Professional Documents
Culture Documents
Converter Technology
Converters for large wind turbines
© ABB Group
September 5, 2016 | Slide 1
Q&A session
© ABB Group
September 5, 2016 | Slide 2
Drive train concepts for wind turbines
All concepts at a glance
DC
brake
10...24 kV, f = 50 Hz 10 ... 24 kV, f = 50 Hz
converter or 60 Hz
or 60 Hz
control
Getriebe 1:50
gearbox brake
start up
equipment line coupling
line coupling transformer
asynchronous generator transformer medium voltage
with squirrel cage rotor medium voltage asynchronous
switchgear
gearbox and two windings switchgear generator
wind turbine
control
f = constant pitch
n = constant drive
wind turbine control
rotor bearing rotor bearing
• simple and robust technology without frequency converter • simple and robust generator
• Obsolete for new turbine design, not supporting grid codes • 0…100% speed variability due to fullscale converter
Doubly fed ASM Machine (+/- 30% speed) Permanent Magnet Machine (0-100% speed)
frequency converter
10...24 kV, f = 50 Hz generator side line side
circuit breaker or 60 Hz
asynchronous converter converter
generator
with slip rings
DC
gearbox
line coupling
transformer 10 ... 24 kV, f = 50 Hz
frequency converter
converter or 60 Hz
medium voltage
brake switchgear control
generator grid side
converter converter
line coupling
transformer
rotor bearing pitch crowbar circuit breaker medium voltage
drive brake pitch switchgear
converter control
drive
permanent magnet
generator
© ABB Group
September 5, 2016 | Slide 3
frequency converter
generator side line side
converter converter
DC
10 ... 24 kV, f = 50 Hz
converter or 60 Hz
control
line coupling
transformer
medium voltage
brake pitch switchgear
drive
permanent magnet
generator
© ABB Group
September 5, 2016 | Slide 4
Drive train concepts for wind turbines
Most popular concept for power above 3.x MW
Nacelle:
Gearbox if used
PM Generator
Mechanical Brake
Pitch Drive
© ABB Group
September 5, 2016 | Slide 5
© ABB Group
September 5, 2016 | Slide 6
Converter technology for large wind turbines
Table of contents
Q&A session
© ABB Group
September 5, 2016 | Slide 7
Special Tasks:
Rotor Positioning mode
Back to Back test operation
© ABB Group
September 5, 2016 | Slide 8
Full scale converters for wind turbines >3.xMW
The example: PCS6000 MV wind converter
For simplification purposes the next slides refer to the PCS6000 medium
voltage wind converter. This modular converter family has a range from 3
to 10MVA with an output voltage of 3.3kV or 4.16kV.
© ABB Group
September 5, 2016 | Slide 9
© ABB Group
September 5, 2016 | Slide 10
Understanding the PCS6000 main components
The dv/dt filter
1.5kV/μs
© ABB Group
September 5, 2016 | Slide 11
© ABB Group
September 5, 2016 | Slide 12
Understanding the PCS6000 main components
The generator side converter – power transfer
Xd = Xh + X1σ
Up IE U1
© ABB Group
September 5, 2016 | Slide 13
© ABB Group
September 5, 2016 | Slide 14
Understanding the PCS6000 main components
The generator side converter – power transfer
© ABB Group
September 5, 2016 | Slide 15
© ABB Group
September 5, 2016 | Slide 16
Understanding the PCS6000 main components
The generator side converter – the voltage source
© ABB Group
September 5, 2016 | Slide 17
© ABB Group
September 5, 2016 | Slide 18
Understanding the PCS6000 main components
The generator side converter – the IGCT
© ABB Group
September 5, 2016 | Slide 19
© ABB Group
September 5, 2016 | Slide 20
Understanding the PCS6000 main components
The DC link
© ABB Group
September 5, 2016 | Slide 21
voltage constant.
The grid side converter consists
of the same HW as the generator
side converter.
Beside DC link voltage control,
the grid side converter has two
more tasks:
Reactive power control during
normal operation.
