.617
- Tulangan Balok B3 Total Panjang
Tumpuan D22 12624 4.34
Lapangan
P1 D22 6791 4.34
P2 D22 6471 4.34
Tengah D10 6791 0.56
Sengkang Ф10 1400 0.617
- Tulangan Balok B4 Total Panjang
Atas D22 4371 4.34
Bawah D22 1615 4.34
Sengkang Ф10 800 0.617
- Tulangan Balok B5 Total Panjang
Tumpuan D22 9024 4.34
Lapangan
P1 D22 4391 4.34
P2 D22 6558 4.34
Tengah D10 4391 0.56
Sengkang Ф10 1100 0.617
- Tulangan Balok B6 Total Panjang
Atas D22 3791 4.34
Bawah D22 3435 4.34
Sengkang Ф10 1100 0.617
- Tulangan Balok B7 Total Panjang
Tumpuan D22 27048 4.34
Lapangan
P1 D22 7376 4.34
P2 D22 7071 4.34
Tengah D10 7376 0.56
Sengkang Ф10 1100 0.617
2 Tulangan Kolom Total Panjang Unit Satuan (Kg/m)
Lantai 1 D16 4562 1.58
Ф10 1430 0.617
Lantai 2 D16 3072 1.58
Ф10 1430 0.617
3 Tulangan Sloof Total Panjang Unit Satuan (Kg/m)
AS A F D16 32668 1.58
Ф10 1400 0.617
AS B,C,D,E D16 59328 1.58
Ф10 1400 0.617
AS A',E' D16 25384 1.58
Ф10 1400 0.617
AS B' D16 5786 1.58
Ф10 1400 0.617
AS C1,C',C2,E1 D16 17136 1.58
Ф10 1400 0.617
AS 1,3 D16 14472 1.58
Ф10 1400 0.617

4 Tulangan Plat
P1 Y Total Panjang Unit Satuan (Kg/m)
1 Ф10 165 0.617
2 Ф10 569.5 0.617
3 Ф10 38 0.617
4 Ф10 569.5 0.617
5 Ф10 541.5 0.617
P1
P1 X Total Panjang Unit Satuan (Kg/m)
1 Ф10 105 0.617
2 Ф10 329.5 0.617
3 Ф10 105 0.617
4 Ф10 329.5 0.617
5 Ф10 301.5 0.617
P2 Y Total Panjang Unit Satuan (Kg/m)
1 Ф10 174.5 0.617
2 Ф10 633.4 0.617
3 Ф10 174.5 0.617
4 Ф10 633.4 0.617
5 Ф10 605.4 0.617
P2
P2 X Total Panjang Unit Satuan (Kg/m)
1 Ф10 112 0.617
2 Ф10 329.5 0.617
3 Ф10 112 0.617
4 Ф10 329.5 0.617
5 Ф10 301.5 0.617
P3 Y Total Panjang Unit Satuan (Kg/m)
1 Ф10 131 0.617
2 Ф10 395.5 0.617
3 Ф10 131 0.617
4 Ф10 395.5 0.617
5 Ф10 381.5 0.617
P3
P3 X Total Panjang Unit Satuan (Kg/m)
P3

1 Ф10 109 0.617


2 Ф10 329.5 0.617
3 Ф10 109 0.617
4 Ф10 329.5 0.617
5 Ф10 301.5 0.617
P4 Y Total Panjang Unit Satuan (Kg/m)
1 Ф10 109 0.617
2 Ф10 329.5 0.617
3 Ф10 109 0.617
4 Ф10 329.5 0.617
5 Ф10 301.5 0.617
P4
P4 X Total Panjang Unit Satuan (Kg/m)
1 Ф10 74.5 0.617
2 Ф10 188 0.617
3 Ф10 74.5 0.617
4 Ф10 188 0.617
5 Ф10 160 0.617
P5 Y Total Panjang Unit Satuan (Kg/m)
1 Ф10 325.5 0.617
2 Ф10 325.5 0.617
P5
P5 X Total Panjang Unit Satuan (Kg/m)
1 Ф10 175.5 0.617
2 Ф10 175.5 0.617
5 Tulangan Tangga
- D12
- Ф8
6 Tulangan Pile Cap Type A
a b c Total Panjang (mm) Unit Satuan (Kg/m)
P1 D22 2520 840 264 3624 4.34
P2 D22 2520 264 2784 4.34
P3 D22 1720 840 264 2824 4.34
P4 D22 1720 264 1984 4.34
6 Tulangan Pile Cap Type B
a b c Total Panjang
P1 D22 1720 840 264 2824 4.34
P2 D22 1720 264 1984 4.34
P3 D22 1720 840 264 2824 4.34
P4 D22 1720 264 1984 4.34

VII. PEKERJAAN BEKISTING


1 Panel Bekisting Pile Cap
- Bekisting Pile Cap Type A
- Bekisting Pile Cap Type B
2 Panel Bekisting Sloof
3 Panel Bekisting Kolom
4 Panel Bekisting Balok
- Balok B1
- Balok B2
- Balok B3
- Balok B4
- Balok B5
- Balok B6
- Balok B7
5 Bekisting Pelat
6 Bekisting Tangga
BACK UP

tinggi jumlah luas


panjang lebar KOEF VOLUME

31.50 19.69 102.38


31.50 19.69 620.24
1.00
JUMLAH PEKERJAAN PERSIAPAN

116.59
1.80 2.60 1.00 6.00 28.08
1.80 1.80 1.00 18.00 58.32
1.00 1.00 1.50 4.00 6.00
43.20
1.000 -
1.80 2.60 0.50 6.00 14.04
1.80 1.80 0.50 18.00 29.16

