DUALIZATION OF MAHDAH - AL RAWDAH ROAD PROJECT Classic Schedule Layout 25-May-14 16:51

Activity ID Activity Name Original Start Finish Total Float Critical 2014 2015 2016
Duration
S Oct N D J F M Apr M J Jul A S Oct N D Jan F M Apr M J Jul A S Oct N D J F M Apr M J
DUALIZATION OF MAHDAH
MA - AL RAWDAH ROAD PROJE 884 15-Jul-13 20-Jun-16 0

DUALIZATION OF MAHDAH
MA - AL RAWDAH ROAD PROJEC 884 15-Jul-13 20-Jun-16 0

PREMOBILIZATION WOR
WORKS 127 15-Jul-13 21-Dec-13 239 21-Dec-13, PREMOBILIZATION WORKS
PZ0CO1000 DATE OF RECEIPT OF LETTER OF INTENT [L.O.I.] 1 15-Jul-13 15-Jul-13 0 E OF RECEIPT OF LETTER OF INTENT [L.O.I.]
PZ0CO1010 PREPARATION OF DOCUMENTS FOR ALL NECES 98 16-Jul-13 16-Nov-13 0 PREPARATION OF DOCUMENTS FOR ALL NECESSARY APPROVALS
REQUEST/ APPLICATION
APPLICATIO FOR DIFFERENT MINISTRIES 84 04-Aug-13 17-Nov-13 77 17-Nov-13, REQUEST/ APPLICATION FOR DIFFERENT MINISTRIES
PZ0CO1020 REQUEST TO MINISTRY OF ENVIRONMENT & CL 1 15-Sep-13 15-Sep-13 42 REQUEST TO MINISTRY OF ENVIRONMENT & CLIMATE AFFAIRS
PZ0CO1030 REQUEST TO PUBLIC AUTHORITY OF ELECTRIC 1 31-Oct-13 31-Oct-13 0 REQUEST TO PUBLIC AUTHORITY OF ELECTRICITY & WATER
PZ0CO1040 REQUEST TO NAWRAS 1 06-Nov-13 06-Nov-13 34 REQUEST TO NAWRAS
PZ0CO1050 REQUEST TO OMANTEL 1 07-Nov-13 07-Nov-13 0 REQUEST TO OMANTEL
PZ0CO1060 REQUEST TO MINISTRY OF HERITAGE & CULT UR 1 07-Nov-13 07-Nov-13 0 REQUEST TO MINISTRY OF HERITAGE & CULT URE
PZ0CO1070 REQUEST TO MINISTRY OF AWQAF & RELIGIOUS 1 07-Nov-13 07-Nov-13 30 REQUEST TO MINISTRY OF AWQAF & RELIGIOUS AFFAIRS
PZ0CO1080 REQUEST TO R.O.P. 1 07-Nov-13 07-Nov-13 1 REQUEST TO R.O.P.
PZ0CO1090 REQUEST TO MINISTRY OF DEFENCE 1 11-Nov-13 11-Nov-13 0 REQUEST TO MINISTRY OF DEFENCE
PZ0CO1100 REQUEST TO PETROLIEM DEVELOPMENT CO. 1 12-Nov-13 12-Nov-13 1 REQUEST TO PETROLIEM DEVELOPMENT CO.
PZ0CO1110 REQUEST TO ADVISOR FOR CONSERVATION OF 1 14-Nov-13 14-Nov-13 19 REQUEST TO ADVISOR FOR CONSERVATION OF THE ENVIRONMENT
PZ0CO1120 REQUEST TO FALAJ DEPARTMENT MAHDAH 1 14-Nov-13 14-Nov-13 19 REQUEST TO FALAJ DEPARTMENT MAHDAH
PZ0CO1130 REQUEST TO OMAN ELECTRICITY TRANSMISSIO 1 17-Nov-13 17-Nov-13 0 REQUEST TO OMAN ELECTRICITY TRANSMISSION COMPANY
PZ0CO1140 REQUEST TO MINISTRY OF REGIONAL MUNICIPA 1 06-Nov-13 06-Nov-13 0 REQUEST TO MINISTRY OF REGIONAL MUNICIPALITIES & WATER RESOURCES
PZ0CO1150 APPLICATION FOR MOBILE CRUSHER & SCREEN 1 04-Aug-13 04-Aug-13 71 PPLICATION FOR MOBILE CRUSHER & SCREENING PLANT
PZ0CO1160 APPLICATION FOR BORROW PITS FOR RIP RAP & 1 04-Aug-13 04-Aug-13 77 PPLICATION FOR BORROW PITS FOR RIP RAP & FILLING MATERIAL
PZ0CO1170 APPLICATION FOR BORROW PITS FOR FILLING M 1 17-Nov-13 17-Nov-13 77 APPLICATION FOR BORROW PITS FOR FILLING MATERIAL
APPROVAL FROM DIFFERENT
DIFF MINISTRIES 110 05-Aug-13 21-Dec-13 239 21-Dec-13, APPROVAL FROM DIFFERENT MINISTRIES
PZ0CO1180 APPROVAL FROM MINISTRY OF ENVIRONMENT & 34 16-Sep-13 28-Oct-13 42 APPROVAL FROM MINISTRY OF ENVIRONMENT & CLIMATE AFFAIRS
PZ0CO1190 APPROVAL FROM PUBLIC AUTHORITY OF ELECT 39 02-Nov-13 19-Dec-13 0 APPROVAL FROM PUBLIC AUTHORITY OF ELECTRICITY & WATER
PZ0CO1200 APPROVAL FROM NAWRAS 1 07-Nov-13 07-Nov-13 34 APPROVAL FROM NAWRAS
PZ0CO1210 APPROVAL FROM OMANTEL 34 09-Nov-13 19-Dec-13 0 APPROVAL FROM OMANTEL
PZ0CO1220 APPROVAL FROM MINISTRY OF HERITAGE & CUL 34 09-Nov-13 19-Dec-13 0 APPROVAL FROM MINISTRY OF HERITAGE & CULTURE
PZ0CO1230 APPROVAL FROM MINISTRY OF AWQAF & RELIGI 4 09-Nov-13 12-Nov-13 30 APPROVAL FROM MINISTRY OF AWQAF & RELIGIOUS AFFAIRS
PZ0CO1240 APPROVAL FROM R.O.P. 33 09-Nov-13 18-Dec-13 1 APPROVAL FROM R.O.P.
PZ0CO1250 APPROVAL FROM MINISTRY OF DEFENCE 31 12-Nov-13 19-Dec-13 0 APPROVAL FROM MINISTRY OF DEFENCE
PZ0CO1260 APPROVAL FROM PETROLIEM DEVELOPMENT CO 29 13-Nov-13 18-Dec-13 1 APPROVAL FROM PETROLIEM DEVELOPMENT CO.
PZ0CO1270 APPROVAL FROM ADVISOR FOR CONSERVATION 9 16-Nov-13 25-Nov-13 19 APPROVAL FROM ADVISOR FOR CONSERVATION OF THE ENVIRONMENT
PZ0CO1280 APPROVAL FROM FALAJ DEPARTMENT MAHDAH 9 16-Nov-13 25-Nov-13 19 APPROVAL FROM FALAJ DEPARTMENT MAHDAH
PZ0CO1290 APPROVAL FROM OMAN ELECTRICITY TRANSMI 26 18-Nov-13 19-Dec-13 0 APPROVAL FROM OMAN ELECTRICITY TRANSMISSION COMPANY
PZ0CO1300 APPROVAL FROM MINISTRY OF REGIONAL MUNI 35 07-Nov-13 19-Dec-13 0 APPROVAL FROM MINISTRY OF REGIONAL MUNICIPALITIES & WATER RESOURCES
PZ0CO1310 APPROVAL FOR MOBILE CRUSHER & SCREENING 110 05-Aug-13 21-Dec-13 71 APPROVAL FOR MOBILE CRUSHER & SCREENING PLANT
PZ0CO1320 APPROVAL FOR BORROW PITS FOR RIP RAP & F 110 05-Aug-13 21-Dec-13 239 APPROVAL FOR BORROW PITS FOR RIP RAP & FILLING MATERIAL
PZ0CO1330 APPROVAL FOR BORROW PITS FOR FILLING MAT 27 18-Nov-13 21-Dec-13 77 APPROVAL FOR BORROW PITS FOR FILLING MATERIAL
MILE STONE 805 23-Oct-13 20-Jun-16 0
PZ0CO1340 CONTRACT AWARD DATE 1 23-Oct-13* 23-Oct-13 0 CONTRACT AWARD DATE
PZ0CO1350 MOBILIZATION 48 23-Oct-13 21-Dec-13 7 MOBILIZATION
PZ0CO1360 CONSTRUCTION DURATION 972 23-Oct-13 20-Jun-16 0
PZ0CO1370 COMPLETION DATE 0 20-Jun-16* 0
MOBILIZATION 230 23-Oct-13 24-Jul-14 48 24-Jul-14, MOBILIZATION
DETAIL MOBILIZATION PLAN 230 23-Oct-13 24-Jul-14 48 24-Jul-14, DETAIL MOBILIZATION PLAN
ESTABLISH CONTRACTOR'S
CONTRA OFFICE 56 23-Oct-13 30-Dec-13 7 30-Dec-13, ESTABLISH CONTRACTOR'S OFFICE
PZ0MO1000 LABOUR ACCOMODATION 20 23-Oct-13 16-Nov-13 7 LABOUR ACCOMODATION
PZ0MO1010 INSTALLATION OF TOILETS FOR LABOUR CAMP 13 26-Oct-13 10-Nov-13 7 INSTALLATION OF TOILETS FOR LABOUR CAMP
PZ0MO1020 OBTAIN ELECTRICAL CONNECTION 29 26-Oct-13 01-Dec-13 7 OBTAIN ELECTRICAL CONNECTION

Actual Work Critical Remaining Work Summary Page 1 of 57 TASK filter: All Activities

Remaining Work Milestone © Oracle Corporation


DUALIZATION OF MAHDAH - AL RAWDAH ROAD PROJECT Classic Schedule Layout 25-May-14 16:51

Activity ID Activity Name Original Start Finish Total Float Critical 2014 2015 2016
Duration
S Oct N D J F M Apr M J Jul A S Oct N D Jan F M Apr M J Jul A S Oct N D J F M Apr M J
PZ0MO1030 STAFF ACCOMODATION 44 28-Oct-13 21-Dec-13 7 STAFF ACCOMODATION
PZ0MO1040 CONTRACTOR'S OFFICE 40 02-Nov-13 21-Dec-13 7 CONTRACTOR'S OFFICE
PZ0MO1050 OBTAIN TELEPHONE CONNECTION 40 02-Nov-13 21-Dec-13 7 OBTAIN TELEPHONE CONNECTION
PZ0MO1060 SETTING UP LABORATORY 37 06-Nov-13 21-Dec-13 7 SETTING UP LABORATORY
PZ0MO1070 FURNISHING LABORATORY 14 15-Dec-13 30-Dec-13 7 FURNISHING LABORATORY
ESTABLISH CONSULTANT'S
CONSU FACILITIES 53 27-Nov-13 30-Jan-14 7 30-Jan-14, ESTABLISH CONSULTANT'S FACILITIES
PZ0MO1080 CONSULTANT OFFICE 39 27-Nov-13 14-Jan-14 7 CONSULTANT OFFICE
PZ0MO1090 FURNISHING OFFICE 9 15-Jan-14 25-Jan-14 12 FURNISHING OFFICE
PZ0MO1100 OBTAIN ELECTRICAL CONNECTION 5 15-Jan-14 20-Jan-14 7 OBTAIN ELECTRICAL CONNECTION
PZ0MO1110 OBTAIN TELEPHONE CONNECTION 9 21-Jan-14 30-Jan-14 7 OBTAIN TELEPHONE CONNECTION
INSTALLATION OF P
PLANT & EQUIPMENTS 230 23-Oct-13 24-Jul-14 48 24-Jul-14, INSTALLATION OF PLANT & EQUIPMENTS
PZ0MO1120 INSTALLATION OF CRUSHER PLANT 1 66 23-Oct-13 11-Jan-14 53 INSTALLATION OF CRUSHER PLANT 1
PZ0MO1130 ARRANGEMENT FOR CRUSHER PLANT 2 83 12-Jan-14 19-Apr-14 53 ARRANGEMENT FOR CRUSHER PLANT 2
PZ0MO1140 INSTALLATION OF CRUSHER PLANT 2 59 20-Apr-14 28-Jun-14 53 INSTALLATION OF CRUSHER PLANT 2
PZ0MO1150 INSTALLATION OF SCRENNING PLANT 1 66 23-Oct-13 11-Jan-14 53 INSTALLATION OF SCRENNING PLANT 1
PZ0MO1160 ARRANGEMENT FOR SCREENING PLANT 2 83 12-Jan-14 19-Apr-14 53 ARRANGEMENT FOR SCREENING PLANT 2
PZ0MO1170 INSTALLATION OF SCRENNING PLANT 2 59 20-Apr-14 28-Jun-14 53 INSTALLATION OF SCRENNING PLANT 2
PZ0MO1180 INSTALLATION OF BATCHING PLANT 1 73 23-Oct-13 20-Jan-14 7 INSTALLATION OF BATCHING PLANT 1
PZ0MO1190 ARRANGEMNT FOR BATCHING PLANT 2 81 21-Jan-14 24-Apr-14 48 ARRANGEMNT FOR BATCHING PLANT 2
PZ0MO1200 INSTALLATION OF BATCHING PLANT 2 76 26-Apr-14 24-Jul-14 48 INSTALLATION OF BATCHING PLANT 2
PZ0MO1210 INSTALLATION OF ASPHALT PLANT 77 20-Feb-14 20-May-14 10 INSTALLATION OF ASPHALT PLANT
PROJECT SIGN BOARD
BOA 42 02-Dec-13 20-Jan-14 7 20-Jan-14, PROJECT SIGN BOARD
PZ0MO1220 DESIGN & APPROVAL 18 02-Dec-13 22-Dec-13 7 DESIGN & APPROVAL
PZ0MO1230 FABRICATION 19 23-Dec-13 14-Jan-14 7 FABRICATION
PZ0MO1240 SHIFTING & ERECTION 7 12-Jan-14 20-Jan-14 7 SHIFTING & ERECTION
N.O.C. FROM DIFF. GOVT.
GOV AUTHORITIES - RECEIPT OF EXCAVATION PE 1 21-Dec-13 21-Dec-13 0 21-Dec-13, N.O.C. FROM DIFF. GOVT. AUTHORITIES - RECEIPT OF EXCAVATION PERMIT
PZ0CO1380 DATE OF RECEIPT OF EXCAVATION PERMIT 1 21-Dec-13 21-Dec-13 0 DATE OF RECEIPT OF EXCAVATION PERMIT
ENGINEERING ACTIVITIES
ACTIVIT 772 04-Dec-13 20-Jun-16 0
SURVEY WORKS 88 04-Dec-13 17-Mar-14 53 17-Mar-14, SURVEY WORKS
BENCH MARKS, TRAVERSE
TRA & CENTERLINE MARKING 15 04-Dec-13 21-Dec-13 15 21-Dec-13, BENCH MARKS, TRAVERSE & CENTERLINE MARKING
EZ0CO1000 BENCH MARKS, TRAVERSE & CENTERLINE MARK 15 04-Dec-13 21-Dec-13 15 BENCH MARKS, TRAVERSE & CENTERLINE MARKING
O.G.L. SURVEY 73 22-Dec-13 17-Mar-14 53 17-Mar-14, O.G.L. SURVEY
EZ0CO1010 O.G.L. SURVEY FOR PART 1 (FROM KM 0+000 to K 20 22-Dec-13 14-Jan-14 0 O.G.L. SURVEY FOR PART 1 (FROM KM 0+000 to KM 20+000 )
EZ0CO1020 O.G.L. SURVEY FOR PART 3 (FROM KM 40+000 to 20 08-Feb-14 02-Mar-14 1 O.G.L. SURVEY FOR PART 3 (FROM KM 40+000 to KM 58+594.604)
EZ0CO1030 O.G.L. SURVEY FOR PART 2 (FROM KM 20+000 to 20 15-Jan-14 06-Feb-14 1 O.G.L. SURVEY FOR PART 2 (FROM KM 20+000 to KM 40+000 )
EZ0CO1040 PREPARATION FOR CROSS SECTION FOR PART 16 23-Dec-13 09-Jan-14 0 PREPARATION FOR CROSS SECTION FOR PART 1
EZ0CO1050 PREPARATION FOR CROSS SECTION FOR PART 17 16-Jan-14 04-Feb-14 73 PREPARATION FOR CROSS SECTION FOR PART 2
EZ0CO1060 PREPARATION FOR CROSS SECTION FOR PART 17 09-Feb-14 27-Feb-14 34 PREPARATION FOR CROSS SECTION FOR PART 3
EZ0CO1070 SUBMISSION OF CROSS SECTION OF PART 1 1 11-Jan-14 11-Jan-14 0 SUBMISSION OF CROSS SECTION OF PART 1
EZ0CO1080 SUBMISSION OF CROSS SECTION OF PART 2 1 05-Feb-14 05-Feb-14 73 SUBMISSION OF CROSS SECTION OF PART 2
EZ0CO1090 SUBMISSION OF CROSS SECTION OF PART 3 1 01-Mar-14 01-Mar-14 34 SUBMISSION OF CROSS SECTION OF PART 3
EZ0CO1100 APPROVAL OF CROSS SECTION OF PART 1 14 12-Jan-14 28-Jan-14 0 APPROVAL OF CROSS SECTION OF PART 1
EZ0CO1110 APPROVAL OF CROSS SECTION OF PART 2 14 06-Feb-14 22-Feb-14 73 APPROVAL OF CROSS SECTION OF PART 2
EZ0CO1120 APPROVAL OF CROSS SECTION OF PART 3 14 02-Mar-14 17-Mar-14 34 APPROVAL OF CROSS SECTION OF PART 3
METHOD STATEMENTS [PREPARATION, SUBMISSIONS & APPROVALS] 236 11-Jan-14 22-Oct-14 364 22-Oct-14, METHOD STATEMENTS [PREPARATION, SUBMISSIONS & APPROVALS
ROAD WORKS 185 11-Jan-14 20-Aug-14 415 20-Aug-14, ROAD WORKS
EZ0CO1130 EARTH WORKS 25 11-Jan-14 09-Feb-14 7 EARTH WORKS
EZ0CO1140 ASPHALTING 27 20-Apr-14 20-May-14 10 ASPHALTING
EZ0CO1150 RIP RAP 24 20-Jul-14 20-Aug-14 10 RIP RAP
EZ0CO1160 GUARD RAILS 26 10-Apr-14 10-May-14 417 GUARD RAILS
EZ0CO1170 ROAD MARKINGS 24 17-Jul-14 18-Aug-14 417 ROAD MARKINGS
MIX DESIGNS 54 23-Jan-14 26-Mar-14 10 26-Mar-14, MIX DESIGNS

Actual Work Critical Remaining Work Summary Page 2 of 57 TASK filter: All Activities

Remaining Work Milestone © Oracle Corporation


DUALIZATION OF MAHDAH - AL RAWDAH ROAD PROJECT Classic Schedule Layout 25-May-14 16:51

Activity ID Activity Name Original Start Finish Total Float Critical 2014 2015 2016
Duration
S Oct N D J F M Apr M J Jul A S Oct N D Jan F M Apr M J Jul A S Oct N D J F M Apr M J
EZ0CO1180 CONCRETE MIX DESIGN 27 23-Jan-14 23-Feb-14 10 CONCRETE MIX DESIGN
EZ0CO1190 ASPHALT & POLYMER MODIFIED BITUMINOUS MI 27 24-Feb-14 26-Mar-14 10 ASPHALT & POLYMER MODIFIED BITUMINOUS MIX DESIGN
INTERCHANGES, UNDERPASSES
UN & CULVERTS 229 20-Jan-14 22-Oct-14 39 22-Oct-14, INTERCHANGES, UNDERPASSES & CULVERTS
CULVERTS 27 20-Jan-14 19-Feb-14 12 19-Feb-14, CULVERTS
EZ0CO1200 CULVERTS 27 20-Jan-14 19-Feb-14 12 CULVERTS
INTERCHANGES 172 27-Mar-14 22-Oct-14 39 22-Oct-14, INTERCHANGES
SUB STRUCTURE
STRUCTU 41 27-Mar-14 13-May-14 10 13-May-14, SUB STRUCTURE
EZ0CO1210 ABUTMENT 30 27-Mar-14 30-Apr-14 10 ABUTMENT
EZ0CO1220 PIERS 26 14-Apr-14 13-May-14 10 PIERS
SUPER STRUCTURE
STRUC 104 16-Jun-14 22-Oct-14 39 22-Oct-14, SUPER STRUCTURE
EZ0CO1230 SOFFIT 25 16-Jun-14 14-Jul-14 10 SOFFIT
EZ0CO1240 WEB 25 16-Jun-14 14-Jul-14 10 WEB
EZ0CO1250 DECK SLAB 25 15-Jul-14 17-Aug-14 10 DECK SLAB
EZ0CO1260 BEARINGS 24 18-Aug-14 14-Sep-14 39 BEARINGS
EZ0CO1270 PRE STRESSING 30 15-Sep-14 22-Oct-14 39 PRE STRESSING
UNDERPASSES 111 12-Apr-14 24-Aug-14 25 24-Aug-14, UNDERPASSES
EZ0CO1280 FOUNDATION 27 12-Apr-14 12-May-14 10 FOUNDATION
EZ0CO1290 RCC WALL 28 13-May-14 15-Jun-14 10 RCC WALL
EZ0CO1300 DECK SLAB 24 24-Jul-14 24-Aug-14 25 DECK SLAB
ELECTRICAL WORK
WORKS 28 18-Mar-14 19-Apr-14 34 19-Apr-14, ELECTRICAL WORKS
EZ0CO1310 ELECTRICAL 28 18-Mar-14 19-Apr-14 34 ELECTRICAL
PREPARATION & APPROVAL
APPR OF WORKING DRAWINGS 475 22-Dec-13 13-Jul-15 149 13-Jul-15, PREPARATION & APPROVAL OF W
SHOP DRAWING PREPARATION
PR & SUBMITTAL 468 22-Dec-13 05-Jul-15 149 05-Jul-15, SHOP DRAWING PREPARATION & S
EZ0CO1320 PRECAST FOR BARRIERS 15 14-Apr-14 30-Apr-14 30 PRECAST FOR BARRIERS
EZ0CO1330 PRECAST FOR MSER WALL 15 28-May-14 14-Jun-14 25 PRECAST FOR MSER WALL
EZ0CO1340 ROAD FURNITURE 15 15-Jul-14 05-Aug-14 39 ROAD FURNITURE
UNDERPASSES SUBMITTAL
S 261 09-Apr-14 21-Feb-15 49 21-Feb-15, UNDERPASSES SUBMITTAL
UNDER PASS AT
A 15+235 14 01-Jul-14 16-Jul-14 70 16-Jul-14, UNDER PASS AT 15+235
EZ0CO2730 UNP. 15+235 FOUNDATION 7 01-Jul-14 08-Jul-14 69 UNP. 15+235 FOUNDATION
EZ0CO2740 UNP. 15+235 SUPER STRUCTURE 7 09-Jul-14 16-Jul-14 70 UNP. 15+235 SUPER STRUCTURE
UNDER PASS AT
A 5+095 14 09-Apr-14 24-Apr-14 55 24-Apr-14, UNDER PASS AT 5+095
EZ0CO2710 UNP. 5+095 FOUNDATION 7 09-Apr-14 16-Apr-14 54 UNP. 5+095 FOUNDATION
EZ0CO2720 UNP. 5+095 SUPER STRUCTURE 7 17-Apr-14 24-Apr-14 55 UNP. 5+095 SUPER STRUCTURE
UNDER PASS AT
A 44+240 14 05-Feb-15 21-Feb-15 49 21-Feb-15, UNDER PASS AT 44+240
EZ0CO2770 UNP. 44+240 FOUNDATION 7 05-Feb-15 12-Feb-15 49 UNP. 44+240 FOUNDATION
EZ0CO2780 UNP. 44+240 SUPER STRUCTURE 7 14-Feb-15 21-Feb-15 49 UNP. 44+240 SUPER STRUCTURE
UNDER PASS AT
A 25+945 14 12-Nov-14 30-Nov-14 24 30-Nov-14, UNDER PASS AT 25+945
EZ0CO2750 UNP. 25+945 FOUNDATION 7 12-Nov-14 19-Nov-14 23 UNP. 25+945 FOUNDATION
EZ0CO2760 UNP. 25+945 SUPER STRUCTURE 7 20-Nov-14 30-Nov-14 24 UNP. 25+945 SUPER STRUCTURE
INTERCHANGES SUBMITTAL 395 18-Mar-14 05-Jul-15 80 05-Jul-15, INTERCHANGES SUBMITTAL
INTERCHANGE 11+630 30 18-Mar-14 21-Apr-14 26 21-Apr-14, INTERCHANGE 11+630
EZ0CO2790 INT. 11+630 FOUNDATION 10 18-Mar-14 29-Mar-14 25 INT. 11+630 FOUNDATION
EZ0CO2800 INT. 11+630 SUB STRUCTURE 10 30-Mar-14 09-Apr-14 26 INT. 11+630 SUB STRUCTURE
EZ0CO2810 INT. 11+630 SUPER STRUCTURE 10 10-Apr-14 21-Apr-14 26 INT. 11+630 SUPER STRUCTURE
INTERCHANGE AT 34+700 30 23-Aug-14 25-Sep-14 47 25-Sep-14, INTERCHANGE AT 34+700
EZ0CO2820 INT. 34+700 FOUNDATION 10 23-Aug-14 02-Sep-14 23 INT. 34+700 FOUNDATION
EZ0CO2830 INT. 34+700 SUB STRUCTURE 10 03-Sep-14 14-Sep-14 23 INT. 34+700 SUB STRUCTURE
EZ0CO2840 INT. 34+700 SUPER STRUCTURE 10 15-Sep-14 25-Sep-14 47 INT. 34+700 SUPER STRUCTURE
INTERCHANGE AT RAWDAH PART 2 [FROM RAWDAH TO MAHDA 30 27-Apr-15 31-May-15 47 31-May-15, INTERCHANGE AT RAWDAH PART 2 [FR
EZ0CO2880 INT. RAW P2 FOUNDATION 10 27-Apr-15 07-May-15 23 INT. RAW P2 FOUNDATION
EZ0CO2890 INT. RAW P2 SUB STRUCTURE 10 09-May-15 19-May-15 27 INT. RAW P2 SUB STRUCTURE
EZ0CO2900 INT. RAW P2 SUPER STRUCTURE 10 20-May-15 31-May-15 47 INT. RAW P2 SUPER STRUCTURE
INTERCHANGE AT HUMAIDAH 30 01-Jun-15 05-Jul-15 80 05-Jul-15, INTERCHANGE AT HUMAIDAH

Actual Work Critical Remaining Work Summary Page 3 of 57 TASK filter: All Activities

Remaining Work Milestone © Oracle Corporation


DUALIZATION OF MAHDAH - AL RAWDAH ROAD PROJECT Classic Schedule Layout 25-May-14 16:51

Activity ID Activity Name Original Start Finish Total Float Critical 2014 2015 2016
Duration
S Oct N D J F M Apr M J Jul A S Oct N D Jan F M Apr M J Jul A S Oct N D J F M Apr M J
EZ0CO2910 INT. HUM FOUNDATION 10 01-Jun-15 11-Jun-15 80 INT. HUM FOUNDATION
EZ0CO2920 INT. HUM SUB STRUCTURE 10 13-Jun-15 23-Jun-15 80 INT. HUM SUB STRUCTURE
EZ0CO2930 INT. HUM SUPER STRUCTURE 10 24-Jun-15 05-Jul-15 80 INT. HUM SUPER STRUCTURE
INTERCHANGE AT RAWDAH PART 1 [FROM MAHDAH TO RAWDA 29 25-Dec-14 28-Jan-15 50 28-Jan-15, INTERCHANGE AT RAWDAH PART 1 [FROM MAHDAH TO
EZ0CO2850 INT. RAW P1 FOUNDATION 9 25-Dec-14 05-Jan-15 23 INT. RAW P1 FOUNDATION
EZ0CO2860 INT. RAW P1 SUB STRUCTURE 10 06-Jan-15 17-Jan-15 23 INT. RAW P1 SUB STRUCTURE
EZ0CO2870 INT. RAW P1 SUPER STRUCTURE 10 18-Jan-15 28-Jan-15 50 INT. RAW P1 SUPER STRUCTURE
CULVERTS - SHOP
SHO DRAWING PREPARATION & SUBMITTAL 390 10-Feb-14 24-May-15 185 24-May-15, CULVERTS - SHOP DRAWING PREPARA
PHASE 1 CULVERTS
CULV - SHOP DRAWING PREPARATION & SUBMITT 149 10-Feb-14 07-Aug-14 75 07-Aug-14, PHASE 1 CULVERTS - SHOP DRAWING PREPARATION & SUBMITTAL
EZ0CO1350 7.02 CELL BOX CULVERT @ CH 2+335 - (1.5X1.5) 2 10-Feb-14 11-Feb-14 1 7.02 CELL BOX CULVERT @ CH 2+335 - (1.5X1.5)
EZ0CO1360 9.02 CELL BOX CULVERT @ CH 2+870 - (2.0X1.5) 3 12-Feb-14 15-Feb-14 1 9.02 CELL BOX CULVERT @ CH 2+870 - (2.0X1.5)
EZ0CO1370 10.07 CELL BOX CULVERT @ CH 3+400 - (2.0X2.0) 3 16-Feb-14 18-Feb-14 1 10.07 CELL BOX CULVERT @ CH 3+400 - (2.0X2.0)
EZ0CO1380 12.06 CELL BOX CULVERT @ CH 3+975 - (2.0X2.0) 7 19-Feb-14 26-Feb-14 1 12.06 CELL BOX CULVERT @ CH 3+975 - (2.0X2.0)
EZ0CO1390 13.02 CELL BOX CULVERT @ CH 4+320 - (2.0X1.5) 6 27-Feb-14 05-Mar-14 1 13.02 CELL BOX CULVERT @ CH 4+320 - (2.0X1.5)
EZ0CO1400 16.02 CELL BOX CULVERT @ CH 5+450 - (2.0X1.5) 3 06-Mar-14 09-Mar-14 1 16.02 CELL BOX CULVERT @ CH 5+450 - (2.0X1.5)
EZ0CO1410 19.02 CELL BOX CULVERT @ CH 7+170 - (2.0X1.5) 4 10-Mar-14 13-Mar-14 1 19.02 CELL BOX CULVERT @ CH 7+170 - (2.0X1.5)
EZ0CO1420 20.03 CELL BOX CULVERT @ CH 10+140 - (2.0X1.5 3 15-Mar-14 17-Mar-14 1 20.03 CELL BOX CULVERT @ CH 10+140 - (2.0X1.5)
EZ0CO1430 21.03 CELL BOX CULVERT @ CH 10+680 - (2.0X1.5 3 18-Mar-14 20-Mar-14 1 21.03 CELL BOX CULVERT @ CH 10+680 - (2.0X1.5)
EZ0CO1440 22.02 CELL BOX CULVERT @ CH 11+790 - (2.0X1.5 4 22-Mar-14 25-Mar-14 1 22.02 CELL BOX CULVERT @ CH 11+790 - (2.0X1.5)
EZ0CO1450 23.03 CELL BOX CULVERT @ CH 12+615 - (2.0X1.5 5 26-Mar-14 31-Mar-14 1 23.03 CELL BOX CULVERT @ CH 12+615 - (2.0X1.5)
EZ0CO1460 24.06 CELL BOX CULVERT @ CH 13+150 - (2.0X1.5 4 01-Apr-14 05-Apr-14 1 24.06 CELL BOX CULVERT @ CH 13+150 - (2.0X1.5)
EZ0CO1470 32.06 CELL BOX CULVERT @ CH 15+880 - (1.5X1.5 6 06-Apr-14 12-Apr-14 1 32.06 CELL BOX CULVERT @ CH 15+880 - (1.5X1.5)
EZ0CO1480 34.51 CELL BOX CULVERT @ CH 16+725 - (3.0X2.0 6 13-Apr-14 19-Apr-14 1 34.51 CELL BOX CULVERT @ CH 16+725 - (3.0X2.0)
EZ0CO1490 35.24 CELL BOX CULVERT @ CH 16+992 - (3.0X2.0 18 20-Apr-14 10-May-14 1 35.24 CELL BOX CULVERT @ CH 16+992 - (3.0X2.0)
EZ0CO1500 36.39 CELL BOX CULVERT @ CH 17+210 - (3.0X2.0 14 11-May-14 26-May-14 1 36.39 CELL BOX CULVERT @ CH 17+210 - (3.0X2.0)
EZ0CO1510 37.06 CELL BOX CULVERT @ CH 17+445 - (3.0X2.0 20 28-May-14 19-Jun-14 1 37.06 CELL BOX CULVERT @ CH 17+445 - (3.0X2.0)
EZ0CO1520 41.06 CELL BOX CULVERT @ CH 18+600 - (2.0X1.5 13 21-Jun-14 05-Jul-14 1 41.06 CELL BOX CULVERT @ CH 18+600 - (2.0X1.5)
EZ0CO1530 42.14 CELL BOX CULVERT @ CH 18+975 - (3.0X1.5 6 06-Jul-14 12-Jul-14 1 42.14 CELL BOX CULVERT @ CH 18+975 - (3.0X1.5)
EZ0CO1540 43.02 CELL BOX CULVERT @ CH 19+280 - (2.0X1.5 9 13-Jul-14 22-Jul-14 1 43.02 CELL BOX CULVERT @ CH 19+280 - (2.0X1.5)
EZ0CO1550 44.02 CELL BOX CULVERT @ CH 19+540 - (2.0X1.5 3 24-Jul-14 27-Jul-14 24 44.02 CELL BOX CULVERT @ CH 19+540 - (2.0X1.5)
EZ0CO1560 45.03 CELL BOX CULVERT @ CH 19+940 - (2.0X1.5 4 31-Jul-14 04-Aug-14 24 45.03 CELL BOX CULVERT @ CH 19+940 - (2.0X1.5)
SINGLE CELL
CEL CULVERTS - 24NOS PREPARATION & SUBMITTA 128 06-Mar-14 07-Aug-14 75 07-Aug-14, SINGLE CELL CULVERTS - 24NOS PREPARATION & SUBMITTAL
EZ0CO15 PART 1 PRECASTING FOR CULVERTS NOS 1,2,3 6 06-Mar-14 12-Mar-14 12 PART 1 PRECASTING FOR CULVERTS NOS 1,2,3
EZ0CO15 PART 1 PRECASTING FOR CULVERTS NOS 4,5,6 3 06-Apr-14 08-Apr-14 31 PART 1 PRECASTING FOR CULVERTS NOS 4,5,6
EZ0CO15 PART 1 PRECASTING FOR CULVERTS NOS 7,8,9 3 20-Apr-14 22-Apr-14 41 PART 1 PRECASTING FOR CULVERTS NOS 7,8,9
EZ0CO16 PART 1 PRECASTING FOR CULVERTS NOS 10,11 4 28-May-14 01-Jun-14 41 PART 1 PRECASTING FOR CULVERTS NOS 10,11,12
EZ0CO16 PART 1 PRECASTING FOR CULVERTS NOS 13,14 6 21-Jun-14 26-Jun-14 41 PART 1 PRECASTING FOR CULVERTS NOS 13,14,15
EZ0CO16 PART 1 PRECASTING FOR CULVERTS NOS 16,17 6 13-Jul-14 19-Jul-14 44 PART 1 PRECASTING FOR CULVERTS NOS 16,17,18
EZ0CO16 PART 1 PRECASTING FOR CULVERTS NOS 19,20 3 31-Jul-14 03-Aug-14 57 PART 1 PRECASTING FOR CULVERTS NOS 19,20,21
EZ0CO16 PART 1 PRECASTING FOR CULVERTS NOS 22,23 3 05-Aug-14 07-Aug-14 75 PART 1 PRECASTING FOR CULVERTS NOS 22,23,24
PHASE 2 CULVERTS
CULV - SHOP DRAWING PREPARATION & SUBMITT 138 24-Jul-14 12-Jan-15 265 12-Jan-15, PHASE 2 CULVERTS - SHOP DRAWING PREPARATION & S
EZ0CO1650 46.2CELL BOX CULVERT @ CH 20+170 (2.0 x 2.0) 4 24-Jul-14 31-Jul-14 1 46.2CELL BOX CULVERT @ CH 20+170 (2.0 x 2.0)
EZ0CO1660 48.2CELL BOX CULVERT @ CH 21+510 (2.0 x 1.5) 4 02-Aug-14 05-Aug-14 1 48.2CELL BOX CULVERT @ CH 21+510 (2.0 x 1.5)
EZ0CO1670 50.4CELL BOX CULVERT @ CH 22+320 (3.0 x 2.0 ) 3 06-Aug-14 09-Aug-14 1 50.4CELL BOX CULVERT @ CH 22+320 (3.0 x 2.0 )
EZ0CO1680 63.4CELL BOX CULVERT @ CH 27+275 (4.0 x 2.0) 3 10-Aug-14 12-Aug-14 1 63.4CELL BOX CULVERT @ CH 27+275 (4.0 x 2.0)
EZ0CO1690 64.4CELL BOX CULVERT @ CH 27+378 (4.0 x 2.0) 4 13-Aug-14 17-Aug-14 1 64.4CELL BOX CULVERT @ CH 27+378 (4.0 x 2.0)
EZ0CO1700 65.4CELL BOX CULVERT @ CH 27+470 (4.0 x 2.0) 4 18-Aug-14 21-Aug-14 1 65.4CELL BOX CULVERT @ CH 27+470 (4.0 x 2.0)
EZ0CO1710 73.2CELL BOX CULVERT @ CH 30+040 (2.0 x 1.5) 3 23-Aug-14 25-Aug-14 1 73.2CELL BOX CULVERT @ CH 30+040 (2.0 x 1.5)
EZ0CO1720 74.3CELL BOX CULVERT @ CH 30+330 (2.0 x 1.5) 3 26-Aug-14 28-Aug-14 1 74.3CELL BOX CULVERT @ CH 30+330 (2.0 x 1.5)
EZ0CO1730 75.12CELL BOX CULVERT @ CH 30+450 (2.0 x 1.5) 4 30-Aug-14 02-Sep-14 1 75.12CELL BOX CULVERT @ CH 30+450 (2.0 x 1.5)
EZ0CO1740 77.3CELL BOX CULVERT @ CH 30+920 (2.0 x 1.5) 5 03-Sep-14 08-Sep-14 1 77.3CELL BOX CULVERT @ CH 30+920 (2.0 x 1.5)

Actual Work Critical Remaining Work Summary Page 4 of 57 TASK filter: All Activities

Remaining Work Milestone © Oracle Corporation


DUALIZATION OF MAHDAH - AL RAWDAH ROAD PROJECT Classic Schedule Layout 25-May-14 16:51

Activity ID Activity Name Original Start Finish Total Float Critical 2014 2015 2016
Duration
S Oct N D J F M Apr M J Jul A S Oct N D Jan F M Apr M J Jul A S Oct N D J F M Apr M J
EZ0CO1750 80.2CELL BOX CULVERT @ CH 31+650 (2.0 x 1.5) 3 09-Sep-14 11-Sep-14 1 80.2CELL BOX CULVERT @ CH 31+650 (2.0 x 1.5)
EZ0CO1760 82.2CELL BOX CULVERT @ CH 32+250 (2.0 x 1.5) 3 13-Sep-14 15-Sep-14 1 82.2CELL BOX CULVERT @ CH 32+250 (2.0 x 1.5)
EZ0CO1770 83.83CELL BOX CULVERT @ CH 32+800 (3.0 x 2.0) 4 16-Sep-14 20-Sep-14 1 83.83CELL BOX CULVERT @ CH 32+800 (3.0 x 2.0)
EZ0CO1780 84.5CELL BOX CULVERT @ CH 33+134 (3.0 x 2.0) 7 21-Sep-14 28-Sep-14 1 84.5CELL BOX CULVERT @ CH 33+134 (3.0 x 2.0)
EZ0CO1790 85.26CELL BOX CULVERT @ CH33+217 (3.0 x 2.0) 5 29-Sep-14 07-Oct-14 1 85.26CELL BOX CULVERT @ CH33+217 (3.0 x 2.0)
EZ0CO1800 86.2CELL BOX CULVERT @ CH33+440 ( 2.0 x 1.5) 7 08-Oct-14 15-Oct-14 1 86.2CELL BOX CULVERT @ CH33+440 ( 2.0 x 1.5)
EZ0CO1810 87.2CELL BOX CULVERT @ CH 33+590 (2.0 x 1.5) 3 16-Oct-14 19-Oct-14 1 87.2CELL BOX CULVERT @ CH 33+590 (2.0 x 1.5)
EZ0CO1820 88.2CELL BOX CULVERT @ CH 33+730 (2.0 x1.5) 3 20-Oct-14 22-Oct-14 1 88.2CELL BOX CULVERT @ CH 33+730 (2.0 x1.5)
EZ0CO1830 90.2CELL BOX CULVERT @ CH 34+242 (2.0 x 1.5) 3 23-Oct-14 27-Oct-14 1 90.2CELL BOX CULVERT @ CH 34+242 (2.0 x 1.5)
EZ0CO1840 91.2CELL BOX CULVERT @ CH34+522 (2.0 x 1.5) 3 28-Oct-14 30-Oct-14 1 91.2CELL BOX CULVERT @ CH34+522 (2.0 x 1.5)
EZ0CO1850 92.2CELL BOX CULVERT @ CH34+640 ( 2.0 x 1.5) 3 01-Nov-14 03-Nov-14 1 92.2CELL BOX CULVERT @ CH34+640 ( 2.0 x 1.5)
EZ0CO1860 93.2CELL BOX CULVERT @ CH 34+730 (2.0 x 1.5) 4 04-Nov-14 08-Nov-14 1 93.2CELL BOX CULVERT @ CH 34+730 (2.0 x 1.5)
EZ0CO1870 94.3CELL BOX CULVERT @ CH 34+900 (2.0 x 1.5) 3 09-Nov-14 11-Nov-14 1 94.3CELL BOX CULVERT @ CH 34+900 (2.0 x 1.5)
EZ0CO1880 95.3CELL BOX CULVERT @ CH 35+100 (2.0 x 1.5) 4 12-Nov-14 16-Nov-14 23 95.3CELL BOX CULVERT @ CH 35+100 (2.0 x 1.5)
EZ0CO1890 96.2CELL BOX CULVERT @ CH35+320 ( 2.0 x 1.5) 3 17-Nov-14 19-Nov-14 23 96.2CELL BOX CULVERT @ CH35+320 ( 2.0 x 1.5)
EZ0CO1900 98.4CELL BOX CULVERT @ CH36+230 (2.0 x 1.5) 3 20-Nov-14 25-Nov-14 23 98.4CELL BOX CULVERT @ CH36+230 (2.0 x 1.5)
EZ0CO1910 99.9CELL BOX CULVERT @ CH 36+520 (2.0 x 1.5) 4 26-Nov-14 30-Nov-14 23 99.9CELL BOX CULVERT @ CH 36+520 (2.0 x 1.5)
EZ0CO1920 101.5CELL BOX CULVERT @ CH 36+840 (2.0 x 1.5) 6 01-Dec-14 07-Dec-14 23 101.5CELL BOX CULVERT @ CH 36+840 (2.0 x 1.5)
EZ0CO1930 102.15CELL BOX CULVERT @ CH 37+350 (3.0 x 2.0 5 08-Dec-14 13-Dec-14 23 102.15CELL BOX CULVERT @ CH 37+350 (3.0 x 2.0)
EZ0CO1940 104.3CELL BOX CULVERT @ CH 38+080 (2.0 x 1.5) 7 14-Dec-14 21-Dec-14 23 104.3CELL BOX CULVERT @ CH 38+080 (2.0 x 1.5)
EZ0CO1950 108.2CELL BOX CULVERT @ CH 39+107 (2.0 x 1.5 ) 3 22-Dec-14 24-Dec-14 23 108.2CELL BOX CULVERT @ CH 39+107 (2.0 x 1.5 )
SINGLE CELL
CEL CULVERTS - 30NOS PREPARATION & SUBMITTA 79 08-Oct-14 12-Jan-15 265 12-Jan-15, SINGLE CELL CULVERTS - 30NOS PREPARATION & SUBMI
EZ0CO19 PART 2 PRE CASTING FOR CULVERTS NOS 1,2,3 3 08-Oct-14 11-Oct-14 15 PART 2 PRE CASTING FOR CULVERTS NOS 1,2,3
EZ0CO19 PART 2 PRE CASTING FOR CULVERTS NOS 4,5,6 3 04-Nov-14 06-Nov-14 20 PART 2 PRE CASTING FOR CULVERTS NOS 4,5,6
EZ0CO19 PART 2 PRE CASTING FOR CULVERTS NOS 7,8,9 3 01-Dec-14 03-Dec-14 35 PART 2 PRE CASTING FOR CULVERTS NOS 7,8,9
EZ0CO19 PART 2 PRE CASTING FOR CULVERTS NOS 10,11 3 04-Dec-14 07-Dec-14 63 PART 2 PRE CASTING FOR CULVERTS NOS 10,11,12
EZ0CO20 PART 2 PRE CASTING FOR CULVERTS NOS 13,14 3 08-Dec-14 10-Dec-14 92 PART 2 PRE CASTING FOR CULVERTS NOS 13,14,15
EZ0CO20 PART 2 PRE CASTING FOR CULVERTS NOS 16,17 3 25-Dec-14 28-Dec-14 108 PART 2 PRE CASTING FOR CULVERTS NOS 16,17,18
EZ0CO20 PART 2 PRE CASTING FOR CULVERTS NOS 19,20 3 29-Dec-14 31-Dec-14 142 PART 2 PRE CASTING FOR CULVERTS NOS 19,20,21
EZ0CO20 PART 2 PRE CASTING FOR CULVERTS NOS 22,23 3 01-Jan-15 05-Jan-15 176 PART 2 PRE CASTING FOR CULVERTS NOS 22,23,24
EZ0CO20 PART 2 PRE CASTING FOR CULVERTS NOS 25,26 3 06-Jan-15 08-Jan-15 231 PART 2 PRE CASTING FOR CULVERTS NOS 25,26,27
EZ0CO20 PART 2 PRE CASTING FOR CULVERTS NOS 28,29 3 10-Jan-15 12-Jan-15 265 PART 2 PRE CASTING FOR CULVERTS NOS 28,29,30
PHASE 3 CULVERTS
CULV - SHOP DRAWING PREPARATION & SUBMITT 163 12-Nov-14 24-May-15 185 24-May-15, PHASE 3 CULVERTS - SHOP DRAWING P
EZ0CO2060 110.2CELL BOX CULVERT @ CH40+872 (2.0 x 1.5) 4 12-Nov-14 16-Nov-14 1 110.2CELL BOX CULVERT @ CH40+872 (2.0 x 1.5)
EZ0CO2070 111.3CELL BOX CULVERT @ CH41+388 (2.0 x 1.5) 5 17-Nov-14 24-Nov-14 10 111.3CELL BOX CULVERT @ CH41+388 (2.0 x 1.5)
EZ0CO2080 116.3CELL BOX CULVERT @ CH42+580 (4.0 x 2.0) 6 25-Nov-14 01-Dec-14 10 116.3CELL BOX CULVERT @ CH42+580 (4.0 x 2.0)
EZ0CO2090 117.14CELL BOX CULVERT @ CH42+737 (4.0 x 2.0) 5 02-Dec-14 07-Dec-14 10 117.14CELL BOX CULVERT @ CH42+737 (4.0 x 2.0)
EZ0CO2100 118.36CELL BOX CULVERT @ CH42+918 (4.0 x 2.0) 7 08-Dec-14 15-Dec-14 10 118.36CELL BOX CULVERT @ CH42+918 (4.0 x 2.0)
EZ0CO2110 123.4CELL BOX CULVERT @ CH44+160 (2.0 x 2.0) 8 16-Dec-14 24-Dec-14 10 123.4CELL BOX CULVERT @ CH44+160 (2.0 x 2.0)
EZ0CO2120 125.2CELL BOX CULVERT @ CH45+650 (2.0 x 1.5) 6 25-Dec-14 31-Dec-14 10 125.2CELL BOX CULVERT @ CH45+650 (2.0 x 1.5)
EZ0CO2130 126.6CELL BOX CULVERT @ CH45+900 (2.0 x 1.5) 5 01-Jan-15 07-Jan-15 10 126.6CELL BOX CULVERT @ CH45+900 (2.0 x 1.5)
EZ0CO2140 127.3CELL BOX CULVERT @ CH46+250 (2.0 x 1.5) 5 08-Jan-15 13-Jan-15 10 127.3CELL BOX CULVERT @ CH46+250 (2.0 x 1.5)
EZ0CO2150 128.6CELL BOX CULVERT @ CH46+500 (2.0 x 1.5) 5 14-Jan-15 19-Jan-15 23 128.6CELL BOX CULVERT @ CH46+500 (2.0 x 1.5)
EZ0CO2160 129.2CELL BOX CULVERT @ CH46+570 (2.0 x1.5) 9 20-Jan-15 29-Jan-15 23 129.2CELL BOX CULVERT @ CH46+570 (2.0 x1.5)
EZ0CO2170 138.12CELL BOX CULVERT @ CH49+113 (3.0 x 1.5) 5 31-Jan-15 04-Feb-15 23 138.12CELL BOX CULVERT @ CH49+113 (3.0 x 1.5)
EZ0CO2180 139.3CELL BOX CULVERT @ CH49+600 (2.0 x 1.5) 7 05-Feb-15 12-Feb-15 23 139.3CELL BOX CULVERT @ CH49+600 (2.0 x 1.5)
EZ0CO2190 141.4CELL BOX CULVERT @ CH50+063 (2.0 x 1.5) 6 14-Feb-15 19-Feb-15 23 141.4CELL BOX CULVERT @ CH50+063 (2.0 x 1.5)
EZ0CO2200 142.7CELL BOX CULVERT @ CH50+217 (2.0 x 1.5) 6 21-Feb-15 26-Feb-15 23 142.7CELL BOX CULVERT @ CH50+217 (2.0 x 1.5)
EZ0CO2210 143.4CELL BOX CULVERT @ CH50+660 (2.0 x 1.5) 8 28-Feb-15 08-Mar-15 23 143.4CELL BOX CULVERT @ CH50+660 (2.0 x 1.5)
EZ0CO2220 149.2CELL BOX CULVERT @ CH52+480 (2.0 x 1.5) 6 09-Mar-15 15-Mar-15 23 149.2CELL BOX CULVERT @ CH52+480 (2.0 x 1.5)
EZ0CO2230 150.2CELL BOX CULVERT @ CH52+720 (2.0 x 1.5) 6 16-Mar-15 22-Mar-15 23 150.2CELL BOX CULVERT @ CH52+720 (2.0 x 1.5)

Actual Work Critical Remaining Work Summary Page 5 of 57 TASK filter: All Activities

Remaining Work Milestone © Oracle Corporation


DUALIZATION OF MAHDAH - AL RAWDAH ROAD PROJECT Classic Schedule Layout 25-May-14 16:51

Activity ID Activity Name Original Start Finish Total Float Critical 2014 2015 2016
Duration
S Oct N D J F M Apr M J Jul A S Oct N D Jan F M Apr M J Jul A S Oct N D J F M Apr M J
EZ0CO2240 151.4CELL BOX CULVERT @ CH53+300 (2.0 x 1.5) 5 23-Mar-15 28-Mar-15 23 151.4CELL BOX CULVERT @ CH53+300 (2.0 x 1.5)
EZ0CO2250 153.2CELL BOX CULVERT @ CH54+242 (2.0 x 1.5) 5 29-Mar-15 02-Apr-15 23 153.2CELL BOX CULVERT @ CH54+242 (2.0 x 1.5)
EZ0CO2260 159.2CELL BOX CULVERT @ CH55+762 (2.0 x 1.5) 6 04-Apr-15 09-Apr-15 23 159.2CELL BOX CULVERT @ CH55+762 (2.0 x 1.5)
EZ0CO2270 160.3CELL BOX CULVERT @ CH56+230 (3.0 x 2.0) 5 11-Apr-15 15-Apr-15 23 160.3CELL BOX CULVERT @ CH56+230 (3.0 x 2.0)
EZ0CO2280 161.8CELL BOX CULVERT @ CH56+420 (3.0 x 2.0) 4 16-Apr-15 20-Apr-15 23 161.8CELL BOX CULVERT @ CH56+420 (3.0 x 2.0)
EZ0CO2290 163.3CELL BOX CULVERT @ CH57+080 (2.0 x 1.5) 5 21-Apr-15 26-Apr-15 23 163.3CELL BOX CULVERT @ CH57+080 (2.0 x 1.5)
EZ0CO2300 166.4CELL BOX CULVERT @ CH58+150 (2.0 x 1.5) 5 27-Apr-15 02-May-15 71 166.4CELL BOX CULVERT @ CH58+150 (2.0 x 1.5)
EZ0CO2310 167.6CELL BOX CULVERT @ CH58+400 (2.0 x 1.5) 5 03-May-15 07-May-15 71 167.6CELL BOX CULVERT @ CH58+400 (2.0 x 1.5)
SINGLE CELL
CEL CULVERTS - 30NOS PREPARATION & SUBMITTA 163 12-Nov-14 24-May-15 185 24-May-15, SINGLE CELL CULVERTS - 30NOS PREP
EZ0CO23 PART 3 PRE CASTING FOR CULVERTS NOS 1,2,3 4 12-Nov-14 16-Nov-14 1 PART 3 PRE CASTING FOR CULVERTS NOS 1,2,3
EZ0CO23 PART 3 PRE CASTING FOR CULVERTS NOS 4,5,6 4 08-Dec-14 11-Dec-14 15 PART 3 PRE CASTING FOR CULVERTS NOS 4,5,6
EZ0CO23 PART 3 PRE CASTING FOR CULVERTS NOS 7,8,9 3 01-Jan-15 05-Jan-15 22 PART 3 PRE CASTING FOR CULVERTS NOS 7,8,9
EZ0CO23 PART 3 PRE CASTING FOR CULVERTS NOS 10,11 8 20-Jan-15 28-Jan-15 28 PART 3 PRE CASTING FOR CULVERTS NOS 10,11,12
EZ0CO23 PART 3 PRE CASTING FOR CULVERTS NOS 13,14 7 14-Feb-15 21-Feb-15 96 PART 3 PRE CASTING FOR CULVERTS NOS 13,14,15
EZ0CO23 PART 3 PRE CASTING FOR CULVERTS NOS 16,17 6 09-Mar-15 15-Mar-15 103 PART 3 PRE CASTING FOR CULVERTS NOS 16,17,18
EZ0CO23 PART 3 PRE CASTING FOR CULVERTS NOS 19,20 3 04-Apr-15 06-Apr-15 110 PART 3 PRE CASTING FOR CULVERTS NOS 19,20,21
EZ0CO23 PART 3 PRE CASTING FOR CULVERTS NOS 22,23 7 21-Apr-15 28-Apr-15 117 PART 3 PRE CASTING FOR CULVERTS NOS 22,23,24
EZ0CO24 PART 3 PRE CASTING FOR CULVERTS NOS 25,26 7 09-May-15 16-May-15 135 PART 3 PRE CASTING FOR CULVERTS NOS 25,26,2
EZ0CO24 PART 3 PRE CASTING FOR CULVERTS NOS 28,29 7 17-May-15 24-May-15 185 PART 3 PRE CASTING FOR CULVERTS NOS 28,29,
PLAN & PROFILE FOR ROAD WORKS SUBMITTAL 166 15-Jan-14 02-Aug-14 325 02-Aug-14, PLAN & PROFILE FOR ROAD WORKS SUBMITTAL
PHASE 2 PLAN & PROFILE SUBMITTAL 140 08-Feb-14 21-Jul-14 61 21-Jul-14, PHASE 2 PLAN & PROFILE SUBMITTAL
EZ0CO2520 PLAN & PROFILE SUBMITTAL FROM KM 20+000 TO 14 08-Feb-14 23-Feb-14 43 PLAN & PROFILE SUBMITTAL FROM KM 20+000 TO 22+000
EZ0CO2530 PLAN & PROFILE SUBMITTAL FROM KM 22+000 TO 14 24-Feb-14 11-Mar-14 53 PLAN & PROFILE SUBMITTAL FROM KM 22+000 TO 24+000
EZ0CO2540 PLAN & PROFILE SUBMITTAL FROM KM 24+000 TO 14 12-Mar-14 27-Mar-14 54 PLAN & PROFILE SUBMITTAL FROM KM 24+000 TO 26+000
EZ0CO2550 PLAN & PROFILE SUBMITTAL FROM KM 26+000 TO 14 29-Mar-14 13-Apr-14 55 PLAN & PROFILE SUBMITTAL FROM KM 26+000 TO 28+000
EZ0CO2560 PLAN & PROFILE SUBMITTAL FROM KM 28+000 TO 14 14-Apr-14 29-Apr-14 56 PLAN & PROFILE SUBMITTAL FROM KM 28+000 TO 30+000
EZ0CO2570 PLAN & PROFILE SUBMITTAL FROM KM 30+000 TO 14 30-Apr-14 15-May-14 57 PLAN & PROFILE SUBMITTAL FROM KM 30+000 TO 32+000
EZ0CO2580 PLAN & PROFILE SUBMITTAL FROM KM 32+000 TO 14 17-May-14 02-Jun-14 58 PLAN & PROFILE SUBMITTAL FROM KM 32+000 TO 34+000
EZ0CO2590 PLAN & PROFILE SUBMITTAL FROM KM 34+000 TO 14 03-Jun-14 18-Jun-14 59 PLAN & PROFILE SUBMITTAL FROM KM 34+000 TO 36+000
EZ0CO2600 PLAN & PROFILE SUBMITTAL FROM KM 36+000 TO 14 19-Jun-14 05-Jul-14 60 PLAN & PROFILE SUBMITTAL FROM KM 36+000 TO 38+000
EZ0CO2610 PLAN & PROFILE SUBMITTAL FROM KM 38+000 TO 14 06-Jul-14 21-Jul-14 61 PLAN & PROFILE SUBMITTAL FROM KM 38+000 TO 40+000
PHASE 1 PLAN & PROFILE SUBMITTAL 96 15-Jan-14 06-May-14 170 06-May-14, PHASE 1 PLAN & PROFILE SUBMITTAL
EZ0CO2420 PLAN & PROFILE SUBMITTAL FROM KM 0+000 TO 6 15-Jan-14 21-Jan-14 0 PLAN & PROFILE SUBMITTAL FROM KM 0+000 TO 2+000
EZ0CO2430 PLAN & PROFILE SUBMITTAL FROM KM 2+000 TO 10 22-Jan-14 02-Feb-14 0 PLAN & PROFILE SUBMITTAL FROM KM 2+000 TO 4+000
EZ0CO2440 PLAN & PROFILE SUBMITTAL FROM KM 4+000 TO 10 03-Feb-14 13-Feb-14 3 PLAN & PROFILE SUBMITTAL FROM KM 4+000 TO 6+000
EZ0CO2450 PLAN & PROFILE SUBMITTAL FROM KM 6+000 TO 10 15-Feb-14 25-Feb-14 8 PLAN & PROFILE SUBMITTAL FROM KM 6+000 TO 8+000
EZ0CO2460 PLAN & PROFILE SUBMITTAL FROM KM 8+000 TO 10 26-Feb-14 09-Mar-14 13 PLAN & PROFILE SUBMITTAL FROM KM 8+000 TO 10+000
EZ0CO2470 PLAN & PROFILE SUBMITTAL FROM KM 10+000 TO 10 10-Mar-14 20-Mar-14 19 PLAN & PROFILE SUBMITTAL FROM KM 10+000 TO 12+000
EZ0CO2480 PLAN & PROFILE SUBMITTAL FROM KM 12+000 TO 10 22-Mar-14 01-Apr-14 54 PLAN & PROFILE SUBMITTAL FROM KM 12+000 TO 14+000
EZ0CO2490 PLAN & PROFILE SUBMITTAL FROM KM 14+000 TO 10 02-Apr-14 13-Apr-14 54 PLAN & PROFILE SUBMITTAL FROM KM 14+000 TO 16+000
EZ0CO2500 PLAN & PROFILE SUBMITTAL FROM KM 16+000 TO 10 14-Apr-14 24-Apr-14 165 PLAN & PROFILE SUBMITTAL FROM KM 16+000 TO 18+000
EZ0CO2510 PLAN & PROFILE SUBMITTAL FROM KM 18+000 TO 10 26-Apr-14 06-May-14 170 PLAN & PROFILE SUBMITTAL FROM KM 18+000 TO 20+000
PHASE 3 PLAN & PROFILE SUBMITTAL 126 03-Mar-14 02-Aug-14 325 02-Aug-14, PHASE 3 PLAN & PROFILE SUBMITTAL
EZ0CO2620 PLAN & PROFILE SUBMITTAL FROM KM 40+000 TO 14 03-Mar-14 18-Mar-14 43 PLAN & PROFILE SUBMITTAL FROM KM 40+000 TO 42+000
EZ0CO2630 PLAN & PROFILE SUBMITTAL FROM KM 42+000 TO 14 19-Mar-14 03-Apr-14 180 PLAN & PROFILE SUBMITTAL FROM KM 42+000 TO 44+000
EZ0CO2640 PLAN & PROFILE SUBMITTAL FROM KM 44+000 TO 14 05-Apr-14 20-Apr-14 188 PLAN & PROFILE SUBMITTAL FROM KM 44+000 TO 46+000
EZ0CO2650 PLAN & PROFILE SUBMITTAL FROM KM 46+000 TO 14 21-Apr-14 06-May-14 287 PLAN & PROFILE SUBMITTAL FROM KM 46+000 TO 48+000
EZ0CO2660 PLAN & PROFILE SUBMITTAL FROM KM 48+000 TO 14 07-May-14 22-May-14 295 PLAN & PROFILE SUBMITTAL FROM KM 48+000 TO 50+000
EZ0CO2670 PLAN & PROFILE SUBMITTAL FROM KM 50+000 TO 14 24-May-14 09-Jun-14 303 PLAN & PROFILE SUBMITTAL FROM KM 50+000 TO 52+000
EZ0CO2680 PLAN & PROFILE SUBMITTAL FROM KM 52+000 TO 14 10-Jun-14 25-Jun-14 311 PLAN & PROFILE SUBMITTAL FROM KM 52+000 TO 54+000
EZ0CO2690 PLAN & PROFILE SUBMITTAL FROM KM 54+000 TO 14 26-Jun-14 12-Jul-14 318 PLAN & PROFILE SUBMITTAL FROM KM 54+000 TO 56+000

