Senior Lecturer cniwagaba@cedat.mak.ac.ug CHAPTER CONTENTS • Introduction/Definitions • Types of Planning – Comprehensive community, Comprehensive functional and definitive planning • Some Constraints of project planning • Planning and Design Considerations • Basis of Volume – Design period, Design population, Design demand, Peaking factors etc., • Sustainability of Water and Wastewater Management systems INTRODUCTION/DEFINITIONS • Planning: A sequence of anticipated actions that are to be executed for a purpose.
• System: A series of related processes
which achieve a certain end.
• Management: Decisions and actions,
which govern the working of a system. INTRODUCTION/DEFINITIONS • Project: A series of actions governed by: – objectives, – targets, – methodologies, – implementation, – operation, – maintenance and evaluation
• For a water supply project the different aspects of
planning are presented in the next slides: INTRODUCTION/DEFINITIONS • Objectives, may be to provide safe water to the community or industry in adequate quantities and at reasonable costs; and more specifically, for example; – To supply safe and wholesome water to the community and thereby control and combat diseases e.g. cholera, dysentery etc; – To promote hygiene; – To make water easily available to consumers; – For irrigation purposes, to boost agricultural productivity of a community; – For industrial purposes. Introduction Cont’d • Targets would be for example coverage – where you consider providing a given quantity of water to a given population by a given date e.g. 80 lpcd to 70% of the population by the year 2020.
• Targets depend on the service level – what is a
service level?
• Service level is a category or standard of water supply
service. The service level includes public standpipes, yard tap, house connection and non-piped supply. INTRODUCTION CONT’D • Methodologies: These include – Verification of the source (quantity and quality): Often a water resources assessment report is prepared – Determination of the demand – Choice of the treatment units, materials, equipment and identification of means of distribution etc. INTRODUCTION CONT’D • Implementation: A decision on what to implement and the actual implementation is guided by considerations of: • cost of the project (capital/ investment costs), • manpower requirements, • financial flows, • infrastructure (roads, buildings, etc), • topography, • legal aspects etc. Introduction Cont’d • Operation and maintenance: The major aim is to achieve sustainable utilization of the project. – Issues to consider include: • operation and maintenance daily schedules • decisions on manpower to be used, • identification of spare parts and other materials that will be routinely required etc. INTRODUCTION CONT’D • Evaluation of the project: – This involves an assessment of the impact of the project on the target community groups to see whether the objectives have been satisfied/met – See example next page. How to measure impact….. Prevalence of disease
Normal course
Impact
Course after implementation of
the project
-5yr 0yr t Time
How to measure impact…..
Course after implementation
85% of the project
Impact Water coverage
Normal course
40%
2002 2010 2035 Time
Conclusion on impact of a project • The impact of the project is the difference in results brought about by project implementation. • Note: That there are also negative impacts of projects e.g., – Irrigation – Schistosomiasis, – Hydropower – Dracunculiasis or river blindness, – Displacement of people. Evaluation of the project….. • Some times the evaluation may necessitate a value for money audit • The value for money audit of water and sanitation facilities needs a team: – Financial auditors/accountants, – Procurement specialists, – Engineers – Planners etc. Types of Planning
• Basically three levels/types of planning:
– Comprehensive community/general planning, – Comprehensive functional planning (also known as preliminary or feasibility study) and, – Definitive or project planning. Comprehensive Community/ General Planning • This is the study of the total region or part of the region within the context of the total region to identify priority projects. • It involves a study of the different aspects of public health and their inter-relation; which may include: – Water supply, – Wastewater management, – Solid waste management, – Community health services, etc. • It is a multidisciplinary activity involving the participation of politicians and policy makers, health and social workers, hydrologists, engineers, architects, planners etc. Comprehensive Community/ General Planning • A comprehensive community planning process includes: • A statement of the goals and objectives • Basic studies, mapping and data analysis • Plan preparation • Plan implementation • Public information and community action • Re-evaluation and continual planning Comprehensive Functional Planning/ Preliminary or Feasibility Study • Following the identification and selection of priority projects from the comprehensive community planning, a comprehensive feasibility study is carried out to consider in detail, the several ways (alternatives) in which the project can be executed, together with approximate costs.
• No detailed engineering or architectural construction plans
are prepared at this stage, but engineering, political, legal, economic and social feasibility or acceptance of each alternative is presented, with advantages and disadvantages, environmental impact, recommendations and cost estimates/source of funding.
• The study should be sufficiently complete to enable decision
makers (politicians) decide as well as NEMA and public information needs. Definitive/Project Planning • After the decision makers give a go ahead for the project, the next step is the establishment of the legal entity, e.g. Ministry (PC/PM, PMU) to administer the project as provided for by the state or local law.
• This is followed by acquisition of necessary rights,
resolution of any legal constraints, financing issues for capital and O&M, debt repayment, etc.