Fault ride through operation
© ABB Group
September 5, 2016 | Slide 22
Understanding the PCS6000 main components
The grid side converter – equivalent circuit
XL XT ZG
ZF
© ABB Group
September 5, 2016 | Slide 23
© ABB Group
September 5, 2016 | Slide 24
Understanding the PCS6000 main components
The grid side converter – reactive power control
© ABB Group
September 5, 2016 | Slide 25
Limitation because of
maximal generator power
Limitation because of
maximal converter current
Active Power
© ABB Group
September 5, 2016 | Slide 26
Understanding the PCS6000 main components
The AC grid filter
0
0
0
0
0
Current 0 0
0
0
0
0
0
Voltage
© ABB Group
September 5, 2016 | Slide 27
0.2
0.1
0
10 20 30 40 50 60 70 80 90 100
Harmonische von 50 Hz
© ABB Group
September 5, 2016 | Slide 28
Understanding the PCS6000 main components
The cooling unit
© ABB Group
September 5, 2016 | Slide 29
© ABB Group
September 5, 2016 | Slide 30
Understanding the PCS6000 main components
The control hardware - overview
optics. (VHDL)
25ns
© ABB Group
September 5, 2016 | Slide 31
emergency off
Trip MCB
Turbine Controller
remote service
possible (Ethernet)
contact
S800 I/O-Cluster binary
Slow I/O 8 16 8 8 signals
data exchange
TB serial link (10ms)
BO BO BI BI
820
Closed loop control, state ON / OFF / Trip MCB
Kombi I/O
1 x UA D141A01 PECINTM 1 PECINTM 3
2 x UA D142A01
12 2 2
UU D UU D 12
148 AE02 148 AE01
ASE ASE
VLSCD1
20 kV GRB GEB
50Hz I I I I I I
I I I
NP
I I I
slope PM
filter GEN
3 x CT
3 x VT
VLSCD2
© ABB Group
September 5, 2016 | Slide 32
Understanding the PCS6000 main components
The control hardware – limited number of interfaces
Hardwired
PRODUCTION OPERATIONAL
FAULT SIGANLS
*EMERGENCY_STOP1
Profibus, Profinet,
Ethercat, Canbus or
CONVERTER CONTROL
MAIN CICUIT
BREAKER CLOSED
*EMERGENCY STOP2
-X930
*EMERGENCY_NOFF
*EMERGENCY_STOP1
TURBINE CONTROL
RELEASED
*EMERGENCY STOP2
data exchange
ROTOR LOCKED
*EMERGENCY_NOFF
24VDC
EOFF
48VDC
CONVERTER
*TRIP LOCAL HW
OFF ON
*CONTROL TRIP
*OFF1_COMBI
*OFF2_Control
GRB CLOSED
GRB ERROR
safety signals
GRB READY
GRB OPEN
+48VDC
LOCAL SERVICE
CLOSE
CONNECTOR
+24VDC
LWL
RJ45 VT / CT GRB
LWL GEB (emergency stop, …)
-X200 -X910 -INT
© ABB Group
September 5, 2016 | Slide 33
Q&A session
© ABB Group
September 5, 2016 | Slide 34
Understanding the PCS6000 main functionalities
Operation states
Production mode:
The converter transfers power
from the generator into the grid
according the torque and reactive
power reference.
VAR compensation mode:
Converter operated as a pure
STATCOM on the grid. The
generator converter is off
Standby mode:
The converter is ready to transfer
to production or VAR compen-
sation within a few seconds
I/f Mode:
Positioning of the rotor to be able
to look mechanically the rotor.
U/f Mode:
Needed for generator test at wind
turbine manufacturing location.
© ABB Group
September 5, 2016 | Slide 35
© ABB Group
September 5, 2016 | Slide 36
Understanding the PCS6000 main functionalities
Control of operation – commissioning, service, …
© ABB Group
September 5, 2016 | Slide 37
Customer
Network PCS 6000 Wind Converter
IPC AC 800PEC
Controller
IPC AC 800PEC
Controller
Service PC
© ABB Group
September 5, 2016 | Slide 38
Understanding the PCS6000 main functionalities
Transient recorder functionality
© ABB Group
September 5, 2016 | Slide 39
© ABB Group
September 5, 2016 | Slide 41
© ABB Group
September 5, 2016 | Slide 42
Converter technology for large wind turbines
Table of contents
Q&A session
© ABB Group
September 5, 2016 | Slide 43
© ABB Group
September 5, 2016 | Slide 44
Understanding the PCS6000 Mechanical Integration
The possible mechanical layouts
© ABB Group
September 5, 2016 | Slide 45
© ABB Group
September 5, 2016 | Slide 46
Converter technology for large wind turbines
Table of contents
Q&A session
© ABB Group
September 5, 2016 | Slide 47
© ABB Group
September 5, 2016 | Slide 48
Hints to components interfacing with the PCS6000
The permanent magnet generator
© ABB Group
September 5, 2016 | Slide 49
There are mainly three values of the transformer which are influenced
Transformer impedance
The transformer impedance can be seen as a part of the AC filter. If the
impedance is not selected the right way, then resonance phenomena can
occur. Additionally the converter also requires a minimal impedance.
Voltage ratio
Typically a voltage ratio of about 3.3kV:33kV would be selected as a first
shoot from the hip.
As learned on slide 24, the transformer needs over voltage on the converter
side to transfer reactive power into the grid depending on the used grid code.
Assumption: transformer impedance: 12%, grid voltage: 105%, active power:
100%, power factor: 0.925
The power factor results in a needed reactive current of 41.1%
The reactive current together with the transformer impedance results into
a needed voltage drop of 41.1% * 12% = 4.9%
This voltage drop results in an needed secondary transformer voltage of
105% + 4.9% = 109.9%.