Actual Work Critical Remaining Work Summary Page 6 of 57 TASK filter: All Activities

Remaining Work Milestone © Oracle Corporation


DUALIZATION OF MAHDAH - AL RAWDAH ROAD PROJECT Classic Schedule Layout 25-May-14 16:51

Activity ID Activity Name Original Start Finish Total Float Critical 2014 2015 2016
Duration
S Oct N D J F M Apr M J Jul A S Oct N D Jan F M Apr M J Jul A S Oct N D J F M Apr M J
EZ0CO2700 PLAN & PROFILE SUBMITTAL FROM KM 56+000 TO 14 13-Jul-14 02-Aug-14 325 PLAN & PROFILE SUBMITTAL FROM KM 56+000 TO 58+595
ELECTRICAL/UTI
ELECTRICAL/UTILITIES SUBMITTAL 68 22-Dec-13 11-Mar-14 9 11-Mar-14, ELECTRICAL/UTILITIES SUBMITTAL
EZ0CO2940 DUCT LAYOUTS 18 22-Dec-13 11-Jan-14 9 DUCT LAYOUTS
EZ0CO2950 DIVERSION OF EXISTING UTILITIES 26 11-Jan-14 10-Feb-14 9 DIVERSION OF EXISTING UTILITIES
EZ0CO2960 STREET LIGHT LAYOUTS 50 12-Jan-14 11-Mar-14 9 STREET LIGHT LAYOUTS
SHOP DRAWING APPROVAL
AP 457 12-Jan-14 13-Jul-15 149 13-Jul-15, SHOP DRAWING APPROVAL
EZ0CO2970 PRECAST FOR BARRIERS 12 01-May-14 14-May-14 30 PRECAST FOR BARRIERS
EZ0CO2980 PRECAST FOR MSER WALL 12 15-Jun-14 28-Jun-14 69 PRECAST FOR MSER WALL
EZ0CO2990 ROAD FURNITURE 11 06-Aug-14 18-Aug-14 417 ROAD FURNITURE
CULVERTS - SHOP
SHO DRAWING APPROVAL 395 12-Feb-14 01-Jun-15 185 01-Jun-15, CULVERTS - SHOP DRAWING APPROVA
PHASE 1 CULVERTS
CULV - SHOP DRAWING APPROVAL 154 12-Feb-14 16-Aug-14 75 16-Aug-14, PHASE 1 CULVERTS - SHOP DRAWING APPROVAL
EZ0CO3000 7.02 CELL BOX CULVERT @ CH 2+335 - (1.5X1.5) 7 12-Feb-14 19-Feb-14 12 7.02 CELL BOX CULVERT @ CH 2+335 - (1.5X1.5)
EZ0CO3010 9.02 CELL BOX CULVERT @ CH 2+870 - (2.0X1.5) 7 16-Feb-14 23-Feb-14 12 9.02 CELL BOX CULVERT @ CH 2+870 - (2.0X1.5)
EZ0CO3020 10.07 CELL BOX CULVERT @ CH 3+400 - (2.0X2.0) 7 19-Feb-14 26-Feb-14 12 10.07 CELL BOX CULVERT @ CH 3+400 - (2.0X2.0)
EZ0CO3030 12.06 CELL BOX CULVERT @ CH 3+975 - (2.0X2.0) 7 27-Feb-14 06-Mar-14 12 12.06 CELL BOX CULVERT @ CH 3+975 - (2.0X2.0)
EZ0CO3040 13.02 CELL BOX CULVERT @ CH 4+320 - (2.0X1.5) 7 06-Mar-14 13-Mar-14 12 13.02 CELL BOX CULVERT @ CH 4+320 - (2.0X1.5)
EZ0CO3050 16.02 CELL BOX CULVERT @ CH 5+450 - (2.0X1.5) 7 10-Mar-14 17-Mar-14 12 16.02 CELL BOX CULVERT @ CH 5+450 - (2.0X1.5)
EZ0CO3060 19.02 CELL BOX CULVERT @ CH 7+170 - (2.0X1.5) 7 15-Mar-14 22-Mar-14 12 19.02 CELL BOX CULVERT @ CH 7+170 - (2.0X1.5)
EZ0CO3070 20.03 CELL BOX CULVERT @ CH 10+140 - (2.0X1.5 7 18-Mar-14 25-Mar-14 12 20.03 CELL BOX CULVERT @ CH 10+140 - (2.0X1.5)
EZ0CO3080 21.03 CELL BOX CULVERT @ CH 10+680 - (2.0X1.5 7 22-Mar-14 29-Mar-14 12 21.03 CELL BOX CULVERT @ CH 10+680 - (2.0X1.5)
EZ0CO3090 22.02 CELL BOX CULVERT @ CH 11+790 - (2.0X1.5 7 26-Mar-14 02-Apr-14 12 22.02 CELL BOX CULVERT @ CH 11+790 - (2.0X1.5)
EZ0CO3100 23.03 CELL BOX CULVERT @ CH 12+615 - (2.0X1.5 7 01-Apr-14 08-Apr-14 12 23.03 CELL BOX CULVERT @ CH 12+615 - (2.0X1.5)
EZ0CO3110 24.06 CELL BOX CULVERT @ CH 13+150 - (2.0X1.5 7 06-Apr-14 13-Apr-14 12 24.06 CELL BOX CULVERT @ CH 13+150 - (2.0X1.5)
EZ0CO3120 32.06 CELL BOX CULVERT @ CH 15+880 - (1.5X1.5 7 13-Apr-14 20-Apr-14 12 32.06 CELL BOX CULVERT @ CH 15+880 - (1.5X1.5)
EZ0CO3130 34.51 CELL BOX CULVERT @ CH 16+725 - (3.0X2.0 7 20-Apr-14 27-Apr-14 12 34.51 CELL BOX CULVERT @ CH 16+725 - (3.0X2.0)
EZ0CO3140 35.24 CELL BOX CULVERT @ CH 16+992 - (3.0X2.0 14 11-May-14 26-May-14 12 35.24 CELL BOX CULVERT @ CH 16+992 - (3.0X2.0)
EZ0CO3150 36.39 CELL BOX CULVERT @ CH 17+210 - (3.0X2.0 14 28-May-14 12-Jun-14 12 36.39 CELL BOX CULVERT @ CH 17+210 - (3.0X2.0)
EZ0CO3160 37.06 CELL BOX CULVERT @ CH 17+445 - (3.0X2.0 14 21-Jun-14 06-Jul-14 12 37.06 CELL BOX CULVERT @ CH 17+445 - (3.0X2.0)
EZ0CO3170 41.06 CELL BOX CULVERT @ CH 18+600 - (2.0X1.5 7 06-Jul-14 13-Jul-14 14 41.06 CELL BOX CULVERT @ CH 18+600 - (2.0X1.5)
EZ0CO3180 42.14 CELL BOX CULVERT @ CH 18+975 - (3.0X1.5 7 13-Jul-14 20-Jul-14 14 42.14 CELL BOX CULVERT @ CH 18+975 - (3.0X1.5)
EZ0CO3190 43.02 CELL BOX CULVERT @ CH 19+280 - (2.0X1.5 7 24-Jul-14 04-Aug-14 14 43.02 CELL BOX CULVERT @ CH 19+280 - (2.0X1.5)
EZ0CO3200 44.02 CELL BOX CULVERT @ CH 19+540 - (2.0X1.5 7 31-Jul-14 07-Aug-14 24 44.02 CELL BOX CULVERT @ CH 19+540 - (2.0X1.5)
EZ0CO3210 45.03 CELL BOX CULVERT @ CH 19+940 - (2.0X1.5 7 05-Aug-14 12-Aug-14 24 45.03 CELL BOX CULVERT @ CH 19+940 - (2.0X1.5)
SINGLE CELL
CEL CULVERTS - 24NOS APPROVAL 129 13-Mar-14 16-Aug-14 75 16-Aug-14, SINGLE CELL CULVERTS - 24NOS APPROVAL
EZ0CO32 PART 1 PRECASTING FOR CULVERTS NOS 1,2,3 7 13-Mar-14 20-Mar-14 12 PART 1 PRECASTING FOR CULVERTS NOS 1,2,3
EZ0CO32 PART 1 PRECASTING FOR CULVERTS NOS 4,5,6 7 09-Apr-14 16-Apr-14 31 PART 1 PRECASTING FOR CULVERTS NOS 4,5,6
EZ0CO32 PART 1 PRECASTING FOR CULVERTS NOS 7,8,9 7 23-Apr-14 30-Apr-14 41 PART 1 PRECASTING FOR CULVERTS NOS 7,8,9
EZ0CO32 PART 1 PRECASTING FOR CULVERTS NOS 10,11 7 02-Jun-14 09-Jun-14 41 PART 1 PRECASTING FOR CULVERTS NOS 10,11,12
EZ0CO32 PART 1 PRECASTING FOR CULVERTS NOS 13,14 7 28-Jun-14 05-Jul-14 41 PART 1 PRECASTING FOR CULVERTS NOS 13,14,15
EZ0CO32 PART 1 PRECASTING FOR CULVERTS NOS 16,17 7 20-Jul-14 31-Jul-14 44 PART 1 PRECASTING FOR CULVERTS NOS 16,17,18
EZ0CO32 PART 1 PRECASTING FOR CULVERTS NOS 19,20 7 04-Aug-14 11-Aug-14 57 PART 1 PRECASTING FOR CULVERTS NOS 19,20,21
EZ0CO32 PART 1 PRECASTING FOR CULVERTS NOS 22,23 7 09-Aug-14 16-Aug-14 75 PART 1 PRECASTING FOR CULVERTS NOS 22,23,24
PHASE 2 CULVERTS
CULV - SHOP DRAWING APPROVAL 141 02-Aug-14 20-Jan-15 265 20-Jan-15, PHASE 2 CULVERTS - SHOP DRAWING APPROVAL
EZ0CO3300 46.2CELL BOX CULVERT @ CH 20+170 (2.0 x 2.0) 7 02-Aug-14 09-Aug-14 9 46.2CELL BOX CULVERT @ CH 20+170 (2.0 x 2.0)
EZ0CO3310 48.2CELL BOX CULVERT @ CH 21+510 (2.0 x 1.5) 7 06-Aug-14 13-Aug-14 9 48.2CELL BOX CULVERT @ CH 21+510 (2.0 x 1.5)
EZ0CO3320 50.4CELL BOX CULVERT @ CH 22+320 (3.0 x 2.0 ) 7 10-Aug-14 17-Aug-14 9 50.4CELL BOX CULVERT @ CH 22+320 (3.0 x 2.0 )
EZ0CO3330 63.4CELL BOX CULVERT @ CH 27+275 (4.0 x 2.0) 7 13-Aug-14 20-Aug-14 9 63.4CELL BOX CULVERT @ CH 27+275 (4.0 x 2.0)
EZ0CO3340 64.4CELL BOX CULVERT @ CH 27+378 (4.0 x 2.0) 7 18-Aug-14 25-Aug-14 9 64.4CELL BOX CULVERT @ CH 27+378 (4.0 x 2.0)
EZ0CO3350 65.4CELL BOX CULVERT @ CH 27+470 (4.0 x 2.0) 7 23-Aug-14 30-Aug-14 9 65.4CELL BOX CULVERT @ CH 27+470 (4.0 x 2.0)
EZ0CO3360 73.2CELL BOX CULVERT @ CH 30+040 (2.0 x 1.5) 7 26-Aug-14 02-Sep-14 9 73.2CELL BOX CULVERT @ CH 30+040 (2.0 x 1.5)
EZ0CO3370 74.3CELL BOX CULVERT @ CH 30+330 (2.0 x 1.5) 7 30-Aug-14 06-Sep-14 100 74.3CELL BOX CULVERT @ CH 30+330 (2.0 x 1.5)

Actual Work Critical Remaining Work Summary Page 7 of 57 TASK filter: All Activities

Remaining Work Milestone © Oracle Corporation


DUALIZATION OF MAHDAH - AL RAWDAH ROAD PROJECT Classic Schedule Layout 25-May-14 16:51

Activity ID Activity Name Original Start Finish Total Float Critical 2014 2015 2016
Duration
S Oct N D J F M Apr M J Jul A S Oct N D Jan F M Apr M J Jul A S Oct N D J F M Apr M J
EZ0CO3380 75.12CELL BOX CULVERT @ CH 30+450 (2.0 x 1.5) 7 03-Sep-14 10-Sep-14 100 75.12CELL BOX CULVERT @ CH 30+450 (2.0 x 1.5)
EZ0CO3390 77.3CELL BOX CULVERT @ CH 30+920 (2.0 x 1.5) 7 09-Sep-14 16-Sep-14 100 77.3CELL BOX CULVERT @ CH 30+920 (2.0 x 1.5)
EZ0CO3400 80.2CELL BOX CULVERT @ CH 31+650 (2.0 x 1.5) 7 13-Sep-14 20-Sep-14 100 80.2CELL BOX CULVERT @ CH 31+650 (2.0 x 1.5)
EZ0CO3410 82.2CELL BOX CULVERT @ CH 32+250 (2.0 x 1.5) 7 16-Sep-14 23-Sep-14 100 82.2CELL BOX CULVERT @ CH 32+250 (2.0 x 1.5)
EZ0CO3420 83.83CELL BOX CULVERT @ CH 32+800 (3.0 x 2.0) 7 21-Sep-14 28-Sep-14 100 83.83CELL BOX CULVERT @ CH 32+800 (3.0 x 2.0)
EZ0CO3430 84.5CELL BOX CULVERT @ CH 33+134 (3.0 x 2.0) 7 29-Sep-14 09-Oct-14 100 84.5CELL BOX CULVERT @ CH 33+134 (3.0 x 2.0)
EZ0CO3440 85.26CELL BOX CULVERT @ CH33+217 (3.0 x 2.0) 7 08-Oct-14 15-Oct-14 100 85.26CELL BOX CULVERT @ CH33+217 (3.0 x 2.0)
EZ0CO3450 86.2CELL BOX CULVERT @ CH33+440 ( 2.0 x 1.5) 7 16-Oct-14 23-Oct-14 100 86.2CELL BOX CULVERT @ CH33+440 ( 2.0 x 1.5)
EZ0CO3460 87.2CELL BOX CULVERT @ CH 33+590 (2.0 x 1.5) 7 20-Oct-14 28-Oct-14 100 87.2CELL BOX CULVERT @ CH 33+590 (2.0 x 1.5)
EZ0CO3470 88.2CELL BOX CULVERT @ CH 33+730 (2.0 x1.5) 7 23-Oct-14 01-Nov-14 100 88.2CELL BOX CULVERT @ CH 33+730 (2.0 x1.5)
EZ0CO3480 90.2CELL BOX CULVERT @ CH 34+242 (2.0 x 1.5) 7 28-Oct-14 04-Nov-14 100 90.2CELL BOX CULVERT @ CH 34+242 (2.0 x 1.5)
EZ0CO3490 91.2CELL BOX CULVERT @ CH34+522 (2.0 x 1.5) 7 01-Nov-14 08-Nov-14 100 91.2CELL BOX CULVERT @ CH34+522 (2.0 x 1.5)
EZ0CO3500 92.2CELL BOX CULVERT @ CH34+640 ( 2.0 x 1.5) 7 04-Nov-14 11-Nov-14 100 92.2CELL BOX CULVERT @ CH34+640 ( 2.0 x 1.5)
EZ0CO3510 93.2CELL BOX CULVERT @ CH 34+730 (2.0 x 1.5) 7 09-Nov-14 16-Nov-14 100 93.2CELL BOX CULVERT @ CH 34+730 (2.0 x 1.5)
EZ0CO3520 94.3CELL BOX CULVERT @ CH 34+900 (2.0 x 1.5) 7 12-Nov-14 19-Nov-14 100 94.3CELL BOX CULVERT @ CH 34+900 (2.0 x 1.5)
EZ0CO3530 95.3CELL BOX CULVERT @ CH 35+100 (2.0 x 1.5) 7 17-Nov-14 26-Nov-14 100 95.3CELL BOX CULVERT @ CH 35+100 (2.0 x 1.5)
EZ0CO3540 96.2CELL BOX CULVERT @ CH35+320 ( 2.0 x 1.5) 7 20-Nov-14 30-Nov-14 100 96.2CELL BOX CULVERT @ CH35+320 ( 2.0 x 1.5)
EZ0CO3550 98.4CELL BOX CULVERT @ CH36+230 (2.0 x 1.5) 7 26-Nov-14 03-Dec-14 105 98.4CELL BOX CULVERT @ CH36+230 (2.0 x 1.5)
EZ0CO3560 99.9CELL BOX CULVERT @ CH 36+520 (2.0 x 1.5) 7 01-Dec-14 08-Dec-14 105 99.9CELL BOX CULVERT @ CH 36+520 (2.0 x 1.5)
EZ0CO3570 101.5CELL BOX CULVERT @ CH 36+840 (2.0 x 1.5) 7 08-Dec-14 15-Dec-14 105 101.5CELL BOX CULVERT @ CH 36+840 (2.0 x 1.5)
EZ0CO3580 102.15CELL BOX CULVERT @ CH 37+350 (3.0 x 2.0 7 14-Dec-14 21-Dec-14 105 102.15CELL BOX CULVERT @ CH 37+350 (3.0 x 2.0)
EZ0CO3590 104.3CELL BOX CULVERT @ CH 38+080 (2.0 x 1.5) 7 22-Dec-14 29-Dec-14 120 104.3CELL BOX CULVERT @ CH 38+080 (2.0 x 1.5)
EZ0CO3600 108.2CELL BOX CULVERT @ CH 39+107 (2.0 x 1.5 ) 7 25-Dec-14 01-Jan-15 120 108.2CELL BOX CULVERT @ CH 39+107 (2.0 x 1.5 )
SINGLE CELL
CEL CULVERTS - 30NOS APPROVAL 83 12-Oct-14 20-Jan-15 265 20-Jan-15, SINGLE CELL CULVERTS - 30NOS APPROVAL
EZ0CO36 PART 2 PRE CASTING FOR CULVERTS NOS 1,2,3 7 12-Oct-14 19-Oct-14 15 PART 2 PRE CASTING FOR CULVERTS NOS 1,2,3
EZ0CO36 PART 2 PRE CASTING FOR CULVERTS NOS 4,5,6 7 08-Nov-14 15-Nov-14 20 PART 2 PRE CASTING FOR CULVERTS NOS 4,5,6
EZ0CO36 PART 2 PRE CASTING FOR CULVERTS NOS 7,8,9 7 04-Dec-14 11-Dec-14 35 PART 2 PRE CASTING FOR CULVERTS NOS 7,8,9
EZ0CO36 PART 2 PRE CASTING FOR CULVERTS NOS 10,11 7 08-Dec-14 15-Dec-14 63 PART 2 PRE CASTING FOR CULVERTS NOS 10,11,12
EZ0CO36 PART 2 PRE CASTING FOR CULVERTS NOS 13,14 7 11-Dec-14 18-Dec-14 92 PART 2 PRE CASTING FOR CULVERTS NOS 13,14,15
EZ0CO36 PART 2 PRE CASTING FOR CULVERTS NOS 16,17 7 29-Dec-14 06-Jan-15 108 PART 2 PRE CASTING FOR CULVERTS NOS 16,17,18
EZ0CO36 PART 2 PRE CASTING FOR CULVERTS NOS 19,20 7 01-Jan-15 10-Jan-15 142 PART 2 PRE CASTING FOR CULVERTS NOS 19,20,21
EZ0CO36 PART 2 PRE CASTING FOR CULVERTS NOS 22,23 7 06-Jan-15 13-Jan-15 176 PART 2 PRE CASTING FOR CULVERTS NOS 22,23,24
EZ0CO36 PART 2 PRE CASTING FOR CULVERTS NOS 25,26 7 10-Jan-15 17-Jan-15 231 PART 2 PRE CASTING FOR CULVERTS NOS 25,26,27
EZ0CO37 PART 2 PRE CASTING FOR CULVERTS NOS 28,29 7 13-Jan-15 20-Jan-15 265 PART 2 PRE CASTING FOR CULVERTS NOS 28,29,30
PHASE 3 CULVERTS
CULV - SHOP DRAWING APPROVAL 166 17-Nov-14 01-Jun-15 185 01-Jun-15, PHASE 3 CULVERTS - SHOP DRAWING
EZ0CO3710 110.2CELL BOX CULVERT @ CH40+872 (2.0 x 1.5) 7 17-Nov-14 26-Nov-14 1 110.2CELL BOX CULVERT @ CH40+872 (2.0 x 1.5)
EZ0CO3720 111.3CELL BOX CULVERT @ CH41+388 (2.0 x 1.5) 7 25-Nov-14 02-Dec-14 10 111.3CELL BOX CULVERT @ CH41+388 (2.0 x 1.5)
EZ0CO3730 116.3CELL BOX CULVERT @ CH42+580 (4.0 x 2.0) 7 02-Dec-14 09-Dec-14 10 116.3CELL BOX CULVERT @ CH42+580 (4.0 x 2.0)
EZ0CO3740 117.14CELL BOX CULVERT @ CH42+737 (4.0 x 2.0) 7 08-Dec-14 15-Dec-14 10 117.14CELL BOX CULVERT @ CH42+737 (4.0 x 2.0)
EZ0CO3750 118.36CELL BOX CULVERT @ CH42+918 (4.0 x 2.0) 7 16-Dec-14 23-Dec-14 10 118.36CELL BOX CULVERT @ CH42+918 (4.0 x 2.0)
EZ0CO3760 123.4CELL BOX CULVERT @ CH44+160 (2.0 x 2.0) 7 25-Dec-14 01-Jan-15 10 123.4CELL BOX CULVERT @ CH44+160 (2.0 x 2.0)
EZ0CO3770 125.2CELL BOX CULVERT @ CH45+650 (2.0 x 1.5) 7 01-Jan-15 10-Jan-15 10 125.2CELL BOX CULVERT @ CH45+650 (2.0 x 1.5)
EZ0CO3780 126.6CELL BOX CULVERT @ CH45+900 (2.0 x 1.5) 7 08-Jan-15 15-Jan-15 10 126.6CELL BOX CULVERT @ CH45+900 (2.0 x 1.5)
EZ0CO3790 127.3CELL BOX CULVERT @ CH46+250 (2.0 x 1.5) 7 14-Jan-15 21-Jan-15 10 127.3CELL BOX CULVERT @ CH46+250 (2.0 x 1.5)
EZ0CO3800 128.6CELL BOX CULVERT @ CH46+500 (2.0 x 1.5) 7 20-Jan-15 27-Jan-15 61 128.6CELL BOX CULVERT @ CH46+500 (2.0 x 1.5)
EZ0CO3810 129.2CELL BOX CULVERT @ CH46+570 (2.0 x1.5) 7 31-Jan-15 07-Feb-15 61 129.2CELL BOX CULVERT @ CH46+570 (2.0 x1.5)
EZ0CO3820 138.12CELL BOX CULVERT @ CH49+113 (3.0 x 1.5) 7 05-Feb-15 12-Feb-15 61 138.12CELL BOX CULVERT @ CH49+113 (3.0 x 1.5)
EZ0CO3830 139.3CELL BOX CULVERT @ CH49+600 (2.0 x 1.5) 7 14-Feb-15 21-Feb-15 61 139.3CELL BOX CULVERT @ CH49+600 (2.0 x 1.5)
EZ0CO3840 141.4CELL BOX CULVERT @ CH50+063 (2.0 x 1.5) 7 21-Feb-15 28-Feb-15 61 141.4CELL BOX CULVERT @ CH50+063 (2.0 x 1.5)
EZ0CO3850 142.7CELL BOX CULVERT @ CH50+217 (2.0 x 1.5) 7 28-Feb-15 07-Mar-15 61 142.7CELL BOX CULVERT @ CH50+217 (2.0 x 1.5)
EZ0CO3860 143.4CELL BOX CULVERT @ CH50+660 (2.0 x 1.5) 7 09-Mar-15 16-Mar-15 68 143.4CELL BOX CULVERT @ CH50+660 (2.0 x 1.5)

Actual Work Critical Remaining Work Summary Page 8 of 57 TASK filter: All Activities

Remaining Work Milestone © Oracle Corporation


DUALIZATION OF MAHDAH - AL RAWDAH ROAD PROJECT Classic Schedule Layout 25-May-14 16:51

Activity ID Activity Name Original Start Finish Total Float Critical 2014 2015 2016
Duration
S Oct N D J F M Apr M J Jul A S Oct N D Jan F M Apr M J Jul A S Oct N D J F M Apr M J
EZ0CO3870 149.2CELL BOX CULVERT @ CH52+480 (2.0 x 1.5) 7 16-Mar-15 23-Mar-15 68 149.2CELL BOX CULVERT @ CH52+480 (2.0 x 1.5)
EZ0CO3880 150.2CELL BOX CULVERT @ CH52+720 (2.0 x 1.5) 7 23-Mar-15 30-Mar-15 68 150.2CELL BOX CULVERT @ CH52+720 (2.0 x 1.5)
EZ0CO3890 151.4CELL BOX CULVERT @ CH53+300 (2.0 x 1.5) 7 29-Mar-15 05-Apr-15 68 151.4CELL BOX CULVERT @ CH53+300 (2.0 x 1.5)
EZ0CO3900 153.2CELL BOX CULVERT @ CH54+242 (2.0 x 1.5) 7 04-Apr-15 11-Apr-15 68 153.2CELL BOX CULVERT @ CH54+242 (2.0 x 1.5)
EZ0CO3910 159.2CELL BOX CULVERT @ CH55+762 (2.0 x 1.5) 7 11-Apr-15 18-Apr-15 71 159.2CELL BOX CULVERT @ CH55+762 (2.0 x 1.5)
EZ0CO3920 160.3CELL BOX CULVERT @ CH56+230 (3.0 x 2.0) 7 16-Apr-15 23-Apr-15 71 160.3CELL BOX CULVERT @ CH56+230 (3.0 x 2.0)
EZ0CO3930 161.8CELL BOX CULVERT @ CH56+420 (3.0 x 2.0) 7 21-Apr-15 28-Apr-15 71 161.8CELL BOX CULVERT @ CH56+420 (3.0 x 2.0)
EZ0CO3940 163.3CELL BOX CULVERT @ CH57+080 (2.0 x 1.5) 7 27-Apr-15 04-May-15 71 163.3CELL BOX CULVERT @ CH57+080 (2.0 x 1.5)
EZ0CO3950 166.4CELL BOX CULVERT @ CH58+150 (2.0 x 1.5) 7 03-May-15 10-May-15 71 166.4CELL BOX CULVERT @ CH58+150 (2.0 x 1.5)
EZ0CO3960 167.6CELL BOX CULVERT @ CH58+400 (2.0 x 1.5) 7 09-May-15 16-May-15 71 167.6CELL BOX CULVERT @ CH58+400 (2.0 x 1.5)
SINGLE CELL
CEL CULVERTS - 30NOS APPROVAL 166 17-Nov-14 01-Jun-15 185 01-Jun-15, SINGLE CELL CULVERTS - 30NOS APPR
EZ0CO39 PART 3 PRE CASTING FOR CULVERTS NOS 1,2,3 7 17-Nov-14 26-Nov-14 1 PART 3 PRE CASTING FOR CULVERTS NOS 1,2,3
EZ0CO39 PART 3 PRE CASTING FOR CULVERTS NOS 4,5,6 7 13-Dec-14 20-Dec-14 15 PART 3 PRE CASTING FOR CULVERTS NOS 4,5,6
EZ0CO39 PART 3 PRE CASTING FOR CULVERTS NOS 7,8,9 7 06-Jan-15 13-Jan-15 22 PART 3 PRE CASTING FOR CULVERTS NOS 7,8,9
EZ0CO40 PART 3 PRE CASTING FOR CULVERTS NOS 10,11 7 29-Jan-15 05-Feb-15 28 PART 3 PRE CASTING FOR CULVERTS NOS 10,11,12
EZ0CO40 PART 3 PRE CASTING FOR CULVERTS NOS 13,14 7 22-Feb-15 01-Mar-15 96 PART 3 PRE CASTING FOR CULVERTS NOS 13,14,15
EZ0CO40 PART 3 PRE CASTING FOR CULVERTS NOS 16,17 7 16-Mar-15 23-Mar-15 103 PART 3 PRE CASTING FOR CULVERTS NOS 16,17,18
EZ0CO40 PART 3 PRE CASTING FOR CULVERTS NOS 19,20 7 07-Apr-15 14-Apr-15 110 PART 3 PRE CASTING FOR CULVERTS NOS 19,20,21
EZ0CO40 PART 3 PRE CASTING FOR CULVERTS NOS 22,23 7 29-Apr-15 06-May-15 117 PART 3 PRE CASTING FOR CULVERTS NOS 22,23,24
EZ0CO40 PART 3 PRE CASTING FOR CULVERTS NOS 25,26 7 17-May-15 24-May-15 135 PART 3 PRE CASTING FOR CULVERTS NOS 25,26,
EZ0CO40 PART 3 PRE CASTING FOR CULVERTS NOS 28,29 7 25-May-15 01-Jun-15 185 PART 3 PRE CASTING FOR CULVERTS NOS 28,29
PLAN & PROFILE FOR ROAD WORKS APPROVALS 174 22-Jan-14 18-Aug-14 325 18-Aug-14, PLAN & PROFILE FOR ROAD WORKS APPROVALS
PHASE 1 PLAN & PROFILE APPROVAL 104 22-Jan-14 22-May-14 170 22-May-14, PHASE 1 PLAN & PROFILE APPROVAL
EZ0CO4070 PLAN & PROFILE APPROVAL FROM KM 0+000 TO 6 22-Jan-14 28-Jan-14 0 PLAN & PROFILE APPROVAL FROM KM 0+000 TO 2+000
EZ0CO4080 PLAN & PROFILE APPROVAL FROM KM 2+000 TO 11 03-Feb-14 15-Feb-14 0 PLAN & PROFILE APPROVAL FROM KM 2+000 TO 4+000
EZ0CO4090 PLAN & PROFILE APPROVAL FROM KM 4+000 TO 14 15-Feb-14 02-Mar-14 3 PLAN & PROFILE APPROVAL FROM KM 4+000 TO 6+000
EZ0CO4100 PLAN & PROFILE APPROVAL FROM KM 6+000 TO 14 26-Feb-14 13-Mar-14 8 PLAN & PROFILE APPROVAL FROM KM 6+000 TO 8+000
EZ0CO4110 PLAN & PROFILE APPROVAL FROM KM 8+000 TO 14 10-Mar-14 25-Mar-14 13 PLAN & PROFILE APPROVAL FROM KM 8+000 TO 10+000
EZ0CO4120 PLAN & PROFILE APPROVAL FROM KM 10+000 TO 14 22-Mar-14 06-Apr-14 19 PLAN & PROFILE APPROVAL FROM KM 10+000 TO 12+000
EZ0CO4130 PLAN & PROFILE APPROVAL FROM KM 12+000 TO 14 02-Apr-14 17-Apr-14 154 PLAN & PROFILE APPROVAL FROM KM 12+000 TO 14+000
EZ0CO4140 PLAN & PROFILE APPROVAL FROM KM 14+000 TO 14 14-Apr-14 29-Apr-14 159 PLAN & PROFILE APPROVAL FROM KM 14+000 TO 16+000
EZ0CO4150 PLAN & PROFILE APPROVAL FROM KM 16+000 TO 14 26-Apr-14 11-May-14 165 PLAN & PROFILE APPROVAL FROM KM 16+000 TO 18+000
EZ0CO4160 PLAN & PROFILE APPROVAL FROM KM 18+000 TO 14 07-May-14 22-May-14 170 PLAN & PROFILE APPROVAL FROM KM 18+000 TO 20+000
PHASE 2 PLAN & PROFILE APPROVAL 140 24-Feb-14 11-Aug-14 61 11-Aug-14, PHASE 2 PLAN & PROFILE APPROVAL
EZ0CO4170 PLAN & PROFILE APPROVAL FROM KM 20+000 TO 14 24-Feb-14 11-Mar-14 43 PLAN & PROFILE APPROVAL FROM KM 20+000 TO 22+000
EZ0CO4180 PLAN & PROFILE APPROVAL FROM KM 22+000 TO 14 12-Mar-14 27-Mar-14 53 PLAN & PROFILE APPROVAL FROM KM 22+000 TO 24+000
EZ0CO4190 PLAN & PROFILE APPROVAL FROM KM 24+000 TO 14 29-Mar-14 13-Apr-14 54 PLAN & PROFILE APPROVAL FROM KM 24+000 TO 26+000
EZ0CO4200 PLAN & PROFILE APPROVAL FROM KM 26+000 TO 14 14-Apr-14 29-Apr-14 55 PLAN & PROFILE APPROVAL FROM KM 26+000 TO 28+000
EZ0CO4210 PLAN & PROFILE APPROVAL FROM KM 28+000 TO 14 30-Apr-14 15-May-14 56 PLAN & PROFILE APPROVAL FROM KM 28+000 TO 30+000
EZ0CO4220 PLAN & PROFILE APPROVAL FROM KM 30+000 TO 14 17-May-14 02-Jun-14 57 PLAN & PROFILE APPROVAL FROM KM 30+000 TO 32+000
EZ0CO4230 PLAN & PROFILE APPROVAL FROM KM 32+000 TO 14 03-Jun-14 18-Jun-14 58 PLAN & PROFILE APPROVAL FROM KM 32+000 TO 34+000
EZ0CO4240 PLAN & PROFILE APPROVAL FROM KM 34+000 TO 14 19-Jun-14 05-Jul-14 59 PLAN & PROFILE APPROVAL FROM KM 34+000 TO 36+000
EZ0CO4250 PLAN & PROFILE APPROVAL FROM KM 36+000 TO 14 06-Jul-14 21-Jul-14 60 PLAN & PROFILE APPROVAL FROM KM 36+000 TO 38+000
EZ0CO4260 PLAN & PROFILE APPROVAL FROM KM 38+000 TO 14 22-Jul-14 11-Aug-14 61 PLAN & PROFILE APPROVAL FROM KM 38+000 TO 40+000
PHASE 3 PLAN & PROFILE APPROVAL 126 19-Mar-14 18-Aug-14 325 18-Aug-14, PHASE 3 PLAN & PROFILE APPROVAL
EZ0CO4270 PLAN & PROFILE APPROVAL FROM KM 40+000 TO 14 19-Mar-14 03-Apr-14 168 PLAN & PROFILE APPROVAL FROM KM 40+000 TO 42+000
EZ0CO4280 PLAN & PROFILE APPROVAL FROM KM 42+000 TO 14 05-Apr-14 20-Apr-14 180 PLAN & PROFILE APPROVAL FROM KM 42+000 TO 44+000
EZ0CO4290 PLAN & PROFILE APPROVAL FROM KM 44+000 TO 14 21-Apr-14 06-May-14 188 PLAN & PROFILE APPROVAL FROM KM 44+000 TO 46+000
EZ0CO4300 PLAN & PROFILE APPROVAL FROM KM 46+000 TO 14 07-May-14 22-May-14 287 PLAN & PROFILE APPROVAL FROM KM 46+000 TO 48+000
EZ0CO4310 PLAN & PROFILE APPROVAL FROM KM 48+000 TO 14 24-May-14 09-Jun-14 295 PLAN & PROFILE APPROVAL FROM KM 48+000 TO 50+000
EZ0CO4320 PLAN & PROFILE APPROVAL FROM KM 50+000 TO 14 10-Jun-14 25-Jun-14 303 PLAN & PROFILE APPROVAL FROM KM 50+000 TO 52+000

Actual Work Critical Remaining Work Summary Page 9 of 57 TASK filter: All Activities

Remaining Work Milestone © Oracle Corporation


DUALIZATION OF MAHDAH - AL RAWDAH ROAD PROJECT Classic Schedule Layout 25-May-14 16:51

Activity ID Activity Name Original Start Finish Total Float Critical 2014 2015 2016
Duration
S Oct N D J F M Apr M J Jul A S Oct N D Jan F M Apr M J Jul A S Oct N D J F M Apr M J
EZ0CO4330 PLAN & PROFILE APPROVAL FROM KM 52+000 TO 14 26-Jun-14 12-Jul-14 311 PLAN & PROFILE APPROVAL FROM KM 52+000 TO 54+000
EZ0CO4340 PLAN & PROFILE APPROVAL FROM KM 54+000 TO 14 13-Jul-14 02-Aug-14 318 PLAN & PROFILE APPROVAL FROM KM 54+000 TO 56+000
EZ0CO4350 PLAN & PROFILE APPROVAL FROM KM 56+000 TO 14 03-Aug-14 18-Aug-14 325 PLAN & PROFILE APPROVAL FROM KM 56+000 TO 58+595
UNDERPASSES APPROVAL
A 261 17-Apr-14 01-Mar-15 49 01-Mar-15, UNDERPASSES APPROVAL
UNDER PASS AT
A 5+095 14 17-Apr-14 03-May-14 55 03-May-14, UNDER PASS AT 5+095
EZ0CO4360 UNP. 5+095 FOUNDATION 7 17-Apr-14 24-Apr-14 54 UNP. 5+095 FOUNDATION
EZ0CO4370 UNP. 5+095 SUPER STRUCTURE 7 26-Apr-14 03-May-14 55 UNP. 5+095 SUPER STRUCTURE
UNDER PASS AT
A 25+945 14 20-Nov-14 08-Dec-14 24 08-Dec-14, UNDER PASS AT 25+945
EZ0CO4400 UNP. 25+945 FOUNDATION 7 20-Nov-14 30-Nov-14 23 UNP. 25+945 FOUNDATION
EZ0CO4410 UNP. 25+945 SUPER STRUCTURE 7 01-Dec-14 08-Dec-14 24 UNP. 25+945 SUPER STRUCTURE
UNDER PASS AT
A 44+240 14 14-Feb-15 01-Mar-15 49 01-Mar-15, UNDER PASS AT 44+240
EZ0CO4420 UNP. 44+240 FOUNDATION 7 14-Feb-15 21-Feb-15 53 UNP. 44+240 FOUNDATION
EZ0CO4430 UNP. 44+240 SUPER STRUCTURE 7 22-Feb-15 01-Mar-15 49 UNP. 44+240 SUPER STRUCTURE
UNDER PASS AT
A 15+235 14 09-Jul-14 26-Jul-14 70 26-Jul-14, UNDER PASS AT 15+235
EZ0CO4380 UNP. 15+235 FOUNDATION 7 09-Jul-14 16-Jul-14 69 UNP. 15+235 FOUNDATION
EZ0CO4390 UNP. 15+235 SUPER STRUCTURE 7 17-Jul-14 26-Jul-14 70 UNP. 15+235 SUPER STRUCTURE
INTERCHANGES APPROVAL 392 30-Mar-14 13-Jul-15 80 13-Jul-15, INTERCHANGES APPROVAL
INTERCHANGE AT RAWDAH PART 2 [FROM RAWDAH TO MAHDA 27 09-May-15 08-Jun-15 47 08-Jun-15, INTERCHANGE AT RAWDAH PART 2 [F
EZ0CO4530 INT. RAW P2 FOUNDATION 7 09-May-15 16-May-15 23 INT. RAW P2 FOUNDATION
EZ0CO4540 INT. RAW P2 SUB STRUCTURE 7 20-May-15 27-May-15 27 INT. RAW P2 SUB STRUCTURE
EZ0CO4550 INT. RAW P2 SUPER STRUCTURE 7 01-Jun-15 08-Jun-15 47 INT. RAW P2 SUPER STRUCTURE
INTERCHANGE AT HUMAIDAH 27 13-Jun-15 13-Jul-15 80 13-Jul-15, INTERCHANGE AT HUMAIDAH
EZ0CO4560 INT. HUM FOUNDATION 7 13-Jun-15 20-Jun-15 93 INT. HUM FOUNDATION
EZ0CO4570 INT. HUM SUB STRUCTURE 7 24-Jun-15 01-Jul-15 86 INT. HUM SUB STRUCTURE
EZ0CO4580 INT. HUM SUPER STRUCTURE 7 06-Jul-15 13-Jul-15 80 INT. HUM SUPER STRUCTURE
INTERCHANGE AT RAWDAH PART 1 [FROM MAHDAH TO RAWDA 27 06-Jan-15 05-Feb-15 50 05-Feb-15, INTERCHANGE AT RAWDAH PART 1 [FROM MAHDAH T
EZ0CO4500 INT. RAW P1 FOUNDATION 7 06-Jan-15 13-Jan-15 23 INT. RAW P1 FOUNDATION
EZ0CO4510 INT. RAW P1 SUB STRUCTURE 7 18-Jan-15 25-Jan-15 23 INT. RAW P1 SUB STRUCTURE
EZ0CO4520 INT. RAW P1 SUPER STRUCTURE 7 29-Jan-15 05-Feb-15 50 INT. RAW P1 SUPER STRUCTURE
INTERCHANGE 11+630 27 30-Mar-14 29-Apr-14 26 29-Apr-14, INTERCHANGE 11+630
EZ0CO4440 INT. 11+630 FOUNDATION 7 30-Mar-14 06-Apr-14 25 INT. 11+630 FOUNDATION
EZ0CO4450 INT. 11+630 SUB STRUCTURE 7 10-Apr-14 17-Apr-14 31 INT. 11+630 SUB STRUCTURE
EZ0CO4460 INT. 11+630 SUPER STRUCTURE 7 22-Apr-14 29-Apr-14 26 INT. 11+630 SUPER STRUCTURE
INTERCHANGE AT 34+700 27 03-Sep-14 07-Oct-14 47 07-Oct-14, INTERCHANGE AT 34+700
EZ0CO4470 INT. 34+700 FOUNDATION 7 03-Sep-14 10-Sep-14 25 INT. 34+700 FOUNDATION
EZ0CO4480 INT. 34+700 SUB STRUCTURE 7 15-Sep-14 22-Sep-14 23 INT. 34+700 SUB STRUCTURE
EZ0CO4490 INT. 34+700 SUPER STRUCTURE 7 27-Sep-14 07-Oct-14 47 INT. 34+700 SUPER STRUCTURE
ELECTRICAL/UTI
ELECTRICAL/UTILITIES APPROVAL 57 12-Jan-14 19-Mar-14 9 19-Mar-14, ELECTRICAL/UTILITIES APPROVAL
EZ0CO4590 DUCT LAYOUTS 7 12-Jan-14 20-Jan-14 9 DUCT LAYOUTS
EZ0CO4600 DIVERSION OF EXISTING UTILITIES 7 11-Feb-14 18-Feb-14 9 DIVERSION OF EXISTING UTILITIES
EZ0CO4610 STREET LIGHT LAYOUTS 7 12-Mar-14 19-Mar-14 9 STREET LIGHT LAYOUTS
MATERIAL SUBMITTALS
SUBMITTAL 196 01-Jan-14 24-Aug-14 265 24-Aug-14, MATERIAL SUBMITTALS
ELECTRICAL 73 05-Jan-14 31-Mar-14 81 31-Mar-14, ELECTRICAL
EZ0CO4720 CABLES 11 19-Mar-14 31-Mar-14 81 CABLES
EZ0CO4730 FEEDER PILLARS 11 05-Jan-14 18-Jan-14 53 FEEDER PILLARS
EZ0CO4740 ROAD LIGHTING 11 09-Mar-14 20-Mar-14 43 ROAD LIGHTING
EZ0CO4750 TRANFORMERS 11 05-Jan-14 18-Jan-14 53 TRANFORMERS
MAJOR/ SPECIALIST SUB CONTRACTOR 118 01-Mar-14 16-Jul-14 25 16-Jul-14, MAJOR/ SPECIALIST SUB CONTRACTOR
EZ0CO4620 PRESTRESSING 11 05-Jul-14 16-Jul-14 25 PRESTRESSING
EZ0CO4630 MSER WALL 11 01-Mar-14 12-Mar-14 69 MSER WALL
CIVIL WORKS 196 01-Jan-14 24-Aug-14 25 24-Aug-14, CIVIL WORKS
INTERCHANGES 167 01-Jan-14 16-Jul-14 25 16-Jul-14, INTERCHANGES

Actual Work Critical Remaining Work Summary Page 10 of 57 TASK filter: All Activities

Remaining Work Milestone © Oracle Corporation


DUALIZATION OF MAHDAH - AL RAWDAH ROAD PROJECT Classic Schedule Layout 25-May-14 16:51

Activity ID Activity Name Original Start Finish Total Float Critical 2014 2015 2016
Duration
S Oct N D J F M Apr M J Jul A S Oct N D Jan F M Apr M J Jul A S Oct N D J F M Apr M J
EZ0CO4640 BEARINGS 11 12-Feb-14 24-Feb-14 25 BEARINGS
EZ0CO4650 PRESTRESSING MATERIALS 11 05-Jul-14 16-Jul-14 25 PRESTRESSING MATERIALS
EZ0CO4660 EXPANSION JOINT 11 09-Jun-14 21-Jun-14 25 EXPANSION JOINT
EZ0CO4670 UPVC DUCTS AND PVC ITEMS 11 01-Jan-14 14-Jan-14 33 UPVC DUCTS AND PVC ITEMS
ROAD WORKS 30 16-Jul-14 24-Aug-14 25 24-Aug-14, ROAD WORKS
EZ0CO4680 GABION BOXES 11 12-Aug-14 24-Aug-14 25 GABION BOXES
EZ0CO4690 ROCK BOLTS 11 16-Jul-14 02-Aug-14 39 ROCK BOLTS
EZ0CO4700 SHORT SCRETING 11 16-Jul-14 02-Aug-14 39 SHORT SCRETING
EZ0CO4710 DI COVERS & GRATIINGS 11 12-Aug-14 24-Aug-14 25 DI COVERS & GRATIINGS
ROAD FURNITURE 34 10-Feb-14 20-Mar-14 394 20-Mar-14, ROAD FURNITURE
EZ0CO4760 GUARD RAILS 11 10-Feb-14 22-Feb-14 417 GUARD RAILS
EZ0CO4770 ROAD SIGNS 11 09-Mar-14 20-Mar-14 43 ROAD SIGNS
EZ0CO4780 ROAD MARKINGS 11 09-Mar-14 20-Mar-14 43 ROAD MARKINGS
EZ0CO4790 ROAD STUDS 11 09-Mar-14 20-Mar-14 43 ROAD STUDS
EZ0CO4800 DELINEATORS 11 09-Mar-14 20-Mar-14 43 DELINEATORS
EZ0CO4810 MARKER POST 11 09-Mar-14 20-Mar-14 43 MARKER POST
MATERIAL APPROVALS 199 15-Jan-14 09-Sep-14 265 09-Sep-14, MATERIAL APPROVALS
MAJOR/ SPECIALIST SUB CONTRACTOR 121 13-Mar-14 06-Aug-14 25 06-Aug-14, MAJOR/ SPECIALIST SUB CONTRACTOR
EZ0CO4820 PRESTRESSING 14 17-Jul-14 06-Aug-14 25 PRESTRESSING
EZ0CO4830 MSER WALL 14 13-Mar-14 29-Mar-14 69 MSER WALL
CIVIL WORKS 199 15-Jan-14 09-Sep-14 25 09-Sep-14, CIVIL WORKS
INTERCHANGES 170 15-Jan-14 06-Aug-14 25 06-Aug-14, INTERCHANGES
EZ0CO4840 BEARINGS 14 25-Feb-14 12-Mar-14 25 BEARINGS
EZ0CO4850 PRESTRESSING MATERIALS 14 17-Jul-14 06-Aug-14 25 PRESTRESSING MATERIALS
EZ0CO4860 EXPANSION JOINT 14 22-Jun-14 07-Jul-14 25 EXPANSION JOINT
EZ0CO4870 UPVC DUCTS AND PVC ITEMS 14 15-Jan-14 30-Jan-14 33 UPVC DUCTS AND PVC ITEMS
ROAD WORKS 33 03-Aug-14 09-Sep-14 25 09-Sep-14, ROAD WORKS
EZ0CO4880 GABION BOXES 14 25-Aug-14 09-Sep-14 25 GABION BOXES
EZ0CO4890 ROCK BOLTS 14 03-Aug-14 18-Aug-14 39 ROCK BOLTS
EZ0CO4900 SHORT SCRETING 14 03-Aug-14 18-Aug-14 39 SHORT SCRETING
EZ0CO4910 DI COVERS & GRATIINGS 14 25-Aug-14 09-Sep-14 25 DI COVERS & GRATIINGS
ELECTRICAL 76 19-Jan-14 16-Apr-14 81 16-Apr-14, ELECTRICAL
EZ0CO4920 CABLES 14 01-Apr-14 16-Apr-14 81 CABLES
EZ0CO4930 FEEDER PILLARS 14 19-Jan-14 03-Feb-14 53 FEEDER PILLARS
EZ0CO4940 ROAD LIGHTING 14 22-Mar-14 06-Apr-14 43 ROAD LIGHTING
EZ0CO4950 TRANFORMERS 14 19-Jan-14 03-Feb-14 53 TRANFORMERS
ROAD FURNITURE 37 23-Feb-14 06-Apr-14 394 06-Apr-14, ROAD FURNITURE
EZ0CO4960 GUARD RAILS 14 23-Feb-14 10-Mar-14 417 GUARD RAILS
EZ0CO4970 ROAD SIGNS 14 22-Mar-14 06-Apr-14 43 ROAD SIGNS
EZ0CO4980 ROAD MARKINGS 14 22-Mar-14 06-Apr-14 43 ROAD MARKINGS
EZ0CO4990 ROAD STUDS 14 22-Mar-14 06-Apr-14 43 ROAD STUDS
EZ0CO5000 DELINEATORS 14 22-Mar-14 06-Apr-14 43 DELINEATORS
EZ0CO5010 MARKER POST 14 22-Mar-14 06-Apr-14 43 MARKER POST
MATERIAL PROCUREMENT
PROCUREM 233 01-Feb-14 09-Nov-14 269 09-Nov-14, MATERIAL PROCUREMENT
MAJOR/ SPECIALIST SUB CONTRACTOR 177 30-Mar-14 01-Nov-14 25 01-Nov-14, MAJOR/ SPECIALIST SUB CONTRACTOR
EZ0CO5020 PRESTRESSING 70 07-Aug-14 01-Nov-14 25 PRESTRESSING
EZ0CO5030 MSER WALL 77 30-Mar-14 28-Jun-14 69 MSER WALL
CIVIL WORKS 233 01-Feb-14 09-Nov-14 65 09-Nov-14, CIVIL WORKS
INTERCHANGES 226 01-Feb-14 01-Nov-14 25 01-Nov-14, INTERCHANGES
EZ0CO5040 BEARINGS 103 13-Mar-14 12-Jul-14 25 BEARINGS
EZ0CO5050 PRESTRESSING MATERIALS 70 07-Aug-14 01-Nov-14 25 PRESTRESSING MATERIALS
EZ0CO5060 EXPANSION JOINT 71 08-Jul-14 02-Oct-14 25 EXPANSION JOINT

Actual Work Critical Remaining Work Summary Page 11 of 57 TASK filter: All Activities

Remaining Work Milestone © Oracle Corporation


DUALIZATION OF MAHDAH - AL RAWDAH ROAD PROJECT Classic Schedule Layout 25-May-14 16:51

Activity ID Activity Name Original Start Finish Total Float Critical 2014 2015 2016
Duration
S Oct N D J F M Apr M J Jul A S Oct N D Jan F M Apr M J Jul A S Oct N D J F M Apr M J
EZ0CO5070 UPVC DUCTS AND PVC ITEMS 25 01-Feb-14 01-Mar-14 33 UPVC DUCTS AND PVC ITEMS
ROAD WORKS 67 19-Aug-14 09-Nov-14 65 09-Nov-14, ROAD WORKS
EZ0CO5080 GABION BOXES 48 10-Sep-14 09-Nov-14 65 GABION BOXES
EZ0CO5090 ROCK BOLTS 45 19-Aug-14 13-Oct-14 39 ROCK BOLTS
EZ0CO5100 SHORT SCRETING 45 19-Aug-14 13-Oct-14 39 SHORT SCRETING
EZ0CO5110 DI COVERS & GRATIINGS 48 10-Sep-14 09-Nov-14 25 DI COVERS & GRATIINGS
ELECTRICAL 152 04-Feb-14 05-Aug-14 43 05-Aug-14, ELECTRICAL
EZ0CO5120 ROAD LIGHTING 99 07-Apr-14 05-Aug-14 43 ROAD LIGHTING
EZ0CO5130 TRANFORMERS 77 04-Feb-14 04-May-14 53 TRANFORMERS
EZ0CO5140 CABLES 49 17-Apr-14 14-Jun-14 81 CABLES
EZ0CO5150 FEEDER PILLARS 77 04-Feb-14 04-May-14 53 FEEDER PILLARS
ROAD FURNITURE 122 11-Mar-14 05-Aug-14 347 05-Aug-14, ROAD FURNITURE
EZ0CO5160 GUARD RAILS 52 11-Mar-14 10-May-14 417 GUARD RAILS
EZ0CO5170 ROAD SIGNS 99 07-Apr-14 05-Aug-14 43 ROAD SIGNS
EZ0CO5180 ROAD MARKINGS 99 07-Apr-14 05-Aug-14 43 ROAD MARKINGS
EZ0CO5190 ROAD STUDS 99 07-Apr-14 05-Aug-14 43 ROAD STUDS
EZ0CO5200 DELINEATORS 99 07-Apr-14 05-Aug-14 43 DELINEATORS
EZ0CO5210 MARKER POST 99 07-Apr-14 05-Aug-14 43 MARKER POST
AS BUILT DRAWINGS 333 16-May-15 20-Jun-16 0
PLAN, PROFILES & CROSS SECTIONS 90 08-Mar-16 20-Jun-16 0
EZ0CO5220 PART 1 (FROM KM 0+000 to KM 20+000 ) 25 08-Mar-16 05-Apr-16 65 PART 1 (
EZ0CO5230 PART 2 (FROM KM 20+000 to KM 40+000 ) 25 19-May-16 16-Jun-16 3
EZ0CO5240 PART 3 (FROM KM 40+000 to KM 58+594.604) 24 24-May-16 20-Jun-16 0
OTHER CIVIL & ELECTRICAL
ELE WORKS 322 16-May-15 07-Jun-16 11
EZ0CO5250 INTERCHANGES 26 03-Apr-16 02-May-16 42 INTE
EZ0CO5260 CULVERTS 26 22-Feb-16 22-Mar-16 77 CULVERTS
EZ0CO5270 RETAINING WALLS 25 16-May-15 13-Jun-15 308 RETAINING WALLS
EZ0CO5280 SIGNING & MARKING 25 05-May-16 02-Jun-16 15 S
EZ0CO5290 ELECTRICAL DRAWINGS 26 09-May-16 07-Jun-16 11