1.000 116.59
JUMLAH PEKERJAAN TANAH

5.40 1.00 1.00 4.00 21.60


5.40 1.00 0.20 1.08
JUMLAH PEKERJAAN PASANGAN

86.40
1.80 2.60 1.00 6.00 28.08
1.80 1.80 1.00 18.00 58.32
9.04
1.80 2.60 0.10 6.00 2.81
1.80 1.80 0.10 18.00 5.83
1.00 1.00 0.10 4.00 0.40
31.50 19.69 0.13 80.63

198.34 0.30 0.50 29.75

0.40 0.40 6.36 24.00 24.42


54.81
64.80 0.30 0.50 9.72
114.57 0.40 0.60 27.50
48.74 0.30 0.50 7.31
18.18 0.20 0.30 1.09
18.09 0.25 0.40 1.81
6.03 0.25 0.40 0.60
60.30 0.25 0.45 6.78

31.50 19.69 0.13 80.63


0.30 3.50 0.13 64.00 4.37
1.50 3.50 0.13 2.00 0.68

JUMLAH PEKERJAAN BETON


15.40 36.00 554.40
15.40 - - 72.00 - 1,108.80
0.60 108.00 64.80
JUMLAH PEKERJAAN PEMANCANGAN

Jumlah Total Berat

12 1,314.92

12 353.68
12 337.01
12 45.64
72 62.19

19 2,230.38

19 608.22
19 583.07
19 78.48
80 88.85

9 493.09

9 265.26
9 252.76
9 34.23
72 62.19

12 227.64
12 84.11
21 10.37

6 234.98

6 114.34
6 170.77
6 14.75
48 32.58

2 32.91
2 29.82
47 31.90

10 1,173.88

10 320.12
10 306.88
10 41.31
80 54.30
Jumlah Total Berat
24 172.99
24 21.18
24 116.49
24 21.18
Jumlah Total Berat(Kg)
32 1,651.69
165 142.53
64 5,999.25
298 257.41
32 1,283.42
128 110.57
16 146.27
30 25.91
64 1,732.79
87 75.15
32 731.70
74 63.92

Jumlah Total Berat


16 16.29
8 28.11
16 3.75 129.72
8 28.11
16 53.46
Jumlah Total Berat
28 18.14
14 28.46
28 18.14 145.29
14 28.46
28 52.09
Jumlah Total Berat
15 16.15
8 31.26
15 16.15 150.86
8 31.26
15 56.03
Jumlah Total Berat
33 22.80
17 34.56
16 11.06 164.37
17 34.56
33 61.39
Jumlah Total Berat
16 12.93
8 19.52
16 12.93
8 19.52
16 37.66
Jumlah Total Berat
16 10.76
10 20.33
20 13.45
10 20.33
20 37.21
Jumlah Total Berat
8 5.38
4 8.13
8 5.38
4 8.13
8 14.88
Jumlah Total Berat
16 7.35
8 9.28
16 7.35
8 9.28
16 15.80
Jumlah Total Berat
7 14.06
4 8.03
Jumlah Total Berat
16 17.33
8 8.66

Jumlah Total Berat(Kg)


10 157.28
10 120.83
15 183.84 591.11
15 129.16

1,008.44
10 122.56
10 86.11
10 122.56 417.33
10 86.11

8.00 2.00
1.80 2.60 0.50 4.40
1.80 1.80 0.50 3.60
198.34 0.30 0.50 257.84
0.40 0.40 6.36 24.00 244.22
880.25 -
64.80 0.30 0.50 168.48
114.57 0.40 0.60 366.62
48.74 0.30 0.50 126.71
18.18 0.20 0.30 29.09
18.09 0.25 0.40 37.99
6.03 0.25 0.40 12.66
60.30 0.25 0.45 138.69
31.50 19.69 0.13 2.00 26.62
0.30 3.50 0.13 64.00 8.74

JUMLAH PEKERJAAN ELEKTRIKAL


SAT

m1

ls
PEKERJAAN PERSIAPAN







AH PEKERJAAN TANAH



PEKERJAAN PASANGAN













LAH PEKERJAAN BETON


m
m
m
RJAAN PEMANCANGAN
titik








EKERJAAN ELEKTRIKAL
BACK UP
PROGRAM : -
KEGIATAN : -
PEKERJAAN : -
LOKASI : -
TH. ANGGARAN : -

tinggi
No. URAIAN PEKERJAAN panjang lebar

I. PEKERJAAN PERSIAPAN
1 Pembuatan bouwplank 31.50 19.69
- Kepala tukang / Mandor

2 Pembersihan lokasi awal s/d akhir pekerjaan 31.50 19.69


3 Mobilisasi Demobilisasi Bahan dan Peralatan

II. PEKERJAAN TANAH


1 Galian Tanah
Galian Pile Cap Tipe A 1.80 2.60 1.00
Galian Pile Cap Tipe B 1.80 1.80 1.00
Galian Batu Kali 1.00 1.00 1.50
2 Urugan Pasir , t = 5 cm
-Dibawah Pondasi Batu Kali
-Dibawah footplat 1 1.80 2.60 0.50
-Dibawah footplat 2 1.80 1.80 0.50

