You are on page 1of 53

Deepwater Development

Flow / Thermal Management


and Subsea Production Concept

(an overall presentation)

by
T.M. Irfansyah
(Total E&P Indonesie)

Depok, 14 March 2009, Engineering Center FTUI

Subject

1. Introduction to Deepwater Development

2. Deepwater Flow Assurance (Hydraulic & Thermo Aspect)


ƒ Flow management
ƒ Thermal Management
ƒ Hydrate Management

3. Subsea Production Concept

4. Case Study & Discussion


ƒ Flowline Diameter & Thermal Insulation Sizing (Classical Loop)

2 - Depok, 14 March, Engineering Center FTUI

1
1. Introduction to Deepwater Development

3 - Depok, 14 March, Engineering Center FTUI

Introduction to Deep Water Development

4 - Depok, 14 March, Engineering Center FTUI

2
eline
press Pip
Neptune
Virgo

Canyon Ex
Marlin

Flowlines 2 x12”, 56 miles each


Ram-Powell

Water
Depth
2200m

King’s
Peak
Pipeline, daisy chain
Umbilical Camden
Hills
Subsea Well Aconcagua

5 - Depok, 14 March, Engineering Center FTUI

Typical sea bed

Courtesy of TOTAL

6 - Depok, 14 March, Engineering Center FTUI

3
Sea bed instability

7 - Depok, 14 March, Engineering Center FTUI

Typical Sea Water Temperature Profile


Hydrographic Profile

water temperature (°C)


0 5 10 15 20 25
0

-200

-400

-600
Water depth (m)

-800

-1000

-1200

-1400

-1600

8 - Depok, 14 March, Engineering Center FTUI

4
Deepwater - Typical Wellhead and Manifold

Manifold
X-tree

Flowline Jumper

Umbilical

9 - Depok, 14 March, Engineering Center FTUI

Deepwater - Typical Manifold

10 - Depok, 14 March, Engineering Center FTUI

5
Typical X-mas tree

11 - Depok, 14 March, Engineering Center FTUI

Instability and Gas Hydrates

12 - Depok, 14 March, Engineering Center FTUI

6
13 - Depok, 14 March, Engineering Center FTUI

Basic Option Deepwater Permanent Production Platform (1)

Up to 450 m

~ 300 to 600 m

~ 1200 m

14 - Depok, 14 March, Engineering Center FTUI

7
Basic Option Deepwater Permanent Production Platform (2)

~ 200 to 2300 m
~ 900 to 2300 m

~ 450 to 1700 m

15 - Depok, 14 March, Engineering Center FTUI

SPAR Platform
Gulf of Mexico
Depth + 800 m
215 m long, 37m diameter

16 - Depok, 14 March, Engineering Center FTUI

8
TLP (Tension Leg Platform)

Gulf Mexico
Depth + 900 m

17 - Depok, 14 March, Engineering Center FTUI

Typical Mini-TLP and FPSO

18 - Depok, 14 March, Engineering Center FTUI

9
FPSO (Floating Production Storage & Offloading)

19 - Depok, 14 March, Engineering Center FTUI

Remotely Operated Vehicles (ROV)

20 - Depok, 14 March, Engineering Center FTUI

10
Remotely Operated Vehicles (ROV)

ROV

ROV

21 - Depok, 14 March, Engineering Center FTUI

Deepwater various Risers and Flowlines

22 - Depok, 14 March, Engineering Center FTUI

11
SCR (Steel Catenary Riser)

Equipment Characteristic g
• Wet Insulation
• High load on facility
• U value > 2.5 W/m2 K

23 - Depok, 14 March, Engineering Center FTUI

Flexible Riser

Integrated Production Bundle

24 - Depok, 14 March, Engineering Center FTUI

12
Riser Tower

25 - Depok, 14 March, Engineering Center FTUI

Riser Tower

2 risers injection 8”
ID
4 Gaslift
Lines
4 risers production 8”
ID
Core pipe

Cathodic
protection

Syntactic
foam
element
Services Lines
2”
Straps

Bundle Insulation (Typical)

26 - Depok, 14 March, Engineering Center FTUI

13
Production Flowline

Wet insulation Pipe in Pipe insulation

Bundle insulation

27 - Depok, 14 March, Engineering Center FTUI

28 - Depok, 14 March, Engineering Center FTUI

14
2. Deepwater Flow Assurance
(Hydraulic and Thermo Aspect)
2.1. Flow management
2.2. Thermal Management
2.3. Hydrate Management

29 - Depok, 14 March, Engineering Center FTUI

Deepwater is critical in term of Flow Assurance


Very low temperature ( 2-4 oC at sea bed)

High Pressure in production flowline and riser

Often long tie-back

Complex sub-sea architecture/design and installation

Severe environment

Involving remote control and power supply

Retrievable sub-sea pieces of equipment

Fairly new type of development

30 - Depok, 14 March, Engineering Center FTUI

15
2. Deepwater Flow Assurance
2.1. Flow Management
a. Production Line Design
b. Minimum Flow Rate Criteria
c. Artificial Lift

d. Hydrodynamic flow study


e. Slug Flow Mitigation means

31 - Depok, 14 March, Engineering Center FTUI

a. Production Line Design


Line diameter determination, is based on many parameter, such us:
ƒ Fluid characteristic over field life: viscocity, density, water cut, Gas Oil Ratio,
Condensate Gas Ratio
ƒ Available pressure at well head along field life
ƒ Minimization of pressure drop at max rate and limitation of detrimental effect of a
possible diameter over-sizing
ƒ Flowline length and differential elevation between wells and process facilities.
ƒ Flowing velocity limitation (erosion velocity, ρv2 criteria)
ƒ Uniform line size is prefered for standarisation purpose.
ƒ If possible to avoid non standard pipe diameter, it could cause extra cost