CONSTRUCTION OF ROAD WORK 757 22-Dec-13 20-Jun-16 0

PART 1 (FROM KM 0+000


0+0 to KM 20+000 ) 652 22-Dec-13 18-Feb-16 65 18-Feb-16, PAR
EXCAVAT ION, FILLING & BITUMINOUS PAVEMENT 489 22-Dec-13 04-Aug-15 68 04-Aug-15, EXCAVATION, FILLING & BITUM
UTILITIES RELOCATION
RELOCAT 125 22-Dec-13 17-May-14 144 17-May-14, UTILITIES RELOCATION
CZ1UT1000 PART 1 UTILITIES RELOCATION CH. FROM KM 0+ 25 22-Dec-13 20-Jan-14 7 PART 1 UTILITIES RELOCATION CH. FROM KM 0+000 TO 4+000
CZ1UT1010 PART 1 UTILITIES RELOCATION CH. FROM KM 4+ 25 21-Jan-14 18-Feb-14 9 PART 1 UTILITIES RELOCATION CH. FROM KM 4+000 TO 8+000
CZ1UT1020 PART 1 UTILITIES RELOCATION CH. FROM KM 8+ 25 19-Feb-14 19-Mar-14 9 PART 1 UTILITIES RELOCATION CH. FROM KM 8+000 TO 12+000
CZ1UT1030 PART 1 UTILITIES RELOCATION CH. FROM KM 12 25 20-Mar-14 17-Apr-14 9 PART 1 UTILITIES RELOCATION CH. FROM KM 12+000 TO 16+000
CZ1UT1040 PART 1 UTILITIES RELOCATION CH. FROM KM 16 25 19-Apr-14 17-May-14 144 PART 1 UTILITIES RELOCATION CH. FROM KM 16+000 TO 20+000
SETTING OUT 154 29-Jan-14 02-Aug-14 130 02-Aug-14, SETTING OUT
CZ1EW1000 SETTING OUT CH. FROM KM 0+000 TO 2+000 15 29-Jan-14 15-Feb-14 0 SETTING OUT CH. FROM KM 0+000 TO 2+000
CZ1EW1010 SETTING OUT CH. FROM KM 2+000 TO 4+000 16 16-Feb-14 05-Mar-14 0 SETTING OUT CH. FROM KM 2+000 TO 4+000
CZ1EW1020 SETTING OUT CH. FROM KM 4+000 TO 6+000 15 06-Mar-14 23-Mar-14 0 SETTING OUT CH. FROM KM 4+000 TO 6+000
CZ1EW1030 SETTING OUT CH. FROM KM 6+000 TO 8+000 15 24-Mar-14 09-Apr-14 0 SETTING OUT CH. FROM KM 6+000 TO 8+000
CZ1EW1040 SETTING OUT CH. FROM KM 8+000 TO 10+000 16 10-Apr-14 28-Apr-14 0 SETTING OUT CH. FROM KM 8+000 TO 10+000
CZ1EW1050 SETTING OUT CH. FROM KM 10+000 TO 12+000 15 29-Apr-14 15-May-14 0 SETTING OUT CH. FROM KM 10+000 TO 12+000
CZ1EW1060 SETTING OUT CH. FROM KM 12+000 TO 14+000 15 17-May-14 03-Jun-14 130 SETTING OUT CH. FROM KM 12+000 TO 14+000
CZ1EW1070 SETTING OUT CH. FROM KM 14+000 TO 16+000 16 04-Jun-14 22-Jun-14 130 SETTING OUT CH. FROM KM 14+000 TO 16+000
CZ1EW1080 SETTING OUT CH. FROM KM 16+000 TO 18+000 15 23-Jun-14 09-Jul-14 130 SETTING OUT CH. FROM KM 16+000 TO 18+000
CZ1EW1090 SETTING OUT CH. FROM KM 18+000 TO 20+000 16 10-Jul-14 02-Aug-14 130 SETTING OUT CH. FROM KM 18+000 TO 20+000
CLEARING AND GRUBBING
GR FOR ROAD WAY 154 01-Feb-14 04-Aug-14 128 04-Aug-14, CLEARING AND GRUBBING FOR ROAD WAY
CZ1EW1100 CLEARING & GRUBBING CH. FROM KM 0+000 TO 15 01-Feb-14 17-Feb-14 5 CLEARING & GRUBBING CH. FROM KM 0+000 TO 2+000

Actual Work Critical Remaining Work Summary Page 12 of 57 TASK filter: All Activities

Remaining Work Milestone © Oracle Corporation


DUALIZATION OF MAHDAH - AL RAWDAH ROAD PROJECT Classic Schedule Layout 25-May-14 16:51

Activity ID Activity Name Original Start Finish Total Float Critical 2014 2015 2016
Duration
S Oct N D J F M Apr M J Jul A S Oct N D Jan F M Apr M J Jul A S Oct N D J F M Apr M J
CZ1EW1110 CLEARING & GRUBBING CH. FROM KM 2+000 TO 16 18-Feb-14 08-Mar-14 27 CLEARING & GRUBBING CH. FROM KM 2+000 TO 4+000
CZ1EW1120 CLEARING & GRUBBING CH. FROM KM 4+000 TO 15 09-Mar-14 25-Mar-14 87 CLEARING & GRUBBING CH. FROM KM 4+000 TO 6+000
CZ1EW1130 CLEARING & GRUBBING CH. FROM KM 6+000 TO 15 26-Mar-14 12-Apr-14 128 CLEARING & GRUBBING CH. FROM KM 6+000 TO 8+000
CZ1EW1140 CLEARING & GRUBBING CH. FROM KM 8+000 TO 16 13-Apr-14 30-Apr-14 128 CLEARING & GRUBBING CH. FROM KM 8+000 TO 10+000
CZ1EW1150 CLEARING & GRUBBING CH. FROM KM 10+000 TO 15 01-May-14 18-May-14 128 CLEARING & GRUBBING CH. FROM KM 10+000 TO 12+000
CZ1EW1160 CLEARING & GRUBBING CH. FROM KM 12+000 TO 15 19-May-14 05-Jun-14 128 CLEARING & GRUBBING CH. FROM KM 12+000 TO 14+000
CZ1EW1170 CLEARING & GRUBBING CH. FROM KM 14+000 TO 16 07-Jun-14 24-Jun-14 128 CLEARING & GRUBBING CH. FROM KM 14+000 TO 16+000
CZ1EW1180 CLEARING & GRUBBING CH. FROM KM 16+000 TO 15 25-Jun-14 12-Jul-14 128 CLEARING & GRUBBING CH. FROM KM 16+000 TO 18+000
CZ1EW1190 CLEARING & GRUBBING CH. FROM KM 18+000 TO 16 13-Jul-14 04-Aug-14 128 CLEARING & GRUBBING CH. FROM KM 18+000 TO 20+000
UNCLASSIFIED EXCAVATIO
EXC N 280 10-Feb-14 15-Jan-15 117 15-Jan-15, UNCLASSIFIED EXCAVATION
CZ1EW1200 UNCLASSIFIED EXCAVATION CH. FROM KM 0+000 28 10-Feb-14 13-Mar-14 7 UNCLASSIFIED EXCAVATION CH. FROM KM 0+000 TO 2+000
CZ1EW1210 UNCLASSIFIED EXCAVATION CH. FROM KM 2+000 28 15-Mar-14 15-Apr-14 25 UNCLASSIFIED EXCAVATION CH. FROM KM 2+000 TO 4+000
CZ1EW1220 UNCLASSIFIED EXCAVATION CH. FROM KM 4+000 28 16-Apr-14 18-May-14 54 UNCLASSIFIED EXCAVATION CH. FROM KM 4+000 TO 6+000
CZ1EW1230 UNCLASSIFIED EXCAVATION CH. FROM KM 6+000 28 19-May-14 21-Jun-14 102 UNCLASSIFIED EXCAVATION CH. FROM KM 6+000 TO 8+000
CZ1EW1240 UNCLASSIFIED EXCAVATION CH. FROM KM 8+000 28 22-Jun-14 24-Jul-14 104 UNCLASSIFIED EXCAVATION CH. FROM KM 8+000 TO 10+000
CZ1EW1250 UNCLASSIFIED EXCAVATION CH. FROM KM 10+00 28 26-Jul-14 30-Aug-14 106 UNCLASSIFIED EXCAVATION CH. FROM KM 10+000 TO 12+000
CZ1EW1260 UNCLASSIFIED EXCAVATION CH. FROM KM 12+00 28 31-Aug-14 01-Oct-14 108 UNCLASSIFIED EXCAVATION CH. FROM KM 12+000 TO 14+000
CZ1EW1270 UNCLASSIFIED EXCAVATION CH. FROM KM 14+00 28 02-Oct-14 08-Nov-14 115 UNCLASSIFIED EXCAVATION CH. FROM KM 14+000 TO 16+000
CZ1EW1280 UNCLASSIFIED EXCAVATION CH. FROM KM 16+00 28 09-Nov-14 13-Dec-14 115 UNCLASSIFIED EXCAVATION CH. FROM KM 16+000 TO 18+000
CZ1EW1290 UNCLASSIFIED EXCAVATION CH. FROM KM 18+00 28 14-Dec-14 15-Jan-15 117 UNCLASSIFIED EXCAVATION CH. FROM KM 18+000 TO 20+000
REMOVAL OF STRUCTURE
STRU & OBSTRUCTIONS 272 16-Feb-14 12-Jan-15 117 12-Jan-15, REMOVAL OF STRUCTURE & OBSTRUCTIONS
CZ1EW1300 REMOVAL OF STRUCTURE & OBSTRUCTIONS CH 20 16-Feb-14 10-Mar-14 10 REMOVAL OF STRUCTURE & OBSTRUCTIONS CH. FROM KM 0+000 TO 2+000
CZ1EW1310 REMOVAL OF STRUCTURE & OBSTRUCTIONS CH 20 20-Mar-14 12-Apr-14 101 REMOVAL OF STRUCTURE & OBSTRUCTIONS CH. FROM KM 2+000 TO 4+000
CZ1EW1320 REMOVAL OF STRUCTURE & OBSTRUCTIONS CH 20 22-Apr-14 14-May-14 103 REMOVAL OF STRUCTURE & OBSTRUCTIONS CH. FROM KM 4+000 TO 6+000
CZ1EW1330 REMOVAL OF STRUCTURE & OBSTRUCTIONS CH 20 25-May-14 17-Jun-14 105 REMOVAL OF STRUCTURE & OBSTRUCTIONS CH. FROM KM 6+000 TO 8+000
CZ1EW1340 REMOVAL OF STRUCTURE & OBSTRUCTIONS CH 20 28-Jun-14 20-Jul-14 107 REMOVAL OF STRUCTURE & OBSTRUCTIONS CH. FROM KM 8+000 TO 10+000
CZ1EW1350 REMOVAL OF STRUCTURE & OBSTRUCTIONS CH 20 04-Aug-14 26-Aug-14 109 REMOVAL OF STRUCTURE & OBSTRUCTIONS CH. FROM KM 10+000 TO 12+000
CZ1EW1360 REMOVAL OF STRUCTURE & OBSTRUCTIONS CH 20 06-Sep-14 28-Sep-14 111 REMOVAL OF STRUCTURE & OBSTRUCTIONS CH. FROM KM 12+000 TO 14+000
CZ1EW1370 REMOVAL OF STRUCTURE & OBSTRUCTIONS CH 20 12-Oct-14 04-Nov-14 143 REMOVAL OF STRUCTURE & OBSTRUCTIONS CH. FROM KM 14+000 TO 16+0
CZ1EW1380 REMOVAL OF STRUCTURE & OBSTRUCTIONS CH 20 15-Nov-14 09-Dec-14 115 REMOVAL OF STRUCTURE & OBSTRUCTIONS CH. FROM KM 16+000 TO
CZ1EW1390 REMOVAL OF STRUCTURE & OBSTRUCTIONS CH 20 20-Dec-14 12-Jan-15 117 REMOVAL OF STRUCTURE & OBSTRUCTIONS CH. FROM KM 18+000
EMBANKMENT FILLING
FILL 336 10-Feb-14 22-Mar-15 88 22-Mar-15, EMBANKMENT FILLING
CZ1EW1400 EMBANKMENT FILLING CH. FROM KM 0+000 TO 2 30 10-Feb-14 16-Mar-14 5 EMBANKMENT FILLING CH. FROM KM 0+000 TO 2+000
CZ1EW1410 EMBANKMENT FILLING CH. FROM KM 2+000 TO 4 30 17-Mar-14 20-Apr-14 94 EMBANKMENT FILLING CH. FROM KM 2+000 TO 4+000
CZ1EW1420 EMBANKMENT FILLING CH. FROM KM 4+000 TO 6 30 21-Apr-14 25-May-14 94 EMBANKMENT FILLING CH. FROM KM 4+000 TO 6+000
CZ1EW1430 EMBANKMENT FILLING CH. FROM KM 6+000 TO 8 30 26-May-14 30-Jun-14 94 EMBANKMENT FILLING CH. FROM KM 6+000 TO 8+000
CZ1EW1440 EMBANKMENT FILLING CH. FROM KM 8+000 TO 1 30 01-Jul-14 09-Aug-14 94 EMBANKMENT FILLING CH. FROM KM 8+000 TO 10+000
CZ1EW1450 EMBANKMENT FILLING CH. FROM KM 10+000 TO 30 10-Aug-14 13-Sep-14 94 EMBANKMENT FILLING CH. FROM KM 10+000 TO 12+000
CZ1EW1460 EMBANKMENT FILLING CH. FROM KM 12+000 TO 30 14-Sep-14 21-Oct-14 94 EMBANKMENT FILLING CH. FROM KM 12+000 TO 14+000
CZ1EW1470 EMBANKMENT FILLING CH. FROM KM 14+000 TO 30 07-Dec-14 11-Jan-15 88 EMBANKMENT FILLING CH. FROM KM 14+000 TO 16+000
CZ1EW1480 EMBANKMENT FILLING CH. FROM KM 16+000 TO 30 12-Jan-15 15-Feb-15 88 EMBANKMENT FILLING CH. FROM KM 16+000 TO 18+000
CZ1EW1490 EMBANKMENT FILLING CH. FROM KM 18+000 TO 30 16-Feb-15 22-Mar-15 88 EMBANKMENT FILLING CH. FROM KM 18+000 TO 20+000
SUB GRADE PREPARATION
PREPA IN CUT 300 24-Mar-14 22-Mar-15 88 22-Mar-15, SUB GRADE PREPARATION IN CUT
CZ1EW1500 SUB GRADE PREPARATION IN CUT CH. FROM KM 30 24-Mar-14 27-Apr-14 5 SUB GRADE PREPARATION IN CUT CH. FROM KM 0+000 TO 2+000
CZ1EW1510 SUB GRADE PREPARATION IN CUT CH. FROM KM 30 28-Apr-14 02-Jun-14 88 SUB GRADE PREPARATION IN CUT CH. FROM KM 2+000 TO 4+000
CZ1EW1520 SUB GRADE PREPARATION IN CUT CH. FROM KM 30 03-Jun-14 07-Jul-14 88 SUB GRADE PREPARATION IN CUT CH. FROM KM 4+000 TO 6+000
CZ1EW1530 SUB GRADE PREPARATION IN CUT CH. FROM KM 30 08-Jul-14 16-Aug-14 88 SUB GRADE PREPARATION IN CUT CH. FROM KM 6+000 TO 8+000
CZ1EW1540 SUB GRADE PREPARATION IN CUT CH. FROM KM 30 17-Aug-14 20-Sep-14 88 SUB GRADE PREPARATION IN CUT CH. FROM KM 8+000 TO 10+000
CZ1EW1550 SUB GRADE PREPARATION IN CUT CH. FROM KM 30 21-Sep-14 29-Oct-14 88 SUB GRADE PREPARATION IN CUT CH. FROM KM 10+000 TO 12+000
CZ1EW1560 SUB GRADE PREPARATION IN CUT CH. FROM KM 30 30-Oct-14 06-Dec-14 88 SUB GRADE PREPARATION IN CUT CH. FROM KM 12+000 TO 14+000
CZ1EW1570 SUB GRADE PREPARATION IN CUT CH. FROM KM 30 07-Dec-14 11-Jan-15 88 SUB GRADE PREPARATION IN CUT CH. FROM KM 14+000 TO 16+000

Actual Work Critical Remaining Work Summary Page 13 of 57 TASK filter: All Activities

Remaining Work Milestone © Oracle Corporation


DUALIZATION OF MAHDAH - AL RAWDAH ROAD PROJECT Classic Schedule Layout 25-May-14 16:51

Activity ID Activity Name Original Start Finish Total Float Critical 2014 2015 2016
Duration
S Oct N D J F M Apr M J Jul A S Oct N D Jan F M Apr M J Jul A S Oct N D J F M Apr M J
CZ1EW1580 SUB GRADE PREPARATION IN CUT CH. FROM KM 30 12-Jan-15 15-Feb-15 88 SUB GRADE PREPARATION IN CUT CH. FROM KM 16+000 TO 18
CZ1EW1590 SUB GRADE PREPARATION IN CUT CH. FROM KM 30 16-Feb-15 22-Mar-15 88 SUB GRADE PREPARATION IN CUT CH. FROM KM 18+000 T
TRENCH EXCAVATION
EXCAVATIO AND BACK FILLING 290 16-Apr-14 02-Apr-15 78 02-Apr-15, TRENCH EXCAVATION AND BACK FILLING
CZ1EW1600 TRENCH EXCAVATION & BACKFILLING CH. FRO M 29 16-Apr-14 19-May-14 5 TRENCH EXCAVATION & BACKFILLING CH. FRO M KM 0+000 TO 2+000
CZ1EW1610 TRENCH EXCAVATION & BACKFILLING CH. FRO M 29 20-May-14 23-Jun-14 64 TRENCH EXCAVATION & BACKFILLING CH. FRO M KM 2+000 TO 4+000
CZ1EW1620 TRENCH EXCAVATION & BACKFILLING CH. FRO M 29 24-Jun-14 31-Jul-14 78 TRENCH EXCAVATION & BAC KFILLING CH. FRO M KM 4+000 TO 6+000
CZ1EW1630 TRENCH EXCAVATION & BACKFILLING CH. FRO M 29 02-Aug-14 03-Sep-14 78 TRENCH EXCAVATION & BACKFILLING CH. FRO M KM 6+000 TO 8+000
CZ1EW1640 TRENCH EXCAVATION & BACKFILLING CH. FRO M 29 04-Sep-14 11-Oct-14 78 TRENCH EXCAVATION & BACKFILLING CH. FRO M KM 8+000 TO 10+000
CZ1EW1650 TRENCH EXCAVATION & BACKFILLING CH. FRO M 29 12-Oct-14 15-Nov-14 78 TRENCH EXCAVATION & BACKFILLING CH. FRO M KM 10+000 TO 12+000
CZ1EW1660 TRENCH EXCAVATION & BACKFILLING CH. FRO M 29 16-Nov-14 21-Dec-14 78 TRENCH EXCAVATION & BAC KFILLING CH. FRO M KM 12+000 TO 14+000
CZ1EW1670 TRENCH EXCAVATION & BACKFILLING CH. FRO M 29 22-Dec-14 25-Jan-15 78 TRENCH EXCAVATION & BACKFILLING CH. FRO M KM 14+000 TO 16
CZ1EW1680 TRENCH EXCAVATION & BACKFILLING CH. FRO M 29 26-Jan-15 28-Feb-15 78 TRENCH EXCAVATION & BACKFILLING CH. FRO M KM 16+000 T
CZ1EW1690 TRENCH EXCAVATION & BACKFILLING CH. FRO M 29 01-Mar-15 02-Apr-15 78 TRENCH EXCAVATION & BACKFILLING CH. FRO M KM 18+0
AGGREGATE BASE COURSE 290 01-May-14 18-Apr-15 65 18-Apr-15, AGGREGATE BASE COURSE
CZ1RW1000 AGGREGATE BASE COURSE CH. FROM KM 0+000 29 01-May-14 04-Jun-14 5 AGGREGATE BASE COURSE CH. FROM KM 0+000 TO 2+000
CZ1RW1010 AGGREGATE BASE COURSE CH. FROM KM 2+000 29 05-Jun-14 08-Jul-14 51 AGGREGATE BASE COURSE CH. FROM KM 2+000 TO 4+000
CZ1RW1020 AGGREGATE BASE COURSE CH. FROM KM 4+000 29 09-Jul-14 16-Aug-14 65 AGGREGATE BASE COURSE CH. FROM KM 4+000 TO 6+000
CZ1RW1030 AGGREGATE BASE COURSE CH. FROM KM 6+000 29 17-Aug-14 18-Sep-14 65 AGGREGATE BASE COURSE CH. FROM KM 6+000 TO 8+000
CZ1RW1040 AGGREGATE BASE COURSE CH. FROM KM 8+000 29 20-Sep-14 27-Oct-14 65 AGGREGATE BASE COURSE CH. FROM KM 8+000 TO 10+000
CZ1RW1050 AGGREGATE BASE COURSE CH. FROM KM 10+00 29 28-Oct-14 02-Dec-14 65 AGGREGATE BASE COURSE CH. FROM KM 10+000 TO 12+000
CZ1RW1060 AGGREGATE BASE COURSE CH. FROM KM 12+00 29 03-Dec-14 06-Jan-15 65 AGGREGATE BASE COURSE CH. FROM KM 12+000 TO 14+000
CZ1RW1070 AGGREGATE BASE COURSE CH. FROM KM 14+00 29 07-Jan-15 09-Feb-15 65 AGGREGATE BASE COURSE CH. FROM KM 14+000 TO 16+000
CZ1RW1080 AGGREGATE BASE COURSE CH. FROM KM 16+00 29 10-Feb-15 15-Mar-15 65 AGGREGATE BASE COURSE CH. FROM KM 16+000 TO 18+00
CZ1RW1090 AGGREGATE BASE COURSE CH. FROM KM 18+00 29 16-Mar-15 18-Apr-15 65 AGGREGATE BASE COURSE CH. FROM KM 18+000 TO 2
BITUMINOUS PAVEMENT
PAVEM 356 28-May-14 04-Aug-15 68 04-Aug-15, BITUMINOUS PAVEMENT
ASPHALT BASE COURSE
C 348 28-May-14 26-Jul-15 65 26-Jul-15, ASPHALT BASE COURSE
CZ1RW1100 ASPHALT BASE COURSE CH. FROM KM 0+000 TO 28 28-May-14 29-Jun-14 5 ASPHALT BASE COURSE CH. FROM KM 0+000 TO 2+000
CZ1RW1110 ASPHALT BASE COURSE CH. FROM KM 2+000 TO 28 30-Jun-14 05-Aug-14 31 ASPHALT BASE COURSE CH. FROM KM 2+000 TO 4+000
CZ1RW1120 ASPHALT BASE COURSE CH. FROM KM 4+000 TO 28 28-Sep-14 03-Nov-14 54 ASPHALT BASE COURSE CH. FROM KM 4+000 TO 6+000
CZ1RW1130 ASPHALT BASE COURSE CH. FROM KM 6+000 TO 28 04-Nov-14 08-Dec-14 94 ASPHALT BASE COURSE CH. FROM KM 6+000 TO 8+000
CZ1RW1140 ASPHALT BASE COURSE CH. FROM KM 8+000 TO 28 09-Dec-14 11-Jan-15 94 ASPHALT BASE COURSE CH. FROM KM 8+000 TO 10+000
CZ1RW1150 ASPHALT BASE COURSE CH. FROM KM 10+000 TO 28 12-Jan-15 12-Feb-15 94 ASPHALT BASE COURSE CH. FROM KM 10+000 TO 12+000
CZ1RW1160 ASPHALT BASE COURSE CH. FROM KM 12+000 TO 26 19-Mar-15 18-Apr-15 65 ASPHALT BASE COURSE CH. FROM KM 12+000 TO 14+0
CZ1RW1170 ASPHALT BASE COURSE CH. FROM KM 14+000 TO 26 19-Apr-15 18-May-15 65 ASPHALT BASE COURSE CH. FROM KM 14+000 TO
CZ1RW1180 ASPHALT BASE COURSE CH. FROM KM 16+000 TO 26 19-May-15 17-Jun-15 65 ASPHALT BASE COURSE CH. FROM KM 16+000
CZ1RW1190 ASPHALT BASE COURSE CH. FROM KM 18+000 TO 28 18-Jun-15 26-Jul-15 65 ASPHALT BASE COURSE CH. FROM KM 18
ASPHALT WEARING
WEARI COURSE 331 26-Jun-14 04-Aug-15 68 04-Aug-15, ASPHALT WEARING COURSE
CZ1RW1200 ASPHALT WEARING COURSE CH. FROM KM 0+00 29 26-Jun-14 03-Aug-14 5 ASPHALT WEARING COURSE CH. FROM KM 0+000 TO 2+000
CZ1RW1210 ASPHALT WEARING COURSE CH. FROM KM 2+00 29 04-Aug-14 06-Sep-14 5 ASPHALT WEARING COURSE CH. FROM KM 2+000 TO 4+000
CZ1RW1220 ASPHALT WEARING COURSE CH. FROM KM 4+00 29 28-Sep-14 04-Nov-14 93 ASPHALT WEARING COURSE CH. FROM KM 4+000 TO 6+000
CZ1RW1230 ASPHALT WEARING COURSE CH. FROM KM 6+00 29 05-Nov-14 10-Dec-14 93 ASPHALT WEARING COURSE CH. FROM KM 6+000 TO 8+000
CZ1RW1240 ASPHALT WEARING COURSE CH. FROM KM 8+00 29 11-Dec-14 14-Jan-15 93 ASPHALT WEARING COURSE CH. FROM KM 8+000 TO 10+000
CZ1RW1250 ASPHALT WEARING COURSE CH. FROM KM 10+0 29 15-Jan-15 17-Feb-15 93 ASPHALT WEARING COURSE CH. FROM KM 10+000 TO 12+000
CZ1RW1260 ASPHALT WEARING COURSE CH. FROM KM 12+0 29 19-Mar-15 21-Apr-15 68 ASPHALT WEARING COURSE CH. FROM KM 12+000 TO
CZ1RW1270 ASPHALT WEARING COURSE CH. FROM KM 14+0 28 22-Apr-15 24-May-15 68 ASPHALT WEARING COURSE CH. FROM KM 14+00
CZ1RW1280 ASPHALT WEARING COURSE CH. FROM KM 16+0 28 25-May-15 25-Jun-15 68 ASPHALT WEARING COURSE CH. FROM KM 16
CZ1RW1290 ASPHALT WEARING COURSE CH. FROM KM 18+0 29 27-Jun-15 04-Aug-15 68 ASPHALT WEARING COURSE CH. FROM
CONCRETE & CONCRETE
CONCRE STRUCTURES 335 20-Feb-14 31-Mar-15 80 31-Mar-15, CONCRETE & CONCRETE STRUCTURES
CONSTRUCTION OF BOX CULVERTS 335 20-Feb-14 31-Mar-15 80 31-Mar-15, CONSTRUCTION OF BOX CULVERTS
7.02 CELL BOX C
CULVERT @ CH 2+335 - (1.5X1.5) 79 20-Feb-14 22-May-14 96 22-May-14, 7.02 CELL BOX CULVERT @ CH 2+335 - (1.5X1.5)
CZ1CU1000 7.02 EXCAVATION 3 20-Feb-14 23-Feb-14 12 7.02 EXCAVATION

Actual Work Critical Remaining Work Summary Page 14 of 57 TASK filter: All Activities

Remaining Work Milestone © Oracle Corporation


DUALIZATION OF MAHDAH - AL RAWDAH ROAD PROJECT Classic Schedule Layout 25-May-14 16:51

Activity ID Activity Name Original Start Finish Total Float Critical 2014 2015 2016
Duration
S Oct N D J F M Apr M J Jul A S Oct N D Jan F M Apr M J Jul A S Oct N D J F M Apr M J
CZ1CU1010 7.02 BLINDING CONCRETE 3 24-Feb-14 26-Feb-14 12 7.02 BLINDING CONCRETE
CZ1CU1020 7.02 CONSTRUCTION OF BASE SLABS 22 27-Feb-14 24-Mar-14 12 7.02 CONSTRUCTION OF BASE SLABS
CZ1CU1030 7.02 CONSTRUCTION OF WALLS & TOP SLABS 35 25-Mar-14 04-May-14 96 7.02 CONSTRUCTION OF WALLS & TOP SLABS
CZ1CU1040 7.02 CONSTRUCTION OF INLET & OUTLET 11 05-May-14 17-May-14 96 7.02 CONSTRUCTION OF INLET & OUTLET
CZ1CU1050 7.02 WATER PROOFING WORKS 11 11-May-14 22-May-14 96 7.02 WATER PROOFING WORKS
9.02 CELL BOX C
CULVERT @ CH 2+870 - (2.0X1.5) 79 24-Feb-14 26-May-14 93 26-May-14, 9.02 CELL BOX CULVERT @ CH 2+870 - (2.0X1.5)
CZ1CU1060 9.02 EXCAVATION 3 24-Feb-14 26-Feb-14 12 9.02 EXCAVATION
CZ1CU1070 9.02 BLINDING CONCRETE 3 27-Feb-14 02-Mar-14 37 9.02 BLINDING CONCRETE
CZ1CU1080 9.02 CONSTRUCTION OF BASE SLABS 22 03-Mar-14 27-Mar-14 93 9.02 CONSTRUCTION OF BASE SLABS
CZ1CU1090 9.02 CONSTRUCTION OF WALLS & TOP SLABS 35 29-Mar-14 07-May-14 93 9.02 CONSTRUCTION OF WALLS & TOP SLABS
CZ1CU1100 9.02 CONSTRUCTION OF INLET & OUTLET 11 08-May-14 20-May-14 93 9.02 CONSTRUCTION OF INLET & OUTLET
CZ1CU1110 9.02 WATER PROOFING WORKS 11 14-May-14 26-May-14 93 9.02 WATER PROOFING WORKS
10.07 CELL BOX C
CULVERT @ CH 3+400 - (2.0X2.0) 101 27-Feb-14 25-Jun-14 98 25-Jun-14, 10.07 CELL BOX CULVERT @ CH 3+400 - (2.0X2.0)
CZ1CU1120 10.07 EXCAVATION 7 27-Feb-14 06-Mar-14 12 10.07 EXCAVATION
CZ1CU1130 10.07 BLINDING CONCRETE 5 08-Mar-14 12-Mar-14 33 10.07 BLINDING CONCRETE
CZ1CU1140 10.07 CONSTRUCTION OF BASE SLABS 35 13-Mar-14 22-Apr-14 98 10.07 CONSTRUCTION OF BASE SLABS
CZ1CU1150 10.07 CONSTRUCTION OF WALLS & TOP SLABS 40 23-Apr-14 09-Jun-14 98 10.07 CONSTRUCTION OF WALLS & TOP SLABS
CZ1CU1160 10.07 CONSTRUCTION OF INLET & OUTLET 10 10-Jun-14 21-Jun-14 98 10.07 CONSTRUCTION OF INLET & OUTLET
CZ1CU1170 10.07 WATER PROOFING WORKS 10 15-Jun-14 25-Jun-14 98 10.07 WATER PROOFING WORKS
12.06 CELL BOX C
CULVERT @ CH 3+975 - (2.0X2.0) 121 08-Mar-14 31-Jul-14 101 31-Jul-14, 12.06 CELL BOX CULVERT @ CH 3+975 - (2.0X2.0)
CZ1CU1180 12.06 EXCAVATION 6 08-Mar-14 13-Mar-14 12 12.06 EXCAVATION
CZ1CU1190 12.06 BLINDING CONCRETE 4 15-Mar-14 18-Mar-14 32 12.06 BLINDING CONCRETE
CZ1CU1200 12.06 CONSTRUCTION OF BASE SLABS 39 19-Mar-14 03-May-14 57 12.06 CONSTRUCTION OF BASE SLABS
CZ1CU1210 12.06 CONSTRUCTION OF WALLS & TOP SLABS 60 04-May-14 13-Jul-14 57 12.06 CONSTRUCTION OF WALLS & TOP SLABS
CZ1CU1220 12.06 CONSTRUCTION OF INLET & OUTLET 9 14-Jul-14 24-Jul-14 101 12.06 CONSTRUCTION OF INLET & OUTLET
CZ1CU1230 12.06 WATER PROOFING WORKS 7 20-Jul-14 31-Jul-14 101 12.06 WATER PROOFING WORKS
13.02 CELL BOX C
CULVERT @ CH 4+320 - (2.0X1.5) 77 15-Mar-14 12-Jun-14 109 12-Jun-14, 13.02 CELL BOX CULVERT @ CH 4+320 - (2.0X1.5)
CZ1CU1240 13.02 EXCAVATION 3 15-Mar-14 17-Mar-14 12 13.02 EXCAVATION
CZ1CU1250 13.02 BLINDING CONCRETE 3 18-Mar-14 20-Mar-14 30 13.02 BLINDING CONCRETE
CZ1CU1260 13.02 CONSTRUCTION OF BASE SLABS 22 22-Mar-14 15-Apr-14 107 13.02 CONSTRUCTION OF BASE SLABS
CZ1CU1270 13.02 CONSTRUCTION OF WALLS & TOP SLABS 36 16-Apr-14 28-May-14 107 13.02 CONSTRUCTION OF WALLS & TOP SLABS
CZ1CU1280 13.02 CONSTRUCTION OF INLET & OUTLET 8 29-May-14 07-Jun-14 107 13.02 CONSTRUCTION OF INLET & OUTLET
CZ1CU1290 13.02 WATER PROOFING WORKS 9 03-Jun-14 12-Jun-14 109 13.02 WATER PROOFING WORKS
16.02 CELL BOX C
CULVERT @ CH 5+450 - (2.0X1.5) 77 18-Mar-14 16-Jun-14 106 16-Jun-14, 16.02 CELL BOX CULVERT @ CH 5+450 - (2.0X1.5)
CZ1CU1300 16.02 EXCAVATION 4 18-Mar-14 22-Mar-14 12 16.02 EXCAVATION
CZ1CU1310 16.02 BLINDING CONCRETE 3 23-Mar-14 25-Mar-14 29 16.02 BLINDING CONCRETE
CZ1CU1320 16.02 CONSTRUCTION OF BASE SLABS 19 26-Mar-14 16-Apr-14 57 16.02 CONSTRUCTION OF BASE SLABS
CZ1CU1330 16.02 CONSTRUCTION OF WALLS & TOP SLABS 33 17-Apr-14 25-May-14 93 16.02 CONSTRUCTION OF WALLS & TOP SLABS
CZ1CU1340 16.02 CONSTRUCTION OF INLET & OUTLET 11 26-May-14 08-Jun-14 106 16.02 CONSTRUCTION OF INLET & OUTLET
CZ1CU1350 16.02 WATER PROOFING WORKS 10 05-Jun-14 16-Jun-14 106 16.02 WATER PROOFING WORKS
19.02 CELL BOX C
CULVERT @ CH 7+170 - (2.0X1.5) 76 23-Mar-14 19-Jun-14 133 19-Jun-14, 19.02 CELL BOX CULVERT @ CH 7+170 - (2.0X1.5)
CZ1CU1360 19.02 EXCAVATION 3 23-Mar-14 25-Mar-14 12 19.02 EXCAVATION
CZ1CU1370 19.02 BLINDING CONCRETE 3 26-Mar-14 29-Mar-14 29 19.02 BLINDING CONCRETE
CZ1CU1380 19.02 CONSTRUCTION OF BASE SLABS 19 30-Mar-14 20-Apr-14 113 19.02 CONSTRUCTION OF BASE SLABS
CZ1CU1390 19.02 CONSTRUCTION OF WALLS & TOP SLABS 35 21-Apr-14 01-Jun-14 113 19.02 CONSTRUCTION OF WALLS & TOP SLABS
CZ1CU1400 19.02 CONSTRUCTION OF INLET & OUTLET 11 02-Jun-14 14-Jun-14 133 19.02 CONSTRUCTION OF INLET & OUTLET
CZ1CU1410 19.02 WATER PROOFING WORKS 11 08-Jun-14 19-Jun-14 133 19.02 WATER PROOFING WORKS
20.03 CELL BOX C
CULVERT @ CH 10+140 - (2.0X1.5) 91 26-Mar-14 10-Jul-14 115 10-Jul-14, 20.03 CELL BOX CULVERT @ CH 10+140 - (2.0X1.5)
CZ1CU1420 20.03 EXCAVATION 3 26-Mar-14 29-Mar-14 12 20.03 EXCAVATION
CZ1CU1430 20.03 BLINDING CONCRETE 4 30-Mar-14 02-Apr-14 29 20.03 BLINDING CONCRETE
CZ1CU1440 20.03 CONSTRUCTION OF BASE SLABS 26 03-Apr-14 03-May-14 93 20.03 CONSTRUCTION OF BASE SLABS

Actual Work Critical Remaining Work Summary Page 15 of 57 TASK filter: All Activities

Remaining Work Milestone © Oracle Corporation


DUALIZATION OF MAHDAH - AL RAWDAH ROAD PROJECT Classic Schedule Layout 25-May-14 16:51

Activity ID Activity Name Original Start Finish Total Float Critical 2014 2015 2016
Duration
S Oct N D J F M Apr M J Jul A S Oct N D Jan F M Apr M J Jul A S Oct N D J F M Apr M J
CZ1CU1450 20.03 CONSTRUCTION OF WALLS & TOP SLABS 43 04-May-14 23-Jun-14 93 20.03 CONSTRUCTION OF WALLS & TOP SLABS
CZ1CU1460 20.03 CONSTRUCTION OF INLET & OUTLET 10 24-Jun-14 05-Jul-14 115 20.03 CONSTRUCTION OF INLET & OUTLET
CZ1CU1470 20.03 WATER PROOFING WORKS 10 30-Jun-14 10-Jul-14 115 20.03 WATER PROOFING WORKS
21.03 CELL BOX C
CULVERT @ CH 10+680 - (2.0X1.5) 68 30-Mar-14 17-Jun-14 105 17-Jun-14, 21.03 CELL BOX CULVERT @ CH 10+680 - (2.0X1.5)
CZ1CU1480 21.03 EXCAVATION 4 30-Mar-14 02-Apr-14 12 21.03 EXCAVATION
CZ1CU1490 21.03 BLINDING CONCRETE 4 03-Apr-14 07-Apr-14 29 21.03 BLINDING CONCRETE
CZ1CU1500 21.03 CONSTRUCTION OF BASE SLABS 22 08-Apr-14 03-May-14 104 21.03 CONSTRUCTION OF BASE SLABS
CZ1CU1510 21.03 CONSTRUCTION OF WALLS & TOP SLABS 27 04-May-14 04-Jun-14 104 21.03 CONSTRUCTION OF WALLS & TOP SLABS
CZ1CU1520 21.03 CONSTRUCTION OF INLET & OUTLET 6 05-Jun-14 11-Jun-14 104 21.03 CONSTRUCTION OF INLET & OUTLET
CZ1CU1530 21.03 WATER PROOFING WORKS 7 10-Jun-14 17-Jun-14 105 21.03 WATER PROOFING WORKS
22.02 CELL BOX C
CULVERT @ CH 11+790 - (2.0X1.5) 79 03-Apr-14 05-Jul-14 90 05-Jul-14, 22.02 CELL BOX CULVERT @ CH 11+790 - (2.0X1.5)
CZ1CU1540 22.02 EXCAVATION 5 03-Apr-14 08-Apr-14 12 22.02 EXCAVATION
CZ1CU1550 22.02 BLINDING CONCRETE 3 09-Apr-14 12-Apr-14 28 22.02 BLINDING CONCRETE
CZ1CU1560 22.02 CONSTRUCTION OF BASE SLABS 23 13-Apr-14 08-May-14 90 22.02 CONSTRUCTION OF BASE SLABS
CZ1CU1570 22.02 CONSTRUCTION OF WALLS & TOP SLABS 34 10-May-14 18-Jun-14 90 22.02 CONSTRUCTION OF WALLS & TOP SLABS
CZ1CU1580 22.02 CONSTRUCTION OF INLET & OUTLET 8 19-Jun-14 28-Jun-14 90 22.02 CONSTRUCTION OF INLET & OUTLET
CZ1CU1590 22.02 WATER PROOFING WORKS 9 25-Jun-14 05-Jul-14 90 22.02 WATER PROOFING WORKS
23.03 CELL BOX C
CULVERT @ CH 12+615 - (2.0X1.5) 87 09-Apr-14 20-Jul-14 107 20-Jul-14, 23.03 CELL BOX CULVERT @ CH 12+615 - (2.0X1.5)
CZ1CU1600 23.03 EXCAVATION 4 09-Apr-14 13-Apr-14 12 23.03 EXCAVATION
CZ1CU1610 23.03 BLINDING CONCRETE 4 14-Apr-14 17-Apr-14 27 23.03 BLINDING CONCRETE
CZ1CU1620 23.03 CONSTRUCTION OF BASE SLABS 26 19-Apr-14 18-May-14 56 23.03 CONSTRUCTION OF BASE SLABS
CZ1CU1630 23.03 CONSTRUCTION OF WALLS & TOP SLABS 43 19-May-14 08-Jul-14 56 23.03 CONSTRUCTION OF WALLS & TOP SLABS
CZ1CU1640 23.03 CONSTRUCTION OF INLET & OUTLET 5 09-Jul-14 14-Jul-14 107 23.03 CONSTRUCTION OF INLET & OUTLET
CZ1CU1650 23.03 WATER PROOFING WORKS 5 15-Jul-14 20-Jul-14 107 23.03 WATER PROOFING WORKS
24.06 CELL BOX C
CULVERT @ CH 13+150 - (2.0X1.5) 120 14-Apr-14 06-Sep-14 100 06-Sep-14, 24.06 CELL BOX CULVERT @ CH 13+150 - (2.0X1.5)
CZ1CU1660 24.06 EXCAVATION 6 14-Apr-14 20-Apr-14 12 24.06 EXCAVATION
CZ1CU1670 24.06 BLINDING CONCRETE 4 21-Apr-14 24-Apr-14 25 24.06 BLINDING CONCRETE
CZ1CU1680 24.06 CONSTRUCTION OF BASE SLABS 38 26-Apr-14 09-Jun-14 29 24.06 CONSTRUCTION OF BASE SLABS
CZ1CU1690 24.06 CONSTRUCTION OF WALLS & TOP SLABS 57 10-Jun-14 19-Aug-14 29 24.06 CONSTRUCTION OF WALLS & TOP SLABS
CZ1CU1700 24.06 CONSTRUCTION OF INLET & OUTLET 9 20-Aug-14 30-Aug-14 100 24.06 CONSTRUCTION OF INLET & OUTLET
CZ1CU1710 24.06 WATER PROOFING WORKS 10 26-Aug-14 06-Sep-14 100 24.06 WATER PROOFING WORKS
32.06 CELL BOX C
CULVERT @ CH 15+880 - (1.5X1.5) 120 21-Apr-14 13-Sep-14 94 13-Sep-14, 32.06 CELL BOX CULVERT @ CH 15+880 - (1.5X1.5)
CZ1CU1720 32.06 EXCAVATION 6 21-Apr-14 27-Apr-14 12 32.06 EXCAVATION
CZ1CU1730 32.06 BLINDING CONCRETE 4 28-Apr-14 01-May-14 23 32.06 BLINDING CONCRETE
CZ1CU1740 32.06 CONSTRUCTION OF BASE SLABS 38 03-May-14 16-Jun-14 23 32.06 CONSTRUCTION OF BASE SLABS
CZ1CU1750 32.06 CONSTRUCTION OF WALLS & TOP SLABS 57 17-Jun-14 26-Aug-14 23 32.06 CONSTRUCTION OF WALLS & TOP SLABS
CZ1CU1760 32.06 CONSTRUCTION OF INLET & OUTLET 9 27-Aug-14 06-Sep-14 94 32.06 CONSTRUCTION OF INLET & OUTLET
CZ1CU1770 32.06 WATER PROOFING WORKS 10 02-Sep-14 13-Sep-14 94 32.06 WATER PROOFING WORKS
34.51 CELL BOX C
CULVERT @ CH 16+725 - (3.0X2.0) 235 28-Apr-14 09-Feb-15 123 09-Feb-15, 34.51 CELL BOX CULVERT @ CH 16+725 - (3.0X2.0)
CZ1CU1780 34.51 EXCAVATION 25 28-Apr-14 26-May-14 12 34.51 EXCAVATION
CZ1CU1790 34.51 BLINDING CONCRETE 14 28-May-14 12-Jun-14 31 34.51 BLINDING CONCRETE
CZ1CU1800 34.51 CONSTRUCTION OF BASE SLABS 77 14-Jun-14 15-Sep-14 96 34.51 CONSTRUCTION OF BASE SLABS
CZ1CU1810 34.51 CONSTRUCTION OF WALLS & TOP SLABS 95 16-Sep-14 12-Jan-15 96 34.51 CONSTRUCTION OF WALLS & TOP SLABS
CZ1CU1820 34.51 CONSTRUCTION OF INLET & OUTLET 22 13-Jan-15 07-Feb-15 123 34.51 CONSTRUCTION OF INLET & OUTLET
CZ1CU1830 34.51 WATER PROOFING WORKS 22 15-Jan-15 09-Feb-15 123 34.51 WATER PROOFING WORKS
35.24 CELL BOX C
CULVERT @ CH 16+992 - (3.0X2.0) 152 28-May-14 02-Dec-14 91 02-Dec-14, 35.24 CELL BOX CULVERT @ CH 16+992 - (3.0X2.0)
CZ1CU1840 35.24 EXCAVATION 14 28-May-14 12-Jun-14 12 35.24 EXCAVATION
CZ1CU1850 35.24 BLINDING CONCRETE 7 14-Jun-14 21-Jun-14 31 35.24 BLINDING CONCRETE
CZ1CU1860 35.24 CONSTRUCTION OF BASE SLABS 49 22-Jun-14 21-Aug-14 91 35.24 CONSTRUCTION OF BASE SLABS
CZ1CU1870 35.24 CONSTRUCTION OF WALLS & TOP SLABS 69 23-Aug-14 15-Nov-14 91 35.24 CONSTRUCTION OF WALLS & TOP SLABS
CZ1CU1880 35.24 CONSTRUCTION OF INLET & OUTLET 8 16-Nov-14 26-Nov-14 91 35.24 CONSTRUCTION OF INLET & OUTLET

Actual Work Critical Remaining Work Summary Page 16 of 57 TASK filter: All Activities

Remaining Work Milestone © Oracle Corporation


DUALIZATION OF MAHDAH - AL RAWDAH ROAD PROJECT Classic Schedule Layout 25-May-14 16:51

Activity ID Activity Name Original Start Finish Total Float Critical 2014 2015 2016
Duration
S Oct N D J F M Apr M J Jul A S Oct N D Jan F M Apr M J Jul A S Oct N D J F M Apr M J
CZ1CU1890 35.24 WATER PROOFING WORKS 11 18-Nov-14 02-Dec-14 91 35.24 WATER PROOFING WORKS
36.39 CELL BOX C
CULVERT @ CH 17+210 - (3.0X2.0) 185 14-Jun-14 27-Jan-15 134 27-Jan-15, 36.39 CELL BOX CULVERT @ CH 17+210 - (3.0X2.0)
CZ1CU1900 36.39 EXCAVATION 20 14-Jun-14 06-Jul-14 12 36.39 EXCAVATION
CZ1CU1910 36.39 BLINDING CONCRETE 12 07-Jul-14 20-Jul-14 134 36.39 BLINDING CONCRETE
CZ1CU1920 36.39 CONSTRUCTION OF BASE SLABS 47 21-Jul-14 17-Sep-14 134 36.39 CONSTRUCTION OF BASE SLABS
CZ1CU1930 36.39 CONSTRUCTION OF WALLS & TOP SLABS 86 18-Sep-14 04-Jan-15 134 36.39 CONSTRUCTION OF WALLS & TOP SLABS
CZ1CU1940 36.39 CONSTRUCTION OF INLET & OUTLET 15 05-Jan-15 21-Jan-15 134 36.39 CONSTRUCTION OF INLET & OUTLET
CZ1CU1950 36.39 WATER PROOFING WORKS 15 11-Jan-15 27-Jan-15 134 36.39 WATER PROOFING WORKS
37.06 CELL BOX C
CULVERT @ CH 17+445 - (3.0X2.0) 115 07-Jul-14 29-Nov-14 94 29-Nov-14, 37.06 CELL BOX CULVERT @ CH 17+445 - (3.0X2.0)
CZ1CU1960 37.06 EXCAVATION 6 07-Jul-14 13-Jul-14 12 37.06 EXCAVATION
CZ1CU1970 37.06 BLINDING CONCRETE 4 14-Jul-14 17-Jul-14 12 37.06 BLINDING CONCRETE
CZ1CU1980 37.06 CONSTRUCTION OF BASE SLABS 36 19-Jul-14 02-Sep-14 12 37.06 CONSTRUCTION OF BASE SLABS
CZ1CU1990 37.06 CONSTRUCTION OF WALLS & TOP SLABS 57 03-Sep-14 12-Nov-14 12 37.06 CONSTRUCTION OF WALLS & TOP SLABS
CZ1CU2000 37.06 CONSTRUCTION OF INLET & OUTLET 8 13-Nov-14 24-Nov-14 93 37.06 CONSTRUCTION OF INLET & OUTLET
CZ1CU2010 37.06 WATER PROOFING WORKS 7 19-Nov-14 29-Nov-14 94 37.06 WATER PROOFING WORKS
41.06 CELL BOX C
CULVERT @ CH 18+600 - (2.0X1.5) 115 14-Jul-14 06-Dec-14 88 06-Dec-14, 41.06 CELL BOX CULVERT @ CH 18+600 - (2.0X1.5)
CZ1CU2020 41.06 EXCAVATION 6 14-Jul-14 20-Jul-14 14 41.06 EXCAVATION
CZ1CU2030 41.06 BLINDING CONCRETE 4 21-Jul-14 26-Jul-14 22 41.06 BLINDING CONCRETE
CZ1CU2040 41.06 CONSTRUCTION OF BASE SLABS 36 27-Jul-14 09-Sep-14 88 41.06 CONSTRUCTION OF BASE SLABS
CZ1CU2050 41.06 CONSTRUCTION OF WALLS & TOP SLABS 57 10-Sep-14 19-Nov-14 88 41.06 CONSTRUCTION OF WALLS & TOP SLABS
CZ1CU2060 41.06 CONSTRUCTION OF INLET & OUTLET 7 20-Nov-14 30-Nov-14 88 41.06 CONSTRUCTION OF INLET & OUTLET
CZ1CU2070 41.06 WATER PROOFING WORKS 9 26-Nov-14 06-Dec-14 88 41.06 WATER PROOFING WORKS
42.14 CELL BOX C
CULVERT @ CH 18+975 - (3.0X1.5) 139 21-Jul-14 11-Jan-15 148 11-Jan-15, 42.14 CELL BOX CULVERT @ CH 18+975 - (3.0X1.5)
CZ1CU2080 42.14 EXCAVATION 9 21-Jul-14 04-Aug-14 14 42.14 EXCAVATION
CZ1CU2090 42.14 BLINDING CONCRETE 6 05-Aug-14 11-Aug-14 148 42.14 BLINDING CONCRETE
CZ1CU2100 42.14 CONSTRUCTION OF BASE SLABS 39 12-Aug-14 25-Sep-14 148 42.14 CONSTRUCTION OF BASE SLABS
CZ1CU2110 42.14 CONSTRUCTION OF WALLS & TOP SLABS 72 27-Sep-14 25-Dec-14 148 42.14 CONSTRUCTION OF WALLS & TOP SLABS
CZ1CU2120 42.14 CONSTRUCTION OF INLET & OUTLET 8 27-Dec-14 05-Jan-15 148 42.14 CONSTRUCTION OF INLET & OUTLET
CZ1CU2130 42.14 WATER PROOFING WORKS 8 01-Jan-15 11-Jan-15 148 42.14 WATER PROOFING WORKS
43.02 CELL BOX C
CULVERT @ CH 19+280 - (2.0X1.5) 74 05-Aug-14 03-Nov-14 114 03-Nov-14, 43.02 CELL BOX CULVERT @ CH 19+280 - (2.0X1.5)
CZ1CU2140 43.02 EXCAVATION 3 05-Aug-14 07-Aug-14 14 43.02 EXCAVATION
CZ1CU2150 43.02 BLINDING CONCRETE 3 09-Aug-14 11-Aug-14 14 43.02 BLINDING CONCRETE
CZ1CU2160 43.02 CONSTRUCTION OF BASE SLABS 22 12-Aug-14 06-Sep-14 14 43.02 CONSTRUCTION OF BASE SLABS
CZ1CU2170 43.02 CONSTRUCTION OF WALLS & TOP SLABS 33 07-Sep-14 18-Oct-14 14 43.02 CONSTRUCTION OF WALLS & TOP SLABS
CZ1CU2180 43.02 CONSTRUCTION OF INLET & OUTLET 8 19-Oct-14 28-Oct-14 114 43.02 CONSTRUCTION OF INLET & OUTLET
CZ1CU2190 43.02 WATER PROOFING WORKS 11 21-Oct-14 03-Nov-14 114 43.02 WATER PROOFING WORKS
44.02 CELL BOX C
CULVERT @ CH 19+540 - (2.0X1.5) 74 09-Aug-14 06-Nov-14 111 06-Nov-14, 44.02 CELL BOX CULVERT @ CH 19+540 - (2.0X1.5)
CZ1CU2200 44.02 EXCAVATION 4 09-Aug-14 12-Aug-14 24 44.02 EXCAVATION
CZ1CU2210 44.02 BLINDING CONCRETE 3 13-Aug-14 16-Aug-14 24 44.02 BLINDING CONCRETE
CZ1CU2220 44.02 CONSTRUCTION OF BASE SLABS 22 17-Aug-14 10-Sep-14 27 44.02 CONSTRUCTION OF BASE SLABS
CZ1CU2230 44.02 CONSTRUCTION OF WALLS & TOP SLABS 32 11-Sep-14 21-Oct-14 29 44.02 CONSTRUCTION OF WALLS & TOP SLABS
CZ1CU2240 44.02 CONSTRUCTION OF INLET & OUTLET 8 22-Oct-14 01-Nov-14 111 44.02 CONSTRUCTION OF INLET & OUTLET
CZ1CU2250 44.02 WATER PROOFING WORKS 9 28-Oct-14 06-Nov-14 111 44.02 WATER PROOFING WORKS
45.03 CELL BOX C
CULVERT @ CH 19+940 - (2.0X1.5) 74 13-Aug-14 11-Nov-14 107 11-Nov-14, 45.03 CELL BOX CULVERT @ CH 19+940 - (2.0X1.5)
CZ1CU2260 45.03 EXCAVATION 3 13-Aug-14 16-Aug-14 24 45.03 EXCAVATION
CZ1CU2270 45.03 BLINDING CONCRETE 3 17-Aug-14 19-Aug-14 24 45.03 BLINDING CONCRETE
CZ1CU2280 45.03 CONSTRUCTION OF BASE SLABS 22 20-Aug-14 14-Sep-14 24 45.03 CONSTRUCTION OF BASE SLABS
CZ1CU2290 45.03 CONSTRUCTION OF WALLS & TOP SLABS 31 15-Sep-14 23-Oct-14 27 45.03 CONSTRUCTION OF WALLS & TOP SLABS
CZ1CU2300 45.03 CONSTRUCTION OF INLET & OUTLET 10 26-Oct-14 05-Nov-14 107 45.03 CONSTRUCTION OF INLET & OUTLET
CZ1CU2310 45.03 WATER PROOFING WORKS 11 30-Oct-14 11-Nov-14 107 45.03 WATER PROOFING WORKS
SINGLE CELL CULVERTS
CU - 24NOS 310 22-Mar-14 31-Mar-15 19 31-Mar-15, SINGLE CELL CULVERTS - 24NOS
PRE CASTING FOR CULVERTS INCLUDING WATER P/F. 177 22-Mar-14 22-Oct-14 41 22-Oct-14, PRE CASTING FOR CULVERTS INCLUDING WATER P/F.