3 Urugan Kembali

III. PEKERJAAN PASANGAN


1 Pondasi Batu kali, lebar atas = 30 cm 5.40 1.00 1.00
2 Pasangan Batu Kosong 5.40 1.00 0.20
Kolom 20 x 20 cm 3.65

IV. PEKERJAAN BETON


1 Pondasi Pile Cap
- Pondasi Pile Cap Type A 1.80 2.60 1.00
- Pondasi Pile Cap Type B 1.80 1.80 1.00
2 Lantai kerja beton t = 10 cm
- Lantai kerja beton untuk Pile Cap Type A 1.80 2.60 0.10
- Lantai kerja beton untuk Pile Cap Type B 1.80 1.80 0.10
- Lantai Kerja Pondasi Batu Kali 1.00 1.00 0.10
3 Plat lantai beton , t = 13 cm 31.50 19.69 0.13
4 Beton Sloof
- SLOOF 30 X 50 CM 198.34 0.30 0.50
5 Beton Kolom
- KOLOM STRUKTUR 40 x 40 cm 0.40 0.40 6.36
7 Beton Balok
- Balok B1 64.80 0.30 0.50
- Balok B2 114.57 0.40 0.60
- Balok B3 48.74 0.30 0.50
- Balok B4 18.18 0.20 0.30
- Balok B5 18.09 0.25 0.40
- Balok B6 6.03 0.25 0.40
- Balok B7 60.30 0.25 0.45
8 Beton Bertulang Plat Atap
- Beton Bertulang Plat atap t = 9 cm 30.15 19.69 0.90
9 Beton untuk tangga, t = 13 cm 0.30 3.50 0.13
10 Beton Bordes 1.50 3.50 0.13
V. PEKERJAAN PEMANCANGAN
1 Tiang Pancang
- Tiang Pancang Diamter 30cm 15.40
- Tiang Pancang Diamter 40cm 15.40 - -
- Potong Tiang Pancang 0.60

VI. PEKERJAAN TULANGAN


1 Tulangan Balok
- Tulangan Balok B1
- D22 64.80 0.016
- D10 64.80 0.01
- Tulangan Balok B2
- D22 114.57 0.016
- D16 114.57 0.01
- Tulangan Balok B3
- D19
- D10
- Tulangan Balok B4
- D19
- D10
- Tulangan Balok B5
- D22
- D10
- Tulangan Balok B6
- D19
- D10
- Tulangan Balok B7
- D19
- D10
2 Tulangan Kolom
- D16

3 Tulangan Sloof
- D16

4 Tulangan Plat
- Ф10
- Ф8
5 Tulangan Tangga
- D12
- Ф8

2 Pengecatan Dinding Baru Dalam

VII. PEKERJAAN BEKISTING


1 Panel Bekisting Pile Cap
- Bekisting Pile Cap Type A 1.80 2.60 0.50
- Bekisting Pile Cap Type B 1.80 1.80 0.50
2 Panel Bekisting Sloof 198.34 0.30 0.50
3 Panel Bekisting Kolom 0.40 0.40 6.36
4 Panel Bekisting Balok
- Balok B1 64.80 0.30 0.50
- Balok B2 114.57 0.40 0.60
- Balok B3 48.74 0.30 0.50
- Balok B4 18.18 0.20 0.30
- Balok B5 18.09 0.25 0.40
- Balok B6 6.03 0.25 0.40
- Balok B7 60.30 0.25 0.45
5 Bekisting Pelat 31.50 19.69 0.13
6 Bekisting Tangga 0.30 3.50 0.13
P

jumlah luas
KOEF VOLUME SAT

102.38 m1

620.24 m²
1.00 ls
JUMLAH PEKERJAAN PERSIAPAN

116.59
6.00 28.08 m³
18.00 58.32 m³
4.00 6.00 m³
43.20 m³
1.000 - m³
6.00 14.04 m³
18.00 29.16

1.000 116.59 m³
JUMLAH PEKERJAAN TANAH

4.00 21.60 m³
1.08 m³
936.000 13,665.60 m1
JUMLAH PEKERJAAN PASANGAN

6.00 28.08 m³
18.00 58.32 m³

6.00 2.81 m³
18.00 5.83 m³
4.00 0.40 m³
80.63 m³
29.75 m³

24.00 24.42 m³

9.72 m³
27.50 m³
7.31 m³
1.09 m³
1.81 m³
0.60 m³
6.78 m³

267.14 m³
64.00 4.37 m³
2.00 0.68 m³

JUMLAH PEKERJAAN BETON


36.00 554.40 m
72.00 - 1,108.80 m
108.00 64.80 m
JUMLAH PEKERJAAN PEMANCANGAN

8.00
2.00

8.00
2.00

- m²

2.00 titik
4.40 m²
3.60 m²
257.84
24.00 244.22 m²
-
168.48 m²
366.62 m²
126.71 m²
29.09 m²
37.99 m²
12.66 m²
138.69 m²
26.62 m²
64.00 -----

