IKZ TUNNEL ENLARGEMENT PROJECT.


PROJECT OVERVIEW OF PHASE 1.

Phase 1: 10 Tunnels (Total 5.7 km)

Total IKZ Project: 55 Tunnels (Total 17km)


HERRENKNECHT AG | UTILITY TUNNELLING | TRAFFIC TUNNELLING

IKZ TUNNEL ENLARGEMENT PROJECT.


TUNNEL CROSS SECTIONS WITH/WITHOUT INNER LINING.
HERRENKNECHT AG | UTILITY TUNNELLING | TRAFFIC TUNNELLING

IKZ TUNNEL ENLARGEMENT PROJECT – PHASE 1.


MOBILIZATION OF TRAIN AND CONNECTION TO ROADHEADER/SHIELD.

Mobilization of support & backup train.

Connection of backup train to shield and roadheader

Pre-support of existing lining prior to excavation

Mobilization of mucking train.

Supply train Support & backup

Shield Muck haulage train


HERRENKNECHT AG | UTILITY TUNNELLING | TRAFFIC TUNNELLING

IKZ TUNNEL ENLARGEMENT PROJECT.


PRE-SUPPORT EXISTING LINING.

Seite 4 11/21/2019 Herrenknecht AG


HERRENKNECHT AG | UTILITY TUNNELLING | TRAFFIC TUNNELLING

IKZ TUNNEL ENLARGEMENT PROJECT – PHASE 1.


SHIELDED PROTECTION AND ROADHEADER FIXATION.

Seite 5 11/21/2019 Herrenknecht AG


HERRENKNECHT AG | UTILITY TUNNELLING | TRAFFIC TUNNELLING

IKZ TUNNEL ENLARGEMENT PROJECT – PHASE 1.


EXCAVATION & (DEDUSTING).

Seite 6 11/21/2019 Herrenknecht AG


HERRENKNECHT AG | UTILITY TUNNELLING | TRAFFIC TUNNELLING

IKZ TUNNEL ENLARGEMENT PROJECT.


EXCAVATION.

UCS of predominantly sandstone

Min. 10

Max.101 MPa

∅ 44 Mpa

For design of roadheader 125


MPa

Seite 7 11/21/2019 Herrenknecht AG


HERRENKNECHT AG | UTILITY TUNNELLING | TRAFFIC TUNNELLING

IKZ TUNNEL ENLARGEMENT PROJECT.


EXCAVATION.

Total power installed: 250kW

Torque cutting head: 32kNm (ref. S-763 Andra de Bure)

Rotation speed cutting head: 60.8 rpm (ref. S-763 Andra de Bure)

Displacement of roadheader: 1000mm

Forces and vibrations: ???

Pick / screw configuration: ???

Wear: ???

Seite 8 11/21/2019 Herrenknecht AG


HERRENKNECHT AG | UTILITY TUNNELLING | TRAFFIC TUNNELLING

IKZ TUNNEL ENLARGEMENT PROJECT – PHASE 1.


MUCKING.

Seite 9 11/21/2019 Herrenknecht AG


HERRENKNECHT AG | UTILITY TUNNELLING | TRAFFIC TUNNELLING

IKZ TUNNEL ENLARGEMENT PROJECT – PHASE 1.


MUCKING.

Seite 10 11/21/2019 Herrenknecht AG


HERRENKNECHT AG | UTILITY TUNNELLING | TRAFFIC TUNNELLING

IKZ TUNNEL ENLARGEMENT PROJECT.


MUCKING ON SEPARATE OPERATIONAL TRAIN.

Seite 11 11/21/2019 Herrenknecht AG


HERRENKNECHT AG | UTILITY TUNNELLING | TRAFFIC TUNNELLING

IKZ TUNNEL ENLARGEMENT PROJECT.


ROCK BOLTING & LATTICE BEAM & WIRE MESH (WAGGON NO.1).

Seite 12 11/21/2019 Herrenknecht AG


HERRENKNECHT AG | UTILITY TUNNELLING | TRAFFIC TUNNELLING

IKZ TUNNEL ENLARGEMENT PROJECT.


GROUND IMPROVEMENT POSSIBILITY AHEAD OF SHIELD.

Seite 13 11/21/2019 Herrenknecht AG


HERRENKNECHT AG | UTILITY TUNNELLING | TRAFFIC TUNNELLING

IKZ TUNNEL ENLARGEMENT PROJECT.


SHOTCRETE – EQUIPMENT WAGGON NO.1.

Seite 14 11/21/2019 Herrenknecht AG


HERRENKNECHT AG | UTILITY TUNNELLING | TRAFFIC TUNNELLING

IKZ TUNNEL ENLARGEMENT PROJECT.


HYDRAULICS & CONTAINER ON EQUIPMENT WAGGON NO.2.

Seite 15 11/21/2019 Herrenknecht AG


HERRENKNECHT AG | UTILITY TUNNELLING | TRAFFIC TUNNELLING

IKZ TUNNEL ENLARGEMENT PROJECT.


DEDUSTER & GENERATOR ON EQUIPMENT WAGGON NO.3.

Seite 16 11/21/2019 Herrenknecht AG


HERRENKNECHT AG | UTILITY TUNNELLING | TRAFFIC TUNNELLING

IKZ TUNNEL ENLARGEMENT PROJECT.


SUPPLY ON WAGGON NO.4.

Seite 17 11/21/2019 Herrenknecht AG