Actual Work Critical Remaining Work Summary Page 17 of 57 TASK filter: All Activities

Remaining Work Milestone © Oracle Corporation


DUALIZATION OF MAHDAH - AL RAWDAH ROAD PROJECT Classic Schedule Layout 25-May-14 16:51

Activity ID Activity Name Original Start Finish Total Float Critical 2014 2015 2016
Duration
S Oct N D J F M Apr M J Jul A S Oct N D Jan F M Apr M J Jul A S Oct N D J F M Apr M J
CZ1CU2320 PART 1 PRECAST FOR CULVERTS INCLUDING WA 22 22-Mar-14 15-Apr-14 12 PART 1 PRECAST FOR CULVERTS INCLUDING WATER P/F. NOS 1,2,3
CZ1CU2330 PART 1 PRECAST FOR CULVERTS INCLUDING WA 22 17-Apr-14 12-May-14 31 PART 1 PRECAST FOR CULVERTS INCLUDING WATER P/F. NOS 4,5,6
CZ1CU2340 PART 1 PRECAST FOR CULVERTS INCLUDING WA 22 13-May-14 08-Jun-14 31 PART 1 PRECAST FOR CULVERTS INCLUDING WATER P/F. NOS 7,8,9
CZ1CU2350 PART 1 PRECAST FOR CULVERTS INCLUDING WA 22 10-Jun-14 05-Jul-14 41 PART 1 PRECAST FOR CULVERTS INCLUDING WATER P/F. NOS 10,11,12
CZ1CU2360 PART 1 PRECAST FOR CULVERTS INCLUDING WA 22 06-Jul-14 04-Aug-14 41 PART 1 PRECAST FOR CULVERTS INCLUDING WATER P/F. NOS 13,14,15
CZ1CU2370 PART 1 PRECAST FOR CULVERTS INCLUDING WA 22 05-Aug-14 30-Aug-14 41 PART 1 PRECAST FOR CULVERTS INCLUDING WATER P/F. NOS 16,17,18
CZ1CU2380 PART 1 PRECAST FOR CULVERTS INCLUDING WA 22 31-Aug-14 24-Sep-14 41 PART 1 PRECAST FOR CULVERTS INCLUDING WATER P/F. NOS 19,20,21
CZ1CU2390 PART 1 PRECAST FOR CULVERTS INCLUDING WA 21 25-Sep-14 22-Oct-14 41 PART 1 PRECAST FOR CULVERTS INCLUDING WATER P/F. NOS 22,23
EXCAVAT ION OF
O CULVERTS 297 25-Mar-14 19-Mar-15 29 19-Mar-15, EXCAVATION OF CULVERTS
CZ1CU2400 PART 1 EXCAVATION OF CULVERTS NOS 1,2,3 38 25-Mar-14 07-May-14 12 PART 1 EXCAVATION OF CULVERTS NOS 1,2,3
CZ1CU2410 PART 1 EXCAVATION OF CULVERTS NOS 4,5,6 37 08-May-14 21-Jun-14 29 PART 1 EXCAVATION OF CULVERTS NOS 4,5,6
CZ1CU2420 PART 1 EXCAVATION OF CULVERTS NOS 7,8,9 37 22-Jun-14 07-Aug-14 29 PART 1 EXCAVATION OF CULVERTS NOS 7,8,9
CZ1CU2430 PART 1 EXCAVATION OF CULVERTS NOS 10,11,12 37 09-Aug-14 20-Sep-14 29 PART 1 EXCAVATION OF CULVERTS NOS 10,11,12
CZ1CU2440 PART 1 EXCAVATION OF CULVERTS NOS 13,14,15 37 21-Sep-14 06-Nov-14 29 PART 1 EXCAVATION OF CULVERTS NOS 13,14,15
CZ1CU2450 PART 1 EXCAVATION OF CULVERTS NOS 16,17,18 37 08-Nov-14 22-Dec-14 29 PART 1 EXCAVATION OF CULVERTS NOS 16,17,18
CZ1CU2460 PART 1 EXCAVATION OF CULVERTS NOS 19,20,21 37 23-Dec-14 04-Feb-15 29 PART 1 EXCAVATION OF CULVERTS NOS 19,20,21
CZ1CU2470 PART 1 EXCAVATION OF CULVERTS NOS 22,23 37 05-Feb-15 19-Mar-15 29 PART 1 EXCAVATION OF CULVERTS NOS 22,23
BLINDING FOR CULVERTS 296 27-Mar-14 21-Mar-15 28 21-Mar-15, BLINDING FOR CULVERTS
CZ1CU2480 PART 1 BLINDING FOR CULVERTS NOS 1,2,3 37 27-Mar-14 08-May-14 27 PART 1 BLINDING FOR CULVERTS NOS 1,2,3
CZ1CU2490 PART 1 BLINDING FOR CULVERTS NOS 4,5,6 37 10-May-14 22-Jun-14 28 PART 1 BLINDING FOR CULVERTS NOS 4,5,6
CZ1CU2500 PART 1 BLINDING FOR CULVERTS NOS 7,8,9 37 23-Jun-14 09-Aug-14 28 PART 1 BLINDING FOR CULVERTS NOS 7,8,9
CZ1CU2510 PART 1 BLINDING FOR CULVERTS NOS 10,11,12 37 10-Aug-14 21-Sep-14 28 PART 1 BLINDING FOR CULVERTS NOS 10,11,12
CZ1CU2520 PART 1 BLINDING FOR CULVERTS NOS 13,14,15 37 22-Sep-14 08-Nov-14 28 PART 1 BLINDING FOR CULVERTS NOS 13,14,15
CZ1CU2530 PART 1 BLINDING FOR CULVERTS NOS 16,17,18 37 09-Nov-14 23-Dec-14 28 PART 1 BLINDING FOR CULVERTS NOS 16,17,18
CZ1CU2540 PART 1 BLINDING FOR CULVERTS NOS 19,20,21 37 24-Dec-14 05-Feb-15 28 PART 1 BLINDING FOR CULVERTS NOS 19,20,21
CZ1CU2550 PART 1 BLINDING FOR CULVERTS NOS 22,23 37 07-Feb-15 21-Mar-15 28 PART 1 BLINDING FOR CULVERTS NOS 22,23
ERECTION OF CULVERTS 281 15-Apr-14 22-Mar-15 27 22-Mar-15, ERECTION OF CULVERTS
CZ1CU2560 PART 1 ERECTION OF CULVERTS NOS 1,2,3 36 15-Apr-14 26-May-14 12 PART 1 ERECTION OF CULVERTS NOS 1,2,3
CZ1CU2570 PART 1 ERECTION OF CULVERTS NOS 4,5,6 35 28-May-14 07-Jul-14 27 PART 1 ERECTION OF CULVERTS NOS 4,5,6
CZ1CU2580 PART 1 ERECTION OF CULVERTS NOS 7,8,9 35 08-Jul-14 21-Aug-14 27 PART 1 ERECTION OF CULVERTS NOS 7,8,9
CZ1CU2590 PART 1 ERECTION OF CULVERTS NOS 10,11,12 35 23-Aug-14 01-Oct-14 27 PART 1 ERECTION OF CULVERTS NOS 10,11,12
CZ1CU2600 PART 1 ERECTION OF CULVERTS NOS 13,14,15 35 02-Oct-14 16-Nov-14 27 PART 1 ERECTION OF CULVERTS NOS 13,14,15
CZ1CU2610 PART 1 ERECTION OF CULVERTS NOS 16,17,18 35 17-Nov-14 29-Dec-14 27 PART 1 ERECTION OF CULVERTS NOS 16,17,18
CZ1CU2620 PART 1 ERECTION OF CULVERTS NOS 19,20,21 35 30-Dec-14 09-Feb-15 27 PART 1 ERECTION OF CULVERTS NOS 19,20,21
CZ1CU2630 PART 1 ERECTION OF CULVERTS NOS 22,23 35 10-Feb-15 22-Mar-15 27 PART 1 ERECTION OF CULVERTS NOS 22,23
END PORTION CASTING OF CULVERTS 291 03-Apr-14 22-Mar-15 27 22-Mar-15, END PORTION CASTING OF CULVERTS
CZ1CU2640 PART 1 END PORTION CASTING OF CULVERTS N 37 03-Apr-14 15-May-14 27 PART 1 END PORTION CASTING OF CULVERTS NOS 1,2,3
CZ1CU2650 PART 1 END PORTION CASTING OF CULVERTS N 37 17-May-14 29-Jun-14 27 PART 1 END PORTION CASTING OF CULVERTS NOS 4,5,6
CZ1CU2660 PART 1 END PORTION CASTING OF CULVERTS N 37 30-Jun-14 16-Aug-14 27 PART 1 END PORTION CASTING OF CULVERTS NOS 7,8,9
CZ1CU2670 PART 1 END PORTION CASTING OF CULVERTS N 37 17-Aug-14 28-Sep-14 27 PART 1 END PORTION CASTING OF CULVERTS NOS 10,11,12
CZ1CU2680 PART 1 END PORTION CASTING OF CULVERTS N 37 29-Sep-14 15-Nov-14 27 PART 1 END PORTION CASTING OF CULVERTS NOS 13,14,15
CZ1CU2690 PART 1 END PORTION CASTING OF CULVERTS N 36 16-Nov-14 29-Dec-14 27 PART 1 END PORTION CASTING OF CULVERTS NOS 16,17,18
CZ1CU2700 PART 1 END PORTION CASTING OF CULVERTS N 36 30-Dec-14 10-Feb-15 27 PART 1 END PORTION CASTING OF CULVERTS NOS 19,20,21
CZ1CU2710 PART 1 END PORTION CASTING OF CULVERTS N 34 11-Feb-15 22-Mar-15 27 PART 1 END PORTION CASTING OF CULVERTS NOS 22,23
CONSTRUCTIO OF INLET & OUT LET
CONSTRUCTION 288 16-Apr-14 31-Mar-15 19 31-Mar-15, CONSTRUCTION OF INLET & OUT LET
CZ1CU2720 PART 1 CONSTRUCTION OF INLET & OUT LET NO 35 16-Apr-14 26-May-14 12 PART 1 CONSTRUCTION OF INLET & OUT LET NOS 1,2,3
CZ1CU2730 PART 1 CONSTRUCTION OF INLET & OUT LET NO 35 28-May-14 07-Jul-14 19 PART 1 CONSTRUCTION OF INLET & OUT LET NOS 4,5,6
CZ1CU2740 PART 1 CONSTRUCTION OF INLET & OUT LET NO 36 08-Jul-14 23-Aug-14 19 PART 1 CONSTRUCTION OF INLET & OUT LET NOS 7,8,9
CZ1CU2750 PART 1 CONSTRUCTION OF INLET & OUT LET NO 36 24-Aug-14 07-Oct-14 19 PART 1 CONSTRUCTION OF INLET & OUT LET NOS 10,11,12
CZ1CU2760 PART 1 CONSTRUCTION OF INLET & OUT LET NO 36 08-Oct-14 19-Nov-14 19 PART 1 CONSTRUCTION OF INLET & OUT LET NOS 13,14,15
CZ1CU2770 PART 1 CONSTRUCTION OF INLET & OUT LET NO 36 20-Nov-14 04-Jan-15 19 PART 1 CONSTRUCTION OF INLET & OUT LET NOS 16,17,18

Actual Work Critical Remaining Work Summary Page 18 of 57 TASK filter: All Activities

Remaining Work Milestone © Oracle Corporation


DUALIZATION OF MAHDAH - AL RAWDAH ROAD PROJECT Classic Schedule Layout 25-May-14 16:51

Activity ID Activity Name Original Start Finish Total Float Critical 2014 2015 2016
Duration
S Oct N D J F M Apr M J Jul A S Oct N D Jan F M Apr M J Jul A S Oct N D J F M Apr M J
CZ1CU2780 PART 1 CONSTRUCTION OF INLET & OUT LET NO 37 05-Jan-15 16-Feb-15 19 PART 1 CONSTRUCTION OF INLET & OUT LET NOS 19,20,21
CZ1CU2790 PART 1 CONSTRUCTION OF INLET & OUT LET NO 37 17-Feb-15 31-Mar-15 19 PART 1 CONSTRUCTION OF INLET & OUT LET NOS 22,23
INTERCHANGE 11+630
11+6 230 04-Mar-14 09-Dec-14 25 09-Dec-14, INTERCHANGE 11+630
INT. 11+630 GEOTECHNICAL
GEOT INVESTIGATION 40 04-Mar-14 19-Apr-14 43 19-Apr-14, INT. 11+630 GEOTECHNICAL INVEST IGATION
CZ1IN1000 INT. 11+630 FINALIZATION OF SUB CONTRACTOR 7 04-Mar-14 11-Mar-14 27 INT. 11+630 FINALIZATION OF SUB CONTRACTOR
CZ1IN1010 INT. 11+630 MOBILIZATION 7 12-Mar-14 19-Mar-14 27 INT. 11+630 MOBILIZATION
CZ1IN1020 INT. 11+630 SOIL INVESTIGATION 14 20-Mar-14 05-Apr-14 27 INT. 11+630 SOIL INVESTIGATION
CZ1IN1030 INT. 11+630 ANALYSIS AND SUBMISSION 6 06-Apr-14 12-Apr-14 27 INT. 11+630 ANALYSIS AND SUBMISSION
CZ1IN1040 INT. 11+630 APPROVAL 6 13-Apr-14 19-Apr-14 43 INT. 11+630 APPROVAL
INT. 11+630 CONSTRUCTION
CONS 201 07-Apr-14 09-Dec-14 25 09-Dec-14, INT. 11+630 CONSTRUCTION
CZ1IN1050 INT. 11+630 SURVEY & SETTING OUT 3 07-Apr-14 09-Apr-14 25 INT. 11+630 SURVEY & SETTING OUT
CZ1IN1060 INT. 11+630 CLEARING AND GRUBBING 4 10-Apr-14 14-Apr-14 25 INT. 11+630 CLEARING AND GRUBBING
CZ1IN1070 INT. 11+630 STRUCTURAL EXACAVATION FOR FO 17 15-Apr-14 04-May-14 25 INT. 11+630 STRUCTURAL EXACAVATION FOR FOUNDATION
CZ1IN1080 INT. 11+630 PCC FOR FOUNDATION 13 26-Apr-14 10-May-14 25 INT. 11+630 PCC FOR FOUNDATION
CZ1IN1090 INT. 11+630 CONCRETING FOR ABUTMENT (AB1, 20 01-May-14 24-May-14 25 INT. 11+630 CONCRETING FOR ABUTMENT (AB1, AB2) FOUNDATIONS
CZ1IN1100 INT. 11+630 CONCRETING FOR ABUTMENT (AB1, 29 25-May-14 28-Jun-14 37 INT. 11+630 CONCRETING FOR ABUTMENT (AB1, AB2) WALL
CZ1IN1110 INT. 11+630 CONCRETING FOR PIER FOUNDATIO 12 14-May-14 28-May-14 25 INT. 11+630 CONCRETING FOR PIER FOUNDATION
CZ1IN1120 INT. 11+630 CONCRETING FOR PIERS 20 29-May-14 21-Jun-14 25 INT. 11+630 CONCRETING FOR PIERS
CZ1IN1130 INT. 11+630 STAGING FOR BOX GIRDERS 21 18-Jun-14 12-Jul-14 25 INT. 11+630 STAGING FOR BOX GIRDERS
CZ1IN1140 INT. 11+630 FIXING OF BEARING 9 13-Jul-14 22-Jul-14 25 INT. 11+630 FIXING OF BEARING
CZ1IN1150 INT. 11+630 SOFFIT FORMWORK ALONG WITH W 12 15-Jul-14 02-Aug-14 25 INT. 11+630 SOFFIT FORMWORK ALONG WITH WINGS OF BOX GIRDER
CZ1IN1160 INT. 11+630 REINFORCEMENT FIXING FOR SOFF 15 03-Aug-14 19-Aug-14 25 INT. 11+630 REINFORCEMENT FIXING FOR SOFFIT & WEB (STIRUPPS)
CZ1IN1170 INT. 11+630 POST TENSIONING DUCT PROFILING 10 12-Aug-14 23-Aug-14 25 INT. 11+630 POST TENSIONING DUCT PROFILING
CZ1IN1180 INT. 11+630 CONCRETING OF SOFFIT 1 24-Aug-14 24-Aug-14 25 INT. 11+630 CONCRETING OF SOFFIT
CZ1IN1190 INT. 11+630 REINFORCEMENT FIXING FOR WEB & 7 25-Aug-14 01-Sep-14 25 INT. 11+630 REINFORCEMENT FIXING FOR WEB & DIAPHARGMS (DISTRIBUTOR)
CZ1IN1200 INT. 11+630 FORMWORK FIXING FOR WEB & DIAP 10 02-Sep-14 13-Sep-14 25 INT. 11+630 FORMWORK FIXING FOR WEB & DIAPHARGMS
CZ1IN1210 INT. 11+630 CONCRETING FOR WEB & DIAPHARG 1 14-Sep-14 14-Sep-14 25 INT. 11+630 CONCRETING FOR WEB & DIAPHARGMS
CZ1IN1220 INT. 11+630 STAGING & FORMWORK FOR DECK S 16 15-Sep-14 02-Oct-14 25 INT. 11+630 STAGING & FORMWORK FOR DECK SLAB
CZ1IN1230 INT. 11+630 REINFORCEMENT FIXING FOR DECK 10 07-Oct-14 18-Oct-14 25 INT. 11+630 REINFORCEMENT FIXING FOR DECK SLAB
CZ1IN1240 INT. 11+630 CONCRETING FOR DECK SLAB 1 19-Oct-14 19-Oct-14 25 INT. 11+630 CONCRETING FOR DECK SLAB
CZ1IN1250 INT. 11+630 THREADING OF STRANDS 10 20-Oct-14 01-Nov-14 25 INT. 11+630 THREADING OF STRANDS
CZ1IN1260 INT. 11+630 STRESSING & GROUTING 7 02-Nov-14 09-Nov-14 25 INT. 11+630 STRESSING & GROUTING
CZ1IN1270 INT. 11+630 DRAINAGE PIPE FIXING 8 10-Nov-14 18-Nov-14 41 INT. 11+630 DRAINAGE PIPE FIXING
CZ1IN1280 INT. 11+630 APPROACH SLAB 15 10-Nov-14 29-Nov-14 29 INT. 11+630 APPROACH SLAB
CZ1IN1290 INT. 11+630 EXPANSION JOINT 10 24-Nov-14 04-Dec-14 29 INT. 11+630 EXPANSION JOINT
CZ1IN1300 INT. 11+630 REMOVAL OF STAGING 15 10-Nov-14 29-Nov-14 25 INT. 11+630 REMOVAL OF STAGING
CZ1IN1310 INT. 11+630 DIRT WALL & CONCRETE BARRIER 24 10-Nov-14 09-Dec-14 25 INT. 11+630 DIRT WALL & CONCRETE BARRIER
UNDERPASSES 250 06-Apr-14 04-Feb-15 68 04-Feb-15, UNDERPASSES
UNDERPASS AT 5+095
5 173 06-Apr-14 03-Nov-14 54 03-Nov-14, UNDERPASS AT 5+095
UNP. GEOTECHNICAL
GEOTECH INVESTIGATION 25 06-Apr-14 04-May-14 54 04-May-14, UNP. GEOTECHNICAL INVESTIGATION
CZ1UN1010 UNP. 5+095 SOIL INVESTIGATION 13 06-Apr-14 20-Apr-14 54 UNP. 5+095 SOIL INVESTIGATION
CZ1UN1020 UNP. 5+095 ANALYSIS AND SUBMISSION 6 21-Apr-14 27-Apr-14 54 UNP. 5+095 ANALYSIS AND SUBMISSION
CZ1UN1030 UNP. 5+095 APPROVAL 6 28-Apr-14 04-May-14 54 UNP. 5+095 APPROVAL
UNDERPASS AT
A 5+095 CONSTRUCTION 156 26-Apr-14 03-Nov-14 54 03-Nov-14, UNDERPASS AT 5+095 CONSTRUCTION
CZ1UN1000 UNP. 5+095 SURVEY & SETTING OUT 3 26-Apr-14 28-Apr-14 54 UNP. 5+095 SURVEY & SETTING OUT
CZ1UN1300 UNP. 5+095 CLEARING AND GRUBBING 5 29-Apr-14 04-May-14 54 UNP. 5+095 CLEARING AND GRUBBING
CZ1UN1310 UNP. 5+095 EXCAVATION FOR FOUNDATION 6 05-May-14 11-May-14 54 UNP. 5+095 EXCAVATION FOR FOUNDATION
CZ1UN1320 UNP. 5+095 PCC FOR FOUNDATION 5 08-May-14 13-May-14 54 UNP. 5+095 PCC FOR FOUNDATION
CZ1UN1330 UNP. 5+095 RCC FOR FOUNDATION 39 13-May-14 28-Jun-14 54 UNP. 5+095 RCC FOR FOUNDATION
CZ1UN1340 UNP. 5+095 CONCRETING FOR WALL 48 16-Jun-14 14-Aug-14 70 UNP. 5+095 CONCRETING FOR WALL
CZ1UN1350 UNP. 5+095 STAGING FOR DECK SLAB 15 19-Jul-14 09-Aug-14 54 UNP. 5+095 STAGING FOR DECK SLAB

Actual Work Critical Remaining Work Summary Page 19 of 57 TASK filter: All Activities

Remaining Work Milestone © Oracle Corporation


DUALIZATION OF MAHDAH - AL RAWDAH ROAD PROJECT Classic Schedule Layout 25-May-14 16:51

Activity ID Activity Name Original Start Finish Total Float Critical 2014 2015 2016
Duration
S Oct N D J F M Apr M J Jul A S Oct N D Jan F M Apr M J Jul A S Oct N D J F M Apr M J
CZ1UN1360 UNP. 5+095 FORMWORK & REINFORCEMENT WO 25 05-Aug-14 02-Sep-14 54 UNP. 5+095 FORMWORK & REINFORCEMENT WORK FOR DECK SLAB
CZ1UN1370 UNP. 5+095 CONCRETING FOR DECK SLAB 9 25-Aug-14 03-Sep-14 54 UNP. 5+095 CONCRETING FOR DECK SLAB
CZ1UN1380 UNP. 5+095 DESHUTTERING FOR DECK SLAB 6 30-Sep-14 09-Oct-14 54 UNP. 5+095 DESHUTTERING FOR DECK SLAB
CZ1UN1390 UNP. 5+095 PRECAST FOR MSER WALL PANELS P 30 29-Jun-14 06-Aug-14 69 UNP. 5+095 PRECAST FOR MSER WALL PANELS PART 1
CZ1UN1400 UNP. 5+095 PRECAST FOR MSER WALL PANELS P 30 07-Aug-14 10-Sep-14 69 UNP. 5+095 PRECAST FOR MSER WALL PANELS PART 2
CZ1UN1410 UNP. 5+095 EXCAVATION FOR MSER WALL PART 1 4 20-Jul-14 24-Jul-14 54 UNP. 5+095 EXCAVATION FOR MSER WALL PART 1
CZ1UN1420 UNP. 5+095 EXCAVATION FOR MSER WALL PART 2 4 26-Jul-14 02-Aug-14 56 UNP. 5+095 EXCAVATION FOR MSER WALL PART 2
CZ1UN1430 UNP. 5+095 PCC FOR MSER WALL PART 1 4 24-Jul-14 31-Jul-14 54 UNP. 5+095 PCC FOR MSER WALL PART 1
CZ1UN1440 UNP. 5+095 PCC FOR MSER WALL PART 2 3 02-Aug-14 04-Aug-14 54 UNP. 5+095 PCC FOR MSER WALL PART 2
CZ1UN1450 UNP. 5+095 FOUNDATION FOR MSER WALL PART 6 05-Aug-14 11-Aug-14 54 UNP. 5+095 FOUNDATION FOR MSER WALL PART 1
CZ1UN1460 UNP. 5+095 FOUNDATION FOR MSER WALL PART 5 12-Aug-14 17-Aug-14 90 UNP. 5+095 FOUNDATION FOR MSER WALL PART 2
CZ1UN1470 UNP. 5+095 FIXING OF MSER WALL PANELS PART 21 11-Aug-14 03-Sep-14 54 UNP. 5+095 FIXING OF MSER WALL PANELS PART 1
CZ1UN1480 UNP. 5+095 FIXING OF MSER WALL PANELS PART 21 04-Sep-14 28-Sep-14 54 UNP. 5+095 FIXING OF MSER WALL PANELS PART 2
CZ1UN1490 UNP. 5+095 APPROACH SLAB 20 11-Oct-14 03-Nov-14 54 UNP. 5+095 APPROACH SLAB
CZ1UN1500 UNP. 5+095 CONCRETE BARRIER 27 28-Aug-14 28-Sep-14 54 UNP. 5+095 CONCRETE BARRIER
CZ1UN1510 UNP. 5+095 MEDIAN WORKS 27 29-Sep-14 03-Nov-14 54 UNP. 5+095 MEDIAN WORKS
UNDERPASS AT 15+235
1 237 21-Apr-14 04-Feb-15 68 04-Feb-15, UNDERPASS AT 15+235
UNP. GEOTECHNICAL
GEOTECH INVESTIGATION 40 21-Apr-14 07-Jun-14 103 07-Jun-14, UNP. GEOTECHNICAL INVESTIGATION
CZ1UN1040 UNP. 15+235 SOIL INVESTIGATION 20 21-Apr-14 13-May-14 103 UNP. 15+235 SOIL INVESTIGATION
CZ1UN1050 UNP. 15+235 ANALYSIS AND SUBMISSION 10 14-May-14 25-May-14 103 UNP. 15+235 ANALYSIS AND SUBMISSION
CZ1UN1060 UNP. 15+235 APPROVAL 10 26-May-14 07-Jun-14 103 UNP. 15+235 APPROVAL
UNDERPASS AT
A 15+235 CONSTRUCTION 162 19-Jul-14 04-Feb-15 68 04-Feb-15, UNDERPASS AT 15+235 CONSTRUCTION
CZ1UN1070 UNP. 15+235 SURVEY & SETTING OUT 3 19-Jul-14 21-Jul-14 68 UNP. 15+235 SURVEY & SETTING OUT
CZ1UN1080 UNP. 15+235 CLEARING AND GRUBBING 5 22-Jul-14 31-Jul-14 68 UNP. 15+235 CLEARING AND GRUBBING
CZ1UN1090 UNP. 15+235 EXCAVATION FOR FOUNDATION 6 02-Aug-14 07-Aug-14 68 UNP. 15+235 EXCAVATION FOR FOUNDATION
CZ1UN1100 UNP. 15+235 PCC FOR FOUNDATION 5 05-Aug-14 10-Aug-14 68 UNP. 15+235 PCC FOR FOUNDATION
CZ1UN1110 UNP. 15+235 RCC FOR FOUNDATION 39 10-Aug-14 23-Sep-14 68 UNP. 15+235 RCC FOR FOUNDATION
CZ1UN1120 UNP. 15+235 CONCRETING FOR WALL 48 11-Sep-14 10-Nov-14 110 UNP. 15+235 CONCRETING FOR WALL
CZ1UN1130 UNP. 15+235 STAGING FOR DECK SLAB 15 18-Oct-14 04-Nov-14 68 UNP. 15+235 STAGING FOR DECK SLAB
CZ1UN1140 UNP. 15+235 FORMWORK & REINFORCEMENT W 25 01-Nov-14 01-Dec-14 94 UNP. 15+235 FORMWORK & REINFORCEMENT WORK FOR DECK SLAB
CZ1UN1150 UNP. 15+235 CONCRETING FOR DECK SLAB 9 20-Nov-14 02-Dec-14 94 UNP. 15+235 CONCRETING FOR DECK SLAB
CZ1UN1160 UNP. 15+235 DESHUTTERING FOR DECK SLAB 6 29-Dec-14 05-Jan-15 94 UNP. 15+235 DESHUTTERING FOR DECK SLAB
CZ1UN1170 UNP. 15+235 PRECAST FOR MSER WALL PANELS 30 24-Sep-14 02-Nov-14 89 UNP. 15+235 PRECAST FOR MSER WALL PANELS PART 1
CZ1UN1180 UNP. 15+235 PRECAST FOR MSER WALL PANELS 30 03-Nov-14 09-Dec-14 89 UNP. 15+235 PRECAST FOR MSER WALL PANELS PART 2
CZ1UN1190 UNP. 15+235 EXCAVATION FOR MSER WALL PART 4 19-Oct-14 22-Oct-14 68 UNP. 15+235 EXCAVATION FOR MSER WALL PART 1
CZ1UN1200 UNP. 15+235 EXCAVATION FOR MSER WALL PART 4 23-Oct-14 28-Oct-14 70 UNP. 15+235 EXCAVATION FOR MSER WALL PART 2
CZ1UN1210 UNP. 15+235 PCC FOR MSER WALL PART 1 4 22-Oct-14 27-Oct-14 68 UNP. 15+235 PCC FOR MSER WALL PART 1
CZ1UN1220 UNP. 15+235 PCC FOR MSER WALL PART 2 3 28-Oct-14 30-Oct-14 68 UNP. 15+235 PCC FOR MSER WALL PART 2
CZ1UN1230 UNP. 15+235 FOUNDATION FOR MSER WALL PAR 6 01-Nov-14 06-Nov-14 68 UNP. 15+235 FOUNDATION FOR MSER WALL PART 1
CZ1UN1240 UNP. 15+235 FOUNDATION FOR MSER WALL PAR 5 08-Nov-14 12-Nov-14 110 UNP. 15+235 FOUNDATION FOR MSER WALL PART 2
CZ1UN1250 UNP. 15+235 FIXING OF MSER WALL PANELS PAR 24 06-Nov-14 06-Dec-14 68 UNP. 15+235 FIXING OF MSER WALL PANELS PART 1
CZ1UN1260 UNP. 15+235 FIXING OF MSER WALL PANELS PAR 24 07-Dec-14 04-Jan-15 68 UNP. 15+235 FIXING OF MSER WALL PANELS PART 2
CZ1UN1270 UNP. 15+235 APPROACH SLAB 20 23-Dec-14 15-Jan-15 85 UNP. 15+235 APPROACH SLAB
CZ1UN1280 UNP. 15+235 CONCRETE BARRIER 27 03-Dec-14 04-Jan-15 68 UNP. 15+235 CONCRETE BARRIER
CZ1UN1290 UNP. 15+235 MEDIAN WORKS 27 05-Jan-15 04-Feb-15 68 UNP. 15+235 MEDIAN WORKS
INCIDENTAL CONSTRUCTION
CONSTRU 593 02-Mar-14 18-Feb-16 65 18-Feb-16, INC
CONSTRUCTION OF SLOPE PROTECTION AND STABILIZATION 472 15-Mar-14 08-Oct-15 65 08-Oct-15, CONSTRUCTION OF S
WADI PROTECTION
PROTECTIO WITH RETAINING WALL 97 15-Mar-14 06-Jul-14 85 06-Jul-14, WADI PROTECTION WITH RETAINING WALL
WADI 1 [MUSAYDIRAH]
[MUSAY PROTECTION CH. KM 0+000 TO 2+000 71 15-Mar-14 05-Jun-14 106 05-Jun-14, WADI 1 [MUSAYDIRAH] PROTECTION CH. KM 0+000 TO 2+000
WADI 1A MAHDAH
MA TO RAWDAH 41 15-Mar-14 30-Apr-14 128 30-Apr-14, WADI 1A MAHDAH TO RAWDAH
CZ1FI1000 WADI 1A EXCAVATION FOR RETAINING WALL 8 15-Mar-14 23-Mar-14 85 WADI 1A EXCAVATION FOR RETAINING WALL

Actual Work Critical Remaining Work Summary Page 20 of 57 TASK filter: All Activities

Remaining Work Milestone © Oracle Corporation


DUALIZATION OF MAHDAH - AL RAWDAH ROAD PROJECT Classic Schedule Layout 25-May-14 16:51

Activity ID Activity Name Original Start Finish Total Float Critical 2014 2015 2016
Duration
S Oct N D J F M Apr M J Jul A S Oct N D Jan F M Apr M J Jul A S Oct N D J F M Apr M J
CZ1FI1010 WADI 1A BLINDING FOR RETAINING WALL 8 17-Mar-14 25-Mar-14 106 WADI 1A BLINDING FOR RETAINING WALL
CZ1FI1020 WADI 1A FOUNDATION FOR RETAINING WALL 20 18-Mar-14 09-Apr-14 106 WADI 1A FOUNDATION FOR RETAINING WALL
CZ1FI1030 WADI 1A RCC WALL FOR RETAINING WALL 30 27-Mar-14 30-Apr-14 106 WADI 1A RCC WALL FOR RETAINING WALL
CZ1FI1040 WADI 1A GABION METRESS 12 08-Apr-14 21-Apr-14 136 WADI 1A GABION METRESS
WADI 1B RAWDAH
RA TO MAHDAH 63 24-Mar-14 05-Jun-14 106 05-Jun-14, WADI 1B RAWDAH TO MAHDAH
CZ1FI1050 WADI 1B EXCAVATION FOR RETAINING WALL 8 24-Mar-14 01-Apr-14 85 WADI 1B EXCAVATION FOR RETAINING WALL
CZ1FI1060 WADI 1B BLINDING FOR RETAINING WALL 8 26-Mar-14 03-Apr-14 159 WADI 1B BLINDING FOR RETAINING WALL
CZ1FI1070 WADI 1B FOUNDATION FOR RETAINING WALL 20 10-Apr-14 03-May-14 134 WADI 1B FOUNDATION FOR RETAINING WALL
CZ1FI1080 WADI 1B RCC WALL FOR RETAINING WALL 30 01-May-14 05-Jun-14 106 WADI 1B RCC WALL FOR RETAINING WALL
CZ1FI1090 WADI 1B GABION METRESS 12 13-May-14 26-May-14 106 WADI 1B GABION METRESS
WADI 2 [SHARM]
[SHARM PROTECTION CH. KM 16+000 TO 18+000 81 02-Apr-14 06-Jul-14 85 06-Jul-14, WADI 2 [SHARM] PROTECTION CH. KM 16+000 TO 18+000
WADI 2A MAHDAH
MA TO RAWDAH 46 02-Apr-14 25-May-14 107 25-May-14, WADI 2A MAHDAH TO RAWDAH
CZ1FI1100 WADI 2A EXCAVATION FOR RETAINING WALL 8 02-Apr-14 10-Apr-14 85 WADI 2A EXCAVATION FOR RETAINING WALL
CZ1FI1110 WADI 2A BLINDING FOR RETAINING WALL 8 05-Apr-14 13-Apr-14 85 WADI 2A BLINDING FOR RETAINING WALL
CZ1FI1120 WADI 2A FOUNDATION FOR RETAINING WALL 25 06-Apr-14 04-May-14 85 WADI 2A FOUNDATION FOR RETAINING WALL
CZ1FI1130 WADI 2A RCC WALL FOR RETAINING WALL 35 15-Apr-14 25-May-14 85 WADI 2A RCC WALL FOR RETAINING WALL
CZ1FI1140 WADI 2A GABION METRESS 12 27-Apr-14 10-May-14 120 WADI 2A GABION METRESS
WADI 2B RAWDAH
RA TO MAHDAH 73 12-Apr-14 06-Jul-14 85 06-Jul-14, WADI 2B RAWDAH TO MAHDAH
CZ1FI1150 WADI 2B EXCAVATION FOR RETAINING WALL 8 12-Apr-14 20-Apr-14 148 WADI 2B EXCAVATION FOR RETAINING WALL
CZ1FI1160 WADI 2B BLINDING FOR RETAINING WALL 8 14-Apr-14 22-Apr-14 148 WADI 2B BLINDING FOR RETAINING WALL
CZ1FI1170 WADI 2B FOUNDATION FOR RETAINING WALL 25 05-May-14 03-Jun-14 113 WADI 2B FOUNDATION FOR RETAINING WALL
CZ1FI1180 WADI 2B RCC WALL FOR RETAINING WALL 35 26-May-14 06-Jul-14 85 WADI 2B RCC WALL FOR RETAINING WALL
CZ1FI1190 WADI 2B GABION METRESS 12 08-Jun-14 21-Jun-14 85 WADI 2B GABION METRESS
MORTARED STONE
STON RIP RAP PROTECTION WITH DYKE 270 27-Aug-14 15-Jul-15 69 15-Jul-15, MORTARED STONE RIP RAP PROT
CZ1FI1200 MORTARED STONE RIP RAP CH. FROM KM 0+000 27 27-Aug-14 27-Sep-14 5 MORTARED STONE RIP RAP CH. FROM KM 0+000 TO 2+000
CZ1FI1210 MORTARED STONE RIP RAP CH. FROM KM 2+000 27 28-Sep-14 02-Nov-14 5 MORTARED STONE RIP RAP CH. FROM KM 2+000 TO 4+000
CZ1FI1220 MORTARED STONE RIP RAP CH. FROM KM 4+000 27 03-Nov-14 06-Dec-14 5 MORTARED STONE RIP RAP CH. FROM KM 4+000 TO 6+000
CZ1FI1230 DYKE CONSTRUCTION CH. KM 4+000 TO 6+000 23 05-Nov-14 03-Dec-14 74 DYKE CONSTRUCTION CH. KM 4+000 TO 6+000
CZ1FI1240 MORTARED STONE RIP RAP CH. FROM KM 6+000 27 07-Dec-14 07-Jan-15 5 MORTARED STONE RIP RAP CH. FROM KM 6+000 TO 8+000
CZ1FI1250 DYKE CONSTRUCTION CH. KM 6+000 TO 8+000 25 04-Dec-14 01-Jan-15 74 DYKE CONSTRUCTION CH. KM 6+000 TO 8+000
CZ1FI1260 MORTARED STONE RIP RAP CH. FROM KM 8+000 27 08-Jan-15 08-Feb-15 5 MORTARED STONE RIP RAP CH. FROM KM 8+000 TO 10+000
CZ1FI1270 DYKE CONSTRUCTION CH. FROM KM 8+000 TO 1 26 04-Jan-15 02-Feb-15 74 DYKE CONSTRUCTION CH. FROM KM 8+000 TO 10+000
CZ1FI1280 MORTARED STONE RIP RAP CH. FROM KM 10+00 27 09-Feb-15 11-Mar-15 5 MORTARED STONE RIP RAP CH. FROM KM 10+000 TO 12+00
CZ1FI1290 DYKE CONSTRUCTION CH. FROM KM 10+000 TO 27 03-Feb-15 05-Mar-15 74 DYKE CONSTRUCTION CH. FROM KM 10+000 TO 12+000
CZ1FI1300 MORTARED STONE RIP RAP CH. FROM KM 12+00 27 12-Mar-15 12-Apr-15 69 MORTARED STONE RIP RAP CH. FROM KM 12+000 TO 14
CZ1FI1310 DYKE CONSTRUCTION CH. FROM KM 12+000 TO 27 07-Mar-15 06-Apr-15 74 DYKE CONSTRUCTION CH. FROM KM 12+000 TO 14+000
CZ1FI1320 MORTARED STONE RIP RAP CH. FROM KM 14+00 27 13-Apr-15 13-May-15 69 MORTARED STONE RIP RAP CH. FROM KM 14+000 T
CZ1FI1330 DYKE CONSTRUCTION CH. FROM KM 14+000 TO 27 07-Apr-15 07-May-15 74 DYKE CONSTRUCTION CH. FROM KM 14+000 TO 16+
CZ1FI1340 MORTARED STONE RIP RAP CH. FROM KM 16+00 27 14-May-15 14-Jun-15 69 MORTARED STONE RIP RAP CH. FROM KM 16+0
CZ1FI1350 DYKE CONSTRUCTION CH. FROM KM 16+000 TO 27 09-May-15 08-Jun-15 74 DYKE CONSTRUCTION CH. FROM KM 16+000 TO
CZ1FI1360 MORTARED STONE RIP RAP CH. FROM KM 18+00 27 15-Jun-15 15-Jul-15 69 MORTARED STONE RIP RAP CH. FROM KM
CZ1FI1370 DYKE CONSTRUCTION CH. FROM KM 18+000 TO 27 09-Jun-15 09-Jul-15 74 DYKE CONSTRUCTION CH. FROM KM 18+00
LOOSE STONE R
RIPRAP PROTECTION 259 28-Sep-14 09-Aug-15 69 09-Aug-15, LOOSE STONE RIPRAP PROT
CZ1FI1380 LOOSE STONE RIP RAP CH. FROM KM 0+000 TO 2 16 28-Sep-14 19-Oct-14 34 LOOSE STONE RIP RAP CH. FROM KM 0+000 TO 2+000
CZ1FI1390 LOOSE STONE RIP RAP CH. FROM KM 2+000 TO 4 16 03-Nov-14 20-Nov-14 33 LOOSE STONE RIP RAP CH. FROM KM 2+000 TO 4+000
CZ1FI1400 LOOSE STONE RIP RAP CH. FROM KM 4+000 TO 6 16 07-Dec-14 24-Dec-14 80 LOOSE STONE RIP RAP CH. FROM KM 4+000 TO 6+000
CZ1FI1410 LOOSE STONE RIP RAP CH. FROM KM 6+000 TO 8 16 08-Jan-15 26-Jan-15 73 LOOSE STONE RIP RAP CH. FROM KM 6+000 TO 8+000
CZ1FI1420 LOOSE STONE RIP RAP CH. FROM KM 8+000 TO 16 09-Feb-15 26-Feb-15 86 LOOSE STONE RIP RAP CH. FROM KM 8+000 TO 10+000
CZ1FI1430 LOOSE STONE RIP RAP CH. FROM KM 10+000 TO 16 12-Mar-15 30-Mar-15 99 LOOSE STONE RIP RAP CH. FROM KM 10+000 TO 12+000
CZ1FI1440 LOOSE STONE RIP RAP CH. FROM KM 12+000 TO 16 13-Apr-15 30-Apr-15 72 LOOSE STONE RIP RAP CH. FROM KM 12+000 TO 14+0
CZ1FI1450 LOOSE STONE RIP RAP CH. FROM KM 14+000 TO 16 14-May-15 01-Jun-15 85 LOOSE STONE RIP RAP CH. FROM KM 14+000 TO

Actual Work Critical Remaining Work Summary Page 21 of 57 TASK filter: All Activities

Remaining Work Milestone © Oracle Corporation


DUALIZATION OF MAHDAH - AL RAWDAH ROAD PROJECT Classic Schedule Layout 25-May-14 16:51

Activity ID Activity Name Original Start Finish Total Float Critical 2014 2015 2016
Duration
S Oct N D J F M Apr M J Jul A S Oct N D Jan F M Apr M J Jul A S Oct N D J F M Apr M J
CZ1FI1460 LOOSE STONE RIP RAP CH. FROM KM 16+000 TO 16 15-Jun-15 02-Jul-15 80 LOOSE STONE RIP RAP CH. FROM KM 16+000
CZ1FI1470 LOOSE STONE RIP RAP CH. FROM KM 18+000 TO 16 16-Jul-15 09-Aug-15 69 LOOSE STONE RIP RAP CH. FROM KM 1
REINFORCED CONCRETE
CO FOR SLOPE PROTECTION 256 20-Oct-14 24-Aug-15 80 24-Aug-15, REINFORCED CONCRETE F
CZ1FI1480 REIF. CONC. FOR SLOPE PROTECTION CH. FRO 21 20-Oct-14 13-Nov-14 295 REIF. CONC. FOR SLOPE PROTECTION CH. FROM KM 0+000 TO 2+000
CZ1FI1490 REIF. CONC. FOR SLOPE PROTECTION CH. FRO 20 24-Nov-14 16-Dec-14 269 REIF. CONC. FOR SLOPE PROTECTION CH. FROM KM 2+000 TO 4+000
CZ1FI1500 REIF. CONC. FOR SLOPE PROTECTION CH. FRO 21 25-Dec-14 19-Jan-15 241 REIF. CONC. FOR SLOPE PROTECTION CH. FROM KM 4+000 TO 6+
CZ1FI1510 REIF. CONC. FOR SLOPE PROTECTION CH. FRO 20 27-Jan-15 18-Feb-15 215 REIF. CONC. FOR SLOPE PROTECTION CH. FROM KM 6+000 TO
CZ1FI1520 REIF. CONC. FOR SLOPE PROTECTION CH. FRO 21 28-Feb-15 23-Mar-15 187 REIF. CONC. FOR SLOPE PROTECTION CH. FROM KM 8+00
CZ1FI1530 REIF. CONC. FOR SLOPE PROTECTION CH. FRO 20 31-Mar-15 22-Apr-15 161 REIF. CONC. FOR SLOPE PROTECTION CH. FROM KM
CZ1FI1540 REIF. CONC. FOR SLOPE PROTECTION CH. FRO 21 02-May-15 25-May-15 133 REIF. CONC. FOR SLOPE PROTECTION CH. FROM
CZ1FI1550 REIF. CONC. FOR SLOPE PROTECTION CH. FRO 21 02-Jun-15 25-Jun-15 106 REIF. CONC. FOR SLOPE PROTECTION CH. FR
CZ1FI1560 REIF. CONC. FOR SLOPE PROTECTION CH. FRO 20 04-Jul-15 01-Aug-15 80 REIF. CONC. FOR SLOPE PROTECTION C
CZ1FI1570 REIF. CONC. FOR SLOPE PROTECTION CH. FRO 20 02-Aug-15 24-Aug-15 80 REIF. CONC. FOR SLOPE PROTECTIO
ROCK BOLTING & ANCHORING, SHORTSCRETE 247 20-Oct-14 13-Aug-15 65 13-Aug-15, ROCK BOLTING & ANCHORIN
CZ1FI1580 ROCK BOLTING & ANCHORING,SHORTCRETE CH 16 20-Oct-14 08-Nov-14 34 ROCK BOLTING & ANCHORING,SHORTCRETE CH. FROM KM 0+000 TO 2+000
CZ1FI1590 ROCK BOLTING & ANCHORING,SHORTCRETE CH 16 09-Nov-14 29-Nov-14 34 ROCK BOLTING & ANCHORING,SHORTCRETE CH. FROM KM 2+000 TO 4+
CZ1FI1600 ROCK BOLTING & ANCHORING,SHORTCRETE CH 16 30-Nov-14 17-Dec-14 34 ROCK BOLTING & ANCHORING,SHORTCRETE CH. FROM KM 4+000 TO
CZ1FI1610 ROCK BOLTING & ANCHORING,SHORTCRETE CH 16 18-Dec-14 06-Jan-15 112 ROCK BOLTING & ANCHORING,SHORTCRETE CH. FROM KM 6+000 T
CZ1FI1620 ROCK BOLTING & ANCHORING,SHORTCRETE CH 16 12-Jan-15 29-Jan-15 148 ROCK BOLTING & ANCHORING,SHORTCRETE CH. FROM KM 8+00
CZ1FI1630 ROCK BOLTING & ANCHORING,SHORTCRETE CH 16 14-Feb-15 03-Mar-15 136 ROCK BOLTING & ANCHORING,SHORTCRETE CH. FROM KM
CZ1FI1640 ROCK BOLTING & ANCHORING,SHORTCRETE CH 16 19-Apr-15 06-May-15 97 ROCK BOLTING & ANCHORING,SHORTCRETE CH. FR
CZ1FI1650 ROCK BOLTING & ANCHORING,SHORTCRETE CH 16 19-May-15 06-Jun-15 87 ROCK BOLTING & ANCHORING,SHORTCRETE CH
CZ1FI1660 ROCK BOLTING & ANCHORING,SHORTCRETE CH 16 18-Jun-15 06-Jul-15 77 ROCK BOLTING & ANCHORING,SHORTCRET
CZ1FI1670 ROCK BOLTING & ANCHORING,SHORTCRETE CH 16 27-Jul-15 13-Aug-15 65 ROCK BOLTING & ANCHORING,SHORTC
DITCH LINING / C
CHUTES 271 20-Oct-14 10-Sep-15 65 10-Sep-15, DITCH LINING / CHUTES
CZ1FI1680 DITCH LINING/ CHUTES CH. FROM KM 0+000 TO 22 20-Oct-14 15-Nov-14 60 DITCH LINING/ CHUTES CH. FROM KM 0+000 TO 2+000
CZ1FI1690 DITCH LINING/ CHUTES CH. FROM KM 2+000 TO 22 24-Nov-14 18-Dec-14 33 DITCH LINING/ CHUTES CH. FROM KM 2+000 TO 4+000
CZ1FI1700 DITCH LINING/ CHUTES CH. FROM KM 4+000 TO 22 25-Dec-14 20-Jan-15 80 DITCH LINING/ CHUTES CH. FROM KM 4+000 TO 6+000
CZ1FI1710 DITCH LINING/ CHUTES CH. FROM KM 6+000 TO 22 27-Jan-15 21-Feb-15 73 DITCH LINING/ CHUTES CH. FROM KM 6+000 TO 8+000
CZ1FI1720 DITCH LINING/ CHUTES CH. FROM KM 8+000 TO 22 28-Feb-15 24-Mar-15 86 DITCH LINING/ CHUTES CH. FROM KM 8+000 TO 10+000
CZ1FI1730 DITCH LINING/ CHUTES CH. FROM KM 10+000 TO 22 31-Mar-15 25-Apr-15 99 DITCH LINING/ CHUTES CH. FROM KM 10+000 TO 12+0
CZ1FI1740 DITCH LINING/ CHUTES CH. FROM KM 12+000 TO 22 02-May-15 26-May-15 72 DITCH LINING/ CHUTES CH. FROM KM 12+000 TO
CZ1FI1750 DITCH LINING/ CHUTES CH. FROM KM 14+000 TO 22 02-Jun-15 27-Jun-15 85 DITCH LINING/ CHUTES CH. FROM KM 14+000
CZ1FI1760 DITCH LINING/ CHUTES CH. FROM KM 16+000 TO 22 04-Jul-15 03-Aug-15 98 DITCH LINING/ CHUTES CH. FROM KM 16
CZ1FI1770 DITCH LINING/ CHUTES CH. FROM KM 18+000 TO 24 15-Aug-15 10-Sep-15 65 DITCH LINING/ CHUTES CH. FROM K
GABION WALLS 270 16-Nov-14 08-Oct-15 65 08-Oct-15, GABION WALLS
CZ1FI1780 GABION WALLS CH. FROM KM 0+000 TO 2+000 21 16-Nov-14 11-Dec-14 60 GABION WALLS CH. FROM KM 0+000 TO 2+000
CZ1FI1790 GABION WALLS CH. FROM KM 2+000 TO 4+000 21 20-Dec-14 13-Jan-15 33 GABION WALLS CH. FROM KM 2+000 TO 4+000
CZ1FI1800 GABION WALLS CH. FROM KM 4+000 TO 6+000 21 21-Jan-15 14-Feb-15 80 GABION WALLS CH. FROM KM 4+000 TO 6+000
CZ1FI1810 GABION WALLS CH. FROM KM 6+000 TO 8+000 21 22-Feb-15 17-Mar-15 73 GABION WALLS CH. FROM KM 6+000 TO 8+000
CZ1FI1820 GABION WALLS CH. FROM KM 8+000 TO 10+000 21 25-Mar-15 18-Apr-15 86 GABION WALLS CH. FROM KM 8+000 TO 10+000
CZ1FI1830 GABION WALLS CH. FROM KM 10+000 TO 12+000 21 26-Apr-15 19-May-15 99 GABION WALLS CH. FROM KM 10+000 TO 12+000
CZ1FI1840 GABION WALLS CH. FROM KM 12+000 TO 14+000 21 27-May-15 20-Jun-15 72 GABION WALLS CH. FROM KM 12+000 TO 14+00
CZ1FI1850 GABION WALLS CH. FROM KM 14+000 TO 16+000 21 28-Jun-15 27-Jul-15 85 GABION WALLS CH. FROM KM 14+000 TO
CZ1FI1860 GABION WALLS CH. FROM KM 16+000 TO 18+000 21 04-Aug-15 27-Aug-15 98 GABION WALLS CH. FROM KM 16+000
CZ1FI1870 GABION WALLS CH. FROM KM 18+000 TO 20+000 21 12-Sep-15 08-Oct-15 65 GABION WALLS CH. FROM KM 1
CONSTRUCTION OF SIDEWALKS,PAVED AREAS AND CURBS 203 05-Feb-15 08-Oct-15 65 08-Oct-15, CONSTRUCTION OF S
CZ1FI1880 SIDE WALKS, PAVED AREAS & CURBS CH. FROM K 20 05-Feb-15 28-Feb-15 68 SIDE WALKS, PAVED AREAS & CURBS CH. FROM KM 0+000 TO
CZ1FI1890 SIDE WALKS, PAVED AREAS & CURBS CH. FROM K 20 01-Mar-15 23-Mar-15 68 SIDE WALKS, PAVED AREAS & CURBS CH. FROM KM 2+000
CZ1FI1900 SIDE WALKS, PAVED AREAS & CURBS CH. FROM K 20 24-Mar-15 15-Apr-15 68 SIDE WALKS, PAVED AREAS & CURBS CH. FROM KM 4+0
CZ1FI1910 SIDE WALKS, PAVED AREAS & CURBS CH. FROM K 20 16-Apr-15 09-May-15 68 SIDE WALKS, PAVED AREAS & CURBS CH. FROM KM

Actual Work Critical Remaining Work Summary Page 22 of 57 TASK filter: All Activities

Remaining Work Milestone © Oracle Corporation


DUALIZATION OF MAHDAH - AL RAWDAH ROAD PROJECT Classic Schedule Layout 25-May-14 16:51

Activity ID Activity Name Original Start Finish Total Float Critical 2014 2015 2016
Duration
S Oct N D J F M Apr M J Jul A S Oct N D Jan F M Apr M J Jul A S Oct N D J F M Apr M J
CZ1FI1920 SIDE WALKS, PAVED AREAS & CURBS CH. FROM K 20 10-May-15 01-Jun-15 68 SIDE WALKS, PAVED AREAS & CURBS CH. FROM K
CZ1FI1930 SIDE WALKS, PAVED AREAS & CURBS CH. FROM K 20 02-Jun-15 24-Jun-15 68 SIDE WALKS, PAVED AREAS & CURBS CH. FRO
CZ1FI1940 SIDE WALKS, PAVED AREAS & CURBS CH. FROM K 20 25-Jun-15 22-Jul-15 68 SIDE WALKS, PAVED AREAS & CURBS CH. F
CZ1FI1950 SIDE WALKS, PAVED AREAS & CURBS CH. FROM K 20 25-Jul-15 16-Aug-15 68 SIDE WALKS, PAVED AREAS & CURBS C
CZ1FI1960 SIDE WALKS, PAVED AREAS & CURBS CH. FROM K 20 17-Aug-15 08-Sep-15 68 SIDE WALKS, PAVED AREAS & CURBS
CZ1FI1970 SIDE WALKS, PAVED AREAS & CURBS CH. FROM K 20 13-Sep-15 08-Oct-15 65 SIDE WALKS, PAVED AREAS & CU
SAFETY BARRIERS AND FENCING WORKS 469 15-May-14 09-Dec-15 75 09-Dec-15, SAFETY BARR
ROAD SIDE BARRIERS
BARR - GUARDRAILS 104 06-Jul-15 14-Nov-15 75 14-Nov-15, ROAD SIDE BAR
CZ1FI1980 GUARDRAILS CH. FROM KM 0+000 TO 2+000 11 06-Jul-15 22-Jul-15 68 GUARDRAILS CH. FROM KM 0+000 TO 2+00
CZ1FI1990 GUARDRAILS CH. FROM KM 2+000 TO 4+000 10 25-Jul-15 04-Aug-15 68 GUARDRAILS CH. FROM KM 2+000 TO 4+
CZ1FI2000 GUARDRAILS CH. FROM KM 4+000 TO 6+000 10 05-Aug-15 16-Aug-15 68 GUARDRAILS CH. FROM KM 4+000 TO 6
CZ1FI2010 GUARDRAILS CH. FROM KM 6+000 TO 8+000 10 17-Aug-15 27-Aug-15 68 GUARDRAILS CH. FROM KM 6+000 TO
CZ1FI2020 GUARDRAILS CH. FROM KM 8+000 TO 10+000 10 29-Aug-15 08-Sep-15 68 GUARDRAILS CH. FROM KM 8+000 T
CZ1FI2030 GUARDRAILS CH. FROM KM 10+000 TO 12+000 10 09-Sep-15 20-Sep-15 68 GUARDRAILS CH. FROM KM 10+00
CZ1FI2040 GUARDRAILS CH. FROM KM 12+000 TO 14+000 10 24-Sep-15 08-Oct-15 65 GUARDRAILS CH. FROM KM 12+
CZ1FI2050 GUARDRAILS CH. FROM KM 14+000 TO 16+000 10 10-Oct-15 21-Oct-15 75 GUARDRAILS CH. FROM KM 14
CZ1FI2060 GUARDRAILS CH. FROM KM 16+000 TO 18+000 10 22-Oct-15 02-Nov-15 75 GUARDRAILS CH. FROM KM
CZ1FI2070 GUARDRAILS CH. FROM KM 18+000 TO 20+000 10 03-Nov-15 14-Nov-15 75 GUARDRAILS CH. FROM KM
PRECAST FOR CONCRETE
C BARRIERS 200 15-May-14 17-Jan-15 30 17-Jan-15, PRECAST FOR CONCRETE BARRIERS
CZ1FI2080 PRECAST FOR CONCRETE BARRIERS CH. FROM 20 15-May-14 08-Jun-14 30 PRECAST FOR CONCRETE BARRIERS CH. FROM KM 0+000 TO 2+000
CZ1FI2090 PRECAST FOR CONCRETE BARRIERS CH. FROM 20 09-Jun-14 01-Jul-14 30 PRECAST FOR CONCRETE BARRIERS CH. FROM KM 2+000 TO 4+000
CZ1FI2100 PRECAST FOR CONCRETE BARRIERS CH. FROM 20 02-Jul-14 26-Jul-14 30 PRECAST FOR CONCRETE BARRIERS CH. FROM KM 4+000 TO 6+000
CZ1FI2110 PRECAST FOR CONCRETE BARRIERS CH. FROM 20 27-Jul-14 21-Aug-14 30 PRECAST FOR CONCRETE BARRIERS CH. FROM KM 6+000 TO 8+000
CZ1FI2120 PRECAST FOR CONCRETE BARRIERS CH. FROM 20 23-Aug-14 14-Sep-14 30 PRECAST FOR CONCRETE BARRIERS CH. FROM KM 8+000 TO 10+000
CZ1FI2130 PRECAST FOR CONCRETE BARRIERS CH. FROM 20 15-Sep-14 11-Oct-14 30 PRECAST FOR CONCRETE BARRIERS CH. FROM KM 10+000 TO 12+000
CZ1FI2140 PRECAST FOR CONCRETE BARRIERS CH. FROM 20 12-Oct-14 04-Nov-14 30 PRECAST FOR CONCRETE BARRIERS CH. FROM KM 12+000 TO 14+000
CZ1FI2150 PRECAST FOR CONCRETE BARRIERS CH. FROM 20 05-Nov-14 30-Nov-14 30 PRECAST FOR CONCRETE BARRIERS CH. FROM KM 14+000 TO 16+000
CZ1FI2160 PRECAST FOR CONCRETE BARRIERS CH. FROM 20 01-Dec-14 23-Dec-14 30 PRECAST FOR CONCRETE BARRIERS CH. FROM KM 16+000 TO 18+000
CZ1FI2170 PRECAST FOR CONCRETE BARRIERS CH. FROM 20 24-Dec-14 17-Jan-15 30 PRECAST FOR CONCRETE BARRIERS CH. FROM KM 18+000 TO 20+
CONCRETE BARRIERS
BARR 113 25-Jul-15 09-Dec-15 75 09-Dec-15, CONCRETE B
CZ1FI2180 CONCRETE BARRIERS CH. FROM KM 0+000 TO 2 10 25-Jul-15 04-Aug-15 128 CONCRETE BARRIERS CH. FROM KM 0+0
CZ1FI2190 CONCRETE BARRIERS CH. FROM KM 2+000 TO 4 10 05-Aug-15 16-Aug-15 118 CONCRETE BARRIERS CH. FROM KM 2
CZ1FI2200 CONCRETE BARRIERS CH. FROM KM 4+000 TO 6 10 17-Aug-15 27-Aug-15 108 CONCRETE BARRIERS CH. FROM KM
CZ1FI2210 CONCRETE BARRIERS CH. FROM KM 6+000 TO 8 10 29-Aug-15 08-Sep-15 98 CONCRETE BARRIERS CH. FROM KM
CZ1FI2220 CONCRETE BARRIERS CH. FROM KM 8+000 TO 1 10 09-Sep-15 20-Sep-15 88 CONCRETE BARRIERS CH. FROM
CZ1FI2230 CONCRETE BARRIERS CH. FROM KM 10+000 TO 10 17-Sep-15 01-Oct-15 81 CONCRETE BARRIERS CH. FROM
CZ1FI2240 CONCRETE BARRIERS CH. FROM KM 12+000 TO 10 10-Oct-15 21-Oct-15 65 CONCRETE BARRIERS CH. FR
CZ1FI2250 CONCRETE BARRIERS CH. FROM KM 14+000 TO 10 22-Oct-15 02-Nov-15 105 CONCRETE BARRIERS CH. F
CZ1FI2260 CONCRETE BARRIERS CH. FROM KM 16+000 TO 10 03-Nov-15 14-Nov-15 95 CONCRETE BARRIERS CH.
CZ1FI2270 CONCRETE BARRIERS CH. FROM KM 18+000 TO 10 26-Nov-15 09-Dec-15 75 CONCRETE BARRIERS C
HIGHWAY SIGN,ROA
SIGN,ROAD STUDS AND ROAD MARKING WORKS 100 22-Oct-15 18-Feb-16 65 18-Feb-16, HIG
CZ1FI2280 HIGHWAY SIGN, ROAD STUDS & MARKINGS CH. F 10 22-Oct-15 02-Nov-15 65 HIGHWAY SIGN, ROAD STUD
CZ1FI2290 HIGHWAY SIGN, ROAD STUDS & MARKINGS CH. F 10 03-Nov-15 14-Nov-15 65 HIGHWAY SIGN, ROAD STU
CZ1FI2300 HIGHWAY SIGN, ROAD STUDS & MARKINGS CH. F 10 15-Nov-15 25-Nov-15 65 HIGHWAY SIGN, ROAD ST
CZ1FI2310 HIGHWAY SIGN, ROAD STUDS & MARKINGS CH. F 10 26-Nov-15 09-Dec-15 65 HIGHWAY SIGN, ROAD S
CZ1FI2320 HIGHWAY SIGN, ROAD STUDS & MARKINGS CH. F 10 10-Dec-15 21-Dec-15 65 HIGHWAY SIGN, ROAD
CZ1FI2330 HIGHWAY SIGN, ROAD STUDS & MARKINGS CH. F 10 22-Dec-15 03-Jan-16 65 HIGHWAY SIGN, ROA
CZ1FI2340 HIGHWAY SIGN, ROAD STUDS & MARKINGS CH. F 10 04-Jan-16 14-Jan-16 65 HIGHWAY SIGN, RO
CZ1FI2350 HIGHWAY SIGN, ROAD STUDS & MARKINGS CH. F 10 16-Jan-16 26-Jan-16 65 HIGHWAY SIGN, R
CZ1FI2360 HIGHWAY SIGN, ROAD STUDS & MARKINGS CH. F 10 27-Jan-16 07-Feb-16 65 HIGHWAY SIGN,
CZ1FI2370 HIGHWAY SIGN, ROAD STUDS & MARKINGS CH. F 10 08-Feb-16 18-Feb-16 65 HIGHWAY SIGN