JUMLAH PEKERJAAN ELEKTRIKAL


BURAM
PROGRAM : PEMBANGUNAN PASAR BATU UNIT SAYUR KOTA SURABAYA
KEGIATAN : PEMBANGUNAN PASAR BATU UNIT SAYUR KOTA SURABAYA
PEKERJAAN : PEMBANGUNAN PASAR BATU UNIT SAYUR KOTA SURABAYA
LOKASI : JL. GUBENG KERTAJAYA - KOTA SURABAYA
TH. ANGGARAN : 2018

tinggi
No. URAIAN PEKERJAAN panjang lebar

I. PEKERJAAN PERSIAPAN
1 Papan Nama proyek
2 Pembuatan bouwplank 75.00 72.00
3 Pagar sementara setinggi 2 m 76.00 73.00
4 Pembersihan lokasi awal s/d akhir pekerjaan 6.00 72.00
5 Listrik dan Air Kerja
6 Perbaikan Kembali Akses Jalan dan Saluran
7 Mobilisasi Demobilisasi Bahan dan Peralatan 90.00
8 Pembuatan direksi keet 18.00 5.00
9 Pembuatan gudang bahan 3.00 6.00
10 Pembuatan Bedeng Relokasi Pedagang (Tidak Permanen)
2.00 3.00
3.00 5.00
12 Pembongkaran bangunan eksisting LOS 1 - 18 7.15 48.65
DOK 1 & 2 12.00 8.00
DOK 3 15.00 12.50
LOS 21 10.00 5.00
LOS 19 76.50 10.50
LOS 23 30.10 7.00

13 Pengganti BPJS

II. PEKERJAAN TANAH


1 Galian Tanah Keras Sedalam 1 Meter / M3
- Batu Kali 18.00 1.00 1.15
- untuk pondasi footplat 1 0.80 0.80 0.90
- untuk pondasi footplat 2 0.50 0.50 0.50
- untuk Galian U Ditch 379.00 0.64 0.72
- untuk Galian bak kontrol 0.90 0.70
2 Urugan Pasir , t = 5 cm
-Dibawah Pondasi Batu Kali 18.00 1.00 0.05
-Dibawah footplat 1 0.80 0.80 0.05
-Dibawah footplat 2 0.50 0.50 0.05

3 Urugan Kembali
4 Cutting tanah 72.00 17.50 0.75

III. PEKERJAAN PASANGAN


1 Pondasi Batu kali, lebar atas = 30 cm 18.00 0.80
2 Pasangan Batu Kosong 18.00 1.00 0.20
3 Pasangan Dinding
- trasram 1,344.98 0.50
- dinding 1,344.98 3.00
- dinding di atas plat leuvel 64.00 1.00
- Pasangan bata merah tebal 1 bata, 1 Pc : 5 Ps
4 Pasangan Dinding Kamar Mandi

5 Pekerjaan Plesteran
6 Pekerjaan Acian
7 Benangan
Plat liufel 66.00 13.00
57.00 7.50
55.50 7.00
Kolom 20 x 20 cm 3.65

IV. PEKERJAAN BETON


1 Pondasi footplat
- Pondasi footplat 80 x 80 cm 0.80 0.80 0.20
- Pondasi footplat 50 x 50 cm 0.50 0.50 0.20
2 Lantai kerja beton K 150, t = 5 cm
- Lantai kerja beton untuk footplat 80 x 80 cm 0.80 0.80 0.05
- Lantai kerja beton untuk footplat 50 x 50 cm 0.50 0.50 0.05
3 Plat lantai beton , t = 5 cm TOTAL LUAS 70.00 72.00 0.05
LUAS TENGAH 52.00 46.00 0.05
4 Beton Sloof
- SLOOF 15 X 25 CM 1,344.98 0.15 0.25
- SLOOF 15 X 20 cm Lantai Los Terbuka
- SLOOF 15 X 20 cm Memanjang 56.00 0.15 0.20
- SLOOF 15 X 20 cm Melintang 50.00 0.15 0.20
5 Beton Kolom
- KOLOM PENDEK 20 X 20 cm 0.20 0.20 1.10
- KOLOM PENDEK 15X 15 cm 0.15 0.15 0.75
- KOLOM PRAKTIS 15 X 15 cm

- KOLOM STRUKTUR 20 x 20 cm 0.20 0.20 3.65


6 Ring Balok
- Ring Balok 15 x 20 CM 1,344.98 0.15 0.20
- Ring Balok Late 15 x 15 CM ( atas rolling door ) 408.00 1.00 1.00
7 Balok kantilever 15 x 15 cm 108.00 0.15 0.15
8 Beton Bertulang Plat Atap
- Beton Bertulang Plat leufel atap t = 8 cm
13.00 66.00 0.08
7.50 57.00 0.08
7.00 55.50 0.08
9 Beton untuk tangga depan, t = 12 cm 8.00 2.90 0.12
V. PEKERJAAN KUSEN
1 Pasang rolling door
Lantai 1
Rolling Door untuk Ruko Depan 2.50 7.50 3.00
Pasang daun pintu pvc Untuk Kamar Mandi
2.25 0.90
2.00 0.70
kusen km 1 2.25 0.90
kusen km 2 2.00 0.70

VI. PEKERJAAN PENGECATAN


1 Pengecatan Dinding Baru Luar
2 Pengecatan Dinding Baru Dalam

VII. PEKERJAAN ELEKTRIKAL


1
Panel Lantai 1
2
Instalasi penerangan
3
Instalasi stop kontak
4
Stop kontak
5
Saklar tunggal
6
Saklar ganda
7
Rumah dan Fiting Lampu
8
Lampu XL 13 WATT
Lampu LED 4 WATT
9 Lampu LED 7 WATT
10 Kabel feeder NYY 4 x 2.5 mm2 60.00