Pipeline thickness, is based on mainly on:


ƒ Maximum Allowable Working Pressure
ƒ Max well shut-in pressure
ƒ Max gas lift injection pressure
ƒ Max chemical injection pressure
ƒ Collapse

32 - Depok, 14 March, Engineering Center FTUI

16
General Pressure Profile in Deepwater

33 - Depok, 14 March, Engineering Center FTUI

b. Minimum Flow Rate Criteria

Minimum expected stable in production line (and associated potential


liquid slud to be handled by receiving facilities)

Minimum flow rate related to steady state arrival temperature (SSAT)

Minimum flow rate related to required cool down time (CDT)


specification

34 - Depok, 14 March, Engineering Center FTUI

17
c. Artificial Lift

Today gas lift injection at riser base is most generally implemented

Gas lift injection is to lighten the liquid column


ƒ Decreases back pressure on the wells
ƒ Boosting oil production
ƒ Mitigation action on severe slugging (during low flow)
ƒ Important during well restart

Subsea multiphase pumps


ƒ For wells with very low pressure
ƒ As consequence, strong emulsion may be created

35 - Depok, 14 March, Engineering Center FTUI

d. Hydrodynamic flow study

To predict different flow regimes of production line, depending of the


anticipated operation condition (mainly gas and/or liquid flowrates,
water cut, gas lift injection rates and arrival topside pressure)

To determine safe operating envelope in term of flow stability

36 - Depok, 14 March, Engineering Center FTUI

18
Historical two-phase flow regime maps

Horizontal (Mandhane-Gregory-Aziz) Vertical (Duns & Ross)

37 - Depok, 14 March, Engineering Center FTUI

Two-phase flow regimes

38 - Depok, 14 March, Engineering Center FTUI

19
Generic flow regime maps, MPFM handbook

Horizontal Vertical

Black oil Black oil


( GOR < 260 SM3/Sm3 ) o il 3 ) ( GOR < 260 SM3/Sm3 ) oil m3 )
ile /Sm tilem3/S
la t m 3 l a
Vo 0 S
Vo 0 S
3 3
<5 <5
OR OR
(G (G

Dead Dead
oil oil Gas-Condensate
Gas-Condensate
( GOR > 530 Sm3/Sm3 ) ( GOR > 530 Sm3/Sm3 )

Dry gas Dry gas

Gas-dominated flow : Gas-dominated flow :


Transitions : Strat Î Wavy Î Annular Î Mist Transitions : Bubble Î Slug Î Churn Î Annular

Oil-dominated flow: Oil-dominated flow:


All transitions possible depending on GOR All transitions possible depending on GOR

39 - Depok, 14 March, Engineering Center FTUI

e. Slug Flow Mitigation means

Riser gas lifting

Riser top choking

Combined between riser gas lifting and riser top chocking

Slug Suppression System

40 - Depok, 14 March, Engineering Center FTUI

20
Riser-induced severe slugging

Liquid slug
reaches riser
top

Gas reaches
riser top

41 - Depok, 14 March, Engineering Center FTUI

Flow stabilisation / activation by gas-lift

FPSO

Riser

Gas lift injection


1500m

Tod
a y's
Subsea wells Off Flowline
sets
: 0.
5-
15
km

Subsea wells

A
42 - Depok, 14 March, Engineering Center FTUI

21
Riser-induced slugging
Slug control system

Principle
ƒ The opening of the slug control valve is automatically adjusted to maintain the
pressure at the riser base.
ƒ This pressure provides enough energy for the gas to lift the liquid as small slugs
and to prevent the formation of large liquid slugs filling the riser (severe slugs)
43 - Depok, 14 March, Engineering Center FTUI

Rriser-induced slugging
Otter Slug Suppression System (S3)
Principle Control of
Liquid in line
the total
flowrate
Liquid holdup m3

Gas + Liquid
Slug 150 m3

SSD
no SSD

0 2 4 6 8
Time (hr)

Pressure at riser base


SSD
no SSD
Pressure bar a
8 bar

With S3
Without S3
0 2 4 6 8
Time (hr)

44 - Depok, 14 March, Engineering Center FTUI

22
2. Deepwater Flow Assurance
2.2. Thermal Management
a. Steady State Arrival Temperature (SSAT)
b. Cool down time after Production Shutdown
c. Operating procedure after shutdown (for Classical Loop)

d. Thermal insulation systems


e. Slug Flow Mitigation means

45 - Depok, 14 March, Engineering Center FTUI

a. Steady State Arrival Temperature (SSAT)

is the Temperature obtained at upstream of 1st separator

can be set by different factors, among them:


ƒ Hydrate temperature
ƒ Wax appearance temperature (WAT)
ƒ Topsite temperature requirement (to ensure efficient oil/water separation, etc)

46 - Depok, 14 March, Engineering Center FTUI

23
General Temperature Profile in Deepwater

47 - Depok, 14 March, Engineering Center FTUI

Fluid related issues (physico-chemistry)

ASPHALTENES
Depth
S E
HYDRAT

CP
7000 m
Pressure

WAX 2
0m
∆T
?
∆P
1
VISC
OSIT
Y

Temperature
FLOW PATH:
1: onshore oil well
Reservoir- bottom hole 2: deep offshore oil
Well tubing/ wellhead
Flowline

48 - Depok, 14 March, Engineering Center FTUI

24
Hydrate
Hydrate &
& Wax
Wax Prevention
Prevention
Hydrate dissociation curves – Wax Appearance Temperature

350

300 Risk of
250 solid
Pressure, bar

200
deposition Safe
operating
150
domain
100
ProII
FHYD
50

0
0 5 10 15 20 25 30

Temterature, °C

49 - Depok, 14 March, Engineering Center FTUI

b. Cool down time after production shutdown

Is the time taken for the fluid to cool down to minimum acceptable
temperature (generally the hydrate temperature)

