Professional Documents
Culture Documents
Ch13 Solutions To Book Examples
Ch13 Solutions To Book Examples
2. On day 51 a project has an earned value of $600, an actual cost of $650, and a
planned cost of $560. Compute the SV, CV, and CPI for the project. What is
your assessment of the project on day 51?
3. Given the project network and baseline information below, complete the form to
develop a status report for the project at the end of period 4 and the end of
period 8. From the data you have collected and computed for periods 4 and 8,
what information are you prepared to tell the customer about the status of the
project at the end of period 8?
The project appears to be doing nicely. In both periods 4 and 8 the cost variance is
positive—+$300 and +$400, respectively. This suggests a pattern of good cost
variance that is under budget.
The schedule variance is also positive—+$300 and +$400 for period 4 and period 8.
Since Task D is already 25% complete, Task B must have been completed at least one
period early.
End of Period 4
Actual % EV AC PV CV SV
Task
Complete $ $ $ $ $
A Finished 400 300 400 +100 0
B 50% 1200 1000 800 +200 +400
C 33% 500 500 600 0 -100
D 0% 0 0 0 0 0
E 0% 0 0 0 0 0
Cumulative Totals $2100 $1800 $1800 $+300 $+300
End of Period 8
Actual % EV AC PV CV SV
Task
Complete $ $ $ $ $
A Finished 400 300 400 +100 0
B Finished 2400 2200 2400 +200 0
C Finished 1500 1500 1500 0 0
D 25% 400 300 0 +100 +400
E 33% 300 300 300 0 0
F 0% 0 0 0 0 0
Cumulative Totals $5000 $4600 $4600 $+400 $+400
Note: Completion of the answer sheet requires constant reference to the baseline
figure.
After 4 time periods the project is roughly 77% (PCIB) complete and is current
getting only 83 cents worth of work for each dollar spent. The project is currently
$10,000 over budget. There is $3,000 worth of work on critical Activity 5 that has
not been completed as planned so the project is behind schedule. Since so much of
the project has been completed the project is expected to come in over budget. The
forecast cost at completion is $78,000 which is $13,000 over budget. Whether the
project will be completed on schedule will depend upon whether Activity 5 can make
up for lost time.
E x e rc is e 1 3 -4 a
0 1 2 2 4 4
1 1 1 1
1 2 3 3 2 5
0 2 3 3 5 5 5 7 6
0 0 0 0 0 0
0 3 3 3 2 5 5 1 6
0 3 2 2 6 5 LEGEND
0 0 0 0 ES ID EF
0 2 2 2 3 5 SL SL
LS DUR LF
After 6 time periods the project is roughly 66% complete and so far work on the
project has taken 1,600 hours less work than planned. There is 400 hours worth of
work on Activity 4 which was suppose to have been done that has not done. Since
Activity 4 is on the critical path, the project is behind schedule. If schedule is the
number priority, the project manager may want to consider investing some of the
savings on accelerating critical activities.
Indexes
Period SPI CPI PCIB
1 1.00 2.00 .07
2 1.00 1.33 .14 SPI = EV / PV
3 .55 1.27 .19 CPI = EV / AC
4 .69 1.06 .35 PCIB = EV / BAC
5 .87 1.26 .54
6 .96 1.20 .66
After 12 time periods the project is roughly 60 percent and the project is only getting
70 cents worth of work for each dollar spent. The project is current $6,200 over
budget. There is $1,000 worth of work that supposed to have been done that has not
been completed according to plan. However, this work involved a noncritical activity
and the project is on schedule with regards to the critical path.
Appendix problems not bothered with, as we will not use the 50/50 or 1-100% rules in
DS856.