VIII PEKERJAAN LANTAI


1 Pemasangan dan Pengadaan Hydrant Pillar (HP)
2 Pemasangan dan Pengadaan VALVE-VALVE & FIXTURES dia 100 mm
3 Pemasangan dan Pengadaan Hose Reel Cabinet ( HRC )
4 Instalasi Pipa Hydrant 294.00
5 Galian Pipa Hydrant 323.40 0.60 0.40

VIII PEKERJAAN LANTAI


1 Lantai 1
Pekerjaan Lantai Acian untuk Kios TOTAL 70.00 72.00
2 Pasang lantai Keramik uk. 40x40 cm Motif los te TENGAH 52.00 46.00
3 Pasang keramik dinding kamar mandi 20X25 30.00 2.00
4 Pasang Lantai keramik ukuran 40 x 40 cm motif untuk tangga 72.00 1.50

IX PEKERJAAN SANITASI DAN PLUMBING


1 Closed Jongkok
2 Kran Air
3 Pipa untuk air bersih
4 Pipa untuk air kotor 523.00
5 Pipa untuk kotoran
6 Memasang Floor Drain
7 Memasang Roof Drain 23.00
IX PEKERJAAN ATAP BAJA RINGAN
1 Rangka Atap Baja Ringan
2 Penutup Atap Metal Sheet tebal min 0.45 mm

X PEKERJAAN LAIN - LAIN


1 Pembuatan Papan Nama
2 Aluminium Composite Panel ( Standart )
0.25 5.40
0.80 5.40
3 Pemasangan jalusi hollow ukuran 0.8 x 5,75 m + cat besi
4 Pasang Tanggulan Bata Keliling Atap
5 Pemasangan Bak kontrol uk. 120 X 75 X 100 cm
6 Pemasangan plat beton tutup bak kontrol uk. 120 X 75 X 12 cm
7 Pemasangan plat beton tutup U ditch uk. 50x60x12 cm
8 Pemasangan saluran U ditch uk. 50x50X120 146.40 146.40
9 Urugan pasir tebal 5 cm bawah saluran 286.80 0.60 0.05
10 Pekerjaan pasang paving tebal 8 cm k 500
72.00 5.00
72.00 1.60
12.00 2.00
11 Pekerjaan Pasangan Dinding Peninggian Lantai untuk kios pedagang
24.00 6.00 0.15
21.00 6.00 0.15
30.00 6.00 0.15
30.00 10.00 0.15
Pekerjaan Pasangan Dinding Peninggian Lantai untuk Teras 280.25 0.32

12 Isian sirtu padat untuk peninggian lantai


24.00 6.00 0.15
21.00 6.00 0.15
30.00 6.00 0.15
30.00 10.00 0.15
13 Urugan Sirtu Padat peninggian leveling lantai bangunan 72.00 70.00 0.20
14 Pekerjaan Water proofing Coating Lantai Atap
66.00 13.93
56.00 8.00
54.00 8.00
14 Pekerjaan Mengexpose plat level
1,330.00 0.24
M

jumlah luas
KOEF VOLUME SAT

1.00 ls
294.00 m1
298.00 m1
432.00 m²
6.00 bln
1.00 ls
1.00 ls
90.00 m²
18.00 m²
324.00 m²
49.00 294.00
2.00 30.00
347.85 m²
2.00 192.00 m²
187.50
50.00
803.25 m²
2.00 421.40
2,002.00
1.00 ls
JUMLAH PEKERJAAN PERSIAPAN

335.66 m³
20.70 m³
234.00 134.78 m³
14.00 1.75 m³
174.64 m³
6.00 3.78 m³
8.56 m³
1.000 0.90 m³
234.00 7.49 m³
14.00 0.18

1.000 584.39 m³
472.50 m³
JUMLAH PEKERJAAN TANAH

7.92 m³
3.60 m³
3,751.43 m2
672.49
4,034.94
64.00

-
-
-
-
7,566.86 m2
7,566.86 m2
14,489.60 m1
4.00 316.00 m1
4.00 258.00
4.00 250.00
936.000 13,665.60 m1
JUMLAH PEKERJAAN PASANGAN

234.00 29.95 m³
14.00 0.70 m³

234.00 7.49 m³
14.00 0.18 m³
252.00 m³
119.60 m³

50.44 m³
28.44
8.00 13.44
10.00 15.00

234.00 10.30 m³
14.00 0.24 m³
m'
m'
m'
234.00 34.16 m³

40.35 m³
408.00 m³
2.43 m³

168.12 m³
858.00 68.64 m³
2.00 855.00 68.40 m³
388.50 31.08 m³
1.39 m³
JUMLAH PEKERJAAN BETON
64.00 1,020.00 134.00 unit
15.25
2.00 4.05 m2
8.00 11.20 m2
2.00 8.10 m'
8.00 27.20 m'
JUMLAH PEKERJAAN KUSEN

2,795.43 m²
2,795.43 m²

2.00 titik
229.00 titik
136.00 titik
136.00 unit
136.00 unit
10.00 unit
229.00 unit
83.00 buah
8.00 buah
138.00 buah
75.00 m1
JUMLAH PEKERJAAN ELEKTRIKAL