Cool down is driven by heat capacitance of fluid / material

Gas cools down more rapidly than liquid

The insulation requirement will always be driven by gas filled section

The thicker inner pipe wall the longer cool down time

50 - Depok, 14 March, Engineering Center FTUI

25
c. Operating Procedure After Shutdown
(Classical Loop)

Typical operation (preservation) sequence:


ƒ Shutdown Æ at time 0
ƒ Investigation (no touch) Æ typically 4 hours
ƒ Pressure equalization in network Æ typically 2 hours
ƒ MeOH injection in tubing, jumper, manifold well head and SPS Æ
typically 2 hours
ƒ Dead oil circulation in loop Æ 8 hours

Duration Elapsed Times (hours)


Operation
(hours) 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16
Shutdown 0
No touch 4
Pressure Equalization 2
MeOH injection (WH, jumper, manifold) 2
Dead Oil Circulation 8

51 - Depok, 14 March, Engineering Center FTUI

d. Thermal Insulation System

Three main technologies suitable for insulated flowline design:

Wet insulation

Bundle insulation

Pipe in Pipe insulation

52 - Depok, 14 March, Engineering Center FTUI

26
Flowline
Thermal insulation : Wet Insulation

53 - Depok, 14 March, Engineering Center FTUI

Flowline
Thermal insulation : Bundle Insulation

54 - Depok, 14 March, Engineering Center FTUI

27
Flowline
Thermal insulation : Pipe in Pipe Insulation

PCM = Phase Change Material


EHTP = Electrically Heat Traced Flowline

55 - Depok, 14 March, Engineering Center FTUI

Approach for Insulation Selection

56 - Depok, 14 March, Engineering Center FTUI

28
2. Deepwater Flow Assurance
2.3. Hydrate Management

57 - Depok, 14 March, Engineering Center FTUI

HYDRATES …

58 - Depok, 14 March, Engineering Center FTUI

29
HYDRATES
What are they?
Crystalline compounds that occur when water forms cage-like structures
around smaller “guest” molecules present in free water.

3 conditions have to be fulfilled for Hydrates to form :


ƒ the presence of water (“free”, dissolved or emulsified)
ƒ the presence of light hydrocarbons (from C1 to C4), or acid gas (CO2, H2S) or Nitrogen
ƒ meet the P, T conditions (depending on the nature & composition of gas)

Some heavier HC also form hydrates

Create operating problems because, at elevated pressures, they can exist at


higher temperatures than ice (e.g; 4°C @ 12bar or 20°C @ 100 bar)

Hydrates can be formed with or without presence of free (liquid) water

Also occur naturally underground, at & below seabed

59 - Depok, 14 March, Engineering Center FTUI

HYDRATES
What are they?

Hydrocarbons (C1,C2,C3,iC4+nC4)
and / or H2S, N2, CO2
+
H20
+
(P, T)
------------------------------------------
=
HYDRATES

I II

60 - Depok, 14 March, Engineering Center FTUI

30
Safety Hazards of Moving Hydrate Plugs
(Figure 1)

61 - Depok, 14 March, Engineering Center FTUI

Safety Hazards of High Pressure Trapped by Hydrates


(Figure 2)

62 - Depok, 14 March, Engineering Center FTUI

31
Avoiding Hydrate: three basic possibilities
P
Hydrates

Operational
Limits Dehydration

Dewpoint water
T

Inhibition

Control P-T domain


63 - Depok, 14 March, Engineering Center FTUI

Typical oil field hydrate management

Might be performed with the topsite shutdown

No part of production subsea system is allowed to enter hydrate formation


domain

No continuous inhibition by chemical injection (on the contrary, for gas field
continuous chemical injection common / recommended)

Flowline/Riser thermal insulation requirement:


ƒ In Steady-state flowing condition: Arrival temperature target (SSAT) > Hydrate temperature & WAT Î insulation
designed on U-value (paraffinic fluid, high WAT)
ƒ In Shut-down conditions: Cool down time (CDT, typically 16-20hr)

Classical loop preservation procedure during shut-down:


ƒ No-touch time (4 hr)
ƒ Pressure equalization
ƒ MeOH injection at cold points (WH, jumpers, manifolds…)
ƒ Dead oil circulation

Remediation philosophy in case of hydrate plug:


ƒ Pipeline and riser depressurization
ƒ Chemical (methanol) injection
ƒ Coiled tubing operation
ƒ Combinations of these options

64 - Depok, 14 March, Engineering Center FTUI

32
3. SUBSEA PRODUCTION CONCEPT

65 - Depok, 14 March, Engineering Center FTUI

3. SUBSEA PRODUCTION CONCEPT

3.1. Classical (Conventional) Loop

3.2. Hybrid Loop

3.3. Subsea Separation

66 - Depok, 14 March, Engineering Center FTUI

33
Classical Loop - General Principles:
is a subsea production system which consists of two production
flow lines working in parallel and linked together at the manifold
by a loop.