Actual Work Critical Remaining Work Summary Page 23 of 57 TASK filter: All Activities

Remaining Work Milestone © Oracle Corporation


DUALIZATION OF MAHDAH - AL RAWDAH ROAD PROJECT Classic Schedule Layout 25-May-14 16:51

Activity ID Activity Name Original Start Finish Total Float Critical 2014 2015 2016
Duration
S Oct N D J F M Apr M J Jul A S Oct N D Jan F M Apr M J Jul A S Oct N D J F M Apr M J
UTILITIES - SERVICE PROTECTION WORKS 247 02-Mar-14 27-Dec-14 45 27-Dec-14, UTILITIES - SERVICE PROTECTION WORKS
SERVICE DUCTS/ SPLIT PIPES 244 02-Mar-14 23-Dec-14 33 23-Dec-14, SERVICE DUCTS/ SPLIT PIPES
CZ1UT1050 SERVICE DUCTS/SPLIT PIPES CH. FROM KM 0+00 25 02-Mar-14 30-Mar-14 33 SERVICE DUCTS/SPLIT PIPES CH. FROM KM 0+000 TO 2+000
CZ1UT1060 SERVICE DUCTS/SPLIT PIPES CH. FROM KM 2+00 25 31-Mar-14 28-Apr-14 33 SERVICE DUCTS/SPLIT PIPES CH. FROM KM 2+000 TO 4+000
CZ1UT1070 SERVICE DUCTS/SPLIT PIPES CH. FROM KM 4+00 25 29-Apr-14 28-May-14 33 SERVICE DUCTS/SPLIT PIPES CH. FROM KM 4+000 TO 6+000
CZ1UT1080 SERVICE DUCTS/SPLIT PIPES CH. FROM KM 6+00 25 29-May-14 26-Jun-14 33 SERVICE DUCTS/SPLIT PIPES CH. FROM KM 6+000 TO 8+000
CZ1UT1090 SERVICE DUCTS/SPLIT PIPES CH. FROM KM 8+00 24 28-Jun-14 26-Jul-14 33 SERVICE DUCTS/SPLIT PIPES CH. FROM KM 8+000 TO 10+000
CZ1UT1100 SERVICE DUCTS/SPLIT PIPES CH. FROM KM 10+0 24 27-Jul-14 26-Aug-14 33 SERVICE DUCTS/SPLIT PIPES CH. FROM KM 10+000 TO 12+000
CZ1UT1110 SERVICE DUCTS/SPLIT PIPES CH. FROM KM 12+0 24 27-Aug-14 23-Sep-14 33 SERVICE DUCTS/SPLIT PIPES CH. FROM KM 12+000 TO 14+000
CZ1UT1120 SERVICE DUCTS/SPLIT PIPES CH. FROM KM 14+0 24 24-Sep-14 26-Oct-14 33 SERVICE DUCTS/SPLIT PIPES CH. FROM KM 14+000 TO 16+000
CZ1UT1130 SERVICE DUCTS/SPLIT PIPES CH. FROM KM 16+0 24 27-Oct-14 25-Nov-14 33 SERVICE DUCTS/SPLIT PIPES CH. FROM KM 16+000 TO 18+000
CZ1UT1140 SERVICE DUCTS/SPLIT PIPES CH. FROM KM 18+0 24 26-Nov-14 23-Dec-14 33 SERVICE DUCTS/SPLIT PIPES CH. FROM KM 18+000 TO 20+000
MEDIAN INLETS 237 12-Mar-14 25-Dec-14 45 25-Dec-14, MEDIAN INLETS
CZ1UT1150 MEDIAN INLETS CH. FROM KM 0+000 TO 2+000 18 12-Mar-14 01-Apr-14 67 MEDIAN INLETS CH. FROM KM 0+000 TO 2+000
CZ1UT1160 MEDIAN INLETS CH. FROM KM 2+000 TO 4+000 18 10-Apr-14 30-Apr-14 63 MEDIAN INLETS CH. FROM KM 2+000 TO 4+000
CZ1UT1170 MEDIAN INLETS CH. FROM KM 4+000 TO 6+000 18 10-May-14 31-May-14 56 MEDIAN INLETS CH. FROM KM 4+000 TO 6+000
CZ1UT1180 MEDIAN INLETS CH. FROM KM 6+000 TO 8+000 18 09-Jun-14 29-Jun-14 49 MEDIAN INLETS CH. FROM KM 6+000 TO 8+000
CZ1UT1190 MEDIAN INLETS CH. FROM KM 8+000 TO 10+000 18 07-Jul-14 31-Jul-14 46 MEDIAN INLETS CH. FROM KM 8+000 TO 10+000
CZ1UT1200 MEDIAN INLETS CH. FROM KM 10+000 TO 12+000 18 09-Aug-14 28-Aug-14 40 MEDIAN INLETS CH. FROM KM 10+000 TO 12+000
CZ1UT1210 MEDIAN INLETS CH. FROM KM 12+000 TO 14+000 18 06-Sep-14 25-Sep-14 34 MEDIAN INLETS CH. FROM KM 12+000 TO 14+000
CZ1UT1220 MEDIAN INLETS CH. FROM KM 14+000 TO 16+000 18 07-Oct-14 28-Oct-14 57 MEDIAN INLETS CH. FROM KM 14+000 TO 16+000
CZ1UT1230 MEDIAN INLETS CH. FROM KM 16+000 TO 18+000 18 05-Nov-14 27-Nov-14 51 MEDIAN INLETS CH. FROM KM 16+000 TO 18+000
CZ1UT1240 MEDIAN INLETS CH. FROM KM 18+000 TO 20+000 18 06-Dec-14 25-Dec-14 45 MEDIAN INLETS CH. FROM KM 18+000 TO 20+000
CONCRETE IN MEDIAN
ME AREA 235 16-Mar-14 27-Dec-14 45 27-Dec-14, CONCRETE IN MEDIAN AREA
CZ1UT1250 CONCRETE IN MEDIAN CH. FROM KM 0+000 TO 2 16 16-Mar-14 02-Apr-14 67 CONCRETE IN MEDIAN CH. FROM KM 0+000 TO 2+000
CZ1UT1260 CONCRETE IN MEDIAN CH. FROM KM 2+000 TO 4 16 14-Apr-14 01-May-14 99 CONCRETE IN MEDIAN CH. FROM KM 2+000 TO 4+000
CZ1UT1270 CONCRETE IN MEDIAN CH. FROM KM 4+000 TO 6 16 13-May-14 01-Jun-14 74 CONCRETE IN MEDIAN CH. FROM KM 4+000 TO 6+000
CZ1UT1280 CONCRETE IN MEDIAN CH. FROM KM 6+000 TO 8 16 12-Jun-14 30-Jun-14 49 CONCRETE IN MEDIAN CH. FROM KM 6+000 TO 8+000
CZ1UT1290 CONCRETE IN MEDIAN CH. FROM KM 8+000 TO 1 16 10-Jul-14 02-Aug-14 82 CONCRETE IN MEDIAN CH. FROM KM 8+000 TO 10+000
CZ1UT1300 CONCRETE IN MEDIAN CH. FROM KM 10+000 TO 16 12-Aug-14 30-Aug-14 58 CONCRETE IN MEDIAN CH. FROM KM 10+000 TO 12+000
CZ1UT1310 CONCRETE IN MEDIAN CH. FROM KM 12+000 TO 16 09-Sep-14 27-Sep-14 34 CONCRETE IN MEDIAN CH. FROM KM 12+000 TO 14+000
CZ1UT1320 CONCRETE IN MEDIAN CH. FROM KM 14+000 TO 16 11-Oct-14 29-Oct-14 93 CONCRETE IN MEDIAN CH. FROM KM 14+000 TO 16+000
CZ1UT1330 CONCRETE IN MEDIAN CH. FROM KM 16+000 TO 16 09-Nov-14 29-Nov-14 69 CONCRETE IN MEDIAN CH. FROM KM 16+000 TO 18+000
CZ1UT1340 CONCRETE IN MEDIAN CH. FROM KM 18+000 TO 16 09-Dec-14 27-Dec-14 45 CONCRETE IN MEDIAN CH. FROM KM 18+000 TO 20+000
ROAD LIGHTING & ELECTRICAL
EL INSTALLATION 250 22-Apr-14 21-Feb-15 41 21-Feb-15, ROAD LIGHTING & ELECTRICAL INSTALLATION
CIVIL WORKS FOR E
ELECTRICAL INSTALLATION 190 22-Apr-14 11-Dec-14 32 11-Dec-14, CIVIL WORKS FOR ELECTRICAL INSTALLATION
CZ1EL1000 CIVIL WORKS FOR ELECTRICAL INSTALLATION C 19 22-Apr-14 13-May-14 32 CIVIL WORKS FOR ELECTRICAL INSTALLATION CH. FROM KM 0+000 TO 2+000
CZ1EL1010 CIVIL WORKS FOR ELECTRICAL INSTALLATION C 19 14-May-14 05-Jun-14 32 CIVIL WORKS FOR ELECTRICAL INSTALLATION CH. FROM KM 2+000 TO 4+000
CZ1EL1020 CIVIL WORKS FOR ELECTRICAL INSTALLATION C 19 07-Jun-14 28-Jun-14 32 CIVIL WORKS FOR ELECTRICAL INSTALLATION CH. FROM KM 4+000 TO 6+000
CZ1EL1030 CIVIL WORKS FOR ELECTRICAL INSTALLATION C 19 29-Jun-14 20-Jul-14 32 CIVIL WORKS FOR ELECTRICAL INSTALLATION CH. FROM KM 6+000 TO 8+000
CZ1EL1040 CIVIL WORKS FOR ELECTRICAL INSTALLATION C 19 21-Jul-14 16-Aug-14 32 CIVIL WORKS FOR ELECTRICAL INSTALLATION CH. FROM KM 8+000 TO 10+000
CZ1EL1050 CIVIL WORKS FOR ELECTRICAL INSTALLATION C 19 17-Aug-14 07-Sep-14 32 CIVIL WORKS FOR ELECTRICAL INSTALLATION CH. FROM KM 10+000 TO 12+000
CZ1EL1060 CIVIL WORKS FOR ELECTRICAL INSTALLATION C 19 08-Sep-14 29-Sep-14 32 CIVIL WORKS FOR ELECTRICAL INSTALLATION CH. FROM KM 12+000 TO 14+000
CZ1EL1070 CIVIL WORKS FOR ELECTRICAL INSTALLATION C 19 30-Sep-14 26-Oct-14 32 CIVIL WORKS FOR ELECTRICAL INSTALLATION CH. FROM KM 14+000 TO 16+00
CZ1EL1080 CIVIL WORKS FOR ELECTRICAL INSTALLATION C 19 27-Oct-14 17-Nov-14 32 CIVIL WORKS FOR ELECTRICAL INSTALLATION CH. FROM KM 16+000 TO 18
CZ1EL1090 CIVIL WORKS FOR ELECTRICAL INSTALLATION C 19 18-Nov-14 11-Dec-14 32 CIVIL WORKS FOR ELECTRICAL INSTALLATION CH. FROM KM 18+000 TO
SUB STATIONS & FE
FEEDER PILLARS 164 05-May-14 24-Nov-14 101 24-Nov-14, SUB STATIONS & FEEDER PILLARS
CZ1EL1100 SUB STATION & FEEDER PILLARS CH. FROM KM 0 17 05-May-14 24-May-14 53 SUB STATION & FEEDER PILLARS CH. FROM KM 0+000 TO 2+000
CZ1EL1110 SUB STATION & FEEDER PILLARS CH. FROM KM 2 17 25-May-14 14-Jun-14 53 SUB STATION & FEEDER PILLARS CH. FROM KM 2+000 TO 4+000
CZ1EL1120 SUB STATION & FEEDER PILLARS CH. FROM KM 4 16 15-Jun-14 02-Jul-14 53 SUB STATION & FEEDER PILLARS CH. FROM KM 4+000 TO 6+000
CZ1EL1130 SUB STATION & FEEDER PILLARS CH. FROM KM 6 16 03-Jul-14 21-Jul-14 53 SUB STATION & FEEDER PILLARS CH. FROM KM 6+000 TO 8+000

Actual Work Critical Remaining Work Summary Page 24 of 57 TASK filter: All Activities

Remaining Work Milestone © Oracle Corporation


DUALIZATION OF MAHDAH - AL RAWDAH ROAD PROJECT Classic Schedule Layout 25-May-14 16:51

Activity ID Activity Name Original Start Finish Total Float Critical 2014 2015 2016
Duration
S Oct N D J F M Apr M J Jul A S Oct N D Jan F M Apr M J Jul A S Oct N D J F M Apr M J
CZ1EL1140 SUB STATION & FEEDER PILLARS CH. FROM KM 8 16 26-Jul-14 16-Aug-14 51 SUB STATION & FEEDER PILLARS CH. FROM KM 8+000 TO 10+000
CZ1EL1150 SUB STATION & FEEDER PILLARS CH. FROM KM 1 16 17-Aug-14 03-Sep-14 54 SUB STATION & FEEDER PILLARS CH. FROM KM 10+000 TO 12+000
CZ1EL1160 SUB STATION & FEEDER PILLARS CH. FROM KM 1 16 04-Sep-14 22-Sep-14 57 SUB STATION & FEEDER PILLARS CH. FROM KM 12+000 TO 14+000
CZ1EL1170 SUB STATION & FEEDER PILLARS CH. FROM KM 1 16 23-Sep-14 14-Oct-14 60 SUB STATION & FEEDER PILLARS CH. FROM KM 14+000 TO 16+000
CZ1EL1180 SUB STATION & FEEDER PILLARS CH. FROM KM 1 16 15-Oct-14 03-Nov-14 63 SUB STATION & FEEDER PILLARS CH. FROM KM 16+000 TO 18+000
CZ1EL1190 SUB STATION & FEEDER PILLARS CH. FROM KM 1 16 04-Nov-14 24-Nov-14 101 SUB STATION & FEEDER PILLARS CH. FROM KM 18+000 TO 20+000
HIGH TENSION OVE
OVERHEAD ELECTRICAL LINE 119 15-Jun-14 09-Nov-14 82 09-Nov-14, HIGH TENSION OVERHEAD ELECTRICAL LINE
CZ1EL1200 HIGH TENSION OVERHEAD ELECTRICAL LINE CH 12 15-Jun-14 28-Jun-14 62 HIGH TENSION OVERHEAD ELECTRICAL LINE CH. FROM KM 0+000 TO 2+000
CZ1EL1210 HIGH TENSION OVERHEAD ELECTRICAL LINE CH 12 29-Jun-14 12-Jul-14 62 HIGH TENSION OVERHEAD ELECTRICAL LINE CH. FROM KM 2+000 TO 4+000
CZ1EL1220 HIGH TENSION OVERHEAD ELECTRICAL LINE CH 12 13-Jul-14 27-Jul-14 62 HIGH TENSION OVERHEAD ELECTRICAL LINE CH. FROM KM 4+000 TO 6+000
CZ1EL1230 HIGH TENSION OVERHEAD ELECTRICAL LINE CH 12 31-Jul-14 13-Aug-14 62 HIGH TENSION OVERHEAD ELECTRICAL LINE CH. FROM KM 6+000 TO 8+000
CZ1EL1240 HIGH TENSION OVERHEAD ELECTRICAL LINE CH 12 14-Aug-14 27-Aug-14 62 HIGH TENSION OVERHEAD ELECTRICAL LINE CH. FROM KM 8+000 TO 10+000
CZ1EL1250 HIGH TENSION OVERHEAD ELECTRICAL LINE CH 12 28-Aug-14 10-Sep-14 62 HIGH TENSION OVERHEAD ELECTRICAL LINE CH. FROM KM 10+000 TO 12+000
CZ1EL1260 HIGH TENSION OVERHEAD ELECTRICAL LINE CH 12 11-Sep-14 24-Sep-14 62 HIGH TENSION OVERHEAD ELECTRICAL LINE CH. FROM KM 12+000 TO 14+000
CZ1EL1270 HIGH TENSION OVERHEAD ELECTRICAL LINE CH 12 25-Sep-14 12-Oct-14 62 HIGH TENSION OVERHEAD ELECTRICAL LINE CH. FROM KM 14+000 TO 16+000
CZ1EL1280 HIGH TENSION OVERHEAD ELECTRICAL LINE CH 12 13-Oct-14 27-Oct-14 69 HIGH TENSION OVERHEAD ELECTRICAL LINE CH. FROM KM 16+000 TO 18+000
CZ1EL1290 HIGH TENSION OVERHEAD ELECTRICAL LINE CH 11 28-Oct-14 09-Nov-14 82 HIGH TENSION OVERHEAD ELECTRICAL LINE CH. FROM KM 18+000 TO 20+0
CABLING WORKS 150 21-Jun-14 23-Dec-14 76 23-Dec-14, CABLING WORKS
CZ1EL1300 CABLING WORKS CH. FROM KM 0+000 TO 2+000 15 21-Jun-14 07-Jul-14 76 CABLING WORKS CH. FROM KM 0+000 TO 2+000
CZ1EL1310 CABLING WORKS CH. FROM KM 2+000 TO 4+000 15 08-Jul-14 26-Jul-14 76 CABLING WORKS CH. FROM KM 2+000 TO 4+000
CZ1EL1320 CABLING WORKS CH. FROM KM 4+000 TO 6+000 15 27-Jul-14 16-Aug-14 76 CABLING WORKS CH. FROM KM 4+000 TO 6+000
CZ1EL1330 CABLING WORKS CH. FROM KM 6+000 TO 8+000 15 17-Aug-14 02-Sep-14 76 CABLING WORKS CH. FROM KM 6+000 TO 8+000
CZ1EL1340 CABLING WORKS CH. FROM KM 8+000 TO 10+000 15 03-Sep-14 20-Sep-14 76 CABLING WORKS CH. FROM KM 8+000 TO 10+000
CZ1EL1350 CABLING WORKS CH. FROM KM 10+000 TO 12+00 15 21-Sep-14 11-Oct-14 76 CABLING WORKS CH. FROM KM 10+000 TO 12+000
CZ1EL1360 CABLING WORKS CH. FROM KM 12+000 TO 14+00 15 12-Oct-14 29-Oct-14 76 CABLING WORKS CH. FROM KM 12+000 TO 14+000
CZ1EL1370 CABLING WORKS CH. FROM KM 14+000 TO 16+00 15 30-Oct-14 16-Nov-14 76 CABLING WORKS CH. FROM KM 14+000 TO 16+000
CZ1EL1380 CABLING WORKS CH. FROM KM 16+000 TO 18+00 15 17-Nov-14 06-Dec-14 76 CABLING WORKS CH. FROM KM 16+000 TO 18+000
CZ1EL1390 CABLING WORKS CH. FROM KM 18+000 TO 20+00 15 07-Dec-14 23-Dec-14 76 CABLING WORKS CH. FROM KM 18+000 TO 20+000
ROAD LIGHTING MASTS,
MA COLUMNS AND LUMINARIES 147 09-Aug-14 03-Feb-15 41 03-Feb-15, ROAD LIGHTING MASTS, COLUMNS AND LUMINARIES
CZ1EL1400 ROAD LIGHTING MASTS, COLUMNS & LUMINARIE 15 09-Aug-14 25-Aug-14 41 ROAD LIGHTING MASTS, COLUMNS & LUMINARIES CH. FROM KM 0+000 TO 2+000
CZ1EL1410 ROAD LIGHTING MASTS, COLUMNS & LUMINARIE 15 26-Aug-14 11-Sep-14 41 ROAD LIGHTING MASTS, COLUMNS & LUMINARIES CH. FROM KM 2+000 TO 4+000
CZ1EL1420 ROAD LIGHTING MASTS, COLUMNS & LUMINARIE 15 13-Sep-14 29-Sep-14 41 ROAD LIGHTING MASTS, COLUMNS & LUMINARIES CH. FROM KM 4+000 TO 6+000
CZ1EL1430 ROAD LIGHTING MASTS, COLUMNS & LUMINARIE 15 30-Sep-14 20-Oct-14 41 ROAD LIGHTING MASTS, COLUMNS & LUMINARIES CH. FROM KM 6+000 TO 8+0
CZ1EL1440 ROAD LIGHTING MASTS, COLUMNS & LUMINARIE 15 21-Oct-14 08-Nov-14 41 ROAD LIGHTING MASTS, COLUMNS & LUMINARIES CH. FROM KM 8+000 TO
CZ1EL1450 ROAD LIGHTING MASTS, COLUMNS & LUMINARIE 15 09-Nov-14 27-Nov-14 41 ROAD LIGHTING MASTS, COLUMNS & LUMINARIES CH. FROM KM 10+000 T
CZ1EL1460 ROAD LIGHTING MASTS, COLUMNS & LUMINARIE 15 29-Nov-14 15-Dec-14 41 ROAD LIGHTING MASTS, COLUMNS & LUMINARIES CH. FROM KM 12+00
CZ1EL1470 ROAD LIGHTING MASTS, COLUMNS & LUMINARIE 14 16-Dec-14 31-Dec-14 41 ROAD LIGHTING MASTS, COLUMNS & LUMINARIES CH. FROM KM 14+
CZ1EL1480 ROAD LIGHTING MASTS, COLUMNS & LUMINARIE 14 01-Jan-15 18-Jan-15 41 ROAD LIGHTING MASTS, COLUMNS & LUMINARIES CH. FROM KM 1
CZ1EL1490 ROAD LIGHTING MASTS, COLUMNS & LUMINARIE 14 19-Jan-15 03-Feb-15 41 ROAD LIGHTING MASTS, COLUMNS & LUMINARIES CH. FROM KM
LIGHTING - TESTING AND COMMISSIONING 147 26-Aug-14 21-Feb-15 41 21-Feb-15, LIGHTING - TESTING AND COMMISSIONING
CZ1EL1500 LIGHTING - TESTING & COMMISSIONING CH. FRO 15 26-Aug-14 11-Sep-14 173 LIGHTING - TESTING & COMMISSIONING CH. FROM KM 0+000 TO 2+000
CZ1EL1510 LIGHTING - TESTING & COMMISSIONING CH. FRO 15 13-Sep-14 29-Sep-14 158 LIGHTING - TESTING & COMMISSIONING CH. FROM KM 2+000 TO 4+000
CZ1EL1520 LIGHTING - TESTING & COMMISSIONING CH. FRO 15 30-Sep-14 20-Oct-14 143 LIGHTING - TESTING & COMMISSIONING CH. FROM KM 4+000 TO 6+000
CZ1EL1530 LIGHTING - TESTING & COMMISSIONING CH. FRO 15 21-Oct-14 08-Nov-14 128 LIGHTING - TESTING & COMMISSIONING CH. FROM KM 6+000 TO 8+000
CZ1EL1540 LIGHTING - TESTING & COMMISSIONING CH. FRO 15 09-Nov-14 27-Nov-14 113 LIGHTING - TESTING & COMMISSIONING CH. FROM KM 8+000 TO 10+000
CZ1EL1550 LIGHTING - TESTING & COMMISSIONING CH. FRO 15 29-Nov-14 15-Dec-14 98 LIGHTING - TESTING & COMMISSIONING CH. FROM KM 10+000 TO 12+0
CZ1EL1560 LIGHTING - TESTING & COMMISSIONING CH. FRO 15 16-Dec-14 01-Jan-15 83 LIGHTING - TESTING & COMMISSIONING CH. FROM KM 12+000 TO 14
CZ1EL1570 LIGHTING - TESTING & COMMISSIONING CH. FRO 15 01-Jan-15 19-Jan-15 69 LIGHTING - TESTING & COMMISSIONING CH. FROM KM 14+000 TO
CZ1EL1580 LIGHTING - TESTING & COMMISSIONING CH. FRO 15 19-Jan-15 04-Feb-15 55 LIGHTING - TESTING & COMMISSIONING CH. FROM KM 16+000 T
CZ1EL1590 LIGHTING - TESTING & COMMISSIONING CH. FRO 15 04-Feb-15 21-Feb-15 41 LIGHTING - TESTING & COMMISSIONING CH. FROM KM 18+000
PART 2 (FROM KM 20+0
20+000 to KM 40+000 ) 664 20-Mar-14 30-May-16 14 3

Actual Work Critical Remaining Work Summary Page 25 of 57 TASK filter: All Activities

Remaining Work Milestone © Oracle Corporation


DUALIZATION OF MAHDAH - AL RAWDAH ROAD PROJECT Classic Schedule Layout 25-May-14 16:51

Activity ID Activity Name Original Start Finish Total Float Critical 2014 2015 2016
Duration
S Oct N D J F M Apr M J Jul A S Oct N D Jan F M Apr M J Jul A S Oct N D J F M Apr M J
EXCAVAT ION, FILLING & BITUMINOUS PAVEMENT 595 20-Mar-14 10-Mar-16 3 10-Mar-16, E
UTILITIES RELOCATION
RELOCAT 125 20-Mar-14 18-Aug-14 69 18-Aug-14, UTILITIES RELOCATION
CZ2UT1300 PART 2 UTILITIES RELOCATION CH. FROM KM 20 25 20-Mar-14 17-Apr-14 35 PART 2 UTILITIES RELOCATION CH. FROM KM 20+000 TO 24+000
CZ2UT1310 PART 2 UTILITIES RELOCATION CH. FROM KM 24 25 19-Apr-14 17-May-14 55 PART 2 UTILITIES RELOCATION CH. FROM KM 24+000 TO 28+000
CZ2UT1320 PART 2 UTILITIES RELOCATION CH. FROM KM 28 25 18-May-14 16-Jun-14 60 PART 2 UTILITIES RELOCATION CH. FROM KM 28+000 TO 32+000
CZ2UT1330 PART 2 UTILITIES RELOCATION CH. FROM KM 32 25 17-Jun-14 15-Jul-14 65 PART 2 UTILITIES RELOCATION CH. FROM KM 32+000 TO 36+000
CZ2UT1340 PART 2 UTILITIES RELOCATION CH. FROM KM 36 25 16-Jul-14 18-Aug-14 69 PART 2 UTILITIES RELOCATION CH. FROM KM 36+000 TO 40+000
CLEARING AND GRUBBING
GR FOR ROAD WAY 124 25-Mar-14 21-Aug-14 66 21-Aug-14, CLEARING AND GRUBBING FOR ROAD WAY
CZ2EW1000 CLEARING & GRUBBING CH. FROM KM 20+000 TO 12 25-Mar-14 07-Apr-14 35 CLEARING & GRUBBING CH. FROM KM 20+000 TO 22+000
CZ2EW1010 CLEARING & GRUBBING CH. FROM KM 22+000 TO 12 08-Apr-14 21-Apr-14 47 CLEARING & GRUBBING CH. FROM KM 22+000 TO 24+000
CZ2EW1020 CLEARING & GRUBBING CH. FROM KM 24+000 TO 12 22-Apr-14 05-May-14 50 CLEARING & GRUBBING CH. FROM KM 24+000 TO 26+000
CZ2EW1030 CLEARING & GRUBBING CH. FROM KM 26+000 TO 12 06-May-14 19-May-14 53 CLEARING & GRUBBING CH. FROM KM 26+000 TO 28+000
CZ2EW1040 CLEARING & GRUBBING CH. FROM KM 28+000 TO 12 20-May-14 03-Jun-14 56 CLEARING & GRUBBING CH. FROM KM 28+000 TO 30+000
CZ2EW1050 CLEARING & GRUBBING CH. FROM KM 30+000 TO 11 04-Jun-14 16-Jun-14 60 CLEARING & GRUBBING CH. FROM KM 30+000 TO 32+000
CZ2EW1060 CLEARING & GRUBBING CH. FROM KM 32+000 TO 11 17-Jun-14 29-Jun-14 63 CLEARING & GRUBBING CH. FROM KM 32+000 TO 34+000
CZ2EW1070 CLEARING & GRUBBING CH. FROM KM 34+000 TO 16 30-Jun-14 17-Jul-14 63 CLEARING & GRUBBING CH. FROM KM 34+000 TO 36+000
CZ2EW1080 CLEARING & GRUBBING CH. FROM KM 36+000 TO 13 19-Jul-14 06-Aug-14 65 CLEARING & GRUBBING CH. FROM KM 36+000 TO 38+000
CZ2EW1090 CLEARING & GRUBBING CH. FROM KM 38+000 TO 13 07-Aug-14 21-Aug-14 66 CLEARING & GRUBBING CH. FROM KM 38+000 TO 40+000
SETTING OUT 149 01-May-14 01-Nov-14 9 01-Nov-14, SETTING OUT
CZ2EW1100 SETTING OUT CH. FROM KM 20+000 TO 22+000 15 01-May-14 18-May-14 0 SETTING OUT CH. FROM KM 20+000 TO 22+000
CZ2EW1110 SETTING OUT CH. FROM KM 22+000 TO 24+000 15 19-May-14 05-Jun-14 9 SETTING OUT CH. FROM KM 22+000 TO 24+000
CZ2EW1120 SETTING OUT CH. FROM KM 24+000 TO 26+000 15 07-Jun-14 23-Jun-14 9 SETTING OUT CH. FROM KM 24+000 TO 26+000
CZ2EW1130 SETTING OUT CH. FROM KM 26+000 TO 28+000 15 24-Jun-14 10-Jul-14 9 SETTING OUT CH. FROM KM 26+000 TO 28+000
CZ2EW1140 SETTING OUT CH. FROM KM 28+000 TO 30+000 15 12-Jul-14 02-Aug-14 9 SETTING OUT CH. FROM KM 28+000 TO 30+000
CZ2EW1150 SETTING OUT CH. FROM KM 30+000 TO 32+000 15 03-Aug-14 19-Aug-14 9 SETTING OUT CH. FROM KM 30+000 TO 32+000
CZ2EW1160 SETTING OUT CH. FROM KM 32+000 TO 34+000 15 20-Aug-14 06-Sep-14 9 SETTING OUT CH. FROM KM 32+000 TO 34+000
CZ2EW1170 SETTING OUT CH. FROM KM 34+000 TO 36+000 15 07-Sep-14 23-Sep-14 9 SETTING OUT CH. FROM KM 34+000 TO 36+000
CZ2EW1180 SETTING OUT CH. FROM KM 36+000 TO 38+000 15 24-Sep-14 14-Oct-14 9 SETTING OUT CH. FROM KM 36+000 TO 38+000
CZ2EW1190 SETTING OUT CH. FROM KM 38+000 TO 40+000 14 15-Oct-14 01-Nov-14 9 SETTING OUT CH. FROM KM 38+000 TO 40+000
UNCLASSIFIED EXCAVATIO
EXC N 470 15-May-14 10-Dec-15 54 10-Dec-15, UNCLASSIFIE
CZ2EW1200 UNCLASSIFIED EXCAVATION CH. FROM KM 20+00 47 15-May-14 09-Jul-14 0 UNCLASSIFIED EXCAVATION CH. FROM KM 20+000 TO 22+000
CZ2EW1210 UNCLASSIFIED EXCAVATION CH. FROM KM 22+00 47 10-Jul-14 07-Sep-14 0 UNCLASSIFIED EXCAVATION CH. FROM KM 22+000 TO 24+000
CZ2EW1220 UNCLASSIFIED EXCAVATION CH. FROM KM 24+00 47 08-Sep-14 05-Nov-14 5 UNCLASSIFIED EXCAVATION CH. FROM KM 24+000 TO 26+000
CZ2EW1230 UNCLASSIFIED EXCAVATION CH. FROM KM 26+00 47 06-Nov-14 01-Jan-15 5 UNCLASSIFIED EXCAVATION CH. FROM KM 26+000 TO 28+000
CZ2EW1240 UNCLASSIFIED EXCAVATION CH. FROM KM 28+00 47 04-Jan-15 26-Feb-15 5 UNCLASSIFIED EXCAVATION CH. FROM KM 28+000 TO 30+000
CZ2EW1250 UNCLASSIFIED EXCAVATION CH. FROM KM 30+00 47 28-Feb-15 22-Apr-15 5 UNCLASSIFIED EXCAVATION CH. FROM KM 30+000 TO
CZ2EW1260 UNCLASSIFIED EXCAVATION CH. FROM KM 32+00 47 23-Apr-15 16-Jun-15 5 UNCLASSIFIED EXCAVATION CH. FROM KM 32+
CZ2EW1270 UNCLASSIFIED EXCAVATION CH. FROM KM 34+00 47 17-Jun-15 16-Aug-15 54 UNCLASSIFIED EXCAVATION CH. FROM
CZ2EW1280 UNCLASSIFIED EXCAVATION CH. FROM KM 36+00 47 17-Aug-15 14-Oct-15 54 UNCLASSIFIED EXCAVATION CH
CZ2EW1290 UNCLASSIFIED EXCAVATION CH. FROM KM 38+00 47 15-Oct-15 10-Dec-15 54 UNCLASSIFIED EXCAVAT
REMOVAL OF STRUCTURE
STRU & OBSTRUCTIONS 448 21-May-14 18-Nov-15 54 18-Nov-15, REMOVAL OF ST
CZ2EW1300 REMOVAL OF STRUCTURE & OBSTRUCTIONS CH 25 21-May-14 19-Jun-14 82 REMOVAL OF STRUCTURE & OBSTRUCTIONS CH. FROM KM 20+000 TO 22+000
CZ2EW1310 REMOVAL OF STRUCTURE & OBSTRUCTIONS CH 25 16-Jul-14 18-Aug-14 96 REMOVAL OF STRUCTURE & OBSTRUCTIONS CH. FROM KM 22+000 TO 24+000
CZ2EW1320 REMOVAL OF STRUCTURE & OBSTRUCTIONS CH 25 14-Sep-14 15-Oct-14 49 REMOVAL OF STRUCTURE & OBSTRUCTIONS CH. FROM KM 24+000 TO 26+000
CZ2EW1330 REMOVAL OF STRUCTURE & OBSTRUCTIONS CH 25 12-Nov-14 13-Dec-14 78 REMOVAL OF STRUCTURE & OBSTRUCTIONS CH. FROM KM 26+000 TO
CZ2EW1340 REMOVAL OF STRUCTURE & OBSTRUCTIONS CH 25 10-Jan-15 07-Feb-15 74 REMOVAL OF STRUCTURE & OBSTRUCTIONS CH. FROM KM 28+
CZ2EW1350 REMOVAL OF STRUCTURE & OBSTRUCTIONS CH 25 05-Mar-15 02-Apr-15 70 REMOVAL OF STRUCTURE & OBSTRUCTIONS CH. FROM
CZ2EW1360 REMOVAL OF STRUCTURE & OBSTRUCTIONS CH 25 29-Apr-15 27-May-15 66 REMOVAL OF STRUCTURE & OBSTRUCTIONS CH
CZ2EW1370 REMOVAL OF STRUCTURE & OBSTRUCTIONS CH 25 23-Jun-15 27-Jul-15 62 REMOVAL OF STRUCTURE & OBSTRUCTIO
CZ2EW1380 REMOVAL OF STRUCTURE & OBSTRUCTIONS CH 25 23-Aug-15 20-Sep-15 58 REMOVAL OF STRUCTURE & OBST
CZ2EW1390 REMOVAL OF STRUCTURE & OBSTRUCTIONS CH 25 21-Oct-15 18-Nov-15 54 REMOVAL OF STRUCTURE

Actual Work Critical Remaining Work Summary Page 26 of 57 TASK filter: All Activities

Remaining Work Milestone © Oracle Corporation


DUALIZATION OF MAHDAH - AL RAWDAH ROAD PROJECT Classic Schedule Layout 25-May-14 16:51

Activity ID Activity Name Original Start Finish Total Float Critical 2014 2015 2016
Duration
S Oct N D J F M Apr M J Jul A S Oct N D Jan F M Apr M J Jul A S Oct N D J F M Apr M J
EMBANKMENT FILLING
FILL 431 05-Aug-14 11-Jan-16 54 11-Jan-16, EMBANKM
CZ2EW1400 EMBANKMENT FILLING CH. FROM KM 20+000 TO 44 05-Aug-14 24-Sep-14 3 EMBANKMENT FILLING CH. FROM KM 20+000 TO 22+000
CZ2EW1410 EMBANKMENT FILLING CH. FROM KM 22+000 TO 43 25-Sep-14 18-Nov-14 21 EMBANKMENT FILLING CH. FROM KM 22+000 TO 24+000
CZ2EW1420 EMBANKMENT FILLING CH. FROM KM 24+000 TO 43 19-Nov-14 11-Jan-15 54 EMBANKMENT FILLING CH. FROM KM 24+000 TO 26+000
CZ2EW1430 EMBANKMENT FILLING CH. FROM KM 26+000 TO 43 12-Jan-15 02-Mar-15 54 EMBANKMENT FILLING CH. FROM KM 26+000 TO 28+000
CZ2EW1440 EMBANKMENT FILLING CH. FROM KM 28+000 TO 43 03-Mar-15 21-Apr-15 54 EMBANKMENT FILLING CH. FROM KM 28+000 TO 30+00
CZ2EW1450 EMBANKMENT FILLING CH. FROM KM 30+000 TO 43 22-Apr-15 10-Jun-15 54 EMBANKMENT FILLING CH. FROM KM 30+000 TO
CZ2EW1460 EMBANKMENT FILLING CH. FROM KM 32+000 TO 43 11-Jun-15 05-Aug-15 54 EMBANKMENT FILLING CH. FROM KM 32
CZ2EW1470 EMBANKMENT FILLING CH. FROM KM 34+000 TO 43 06-Aug-15 24-Sep-15 54 EMBANKMENT FILLING CH. FROM
CZ2EW1480 EMBANKMENT FILLING CH. FROM KM 36+000 TO 43 29-Sep-15 18-Nov-15 54 EMBANKMENT FILLING CH
CZ2EW1490 EMBANKMENT FILLING CH. FROM KM 38+000 TO 43 19-Nov-15 11-Jan-16 54 EMBANKMENT FILLI
SUB GRADE PREPARATION
PREPA IN CUT 401 02-Sep-14 04-Jan-16 60 04-Jan-16, SUB GRAD
CZ2EW1500 SUB GRADE PREPARATION IN CUT CH. FROM KM 41 02-Sep-14 22-Oct-14 3 SUB GRADE PREPARATION IN CUT CH. FROM KM 20+000 TO 22+000
CZ2EW1510 SUB GRADE PREPARATION IN CUT CH. FROM KM 40 23-Oct-14 11-Dec-14 3 SUB GRADE PREPARATION IN CUT CH. FROM KM 22+000 TO 24+000
CZ2EW1520 SUB GRADE PREPARATION IN CUT CH. FROM KM 40 13-Dec-14 28-Jan-15 57 SUB GRADE PREPARATION IN CUT CH. FROM KM 24+000 TO 26+0
CZ2EW1530 SUB GRADE PREPARATION IN CUT CH. FROM KM 40 29-Jan-15 16-Mar-15 57 SUB GRADE PREPARATION IN CUT CH. FROM KM 26+000 TO
CZ2EW1540 SUB GRADE PREPARATION IN CUT CH. FROM KM 40 17-Mar-15 02-May-15 57 SUB GRADE PREPARATION IN CUT CH. FROM KM 28+
CZ2EW1550 SUB GRADE PREPARATION IN CUT CH. FROM KM 40 03-May-15 17-Jun-15 57 SUB GRADE PREPARATION IN CUT CH. FROM K
CZ2EW1560 SUB GRADE PREPARATION IN CUT CH. FROM KM 40 18-Jun-15 09-Aug-15 57 SUB GRADE PREPARATION IN CUT CH. F
CZ2EW1570 SUB GRADE PREPARATION IN CUT CH. FROM KM 40 10-Aug-15 24-Sep-15 57 SUB GRADE PREPARATION IN CUT
CZ2EW1580 SUB GRADE PREPARATION IN CUT CH. FROM KM 40 29-Sep-15 15-Nov-15 57 SUB GRADE PREPARATION
CZ2EW1590 SUB GRADE PREPARATION IN CUT CH. FROM KM 40 16-Nov-15 04-Jan-16 60 SUB GRADE PREPAR
TRENCH EXCAVATION
EXCAVATIO AND BACK FILLING 475 14-Jun-14 14-Jan-16 51 14-Jan-16, TRENCH
CZ2EW1600 TRENCH EXCAVATION & BACKFILLING CH. FRO M 48 14-Jun-14 12-Aug-14 51 TRENCH EXCAVATION & BACKFILLING CH. FRO M KM 20+000 TO 22+000
CZ2EW1610 TRENCH EXCAVATION & BACKFILLING CH. FRO M 48 13-Aug-14 11-Oct-14 51 TRENCH EXCAVATION & BACKFILLING CH. FRO M KM 22+000 TO 24+000
CZ2EW1620 TRENCH EXCAVATION & BACKFILLING CH. FRO M 48 12-Oct-14 09-Dec-14 51 TRENCH EXCAVATION & BACKFILLING CH. FRO M KM 24+000 TO 26+000
CZ2EW1630 TRENCH EXCAVATION & BACKFILLING CH. FRO M 48 10-Dec-14 04-Feb-15 51 TRENCH EXCAVATION & BACKFILLING CH. FRO M KM 26+000 TO 2
CZ2EW1640 TRENCH EXCAVATION & BACKFILLING CH. FRO M 48 05-Feb-15 01-Apr-15 51 TRENCH EXCAVATION & BACKFILLING CH. FRO M KM 28+0
CZ2EW1650 TRENCH EXCAVATION & BACKFILLING CH. FRO M 47 02-Apr-15 26-May-15 51 TRENCH EXCAVATION & BACKFILLING CH. FRO M K
CZ2EW1660 TRENCH EXCAVATION & BACKFILLING CH. FRO M 47 27-May-15 26-Jul-15 51 TRENCH EXCAVATION & BACKFILLING CH.
CZ2EW1670 TRENCH EXCAVATION & BACKFILLING CH. FRO M 47 27-Jul-15 19-Sep-15 51 TRENCH EXCAVATION & BAC KFILL
CZ2EW1680 TRENCH EXCAVATION & BACKFILLING CH. FRO M 47 20-Sep-15 17-Nov-15 51 TRENCH EXCAVATION & BA
CZ2EW1690 TRENCH EXCAVATION & BACKFILLING CH. FRO M 47 18-Nov-15 14-Jan-16 51 TRENCH EXCAVATIO
AGGREGATE BASE COURSE 375 17-Nov-14 14-Feb-16 25 14-Feb-16, AGG
CZ2RW1000 AGGREGATE BASE COURSE CH. FROM KM 20+00 38 17-Nov-14 01-Jan-15 3 AGGREGATE BASE COURSE CH. FROM KM 20+000 TO 22+000
CZ2RW1010 AGGREGATE BASE COURSE CH. FROM KM 22+00 38 04-Jan-15 16-Feb-15 3 AGGREGATE BASE COURSE CH. FROM KM 22+000 TO 24+000
CZ2RW1020 AGGREGATE BASE COURSE CH. FROM KM 24+00 38 17-Feb-15 01-Apr-15 4 AGGREGATE BASE COURSE CH. FROM KM 24+000 TO 26+
CZ2RW1030 AGGREGATE BASE COURSE CH. FROM KM 26+00 38 02-Apr-15 16-May-15 4 AGGREGATE BASE COURSE CH. FROM KM 26+000 T
CZ2RW1040 AGGREGATE BASE COURSE CH. FROM KM 28+00 38 17-May-15 29-Jun-15 4 AGGREGATE BASE COURSE CH. FROM KM 28
CZ2RW1050 AGGREGATE BASE COURSE CH. FROM KM 30+00 37 30-Jun-15 17-Aug-15 4 AGGREGATE BASE COURSE CH. FROM
CZ2RW1060 AGGREGATE BASE COURSE CH. FROM KM 32+00 37 18-Aug-15 03-Oct-15 4 AGGREGATE BASE COURSE CH.
CZ2RW1070 AGGREGATE BASE COURSE CH. FROM KM 34+00 37 04-Oct-15 16-Nov-15 25 AGGREGATE BASE COURS
CZ2RW1080 AGGREGATE BASE COURSE CH. FROM KM 36+00 37 17-Nov-15 02-Jan-16 25 AGGREGATE BASE C
CZ2RW1090 AGGREGATE BASE COURSE CH. FROM KM 38+00 37 03-Jan-16 14-Feb-16 25 AGGREGATE BA
BITUMINOUS PAVEMENT
PAVEM 359 04-Jan-15 10-Mar-16 3 10-Mar-16, B
ASPHALT BASE COURSE
C 349 04-Jan-15 28-Feb-16 13 28-Feb-16, AS
CZ2RW1100 ASPHALT BASE COURSE CH. FROM KM 20+000 TO 35 04-Jan-15 12-Feb-15 3 ASPHALT BASE COURSE CH. FROM KM 20+000 TO 22+000
CZ2RW1110 ASPHALT BASE COURSE CH. FROM KM 22+000 TO 35 14-Feb-15 25-Mar-15 13 ASPHALT BASE COURSE CH. FROM KM 22+000 TO 24+000
CZ2RW1120 ASPHALT BASE COURSE CH. FROM KM 24+000 TO 35 26-Mar-15 05-May-15 13 ASPHALT BASE COURSE CH. FROM KM 24+000 TO 26
CZ2RW1130 ASPHALT BASE COURSE CH. FROM KM 26+000 TO 35 06-May-15 15-Jun-15 13 ASPHALT BASE COURSE CH. FROM KM 26+000 T
CZ2RW1140 ASPHALT BASE COURSE CH. FROM KM 28+000 TO 35 16-Jun-15 01-Aug-15 13 ASPHALT BASE COURSE CH. FROM KM 28

Actual Work Critical Remaining Work Summary Page 27 of 57 TASK filter: All Activities

Remaining Work Milestone © Oracle Corporation


DUALIZATION OF MAHDAH - AL RAWDAH ROAD PROJECT Classic Schedule Layout 25-May-14 16:51

Activity ID Activity Name Original Start Finish Total Float Critical 2014 2015 2016
Duration
S Oct N D J F M Apr M J Jul A S Oct N D Jan F M Apr M J Jul A S Oct N D J F M Apr M J
CZ2RW1150 ASPHALT BASE COURSE CH. FROM KM 30+000 TO 35 02-Aug-15 10-Sep-15 13 ASPHALT BASE COURSE CH. FROM
CZ2RW1160 ASPHALT BASE COURSE CH. FROM KM 32+000 TO 35 12-Sep-15 26-Oct-15 13 ASPHALT BASE COURSE CH. F
CZ2RW1170 ASPHALT BASE COURSE CH. FROM KM 34+000 TO 35 27-Oct-15 08-Dec-15 13 ASPHALT BASE COURSE
CZ2RW1180 ASPHALT BASE COURSE CH. FROM KM 36+000 TO 35 09-Dec-15 19-Jan-16 13 ASPHALT BASE CO
CZ2RW1190 ASPHALT BASE COURSE CH. FROM KM 38+000 TO 34 20-Jan-16 28-Feb-16 13 ASPHALT BAS
ASPHALT WEARING
WEARI COURSE 349 15-Jan-15 10-Mar-16 3 10-Mar-16, A
CZ2RW1200 ASPHALT WEARING COURSE CH. FROM KM 20+0 35 15-Jan-15 24-Feb-15 3 ASPHALT WEARING COURSE CH. FROM KM 20+000 TO 22+000
CZ2RW1210 ASPHALT WEARING COURSE CH. FROM KM 22+0 35 25-Feb-15 06-Apr-15 3 ASPHALT WEARING COURSE CH. FROM KM 22+000 TO 2
CZ2RW1220 ASPHALT WEARING COURSE CH. FROM KM 24+0 35 07-Apr-15 17-May-15 3 ASPHALT WEARING COURSE CH. FROM KM 24+000
CZ2RW1230 ASPHALT WEARING COURSE CH. FROM KM 26+0 35 18-May-15 27-Jun-15 3 ASPHALT WEARING COURSE CH. FROM KM 2
CZ2RW1240 ASPHALT WEARING COURSE CH. FROM KM 28+0 35 28-Jun-15 12-Aug-15 3 ASPHALT WEARING COURSE CH. FROM
CZ2RW1250 ASPHALT WEARING COURSE CH. FROM KM 30+0 35 13-Aug-15 22-Sep-15 3 ASPHALT WEARING COURSE CH. F
CZ2RW1260 ASPHALT WEARING COURSE CH. FROM KM 32+0 35 23-Sep-15 07-Nov-15 3 ASPHALT WEARING COURSE
CZ2RW1270 ASPHALT WEARING COURSE CH. FROM KM 34+0 35 08-Nov-15 20-Dec-15 3 ASPHALT WEARING CO
CZ2RW1280 ASPHALT WEARING COURSE CH. FROM KM 36+0 35 21-Dec-15 31-Jan-16 3 ASPHALT WEARIN
CZ2RW1290 ASPHALT WEARING COURSE CH. FROM KM 38+0 34 01-Feb-16 10-Mar-16 3 ASPHALT W
CONCRETE & CONCRETE
CONCRE STRUCTURES 386 10-Aug-14 21-Nov-15 58 21-Nov-15, CONCRETE & C
CONSTRUCTION OF BOX CULVERTS 386 10-Aug-14 21-Nov-15 58 21-Nov-15, CONSTRUCTIO
46.2CELL BOX CULVERT
CU @ CH 20+170 (2.0 x 2.0) 75 10-Aug-14 09-Nov-14 29 09-Nov-14, 46.2CELL BOX CULVERT @ CH 20+170 (2.0 x 2.0)
CZ2CU1000 46.2 EXCAVATION 4 10-Aug-14 13-Aug-14 9 46.2 EXCAVATION
CZ2CU1010 46.2 BLINDING CONCRETE 2 14-Aug-14 16-Aug-14 9 46.2 BLINDING CONCRETE
CZ2CU1020 46.2 CONSTRUCTION OF BASE SLABS 23 17-Aug-14 11-Sep-14 9 46.2 CONSTRUCTION OF BASE SLABS
CZ2CU1030 46.2 CONSTRUCTION OF WALLS & TOP SLABS 33 13-Sep-14 23-Oct-14 9 46.2 CONSTRUCTION OF WALLS & TOP SLABS
CZ2CU1040 46.2 CONSTRUCTION OF INLET & OUTLET 8 26-Oct-14 03-Nov-14 9 46.2 CONSTRUCTION OF INLET & OUTLET
CZ2CU1050 46.2 WATER PROOFING WORKS 9 30-Oct-14 09-Nov-14 29 46.2 WATER PROOFING WORKS
48.2CELL BOX CULVERT
CU @ CH 21+510 (2.0 x 1.5) 75 14-Aug-14 13-Nov-14 25 13-Nov-14, 48.2CELL BOX CULVERT @ CH 21+510 (2.0 x 1.5)
CZ2CU1060 48.2 EXCAVATION 3 14-Aug-14 17-Aug-14 9 48.2 EXCAVATION
CZ2CU1070 48.2 BLINDING CONCRETE 3 18-Aug-14 20-Aug-14 13 48.2 BLINDING CONCRETE
CZ2CU1080 48.2 CONSTRUCTION OF BASE SLABS 26 21-Aug-14 20-Sep-14 19 48.2 CONSTRUCTION OF BASE SLABS
CZ2CU1090 48.2 CONSTRUCTION OF WALLS & TOP SLABS 28 21-Sep-14 27-Oct-14 25 48.2 CONSTRUCTION OF WALLS & TOP SLABS
CZ2CU1100 48.2 CONSTRUCTION OF INLET & OUTLET 9 28-Oct-14 06-Nov-14 25 48.2 CONSTRUCTION OF INLET & OUTLET
CZ2CU1110 48.2 WATER PROOFING WORKS 10 03-Nov-14 13-Nov-14 25 48.2 WATER PROOFING WORKS
50.4CELL BOX CULVERT
CU @ CH 22+320 (3.0 x 2.0 ) 83 18-Aug-14 29-Nov-14 14 29-Nov-14, 50.4CELL BOX CULVERT @ CH 22+320 (3.0 x 2.0 )
CZ2CU1120 50.4 EXCAVATION 3 18-Aug-14 20-Aug-14 9 50.4 EXCAVATION
CZ2CU1130 50.4 BLINDING CONCRETE 3 21-Aug-14 24-Aug-14 13 50.4 BLINDING CONCRETE
CZ2CU1140 50.4 CONSTRUCTION OF BASE SLABS 28 25-Aug-14 25-Sep-14 14 50.4 CONSTRUCTION OF BASE SLABS
CZ2CU1150 50.4 CONSTRUCTION OF WALLS & TOP SLABS 34 27-Sep-14 09-Nov-14 14 50.4 CONSTRUCTION OF WALLS & TOP SLABS
CZ2CU1160 50.4 CONSTRUCTION OF INLET & OUTLET 10 10-Nov-14 20-Nov-14 14 50.4 CONSTRUCTION OF INLET & OUTLET
CZ2CU1170 50.4 WATER PROOFING WORKS 10 16-Nov-14 29-Nov-14 14 50.4 WATER PROOFING WORKS
63.4CELL BOX CULVERT
CU @ CH 27+275 (4.0 x 2.0) 68 21-Aug-14 12-Nov-14 26 12-Nov-14, 63.4CELL BOX CULVERT @ CH 27+275 (4.0 x 2.0)
CZ2CU1180 63.4 EXCAVATION 4 21-Aug-14 25-Aug-14 9 63.4 EXCAVATION
CZ2CU1190 63.4 BLINDING CONCRETE 2 26-Aug-14 27-Aug-14 12 63.4 BLINDING CONCRETE
CZ2CU1200 63.4 CONSTRUCTION OF BASE SLABS 23 28-Aug-14 23-Sep-14 26 63.4 CONSTRUCTION OF BASE SLABS
CZ2CU1210 63.4 CONSTRUCTION OF WALLS & TOP SLABS 34 24-Sep-14 06-Nov-14 26 63.4 CONSTRUCTION OF WALLS & TOP SLABS
CZ2CU1220 63.4 CONSTRUCTION OF INLET & OUTLET 10 27-Oct-14 06-Nov-14 26 63.4 CONSTRUCTION OF INLET & OUTLET
CZ2CU1230 63.4 WATER PROOFING WORKS 10 02-Nov-14 12-Nov-14 26 63.4 WATER PROOFING WORKS
64.4CELL BOX CULVERT
CU @ CH 27+378 (4.0 x 2.0) 78 26-Aug-14 01-Dec-14 12 01-Dec-14, 64.4CELL BOX CULVERT @ CH 27+378 (4.0 x 2.0)
CZ2CU1240 64.4 EXCAVATION 4 26-Aug-14 30-Aug-14 9 64.4 EXCAVATION
CZ2CU1250 64.4 BLINDING CONCRETE 2 31-Aug-14 01-Sep-14 10 64.4 BLINDING CONCRETE
CZ2CU1260 64.4 CONSTRUCTION OF BASE SLABS 23 02-Sep-14 28-Sep-14 12 64.4 CONSTRUCTION OF BASE SLABS
CZ2CU1270 64.4 CONSTRUCTION OF WALLS & TOP SLABS 34 29-Sep-14 11-Nov-14 12 64.4 CONSTRUCTION OF WALLS & TOP SLABS

Actual Work Critical Remaining Work Summary Page 28 of 57 TASK filter: All Activities

Remaining Work Milestone © Oracle Corporation


DUALIZATION OF MAHDAH - AL RAWDAH ROAD PROJECT Classic Schedule Layout 25-May-14 16:51