4.00 titik
4.00 titik
4.00 titik
323.40 m'
77.62 m3
JUMLAH PEKERJAAN ELEKTRIKAL

256.00 m2
2,648.00 m2
2,392.00
60.00 m2
108.00 m2
JUMLAH PEKERJAAN LANTAI

8 unit
8 unit
88 m'
575.30 m'
22 m'
28 unit
2 46.00 unit
JUMLAH PEKERJAAN LANTAI

- m²
- m²
PEKERJAAN ATAP BAJA RINGAN

1.00 1.00 ls
136.08 m2
12.00 32.40
12.00 103.68
10 10 unit
488 m'
20 unit
20 unit
286.80 m'
286.80 m'
8.604 m3
163.2 m2
m2
115.2 m2
2.00 48 m2
p.tot 79.80 m2
120 18
108 16.2
144 21.6
160 24
-

m3
2.00 43.2
2.00 37.8
2.00 54
2.00 90
760.50 m3
1,527.86 m2
919.38 m2
2 896.00
432.00
2,566.58 m2
319.20

PEKERJAAN LAIN - LAIN


HSPK Surabaya, 15 Februari 2018
BI Inflasi : 0.0325

HARGA SATUAN HARGA SATUAN


PEMBULATAN
NO JENIS UPAH, BAHAN, ALAT, SPESIFIKASI, DAN MERK SATUAN DIKETAHUI SEPTEMBER 2018
( Rp. ) ( Rp. ) ( Rp. )
A UPAH
1 Pekerja / Pembantu Tukang Hari 145,000.00 149,712.50 150,000.00
2 Mandor Hari 171,000.00 176,557.50 177,000.00
3 Tukang Batu Hari 156,000.00 161,070.00 161,000.00
4 Kepala Tukang batu Hari 171,000.00 176,557.50 177,000.00
5 Tukang Kayu Hari 156,000.00 161,070.00 161,000.00
6 Kepala Tukang Kayu Hari 171,000.00 176,557.50 177,000.00
7 Tukang Besi Hari 156,000.00 161,070.00 161,000.00
8 Kepala Tukang Besi Hari 171,000.00 176,557.50 177,000.00
9 Tukang Cat Hari 156,000.00 161,070.00 161,000.00
10 Kepala Tukang Cat Hari 171,000.00 176,557.50 177,000.00
11 Tukang Pipa Hari 156,000.00 161,070.00 161,000.00
12 Kepala Tukang Pipa Hari 171,000.00 176,557.50 177,000.00
13 Tukang Listrik Hari 156,000.00 161,070.00 161,000.00
14 Kepala Tukang Listrik Hari 171,000.00 176,557.50 177,000.00
B BAHAN PEKERJAAN SIPIL DAN STRUKTUR
1 Pasir Urug ex. Lokal terbaik m³ 177,000.00 182,752.50 183,000.00
2 Sirtu ex. Lokal terbaik m³ 205,000.00 211,662.50 212,000.00
3 Pasir Cor / Beton ex. Lokal terbaik m³ 272,500.00 281,356.25 281,000.00
4 Pasir Pasang ex. Lokal terbaik m³ 272,500.00 281,356.25 281,000.00
5 Bata Merah ex. Lokal terbaik buah 800.00 826.00 1,000.00
6 Batu Pecah 2/3 ( pecah mesin ) ex. Lokal terbaik m³ 275,000.00 283,937.50 284,000.00
7 Batu Pecah 5/7 ex. Lokal terbaik m³ 275,000.00 283,937.50 284,000.00
8 Batu Kali / Gunung Belah ex. Lokal terbaik m³ 451,000.00 465,657.50 466,000.00
9 Batu Alam ex. Lokal terbaik m² 110,000.00 113,575.00 114,000.00
10 Semen Portland ex. Semen Indonesia,Tiga Roda, Gresik, Holcim kg 1,454.00 1,501.26 2,000.00
11 Semen Warna ex. Semen Indonesia,Tiga Roda, Gresik, Holcim kg 2,587.50 2,671.59 3,000.00
12 Besi Beton Polos ex. Bhirawa, Hanil, Master Steel, setara kg 13,500.00 13,938.75 14,000.00
13 Besi Beton Ulir ex. Bhirawa, Hanil, Master Steel, setara kg 14,950.00 15,435.88 15,000.00
14 Besi Profil ( IWF, CNP, Siku, Plate, Pipa ) ex. KS, Gunung Garuda kg 12,500.00 12,906.25 13,000.00
15 Pipa Stain less Dia. 4" t = 3,2 mm (Roll) ex. Lokal terbaik kg 20,125.00 20,779.06 21,000.00
16 Dynabolt ex. KS, Gunung Garuda kg 25,760.00 26,597.20 27,000.00
17 Mur Baut ( HTB ) ex. KS, Gunung Garuda kg 36,800.00 37,996.00 38,000.00
18 Atap Baja Ringan ex. Smart Truss, Pryda kg 24,437.50 25,231.72 25,000.00
19 Penutup Atap Zincalume + Peredam m2 315,500.00 325,753.75 326,000.00
20 Roofmesh m2 129,500.00 133,708.75 134,000.00
21 Paku ex. Lokal terbaik kg 15,933.00 16,450.82 16,000.00
22 Kawat Beton ex. Lokal terbaik kg 26,900.00 27,774.25 28,000.00
23 Kayu Dolken / Galam Ø 10 cm - 4 m ex. Lokal terbaik batang 11,500.00 11,873.75 12,000.00
24 Kayu Begesting Kl. IV ex. Lokal terbaik m³ - - -