Water (and/or) gas injection lines system is installed using y


it
separate flow lines near the production loop.
ing Facil
Float
old
Manif
•Hydrate prevention strategy based on thermal
insulation, Methanol injection and dead oil
p
n Loo
circulation.
uctio
Prod

ƒ Wax strategy (thermal insulation + pigging)

ction
r Inje
Wate Injection
s
or Ga

67 - Depok, 14 March, Engineering Center FTUI

Classical Loop

Courtesy of TOTAL

68 - Depok, 14 March, Engineering Center FTUI

34
Typical subsea production system (classical loop)

Offloading Buoy

FPSO

Riser Towers

Injection Line
2 wellheads manifold
Production Loop
Production well
Umbilical
Injection Well
Courtesy of TOTAL

69 - Depok, 14 March, Engineering Center FTUI

Hybrid Loop - General Principles :


A hybrid system consists of interconnected production and water injection line.

it y
ing Facil
Float ine
tion L
anif old oduc
FluidMreplacement after shut-down le Pr
Sing
ƒ Circulation with WI pumps
ƒ Pigging philosophy: From Subsea Pig
p
launcher n Loo
ƒ ro ductio
pressurePequalization between the WI and the
prod. Line

Warm-up before well restart


ƒ Hot water circulation with water injection
pumps from WI to Prod
ƒ Water injection to be slightly insulated

ction
r Inje
Field Layout Wate Injection
s
ƒ Subsea Pig Launcher (depending on pigging or Ga
philosophy)
ƒ Single production flowlines and in-line tees
• Hydrate prevention strategy based on thermal
insulation, Methanol injection and water circulation.

70 - Depok, 14 March, Engineering Center FTUI

35
Typical Hybrid loop - Subsea Design

71 - Depok, 14 March, Engineering Center FTUI

Hybrid loop – Operating sequence:


Production/Shutdown
Water Injection
Topsides
MeOH

Live Oil
Production
Injection

Wells
Wells

Subsea Pig
Launcher

72 - Depok, 14 March, Engineering Center FTUI

36
Hybrid loop – Operating sequence:
Flushing/Pigging
Water Injection
Topsides
MeOH

Live Oil

Production
Injection

Wells
Wells

Subsea Pig
Launcher

73 - Depok, 14 March, Engineering Center FTUI

Subsea gas / liquid separation


General Principles:
ƒ Gas/liquid separation at the mud line
ƒ Gas export by 1 or 2 dedicated risers
ƒ Liquid export by 1 riser thanks to a
boosting system Gas riser
Liquid riser
ƒ Different hydrate philosophy
ƒ Gas: depressurisation + inhibition flowline 2ϕ sep.
ƒ Liquid: operation outside hydrate zone
ƒ Multiphase: depressurisation

ƒ SSU location Riser


Riser
top XV
top XV
ƒ Close to WH: potential operational
issue for gas risers
ƒ Close to RB: natural drainage of Sep gas
multiphase flowline PC
XV

Advantages: LAH

23bar
ƒ Hydrate preservation philosophy PWV
RO
Sep
60°C LC

Sep
Choke inlet
based on depressurization
LAL
inlet XV Pump
valve
bypass outlet XV
XV
ƒ Thermal insulation PMV
Separator
ROV
liquid XV Pumps
ƒ Line number and length ROV

ƒ Potential gain of Production


74 - Depok, 14 March, Engineering Center FTUI

37
Riser base gas/liquid separator
Single production flowlines and in-line tees

Gas-liquid separation at riser base and at lower pressure


(hydrate management by depressurization) Riser
top XV

Gas transferred through one (or more) dedicated riser Riser


top XV

Liquid transferred through one dedicated riser (pumping


required)
Sep gas
PC
XV

LAH

40/65bar
RO 55°C LC
PWV Sep
Sep
Choke inlet LAL
inlet XV Pump
valve
bypass outlet XV
PMV XV
Separator Pumps
ROV
liquid XV
ROV
ROV

75 - Depok, 14 March, Engineering Center FTUI

Riser base gas/liquid separation

Flow management
ƒ Hydrate prevention by low pressure operation in flowline, allows
relaxing the thermal insulation of the flowline
ƒ Elimination of slugging in the liquid riser
ƒ Wax management ? Î Applicable to non – paraffinic or low WAT
effluent

Drawbacks
ƒ Increased friction in flowline
ƒ Manifolding at riser base
ƒ Additional riser for gas transfer
ƒ Management of start up
ƒ Management of flow instability in the riser (liquid carry-over)

76 - Depok, 14 March, Engineering Center FTUI

38
Subsea Gas Liquid separation 0.00
-100.00
-200.00
-300.00
-400.00
-500.00
-600.00

Sea dep th (m )
-700.00
-800.00
-900.00
-1000.00
-1100.00
SSU @ WH
HydrateCurve
Hydrate curveof
of Field
Preowei
XYZwith
witha aSSU
SSUlocated close
located to the
close riser
to the bottom
riser bottom -1200.00 SSU @ Riser Base
-1300.00
bara
-1400.00
400 -1500.00
-1600.00
380
0 5000 10000 15000 20000 25000 30000
360 Horizontal distance (m )

340
320
300
280
Liquid // Pssu = 10 bara
260 Liquid // Pssu = 11 bara
Liquid // Pssu = 12 bara
240
Liquid // Pssu = 13 bara
220 Liquid // Pssu = 14 bara
Liquid // Pssu = 15 bara
200
Liquid // Pssu = 20 bara
180 Gas // Pssu = 10 bara
Reservoir fluid
160
140
120
100
80
60
40
20
0
-10 -5 0 5 10 15 20 25 °C

77 - Depok, 14 March, Engineering Center FTUI

4. Case Study & Discussion

Flowline Diameter & Thermal Insulation Sizing


(Classical Loop)

78 - Depok, 14 March, Engineering Center FTUI

39
4. Case Study & Discussion

Flowline Diameter & Thermal Insulation Sizing (Classical Loop)

Physical Properties Study


ƒ To get reservoir (fluid) data
ƒ To match the fluid model to the actual fluid (physical properties, fluid tuning)

Production Profile
ƒ To get production profile over field life (with the best forecast)

Hydraulic Study
ƒ Available Vs Required WHFP Profile
ƒ Determine ID of flowline with satisfy the production profile
ƒ Determine Gas Lift rate to ensure stability of flow

Thermal Study
ƒ Determine (adjust) the flowline and riser insulation to meet Cool Down Time
(hydrate curve) and Wax Appearance Temperature requirement

79 - Depok, 14 March, Engineering Center FTUI

Flow Assurance Methodology (Simplified Scheme): Classical & Hybrid Loop

Reservoir
Process Process
Reservoir PVT.tab (by ProII) Hydraulic Study Thermal Study
Data
Pipeline profile
Flowline ID Flowline type/insulation
Gas Lift Riser type/insulation
Etc.