Activity ID Activity Name Original Start Finish Total Float Critical 2014 2015 2016
Duration
S Oct N D J F M Apr M J Jul A S Oct N D Jan F M Apr M J Jul A S Oct N D J F M Apr M J
CZ2CU1280 64.4 CONSTRUCTION OF INLET & OUTLET 10 12-Nov-14 25-Nov-14 12 64.4 CONSTRUCTION OF INLET & OUTLET
CZ2CU1290 64.4 WATER PROOFING WORKS 10 18-Nov-14 01-Dec-14 12 64.4 WATER PROOFING WORKS
65.4CELL BOX CULVERT
CU @ CH 27+470 (4.0 x 2.0) 76 31-Aug-14 03-Dec-14 10 03-Dec-14, 65.4CELL BOX CULVERT @ CH 27+470 (4.0 x 2.0)
CZ2CU1300 65.4 EXCAVATION 3 31-Aug-14 02-Sep-14 9 65.4 EXCAVATION
CZ2CU1310 65.4 BLINDING CONCRETE 3 03-Sep-14 06-Sep-14 9 65.4 BLINDING CONCRETE
CZ2CU1320 65.4 CONSTRUCTION OF BASE SLABS 23 07-Sep-14 02-Oct-14 10 65.4 CONSTRUCTION OF BASE SLABS
CZ2CU1330 65.4 CONSTRUCTION OF WALLS & TOP SLABS 33 07-Oct-14 15-Nov-14 10 65.4 CONSTRUCTION OF WALLS & TOP SLABS
CZ2CU1340 65.4 CONSTRUCTION OF INLET & OUTLET 11 16-Nov-14 30-Nov-14 10 65.4 CONSTRUCTION OF INLET & OUTLET
CZ2CU1350 65.4 WATER PROOFING WORKS 9 24-Nov-14 03-Dec-14 10 65.4 WATER PROOFING WORKS
73.2CELL BOX CULVERT
CU @ CH 30+040 (2.0 x 1.5) 74 03-Sep-14 04-Dec-14 9 04-Dec-14, 73.2CELL BOX CULVERT @ CH 30+040 (2.0 x 1.5)
CZ2CU1360 73.2 EXCAVATION 3 03-Sep-14 06-Sep-14 9 73.2 EXCAVATION
CZ2CU1370 73.2 BLINDING CONCRETE 3 07-Sep-14 09-Sep-14 9 73.2 BLINDING CONCRETE
CZ2CU1380 73.2 CONSTRUCTION OF BASE SLABS 23 10-Sep-14 09-Oct-14 9 73.2 CONSTRUCTION OF BASE SLABS
CZ2CU1390 73.2 CONSTRUCTION OF WALLS & TOP SLABS 31 11-Oct-14 16-Nov-14 9 73.2 CONSTRUCTION OF WALLS & TOP SLABS
CZ2CU1400 73.2 CONSTRUCTION OF INLET & OUTLET 9 17-Nov-14 29-Nov-14 9 73.2 CONSTRUCTION OF INLET & OUTLET
CZ2CU1410 73.2 WATER PROOFING WORKS 9 25-Nov-14 04-Dec-14 9 73.2 WATER PROOFING WORKS
74.3CELL BOX CULVERT
CU @ CH 30+330 (2.0 x 1.5) 89 07-Sep-14 25-Dec-14 125 25-Dec-14, 74.3CELL BOX CULVERT @ CH 30+330 (2.0 x 1.5)
CZ2CU1420 74.3 EXCAVATION 4 07-Sep-14 10-Sep-14 100 74.3 EXCAVATION
CZ2CU1430 74.3 BLINDING CONCRETE 2 11-Sep-14 13-Sep-14 115 74.3 BLINDING CONCRETE
CZ2CU1440 74.3 CONSTRUCTION OF BASE SLABS 27 14-Sep-14 18-Oct-14 115 74.3 CONSTRUCTION OF BASE SLABS
CZ2CU1450 74.3 CONSTRUCTION OF WALLS & TOP SLABS 41 19-Oct-14 08-Dec-14 115 74.3 CONSTRUCTION OF WALLS & TOP SLABS
CZ2CU1460 74.3 CONSTRUCTION OF INLET & OUTLET 10 09-Dec-14 20-Dec-14 115 74.3 CONSTRUCTION OF INLET & OUTLET
CZ2CU1470 74.3 WATER PROOFING WORKS 10 15-Dec-14 25-Dec-14 125 74.3 WATER PROOFING WORKS
75.12CELL BOX C
CULVERT @ CH 30+450 (2.0 x 1.5) 130 11-Sep-14 17-Feb-15 120 17-Feb-15, 75.12CELL BOX CULVERT @ CH 30+450 (2.0 x 1.5)
CZ2CU1480 75.12 EXCAVATION 5 11-Sep-14 16-Sep-14 100 75.12 EXCAVATION
CZ2CU1490 75.12 BLINDING CONCRETE 4 17-Sep-14 21-Sep-14 115 75.12 BLINDING CONCRETE
CZ2CU1500 75.12 CONSTRUCTION OF BASE SLABS 37 22-Sep-14 08-Nov-14 120 75.12 CONSTRUCTION OF BASE SLABS
CZ2CU1510 75.12 CONSTRUCTION OF WALLS & TOP SLABS 62 09-Nov-14 22-Jan-15 120 75.12 CONSTRUCTION OF WALLS & TOP SLABS
CZ2CU1520 75.12 CONSTRUCTION OF INLET & OUTLET 16 24-Jan-15 10-Feb-15 120 75.12 CONSTRUCTION OF INLET & OUTLET
CZ2CU1530 75.12 WATER PROOFING WORKS 17 29-Jan-15 17-Feb-15 120 75.12 WATER PROOFING WORKS
77.3CELL BOX CULVERT
CU @ CH 30+920 (2.0 x 1.5) 109 17-Sep-14 29-Jan-15 96 29-Jan-15, 77.3CELL BOX CULVERT @ CH 30+920 (2.0 x 1.5)
CZ2CU1540 77.3 EXCAVATION 3 17-Sep-14 20-Sep-14 100 77.3 EXCAVATION
CZ2CU1550 77.3 BLINDING CONCRETE 3 22-Sep-14 24-Sep-14 115 77.3 BLINDING CONCRETE
CZ2CU1560 77.3 CONSTRUCTION OF BASE SLABS 27 25-Sep-14 30-Oct-14 115 77.3 CONSTRUCTION OF BASE SLABS
CZ2CU1570 77.3 CONSTRUCTION OF WALLS & TOP SLABS 41 25-Nov-14 12-Jan-15 96 77.3 CONSTRUCTION OF WALLS & TOP SLABS
CZ2CU1580 77.3 CONSTRUCTION OF INLET & OUTLET 10 13-Jan-15 24-Jan-15 96 77.3 CONSTRUCTION OF INLET & OUTLET
CZ2CU1590 77.3 WATER PROOFING WORKS 10 19-Jan-15 29-Jan-15 96 77.3 WATER PROOFING WORKS
80.2CELL BOX CULVERT
CU @ CH 31+650 (2.0 x 1.5) 79 21-Sep-14 28-Dec-14 123 28-Dec-14, 80.2CELL BOX CULVERT @ CH 31+650 (2.0 x 1.5)
CZ2CU1600 80.2 EXCAVATION 3 21-Sep-14 23-Sep-14 100 80.2 EXCAVATION
CZ2CU1610 80.2 BLINDING CONCRETE 3 25-Sep-14 28-Sep-14 115 80.2 BLINDING CONCRETE
CZ2CU1620 80.2 CONSTRUCTION OF BASE SLABS 22 29-Sep-14 28-Oct-14 123 80.2 CONSTRUCTION OF BASE SLABS
CZ2CU1630 80.2 CONSTRUCTION OF WALLS & TOP SLABS 35 29-Oct-14 10-Dec-14 123 80.2 CONSTRUCTION OF WALLS & TOP SLABS
CZ2CU1640 80.2 CONSTRUCTION OF INLET & OUTLET 10 11-Dec-14 22-Dec-14 123 80.2 CONSTRUCTION OF INLET & OUTLET
CZ2CU1650 80.2 WATER PROOFING WORKS 10 17-Dec-14 28-Dec-14 123 80.2 WATER PROOFING WORKS
82.2CELL BOX CULVERT
CU @ CH 32+250 (2.0 x 1.5) 78 24-Sep-14 30-Dec-14 121 30-Dec-14, 82.2CELL BOX CULVERT @ CH 32+250 (2.0 x 1.5)
CZ2CU1660 82.2 EXCAVATION 4 24-Sep-14 28-Sep-14 100 82.2 EXCAVATION
CZ2CU1670 82.2 BLINDING CONCRETE 2 29-Sep-14 30-Sep-14 115 82.2 BLINDING CONCRETE
CZ2CU1680 82.2 CONSTRUCTION OF BASE SLABS 23 01-Oct-14 01-Nov-14 121 82.2 CONSTRUCTION OF BASE SLABS
CZ2CU1690 82.2 CONSTRUCTION OF WALLS & TOP SLABS 35 02-Nov-14 14-Dec-14 121 82.2 CONSTRUCTION OF WALLS & TOP SLABS
CZ2CU1700 82.2 CONSTRUCTION OF INLET & OUTLET 9 15-Dec-14 24-Dec-14 121 82.2 CONSTRUCTION OF INLET & OUTLET
CZ2CU1710 82.2 WATER PROOFING WORKS 9 21-Dec-14 30-Dec-14 121 82.2 WATER PROOFING WORKS

Actual Work Critical Remaining Work Summary Page 29 of 57 TASK filter: All Activities

Remaining Work Milestone © Oracle Corporation


DUALIZATION OF MAHDAH - AL RAWDAH ROAD PROJECT Classic Schedule Layout 25-May-14 16:51

Activity ID Activity Name Original Start Finish Total Float Critical 2014 2015 2016
Duration
S Oct N D J F M Apr M J Jul A S Oct N D Jan F M Apr M J Jul A S Oct N D J F M Apr M J
83.83CELL BOX C
CULVERT @ CH 32+800 (3.0 x 2.0) 150 29-Sep-14 30-Mar-15 125 30-Mar-15, 83.83CELL BOX CULVERT @ CH 32+800 (3.0 x 2.
CZ2CU1720 83.83 EXCAVATION 7 29-Sep-14 09-Oct-14 100 83.83 EXCAVATION
CZ2CU1730 83.83 BLINDING CONCRETE 5 11-Oct-14 15-Oct-14 110 83.83 BLINDING CONCRETE
CZ2CU1740 83.83 CONSTRUCTION OF BASE SLABS 43 16-Oct-14 08-Dec-14 125 83.83 CONSTRUCTION OF BASE SLABS
CZ2CU1750 83.83 CONSTRUCTION OF WALLS & TOP SLABS 71 09-Dec-14 02-Mar-15 125 83.83 CONSTRUCTION OF WALLS & TOP SLABS
CZ2CU1760 83.83 CONSTRUCTION OF INLET & OUTLET 19 03-Mar-15 24-Mar-15 125 83.83 CONSTRUCTION OF INLET & OUTLET
CZ2CU1770 83.83 WATER PROOFING WORKS 19 09-Mar-15 30-Mar-15 125 83.83 WATER PROOFING WORKS
84.5CELL BOX CULVERT
CU @ CH 33+134 (3.0 x 2.0) 115 11-Oct-14 25-Feb-15 113 25-Feb-15, 84.5CELL BOX CULVERT @ CH 33+134 (3.0 x 2.0)
CZ2CU1780 84.5 EXCAVATION 5 11-Oct-14 15-Oct-14 100 84.5 EXCAVATION
CZ2CU1790 84.5 BLINDING CONCRETE 4 16-Oct-14 20-Oct-14 110 84.5 BLINDING CONCRETE
CZ2CU1800 84.5 CONSTRUCTION OF BASE SLABS 32 21-Oct-14 30-Nov-14 113 84.5 CONSTRUCTION OF BASE SLABS
CZ2CU1810 84.5 CONSTRUCTION OF WALLS & TOP SLABS 54 01-Dec-14 02-Feb-15 113 84.5 CONSTRUCTION OF WALLS & TOP SLABS
CZ2CU1820 84.5 CONSTRUCTION OF INLET & OUTLET 15 03-Feb-15 19-Feb-15 113 84.5 CONSTRUCTION OF INLET & OUTLET
CZ2CU1830 84.5 WATER PROOFING WORKS 14 10-Feb-15 25-Feb-15 113 84.5 WATER PROOFING WORKS
85.26CELL BOX C
CULVERT @ CH33+217 (3.0 x 2.0) 148 16-Oct-14 11-Apr-15 115 11-Apr-15, 85.26CELL BOX CULVERT @ CH33+217 (3.0 x 2
CZ2CU1840 85.26 EXCAVATION 7 16-Oct-14 23-Oct-14 100 85.26 EXCAVATION
CZ2CU1850 85.26 BLINDING CONCRETE 5 26-Oct-14 30-Oct-14 107 85.26 BLINDING CONCRETE
CZ2CU1860 85.26 CONSTRUCTION OF BASE SLABS 42 01-Nov-14 21-Dec-14 115 85.26 CONSTRUCTION OF BASE SLABS
CZ2CU1870 85.26 CONSTRUCTION OF WALLS & TOP SLABS 71 22-Dec-14 15-Mar-15 115 85.26 CONSTRUCTION OF WALLS & TOP SLABS
CZ2CU1880 85.26 CONSTRUCTION OF INLET & OUTLET 18 16-Mar-15 05-Apr-15 115 85.26 CONSTRUCTION OF INLET & OUTLET
CZ2CU1890 85.26 WATER PROOFING WORKS 18 22-Mar-15 11-Apr-15 115 85.26 WATER PROOFING WORKS
86.2CELL BOX CULVERT
CU @ CH33+440 ( 2.0 x 1.5) 77 26-Oct-14 26-Jan-15 139 26-Jan-15, 86.2CELL BOX CULVERT @ CH33+440 ( 2.0 x 1.5)
CZ2CU1900 86.2 EXCAVATION 3 26-Oct-14 28-Oct-14 100 86.2 EXCAVATION
CZ2CU1910 86.2 BLINDING CONCRETE 3 29-Oct-14 01-Nov-14 106 86.2 BLINDING CONCRETE
CZ2CU1920 86.2 CONSTRUCTION OF BASE SLABS 21 02-Nov-14 27-Nov-14 130 86.2 CONSTRUCTION OF BASE SLABS
CZ2CU1930 86.2 CONSTRUCTION OF WALLS & TOP SLABS 36 29-Nov-14 10-Jan-15 130 86.2 CONSTRUCTION OF WALLS & TOP SLABS
CZ2CU1940 86.2 CONSTRUCTION OF INLET & OUTLET 9 11-Jan-15 20-Jan-15 139 86.2 CONSTRUCTION OF INLET & OUTLET
CZ2CU1950 86.2 WATER PROOFING WORKS 9 17-Jan-15 26-Jan-15 139 86.2 WATER PROOFING WORKS
87.2CELL BOX CULVERT
CU @ CH 33+590 (2.0 x 1.5) 78 29-Oct-14 31-Jan-15 135 31-Jan-15, 87.2CELL BOX CULVERT @ CH 33+590 (2.0 x 1.5)
CZ2CU1960 87.2 EXCAVATION 3 29-Oct-14 01-Nov-14 100 87.2 EXCAVATION
CZ2CU1970 87.2 BLINDING CONCRETE 2 02-Nov-14 03-Nov-14 106 87.2 BLINDING CONCRETE
CZ2CU1980 87.2 CONSTRUCTION OF BASE SLABS 22 04-Nov-14 01-Dec-14 135 87.2 CONSTRUCTION OF BASE SLABS
CZ2CU1990 87.2 CONSTRUCTION OF WALLS & TOP SLABS 36 02-Dec-14 13-Jan-15 135 87.2 CONSTRUCTION OF WALLS & TOP SLABS
CZ2CU2000 87.2 CONSTRUCTION OF INLET & OUTLET 10 14-Jan-15 25-Jan-15 135 87.2 CONSTRUCTION OF INLET & OUTLET
CZ2CU2010 87.2 WATER PROOFING WORKS 11 19-Jan-15 31-Jan-15 135 87.2 WATER PROOFING WORKS
88.2CELL BOX CULVERT
CU @ CH 33+730 (2.0 x1.5) 78 02-Nov-14 03-Feb-15 132 03-Feb-15, 88.2CELL BOX CULVERT @ CH 33+730 (2.0 x1.5)
CZ2CU2020 88.2 EXCAVATION 3 02-Nov-14 04-Nov-14 100 88.2 EXCAVATION
CZ2CU2030 88.2 BLINDING CONCRETE 2 05-Nov-14 06-Nov-14 105 88.2 BLINDING CONCRETE
CZ2CU2040 88.2 CONSTRUCTION OF BASE SLABS 23 08-Nov-14 06-Dec-14 132 88.2 CONSTRUCTION OF BASE SLABS
CZ2CU2050 88.2 CONSTRUCTION OF WALLS & TOP SLABS 36 07-Dec-14 18-Jan-15 132 88.2 CONSTRUCTION OF WALLS & TOP SLABS
CZ2CU2060 88.2 CONSTRUCTION OF INLET & OUTLET 9 19-Jan-15 28-Jan-15 132 88.2 CONSTRUCTION OF INLET & OUTLET
CZ2CU2070 88.2 WATER PROOFING WORKS 11 22-Jan-15 03-Feb-15 132 88.2 WATER PROOFING WORKS
90.2CELL BOX CULVERT
CU @ CH 34+242 (2.0 x 1.5) 79 05-Nov-14 08-Feb-15 128 08-Feb-15, 90.2CELL BOX CULVERT @ CH 34+242 (2.0 x 1.5)
CZ2CU2080 90.2 EXCAVATION 3 05-Nov-14 08-Nov-14 100 90.2 EXCAVATION
CZ2CU2090 90.2 BLINDING CONCRETE 3 09-Nov-14 11-Nov-14 104 90.2 BLINDING CONCRETE
CZ2CU2100 90.2 CONSTRUCTION OF BASE SLABS 22 12-Nov-14 09-Dec-14 128 90.2 CONSTRUCTION OF BASE SLABS
CZ2CU2110 90.2 CONSTRUCTION OF WALLS & TOP SLABS 36 10-Dec-14 21-Jan-15 128 90.2 CONSTRUCTION OF WALLS & TOP SLABS
CZ2CU2120 90.2 CONSTRUCTION OF INLET & OUTLET 10 22-Jan-15 02-Feb-15 128 90.2 CONSTRUCTION OF INLET & OUTLET
CZ2CU2130 90.2 WATER PROOFING WORKS 10 28-Jan-15 08-Feb-15 128 90.2 WATER PROOFING WORKS
91.2CELL BOX CULVERT
CU @ CH34+522 (2.0 x 1.5) 79 09-Nov-14 11-Feb-15 125 11-Feb-15, 91.2CELL BOX CULVERT @ CH34+522 (2.0 x 1.5)
CZ2CU2140 91.2 EXCAVATION 3 09-Nov-14 11-Nov-14 100 91.2 EXCAVATION

Actual Work Critical Remaining Work Summary Page 30 of 57 TASK filter: All Activities

Remaining Work Milestone © Oracle Corporation


DUALIZATION OF MAHDAH - AL RAWDAH ROAD PROJECT Classic Schedule Layout 25-May-14 16:51

Activity ID Activity Name Original Start Finish Total Float Critical 2014 2015 2016
Duration
S Oct N D J F M Apr M J Jul A S Oct N D Jan F M Apr M J Jul A S Oct N D J F M Apr M J
CZ2CU2150 91.2 BLINDING CONCRETE 3 12-Nov-14 15-Nov-14 104 91.2 BLINDING CONCRETE
CZ2CU2160 91.2 CONSTRUCTION OF BASE SLABS 22 16-Nov-14 13-Dec-14 117 91.2 CONSTRUCTION OF BASE SLABS
CZ2CU2170 91.2 CONSTRUCTION OF WALLS & TOP SLABS 36 14-Dec-14 25-Jan-15 117 91.2 CONSTRUCTION OF WALLS & TOP SLABS
CZ2CU2180 91.2 CONSTRUCTION OF INLET & OUTLET 10 26-Jan-15 05-Feb-15 125 91.2 CONSTRUCTION OF INLET & OUTLET
CZ2CU2190 91.2 WATER PROOFING WORKS 10 01-Feb-15 11-Feb-15 125 91.2 WATER PROOFING WORKS
92.2CELL BOX CULVERT
CU @ CH34+640 ( 2.0 x 1.5) 79 12-Nov-14 15-Feb-15 122 15-Feb-15, 92.2CELL BOX CULVERT @ CH34+640 ( 2.0 x 1.5)
CZ2CU2200 92.2 EXCAVATION 4 12-Nov-14 16-Nov-14 100 92.2 EXCAVATION
CZ2CU2210 92.2 BLINDING CONCRETE 2 17-Nov-14 18-Nov-14 103 92.2 BLINDING CONCRETE
CZ2CU2220 92.2 CONSTRUCTION OF BASE SLABS 23 19-Nov-14 17-Dec-14 113 92.2 CONSTRUCTION OF BASE SLABS
CZ2CU2230 92.2 CONSTRUCTION OF WALLS & TOP SLABS 36 18-Dec-14 29-Jan-15 113 92.2 CONSTRUCTION OF WALLS & TOP SLABS
CZ2CU2240 92.2 CONSTRUCTION OF INLET & OUTLET 9 31-Jan-15 09-Feb-15 122 92.2 CONSTRUCTION OF INLET & OUTLET
CZ2CU2250 92.2 WATER PROOFING WORKS 9 05-Feb-15 15-Feb-15 122 92.2 WATER PROOFING WORKS
93.2CELL BOX CULVERT
CU @ CH 34+730 (2.0 x 1.5) 79 17-Nov-14 19-Feb-15 118 19-Feb-15, 93.2CELL BOX CULVERT @ CH 34+730 (2.0 x 1.5)
CZ2CU2260 93.2 EXCAVATION 3 17-Nov-14 19-Nov-14 100 93.2 EXCAVATION
CZ2CU2270 93.2 BLINDING CONCRETE 3 20-Nov-14 25-Nov-14 102 93.2 BLINDING CONCRETE
CZ2CU2280 93.2 CONSTRUCTION OF BASE SLABS 22 26-Nov-14 21-Dec-14 110 93.2 CONSTRUCTION OF BASE SLABS
CZ2CU2290 93.2 CONSTRUCTION OF WALLS & TOP SLABS 36 22-Dec-14 02-Feb-15 110 93.2 CONSTRUCTION OF WALLS & TOP SLABS
CZ2CU2300 93.2 CONSTRUCTION OF INLET & OUTLET 10 03-Feb-15 14-Feb-15 118 93.2 CONSTRUCTION OF INLET & OUTLET
CZ2CU2310 93.2 WATER PROOFING WORKS 11 08-Feb-15 19-Feb-15 118 93.2 WATER PROOFING WORKS
94.3CELL BOX CULVERT
CU @ CH 34+900 (2.0 x 1.5) 79 20-Nov-14 23-Feb-15 115 23-Feb-15, 94.3CELL BOX CULVERT @ CH 34+900 (2.0 x 1.5)
CZ2CU2320 94.3 EXCAVATION 4 20-Nov-14 26-Nov-14 100 94.3 EXCAVATION
CZ2CU2330 94.3 BLINDING CONCRETE 2 27-Nov-14 29-Nov-14 101 94.3 BLINDING CONCRETE
CZ2CU2340 94.3 CONSTRUCTION OF BASE SLABS 22 30-Nov-14 24-Dec-14 107 94.3 CONSTRUCTION OF BASE SLABS
CZ2CU2350 94.3 CONSTRUCTION OF WALLS & TOP SLABS 36 25-Dec-14 05-Feb-15 107 94.3 CONSTRUCTION OF WALLS & TOP SLABS
CZ2CU2360 94.3 CONSTRUCTION OF INLET & OUTLET 10 07-Feb-15 17-Feb-15 115 94.3 CONSTRUCTION OF INLET & OUTLET
CZ2CU2370 94.3 WATER PROOFING WORKS 10 12-Feb-15 23-Feb-15 115 94.3 WATER PROOFING WORKS
95.3CELL BOX CULVERT
CU @ CH 35+100 (2.0 x 1.5) 78 27-Nov-14 26-Feb-15 112 26-Feb-15, 95.3CELL BOX CULVERT @ CH 35+100 (2.0 x 1.5)
CZ2CU2380 95.3 EXCAVATION 3 27-Nov-14 30-Nov-14 100 95.3 EXCAVATION
CZ2CU2390 95.3 BLINDING CONCRETE 3 01-Dec-14 03-Dec-14 100 95.3 BLINDING CONCRETE
CZ2CU2400 95.3 CONSTRUCTION OF BASE SLABS 22 04-Dec-14 29-Dec-14 103 95.3 CONSTRUCTION OF BASE SLABS
CZ2CU2410 95.3 CONSTRUCTION OF WALLS & TOP SLABS 36 30-Dec-14 10-Feb-15 103 95.3 CONSTRUCTION OF WALLS & TOP SLABS
CZ2CU2420 95.3 CONSTRUCTION OF INLET & OUTLET 9 11-Feb-15 21-Feb-15 112 95.3 CONSTRUCTION OF INLET & OUTLET
CZ2CU2430 95.3 WATER PROOFING WORKS 9 17-Feb-15 26-Feb-15 112 95.3 WATER PROOFING WORKS
96.2CELL BOX CULVERT
CU @ CH35+320 ( 2.0 x 1.5) 79 01-Dec-14 03-Mar-15 108 03-Mar-15, 96.2CELL BOX CULVERT @ CH35+320 ( 2.0 x 1.5)
CZ2CU2440 96.2 EXCAVATION 3 01-Dec-14 03-Dec-14 100 96.2 EXCAVATION
CZ2CU2450 96.2 BLINDING CONCRETE 3 04-Dec-14 07-Dec-14 100 96.2 BLINDING CONCRETE
CZ2CU2460 96.2 CONSTRUCTION OF BASE SLABS 22 08-Dec-14 01-Jan-15 100 96.2 CONSTRUCTION OF BASE SLABS
CZ2CU2470 96.2 CONSTRUCTION OF WALLS & TOP SLABS 36 04-Jan-15 14-Feb-15 100 96.2 CONSTRUCTION OF WALLS & TOP SLABS
CZ2CU2480 96.2 CONSTRUCTION OF INLET & OUTLET 10 15-Feb-15 25-Feb-15 108 96.2 CONSTRUCTION OF INLET & OUTLET
CZ2CU2490 96.2 WATER PROOFING WORKS 10 21-Feb-15 03-Mar-15 108 96.2 WATER PROOFING WORKS
98.4CELL BOX CULVERT
CU @ CH36+230 (2.0 x 1.5) 114 04-Dec-14 16-Apr-15 100 16-Apr-15, 98.4CELL BOX CULVERT @ CH36+230 (2.0 x 1.
CZ2CU2500 98.4 EXCAVATION 4 04-Dec-14 08-Dec-14 105 98.4 EXCAVATION
CZ2CU2510 98.4 BLINDING CONCRETE 2 09-Dec-14 10-Dec-14 113 98.4 BLINDING CONCRETE
CZ2CU2520 98.4 CONSTRUCTION OF BASE SLABS 24 18-Jan-15 14-Feb-15 100 98.4 CONSTRUCTION OF BASE SLABS
CZ2CU2530 98.4 CONSTRUCTION OF WALLS & TOP SLABS 37 15-Feb-15 29-Mar-15 100 98.4 CONSTRUCTION OF WALLS & TOP SLABS
CZ2CU2540 98.4 CONSTRUCTION OF INLET & OUTLET 11 30-Mar-15 11-Apr-15 100 98.4 CONSTRUCTION OF INLET & OUTLET
CZ2CU2550 98.4 WATER PROOFING WORKS 11 05-Apr-15 16-Apr-15 100 98.4 WATER PROOFING WORKS
99.9CELL BOX CULVERT
CU @ CH 36+520 (2.0 x 1.5) 142 09-Dec-14 24-May-15 118 24-May-15, 99.9CELL BOX CULVERT @ CH 36+520 (2
CZ2CU2560 99.9 EXCAVATION 6 09-Dec-14 15-Dec-14 105 99.9 EXCAVATION
CZ2CU2570 99.9 BLINDING CONCRETE 4 16-Dec-14 20-Dec-14 109 99.9 BLINDING CONCRETE
CZ2CU2580 99.9 CONSTRUCTION OF BASE SLABS 39 30-Dec-14 14-Feb-15 105 99.9 CONSTRUCTION OF BASE SLABS

Actual Work Critical Remaining Work Summary Page 31 of 57 TASK filter: All Activities

Remaining Work Milestone © Oracle Corporation


DUALIZATION OF MAHDAH - AL RAWDAH ROAD PROJECT Classic Schedule Layout 25-May-14 16:51

Activity ID Activity Name Original Start Finish Total Float Critical 2014 2015 2016
Duration
S Oct N D J F M Apr M J Jul A S Oct N D Jan F M Apr M J Jul A S Oct N D J F M Apr M J
CZ2CU2590 99.9 CONSTRUCTION OF WALLS & TOP SLABS 62 15-Feb-15 27-Apr-15 105 99.9 CONSTRUCTION OF WALLS & TOP SLABS
CZ2CU2600 99.9 CONSTRUCTION OF INLET & OUTLET 17 28-Apr-15 17-May-15 105 99.9 CONSTRUCTION OF INLET & OUTLET
CZ2CU2610 99.9 WATER PROOFING WORKS 18 04-May-15 24-May-15 118 99.9 WATER PROOFING WORKS
101.5CELL BOX C
CULVERT @ CH 36+840 (2.0 x 1.5) 118 16-Dec-14 03-May-15 136 03-May-15, 101.5CELL BOX CULVERT @ CH 36+840 (2.0
CZ2CU2620 101.5 EXCAVATION 5 16-Dec-14 21-Dec-14 105 101.5 EXCAVATION
CZ2CU2630 101.5 BLINDING CONCRETE 4 22-Dec-14 25-Dec-14 108 101.5 BLINDING CONCRETE
CZ2CU2640 101.5 CONSTRUCTION OF BASE SLABS 34 27-Dec-14 04-Feb-15 138 101.5 CONSTRUCTION OF BASE SLABS
CZ2CU2650 101.5 CONSTRUCTION OF WALLS & TOP SLABS 54 05-Feb-15 08-Apr-15 138 101.5 CONSTRUCTION OF WALLS & TOP SLABS
CZ2CU2660 101.5 CONSTRUCTION OF INLET & OUTLET 14 12-Apr-15 27-Apr-15 136 101.5 CONSTRUCTION OF INLET & OUTLET
CZ2CU2670 101.5 WATER PROOFING WORKS 14 18-Apr-15 03-May-15 136 101.5 WATER PROOFING WORKS
102.15CELL BOX CULVERT @ CH 37+350 (3.0 x 2.0) 144 22-Dec-14 08-Jun-15 105 08-Jun-15, 102.15CELL BOX CULVERT @ CH 37+35
CZ2CU2680 102.15 EXCAVATION 7 22-Dec-14 29-Dec-14 105 102.15 EXCAVATION
CZ2CU2690 102.15 BLINDING CONCRETE 4 30-Dec-14 04-Jan-15 105 102.15 BLINDING CONCRETE
CZ2CU2700 102.15 CONSTRUCTION OF BASE SLABS 44 05-Jan-15 24-Feb-15 105 102.15 CONSTRUCTION OF BASE SLABS
CZ2CU2710 102.15 CONSTRUCTION OF WALLS & TOP SLABS 70 25-Feb-15 17-May-15 105 102.15 CONSTRUCTION OF WALLS & TOP SLABS
CZ2CU2720 102.15 CONSTRUCTION OF INLET & OUTLET 14 18-May-15 02-Jun-15 105 102.15 CONSTRUCTION OF INLET & OUTLET
CZ2CU2730 102.15 WATER PROOFING WORKS 16 21-May-15 08-Jun-15 105 102.15 WATER PROOFING WORKS
104.3CELL BOX C
CULVERT @ CH 38+080 (2.0 x 1.5) 102 30-Dec-14 28-Apr-15 100 28-Apr-15, 104.3CELL BOX CULVERT @ CH 38+080 (2.0
CZ2CU2740 104.3 EXCAVATION 3 30-Dec-14 01-Jan-15 120 104.3 EXCAVATION
CZ2CU2750 104.3 BLINDING CONCRETE 3 04-Jan-15 06-Jan-15 121 104.3 BLINDING CONCRETE
CZ2CU2760 104.3 CONSTRUCTION OF BASE SLABS 22 07-Jan-15 01-Feb-15 123 104.3 CONSTRUCTION OF BASE SLABS
CZ2CU2770 104.3 CONSTRUCTION OF WALLS & TOP SLABS 36 02-Feb-15 15-Mar-15 123 104.3 CONSTRUCTION OF WALLS & TOP SLABS
CZ2CU2780 104.3 CONSTRUCTION OF INLET & OUTLET 10 12-Apr-15 22-Apr-15 100 104.3 CONSTRUCTION OF INLET & OUTLET
CZ2CU2790 104.3 WATER PROOFING WORKS 10 18-Apr-15 28-Apr-15 100 104.3 WATER PROOFING WORKS
108.2CELL BOX C
CULVERT @ CH 39+107 (2.0 x 1.5 ) 99 04-Jan-15 28-Apr-15 100 28-Apr-15, 108.2CELL BOX CULVERT @ CH 39+107 (2.0
CZ2CU2800 108.2 EXCAVATION 4 04-Jan-15 07-Jan-15 120 108.2 EXCAVATION
CZ2CU2810 108.2 BLINDING CONCRETE 2 08-Jan-15 10-Jan-15 120 108.2 BLINDING CONCRETE
CZ2CU2820 108.2 CONSTRUCTION OF BASE SLABS 23 11-Jan-15 05-Feb-15 120 108.2 CONSTRUCTION OF BASE SLABS
CZ2CU2830 108.2 CONSTRUCTION OF WALLS & TOP SLABS 36 07-Feb-15 19-Mar-15 120 108.2 CONSTRUCTION OF WALLS & TOP SLABS
CZ2CU2840 108.2 CONSTRUCTION OF INLET & OUTLET 9 13-Apr-15 22-Apr-15 100 108.2 CONSTRUCTION OF INLET & OUTLET
CZ2CU2850 108.2 WATER PROOFING WORKS 9 19-Apr-15 28-Apr-15 100 108.2 WATER PROOFING WORKS
SINGLE CELL CULVERTS
CU - 30NOS 322 28-Oct-14 21-Nov-15 58 21-Nov-15, SINGLE CELL C
PRE CASTING FOR CULVERTS INCLUDING WATER P/F. 194 28-Oct-14 14-Jun-15 160 14-Jun-15, PRE CASTING FOR CULVERTS INCLU
CZ2CU2860 PART 2 PRECAST FOR CULVERTS INCLUDING WA 20 28-Oct-14 19-Nov-14 9 PART 2 PRECAST FOR CULVERTS INCLUDING WATER P/F. NOS 1,2,3
CZ2CU2870 PART 2 PRECAST FOR CULVERTS INCLUDING WA 20 20-Nov-14 15-Dec-14 16 PART 2 PRECAST FOR CULVERTS INCLUDING WATER P/F. NOS 4,5,6
CZ2CU2880 PART 2 PRECAST FOR CULVERTS INCLUDING WA 20 16-Dec-14 08-Jan-15 32 PART 2 PRECAST FOR CULVERTS INCLUDING WATER P/F. NOS 7,8,9
CZ2CU2890 PART 2 PRECAST FOR CULVERTS INCLUDING WA 20 10-Jan-15 01-Feb-15 43 PART 2 PRECAST FOR CULVERTS INCLUDING WATER P/F. NOS 10
CZ2CU2900 PART 2 PRECAST FOR CULVERTS INCLUDING WA 19 02-Feb-15 23-Feb-15 55 PART 2 PRECAST FOR CULVERTS INCLUDING WATER P/F. NOS
CZ2CU2910 PART 2 PRECAST FOR CULVERTS INCLUDING WA 19 24-Feb-15 17-Mar-15 67 PART 2 PRECAST FOR CULVERTS INCLUDING WATER P/F. N
CZ2CU2920 PART 2 PRECAST FOR CULVERTS INCLUDING WA 19 18-Mar-15 08-Apr-15 85 PART 2 PRECAST FOR CULVERTS INCLUDING WATER P/
CZ2CU2930 PART 2 PRECAST FOR CULVERTS INCLUDING WA 19 09-Apr-15 30-Apr-15 103 PART 2 PRECAST FOR CULVERTS INCLUDING WATER
CZ2CU2940 PART 2 PRECAST FOR CULVERTS INCLUDING WA 19 02-May-15 23-May-15 142 PART 2 PRECAST FOR CULVERTS INCLUDING WAT
CZ2CU2950 PART 2 PRECAST FOR CULVERTS INCLUDING WA 19 24-May-15 14-Jun-15 160 PART 2 PRECAST FOR CULVERTS INCLUDING W
EXCAVAT ION OF
O CULVERTS 270 01-Nov-14 20-Sep-15 107 20-Sep-15, EXCAVATION OF CULVE
CZ2CU2960 PART 2 EXCAVATION OF CULVERTS NOS 1,2,3 27 01-Nov-14 03-Dec-14 9 PART 2 EXCAVATION OF CULVERTS NOS 1,2,3
CZ2CU2970 PART 2 EXCAVATION OF CULVERTS NOS 4,5,6 27 04-Dec-14 05-Jan-15 107 PART 2 EXCAVATION OF CULVERTS NOS 4,5,6
CZ2CU2980 PART 2 EXCAVATION OF CULVERTS NOS 7,8,9 27 06-Jan-15 05-Feb-15 107 PART 2 EXCAVATION OF CULVERTS NOS 7,8,9
CZ2CU2990 PART 2 EXCAVATION OF CULVERTS NOS 10,11,12 27 07-Feb-15 09-Mar-15 107 PART 2 EXCAVATION OF CULVERTS NOS 10,11,12
CZ2CU3000 PART 2 EXCAVATION OF CULVERTS NOS 13,14,15 27 10-Mar-15 09-Apr-15 107 PART 2 EXCAVATION OF CULVERTS NOS 13,14,15
CZ2CU3010 PART 2 EXCAVATION OF CULVERTS NOS 16,17,18 27 11-Apr-15 11-May-15 107 PART 2 EXCAVATION OF CULVERTS NOS 16,17,18
CZ2CU3020 PART 2 EXCAVATION OF CULVERTS NOS 19,20,21 27 12-May-15 11-Jun-15 107 PART 2 EXCAVATION OF CULVERTS NOS 19,20,2

Actual Work Critical Remaining Work Summary Page 32 of 57 TASK filter: All Activities

Remaining Work Milestone © Oracle Corporation


DUALIZATION OF MAHDAH - AL RAWDAH ROAD PROJECT Classic Schedule Layout 25-May-14 16:51

Activity ID Activity Name Original Start Finish Total Float Critical 2014 2015 2016
Duration
S Oct N D J F M Apr M J Jul A S Oct N D Jan F M Apr M J Jul A S Oct N D J F M Apr M J
CZ2CU3030 PART 2 EXCAVATION OF CULVERTS NOS 22,23,24 27 13-Jun-15 13-Jul-15 107 PART 2 EXCAVATION OF CULVERTS NOS 22,
CZ2CU3040 PART 2 EXCAVATION OF CULVERTS NOS 25,26,27 27 14-Jul-15 19-Aug-15 107 PART 2 EXCAVATION OF CULVERTS NO
CZ2CU3050 PART 2 EXCAVATION OF CULVERTS NOS 28,29,30 27 20-Aug-15 20-Sep-15 107 PART 2 EXCAVATION OF CULVERTS
BLINDING FOR CULVERTS 270 03-Nov-14 22-Sep-15 105 22-Sep-15, BLINDING FOR CULVER
CZ2CU3060 PART 2 BLINDING FOR CULVERTS NOS 1,2,3 27 03-Nov-14 06-Dec-14 9 PART 2 BLINDING FOR CULVERTS NOS 1,2,3
CZ2CU3070 PART 2 BLINDING FOR CULVERTS NOS 4,5,6 27 07-Dec-14 07-Jan-15 32 PART 2 BLINDING FOR CULVERTS NOS 4,5,6
CZ2CU3080 PART 2 BLINDING FOR CULVERTS NOS 7,8,9 27 08-Jan-15 08-Feb-15 32 PART 2 BLINDING FOR CULVERTS NOS 7,8,9
CZ2CU3090 PART 2 BLINDING FOR CULVERTS NOS 10,11,12 27 09-Feb-15 11-Mar-15 36 PART 2 BLINDING FOR CULVERTS NOS 10,11,12
CZ2CU3100 PART 2 BLINDING FOR CULVERTS NOS 13,14,15 27 12-Mar-15 12-Apr-15 40 PART 2 BLINDING FOR CULVERTS NOS 13,14,15
CZ2CU3110 PART 2 BLINDING FOR CULVERTS NOS 16,17,18 27 13-Apr-15 13-May-15 44 PART 2 BLINDING FOR CULVERTS NOS 16,17,18
CZ2CU3120 PART 2 BLINDING FOR CULVERTS NOS 19,20,21 27 14-May-15 14-Jun-15 54 PART 2 BLINDING FOR CULVERTS NOS 19,20,21
CZ2CU3130 PART 2 BLINDING FOR CULVERTS NOS 22,23,24 27 15-Jun-15 15-Jul-15 64 PART 2 BLINDING FOR CULVERTS NOS 22,2
CZ2CU3140 PART 2 BLINDING FOR CULVERTS NOS 25,26,27 27 16-Jul-15 22-Aug-15 95 PART 2 BLINDING FOR CULVERTS NOS
CZ2CU3150 PART 2 BLINDING FOR CULVERTS NOS 28,29,30 27 23-Aug-15 22-Sep-15 105 PART 2 BLINDING FOR CULVERTS
ERECTION OF CULVERTS 261 26-Nov-14 06-Oct-15 96 06-Oct-15, ERECTION OF CULVER
CZ2CU3160 PART 2 ERECTION OF CULVERTS NOS 1,2,3 27 26-Nov-14 27-Dec-14 16 PART 2 ERECTION OF CULVERTS NOS 1,2,3
CZ2CU3170 PART 2 ERECTION OF CULVERTS NOS 4,5,6 26 28-Dec-14 27-Jan-15 16 PART 2 ERECTION OF CULVERTS NOS 4,5,6
CZ2CU3180 PART 2 ERECTION OF CULVERTS NOS 7,8,9 26 28-Jan-15 26-Feb-15 16 PART 2 ERECTION OF CULVERTS NOS 7,8,9
CZ2CU3190 PART 2 ERECTION OF CULVERTS NOS 10,11,12 26 28-Feb-15 29-Mar-15 21 PART 2 ERECTION OF CULVERTS NOS 10,11,12
CZ2CU3200 PART 2 ERECTION OF CULVERTS NOS 13,14,15 26 30-Mar-15 28-Apr-15 26 PART 2 ERECTION OF CULVERTS NOS 13,14,15
CZ2CU3210 PART 2 ERECTION OF CULVERTS NOS 16,17,18 26 29-Apr-15 28-May-15 31 PART 2 ERECTION OF CULVERTS NOS 16,17,18
CZ2CU3220 PART 2 ERECTION OF CULVERTS NOS 19,20,21 26 30-May-15 28-Jun-15 42 PART 2 ERECTION OF CULVERTS NOS 19,20,2
CZ2CU3230 PART 2 ERECTION OF CULVERTS NOS 22,23,24 26 29-Jun-15 03-Aug-15 53 PART 2 ERECTION OF CULVERTS NOS 22
CZ2CU3240 PART 2 ERECTION OF CULVERTS NOS 25,26,27 26 04-Aug-15 02-Sep-15 85 PART 2 ERECTION OF CULVERTS NO
CZ2CU3250 PART 2 ERECTION OF CULVERTS NOS 28,29,30 26 03-Sep-15 06-Oct-15 96 PART 2 ERECTION OF CULVERTS
END PORTION CASTING OF CULVERTS 306 09-Nov-14 14-Nov-15 64 14-Nov-15, END PORTION C
CZ2CU3260 PART 2 END PORTION CASTING OF CULVERTS N 31 09-Nov-14 16-Dec-14 9 PART 2 END PORTION CASTING OF CULVERTS NOS 1,2,3
CZ2CU3270 PART 2 END PORTION CASTING OF CULVERTS N 31 17-Dec-14 22-Jan-15 15 PART 2 END PORTION CASTING OF CULVERTS NOS 4,5,6
CZ2CU3280 PART 2 END PORTION CASTING OF CULVERTS N 31 24-Jan-15 28-Feb-15 15 PART 2 END PORTION CASTING OF CULVERTS NOS 7,8,9
CZ2CU3290 PART 2 END PORTION CASTING OF CULVERTS N 31 01-Mar-15 05-Apr-15 15 PART 2 END PORTION CASTING OF CULVERTS NOS 10,1
CZ2CU3300 PART 2 END PORTION CASTING OF CULVERTS N 31 06-Apr-15 11-May-15 15 PART 2 END PORTION CASTING OF CULVERTS NOS
CZ2CU3310 PART 2 END PORTION CASTING OF CULVERTS N 31 12-May-15 16-Jun-15 15 PART 2 END PORTION CASTING OF CULVERTS
CZ2CU3320 PART 2 END PORTION CASTING OF CULVERTS N 30 17-Jun-15 27-Jul-15 22 PART 2 END PORTION CASTING OF CULVE
CZ2CU3330 PART 2 END PORTION CASTING OF CULVERTS N 30 28-Jul-15 31-Aug-15 29 PART 2 END PORTION CASTING OF C
CZ2CU3340 PART 2 END PORTION CASTING OF CULVERTS N 30 01-Sep-15 08-Oct-15 57 PART 2 END PORTION CASTING
CZ2CU3350 PART 2 END PORTION CASTING OF CULVERTS N 30 10-Oct-15 14-Nov-15 64 PART 2 END PORTION CAST
CONSTRUCTIO OF INLET & OUT LET
CONSTRUCTION 306 16-Nov-14 21-Nov-15 58 21-Nov-15, CONSTRUCTIO
CZ2CU3360 PART 2 CONSTRUCTION OF INLET & OUT LET NO 31 16-Nov-14 23-Dec-14 9 PART 2 CONSTRUCTION OF INLET & OUT LET NOS 1,2,3
CZ2CU3370 PART 2 CONSTRUCTION OF INLET & OUT LET NO 31 24-Dec-14 29-Jan-15 9 PART 2 CONSTRUCTION OF INLET & OUT LET NOS 4,5,6
CZ2CU3380 PART 2 CONSTRUCTION OF INLET & OUT LET NO 31 31-Jan-15 07-Mar-15 9 PART 2 CONSTRUCTION OF INLET & OUT LET NOS 7,8,9
CZ2CU3390 PART 2 CONSTRUCTION OF INLET & OUT LET NO 31 08-Mar-15 12-Apr-15 9 PART 2 CONSTRUCTION OF INLET & OUT LET NOS 10,1
CZ2CU3400 PART 2 CONSTRUCTION OF INLET & OUT LET NO 31 13-Apr-15 18-May-15 9 PART 2 CONSTRUCTION OF INLET & OUT LET NOS
CZ2CU3410 PART 2 CONSTRUCTION OF INLET & OUT LET NO 31 19-May-15 23-Jun-15 9 PART 2 CONSTRUCTION OF INLET & OUT LET
CZ2CU3420 PART 2 CONSTRUCTION OF INLET & OUT LET NO 30 24-Jun-15 03-Aug-15 16 PART 2 CONSTRUCTION OF INLET & OUT
CZ2CU3430 PART 2 CONSTRUCTION OF INLET & OUT LET NO 30 04-Aug-15 07-Sep-15 23 PART 2 CONSTRUCTION OF INLET &
CZ2CU3440 PART 2 CONSTRUCTION OF INLET & OUT LET NO 30 08-Sep-15 17-Oct-15 51 PART 2 CONSTRUCTION OF IN
CZ2CU3450 PART 2 CONSTRUCTION OF INLET & OUT LET NO 30 18-Oct-15 21-Nov-15 58 PART 2 CONSTRUCTION O
INTERCHANGE AT 34+700
3 189 20-Aug-14 05-Apr-15 24 05-Apr-15, INTERCHANGE AT 34+700
INT. 34+700 GEOTECHNICAL
GEOT INVESTIGATION 33 20-Aug-14 27-Sep-14 23 27-Sep-14, INT. 34+700 GEOTECHNICAL INVESTIGATION
CZ2IN1000 INT. 34+700 MOBILIZATION 7 20-Aug-14 27-Aug-14 23 INT. 34+700 MOBILIZATION
CZ2IN1010 INT. 34+700 SOIL INVESTIGATION 14 28-Aug-14 13-Sep-14 23 INT. 34+700 SOIL INVESTIGATION

Actual Work Critical Remaining Work Summary Page 33 of 57 TASK filter: All Activities

Remaining Work Milestone © Oracle Corporation


DUALIZATION OF MAHDAH - AL RAWDAH ROAD PROJECT Classic Schedule Layout 25-May-14 16:51

Activity ID Activity Name Original Start Finish Total Float Critical 2014 2015 2016
Duration
S Oct N D J F M Apr M J Jul A S Oct N D Jan F M Apr M J Jul A S Oct N D J F M Apr M J
CZ2IN1020 INT. 34+700 ANALYSIS AND SUBMISSION 6 14-Sep-14 20-Sep-14 23 INT. 34+700 ANALYSIS AND SUBMISSION
CZ2IN1030 INT. 34+700 APPROVAL 6 21-Sep-14 27-Sep-14 23 INT. 34+700 APPROVAL
INT. 34+700 CONSTRUCTION
CONS 168 14-Sep-14 05-Apr-15 24 05-Apr-15, INT. 34+700 CONSTRUCTION
CZ2IN1040 INT. 34+700 SURVEY & SETTING OUT 3 14-Sep-14 16-Sep-14 23 INT. 34+700 SURVEY & SETTING OUT
CZ2IN1050 INT. 34+700 CLEARING AND GRUBBING 5 17-Sep-14 22-Sep-14 23 INT. 34+700 CLEARING AND GRUBBING
CZ2IN1060 INT. 34+700 STRUCTURAL EXACAVATION FOR FO 12 23-Sep-14 09-Oct-14 23 INT. 34+700 STRUCTURAL EXACAVATION FOR FOUNDATION
CZ2IN1070 INT. 34+700 PCC FOR FOUNDATION 7 01-Oct-14 12-Oct-14 23 INT. 34+700 PCC FOR FOUNDATION
CZ2IN1080 INT. 34+700 CONCRETING FOR ABUTMENT (AB1, 14 02-Oct-14 21-Oct-14 23 INT. 34+700 CONCRETING FOR ABUTMENT (AB1, AB2) FOUNDATIONS
CZ2IN1090 INT. 34+700 CONCRETING FOR ABUTMENT (AB1, 23 22-Oct-14 18-Nov-14 35 INT. 34+700 CONCRETING FOR ABUTMENT (AB1, AB2) WALL
CZ2IN1100 INT. 34+700 CONCRETING FOR PIER FOUNDATIO 8 16-Oct-14 26-Oct-14 23 INT. 34+700 CONCRETING FOR PIER FOUNDATION
CZ2IN1110 INT. 34+700 CONCRETING FOR PIERS 17 27-Oct-14 15-Nov-14 23 INT. 34+700 CONCRETING FOR PIERS
CZ2IN1120 INT. 34+700 STAGING FOR BOX GIRDERS 15 16-Nov-14 04-Dec-14 23 INT. 34+700 STAGING FOR BOX GIRDERS
CZ2IN1130 INT. 34+700 FIXING OF BEARING 6 06-Dec-14 11-Dec-14 23 INT. 34+700 FIXING OF BEARING
CZ2IN1140 INT. 34+700 SOFFIT FORMWORK ALONG WITH W 12 04-Dec-14 17-Dec-14 23 INT. 34+700 SOFFIT FORMWORK ALONG WITH WINGS OF BOX GIRDER
CZ2IN1150 INT. 34+700 REINFORCEMENT FIXING FOR SOFF 13 18-Dec-14 01-Jan-15 24 INT. 34+700 REINFORCEMENT FIXING FOR SOFFIT & WEB (STIRUPPS
CZ2IN1160 INT. 34+700 POST TENSIONING DUCT PROFILING 7 28-Dec-14 05-Jan-15 24 INT. 34+700 POST TENSIONING DUCT PROFILING
CZ2IN1170 INT. 34+700 CONCRETING OF SOFFIT 1 06-Jan-15 06-Jan-15 24 INT. 34+700 CONCRETING OF SOFFIT
CZ2IN1180 INT. 34+700 REINFORCEMENT FIXING FOR WEB & 4 07-Jan-15 11-Jan-15 24 INT. 34+700 REINFORCEMENT FIXING FOR WEB & DIAPHARGMS (DI
CZ2IN1190 INT. 34+700 FORMWORK FIXING FOR WEB & DIAP 10 12-Jan-15 22-Jan-15 24 INT. 34+700 FORMWORK FIXING FOR WEB & DIAPHARGMS
CZ2IN1200 INT. 34+700 CONCRETING FOR WEB & DIAPHARG 1 24-Jan-15 24-Jan-15 24 INT. 34+700 CONCRETING FOR WEB & DIAPHARGMS
CZ2IN1210 INT. 34+700 STAGING & FORMWORK FOR DECK S 12 25-Jan-15 07-Feb-15 24 INT. 34+700 STAGING & FORMWORK FOR DECK SLAB
CZ2IN1220 INT. 34+700 REINFORCEMENT FIXING FOR DECK 11 08-Feb-15 19-Feb-15 24 INT. 34+700 REINFORCEMENT FIXING FOR DECK SLAB
CZ2IN1230 INT. 34+700 CONCRETING FOR DECK SLAB 1 21-Feb-15 21-Feb-15 24 INT. 34+700 CONCRETING FOR DECK SLAB
CZ2IN1240 INT. 34+700 THREADING OF STRANDS 11 22-Feb-15 05-Mar-15 24 INT. 34+700 THREADING OF STRANDS
CZ2IN1250 INT. 34+700 STRESSING & GROUTING 5 07-Mar-15 11-Mar-15 24 INT. 34+700 STRESSING & GROUTING
CZ2IN1260 INT. 34+700 DRAINAGE PIPE FIXING 7 12-Mar-15 19-Mar-15 38 INT. 34+700 DRAINAGE PIPE FIXING
CZ2IN1270 INT. 34+700 APPROACH SLAB 12 12-Mar-15 25-Mar-15 24 INT. 34+700 APPROACH SLAB
CZ2IN1280 INT. 34+700 EXPANSION JOINT 9 21-Mar-15 30-Mar-15 24 INT. 34+700 EXPANSION JOINT
CZ2IN1290 INT. 34+700 REMOVAL OF STAGING 11 12-Mar-15 24-Mar-15 34 INT. 34+700 REMOVAL OF STAGING
CZ2IN1300 INT. 34+700 DIRT WALL & CONCRETE BARRIER 21 12-Mar-15 05-Apr-15 24 INT. 34+700 DIRT WALL & CONCRETE BARRIER
UNDER PASS AT 25+945
25+ 207 28-Sep-14 03-Jun-15 23 03-Jun-15, UNDER PASS AT 25+945
UNP. 25+945 GEOTECHNICAL
GEO INVESTIGATION 49 28-Sep-14 30-Nov-14 23 30-Nov-14, UNP. 25+945 GEOTECHNICAL INVESTIGATION
CZ2UN1000 UNP. 25+945 SOIL INVESTIGATION 20 28-Sep-14 23-Oct-14 23 UNP. 25+945 SOIL INVESTIGATION
CZ2UN1010 UNP. 25+945 ANALYSIS AND SUBMISSION 15 26-Oct-14 11-Nov-14 23 UNP. 25+945 ANALYSIS AND SUBMISSION
CZ2UN1020 UNP. 25+945 APPROVAL 14 12-Nov-14 30-Nov-14 23 UNP. 25+945 APPROVAL
UNDER PASS AT 25+945 CONSTRUCTION 158 01-Dec-14 03-Jun-15 23 03-Jun-15, UNDER PASS AT 25+945 CONSTRUCTIO
CZ2UN1030 UNP. 25+945 SURVEY & SETTING OUT 3 01-Dec-14 03-Dec-14 23 UNP. 25+945 SURVEY & SETTING OUT
CZ2UN1040 UNP. 25+945 CLEARING AND GRUBBING 5 04-Dec-14 09-Dec-14 23 UNP. 25+945 CLEARING AND GRUBBING
CZ2UN1050 UNP. 25+945 EXCAVATION FOR FOUNDATION 6 10-Dec-14 16-Dec-14 23 UNP. 25+945 EXCAVATION FOR FOUNDATION
CZ2UN1060 UNP. 25+945 PCC FOR FOUNDATION 5 14-Dec-14 18-Dec-14 23 UNP. 25+945 PCC FOR FOUNDATION
CZ2UN1070 UNP. 25+945 RCC FOR FOUNDATION 39 18-Dec-14 02-Feb-15 23 UNP. 25+945 RCC FOR FOUNDATION
CZ2UN1080 UNP. 25+945 CONCRETING FOR WALL 48 21-Jan-15 17-Mar-15 61 UNP. 25+945 CONCRETING FOR WALL
CZ2UN1090 UNP. 25+945 STAGING FOR DECK SLAB 15 23-Feb-15 11-Mar-15 23 UNP. 25+945 STAGING FOR DECK SLAB
CZ2UN1100 UNP. 25+945 FORMWORK & REINFORCEMENT W 25 08-Mar-15 05-Apr-15 45 UNP. 25+945 FORMWORK & REINFORCEMENT WORK FO
CZ2UN1110 UNP. 25+945 CONCRETING FOR DECK SLAB 9 28-Mar-15 06-Apr-15 45 UNP. 25+945 CONCRETING FOR DECK SLAB
CZ2UN1120 UNP. 25+945 DESHUTTERING FOR DECK SLAB 6 03-May-15 09-May-15 45 UNP. 25+945 DESHUTTERING FOR DECK SLAB
CZ2UN1130 UNP. 25+945 PRECAST FOR MSER WALL PANELS 30 03-Feb-15 09-Mar-15 40 UNP. 25+945 PRECAST FOR MSER WALL PANELS PART 1
CZ2UN1140 UNP. 25+945 PRECAST FOR MSER WALL PANELS 30 10-Mar-15 13-Apr-15 40 UNP. 25+945 PRECAST FOR MSER WALL PANELS PART 2
CZ2UN1150 UNP. 25+945 EXCAVATION FOR MSER WALL PART 4 24-Feb-15 28-Feb-15 23 UNP. 25+945 EXCAVATION FOR MSER WALL PART 1
CZ2UN1160 UNP. 25+945 EXCAVATION FOR MSER WALL PART 4 01-Mar-15 04-Mar-15 25 UNP. 25+945 EXCAVATION FOR MSER WALL PART 2
CZ2UN1170 UNP. 25+945 PCC FOR MSER WALL PART 1 4 28-Feb-15 03-Mar-15 23 UNP. 25+945 PCC FOR MSER WALL PART 1