25 Papan Begesting Kl. IV ex. Lokal terbaik m³ 4,188,000.00 4,324,110.00 4,324,000.00
26 Kayu Meranti / Kruing ex. Lokal terbaik m³ 3,350,400.00 3,459,288.00 3,459,000.00
27 Papan Kayu Kamper ex. Lokal terbaik m³ 9,455,000.00 9,762,287.50 9,762,000.00
28 Triplek 4 mm ex. Lokal terbaik lembar 64,000.00 66,080.00 66,000.00
29 Multiplek 9 mm ex. Lokal terbaik lembar 161,000.00 166,232.50 166,000.00
30 Minyak Begisting ex. Lokal terbaik ltr 30,100.00 31,078.25 31,000.00
31 Beton Ready Mix K 275 ex. Lokal terbaik m³ 861,679.00 889,683.57 890,000.00
32 Beton Ready Mix K 300 ex. Lokal terbaik m³ 870,674.00 898,970.91 899,000.00
33 Beton Ready Mix K 350 ex. Lokal terbaik m³ 916,404.00 946,187.13 946,000.00
34 Atap Spandek tebal 0,45 ex. Lokal terbaik lembar 75,000.00 77,437.50 77,000.00
35 Plat beton tutup Bak Kontrol uk 120x75x12 ex. Lokal terbaik bh 506,253.00 522,706.22 523,000.00
36 Plat beton tutup U-ditch uk 68x120x12 ex. Lokal terbaik bh 466,578.00 481,741.79 482,000.00
37 Saluran U ditch uk 50x50 cm ex. Lokal terbaik bh 866,502.00 894,663.32 895,000.00
38 Cover bak kontrol uk. 120X75X10 ex. Lokal terbaik bh 235,000.00 242,637.50 243,000.00
39 Besi Strip ex. Lokal terbaik kg 17,857.14 18,437.50 18,000.00
40 Pipa 4" 320,000.00 330,400.00 330,000.00
41 Pipa 2" 58,000.00 59,885.00 60,000.00
42 Ball joint diameter 3" 225,000.00 232,312.50 232,000.00
43 Paving tebal 8 cm K-500 96,167.00 99,292.43 99,000.00
C BAHAN PEKERJAAN ARSITEKTUR
1 Keramik Lantai 40 x 40 motif ex. KIA, Platinum, Roman m² 141,500.00 146,098.75 146,000.00
2 Keramik Lantai40 x 40 polos ex. KIA, Platinum, Roman m² 91,833.00 94,817.57 95,000.00
3 Keramik Lantai 20 x 25 ex. KIA, Platinum, Roman m² 65,000.00 67,112.50 67,000.00
4 Cat Dasar ex. Dulux, Jotun, Mowilex kg 26,806.50 27,677.71 28,000.00
5 Cat Dinding Eksterior ( weather shield ) ex. Dulux, Jotun, Mowilex kg 43,125.00 44,526.56 45,000.00
6 Cat Dinding Interior ex. Dulux, Jotun, Mowilex kg 27,772.50 28,675.11 29,000.00
7 Cat Minyak / Besi ex. Nippon Paint, Emco, Avian kg 62,905.00 64,949.41 65,000.00
8 Zincromate / Meni Besi ex. Nippon Paint, Emco, Avian kg 42,092.00 43,459.99 43,000.00
9 Cat Duco kg 33,000.00 34,072.50 34,000.00
10 Kusen Aluminium 4' Natural ex. Indal, Alexindo m' 126,500.00 130,611.25 131,000.00
11 ACP ( aluminium composite panel ) Outdoor 4mm tc ex. Seven, Alcopanel, Alucopan m² 350,000.00 361,375.00 361,000.00
12 0.5 mm, PVDF clear coating anti scratch alloy 3003 - -
13 Seng Gelombang ex. Lokfom, Fumira, setara lembar 63,000.00 65,047.50 65,000.00
14 Jendela Naco Uk. 15 cm x 90 Cm Bh 41,428.75 42,775.18 43,000.00
15 Kunci Tanam Bh 146,333.00 151,088.82 151,000.00
16 Paku skrup 3,5" bh 690.00 712.43 1,000.00
17 Sealant tube 41,428.75 42,775.18 43,000.00
18 Minyak Cat / Afduner liter 8,004.00 8,264.13 8,000.00
19 Kertas Gosok lembar 20,467.00 21,132.18 21,000.00
20 Besi Hollow 40/40 m' 97,000.00 100,152.50 100,000.00
21 Besi Hollow 20/40 m' 70,000.00 72,275.00 72,000.00
22 Pintu Rolling Door unit 8,913,937.50 9,203,640.47 9,204,000.00
23 Pintu PVC bh 331,300.00 342,067.25 342,000.00
24 Engsel Pintu bh 66,000.00 68,145.00 68,000.00
D BAHAN PEKERJAAN MEKANIKAL
1 Roof Drain Diecast Iron ex. Antasan, SanEi, setara 305,900.00 315,841.75 316,000.00
2 Coating Sikatop 107 kg 90,505.00 93,446.41 93,000.00
3 Kuas bh 34,743.00 35,872.15 36,000.00
4 Kloset jongkok bh 444,833.00 459,290.07 459,000.00