Production
Profile OLGA Hydraulic
(QL, GOR, WC) Simulations OLGA Thermal
P is fixed at top site
Qmin. Simulations
T is fixed at WH GL Req.

Available Required Hydrate Curves


WHFP Profile WHFP Profile WAT Curves
CDT Req.
AWHFP>
RWHFP?
No
& Flow Stable?

Meet CDT No
Yes Requirement ?
Flowline ID
Gas Lift No Yes
Flow
Stable?

Yes Finish
80 - Depok, 14 March, Engineering Center FTUI

40
Physical Properties Study
Define PVT tab file for Simulation

Required Data for PVT Simulation


ƒ Components : C1-C10, Cn1, Cn2, N2, Component Mole Mw Tc Pc Omega Vc Sg
N2
CO2 CO2
C1
ƒ Percent mole C2
C3
ƒ Molecular Weight, MW iC4
nC4
ƒ Critical Temperature, Tc iC5
nC5
ƒ Critical Pressure, Pc C6
C7
ƒ Specific Volume, Vc C8
C9

ƒ Omega, ω
C10
Cn1
Cn2
ƒ Binary Coefficient, Kij

Compare physical properties: PVT Simulation


Parameter Unit PVT (lab)
Lab result Vs PVT simulation result value PVT gap (%)
Reservoir Pressure bara
Reservoir Temperature °C
3 3

Fluid Tuning GOR total


Tank density (@1 bara, 15°C)
Sm /Sm
kg/Sm
3

3
Density at reservoir condition kg/m
Bubble Point @ T reservoir bara
Viscosity @ 4°C, 1 bara cP
Viscosity @ 30°C, 1 bara cP
Viscosity @ 50°C, 1 bara cP
Viscosity @ Reservoir condition cP

81 - Depok, 14 March, Engineering Center FTUI

Conventional loop: Field XYZ, ID selection, No Gas Lift


Field XYZ Liquid Production Profile
Liquid Production Flowrates and associated Water Cut
120
90

100 80
53 kSbpd 70
80
Scenario: Field XYZ, Classical Loop, No Gas Lift 60
Water Cut (%)

Available & Required Pressure @ WH


kSbpd

50
60
Back Pressure from FPSO = 25 bara 40
40
L=31043.8 km, H (riser)=1667.5 m, U-flow line=3 W/m2.K, U-riser=3.5 W/m2.K 30
320 20
20
300 10
280 0 0
0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20
260 Tim e (years)
240 OIL RATE WAT RATE LIQ RATE
Liq. rate in ONE branch WC
220
200
WHFP (bara)

8” flowline ID
180
160
10” flowline ID
140 11” flowline ID
120
100 Available WHFP
80
60 Unstanble flows are notified
40
20
0
0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20
Tim e (years)
8" ID min WHFP 8" ID max WHFP 10" ID min WHFP 10" ID max WHFP
11" ID min WHFP 11" ID max WHFP 12" ID min WHFP 12" ID max WHFP
14" ID min WHFP 14" ID max WHFP A vailable WHFP

82 - Depok, 14 March, Engineering Center FTUI

41
Conventional loop: ID Selection, With Gas Lift
Scenario: Field XYZ, Classical Loop, ID=10", With Gas Lift
Available & Required Pressure @ WH
Back Pressure from FPSO = 25 bara
L=31043.8 km, H (riser)=1667.5 m, U-flow line=3 W/m2.K, U-riser=3.5 W/m2.K
200
180

increasing Gas Lift rate


160 Gas Lift 1000 kSm3/day
140
WHFP (bara)

120
100 Req WHFP is not always < Available WHFP
80
60
40
Required WHFP exceeds the available WHFP
20
0
0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20
Tim e (years)
Qlift=0 kSm3/d min WHFP Qlift=0 kSm3/d max WHFP Qlif t=100 kSm3/d min WHFP
Qlift=100 kSm3/d max WHFP Qlift=200 kSm3/ d min WHFP Qlif t=200 kSm3/d max WHFP
Qlift=400 kSm3/ d min WHFP Qlift=400 kSm3/ d max WHFP Qlif t=600 kSm3/d min WHFP
Qlift=600 kSm3/ d max WHFP Qlift=800 kSm3/ d min WHFP Qlif t=800 kSm3/d max WHFP
Qlift=1000 kSm3/d min WHFP Qlift=1000 kSm3/d max WHFP Available WHFP

Scenario: Field XYZ, Classical Loop, ID=11", With Gas Lift


Available & Required Pressure @ WH
Back Pressure from FPSO = 25 bara
L=31043.8 km, H (riser)=1667.5 m, U-flow line=3 W/m2.K, U-riser=3.5 W/m2.K
200
180
11” flowline ID
160
140 increasing Gas Lift rate Gas Lift 800 kSm3/day
WHFP (bara)

120
100 Req WHFP is always < Available WHFP
80
60
40
20 Required WHFP exceeds the available WHFP