Actual Work Critical Remaining Work Summary Page 34 of 57 TASK filter: All Activities

Remaining Work Milestone © Oracle Corporation


DUALIZATION OF MAHDAH - AL RAWDAH ROAD PROJECT Classic Schedule Layout 25-May-14 16:51

Activity ID Activity Name Original Start Finish Total Float Critical 2014 2015 2016
Duration
S Oct N D J F M Apr M J Jul A S Oct N D Jan F M Apr M J Jul A S Oct N D J F M Apr M J
CZ2UN1180 UNP. 25+945 PCC FOR MSER WALL PART 2 3 04-Mar-15 07-Mar-15 23 UNP. 25+945 PCC FOR MSER WALL PART 2
CZ2UN1190 UNP. 25+945 FOUNDATION FOR MSER WALL PAR 6 08-Mar-15 14-Mar-15 23 UNP. 25+945 FOUNDATION FOR MSER WALL PART 1
CZ2UN1200 UNP. 25+945 FOUNDATION FOR MSER WALL PAR 5 15-Mar-15 19-Mar-15 61 UNP. 25+945 FOUNDATION FOR MSER WALL PART 2
CZ2UN1210 UNP. 25+945 FIXING OF MSER WALL PANELS PAR 22 14-Mar-15 07-Apr-15 23 UNP. 25+945 FIXING OF MSER WALL PANELS PART 1
CZ2UN1220 UNP. 25+945 FIXING OF MSER WALL PANELS PAR 22 08-Apr-15 03-May-15 23 UNP. 25+945 FIXING OF MSER WALL PANELS PART 2
CZ2UN1230 UNP. 25+945 APPROACH SLAB 20 22-Apr-15 14-May-15 40 UNP. 25+945 APPROACH SLAB
CZ2UN1240 UNP. 25+945 CONCRETE BARRIER 27 02-Apr-15 03-May-15 23 UNP. 25+945 CONCRETE BARRIER
CZ2UN1250 UNP. 25+945 MEDIAN WORKS 27 04-May-15 03-Jun-15 23 UNP. 25+945 MEDIAN WORKS
INCIDENTAL CONSTRUCTION
CONSTRU 450 08-Dec-14 30-May-16 14 3
CONSTRUCTION OF SLOPE PROTECTION AND STABILIZATION 288 16-Feb-15 31-Jan-16 5 31-Jan-16, CONST
WADI PROTECTION
PROTECTIO WITH RETAINING WALL 81 23-Apr-15 01-Aug-15 5 01-Aug-15, WADI PROTECTION WITH RET
WADI 3 [SUMAYNI]
[SUMAY PROTECTION CH. FROM KM 32+000 TO 34+000 81 23-Apr-15 01-Aug-15 5 01-Aug-15, WADI 3 [SUMAYNI] PROTECTIO
WADI 3A MAHDAH
MA TO RAWDAH 46 23-Apr-15 15-Jun-15 5 15-Jun-15, WADI 3A MAHDAH TO RAWDAH
CZ2FI1000 WADI 3A EXCAVATION FOR RETAINING WALL 8 23-Apr-15 02-May-15 5 WADI 3A EXCAVATION FOR RETAINING WALL
CZ2FI1010 WADI 3A BLINDING FOR RETAINING WALL 8 26-Apr-15 04-May-15 5 WADI 3A BLINDING FOR RETAINING WALL
CZ2FI1020 WADI 3A FOUNDATION FOR RETAINING WALL 25 27-Apr-15 25-May-15 5 WADI 3A FOUNDATION FOR RETAINING WALL
CZ2FI1030 WADI 3A RCC WALL FOR RETAINING WALL 35 06-May-15 15-Jun-15 5 WADI 3A RCC WALL FOR RETAINING WALL
CZ2FI1040 WADI 3A GABION METRESS 12 18-May-15 31-May-15 15 WADI 3A GABION METRESS
WADI 3B RAWDAH
RA TO MAHDAH 73 03-May-15 01-Aug-15 5 01-Aug-15, WADI 3B RAWDAH TO MAHDAH
CZ2FI1050 WADI 3B EXCAVATION FOR RETAINING WALL 8 03-May-15 11-May-15 55 WADI 3B EXCAVATION FOR RETAINING WALL
CZ2FI1060 WADI 3B BLINDING FOR RETAINING WALL 8 05-May-15 13-May-15 55 WADI 3B BLINDING FOR RETAINING WALL
CZ2FI1070 WADI 3B FOUNDATION FOR RETAINING WALL 25 01-Jun-15 29-Jun-15 15 WADI 3B FOUNDATION FOR RETAINING WALL
CZ2FI1080 WADI 3B RCC WALL FOR RETAINING WALL 35 16-Jun-15 01-Aug-15 5 WADI 3B RCC WALL FOR RETAINING WAL
CZ2FI1090 WADI 3B GABION METRESS 12 28-Jun-15 11-Jul-15 5 WADI 3B GABION METRESS
MORTARED STONE
STON RIP RAP PROTECTION 250 16-Feb-15 16-Dec-15 5 16-Dec-15, MORTARED
CZ2FI1100 MORTARED STONE RIP RAP CH. FROM KM 20+00 25 16-Feb-15 16-Mar-15 5 MORTARED STONE RIP RAP CH. FROM KM 20+000 TO 22+00
CZ2FI1110 MORTARED STONE RIP RAP CH. FROM KM 22+00 25 17-Mar-15 14-Apr-15 5 MORTARED STONE RIP RAP CH. FROM KM 22+000 TO 2
CZ2FI1120 MORTARED STONE RIP RAP CH. FROM KM 24+00 25 15-Apr-15 13-May-15 5 MORTARED STONE RIP RAP CH. FROM KM 24+000 T
CZ2FI1130 MORTARED STONE RIP RAP CH. FROM KM 26+00 25 14-May-15 11-Jun-15 5 MORTARED STONE RIP RAP CH. FROM KM 26+0
CZ2FI1140 MORTARED STONE RIP RAP CH. FROM KM 28+00 25 13-Jun-15 11-Jul-15 5 MORTARED STONE RIP RAP CH. FROM KM 2
CZ2FI1150 MORTARED STONE RIP RAP CH. FROM KM 30+00 25 12-Jul-15 15-Aug-15 5 MORTARED STONE RIP RAP CH. FROM
CZ2FI1160 MORTARED STONE RIP RAP CH. FROM KM 32+00 25 16-Aug-15 13-Sep-15 5 MORTARED STONE RIP RAP CH. FR
CZ2FI1170 MORTARED STONE RIP RAP CH. FROM KM 34+00 25 14-Sep-15 17-Oct-15 5 MORTARED STONE RIP RAP CH
CZ2FI1180 MORTARED STONE RIP RAP CH. FROM KM 36+00 25 18-Oct-15 15-Nov-15 5 MORTARED STONE RIP RA
CZ2FI1190 MORTARED STONE RIP RAP CH. FROM KM 38+00 25 16-Nov-15 16-Dec-15 5 MORTARED STONE RIP
LOOSE STONE R
RIPRAP PROTECTION 242 17-Mar-15 06-Jan-16 5 06-Jan-16, LOOSE ST
CZ2FI1200 LOOSE STONE RIP RAP CH. FROM KM 20+000 TO 17 17-Mar-15 05-Apr-15 6 LOOSE STONE RIP RAP CH. FROM KM 20+000 TO 22+000
CZ2FI1210 LOOSE STONE RIP RAP CH. FROM KM 22+000 TO 17 15-Apr-15 04-May-15 5 LOOSE STONE RIP RAP CH. FROM KM 22+000 TO 24+
CZ2FI1220 LOOSE STONE RIP RAP CH. FROM KM 24+000 TO 17 14-May-15 02-Jun-15 5 LOOSE STONE RIP RAP CH. FROM KM 24+000 TO
CZ2FI1230 LOOSE STONE RIP RAP CH. FROM KM 26+000 TO 17 13-Jun-15 01-Jul-15 5 LOOSE STONE RIP RAP CH. FROM KM 26+000
CZ2FI1240 LOOSE STONE RIP RAP CH. FROM KM 28+000 TO 17 12-Jul-15 05-Aug-15 5 LOOSE STONE RIP RAP CH. FROM KM 28
CZ2FI1250 LOOSE STONE RIP RAP CH. FROM KM 30+000 TO 17 16-Aug-15 03-Sep-15 5 LOOSE STONE RIP RAP CH. FROM K
CZ2FI1260 LOOSE STONE RIP RAP CH. FROM KM 32+000 TO 17 14-Sep-15 06-Oct-15 5 LOOSE STONE RIP RAP CH. FRO
CZ2FI1270 LOOSE STONE RIP RAP CH. FROM KM 34+000 TO 17 18-Oct-15 05-Nov-15 5 LOOSE STONE RIP RAP CH.
CZ2FI1280 LOOSE STONE RIP RAP CH. FROM KM 36+000 TO 17 16-Nov-15 07-Dec-15 5 LOOSE STONE RIP RAP
CZ2FI1290 LOOSE STONE RIP RAP CH. FROM KM 38+000 TO 17 17-Dec-15 06-Jan-16 5 LOOSE STONE RIP R
REINFORCED CONCRETE
CO FOR SLOPE PROTECTION 246 06-Apr-15 31-Jan-16 5 31-Jan-16, REINFO
CZ2FI1300 REIF. CONC. FOR SLOPE PROTECTION CH. FRO 21 06-Apr-15 29-Apr-15 6 REIF. CONC. FOR SLOPE PROTECTION CH. FROM KM
CZ2FI1310 REIF. CONC. FOR SLOPE PROTECTION CH. FRO 21 05-May-15 28-May-15 5 REIF. CONC. FOR SLOPE PROTECTION CH. FROM
CZ2FI1320 REIF. CONC. FOR SLOPE PROTECTION CH. FRO 21 03-Jun-15 27-Jun-15 5 REIF. CONC. FOR SLOPE PROTECTION CH. F
CZ2FI1330 REIF. CONC. FOR SLOPE PROTECTION CH. FRO 21 02-Jul-15 01-Aug-15 5 REIF. CONC. FOR SLOPE PROTECTION C
CZ2FI1340 REIF. CONC. FOR SLOPE PROTECTION CH. FRO 21 06-Aug-15 30-Aug-15 5 REIF. CONC. FOR SLOPE PROTECTIO

Actual Work Critical Remaining Work Summary Page 35 of 57 TASK filter: All Activities

Remaining Work Milestone © Oracle Corporation


DUALIZATION OF MAHDAH - AL RAWDAH ROAD PROJECT Classic Schedule Layout 25-May-14 16:51

Activity ID Activity Name Original Start Finish Total Float Critical 2014 2015 2016
Duration
S Oct N D J F M Apr M J Jul A S Oct N D Jan F M Apr M J Jul A S Oct N D J F M Apr M J
CZ2FI1350 REIF. CONC. FOR SLOPE PROTECTION CH. FRO 21 05-Sep-15 01-Oct-15 5 REIF. CONC. FOR SLOPE PROTEC
CZ2FI1360 REIF. CONC. FOR SLOPE PROTECTION CH. FRO 21 07-Oct-15 01-Nov-15 5 REIF. CONC. FOR SLOPE PRO
CZ2FI1370 REIF. CONC. FOR SLOPE PROTECTION CH. FRO 21 07-Nov-15 02-Dec-15 5 REIF. CONC. FOR SLOPE
CZ2FI1380 REIF. CONC. FOR SLOPE PROTECTION CH. FRO 21 08-Dec-15 02-Jan-16 5 REIF. CONC. FOR SL
CZ2FI1390 REIF. CONC. FOR SLOPE PROTECTION CH. FRO 21 07-Jan-16 31-Jan-16 5 REIF. CONC. FOR
ROCK BOLTING & ANCHORING, SHORTSCRETE 180 06-Apr-15 11-Nov-15 21 11-Nov-15, ROCK BOLTING &
CZ2FI1400 ROCK BOLTING & ANCHORING,SHORTCRETE CH 18 06-Apr-15 26-Apr-15 21 ROCK BOLTING & ANCHORING,SHORTCRETE CH. FRO
CZ2FI1410 ROCK BOLTING & ANCHORING,SHORTCRETE CH 18 27-Apr-15 17-May-15 21 ROCK BOLTING & ANCHORING,SHORTCRETE CH. F
CZ2FI1420 ROCK BOLTING & ANCHORING,SHORTCRETE CH 18 18-May-15 07-Jun-15 21 ROCK BOLTING & ANCHORING,SHORTCRETE CH
CZ2FI1430 ROCK BOLTING & ANCHORING,SHORTCRETE CH 18 08-Jun-15 28-Jun-15 21 ROCK BOLTING & ANCHORING,SHORTCRETE
CZ2FI1440 ROCK BOLTING & ANCHORING,SHORTCRETE CH 18 29-Jun-15 25-Jul-15 21 ROCK BOLTING & ANCHORING,SHORTCR
CZ2FI1450 ROCK BOLTING & ANCHORING,SHORTCRETE CH 18 26-Jul-15 15-Aug-15 21 ROCK BOLTING & ANCHORING,SHORTC
CZ2FI1460 ROCK BOLTING & ANCHORING,SHORTCRETE CH 18 16-Aug-15 05-Sep-15 21 ROCK BOLTING & ANCHORING,SHOR
CZ2FI1470 ROCK BOLTING & ANCHORING,SHORTCRETE CH 18 06-Sep-15 29-Sep-15 21 ROCK BOLTING & ANCHORING,SH
CZ2FI1480 ROCK BOLTING & ANCHORING,SHORTCRETE CH 18 30-Sep-15 21-Oct-15 21 ROCK BOLTING & ANCHORING
CZ2FI1490 ROCK BOLTING & ANCHORING,SHORTCRETE CH 18 22-Oct-15 11-Nov-15 21 ROCK BOLTING & ANCHOR
DITCH LINING / C
CHUTES 246 06-Apr-15 31-Jan-16 5 31-Jan-16, DITCH
CZ2FI1500 DITCH LINING/ CHUTES CH. FROM KM 20+000 TO 21 06-Apr-15 29-Apr-15 6 DITCH LINING/ CHUTES CH. FROM KM 20+000 TO 22+
CZ2FI1510 DITCH LINING/ CHUTES CH. FROM KM 22+000 TO 21 05-May-15 28-May-15 5 DITCH LINING/ CHUTES CH. FROM KM 22+000 TO
CZ2FI1520 DITCH LINING/ CHUTES CH. FROM KM 24+000 TO 21 03-Jun-15 27-Jun-15 5 DITCH LINING/ CHUTES CH. FROM KM 24+000
CZ2FI1530 DITCH LINING/ CHUTES CH. FROM KM 26+000 TO 21 02-Jul-15 01-Aug-15 5 DITCH LINING/ CHUTES CH. FROM KM 26
CZ2FI1540 DITCH LINING/ CHUTES CH. FROM KM 28+000 TO 21 06-Aug-15 30-Aug-15 5 DITCH LINING/ CHUTES CH. FROM KM
CZ2FI1550 DITCH LINING/ CHUTES CH. FROM KM 30+000 TO 21 05-Sep-15 01-Oct-15 5 DITCH LINING/ CHUTES CH. FRO
CZ2FI1560 DITCH LINING/ CHUTES CH. FROM KM 32+000 TO 21 07-Oct-15 01-Nov-15 5 DITCH LINING/ CHUTES CH. F
CZ2FI1570 DITCH LINING/ CHUTES CH. FROM KM 34+000 TO 21 07-Nov-15 02-Dec-15 5 DITCH LINING/ CHUTES C
CZ2FI1580 DITCH LINING/ CHUTES CH. FROM KM 36+000 TO 21 08-Dec-15 02-Jan-16 5 DITCH LINING/ CHUT
CZ2FI1590 DITCH LINING/ CHUTES CH. FROM KM 38+000 TO 21 07-Jan-16 31-Jan-16 5 DITCH LINING/ CH
GABION WALLS 247 05-Apr-15 31-Jan-16 5 31-Jan-16, GABIO
CZ2FI1600 GABION WALLS CH. FROM KM 20+000 TO 22+000 22 05-Apr-15 29-Apr-15 6 GABION WALLS CH. FROM KM 20+000 TO 22+000
CZ2FI1610 GABION WALLS CH. FROM KM 22+000 TO 24+000 24 02-May-15 28-May-15 5 GABION WALLS CH. FROM KM 22+000 TO 24+000
CZ2FI1620 GABION WALLS CH. FROM KM 24+000 TO 26+000 25 30-May-15 27-Jun-15 5 GABION WALLS CH. FROM KM 24+000 TO 26+0
CZ2FI1630 GABION WALLS CH. FROM KM 26+000 TO 28+000 25 28-Jun-15 01-Aug-15 5 GABION WALLS CH. FROM KM 26+000 TO
CZ2FI1640 GABION WALLS CH. FROM KM 28+000 TO 30+000 25 02-Aug-15 30-Aug-15 5 GABION WALLS CH. FROM KM 28+000
CZ2FI1650 GABION WALLS CH. FROM KM 30+000 TO 32+000 25 31-Aug-15 01-Oct-15 5 GABION WALLS CH. FROM KM 30
CZ2FI1660 GABION WALLS CH. FROM KM 32+000 TO 34+000 25 03-Oct-15 01-Nov-15 5 GABION WALLS CH. FROM KM
CZ2FI1670 GABION WALLS CH. FROM KM 34+000 TO 36+000 25 02-Nov-15 02-Dec-15 5 GABION WALLS CH. FRO
CZ2FI1680 GABION WALLS CH. FROM KM 36+000 TO 38+000 25 03-Dec-15 02-Jan-16 5 GABION WALLS CH. F
CZ2FI1690 GABION WALLS CH. FROM KM 38+000 TO 40+000 25 03-Jan-16 31-Jan-16 5 GABION WALLS C
CONSTRUCTION OF SIDEWALKS,PAVED AREAS AND CURBS 166 17-Mar-15 05-Oct-15 88 05-Oct-15, CONSTRUCTION OF S
CZ2FI1700 SIDEWALKS, PAVED AREAS & CURBS CH. FROM K 17 17-Mar-15 05-Apr-15 88 SIDEWALKS, PAVED AREAS & CURBS CH. FROM KM 20+00
CZ2FI1710 SIDEWALKS, PAVED AREAS & CURBS CH. FROM K 17 06-Apr-15 25-Apr-15 88 SIDEWALKS, PAVED AREAS & CURBS CH. FROM KM 22
CZ2FI1720 SIDEWALKS, PAVED AREAS & CURBS CH. FROM K 17 26-Apr-15 14-May-15 88 SIDEWALKS, PAVED AREAS & CURBS CH. FROM KM
CZ2FI1730 SIDEWALKS, PAVED AREAS & CURBS CH. FROM K 17 16-May-15 03-Jun-15 88 SIDEWALKS, PAVED AREAS & CURBS CH. FROM K
CZ2FI1740 SIDEWALKS, PAVED AREAS & CURBS CH. FROM K 17 04-Jun-15 23-Jun-15 88 SIDEWALKS, PAVED AREAS & CURBS CH. FROM
CZ2FI1750 SIDEWALKS, PAVED AREAS & CURBS CH. FROM K 17 24-Jun-15 13-Jul-15 88 SIDEWALKS, PAVED AREAS & CURBS CH. FR
CZ2FI1760 SIDEWALKS, PAVED AREAS & CURBS CH. FROM K 16 14-Jul-15 06-Aug-15 88 SIDEWALKS, PAVED AREAS & CURBS CH.
CZ2FI1770 SIDEWALKS, PAVED AREAS & CURBS CH. FROM K 16 08-Aug-15 25-Aug-15 88 SIDEWALKS, PAVED AREAS & CURBS C
CZ2FI1780 SIDEWALKS, PAVED AREAS & CURBS CH. FROM K 16 26-Aug-15 13-Sep-15 88 SIDEWALKS, PAVED AREAS & CURBS
CZ2FI1790 SIDEWALKS, PAVED AREAS & CURBS CH. FROM K 16 14-Sep-15 05-Oct-15 88 SIDEWALKS, PAVED AREAS & CUR
SAFETY BARRIERS AND FENCING WORKS 377 18-Jan-15 14-Apr-16 53 14-Apr-
ROAD SIDE BARRIERS
BARR - GUARDRAILS 140 24-Oct-15 06-Apr-16 53 06-Apr-1

Actual Work Critical Remaining Work Summary Page 36 of 57 TASK filter: All Activities

Remaining Work Milestone © Oracle Corporation


DUALIZATION OF MAHDAH - AL RAWDAH ROAD PROJECT Classic Schedule Layout 25-May-14 16:51

Activity ID Activity Name Original Start Finish Total Float Critical 2014 2015 2016
Duration
S Oct N D J F M Apr M J Jul A S Oct N D Jan F M Apr M J Jul A S Oct N D J F M Apr M J
CZ2FI1800 GUARDRAILS CH. FROM KM 20+000 TO 22+000 14 24-Oct-15 08-Nov-15 5 GUARDRAILS CH. FROM KM
CZ2FI1810 GUARDRAILS CH. FROM KM 22+000 TO 24+000 14 09-Nov-15 24-Nov-15 5 GUARDRAILS CH. FROM K
CZ2FI1820 GUARDRAILS CH. FROM KM 24+000 TO 26+000 14 25-Nov-15 13-Dec-15 5 GUARDRAILS CH. FROM
CZ2FI1830 GUARDRAILS CH. FROM KM 26+000 TO 28+000 14 14-Dec-15 30-Dec-15 5 GUARDRAILS CH. FR
CZ2FI1840 GUARDRAILS CH. FROM KM 28+000 TO 30+000 14 31-Dec-15 16-Jan-16 5 GUARDRAILS CH. F
CZ2FI1850 GUARDRAILS CH. FROM KM 30+000 TO 32+000 14 17-Jan-16 01-Feb-16 5 GUARDRAILS CH
CZ2FI1860 GUARDRAILS CH. FROM KM 32+000 TO 34+000 14 02-Feb-16 17-Feb-16 53 GUARDRAILS C
CZ2FI1870 GUARDRAILS CH. FROM KM 34+000 TO 36+000 14 18-Feb-16 05-Mar-16 53 GUARDRAILS
CZ2FI1880 GUARDRAILS CH. FROM KM 36+000 TO 38+000 14 06-Mar-16 21-Mar-16 53 GUARDRA
CZ2FI1890 GUARDRAILS CH. FROM KM 38+000 TO 40+000 14 22-Mar-16 06-Apr-16 53 GUARDR
PRECAST FOR CONCRETE
C BARRIERS 200 18-Jan-15 13-Sep-15 30 13-Sep-15, PRECAST FOR CONCRE
CZ2FI1900 PRECAST FOR CONCRETE BARRIERS CH. FROM 20 18-Jan-15 09-Feb-15 30 PRECAST FOR CONCRETE BARRIERS CH. FROM KM 20+000 TO
CZ2FI1910 PRECAST FOR CONCRETE BARRIERS CH. FROM 20 10-Feb-15 04-Mar-15 30 PRECAST FOR CONCRETE BARRIERS CH. FROM KM 22+000
CZ2FI1920 PRECAST FOR CONCRETE BARRIERS CH. FROM 20 05-Mar-15 28-Mar-15 30 PRECAST FOR CONCRETE BARRIERS CH. FROM KM 24+0
CZ2FI1930 PRECAST FOR CONCRETE BARRIERS CH. FROM 20 29-Mar-15 20-Apr-15 30 PRECAST FOR CONCRETE BARRIERS CH. FROM KM 26
CZ2FI1940 PRECAST FOR CONCRETE BARRIERS CH. FROM 20 21-Apr-15 13-May-15 30 PRECAST FOR CONCRETE BARRIERS CH. FROM KM
CZ2FI1950 PRECAST FOR CONCRETE BARRIERS CH. FROM 20 14-May-15 06-Jun-15 30 PRECAST FOR CONCRETE BARRIERS CH. FROM
CZ2FI1960 PRECAST FOR CONCRETE BARRIERS CH. FROM 20 07-Jun-15 29-Jun-15 30 PRECAST FOR CONCRETE BARRIERS CH. FR
CZ2FI1970 PRECAST FOR CONCRETE BARRIERS CH. FROM 20 30-Jun-15 28-Jul-15 30 PRECAST FOR CONCRETE BARRIERS CH
CZ2FI1980 PRECAST FOR CONCRETE BARRIERS CH. FROM 20 29-Jul-15 20-Aug-15 30 PRECAST FOR CONCRETE BARRIERS
CZ2FI1990 PRECAST FOR CONCRETE BARRIERS CH. FROM 20 22-Aug-15 13-Sep-15 30 PRECAST FOR CONCRETE BARRIE
CONCRETE BARRIERS
BARR 143 28-Oct-15 14-Apr-16 53 14-Apr-
CZ2FI2000 CONCRETE BARRIERS CH. FROM KM 20+000 TO 17 28-Oct-15 16-Nov-15 60 CONCRETE BARRIERS CH.
CZ2FI2010 CONCRETE BARRIERS CH. FROM KM 22+000 TO 17 14-Nov-15 05-Dec-15 46 CONCRETE BARRIERS C
CZ2FI2020 CONCRETE BARRIERS CH. FROM KM 24+000 TO 17 02-Dec-15 21-Dec-15 47 CONCRETE BARRIERS
CZ2FI2030 CONCRETE BARRIERS CH. FROM KM 26+000 TO 17 19-Dec-15 07-Jan-16 33 CONCRETE BARRIER
CZ2FI2040 CONCRETE BARRIERS CH. FROM KM 28+000 TO 17 05-Jan-16 24-Jan-16 19 CONCRETE BARR
CZ2FI2050 CONCRETE BARRIERS CH. FROM KM 30+000 TO 17 21-Jan-16 09-Feb-16 5 CONCRETE BAR
CZ2FI2060 CONCRETE BARRIERS CH. FROM KM 32+000 TO 17 07-Feb-16 25-Feb-16 95 CONCRETE BA
CZ2FI2070 CONCRETE BARRIERS CH. FROM KM 34+000 TO 17 23-Feb-16 13-Mar-16 81 CONCRETE
CZ2FI2080 CONCRETE BARRIERS CH. FROM KM 36+000 TO 17 10-Mar-16 29-Mar-16 67 CONCRET
CZ2FI2090 CONCRETE BARRIERS CH. FROM KM 38+000 TO 17 27-Mar-16 14-Apr-16 53 CONCR
HIGHWAY SIGN,ROA
SIGN,ROAD STUDS AND ROAD MARKING WORKS 117 16-Jan-16 30-May-16 3 3
CZ2FI2100 HIGHWAY SIGN, ROAD STUDS & MARKINGS CH. F 12 16-Jan-16 28-Jan-16 3 HIGHWAY SIGN, R
CZ2FI2110 HIGHWAY SIGN, ROAD STUDS & MARKINGS CH. F 12 30-Jan-16 11-Feb-16 3 HIGHWAY SIGN
CZ2FI2120 HIGHWAY SIGN, ROAD STUDS & MARKINGS CH. F 12 13-Feb-16 25-Feb-16 3 HIGHWAY SIG
CZ2FI2130 HIGHWAY SIGN, ROAD STUDS & MARKINGS CH. F 12 27-Feb-16 10-Mar-16 3 HIGHWAY S
CZ2FI2140 HIGHWAY SIGN, ROAD STUDS & MARKINGS CH. F 12 12-Mar-16 24-Mar-16 3 HIGHWAY
CZ2FI2150 HIGHWAY SIGN, ROAD STUDS & MARKINGS CH. F 12 26-Mar-16 07-Apr-16 3 HIGHWA
CZ2FI2160 HIGHWAY SIGN, ROAD STUDS & MARKINGS CH. F 12 09-Apr-16 21-Apr-16 3 HIGHW
CZ2FI2170 HIGHWAY SIGN, ROAD STUDS & MARKINGS CH. F 11 23-Apr-16 04-May-16 3 HIGH
CZ2FI2180 HIGHWAY SIGN, ROAD STUDS & MARKINGS CH. F 11 05-May-16 17-May-16 3 HIG
CZ2FI2190 HIGHWAY SIGN, ROAD STUDS & MARKINGS CH. F 11 18-May-16 30-May-16 3 H
UTILITIES - SERVICE PROTECTION WORKS 251 08-Dec-14 06-Oct-15 35 06-Oct-15, UTILITIES - SERVICE P
SERVICE DUCTS/ SPLIT PIPES 248 08-Dec-14 03-Oct-15 35 03-Oct-15, SERVICE DUCTS/ SPLI
CZ2UT1000 SERVICE DUCTS & SPLIT PIPES CH. FROM KM 20 26 08-Dec-14 07-Jan-15 33 SERVICE DUCTS & SPLIT PIPES CH. FROM KM 20+000 TO 22+000
CZ2UT1010 SERVICE DUCTS & SPLIT PIPES CH. FROM KM 22 26 08-Jan-15 07-Feb-15 35 SERVICE DUCTS & SPLIT PIPES CH. FROM KM 22+000 TO 24+000
CZ2UT1020 SERVICE DUCTS & SPLIT PIPES CH. FROM KM 24 26 08-Feb-15 09-Mar-15 35 SERVICE DUCTS & SPLIT PIPES CH. FROM KM 24+000 TO 26+
CZ2UT1030 SERVICE DUCTS & SPLIT PIPES CH. FROM KM 26 26 10-Mar-15 08-Apr-15 35 SERVICE DUCTS & SPLIT PIPES CH. FROM KM 26+000 TO
CZ2UT1040 SERVICE DUCTS & SPLIT PIPES CH. FROM KM 28 24 09-Apr-15 06-May-15 35 SERVICE DUCTS & SPLIT PIPES CH. FROM KM 28+000
CZ2UT1050 SERVICE DUCTS & SPLIT PIPES CH. FROM KM 30 24 07-May-15 03-Jun-15 35 SERVICE DUCTS & SPLIT PIPES CH. FROM KM 30

Actual Work Critical Remaining Work Summary Page 37 of 57 TASK filter: All Activities

Remaining Work Milestone © Oracle Corporation


DUALIZATION OF MAHDAH - AL RAWDAH ROAD PROJECT Classic Schedule Layout 25-May-14 16:51

Activity ID Activity Name Original Start Finish Total Float Critical 2014 2015 2016
Duration
S Oct N D J F M Apr M J Jul A S Oct N D Jan F M Apr M J Jul A S Oct N D J F M Apr M J
CZ2UT1060 SERVICE DUCTS & SPLIT PIPES CH. FROM KM 32 24 04-Jun-15 01-Jul-15 35 SERVICE DUCTS & SPLIT PIPES CH. FROM KM
CZ2UT1070 SERVICE DUCTS & SPLIT PIPES CH. FROM KM 34 24 02-Jul-15 04-Aug-15 35 SERVICE DUCTS & SPLIT PIPES CH. FRO
CZ2UT1080 SERVICE DUCTS & SPLIT PIPES CH. FROM KM 36 24 05-Aug-15 01-Sep-15 35 SERVICE DUCTS & SPLIT PIPES CH. F
CZ2UT1090 SERVICE DUCTS & SPLIT PIPES CH. FROM KM 38 24 02-Sep-15 03-Oct-15 35 SERVICE DUCTS & SPLIT PIPES C
MEDIAN INLETS 240 20-Dec-14 05-Oct-15 35 05-Oct-15, MEDIAN INLETS
CZ2UT1100 MEDIAN INLETS CH. FROM KM 20+000 TO 22+000 18 20-Dec-14 10-Jan-15 33 MEDIAN INLETS CH. FROM KM 20+000 TO 22+000
CZ2UT1110 MEDIAN INLETS CH. FROM KM 22+000 TO 24+000 18 20-Jan-15 09-Feb-15 87 MEDIAN INLETS CH. FROM KM 22+000 TO 24+000
CZ2UT1120 MEDIAN INLETS CH. FROM KM 24+000 TO 26+000 18 19-Feb-15 11-Mar-15 61 MEDIAN INLETS CH. FROM KM 24+000 TO 26+000
CZ2UT1130 MEDIAN INLETS CH. FROM KM 26+000 TO 28+000 18 22-Mar-15 11-Apr-15 35 MEDIAN INLETS CH. FROM KM 26+000 TO 28+000
CZ2UT1140 MEDIAN INLETS CH. FROM KM 28+000 TO 30+000 18 19-Apr-15 09-May-15 88 MEDIAN INLETS CH. FROM KM 28+000 TO 30+000
CZ2UT1150 MEDIAN INLETS CH. FROM KM 30+000 TO 32+000 18 17-May-15 06-Jun-15 64 MEDIAN INLETS CH. FROM KM 30+000 TO 32+000
CZ2UT1160 MEDIAN INLETS CH. FROM KM 32+000 TO 34+000 18 14-Jun-15 04-Jul-15 40 MEDIAN INLETS CH. FROM KM 32+000 TO 34+
CZ2UT1170 MEDIAN INLETS CH. FROM KM 34+000 TO 36+000 18 12-Jul-15 06-Aug-15 83 MEDIAN INLETS CH. FROM KM 34+000 TO
CZ2UT1180 MEDIAN INLETS CH. FROM KM 36+000 TO 38+000 18 15-Aug-15 03-Sep-15 59 MEDIAN INLETS CH. FROM KM 36+00
CZ2UT1190 MEDIAN INLETS CH. FROM KM 38+000 TO 40+000 18 12-Sep-15 05-Oct-15 35 MEDIAN INLETS CH. FROM KM 38
CONCRETE IN MEDIAN
ME AREA 238 23-Dec-14 06-Oct-15 35 06-Oct-15, CONCRETE IN MEDIAN
CZ2UT1200 CONCRETE IN MEDIAN AREA CH. FROM KM 20+00 16 23-Dec-14 11-Jan-15 33 CONCRETE IN MEDIAN AREA CH. FROM KM 20+000 TO 22+000
CZ2UT1210 CONCRETE IN MEDIAN AREA CH. FROM KM 22+00 16 24-Jan-15 10-Feb-15 87 CONCRETE IN MEDIAN AREA CH. FROM KM 22+000 TO 24+000
CZ2UT1220 CONCRETE IN MEDIAN AREA CH. FROM KM 24+00 16 23-Feb-15 12-Mar-15 61 CONCRETE IN MEDIAN AREA CH. FROM KM 24+000 TO 26+00
CZ2UT1230 CONCRETE IN MEDIAN AREA CH. FROM KM 26+00 16 25-Mar-15 12-Apr-15 35 CONCRETE IN MEDIAN AREA CH. FROM KM 26+000 TO 2
CZ2UT1240 CONCRETE IN MEDIAN AREA CH. FROM KM 28+00 16 22-Apr-15 10-May-15 88 CONCRETE IN MEDIAN AREA CH. FROM KM 28+000 T
CZ2UT1250 CONCRETE IN MEDIAN AREA CH. FROM KM 30+00 16 20-May-15 07-Jun-15 64 CONCRETE IN MEDIAN AREA CH. FROM KM 30+0
CZ2UT1260 CONCRETE IN MEDIAN AREA CH. FROM KM 32+00 16 17-Jun-15 05-Jul-15 40 CONCRETE IN MEDIAN AREA CH. FROM KM 3
CZ2UT1270 CONCRETE IN MEDIAN AREA CH. FROM KM 34+00 16 15-Jul-15 08-Aug-15 83 CONCRETE IN MEDIAN AREA CH. FROM
CZ2UT1280 CONCRETE IN MEDIAN AREA CH. FROM KM 36+00 16 18-Aug-15 05-Sep-15 59 CONCRETE IN MEDIAN AREA CH. FR
CZ2UT1290 CONCRETE IN MEDIAN AREA CH. FROM KM 38+00 16 15-Sep-15 06-Oct-15 35 CONCRETE IN MEDIAN AREA CH
ROAD LIGHTING & ELECTRICAL
EL INSTALLATION 265 25-Nov-14 10-Oct-15 32 10-Oct-15, ROAD LIGHTING & EL
CIVIL WORKS FOR E
ELECTRICAL INSTALLATION 197 25-Nov-14 13-Jul-15 33 13-Jul-15, CIVIL WORKS FOR ELECTRICAL IN
CZ2EL1000 CIVIL WORKS FOR ELECTRICAL INSTALLATION C 20 25-Nov-14 17-Dec-14 32 CIVIL WORKS FOR ELECTRICAL INSTALLATION CH. FROM KM 20+000 TO
CZ2EL1010 CIVIL WORKS FOR ELECTRICAL INSTALLATION C 20 18-Dec-14 11-Jan-15 33 CIVIL WORKS FOR ELECTRICAL INSTALLATION CH. FROM KM 22+00
CZ2EL1020 CIVIL WORKS FOR ELECTRICAL INSTALLATION C 20 12-Jan-15 03-Feb-15 33 CIVIL WORKS FOR ELECTRICAL INSTALLATION CH. FROM KM 24
CZ2EL1030 CIVIL WORKS FOR ELECTRICAL INSTALLATION C 20 04-Feb-15 26-Feb-15 33 CIVIL WORKS FOR ELECTRICAL INSTALLATION CH. FROM KM
CZ2EL1040 CIVIL WORKS FOR ELECTRICAL INSTALLATION C 20 28-Feb-15 22-Mar-15 33 CIVIL WORKS FOR ELECTRICAL INSTALLATION CH. FROM
CZ2EL1050 CIVIL WORKS FOR ELECTRICAL INSTALLATION C 20 23-Mar-15 14-Apr-15 33 CIVIL WORKS FOR ELECTRICAL INSTALLATION CH. FRO
CZ2EL1060 CIVIL WORKS FOR ELECTRICAL INSTALLATION C 20 15-Apr-15 07-May-15 33 CIVIL WORKS FOR ELECTRICAL INSTALLATION CH. F
CZ2EL1070 CIVIL WORKS FOR ELECTRICAL INSTALLATION C 19 09-May-15 30-May-15 33 CIVIL WORKS FOR ELECTRICAL INSTALLATION CH
CZ2EL1080 CIVIL WORKS FOR ELECTRICAL INSTALLATION C 19 31-May-15 21-Jun-15 33 CIVIL WORKS FOR ELECTRICAL INSTALLATION
CZ2EL1090 CIVIL WORKS FOR ELECTRICAL INSTALLATION C 19 22-Jun-15 13-Jul-15 33 CIVIL WORKS FOR ELECTRICAL INSTALLATI
SUBSTATION FEEDER
FEEDE PILLARS 170 07-Dec-14 23-Jun-15 50 23-Jun-15, SUBSTATION FEEDER PILLARS
CZ2EL1100 SUB STATION & FEEDER PILLARS CH. FROM KM 2 17 07-Dec-14 25-Dec-14 32 SUB STATION & FEEDER PILLARS CH. FROM KM 20+000 TO 22+000
CZ2EL1110 SUB STATION & FEEDER PILLARS CH. FROM KM 2 17 27-Dec-14 15-Jan-15 32 SUB STATION & FEEDER PILLARS CH. FROM KM 22+000 TO 24+000
CZ2EL1120 SUB STATION & FEEDER PILLARS CH. FROM KM 2 17 17-Jan-15 04-Feb-15 32 SUB STATION & FEEDER PILLARS CH. FROM KM 24+000 TO 26+00
CZ2EL1130 SUB STATION & FEEDER PILLARS CH. FROM KM 2 17 05-Feb-15 24-Feb-15 35 SUB STATION & FEEDER PILLARS CH. FROM KM 26+000 TO 28+
CZ2EL1140 SUB STATION & FEEDER PILLARS CH. FROM KM 2 17 25-Feb-15 16-Mar-15 38 SUB STATION & FEEDER PILLARS CH. FROM KM 28+000 TO
CZ2EL1150 SUB STATION & FEEDER PILLARS CH. FROM KM 3 17 17-Mar-15 05-Apr-15 41 SUB STATION & FEEDER PILLARS CH. FROM KM 30+000 T
CZ2EL1160 SUB STATION & FEEDER PILLARS CH. FROM KM 3 17 06-Apr-15 25-Apr-15 44 SUB STATION & FEEDER PILLARS CH. FROM KM 32+00
CZ2EL1170 SUB STATION & FEEDER PILLARS CH. FROM KM 3 17 26-Apr-15 14-May-15 46 SUB STATION & FEEDER PILLARS CH. FROM KM 34+
CZ2EL1180 SUB STATION & FEEDER PILLARS CH. FROM KM 3 17 16-May-15 03-Jun-15 48 SUB STATION & FEEDER PILLARS CH. FROM KM 3
CZ2EL1190 SUB STATION & FEEDER PILLARS CH. FROM KM 3 17 04-Jun-15 23-Jun-15 50 SUB STATION & FEEDER PILLARS CH. FROM K
CABLING WORKS 156 02-Feb-15 08-Aug-15 69 08-Aug-15, CABLING WORKS
CZ2EL1200 CABLING WORKS CH. FROM KM 20+000 TO 22+00 16 02-Feb-15 19-Feb-15 32 CABLING WORKS CH. FROM KM 20+000 TO 22+000

Actual Work Critical Remaining Work Summary Page 38 of 57 TASK filter: All Activities

Remaining Work Milestone © Oracle Corporation


DUALIZATION OF MAHDAH - AL RAWDAH ROAD PROJECT Classic Schedule Layout 25-May-14 16:51

Activity ID Activity Name Original Start Finish Total Float Critical 2014 2015 2016
Duration
S Oct N D J F M Apr M J Jul A S Oct N D Jan F M Apr M J Jul A S Oct N D J F M Apr M J
CZ2EL1210 CABLING WORKS CH. FROM KM 22+000 TO 24+00 16 21-Feb-15 10-Mar-15 32 CABLING WORKS CH. FROM KM 22+000 TO 24+000
CZ2EL1220 CABLING WORKS CH. FROM KM 24+000 TO 26+00 16 11-Mar-15 29-Mar-15 32 CABLING WORKS CH. FROM KM 24+000 TO 26+000
CZ2EL1230 CABLING WORKS CH. FROM KM 26+000 TO 28+00 16 30-Mar-15 16-Apr-15 69 CABLING WORKS CH. FROM KM 26+000 TO 28+000
CZ2EL1240 CABLING WORKS CH. FROM KM 28+000 TO 30+00 16 18-Apr-15 05-May-15 69 CABLING WORKS CH. FROM KM 28+000 TO 30+000
CZ2EL1250 CABLING WORKS CH. FROM KM 30+000 TO 32+00 16 06-May-15 24-May-15 69 CABLING WORKS CH. FROM KM 30+000 TO 32+000
CZ2EL1260 CABLING WORKS CH. FROM KM 32+000 TO 34+00 15 25-May-15 10-Jun-15 69 CABLING WORKS CH. FROM KM 32+000 TO 34+0
CZ2EL1270 CABLING WORKS CH. FROM KM 34+000 TO 36+00 15 11-Jun-15 28-Jun-15 69 CABLING WORKS CH. FROM KM 34+000 TO 36
CZ2EL1280 CABLING WORKS CH. FROM KM 36+000 TO 38+00 15 29-Jun-15 15-Jul-15 69 CABLING WORKS CH. FROM KM 36+000 TO
CZ2EL1290 CABLING WORKS CH. FROM KM 38+000 TO 40+00 15 16-Jul-15 08-Aug-15 69 CABLING WORKS CH. FROM KM 38+000
HIGH TENSION OVE
OVERHEAD ELECTRICAL LINE 122 30-Mar-15 24-Aug-15 55 24-Aug-15, HIGH TENSION OVERHEAD
CZ2EL1300 HIGH TENSION OVERHEAD ELECTRICAL LINE CH 13 30-Mar-15 13-Apr-15 34 HIGH TENSION OVERHEAD ELECTRICAL LINE CH. FROM
CZ2EL1310 HIGH TENSION OVERHEAD ELECTRICAL LINE CH 13 14-Apr-15 28-Apr-15 34 HIGH TENSION OVERHEAD ELECTRICAL LINE CH. FRO
CZ2EL1320 HIGH TENSION OVERHEAD ELECTRICAL LINE CH 12 29-Apr-15 12-May-15 34 HIGH TENSION OVERHEAD ELECTRICAL LINE CH. F
CZ2EL1330 HIGH TENSION OVERHEAD ELECTRICAL LINE CH 12 13-May-15 26-May-15 37 HIGH TENSION OVERHEAD ELECTRICAL LINE CH.
CZ2EL1340 HIGH TENSION OVERHEAD ELECTRICAL LINE CH 12 27-May-15 09-Jun-15 40 HIGH TENSION OVERHEAD ELECTRICAL LINE CH
CZ2EL1350 HIGH TENSION OVERHEAD ELECTRICAL LINE CH 12 10-Jun-15 23-Jun-15 43 HIGH TENSION OVERHEAD ELECTRICAL LINE
CZ2EL1360 HIGH TENSION OVERHEAD ELECTRICAL LINE CH 12 24-Jun-15 07-Jul-15 46 HIGH TENSION OVERHEAD ELECTRICAL LIN
CZ2EL1370 HIGH TENSION OVERHEAD ELECTRICAL LINE CH 12 08-Jul-15 27-Jul-15 49 HIGH TENSION OVERHEAD ELECTRICAL L
CZ2EL1380 HIGH TENSION OVERHEAD ELECTRICAL LINE CH 12 28-Jul-15 10-Aug-15 52 HIGH TENSION OVERHEAD ELECTRICAL
CZ2EL1390 HIGH TENSION OVERHEAD ELECTRICAL LINE CH 12 11-Aug-15 24-Aug-15 55 HIGH TENSION OVERHEAD ELECTRIC
ROAD LIGHTING MASTS,
MA COLUMNS AND LUMINARIES 150 24-Mar-15 20-Sep-15 32 20-Sep-15, ROAD LIGHTING MASTS
CZ2EL1400 ROAD LIGHTING MASTS, COLUMNS & LUMINARIE 15 24-Mar-15 09-Apr-15 32 ROAD LIGHTING MASTS, COLUMNS & LUMINARIES CH. F
CZ2EL1410 ROAD LIGHTING MASTS, COLUMNS & LUMINARIE 15 11-Apr-15 27-Apr-15 32 ROAD LIGHTING MASTS, COLUMNS & LUMINARIES CH
CZ2EL1420 ROAD LIGHTING MASTS, COLUMNS & LUMINARIE 15 28-Apr-15 14-May-15 32 ROAD LIGHTING MASTS, COLUMNS & LUMINARIES
CZ2EL1430 ROAD LIGHTING MASTS, COLUMNS & LUMINARIE 15 16-May-15 01-Jun-15 32 ROAD LIGHTING MASTS, COLUMNS & LUMINARIE
CZ2EL1440 ROAD LIGHTING MASTS, COLUMNS & LUMINARIE 15 02-Jun-15 18-Jun-15 32 ROAD LIGHTING MASTS, COLUMNS & LUMINAR
CZ2EL1450 ROAD LIGHTING MASTS, COLUMNS & LUMINARIE 15 20-Jun-15 06-Jul-15 32 ROAD LIGHTING MASTS, COLUMNS & LUMIN
CZ2EL1460 ROAD LIGHTING MASTS, COLUMNS & LUMINARIE 15 07-Jul-15 29-Jul-15 32 ROAD LIGHTING MASTS, COLUMNS & LUM
CZ2EL1470 ROAD LIGHTING MASTS, COLUMNS & LUMINARIE 15 30-Jul-15 16-Aug-15 32 ROAD LIGHTING MASTS, COLUMNS & L
CZ2EL1480 ROAD LIGHTING MASTS, COLUMNS & LUMINARIE 15 17-Aug-15 02-Sep-15 32 ROAD LIGHTING MASTS, COLUMNS &
CZ2EL1490 ROAD LIGHTING MASTS, COLUMNS & LUMINARIE 15 03-Sep-15 20-Sep-15 32 ROAD LIGHTING MASTS, COLUMN
LIGHTING - TESTING AND COMMISSIONING 149 11-Apr-15 10-Oct-15 32 10-Oct-15, LIGHTING - TESTING
CZ2EL1500 LIGHTING - TESTING & COMMISSIONING CH. FRO 15 11-Apr-15 27-Apr-15 166 LIGHTING - TESTING & COMMISSIONING CH. FROM K
CZ2EL1510 LIGHTING - TESTING & COMMISSIONING CH. FRO 15 28-Apr-15 14-May-15 151 LIGHTING - TESTING & COMMISSIONING CH. FROM
CZ2EL1520 LIGHTING - TESTING & COMMISSIONING CH. FRO 15 16-May-15 01-Jun-15 136 LIGHTING - TESTING & COMMISSIONING CH. FRO
CZ2EL1530 LIGHTING - TESTING & COMMISSIONING CH. FRO 15 02-Jun-15 18-Jun-15 121 LIGHTING - TESTING & COMMISSIONING CH. F
CZ2EL1540 LIGHTING - TESTING & COMMISSIONING CH. FRO 15 20-Jun-15 06-Jul-15 106 LIGHTING - TESTING & COMMISSIONING CH
CZ2EL1550 LIGHTING - TESTING & COMMISSIONING CH. FRO 15 07-Jul-15 29-Jul-15 91 LIGHTING - TESTING & COMMISSIONING
CZ2EL1560 LIGHTING - TESTING & COMMISSIONING CH. FRO 15 30-Jul-15 16-Aug-15 76 LIGHTING - TESTING & COMMISSIONIN
CZ2EL1570 LIGHTING - TESTING & COMMISSIONING CH. FRO 14 17-Aug-15 01-Sep-15 62 LIGHTING - TESTING & COMMISSION
CZ2EL1580 LIGHTING - TESTING & COMMISSIONING CH. FRO 14 03-Sep-15 19-Sep-15 47 LIGHTING - TESTING & COMMISSIO
CZ2EL1590 LIGHTING - TESTING & COMMISSIONING CH. FRO 14 21-Sep-15 10-Oct-15 32 LIGHTING - TESTING & COMMIS
PART 3 (FROM KM 40+0
40+000 to KM 58+594.604) 569 14-Jul-14 02-Jun-16 15 0
EXCAVAT ION ,FILLING AND BITUMINOUS PAVEMENT 563 14-Jul-14 26-May-16 17 26
UTILITIES RELOCATION
RELOCAT 129 14-Jul-14 22-Dec-14 23 22-Dec-14, UTILITIES RELOCATION
CZ3UT1000 PART 3 UTILITIES RELOCATION CH. FROM KM 40 25 14-Jul-14 16-Aug-14 0 PART 3 UTILITIES RELOCATION CH. FROM KM 40+000 TO 44+000
CZ3UT1010 PART 3 UTILITIES RELOCATION CH. FROM KM 44 25 17-Aug-14 14-Sep-14 0 PART 3 UTILITIES RELOCATION CH. FROM KM 44+000 TO 48+000
CZ3UT1020 PART 3 UTILITIES RELOCATION CH. FROM KM 48 25 15-Sep-14 16-Oct-14 0 PART 3 UTILITIES RELOCATION CH. FROM KM 48+000 TO 52+000
CZ3UT1030 PART 3 UTILITIES RELOCATION CH. FROM KM 52 25 18-Oct-14 16-Nov-14 0 PART 3 UTILITIES RELOCATION CH. FROM KM 52+000 TO 56+000
CZ3UT1040 PART 3 UTILITIES RELOCATION CH. FROM KM 56 29 17-Nov-14 22-Dec-14 23 PART 3 UTILITIES RELOCATION CH. FROM KM 56+000 TO 58+594.604
SETTING OUT 194 28-Oct-14 14-Jun-15 101 14-Jun-15, SETTING OUT

Actual Work Critical Remaining Work Summary Page 39 of 57 TASK filter: All Activities

Remaining Work Milestone © Oracle Corporation


DUALIZATION OF MAHDAH - AL RAWDAH ROAD PROJECT Classic Schedule Layout 25-May-14 16:51

Activity ID Activity Name Original Start Finish Total Float Critical 2014 2015 2016
Duration
S Oct N D J F M Apr M J Jul A S Oct N D Jan F M Apr M J Jul A S Oct N D J F M Apr M J
CZ3EW1000 SETTING OUT CH. FROM KM 40+000 TO 42+000 21 28-Oct-14 20-Nov-14 0 SETTING OUT CH. FROM KM 40+000 TO 42+000
CZ3EW1010 SETTING OUT CH. FROM KM 42+000 TO 44+000 21 24-Nov-14 17-Dec-14 5 SETTING OUT CH. FROM KM 42+000 TO 44+000
CZ3EW1020 SETTING OUT CH. FROM KM 44+000 TO 46+000 21 18-Dec-14 12-Jan-15 6 SETTING OUT CH. FROM KM 44+000 TO 46+000
CZ3EW1030 SETTING OUT CH. FROM KM 46+000 TO 48+000 21 13-Jan-15 05-Feb-15 98 SETTING OUT CH. FROM KM 46+000 TO 48+000
CZ3EW1040 SETTING OUT CH. FROM KM 48+000 TO 50+000 21 07-Feb-15 02-Mar-15 99 SETTING OUT CH. FROM KM 48+000 TO 50+000
CZ3EW1050 SETTING OUT CH. FROM KM 50+000 TO 52+000 21 03-Mar-15 26-Mar-15 100 SETTING OUT CH. FROM KM 50+000 TO 52+000
CZ3EW1060 SETTING OUT CH. FROM KM 52+000 TO 54+000 21 28-Mar-15 20-Apr-15 101 SETTING OUT CH. FROM KM 52+000 TO 54+000
CZ3EW1070 SETTING OUT CH. FROM KM 54+000 TO 56+000 21 21-Apr-15 14-May-15 101 SETTING OUT CH. FROM KM 54+000 TO 56+000
CZ3EW1080 SETTING OUT CH. FROM KM 56+000 TO 58+594.6 26 16-May-15 14-Jun-15 101 SETTING OUT CH. FROM KM 56+000 TO 58+594
CLEARING AND GRUBBING
GR FOR ROAD WAY 203 29-Oct-14 25-Jun-15 91 25-Jun-15, CLEARING AND GRUBBING FOR RO
CZ3EW1090 CLEARING & GRUBBING CH. FROM KM 40+000 TO 23 29-Oct-14 26-Nov-14 0 CLEARING & GRUBBING CH. FROM KM 40+000 TO 42+000
CZ3EW1100 CLEARING & GRUBBING CH. FROM KM 42+000 TO 23 27-Nov-14 23-Dec-14 0 CLEARING & GRUBBING CH. FROM KM 42+000 TO 44+000
CZ3EW1110 CLEARING & GRUBBING CH. FROM KM 44+000 TO 22 24-Dec-14 19-Jan-15 0 CLEARING & GRUBBING CH. FROM KM 44+000 TO 46+000
CZ3EW1120 CLEARING & GRUBBING CH. FROM KM 46+000 TO 22 20-Jan-15 14-Feb-15 91 CLEARING & GRUBBING CH. FROM KM 46+000 TO 48+000
CZ3EW1130 CLEARING & GRUBBING CH. FROM KM 48+000 TO 22 15-Feb-15 11-Mar-15 91 CLEARING & GRUBBING CH. FROM KM 48+000 TO 50+000
CZ3EW1140 CLEARING & GRUBBING CH. FROM KM 50+000 TO 22 12-Mar-15 06-Apr-15 91 CLEARING & GRUBBING CH. FROM KM 50+000 TO 52+000
CZ3EW1150 CLEARING & GRUBBING CH. FROM KM 52+000 TO 22 07-Apr-15 02-May-15 91 CLEARING & GRUBBING CH. FROM KM 52+000 TO 54+
CZ3EW1160 CLEARING & GRUBBING CH. FROM KM 54+000 TO 22 03-May-15 27-May-15 91 CLEARING & GRUBBING CH. FROM KM 54+000 TO
CZ3EW1170 CLEARING & GRUBBING CH. FROM KM 56+000 TO 25 28-May-15 25-Jun-15 91 CLEARING & GRUBBING CH. FROM KM 56+000
UNCLASSIFIED EXCAVATIO
EXC N 362 24-Dec-14 05-Mar-16 88 05-Mar-16, U
CZ3EW1180 UNCLASSIFIED EXCAVATION CH. FROM KM 40+00 40 24-Dec-14 09-Feb-15 0 UNCLASSIFIED EXCAVATION CH. FROM KM 40+000 TO 42+000
CZ3EW1190 UNCLASSIFIED EXCAVATION CH. FROM KM 42+00 40 10-Feb-15 28-Mar-15 0 UNCLASSIFIED EXCAVATION CH. FROM KM 42+000 TO 44+
CZ3EW1200 UNCLASSIFIED EXCAVATION CH. FROM KM 44+00 40 29-Mar-15 13-May-15 88 UNCLASSIFIED EXCAVATION CH. FROM KM 44+000 T
CZ3EW1210 UNCLASSIFIED EXCAVATION CH. FROM KM 46+00 40 14-May-15 29-Jun-15 88 UNCLASSIFIED EXCAVATION CH. FROM KM 46
CZ3EW1220 UNCLASSIFIED EXCAVATION CH. FROM KM 48+00 40 30-Jun-15 20-Aug-15 88 UNCLASSIFIED EXCAVATION CH. FROM
CZ3EW1230 UNCLASSIFIED EXCAVATION CH. FROM KM 50+00 40 22-Aug-15 10-Oct-15 88 UNCLASSIFIED EXCAVATION CH
CZ3EW1240 UNCLASSIFIED EXCAVATION CH. FROM KM 52+00 39 11-Oct-15 25-Nov-15 88 UNCLASSIFIED EXCAVATIO
CZ3EW1250 UNCLASSIFIED EXCAVATION CH. FROM KM 54+00 39 26-Nov-15 13-Jan-16 88 UNCLASSIFIED EXC
CZ3EW1260 UNCLASSIFIED EXCAVATION CH. FROM KM 56+00 44 14-Jan-16 05-Mar-16 88 UNCLASSIFIE
REMOVAL OF STRUCTURE
STRU & OBSTRUCTIONS 346 30-Dec-14 21-Feb-16 88 21-Feb-16, REM
CZ3EW1270 REMOVAL OF STRUCTURE & OBSTRUCTIONS CH 30 30-Dec-14 03-Feb-15 38 REMOVAL OF STRUCTURE & OBSTRUCTIONS CH. FROM KM 40+
CZ3EW1280 REMOVAL OF STRUCTURE & OBSTRUCTIONS CH 30 14-Feb-15 19-Mar-15 0 REMOVAL OF STRUCTURE & OBSTRUCTIONS CH. FROM K
CZ3EW1290 REMOVAL OF STRUCTURE & OBSTRUCTIONS CH 30 01-Apr-15 05-May-15 115 REMOVAL OF STRUCTURE & OBSTRUCTIONS CH. FR
CZ3EW1300 REMOVAL OF STRUCTURE & OBSTRUCTIONS CH 30 18-May-15 21-Jun-15 104 REMOVAL OF STRUCTURE & OBSTRUCTIONS
CZ3EW1310 REMOVAL OF STRUCTURE & OBSTRUCTIONS CH 30 04-Jul-15 12-Aug-15 93 REMOVAL OF STRUCTURE & OBSTRUC
CZ3EW1320 REMOVAL OF STRUCTURE & OBSTRUCTIONS CH 30 25-Aug-15 01-Oct-15 111 REMOVAL OF STRUCTURE & OBS
CZ3EW1330 REMOVAL OF STRUCTURE & OBSTRUCTIONS CH 30 15-Oct-15 18-Nov-15 100 REMOVAL OF STRUCTURE
CZ3EW1340 REMOVAL OF STRUCTURE & OBSTRUCTIONS CH 30 02-Dec-15 06-Jan-16 94 REMOVAL OF STRUC
CZ3EW1350 REMOVAL OF STRUCTURE & OBSTRUCTIONS CH 30 18-Jan-16 21-Feb-16 88 REMOVAL OF
EMBANKMENT FILLING
FILL 267 22-Feb-15 12-Jan-16 89 12-Jan-16, EMBANKM
CZ3EW1360 EMBANKMENT FILLING CH. FROM KM 40+000 TO 30 22-Feb-15 28-Mar-15 0 EMBANKMENT FILLING CH. FROM KM 40+000 TO 42+000
CZ3EW1370 EMBANKMENT FILLING CH. FROM KM 42+000 TO 30 29-Mar-15 02-May-15 89 EMBANKMENT FILLING CH. FROM KM 42+000 TO 44+0
CZ3EW1380 EMBANKMENT FILLING CH. FROM KM 44+000 TO 29 03-May-15 04-Jun-15 89 EMBANKMENT FILLING CH. FROM KM 44+000 TO
CZ3EW1390 EMBANKMENT FILLING CH. FROM KM 46+000 TO 29 06-Jun-15 08-Jul-15 89 EMBANKMENT FILLING CH. FROM KM 46+000
CZ3EW1400 EMBANKMENT FILLING CH. FROM KM 48+000 TO 29 09-Jul-15 17-Aug-15 89 EMBANKMENT FILLING CH. FROM KM 4
CZ3EW1410 EMBANKMENT FILLING CH. FROM KM 50+000 TO 29 18-Aug-15 20-Sep-15 89 EMBANKMENT FILLING CH. FROM
CZ3EW1420 EMBANKMENT FILLING CH. FROM KM 52+000 TO 29 21-Sep-15 28-Oct-15 89 EMBANKMENT FILLING CH. FR
CZ3EW1430 EMBANKMENT FILLING CH. FROM KM 54+000 TO 29 29-Oct-15 03-Dec-15 89 EMBANKMENT FILLING C
CZ3EW1440 EMBANKMENT FILLING CH. FROM KM 56+000 TO 33 05-Dec-15 12-Jan-16 89 EMBANKMENT FILL
SUB GRADE PREPARATION
PREPA IN CUT 305 24-Mar-15 27-Mar-16 58 27-Mar-16
CZ3EW1450 SUB GRADE PREPARATION IN CUT CH. FROM KM 33 24-Mar-15 30-Apr-15 0 SUB GRADE PREPARATION IN CUT CH. FROM KM 40+

