INCINERATOR & OXIDISER - A 29-Oct-11 08:43 AM

Activity ID Activity Name Original Start Finish BL Project Finish Duration % June 2011 July 2011 August 2011 September 2011 October 2011 2011
Complete
04 11 18 25 02 09 16 23 30 06 13 20 27 03 10 17 24 01 08 15 22 29 05
Duration
INCI-A RELINING
RELIN & REPAIRING OF OXIDIZER-A 3577h 10-Jun-11 07:00 AM A 06-Nov-11 08:00 AM 10-Nov-11 04:00 PM 94.63%

INCI-A.1 RELINING
RELIN OF INCINERATOR-A 3565h 10-Jun-11 07:00 AM A 05-Nov-11 08:00 PM 03-Oct-11 03:00 AM 94.95%
INCI-A.1.OPER RELEASING OF SYSTEM
INCI-A.1.OPER- 60h 10-Jun-11 07:00 AM A 12-Jun-11 07:00 PM A 12-Jun-11 07:00 PM 100%
INCI-A.1.1 MILESTONE
MIL OF INCINERATOR - A 2913h 10-Jun-11 07:00 AM A 10-Oct-11 04:00 PM A 27-Sep-11 03:00 PM 100%
INCI-A.1.2 MOBILIZATION
MO FOR INCINERATOR - A 72h 10-Jun-11 07:00 AM A 13-Jun-11 07:00 AM A 13-Jun-11 07:00 AM 100%
INCI-A.1.3 DEMOLITION
DE OF INCINERATOR - A 3337h 14-Jun-11 07:00 AM A 31-Oct-11 08:00 AM 28-Aug-11 05:00 PM 98.56%
INCI-A.1.3.1 TOP BRICKS (2.207M) 48h 05-Jul-11 07:00 AM A 07-Jul-11 07:00 AM A 23-Jun-11 07:00 AM 100%
INCI-A.1.3.2 TOP CONE (GUNNING) 516h 20-Jun-11 07:00 AM A 29-Jun-11 07:00 PM A 14-Jul-11 07:00 PM 100%
INCI-A.1.3.3 BARREL SECTION (CASTING) 500h 22-Jun-11 07:00 AM A 02-Jul-11 07:00 PM A 19-Jul-11 03:00 AM 100%
INCI-A.1.3.4 BOTTOM CONE (GUNNING) 284h 26-Jun-11 07:00 AM A 05-Jul-11 07:00 PM A 20-Jul-11 03:00 AM 100%
INCI-A.1.3.5 INSPECTION AFTER DEMOLITION 120h 06-Jul-11 08:00 AM A 14-Jul-11 07:00 PM A 25-Jul-11 03:00 AM 100%
INCI-A.1.3.6 DEMOBILIZATION 48h 20-Jul-11 07:00 AM A 20-Jul-11 07:00 AM A 22-Jul-11 07:00 AM 100%
INCI-A.1.4 RE-CONSTRUCTION
RE OF INCINERATOR - A 2497h 20-Jul-11 07:00 AM A 04-Nov-11 08:00 PM 30-Sep-11 03:00 AM 93.75%
INCI-A.1.4.7 MOBILIZATION (2ND TIME) 48h 08-Aug-11 07:00 AM A 10-Aug-11 05:00 P... 17-Aug-11 05:00 PM 100%
INCI-A.1.4.1 GRITBLASTING & PAINTING 204h 11-Aug-11 08:00 AM A 01-Oct-11 10:00 AM A 01-Sep-11 05:00 PM 100%
INCI-A.1.4.2 APPLICATION TEST 36h 03-Aug-11 11:00 AM A 09-Aug-11 05:00 P... 02-Aug-11 07:00 PM 100%
INCI-A.1.4.3 TOP BRICKS (2.207M) 48h 12-Oct-11 06:00 AM A 29-Oct-11 10:24 AM 29-Sep-11 03:00 PM 95%
INCI-A.1.4.4 TOP CONE & PARTIAL BARREL SEC. (GUNNING) (4.2M) 1700h 20-Jul-11 07:00 AM A 22-Sep-11 05:00 P... 25-Sep-11 09:48 AM 100%
INCI-A.1.4.5 BARREL SECTION (CASTING) (9.3M) ULTRAGREEN 57A 1650h 25-Jul-11 08:00 AM A 21-Sep-11 11:00 A... 24-Sep-11 07:48 PM 100%
INCI-A.1.4.5.1 FIRST RING (0.96M)
INCI-A.1.4 62h 24-Aug-11 07:00 AM A 27-Aug-11 11:00 A... 26-Aug-11 09:48 AM 100%