0
0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20
Tim e (years)
Qlif t=0 kSm3/d min WHFP Qlift =0 kSm3/ d max WHFP Qlif t=100 kSm3/ d min WHFP
Qlif t=100 kSm3/ d max WHFP Qlift =200 kSm3/ d min WHFP Qlif t=200 kSm3/d max WHFP
Qlif t=400 kSm3/d min WHFP Qlift =400 kSm3/ d max WHFP Qlif t=600 kSm3/d min WHFP
Qlif t=600 kSm3/d max WHFP Qlift =800 kSm3/ d min WHFP Qlif t=800 kSm3/d max WHFP
83 - Depok, 14 March, Qlif
Engineering Center
t=1000 kSm3/ d min WHFP FTUI Qlift =1000 kSm3/d max WHFP Available WHFP

Conventional loop: 11” ID, flow stability, No Gas Lift


Scenario: Field XYZ, Classical Loop, No Gas Lift, ID=11''
Required Pres @WH Vs Liquid Prod Flow rate
Back Pres from FPSO=25 bara
L=31043.8 m, H(riser)=1667.6 m, U-flow line=3 W/m2.K, U-riser=3.5 W/m2.K
260

240
220

200
Required Pressure @ WH (bara)

stable flow
180
160
140

120
100 min WC = 0%
unstable flow 80
max WC = 0%
min WC = 30%
max WC = 30%
60 min WC = 50%
max WC = 50%
Preowei to Egina FPSO 40 min WC = 90%
Wellhead Manifold to FPSO max WC = 90%
20 Q design
-1100
0
-1150 10 15 20 25 30 35 40 45 50 55 60 65 70 75 80 85 90 95 100 105 110

-1200
Liquid Production Flow rate (kSbpd) / Branch
-1250

-1300
31 km
D epth (m)

-1350 400m
-1400

-1450

-1500

-1550

-1600
0 2 4 6 8 10 12 14 16 18 20 22 24 26 28 30 32 34
Length (km)

84 - Depok, 14 March, Engineering Center FTUI

42
Conventional loop: Field XYZ, 11” ID, WC 0%, Flow Stability,
Minimum Flow, Gas Lift Requirement

Scenario: Field XYZ, Classical Loop, GL 30°C, ID= 11'', WC=0%


Required Pres @WH Vs Gas Lift Flowrate
Back Pres from FPSO=25 bara, WHFT=46.7 °C
L=31043.8 m, H(riser)=1667.6 m, U-flow line=3 W/m2.K and U-riser=3.5 W/m2.K
340
320 Minimum Flow:
300
280
~ 15 to 25 k Sbpd
Required Pressure @ WH (bara)

260
240 11” flowline ID
220 Gas Lift for stabilisation
200
180
600 k Sm3/day
160
140
120
100 Increase GL to 800 kSm3/day
80
60 not significant to gain dP
40
20
0
0 100 200 300 400 500 600 700 800 900 1000
Gas Lift Flow rate (kSm 3/d) / Branch
min, Q = 10 kbpd max, Q = 10 kbpd min, Q = 15 kbpd max, Q = 15 kbpd min, Q = 20 kbpd
max, Q = 20 kbpd min, Q = 25 kbpd max, Q = 25 kbpd min, Q = 30 kbpd max, Q = 30 kbpd
min, Q = 40 kbpd max, Q = 40 kbpd min, Q = 55 kbpd max, Q = 55 kbpd min, Q = 65 kbpd
max, Q = 65 kbpd min, Q = 75 kbpd max, Q = 75 kbpd min, Q = 90 kbpd max, Q = 90 kbpd
min, Q = 110 kbpd max, Q = 110 kbpd

85 - Depok, 14 March, Engineering Center FTUI

Field XYZ hydrate curve


Hydrate Dissociation Curve of Field XYZ

450
0 g/l NaCl
10 g/l NaCl
400
33 g/l NaCl

350

300
Pressure (bara)

250
230 bara
(WHSIP)
200

150

100

50

0
0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21
Temperature (°C)

T hydrate = 18.5°C + 3°C = 21.5°C


86 - Depok, 14 March, Engineering Center FTUI

43
Thermal Study Scenario: Field XYZ, Classical Loop, ID=11",
Fluid tem perature during cool dow n,
GL=1 Million Sm3/day, Temp GL=30°C, L=31043 m, H(riser) = 1667 m,
U flow line PIP = 0.8 W/m2.K and U flexible riser = 2.5 W/m2.K
60 200
Initial Production flow rate @ FPSO = 20 kSbpd
55 WC = 0 % 0
50 Gas Lift @ Riser Base = 1 Million Sm3/day
-200
45 Steady state flow

Fluid temperature (°C)


-400
40 4 h shut dow n

Water detph (m)


35 8 h shut dow n -600
12 h shut dow n
30 -800
16 h shut dow n
25 20 h shut dow n -1000
24 h shut dow n
20
30 h shut dow n -1200
15 40 h shut dow n
-1400
10
5 -1600

0 -1800
0 5 10 15 20 25 30 35
Scenario:Distance
Field XYZ, Classical
from WH (km Loop,
) ID=11",
Steady state Fluid
flow tem perature
4 h shutduring
dow n cool dow n, 8 h shut dow n
12 h shut
GL=1 dow
Million n
Sm3/day, Temp16 h shut dow
GL=30°C, n
L=31043 20 h =
m, H(riser) shut dow
1667 m,n
24 h shut dow n 30 h shut dow n 40 h shut dow n
U flow line PIP = 0.8 W/m2.K and U flexible riser = 2.5 W/m2.K
Elevation
7 1.1
1
6
0.9
0.8

Liquid Holdup (m2/m2)


5
0.7
Pressure (Mpa)