5 Pipa PVC tipe AW Ø 1/2" m' 6,600.00 6,814.50 7,000.00
6 Pipa PVC tipe AW Ø 4 " m' 20,633.33 21,303.92 21,000.00
7 Pipa PVC tipe AW Ø 6 " m' 35,916.67 37,083.96 37,000.00
8 Kran air bh 150,000.00 154,875.00 155,000.00
9 floor drain bh 45,000.00 46,462.50 46,000.00
10 Roof Drain Diecast Iron bh 305,900.00 315,841.75 316,000.00
11 Memasang 1 unit septictank kapasitas 50 orang unit 13,248,401.00 13,678,974.04 13,679,000.00
12 Saluran U ditch uk 50x50 cm bh 895,000.00 924,087.50 924,000.00
13 Kloset Jongkok Teraso bh 206,500.00 213,211.25 213,000.00
E BAHAN PEKERJAAN ELEKTRIKAL DAN ELEKTRONIK
Kabel Elektrik dan Elektronik - -
NYY - -
1 - 4×6 mm2 0,6/1 kV ex. Supreme, Kabelindo, Kabel Metal, Jembo m' 30,360.00 31,346.70 31,000.00
NYA - -
2 - 1×2,5 mm2 450/700 V ex. Supreme, Kabelindo, Kabel Metal, Jembo m' - - -
3 - Lampu led 7 Watt ex. Philip, Artolite, Saka, Osram, setara unit 48,875.00 50,463.44 50,000.00
4 - Lampu Led 4 Watt ex. Philip, Artolite, Saka, Osram, setara unit 26,450.00 27,309.63 27,000.00
5 - Rumah dan Fiting Lampu unit 116,437.50 120,221.72 120,000.00
6 - Lampu LED 13 watt unit 85,675.00 88,459.44 88,000.00
Type BC - -
7 - 1x6 mm2 ex. Supreme, Kabelindo, Kabel Metal, Jembo m' 7,128.85 7,360.54 7,000.00
NYM - -
8 - 3×2,5 mm2 300/500 V ex. Supreme, Kabelindo, Kabel Metal, Jembo m' 15,600.00 16,107.00 16,000.00
9 Stop Kontak ex. Clipsal, Panasonic, Berker, Legrand, setara unit 27,300.00 28,187.25 28,000.00
10 Saklar Tunggal ex. Clipsal, Panasonic, Berker, Legrand, setara unit 17,250.00 17,810.63 18,000.00
11 Saklar Double ex. Clipsal, Panasonic, Berker, Legrand, setara unit 49,400.00 51,005.50 51,000.00
12 Isolator m' 8,000.00 8,260.00 8,000.00
13 Las Doof bh 12,420.00 12,823.65 13,000.00
14 Konduit dia 20 mm (3/4") ex. Clipsal, Panasonic, Berker, Legrand, setara m' 3,808.80 3,932.59 4,000.00
15 Claim conduit bh 431.25 445.27 400.00
16 Box Panel 50 x 40 x 25 cm dan aksesoris lainnya bh 2,843,904.00 2,936,330.88 29,363,000.00
17 MCB 40A/3P, 10 kA bh 713,379.65 736,564.49 737,000.00
18 MCB 16A/1P, 6kA bh 105,050.00 108,464.13 108,000.00
19 Pilot Lamp RST+Fuse bh 48,000.00 49,560.00 50,000.00
20 Volt Meter bh 290,314.27 299,749.49 300,000.00
21 SSV bh 179,968.58 185,817.56 186,000.00
22 Ampere Meter bh 253,532.38 261,772.18 262,000.00
23 Shunt Trip bh 447,234.45 461,769.57 462,000.00
24 CT bh 226,602.77 233,967.36 234,000.00
25 Busbar m 172,500.00 178,106.25 178,000.00
26 Pipa Diameter 100 mm m' 206,942.50 213,668.13 214,000.00
27 VALVE-VALVE & FIXTURES dia 100 mm bh 2,479,400.00 2,559,980.50 2,560,000.00
28 Hose Reel Cabinet ( HRC ) lot 3,145,393.75 3,247,619.05 3,248,000.00
29 Hydrant Pillar (HP) bh 2,130,375.00 2,199,612.19 2,200,000.00
30 Flange bh 101,900.00 105,211.75 105,000.00
31 Inbow doos bh 5,375.00 5,549.69 6,000.00
F PERALATAN MEKANIK
1 Dozer jam - - -
2 Excavator PC 300 jam 1,226,664.00 1,266,530.58 1,267,000.00
3 Wheel Loader hari 5,064,800.00 5,229,406.00 5,229,000.00
4 Motor Grader hari 2,435,200.00 2,514,344.00 2,514,000.00
5 Vibro Roller hari 1,195,200.00 1,234,044.00 1,234,000.00
6 Water Tanker hari 1,518,000.00 1,567,335.00 1,567,000.00
7 Dump Truck Light Truck hari - - -
8 Crane 25 s/d 30 ton jam - - -
9 Jack In pile jam - - -
10 Genset type Silent 25 -50 kVA hari - - -
11 Pompa Air Mesin hari - - -
12 Throwel hari - - -
13 Vibrator hari - - -
14 Molen hari - - -
15 Survey ( Waterpass, Theodolit, dan Total Station ) hari - - -
16 PDA test titik - - -