Professional Documents
Culture Documents
At first there has to be WBS Code further the WBS Description through gap.
This list can be created in Word or any other text editor.
It is necessary to remember the following restrictions during creation of such list:
1. By default In Primavera P6 maximum length of WBS Code cannot exceed 20 characters.
However if necessary, you can increase it in Admin settings:
Admin-> Admin Preferences …-> ID Lengths
2. Maximum length of WBS Description cannot exceed 98 characters.
Therefore, now we will describe steps, which need to be made for import WBS from Excel to
Primavera P6:
1. We open Excel file called “Import WBS from Excel to P6” (download link in end of this article).
2. Paste WBS Codes & Descriptions in above described format starting from green highlighted
cell A5.
In the picture given below we used as an example of WBS for petrochemical plant revamp
project scope included design and engineering, purchasing of equipment and materials and
construction of furnace and compressor areas:
3. Open Primavera P6.
4. Create dummy Project: Projects -> Ctrl+N -> Select EPS -> Finish
5. Open Project: Ctrl+O -> Open
6. Export Project to your PC.
7. Open xer file with Notepad:
8. To clear the last line containing “%E”: Ctrl+End -> Press Backspace 3 times
9. To put the cursor for the line containing "%T To PROJWBS": Press Up Arrow 3 times
10. Ctrl+Shift+End
11. Go back to Excel file and click on green highlighted cell P2.
12. Paste Text
Downloads:
Full-function demo version of Excel file “Import WBS from Excel to P6” (maximum 100 WBS
descriptions):
https://app.box.com/s/mi27im4pdywzcro5rblxqb03kwms8fzq
Tofik Nazirov
Planning and Project Controls Professional
Email: tnazirov@gmail.com
Mobile: +994557579912
+994557579912
+994557579912