4 0.6

0.5
3 0.4
0.3
2 Initial Production flow rate @ FPSO = 20 kSbpd
WC = 0 % 0.2
Gas Lift @ Riser Base = 1 Million Sm3/day 0.1
1
0
0 -0.1
0 5 10 15 20 25 30 35
Distance from WH (km )
P(Steady st ate f low) P(8 h shut down)
P(30 h shut down) Holdup(Steady stat e flow)
Holdup(8 h shut down) Holdup(30 h shut down)

87 - Depok, 14 March, Engineering Center FTUI

Thermal Study – Cool Down


Basis of Design: Base case
ƒ Tie-back: 27 km and Thyd = 18.6°C ƒ PiP aerogel: 0.8 W/m2°C
ƒ 8” ID + TD rate = 15 kbopd/branch (25%) ƒ Riser tower: 1.5 W/m2°C
ƒ NO WAT ƒ Flexible jumper: 3.4 W/m2°C
ƒ CDT: 19 hr
ƒ Design with conventional philosophy

bara PREOWEI Reference design 0g/l NaCl


Designing spot P&T envelop 33g/l NaCl + 1°C
250
33g/l NaCl + 2.7°C
1st Flexible
1st Riser
1st Flow line
2nd Flow line
200 2nd Riser
2nd Flexible
Thydrate (pure w ater) + 3°C of margin

150

100

50

[°C]
0
0 5 10 15 20 25 30 35 40 45 50

88 - Depok, 14 March, Engineering Center FTUI

44
Field XYZ dynamic

Field XYZ

89 - Depok, 14 March, Engineering Center FTUI

END
&
THANK YOU

90 - Depok, 14 March, Engineering Center FTUI

45
BACK UP

91 - Depok, 14 March, Engineering Center FTUI

Conventional loop: Filed XYZ, 11 ID, WC 0%, Flow Stability,


Minimum Flow, Gas Lift Requirement

Q=30kbbld - GL=700kSm3/d (6.14kg/s)


@ Wellhead @ RT bottom @ Topside

Max DP variation = 0.3bara

Q=30kbbld - GL=600kSm3/d (5.3kg/s)


@ Wellhead @ RT bottom @ Topside

Max DP variation = 0.15bara

92 - Depok, 14 March, Engineering Center FTUI

46
Conventional loop: Field YZ, 11” ID, WC 0%, Flow Stability,
Minimum Flow, Gas Lift Requirement

Q=25kbbld - GL=800kSm3/d (6.43kg/s)

@ Well Head
Max DP variation = 0 bara

@ Riser Tower Bottom


Max DP variation = 0 bara

93 - Depok, 14 March, Engineering Center FTUI

Conventional loop: Field YZ , 11” ID, WC 0%, Flow Stability,


Minimum Flow, Gas Lift Requirement

Q=25kbbld - GL=600kSm3/d (4.82kg/s)


@ Wellhead @ RT bottom @ Topside

Max DP variation = 3.5bara Max DP variation = 12bara Max DP variation = bara

Q=25kbbld - GL=800kSm3/d (6.43kg/s)


@ Wellhead @ RT bottom @ Topside

Max DP variation = bara Max DP variation = bara Max DP variation = bara

94 - Depok, 14 March, Engineering Center FTUI

47
95 - Depok, 14 March, Engineering Center FTUI

Definitions

Two-phase flow
Flow in which two phases are present; a gas phase and a hydrocarbon liquid phase

Multi-phase flow
Flow in which several phases are present; gas, hydrocarbon liquid, free water (with
chemical additives) and sometimes solids
Unlike in single-phase flow:
ƒ The fluid is not homogeneous
ƒ A segregation of the gas and the liquid phases occurs in the pipeline

Flow pattern or flow regime


The manner in which the gas and the liquid phases are distributed in a pipeline
section

96 - Depok, 14 March, Engineering Center FTUI

48
Effect of GOR and gravity on flow pattern
(steady-state two-phase flow)

ρG Decreases with pressure drop Consequence


Consequence
ρL Remains practically constant A
A multiphase
multiphase pipeline
pipeline can
can be
be seen
seen as
as

vG , actual gas velocity, increases Single-phase pipeline


Multiphase pipeline ~
with pressure drop, along the line +
Liquid storage tank
vL , actual liquid velocity, remains
practically constant, along the line
The
The flow
flow pattern
pattern in
in aa pipeline
pipeline is
is function
function
of:
of:
Slippage between gas and liquid phases GOR
GOR
Slip velocity: vslip = vG - vL Flowrate
Flowrate
Pipe
Pipe slope
slope
Flow direction
and
and may
may change
change along
along thethe pipe
pipe length
length

i le
p rof
ity
loc
Ve

97 - Depok, 14 March, Engineering Center FTUI

Experimental flow pattern maps

Show
Show the
the effect
effect of
of GOR
GOR and
and Flow
Flow maps
maps are
are usually
usually functions
functions of:
of:
flowrate
flowrate on
on flow
flow pattern
pattern Superficial
Superficial gas
gas velocity
velocity
Based
Based onon experimental
experimental results
results vvSG = q G// SS
SG = qG
usually
usually obtained
obtained onon laboratory
laboratory test
test
loops Superficial
Superficial liquid
liquid velocity
velocity
loops (short
(short length,
length, small
small diameter
diameter
lines vvSL =q /S
SL = qLL/ S
lines handling
handling air/water
air/water mixtures
mixtures atat
near
near atmospheric
atmospheric pressure).
pressure). with:
with:
Flow
Flow patterns
patterns are
are discriminated
discriminated byby qqGG Gas
Gas volumetric
volumetric flowrate
flowrate
visual
visual observation.
observation. qqLL Liquid
Liquid volumetric
volumetric flowrate
flowrate
SS Pipeline
Pipeline cross-section
cross-section
THERE
THERE IS
IS ONE
ONE FLOW
FLOW MAP
MAP PER
PER PIPE
PIPE
SLOPE AND EACH FLOW
SLOPE AND EACH FLOW MAP MAP
DEPENDS
DEPENDS ON ON THE
THE AUTHOR
AUTHOR ’s’s
EXPERIMENTAL
EXPERIMENTAL RESULTS
RESULTS

