Professional Documents
Culture Documents
Pre-commissioning activity test records are prepared Air tightness “Leak” testing of systems
to record the satisfactory completion of various
Lubricants application
system preparation tasks & activities.
Pre-commissioning “Run-in” of major rotating
Cleaning
equipment and electrical motors
Chemical cleaning Pre-Commissioning Activities (Examples)
Installation of filters
Drying
Construction QA/QC documentation Pre-Commissioning Test Records Packing of distillation columns
Air tightness test
Systems punchlist (commissioning punch) Loading of catalyst and molecular sieve beds
Loading of catalysts
Piping pre-commissioning activities Refractory dry-out (if possible - mostly
Blinds list commissioning activity)
Stationary equipment pre-commissioning activities
Vendor and factory acceptance testing
Rotating equipment pre-commissioning activities
Performance Indicators
The 9 Key Elements Instrument, electrical and motor loop testing
Instrumentation pre-commissioning activities
of
Successful Punchlisting (ongoing process)
Tightness tests Plant Commissioning 1. Power and control system (electrical sub-stations)
Total / Completed / Remaining Reporting
2. Building power, HVAC, fire & gas protection
Many different checklists for different types of
Element 4
3. DCS and PLC systems and instrumentation
equipment - PRE-COMMISSIONING -
To record the inspection and status of equipment 4. Raw water and fire fighting systems
items within the plant Pre-Commissioning Checklists 5. Waste water treatment systems
To conform readiness for commissioning 6. Oily sewer / clean sewer systems and chemical
Often to be witnessed by client, PMC & licensor sewers & neutralization pits
NOTE: All slip blinds or spectacle plates utilized 7. Service water / potable water / cooling water
must be given a suitable tail or handle so immediate Spectacle blind installation checks systems
identification can be made in the field. 8. Instrument air / plant air and regeneration air
Non-return valve internals installation checks systems
Thermal refractory lining installation checks 9. Water treatment systems, demineralization units
and boiler water system
Mechanical interlock checks
10. Nitrogen system
Fitting of all locks on valves
Pre-Commissioning Sequence (Example) 11. Flare system
Packing of a distillation or scrubbing column
12. Plant safety equipment and fire & gas detection
Packing a reactor with catalyst
13. Fuel gas and fuel oil system
Installation of filter medium and cartridges Pre-Commissioning Procedures (Examples)
14. Slop systems
Air blowing
15. Flushing oil system
Steam blowing
16. Boiler systems with steam & condensate
Water flushing networks
Mechanical test run of pumps 20. Sour water treatment section and chemical
handling treatment section