INCI-A.1.4.5.2 SECOND RING (0.96M)
INCI-A.1.4 63h 26-Aug-11 07:00 AM A 29-Aug-11 04:00 P... 04-Sep-11 12:48 AM 100%
INCI-A.1.4.5.3 THIRD RING (0.96M)
INCI-A.1.4 164h 29-Aug-11 07:00 AM A 03-Sep-11 03:00 P... 06-Sep-11 02:48 PM 100%
INCI-A.1.4.5.4 FOURTH RING (0.96M)
INCI-A.1.4 63h 03-Sep-11 07:00 AM A 06-Sep-11 05:00 P... 09-Sep-11 05:48 AM 100%
INCI-A.1.4.5.5 FIFTH RING (0.96M)
INCI-A.1.4 187h 06-Sep-11 07:00 AM A 08-Sep-11 05:00 P... 11-Sep-11 07:48 PM 100%
INCI-A.1.4.5.6 SIXTH RING (0.96M)
INCI-A.1.4 63h 10-Sep-11 06:00 AM A 13-Sep-11 03:00 P... 14-Sep-11 10:48 AM 100%
INCI-A.1.4.5.7 SEVENTH RING (0.96M)
INCI-A.1.4 62h 13-Sep-11 07:00 AM A 15-Sep-11 05:00 P... 17-Sep-11 12:48 AM 100%
INCI-A.1.4.5.8 EIGHT RING (0.96M)
INCI-A.1.4 44h 15-Sep-11 08:00 AM A 18-Sep-11 05:00 P... 19-Sep-11 03:48 PM 100%
INCI-A.1.4.5.9 NINTH RING (0.96M)
INCI-A.1.4 62h 18-Sep-11 06:00 AM A 21-Sep-11 11:00 A... 22-Sep-11 05:48 AM 100%
INCI-A.1.4.5.10 TENTH RING (0.96M)
INCI-A.1.4 62h 20-Sep-11 10:00 AM A 20-Sep-11 10:00 P... 24-Sep-11 07:48 PM 100%
INCI-A.1.4.6 BOTTOM CONE & PARTIAL BARREL (GUNNING) (5M) 1582h 09-Aug-11 08:00 AM A 11-Oct-11 06:00 PM A 03-Sep-11 10:48 PM 100%
INCI-A.1.5 BOX
BO UP OF INCINERATOR - A 108h 01-Nov-11 08:00 AM 05-Nov-11 08:00 PM 03-Oct-11 03:00 AM 0%
INCI-A.2 REPAIRING
REPA OF OXIDIZER-A 2505h 02-Jul-11 07:00 AM A 01-Nov-11 04:00 PM 10-Nov-11 04:00 AM 96.81%
INCI-A.2.1 RELEASING
RE OF SYSTEM 48h 02-Jul-11 07:00 AM A 04-Jul-11 05:00 PM A 22-Jul-11 07:00 AM 100%
INCI-A.2.2 MIL
MILESTONE OF OXIDIZER - A 2437h 02-Jul-11 07:00 AM A 29-Oct-11 08:00 PM A 29-Oct-11 08:00 PM 100%
INCI-A.2.3 MO
MOBILIZATION FOR OXIDIZER - A 8h 22-Jul-11 07:00 AM A 22-Jul-11 03:00 PM A 22-Jul-11 03:00 PM 100%
INCI-A.2.4 DE
DEMOLITION OF OXIDIZER- A 873h 04-Jul-11 07:00 AM A 30-Jul-11 04:00 PM A 27-Aug-11 04:00 PM 100%
INCI-A.2.5 INSPECTION
INS AFTER DEMOLITION 2301h 06-Jul-11 09:00 AM A 31-Oct-11 08:00 AM 08-Nov-11 08:00 PM 98.31%
INCI-A.2.6 RE-CONSTRUCTION
RE OF OXIDIZER - A 154h 11-Oct-11 08:00 AM A 30-Oct-11 01:00 AM 08-Nov-11 12:00 AM 88.96%
INCI-A.2.7 BOX
BO UP OF OXIDIZER - A 32h 31-Oct-11 08:00 AM 01-Nov-11 04:00 PM 10-Nov-11 04:00 AM 0%
INCI-A.6 FINAL DEMOBILIZATION FROM INCINERATOR - A 12h 05-Nov-11 08:00 PM 06-Nov-11 08:00 AM 10-Nov-11 04:00 PM 0%

INCI-A.OPERATION START UP
INCI-A.OPERAT 0h 06-Nov-11 08:00 AM 06-Nov-11 08:00 AM 10-Nov-11 04:00 PM 0%

Actual Work Critical Remaining Work Summary Page 1 of 1 Date Revision Checked Approved