98 - Depok, 14 March, Engineering Center FTUI

49
Pressure gradient in two-phase flow

For a mass unit of fluid: Momentum balance:

dl S -dP/dl = d(ρ v2/2)/ dl + ρ g sinθ + fD ρ v2/2

P+dP
v
S dz acceleration gravity friction

P
With:

Inclined pipe, constant cross-section fD = fD ( Re, ε/D )


S, no mechanical energy exchanged

99 - Depok, 14 March, Engineering Center FTUI

Pressure gradient in two-phase flow

For a gas/liquid flow element: Hold-up definition :


(volumetric
(volumetric fraction)
fraction)
Due to the non-homogeneity of
the phase distribution: Liquid volume in a section of pipe
HL =
ƒ The gas and the liquid do not flow Volume of this section of pipe
at the same velocity
HG = Gas volume in a section of pipe
ƒ There is slippage between the Volume of this section of pipe
phases
HG
ƒ It is necessary to know the liquid HL + HG = 1
hold-up HL (or αL)of the pipe HL
element to determine the actual
gas and liquid velocities: HL HL
VG= VSG/(1-HL), VL= VSL/HL Uphill Downhill section
section

ƒ A rigorous momentum balance


can be written for each of the
Flow Flow
gas and liquid phases

100 - Depok, 14 March, Engineering Center FTUI

50
Pressure gradient in two-phase flow

For a gas/liquid flow element:

ƒ Gravity term:

(dP/dl)gravity = [ ρG + (ρL - ρG)HL ] g sinθ


ƒ Friction term:

Gas friction against pipewall


(dP/dl)friction = Fonction of Gas/liquid interfacial friction
Liquid friction against pipewall

ƒ Acceleration term:
Sometimes discarded as it is negligible compared to the others

101 - Depok, 14 March, Engineering Center FTUI

Pressure gradient multiphase vs single phase

Unlike
Unlike single
single phase
phase flow,
flow, in
in multiphase
multiphase flow
flow the
the pressure
pressure
gradient
gradient goes
goes through
through aa minimum
minimum with
with increasing
increasing flowrate
flowrate

uphill slope downhill slope


single-phase flow TWO-PHASE FLOW single-phase flow two-phase flow
Dp/Dl Dp/Dl
Dp/Dl Dp/Dl
total
total
friction
gravity
flowrate flowrate
gravity
friction
flowrate flowrate

dP/dL
dP/dL is
is gravity-dominated
gravity-dominated at
at low
low flowrate,
flowrate, friction-dominated
friction-dominated at
at high
high flowrate
flowrate

102 - Depok, 14 March, Engineering Center FTUI

51
Problems related to slugging

Different types of « slugging » Main concerns


ƒ Hydrodynamic Slugging = Slug flow ƒ The steady operation of the
regime downstream facilities
ƒ Natural hydrodynamic phenomenon ƒ The design of the slugcatcher to be
ƒ The mechanisms of slug formation installed at the outlet of the pipeline
and evolution still not well known nor
modelled
Different types of slugcatchers
ƒ Additional capacity in inlet vessel
Slug volume

ƒ Terrain and riser induced slugging


between NLL and LAH Î Crude oil
(severe slugging) system (generally)

SC volume
ƒ Vessel-type Gas/Condensate
ƒ Operational Slugs :
ƒ Finger-type system, onshore
ƒ due to depressurisation
ƒ due to variations of operating
conditions (flow ramping) ƒ Two-phase or Three-phase
ƒ due to pigging

103 - Depok, 14 March, Engineering Center FTUI

Terrain or riser-induced severe slugging

Severe slugging
ƒ Intermittent flow which may
occur at low points of a
multiphase pipeline, due to
coupling effects between uphill
and downhill sections

ƒ Typically encountered in upward


risers

104 - Depok, 14 March, Engineering Center FTUI

52
Wax management

Risk
Risk assessment:
assessment:
ƒƒ Lab
Lab analysis
analysis of
of fluid
fluid samples
samples to
to quantify
quantify paraffin
paraffin content
content and
and WAT
WAT (Wax
(Wax
Appearance
Appearance Temperature)
Temperature)
ƒƒ Assessment
Assessment ofof wax
wax deposition
deposition quantities
quantities vs
vs sample
sample information.
information.

Design:
Design:
ƒƒ Find
Find best
best compromise
compromise ::
ƒƒ Thermal
Thermal insulation
insulation toto maintain
maintain the
the pipe
pipe inner
inner wall
wall temperature
temperature above
above the
the WAT
WAT
ƒƒ Inhibition
Inhibition by
by chemical
chemical injection
injection (ppd
(ppd paraffin
paraffin dispersant)
dispersant)
ƒƒ Pigging:
Pigging: to
to routinely
routinely scrape
scrape the
the paraffin
paraffin deposit.
deposit.
ƒƒ Simulate
Simulate &
& monitor
monitor thickness
thickness &
& nature
nature of
of deposit
deposit

Operation:
Operation:
ƒƒ Adjust
Adjust frequency
frequency of
of pigging
pigging operation
operation

105 - Depok, 14 March, Engineering Center FTUI

Two-phase flow regimes

Horizontal Vertical

106 - Depok, 14 March, Engineering Center FTUI

53

You might also like