• Bidding is done to select consultant to design and
prepare plans, specifications, drawings.
• Legal entity e.g. Ministry advertises bids and
subsequently award the contract. DEFINITIVE/PROJECT PLANNING • Supervision is carried out by a consulting engineer (not necessarily one who initially drew plans, specifications etc.).
• A site engineer is also employed to take charge of
the construction at the site (could be from Ministry or Ministry may appoint a Consultant Engineer to be RE).
• The consulting engineer provides updated
drawings/manuals and guidelines to the municipality and/or community as well as to the operation and maintenance personnel and trains staff to take over full operation. CONCLUDING REMARKS ON PLANNING
• The planning in the context of comprehensive
community/general planning, Comprehensive functional planning (preliminary or feasibility studies) and Definitive or project planning is the classical planning approach which is very much applicable to large scale water supply and wastewater management projects.
• For sanitation planning, especially when taking into account
on-site sanitation systems, the planning approaches may be different; and they differ by location, e.g. urban, or rural.
• Examples include CLTS, HCES, CLUES, Town Sanitation
Planning etc. Constraints of Project Planning • Lack of resources – Financial – Materials and equipment – Manpower (managerial, skilled workers etc.) – Land. • Infrastructure – Roads (access to the project site) – Communication – Energy – Water supply. Constraints of Project Planning • Institutional arrangement • Water supply and wastewater management projects are usually under a ministerial department or NGO, therefore: – responsibility at all levels should be ensured, – line of command should be clear, – protocol within institutions should be respected. • Political instability Constraints of Project Planning • Change of governments may lead to extermination of projects as different governments may have different priorities. • Public opinion • Negative attitudes, ignorance etc of the people may lead to failure of a project. Planning Considerations • In general terms, three basic steps are followed: – the determination of the current and future needs, – the appraisal of all possible means to meet these needs, – the selection of the most economic approaches for satisfying the anticipated requirements. Examples of activities of the planning process – Project site – Decisions about project site are usually made at a higher level e.g. by policy makers (politicians); – Size of the project area including information on population, economic land use, and other associated planning studies essential for the prediction of the water quality and quantity requirements for the various anticipated uses for the duration of the planning period chosen; – Topography – issues to answer: • Can the water (in case of water supply) flow by gravity with respect to distribution? • What of the wastewater? The existing topography should be exploited as much as possible to avoid pumping of wastewater. Examples of activities of the planning process – Hydrologic investigations to provide estimates of the quantities (and temporal/spatial distribution) of fresh surface water and groundwater entering the basin: • Use of data on the meteorological and hydrologic characteristics of the basin, • Field measurements, statistical analyses and modelling tools, • Determination of environmental flow requirements. – Comprehensive field investigations to evaluate the physical, chemical, radiological and biological characteristics of the surface waters of the basin. The information determined will indicate: • the degree to which the water should be treated for the various purposes, • the ability of the watercourse to assimilate waste discharges while continuing to sustain fish and wild life, and • the recreational and aesthetic values of the waters. Examples of activities of the planning process – Studies of the storage capacities and uses of existing and proposed reservoirs in the basin. • Involves detailed studies of the topography and geology of the basin to determine additional reservoir sites of a satisfactory nature. – Investigations to determine the location and extent of ground water storage, aquifer characteristics and the quality of the underground supplies; – Studies on existing and anticipated sources of wastes that may be introduced into surface and underground water bodies (anthropogenic pollution) • Knowledge of the characteristics and volumes of the wastes • Information on the optimum treatment the wastes. Examples of activities of the planning process – Estimates of water requirements to be used to augment low flows for quality and quantity control of surface water bodies. – Public health information on the area – such would include information on what kind of water related diseases e.g. water washed (quantity related) or water-borne (quality related). – Standards of living (socio-economic status) – affects the water use and consequently the quantities of wastewater generated; – Availability of local materials for construction – affects construction costs; – Legal aspects – Activity should not violate laws of the land. Examples of legal instruments: – Public Health Act, – National Environment Statute, – WHO (and if available, local) drinking water quality standards, – Discharge standards for wastewater etc. Examples of activities of the planning process – Manpower availability – both skilled and unskilled; – Construction, operation, maintenance and repair should preferably be within the competence of local technical staff. The available skills in the local community need to be utilised and improved, if required e.g., through training; – Evaluation of the benefits that will result from the proposed water supply and wastewater management project. Design considerations • QUANTITY of water (Yield of the source) – Will the source be exploited without distorting the biodiversity and ecological features of the area? – Will the source satisfy the minimum environmental flow requirement? • QUALITY of water from the water source. – Is it feasible to develop that source, given quality of the raw water and thus the nature of treatment required? • OR should an alternative source be identified given the water QUANTITY and QUALITY of the earlier identified source?