The reactive current requirement leads now to following transformer
voltage ratio: 33kV:(3.3kV/109.9%*100%) which is 33kV:3.0kV
© ABB Group
September 5, 2016 | Slide 50
Hints to components interfacing with the PCS6000
The main transformer
© ABB Group
September 5, 2016 | Slide 51
The PCS6000 is designed in such a way that all kind of different water
and air temperature requirements can be fulfilled.
The strategy we follow is based on that we know for each module, for
each water and air temperature, exactly the safe operating area.
If customers power requirements cannot be fulfilled anymore, then an
additional module will be taken.
© ABB Group
September 5, 2016 | Slide 52
Hints to components interfacing with the PCS6000
Environmental conditions – water and air
Operation above the absolute temperature might turn into faster aging
or destruction.
© ABB Group
September 5, 2016 | Slide 53
Taking the component temperature limits, the Fourier’s law and the
flexible temperature models of the PCS6000 into account, then
following conclusion can be done:
The lower the cooling media temperature, the higher the allowed
current through a component, the higher the power capacity of the
PCS6000.
Its recommended to define two temperature ranges:
One where nominal operation should be possible
The other one, where operation with reduced power is allowed
The re-cooling circuit can be either done with a water to air heat
exchanger or much more effective with a water to water heat
exchanger if seawater or industrial water is available.
Note:
The wind speed is normally lower at high temperatures.
The converter can be operated up to 50°C of cooling water inlet temperature
with reduced capacity. Higher temperatures also possible on request.
An optimal cooling water temperature for nominal operation is between 30°C
to 40°C depending on the design.
ABB is happy helping defining the optimal operation temperatures
© ABB Group
September 5, 2016 | Slide 54
Converter technology for large wind turbines
Table of contents
Q&A session
© ABB Group
September 5, 2016 | Slide 55
Questions
© ABB Group
September 5, 2016 | Slide 56
© ABB Group
September 5, 2016 | Slide 57
High quality and little number of power electronic High system reliability. High MTBF. Therefore low
components. Built to last components. maintenance and service cost. Extended system
uptimes and production.
Motor drive operation of generator for workshop Extended workshop heat-run trial test and workshop
full current test run. / Accurate rotor hold & validation. Therefore easier and faster
positioning for service purpose. commissioning. / Good serviceability of rotating
components.
Engineered solution for reactive grid power Frequency converter gives power quality system
control in operation- or standby-mode. Supply of benefits! Reactive power compensation. Grid
leading / lagging possible (Statcom functionality). stabilization.
Grid loss fault ride through with dynamic rotor Generator overspeed protection. No damage to rotor
braking and generator power dissipation. blades, generator and gear box. Longer lifetime of
mechanical components.
© ABB Group
September 5, 2016 | Slide 58
Converter technology for large wind turbines
Benefits and system aspects
Enduring generator connection (no fuse, no Generator overspeed protection. No damage to rotor
breaker). No generator disconnection in case of blades, generator and gear box. Extended lifetime of
failure and keeping converter load by protection mechanical components.
firing.
Small currents due to MV technology. Small cable Low cabling effort. Low losses. High productivity.
size. Small generator. No generator double
winding design required.
Grid friendly converter and transformer pre- Stress-free transformer switch-on. Grid code
charging and synchronization. No inrush. No compliance.
flicker.
Engineered filter circuits matching generator, Matching cable type and length criteria. Stress-free
cable & grid requirements. generator and cable operation. Grid code
compliance.
Quick and easy semiconductor change. Not full No need to open hydraulic cooling system. No de-
modules to be replaced. No hoist gear required. aeration required. Good MTBR. Low service cost.
Robust capacitor bank (film capacitors). High system reliability. High MTBF.
Redundant integrated pump stand. Engineered Fully engineered cooling system. All inclusive
fully single closed loop cooling circuit with water- cooling with provided external water-to-air heat-
to-air heat-exchanger. No need for raw-water exchanger. No need for cooling raw-water.
supply. Operation below freezing point possible.
Temperature control with by-pass valve
integrated.
© ABB Group
September 5, 2016 | Slide 59
Sophisticated control algorithm for permanent Flexibility in best matching generator design.
magnet synchronous and asynchronous
generator.
Fully integrated, flexible industrial controller Easy customization possible when needed.
platform. High performance AC800 PEC controller
and I/O devices. Std high level programming and
diagnostic tools.
Built-in converter control dedicated redundant Always safe operation and shut-down. No damage
DC-UPS. due to uncontrolled operation. Shut-down event log
for diagnostic available.
Humidity condensation protection logic. Save start-up. No damage electronic boards.
Active drive train damping control. Low torque ripple and smooth operation of rotating
devices. Extended lifetime of mechanical
components. Trouble-free operation.
© ABB Group
September 5, 2016 | Slide 60