Actual Work Critical Remaining Work Summary Page 40 of 57 TASK filter: All Activities

Remaining Work Milestone © Oracle Corporation


DUALIZATION OF MAHDAH - AL RAWDAH ROAD PROJECT Classic Schedule Layout 25-May-14 16:51

Activity ID Activity Name Original Start Finish Total Float Critical 2014 2015 2016
Duration
S Oct N D J F M Apr M J Jul A S Oct N D Jan F M Apr M J Jul A S Oct N D J F M Apr M J
CZ3EW1460 SUB GRADE PREPARATION IN CUT CH. FROM KM 33 04-May-15 10-Jun-15 64 SUB GRADE PREPARATION IN CUT CH. FROM KM
CZ3EW1470 SUB GRADE PREPARATION IN CUT CH. FROM KM 33 15-Jun-15 28-Jul-15 61 SUB GRADE PREPARATION IN CUT CH. FR
CZ3EW1480 SUB GRADE PREPARATION IN CUT CH. FROM KM 33 29-Jul-15 05-Sep-15 61 SUB GRADE PREPARATION IN CUT C
CZ3EW1490 SUB GRADE PREPARATION IN CUT CH. FROM KM 33 06-Sep-15 18-Oct-15 61 SUB GRADE PREPARATION IN C
CZ3EW1500 SUB GRADE PREPARATION IN CUT CH. FROM KM 33 19-Oct-15 25-Nov-15 61 SUB GRADE PREPARATIO
CZ3EW1510 SUB GRADE PREPARATION IN CUT CH. FROM KM 33 26-Nov-15 06-Jan-16 61 SUB GRADE PREPAR
CZ3EW1520 SUB GRADE PREPARATION IN CUT CH. FROM KM 33 07-Jan-16 14-Feb-16 61 SUB GRADE PR
CZ3EW1530 SUB GRADE PREPARATION IN CUT CH. FROM KM 33 18-Feb-16 27-Mar-16 58 SUB GRAD
TRENCH EXCAVATION
EXCAVATIO AND BACK FILLING 305 24-Mar-15 27-Mar-16 58 27-Mar-16
CZ3EW1540 TRENCH EXCAVATION & BACKFILLING CH. FRO M 34 24-Mar-15 02-May-15 0 TRENCH EXCAVATION & BAC KFILLING CH. FRO M KM
CZ3EW1550 TRENCH EXCAVATION & BACKFILLING CH. FRO M 34 03-May-15 10-Jun-15 13 TRENCH EXCAVATION & BACKFILLING CH. FRO M
CZ3EW1560 TRENCH EXCAVATION & BACKFILLING CH. FRO M 34 11-Jun-15 26-Jul-15 54 TRENCH EXCAVATION & BACKFILLING CH.
CZ3EW1570 TRENCH EXCAVATION & BACKFILLING CH. FRO M 34 27-Jul-15 03-Sep-15 54 TRENCH EXCAVATION & BACKFILLING
CZ3EW1580 TRENCH EXCAVATION & BACKFILLING CH. FRO M 33 05-Sep-15 17-Oct-15 55 TRENCH EXCAVATION & BACKF
CZ3EW1590 TRENCH EXCAVATION & BACKFILLING CH. FRO M 33 18-Oct-15 24-Nov-15 56 TRENCH EXCAVATION & BA
CZ3EW1600 TRENCH EXCAVATION & BACKFILLING CH. FRO M 33 25-Nov-15 05-Jan-16 57 TRENCH EXCAVATIO
CZ3EW1610 TRENCH EXCAVATION & BACKFILLING CH. FRO M 33 06-Jan-16 13-Feb-16 58 TRENCH EXCAV
CZ3EW1620 TRENCH EXCAVATION & BACKFILLING CH. FRO M 37 14-Feb-16 27-Mar-16 58 TRENCH E
AGGREGATE BASE COURSE 309 08-Apr-15 16-Apr-16 41 16-Apr-
CZ3RW1000 AGGREGATE BASE COURSE CH. FROM KM 40+00 34 08-Apr-15 17-May-15 0 AGGREGATE BASE COURSE CH. FROM KM 40+000
CZ3RW1010 AGGREGATE BASE COURSE CH. FROM KM 42+00 34 18-May-15 25-Jun-15 0 AGGREGATE BASE COURSE CH. FROM KM 42
CZ3RW1020 AGGREGATE BASE COURSE CH. FROM KM 44+00 34 27-Jun-15 10-Aug-15 41 AGGREGATE BASE COURSE CH. FROM
CZ3RW1030 AGGREGATE BASE COURSE CH. FROM KM 46+00 34 11-Aug-15 19-Sep-15 41 AGGREGATE BASE COURSE CH. F
CZ3RW1040 AGGREGATE BASE COURSE CH. FROM KM 48+00 34 20-Sep-15 02-Nov-15 41 AGGREGATE BASE COURSE
CZ3RW1050 AGGREGATE BASE COURSE CH. FROM KM 50+00 34 03-Nov-15 14-Dec-15 41 AGGREGATE BASE COU
CZ3RW1060 AGGREGATE BASE COURSE CH. FROM KM 52+00 34 15-Dec-15 24-Jan-16 41 AGGREGATE BASE
CZ3RW1070 AGGREGATE BASE COURSE CH. FROM KM 54+00 34 25-Jan-16 03-Mar-16 41 AGGREGATE
CZ3RW1080 AGGREGATE BASE COURSE CH. FROM KM 56+00 37 05-Mar-16 16-Apr-16 41 AGGRE
BITUMINOUS PAVEMENT
PAVEM 279 23-Jun-15 26-May-16 6 26
ASPHALT BASE COURSE
C 262 23-Jun-15 07-May-16 23 07-M
CZ3RW1090 ASPHALT BASE COURSE CH. FROM KM 40+000 TO 29 23-Jun-15 01-Aug-15 3 ASPHALT BASE COURSE CH. FROM KM 40
CZ3RW1100 ASPHALT BASE COURSE CH. FROM KM 42+000 TO 29 02-Aug-15 03-Sep-15 18 ASPHALT BASE COURSE CH. FROM K
CZ3RW1110 ASPHALT BASE COURSE CH. FROM KM 44+000 TO 29 05-Sep-15 11-Oct-15 18 ASPHALT BASE COURSE CH. FR
CZ3RW1120 ASPHALT BASE COURSE CH. FROM KM 46+000 TO 29 12-Oct-15 15-Nov-15 18 ASPHALT BASE COURSE CH
CZ3RW1130 ASPHALT BASE COURSE CH. FROM KM 48+000 TO 29 16-Nov-15 21-Dec-15 18 ASPHALT BASE COURS
CZ3RW1140 ASPHALT BASE COURSE CH. FROM KM 50+000 TO 29 22-Dec-15 25-Jan-16 21 ASPHALT BASE CO
CZ3RW1150 ASPHALT BASE COURSE CH. FROM KM 52+000 TO 29 26-Jan-16 28-Feb-16 21 ASPHALT BAS
CZ3RW1160 ASPHALT BASE COURSE CH. FROM KM 54+000 TO 29 29-Feb-16 02-Apr-16 21 ASPHALT
CZ3RW1170 ASPHALT BASE COURSE CH. FROM KM 56+000 TO 30 03-Apr-16 07-May-16 23 ASPH
ASPHALT WEARING
WEARI COURSE 264 11-Jul-15 26-May-16 6 26
CZ3RW1180 ASPHALT WEARING COURSE CH. FROM KM 40+0 29 11-Jul-15 18-Aug-15 3 ASPHALT WEARING COURSE CH. FROM
CZ3RW1190 ASPHALT WEARING COURSE CH. FROM KM 42+0 29 19-Aug-15 21-Sep-15 3 ASPHALT WEARING COURSE CH. F
CZ3RW1200 ASPHALT WEARING COURSE CH. FROM KM 44+0 29 22-Sep-15 29-Oct-15 3 ASPHALT WEARING COURSE
CZ3RW1210 ASPHALT WEARING COURSE CH. FROM KM 46+0 29 31-Oct-15 05-Dec-15 3 ASPHALT WEARING COU
CZ3RW1220 ASPHALT WEARING COURSE CH. FROM KM 48+0 29 06-Dec-15 09-Jan-16 3 ASPHALT WEARING
CZ3RW1230 ASPHALT WEARING COURSE CH. FROM KM 50+0 29 10-Jan-16 11-Feb-16 6 ASPHALT WEAR
CZ3RW1240 ASPHALT WEARING COURSE CH. FROM KM 52+0 29 13-Feb-16 16-Mar-16 6 ASPHALT W
CZ3RW1250 ASPHALT WEARING COURSE CH. FROM KM 54+0 29 17-Mar-16 19-Apr-16 6 ASPHA
CZ3RW1260 ASPHALT WEARING COURSE CH. FROM KM 56+0 32 20-Apr-16 26-May-16 6 AS
CONCRETE AND CONCRETE
CONC STRUCTURES 409 27-Nov-14 02-Apr-16 68 02-Apr-16
CONSTRUCTION OF BOX CULVERTS 287 27-Nov-14 08-Nov-15 76 08-Nov-15, CONSTRUCTION

Actual Work Critical Remaining Work Summary Page 41 of 57 TASK filter: All Activities

Remaining Work Milestone © Oracle Corporation


DUALIZATION OF MAHDAH - AL RAWDAH ROAD PROJECT Classic Schedule Layout 25-May-14 16:51

Activity ID Activity Name Original Start Finish Total Float Critical 2014 2015 2016
Duration
S Oct N D J F M Apr M J Jul A S Oct N D Jan F M Apr M J Jul A S Oct N D J F M Apr M J
110.2CELL BOX C
CULVERT @ CH40+872 (2.0 x 1.5) 76 27-Nov-14 24-Feb-15 56 24-Feb-15, 110.2CELL BOX CULVERT @ CH40+872 (2.0 x 1.5)
CZ3CU1000 110.2 EXCAVATION 5 27-Nov-14 02-Dec-14 1 110.2 EXCAVATION
CZ3CU1010 110.2 BLINDING CONCRETE 3 03-Dec-14 06-Dec-14 31 110.2 BLINDING CONCRETE
CZ3CU1020 110.2 CONSTRUCTION OF BASE SLABS 17 07-Dec-14 25-Dec-14 46 110.2 CONSTRUCTION OF BASE SLABS
CZ3CU1030 110.2 CONSTRUCTION OF WALLS & TOP SLABS 36 27-Dec-14 07-Feb-15 46 110.2 CONSTRUCTION OF WALLS & TOP SLABS
CZ3CU1040 110.2 CONSTRUCTION OF INLET & OUTLET 10 08-Feb-15 18-Feb-15 46 110.2 CONSTRUCTION OF INLET & OUTLET
CZ3CU1050 110.2 WATER PROOFING WORKS 9 15-Feb-15 24-Feb-15 56 110.2 WATER PROOFING WORKS
111.3CELL BOX C
CULVERT @ CH41+388 (2.0 x 1.5) 74 03-Dec-14 28-Feb-15 53 28-Feb-15, 111.3CELL BOX CULVERT @ CH41+388 (2.0 x 1.5)
CZ3CU1060 111.3 EXCAVATION 6 03-Dec-14 09-Dec-14 10 111.3 EXCAVATION
CZ3CU1070 111.3 BLINDING CONCRETE 3 10-Dec-14 13-Dec-14 28 111.3 BLINDING CONCRETE
CZ3CU1080 111.3 CONSTRUCTION OF BASE SLABS 17 14-Dec-14 01-Jan-15 41 111.3 CONSTRUCTION OF BASE SLABS
CZ3CU1090 111.3 CONSTRUCTION OF WALLS & TOP SLABS 36 04-Jan-15 14-Feb-15 41 111.3 CONSTRUCTION OF WALLS & TOP SLABS
CZ3CU1100 111.3 CONSTRUCTION OF INLET & OUTLET 7 15-Feb-15 22-Feb-15 43 111.3 CONSTRUCTION OF INLET & OUTLET
CZ3CU1110 111.3 WATER PROOFING WORKS 9 18-Feb-15 28-Feb-15 53 111.3 WATER PROOFING WORKS
116.3CELL BOX C
CULVERT @ CH42+580 (4.0 x 2.0) 73 10-Dec-14 05-Mar-15 48 05-Mar-15, 116.3CELL BOX CULVERT @ CH42+580 (4.0 x 2.0)
CZ3CU1120 116.3 EXCAVATION 5 10-Dec-14 15-Dec-14 10 116.3 EXCAVATION
CZ3CU1130 116.3 BLINDING CONCRETE 2 16-Dec-14 17-Dec-14 26 116.3 BLINDING CONCRETE
CZ3CU1140 116.3 CONSTRUCTION OF BASE SLABS 19 18-Dec-14 10-Jan-15 38 116.3 CONSTRUCTION OF BASE SLABS
CZ3CU1150 116.3 CONSTRUCTION OF WALLS & TOP SLABS 33 11-Jan-15 17-Feb-15 38 116.3 CONSTRUCTION OF WALLS & TOP SLABS
CZ3CU1160 116.3 CONSTRUCTION OF INLET & OUTLET 9 18-Feb-15 28-Feb-15 38 116.3 CONSTRUCTION OF INLET & OUTLET
CZ3CU1170 116.3 WATER PROOFING WORKS 9 24-Feb-15 05-Mar-15 48 116.3 WATER PROOFING WORKS
117.14CELL BOX CULVERT @ CH42+737 (4.0 x 2.0) 127 16-Dec-14 13-May-15 88 13-May-15, 117.14CELL BOX CULVERT @ CH42+737 (
CZ3CU1180 117.14 EXCAVATION 7 16-Dec-14 23-Dec-14 10 117.14 EXCAVATION
CZ3CU1190 117.14 BLINDING CONCRETE 5 24-Dec-14 29-Dec-14 21 117.14 BLINDING CONCRETE
CZ3CU1200 117.14 CONSTRUCTION OF BASE SLABS 38 30-Dec-14 12-Feb-15 88 117.14 CONSTRUCTION OF BASE SLABS
CZ3CU1210 117.14 CONSTRUCTION OF WALLS & TOP SLABS 56 14-Feb-15 19-Apr-15 88 117.14 CONSTRUCTION OF WALLS & TOP SLABS
CZ3CU1220 117.14 CONSTRUCTION OF INLET & OUTLET 16 20-Apr-15 07-May-15 88 117.14 CONSTRUCTION OF INLET & OUTLET
CZ3CU1230 117.14 WATER PROOFING WORKS 15 27-Apr-15 13-May-15 88 117.14 WATER PROOFING WORKS
118.36CELL BOX CULVERT @ CH42+918 (4.0 x 2.0) 145 24-Dec-14 11-Jun-15 96 11-Jun-15, 118.36CELL BOX CULVERT @ CH42+91
CZ3CU1240 118.36 EXCAVATION 8 24-Dec-14 01-Jan-15 10 118.36 EXCAVATION
CZ3CU1250 118.36 BLINDING CONCRETE 5 04-Jan-15 08-Jan-15 18 118.36 BLINDING CONCRETE
CZ3CU1260 118.36 CONSTRUCTION OF BASE SLABS 41 10-Jan-15 25-Feb-15 96 118.36 CONSTRUCTION OF BASE SLABS
CZ3CU1270 118.36 CONSTRUCTION OF WALLS & TOP SLABS 67 26-Feb-15 14-May-15 96 118.36 CONSTRUCTION OF WALLS & TOP SLABS
CZ3CU1280 118.36 CONSTRUCTION OF INLET & OUTLET 19 16-May-15 06-Jun-15 96 118.36 CONSTRUCTION OF INLET & OUTLET
CZ3CU1290 118.36 WATER PROOFING WORKS 20 20-May-15 11-Jun-15 96 118.36 WATER PROOFING WORKS
123.4CELL BOX C
CULVERT @ CH44+160 (2.0 x 2.0) 77 04-Jan-15 02-Apr-15 24 02-Apr-15, 123.4CELL BOX CULVERT @ CH44+160 (2.0 x 2.0
CZ3CU1300 123.4 EXCAVATION 6 04-Jan-15 10-Jan-15 10 123.4 EXCAVATION
CZ3CU1310 123.4 BLINDING CONCRETE 2 11-Jan-15 12-Jan-15 17 123.4 BLINDING CONCRETE
CZ3CU1320 123.4 CONSTRUCTION OF BASE SLABS 22 13-Jan-15 07-Feb-15 21 123.4 CONSTRUCTION OF BASE SLABS
CZ3CU1330 123.4 CONSTRUCTION OF WALLS & TOP SLABS 32 08-Feb-15 16-Mar-15 24 123.4 CONSTRUCTION OF WALLS & TOP SLABS
CZ3CU1340 123.4 CONSTRUCTION OF INLET & OUTLET 10 17-Mar-15 28-Mar-15 24 123.4 CONSTRUCTION OF INLET & OUTLET
CZ3CU1350 123.4 WATER PROOFING WORKS 9 24-Mar-15 02-Apr-15 24 123.4 WATER PROOFING WORKS
125.2CELL BOX C
CULVERT @ CH45+650 (2.0 x 1.5) 77 11-Jan-15 09-Apr-15 18 09-Apr-15, 125.2CELL BOX CULVERT @ CH45+650 (2.0 x 1
CZ3CU1360 125.2 EXCAVATION 5 11-Jan-15 15-Jan-15 10 125.2 EXCAVATION
CZ3CU1370 125.2 BLINDING CONCRETE 3 17-Jan-15 19-Jan-15 14 125.2 BLINDING CONCRETE
CZ3CU1380 125.2 CONSTRUCTION OF BASE SLABS 21 20-Jan-15 12-Feb-15 16 125.2 CONSTRUCTION OF BASE SLABS
CZ3CU1390 125.2 CONSTRUCTION OF WALLS & TOP SLABS 33 14-Feb-15 23-Mar-15 18 125.2 CONSTRUCTION OF WALLS & TOP SLABS
CZ3CU1400 125.2 CONSTRUCTION OF INLET & OUTLET 10 24-Mar-15 04-Apr-15 18 125.2 CONSTRUCTION OF INLET & OUTLET
CZ3CU1410 125.2 WATER PROOFING WORKS 9 31-Mar-15 09-Apr-15 18 125.2 WATER PROOFING WORKS
126.6CELL BOX C
CULVERT @ CH45+900 (2.0 x 1.5) 77 17-Jan-15 15-Apr-15 13 15-Apr-15, 126.6CELL BOX CULVERT @ CH45+900 (2.0 x 1
CZ3CU1420 126.6 EXCAVATION 5 17-Jan-15 21-Jan-15 10 126.6 EXCAVATION

Actual Work Critical Remaining Work Summary Page 42 of 57 TASK filter: All Activities

Remaining Work Milestone © Oracle Corporation


DUALIZATION OF MAHDAH - AL RAWDAH ROAD PROJECT Classic Schedule Layout 25-May-14 16:51

Activity ID Activity Name Original Start Finish Total Float Critical 2014 2015 2016
Duration
S Oct N D J F M Apr M J Jul A S Oct N D Jan F M Apr M J Jul A S Oct N D J F M Apr M J
CZ3CU1430 126.6 BLINDING CONCRETE 3 22-Jan-15 25-Jan-15 12 126.6 BLINDING CONCRETE
CZ3CU1440 126.6 CONSTRUCTION OF BASE SLABS 19 26-Jan-15 16-Feb-15 13 126.6 CONSTRUCTION OF BASE SLABS
CZ3CU1450 126.6 CONSTRUCTION OF WALLS & TOP SLABS 35 17-Feb-15 29-Mar-15 13 126.6 CONSTRUCTION OF WALLS & TOP SLABS
CZ3CU1460 126.6 CONSTRUCTION OF INLET & OUTLET 10 30-Mar-15 09-Apr-15 13 126.6 CONSTRUCTION OF INLET & OUTLET
CZ3CU1470 126.6 WATER PROOFING WORKS 9 06-Apr-15 15-Apr-15 13 126.6 WATER PROOFING WORKS
127.3CELL BOX C
CULVERT @ CH46+250 (2.0 x 1.5) 75 22-Jan-15 19-Apr-15 10 19-Apr-15, 127.3CELL BOX CULVERT @ CH46+250 (2.0 x
CZ3CU1480 127.3 EXCAVATION 5 22-Jan-15 27-Jan-15 10 127.3 EXCAVATION
CZ3CU1490 127.3 BLINDING CONCRETE 3 28-Jan-15 31-Jan-15 10 127.3 BLINDING CONCRETE
CZ3CU1500 127.3 CONSTRUCTION OF BASE SLABS 19 01-Feb-15 22-Feb-15 10 127.3 CONSTRUCTION OF BASE SLABS
CZ3CU1510 127.3 CONSTRUCTION OF WALLS & TOP SLABS 35 23-Feb-15 04-Apr-15 10 127.3 CONSTRUCTION OF WALLS & TOP SLABS
CZ3CU1520 127.3 CONSTRUCTION OF INLET & OUTLET 8 05-Apr-15 13-Apr-15 10 127.3 CONSTRUCTION OF INLET & OUTLET
CZ3CU1530 127.3 WATER PROOFING WORKS 9 09-Apr-15 19-Apr-15 10 127.3 WATER PROOFING WORKS
128.6CELL BOX C
CULVERT @ CH46+500 (2.0 x 1.5) 121 28-Jan-15 17-Jun-15 91 17-Jun-15, 128.6CELL BOX CULVERT @ CH46+50
CZ3CU1540 128.6 EXCAVATION 9 28-Jan-15 07-Feb-15 61 128.6 EXCAVATION
CZ3CU1550 128.6 BLINDING CONCRETE 5 08-Feb-15 12-Feb-15 64 128.6 BLINDING CONCRETE
CZ3CU1560 128.6 CONSTRUCTION OF BASE SLABS 31 14-Feb-15 21-Mar-15 64 128.6 CONSTRUCTION OF BASE SLABS
CZ3CU1570 128.6 CONSTRUCTION OF WALLS & TOP SLABS 55 22-Mar-15 24-May-15 64 128.6 CONSTRUCTION OF WALLS & TOP SLABS
CZ3CU1580 128.6 CONSTRUCTION OF INLET & OUTLET 16 25-May-15 11-Jun-15 91 128.6 CONSTRUCTION OF INLET & OUTLET
CZ3CU1590 128.6 WATER PROOFING WORKS 17 30-May-15 17-Jun-15 91 128.6 WATER PROOFING WORKS
129.2CELL BOX C
CULVERT @ CH46+570 (2.0 x1.5) 78 08-Feb-15 09-May-15 92 09-May-15, 129.2CELL BOX CULVERT @ CH46+570 (2.
CZ3CU1600 129.2 EXCAVATION 5 08-Feb-15 12-Feb-15 61 129.2 EXCAVATION
CZ3CU1610 129.2 BLINDING CONCRETE 3 14-Feb-15 16-Feb-15 77 129.2 BLINDING CONCRETE
CZ3CU1620 129.2 CONSTRUCTION OF BASE SLABS 21 17-Feb-15 12-Mar-15 83 129.2 CONSTRUCTION OF BASE SLABS
CZ3CU1630 129.2 CONSTRUCTION OF WALLS & TOP SLABS 34 14-Mar-15 21-Apr-15 83 129.2 CONSTRUCTION OF WALLS & TOP SLABS
CZ3CU1640 129.2 CONSTRUCTION OF INLET & OUTLET 10 22-Apr-15 03-May-15 83 129.2 CONSTRUCTION OF INLET & OUTLET
CZ3CU1650 129.2 WATER PROOFING WORKS 9 29-Apr-15 09-May-15 92 129.2 WATER PROOFING WORKS
138.12CELL BOX CULVERT @ CH49+113 (3.0 x 1.5) 123 14-Feb-15 06-Jul-15 75 06-Jul-15, 138.12CELL BOX CULVERT @ CH49
CZ3CU1660 138.12 EXCAVATION 7 14-Feb-15 21-Feb-15 61 138.12 EXCAVATION
CZ3CU1670 138.12 BLINDING CONCRETE 4 22-Feb-15 25-Feb-15 73 138.12 BLINDING CONCRETE
CZ3CU1680 138.12 CONSTRUCTION OF BASE SLABS 34 26-Feb-15 06-Apr-15 75 138.12 CONSTRUCTION OF BASE SLABS
CZ3CU1690 138.12 CONSTRUCTION OF WALLS & TOP SLABS 57 07-Apr-15 11-Jun-15 75 138.12 CONSTRUCTION OF WALLS & TOP SLABS
CZ3CU1700 138.12 CONSTRUCTION OF INLET & OUTLET 16 13-Jun-15 30-Jun-15 75 138.12 CONSTRUCTION OF INLET & OUTLET
CZ3CU1710 138.12 WATER PROOFING WORKS 17 17-Jun-15 06-Jul-15 75 138.12 WATER PROOFING WORKS
139.3CELL BOX C
CULVERT @ CH49+600 (2.0 x 1.5) 78 22-Feb-15 23-May-15 80 23-May-15, 139.3CELL BOX CULVERT @ CH49+600 (
CZ3CU1720 139.3 EXCAVATION 6 22-Feb-15 28-Feb-15 61 139.3 EXCAVATION
CZ3CU1730 139.3 BLINDING CONCRETE 2 01-Mar-15 02-Mar-15 71 139.3 BLINDING CONCRETE
CZ3CU1740 139.3 CONSTRUCTION OF BASE SLABS 23 03-Mar-15 29-Mar-15 80 139.3 CONSTRUCTION OF BASE SLABS
CZ3CU1750 139.3 CONSTRUCTION OF WALLS & TOP SLABS 33 30-Mar-15 06-May-15 80 139.3 CONSTRUCTION OF WALLS & TOP SLABS
CZ3CU1760 139.3 CONSTRUCTION OF INLET & OUTLET 9 07-May-15 17-May-15 80 139.3 CONSTRUCTION OF INLET & OUTLET
CZ3CU1770 139.3 WATER PROOFING WORKS 9 13-May-15 23-May-15 80 139.3 WATER PROOFING WORKS
141.4CELL BOX C
CULVERT @ CH50+063 (2.0 x 1.5) 88 01-Mar-15 10-Jun-15 64 10-Jun-15, 141.4CELL BOX CULVERT @ CH50+063
CZ3CU1780 141.4 EXCAVATION 6 01-Mar-15 07-Mar-15 61 141.4 EXCAVATION
CZ3CU1790 141.4 BLINDING CONCRETE 2 08-Mar-15 09-Mar-15 67 141.4 BLINDING CONCRETE
CZ3CU1800 141.4 CONSTRUCTION OF BASE SLABS 22 10-Mar-15 04-Apr-15 74 141.4 CONSTRUCTION OF BASE SLABS
CZ3CU1810 141.4 CONSTRUCTION OF WALLS & TOP SLABS 33 16-Apr-15 24-May-15 64 141.4 CONSTRUCTION OF WALLS & TOP SLABS
CZ3CU1820 141.4 CONSTRUCTION OF INLET & OUTLET 10 25-May-15 04-Jun-15 64 141.4 CONSTRUCTION OF INLET & OUTLET
CZ3CU1830 141.4 WATER PROOFING WORKS 9 01-Jun-15 10-Jun-15 64 141.4 WATER PROOFING WORKS
142.7CELL BOX C
CULVERT @ CH50+217 (2.0 x 1.5) 124 08-Mar-15 04-Aug-15 88 04-Aug-15, 142.7CELL BOX CULVERT @ C
CZ3CU1840 142.7 EXCAVATION 8 08-Mar-15 16-Mar-15 61 142.7 EXCAVATION
CZ3CU1850 142.7 BLINDING CONCRETE 4 17-Mar-15 21-Mar-15 61 142.7 BLINDING CONCRETE
CZ3CU1860 142.7 CONSTRUCTION OF BASE SLABS 33 22-Mar-15 28-Apr-15 61 142.7 CONSTRUCTION OF BASE SLABS

Actual Work Critical Remaining Work Summary Page 43 of 57 TASK filter: All Activities

Remaining Work Milestone © Oracle Corporation


DUALIZATION OF MAHDAH - AL RAWDAH ROAD PROJECT Classic Schedule Layout 25-May-14 16:51

Activity ID Activity Name Original Start Finish Total Float Critical 2014 2015 2016
Duration
S Oct N D J F M Apr M J Jul A S Oct N D Jan F M Apr M J Jul A S Oct N D J F M Apr M J
CZ3CU1870 142.7 CONSTRUCTION OF WALLS & TOP SLABS 59 29-Apr-15 06-Jul-15 61 142.7 CONSTRUCTION OF WALLS & TOP SLA
CZ3CU1880 142.7 CONSTRUCTION OF INLET & OUTLET 15 07-Jul-15 29-Jul-15 88 142.7 CONSTRUCTION OF INLET & OUTLE
CZ3CU1890 142.7 WATER PROOFING WORKS 17 11-Jul-15 04-Aug-15 88 142.7 WATER PROOFING WORKS
143.4CELL BOX C
CULVERT @ CH50+660 (2.0 x 1.5) 83 17-Mar-15 21-Jun-15 88 21-Jun-15, 143.4CELL BOX CULVERT @ CH50+66
CZ3CU1900 143.4 EXCAVATION 6 17-Mar-15 23-Mar-15 68 143.4 EXCAVATION
CZ3CU1910 143.4 BLINDING CONCRETE 3 24-Mar-15 26-Mar-15 76 143.4 BLINDING CONCRETE
CZ3CU1920 143.4 CONSTRUCTION OF BASE SLABS 21 28-Mar-15 20-Apr-15 90 143.4 CONSTRUCTION OF BASE SLABS
CZ3CU1930 143.4 CONSTRUCTION OF WALLS & TOP SLABS 35 21-Apr-15 31-May-15 91 143.4 CONSTRUCTION OF WALLS & TOP SLABS
CZ3CU1940 143.4 CONSTRUCTION OF INLET & OUTLET 9 06-Jun-15 15-Jun-15 88 143.4 CONSTRUCTION OF INLET & OUTLET
CZ3CU1950 143.4 WATER PROOFING WORKS 9 11-Jun-15 21-Jun-15 88 143.4 WATER PROOFING WORKS
149.2CELL BOX C
CULVERT @ CH52+480 (2.0 x 1.5) 104 24-Mar-15 28-Jul-15 61 28-Jul-15, 149.2CELL BOX CULVERT @ CH5
CZ3CU1960 149.2 EXCAVATION 6 24-Mar-15 30-Mar-15 68 149.2 EXCAVATION
CZ3CU1970 149.2 BLINDING CONCRETE 3 31-Mar-15 02-Apr-15 73 149.2 BLINDING CONCRETE
CZ3CU1980 149.2 CONSTRUCTION OF BASE SLABS 20 06-Apr-15 28-Apr-15 84 149.2 CONSTRUCTION OF BASE SLABS
CZ3CU1990 149.2 CONSTRUCTION OF WALLS & TOP SLABS 36 26-May-15 06-Jul-15 61 149.2 CONSTRUCTION OF WALLS & TOP SLA
CZ3CU2000 149.2 CONSTRUCTION OF INLET & OUTLET 9 07-Jul-15 16-Jul-15 61 149.2 CONSTRUCTION OF INLET & OUTLET
CZ3CU2010 149.2 WATER PROOFING WORKS 9 13-Jul-15 28-Jul-15 61 149.2 WATER PROOFING WORKS
150.2CELL BOX C
CULVERT @ CH52+720 (2.0 x 1.5) 98 31-Mar-15 28-Jul-15 61 28-Jul-15, 150.2CELL BOX CULVERT @ CH5
CZ3CU2020 150.2 EXCAVATION 5 31-Mar-15 05-Apr-15 68 150.2 EXCAVATION
CZ3CU2030 150.2 BLINDING CONCRETE 4 06-Apr-15 09-Apr-15 71 150.2 BLINDING CONCRETE
CZ3CU2040 150.2 CONSTRUCTION OF BASE SLABS 21 11-Apr-15 04-May-15 78 150.2 CONSTRUCTION OF BASE SLABS
CZ3CU2050 150.2 CONSTRUCTION OF WALLS & TOP SLABS 36 05-May-15 15-Jun-15 78 150.2 CONSTRUCTION OF WALLS & TOP SLABS
CZ3CU2060 150.2 CONSTRUCTION OF INLET & OUTLET 10 06-Jul-15 16-Jul-15 61 150.2 CONSTRUCTION OF INLET & OUTLET
CZ3CU2070 150.2 WATER PROOFING WORKS 9 13-Jul-15 28-Jul-15 61 150.2 WATER PROOFING WORKS
151.4CELL BOX C
CULVERT @ CH53+300 (2.0 x 1.5) 93 06-Apr-15 28-Jul-15 61 28-Jul-15, 151.4CELL BOX CULVERT @ CH5
CZ3CU2080 151.4 EXCAVATION 5 06-Apr-15 11-Apr-15 68 151.4 EXCAVATION
CZ3CU2090 151.4 BLINDING CONCRETE 4 12-Apr-15 15-Apr-15 70 151.4 BLINDING CONCRETE
CZ3CU2100 151.4 CONSTRUCTION OF BASE SLABS 21 16-Apr-15 10-May-15 73 151.4 CONSTRUCTION OF BASE SLABS
CZ3CU2110 151.4 CONSTRUCTION OF WALLS & TOP SLABS 36 11-May-15 21-Jun-15 73 151.4 CONSTRUCTION OF WALLS & TOP SLABS
CZ3CU2120 151.4 CONSTRUCTION OF INLET & OUTLET 10 06-Jul-15 16-Jul-15 61 151.4 CONSTRUCTION OF INLET & OUTLET
CZ3CU2130 151.4 WATER PROOFING WORKS 9 13-Jul-15 28-Jul-15 61 151.4 WATER PROOFING WORKS
153.2CELL BOX C
CULVERT @ CH54+242 (2.0 x 1.5) 88 12-Apr-15 28-Jul-15 61 28-Jul-15, 153.2CELL BOX CULVERT @ CH5
CZ3CU2140 153.2 EXCAVATION 6 12-Apr-15 18-Apr-15 68 153.2 EXCAVATION
CZ3CU2150 153.2 BLINDING CONCRETE 3 19-Apr-15 21-Apr-15 68 153.2 BLINDING CONCRETE
CZ3CU2160 153.2 CONSTRUCTION OF BASE SLABS 22 22-Apr-15 17-May-15 68 153.2 CONSTRUCTION OF BASE SLABS
CZ3CU2170 153.2 CONSTRUCTION OF WALLS & TOP SLABS 36 18-May-15 28-Jun-15 68 153.2 CONSTRUCTION OF WALLS & TOP SLAB
CZ3CU2180 153.2 CONSTRUCTION OF INLET & OUTLET 9 07-Jul-15 16-Jul-15 61 153.2 CONSTRUCTION OF INLET & OUTLET
CZ3CU2190 153.2 WATER PROOFING WORKS 9 13-Jul-15 28-Jul-15 61 153.2 WATER PROOFING WORKS
159.2CELL BOX C
CULVERT @ CH55+762 (2.0 x 1.5) 82 19-Apr-15 28-Jul-15 94 28-Jul-15, 159.2CELL BOX CULVERT @ CH5
CZ3CU2200 159.2 EXCAVATION 5 19-Apr-15 23-Apr-15 71 159.2 EXCAVATION
CZ3CU2210 159.2 BLINDING CONCRETE 3 25-Apr-15 27-Apr-15 79 159.2 BLINDING CONCRETE
CZ3CU2220 159.2 CONSTRUCTION OF BASE SLABS 22 28-Apr-15 23-May-15 95 159.2 CONSTRUCTION OF BASE SLABS
CZ3CU2230 159.2 CONSTRUCTION OF WALLS & TOP SLABS 36 24-May-15 04-Jul-15 95 159.2 CONSTRUCTION OF WALLS & TOP SLA
CZ3CU2240 159.2 CONSTRUCTION OF INLET & OUTLET 10 06-Jul-15 16-Jul-15 94 159.2 CONSTRUCTION OF INLET & OUTLET
CZ3CU2250 159.2 WATER PROOFING WORKS 9 13-Jul-15 28-Jul-15 94 159.2 WATER PROOFING WORKS
160.3CELL BOX C
CULVERT @ CH56+230 (3.0 x 2.0) 81 25-Apr-15 02-Aug-15 90 02-Aug-15, 160.3CELL BOX CULVERT @ CH
CZ3CU2260 160.3 EXCAVATION 4 25-Apr-15 28-Apr-15 71 160.3 EXCAVATION
CZ3CU2270 160.3 BLINDING CONCRETE 4 29-Apr-15 03-May-15 78 160.3 BLINDING CONCRETE
CZ3CU2280 160.3 CONSTRUCTION OF BASE SLABS 22 04-May-15 28-May-15 90 160.3 CONSTRUCTION OF BASE SLABS
CZ3CU2290 160.3 CONSTRUCTION OF WALLS & TOP SLABS 36 30-May-15 09-Jul-15 90 160.3 CONSTRUCTION OF WALLS & TOP SLA
CZ3CU2300 160.3 CONSTRUCTION OF INLET & OUTLET 10 11-Jul-15 27-Jul-15 90 160.3 CONSTRUCTION OF INLET & OUTLE

Actual Work Critical Remaining Work Summary Page 44 of 57 TASK filter: All Activities

Remaining Work Milestone © Oracle Corporation


DUALIZATION OF MAHDAH - AL RAWDAH ROAD PROJECT Classic Schedule Layout 25-May-14 16:51

Activity ID Activity Name Original Start Finish Total Float Critical 2014 2015 2016
Duration
S Oct N D J F M Apr M J Jul A S Oct N D Jan F M Apr M J Jul A S Oct N D J F M Apr M J
CZ3CU2310 160.3 WATER PROOFING WORKS 9 22-Jul-15 02-Aug-15 90 160.3 WATER PROOFING WORKS
161.8CELL BOX C
CULVERT @ CH56+420 (3.0 x 2.0) 80 29-Apr-15 05-Aug-15 87 05-Aug-15, 161.8CELL BOX CULVERT @ C
CZ3CU2320 161.8 EXCAVATION 5 29-Apr-15 04-May-15 71 161.8 EXCAVATION
CZ3CU2330 161.8 BLINDING CONCRETE 3 05-May-15 07-May-15 77 161.8 BLINDING CONCRETE
CZ3CU2340 161.8 CONSTRUCTION OF BASE SLABS 22 09-May-15 02-Jun-15 86 161.8 CONSTRUCTION OF BASE SLABS
CZ3CU2350 161.8 CONSTRUCTION OF WALLS & TOP SLABS 36 03-Jun-15 14-Jul-15 86 161.8 CONSTRUCTION OF WALLS & TOP SL
CZ3CU2360 161.8 CONSTRUCTION OF INLET & OUTLET 9 15-Jul-15 30-Jul-15 87 161.8 CONSTRUCTION OF INLET & OUTLE
CZ3CU2370 161.8 WATER PROOFING WORKS 9 27-Jul-15 05-Aug-15 87 161.8 WATER PROOFING WORKS
163.3CELL BOX C
CULVERT @ CH57+080 (2.0 x 1.5) 81 05-May-15 12-Aug-15 81 12-Aug-15, 163.3CELL BOX CULVERT @ C
CZ3CU2380 163.3 EXCAVATION 5 05-May-15 10-May-15 71 163.3 EXCAVATION
CZ3CU2390 163.3 BLINDING CONCRETE 3 11-May-15 13-May-15 75 163.3 BLINDING CONCRETE
CZ3CU2400 163.3 CONSTRUCTION OF BASE SLABS 23 14-May-15 09-Jun-15 81 163.3 CONSTRUCTION OF BASE SLABS
CZ3CU2410 163.3 CONSTRUCTION OF WALLS & TOP SLABS 36 10-Jun-15 27-Jul-15 81 163.3 CONSTRUCTION OF WALLS & TOP S
CZ3CU2420 163.3 CONSTRUCTION OF INLET & OUTLET 9 28-Jul-15 06-Aug-15 81 163.3 CONSTRUCTION OF INLET & OUTL
CZ3CU2430 163.3 WATER PROOFING WORKS 9 03-Aug-15 12-Aug-15 81 163.3 WATER PROOFING WORKS
166.4CELL BOX C
CULVERT @ CH58+150 (2.0 x 1.5) 81 11-May-15 18-Aug-15 76 18-Aug-15, 166.4CELL BOX CULVERT @
CZ3CU2440 166.4 EXCAVATION 5 11-May-15 16-May-15 71 166.4 EXCAVATION
CZ3CU2450 166.4 BLINDING CONCRETE 3 17-May-15 19-May-15 73 166.4 BLINDING CONCRETE
CZ3CU2460 166.4 CONSTRUCTION OF BASE SLABS 22 20-May-15 14-Jun-15 76 166.4 CONSTRUCTION OF BASE SLABS
CZ3CU2470 166.4 CONSTRUCTION OF WALLS & TOP SLABS 36 15-Jun-15 01-Aug-15 76 166.4 CONSTRUCTION OF WALLS & TOP
CZ3CU2480 166.4 CONSTRUCTION OF INLET & OUTLET 10 02-Aug-15 12-Aug-15 76 166.4 CONSTRUCTION OF INLET & OUT
CZ3CU2490 166.4 WATER PROOFING WORKS 9 09-Aug-15 18-Aug-15 76 166.4 WATER PROOFING WORKS
167.6CELL BOX C
CULVERT @ CH58+400 (2.0 x 1.5) 81 17-May-15 24-Aug-15 71 24-Aug-15, 167.6CELL BOX CULVERT @
CZ3CU2500 167.6 EXCAVATION 5 17-May-15 21-May-15 71 167.6 EXCAVATION
CZ3CU2510 167.6 BLINDING CONCRETE 3 23-May-15 25-May-15 71 167.6 BLINDING CONCRETE
CZ3CU2520 167.6 CONSTRUCTION OF BASE SLABS 23 26-May-15 21-Jun-15 71 167.6 CONSTRUCTION OF BASE SLABS
CZ3CU2530 167.6 CONSTRUCTION OF WALLS & TOP SLABS 36 22-Jun-15 08-Aug-15 71 167.6 CONSTRUCTION OF WALLS & TOP
CZ3CU2540 167.6 CONSTRUCTION OF INLET & OUTLET 9 09-Aug-15 18-Aug-15 71 167.6 CONSTRUCTION OF INLET & OUT
CZ3CU2550 167.6 WATER PROOFING WORKS 9 15-Aug-15 24-Aug-15 71 167.6 WATER PROOFING WORKS
SINGLE CELL CULVERTS
CU - 30NOS 287 27-Nov-14 08-Nov-15 76 08-Nov-15, SINGLE CELL CU
PRE CASTING FOR CULVERTS INCLUDING WATER P/F. 194 27-Nov-14 12-Jul-15 169 12-Jul-15, PRE CASTING FOR CULVERTS INC
CZ3CU2560 PART 3 PRECAST FOR CULVERTS INCLUDING WA 20 27-Nov-14 20-Dec-14 1 PART 3 PRECAST FOR CULVERTS INCLUDING WATER P/F. NOS 1,2,3
CZ3CU2570 PART 3 PRECAST FOR CULVERTS INCLUDING WA 20 21-Dec-14 13-Jan-15 15 PART 3 PRECAST FOR CULVERTS INCLUDING WATER P/F. NOS 4,5,6
CZ3CU2580 PART 3 PRECAST FOR CULVERTS INCLUDING WA 20 14-Jan-15 05-Feb-15 22 PART 3 PRECAST FOR CULVERTS INCLUDING WATER P/F. NOS 7
CZ3CU2590 PART 3 PRECAST FOR CULVERTS INCLUDING WA 20 07-Feb-15 01-Mar-15 28 PART 3 PRECAST FOR CULVERTS INCLUDING WATER P/F. NO
CZ3CU2600 PART 3 PRECAST FOR CULVERTS INCLUDING WA 19 02-Mar-15 23-Mar-15 96 PART 3 PRECAST FOR CULVERTS INCLUDING WATER P/F.
CZ3CU2610 PART 3 PRECAST FOR CULVERTS INCLUDING WA 19 24-Mar-15 14-Apr-15 103 PART 3 PRECAST FOR CULVERTS INCLUDING WATER P
CZ3CU2620 PART 3 PRECAST FOR CULVERTS INCLUDING WA 19 15-Apr-15 06-May-15 110 PART 3 PRECAST FOR CULVERTS INCLUDING WATER
CZ3CU2630 PART 3 PRECAST FOR CULVERTS INCLUDING WA 19 07-May-15 28-May-15 117 PART 3 PRECAST FOR CULVERTS INCLUDING WA
CZ3CU2640 PART 3 PRECAST FOR CULVERTS INCLUDING WA 19 30-May-15 20-Jun-15 131 PART 3 PRECAST FOR CULVERTS INCLUDING
CZ3CU2650 PART 3 PRECAST FOR CULVERTS INCLUDING WA 19 21-Jun-15 12-Jul-15 169 PART 3 PRECAST FOR CULVERTS INCLUDIN
EXCAVAT ION OF
O CULVERTS 250 01-Dec-14 24-Sep-15 110 24-Sep-15, EXCAVATION OF CULVE
CZ3CU2660 PART 3 EXCAVATION OF CULVERTS NOS 1,2,3 25 01-Dec-14 29-Dec-14 15 PART 3 EXCAVATION OF CULVERTS NOS 1,2,3
CZ3CU2670 PART 3 EXCAVATION OF CULVERTS NOS 4,5,6 25 30-Dec-14 28-Jan-15 26 PART 3 EXCAVATION OF CULVERTS NOS 4,5,6
CZ3CU2680 PART 3 EXCAVATION OF CULVERTS NOS 7,8,9 25 29-Jan-15 26-Feb-15 28 PART 3 EXCAVATION OF CULVERTS NOS 7,8,9
CZ3CU2690 PART 3 EXCAVATION OF CULVERTS NOS 10,11,12 25 28-Feb-15 28-Mar-15 29 PART 3 EXCAVATION OF CULVERTS NOS 10,11,12
CZ3CU2700 PART 3 EXCAVATION OF CULVERTS NOS 13,14,15 25 29-Mar-15 26-Apr-15 91 PART 3 EXCAVATION OF CULVERTS NOS 13,14,15
CZ3CU2710 PART 3 EXCAVATION OF CULVERTS NOS 16,17,18 25 27-Apr-15 25-May-15 92 PART 3 EXCAVATION OF CULVERTS NOS 16,17,18
CZ3CU2720 PART 3 EXCAVATION OF CULVERTS NOS 19,20,21 25 26-May-15 23-Jun-15 93 PART 3 EXCAVATION OF CULVERTS NOS 19,20
CZ3CU2730 PART 3 EXCAVATION OF CULVERTS NOS 22,23,24 25 24-Jun-15 28-Jul-15 94 PART 3 EXCAVATION OF CULVERTS NOS 2
CZ3CU2740 PART 3 EXCAVATION OF CULVERTS NOS 25,26,27 25 29-Jul-15 26-Aug-15 102 PART 3 EXCAVATION OF CULVERTS NO

Actual Work Critical Remaining Work Summary Page 45 of 57 TASK filter: All Activities

Remaining Work Milestone © Oracle Corporation


DUALIZATION OF MAHDAH - AL RAWDAH ROAD PROJECT Classic Schedule Layout 25-May-14 16:51

Activity ID Activity Name Original Start Finish Total Float Critical 2014 2015 2016
Duration
S Oct N D J F M Apr M J Jul A S Oct N D Jan F M Apr M J Jul A S Oct N D J F M Apr M J
CZ3CU2750 PART 3 EXCAVATION OF CULVERTS NOS 28,29,30 25 27-Aug-15 24-Sep-15 110 PART 3 EXCAVATION OF CULVERT
BLINDING FOR CULVERTS 250 03-Dec-14 30-Sep-15 108 30-Sep-15, BLINDING FOR CULVE
CZ3CU2760 PART 3 BLINDING FOR CULVERTS NOS 1,2,3 25 03-Dec-14 31-Dec-14 15 PART 3 BLINDING FOR CULVERTS NOS 1,2,3
CZ3CU2770 PART 3 BLINDING FOR CULVERTS NOS 4,5,6 25 01-Jan-15 31-Jan-15 24 PART 3 BLINDING FOR CULVERTS NOS 4,5,6
CZ3CU2780 PART 3 BLINDING FOR CULVERTS NOS 7,8,9 25 01-Feb-15 01-Mar-15 26 PART 3 BLINDING FOR CULVERTS NOS 7,8,9
CZ3CU2790 PART 3 BLINDING FOR CULVERTS NOS 10,11,12 25 02-Mar-15 30-Mar-15 27 PART 3 BLINDING FOR CULVERTS NOS 10,11,12
CZ3CU2800 PART 3 BLINDING FOR CULVERTS NOS 13,14,15 25 31-Mar-15 28-Apr-15 89 PART 3 BLINDING FOR CULVERTS NOS 13,14,15
CZ3CU2810 PART 3 BLINDING FOR CULVERTS NOS 16,17,18 25 29-Apr-15 27-May-15 90 PART 3 BLINDING FOR CULVERTS NOS 16,17,18
CZ3CU2820 PART 3 BLINDING FOR CULVERTS NOS 19,20,21 25 28-May-15 25-Jun-15 91 PART 3 BLINDING FOR CULVERTS NOS 19,20,2
CZ3CU2830 PART 3 BLINDING FOR CULVERTS NOS 22,23,24 25 27-Jun-15 30-Jul-15 92 PART 3 BLINDING FOR CULVERTS NOS 22
CZ3CU2840 PART 3 BLINDING FOR CULVERTS NOS 25,26,27 25 01-Aug-15 29-Aug-15 100 PART 3 BLINDING FOR CULVERTS NO
CZ3CU2850 PART 3 BLINDING FOR CULVERTS NOS 28,29,30 25 30-Aug-15 30-Sep-15 108 PART 3 BLINDING FOR CULVERTS
ERECTION OF CULVERTS 240 21-Dec-14 06-Oct-15 103 06-Oct-15, ERECTION OF CULVER
CZ3CU2860 PART 3 ERECTION OF CULVERTS NOS 1,2,3 24 21-Dec-14 18-Jan-15 1 PART 3 ERECTION OF CULVERTS NOS 1,2,3
CZ3CU2870 PART 3 ERECTION OF CULVERTS NOS 4,5,6 24 19-Jan-15 15-Feb-15 11 PART 3 ERECTION OF CULVERTS NOS 4,5,6
CZ3CU2880 PART 3 ERECTION OF CULVERTS NOS 7,8,9 24 16-Feb-15 15-Mar-15 14 PART 3 ERECTION OF CULVERTS NOS 7,8,9
CZ3CU2890 PART 3 ERECTION OF CULVERTS NOS 10,11,12 24 16-Mar-15 12-Apr-15 16 PART 3 ERECTION OF CULVERTS NOS 10,11,12
CZ3CU2900 PART 3 ERECTION OF CULVERTS NOS 13,14,15 24 13-Apr-15 10-May-15 79 PART 3 ERECTION OF CULVERTS NOS 13,14,15
CZ3CU2910 PART 3 ERECTION OF CULVERTS NOS 16,17,18 24 11-May-15 07-Jun-15 81 PART 3 ERECTION OF CULVERTS NOS 16,17,18
CZ3CU2920 PART 3 ERECTION OF CULVERTS NOS 19,20,21 24 08-Jun-15 05-Jul-15 83 PART 3 ERECTION OF CULVERTS NOS 19,20,
CZ3CU2930 PART 3 ERECTION OF CULVERTS NOS 22,23,24 24 06-Jul-15 08-Aug-15 85 PART 3 ERECTION OF CULVERTS NOS 2
CZ3CU2940 PART 3 ERECTION OF CULVERTS NOS 25,26,27 24 09-Aug-15 05-Sep-15 94 PART 3 ERECTION OF CULVERTS NO
CZ3CU2950 PART 3 ERECTION OF CULVERTS NOS 28,29,30 24 06-Sep-15 06-Oct-15 103 PART 3 ERECTION OF CULVERTS
END PORTION CASTING OF CULVERTS 258 24-Dec-14 01-Nov-15 82 01-Nov-15, END PORTION CA
CZ3CU2960 PART 3 END PORTION CASTING OF CULVERTS N 26 24-Dec-14 24-Jan-15 1 PART 3 END PORTION CASTING OF CULVERTS NOS 1,2,3
CZ3CU2970 PART 3 END PORTION CASTING OF CULVERTS N 26 25-Jan-15 23-Feb-15 4 PART 3 END PORTION CASTING OF CULVERTS NOS 4,5,6
CZ3CU2980 PART 3 END PORTION CASTING OF CULVERTS N 26 24-Feb-15 25-Mar-15 5 PART 3 END PORTION CASTING OF CULVERTS NOS 7,8,9
CZ3CU2990 PART 3 END PORTION CASTING OF CULVERTS N 26 26-Mar-15 25-Apr-15 5 PART 3 END PORTION CASTING OF CULVERTS NOS 1
CZ3CU3000 PART 3 END PORTION CASTING OF CULVERTS N 26 26-Apr-15 25-May-15 66 PART 3 END PORTION CASTING OF CULVERTS NO
CZ3CU3010 PART 3 END PORTION CASTING OF CULVERTS N 26 26-May-15 24-Jun-15 66 PART 3 END PORTION CASTING OF CULVERTS
CZ3CU3020 PART 3 END PORTION CASTING OF CULVERTS N 26 25-Jun-15 30-Jul-15 66 PART 3 END PORTION CASTING OF CULV
CZ3CU3030 PART 3 END PORTION CASTING OF CULVERTS N 26 01-Aug-15 30-Aug-15 66 PART 3 END PORTION CASTING OF C
CZ3CU3040 PART 3 END PORTION CASTING OF CULVERTS N 25 31-Aug-15 01-Oct-15 74 PART 3 END PORTION CASTING O
CZ3CU3050 PART 3 END PORTION CASTING OF CULVERTS N 25 03-Oct-15 01-Nov-15 82 PART 3 END PORTION CASTI
CONSTRUCTIO OF INLET & OUT LET
CONSTRUCTION 263 25-Dec-14 08-Nov-15 76 08-Nov-15, CONSTRUCTION
CZ3CU3060 PART 3 CONSTRUCTION OF INLET & OUT LET NO 27 25-Dec-14 26-Jan-15 1 PART 3 CONSTRUCTION OF INLET & OUT LET NOS 1,2,3
CZ3CU3070 PART 3 CONSTRUCTION OF INLET & OUT LET NO 27 27-Jan-15 26-Feb-15 1 PART 3 CONSTRUCTION OF INLET & OUT LET NOS 4,5,6
CZ3CU3080 PART 3 CONSTRUCTION OF INLET & OUT LET NO 27 28-Feb-15 30-Mar-15 1 PART 3 CONSTRUCTION OF INLET & OUT LET NOS 7,8,9
CZ3CU3090 PART 3 CONSTRUCTION OF INLET & OUT LET NO 26 31-Mar-15 29-Apr-15 1 PART 3 CONSTRUCTION OF INLET & OUT LET NOS 10
CZ3CU3100 PART 3 CONSTRUCTION OF INLET & OUT LET NO 26 30-Apr-15 30-May-15 69 PART 3 CONSTRUCTION OF INLET & OUT LET NO
CZ3CU3110 PART 3 CONSTRUCTION OF INLET & OUT LET NO 26 31-May-15 29-Jun-15 69 PART 3 CONSTRUCTION OF INLET & OUT LET
CZ3CU3120 PART 3 CONSTRUCTION OF INLET & OUT LET NO 26 30-Jun-15 04-Aug-15 69 PART 3 CONSTRUCTION OF INLET & OUT
CZ3CU3130 PART 3 CONSTRUCTION OF INLET & OUT LET NO 26 05-Aug-15 03-Sep-15 69 PART 3 CONSTRUCTION OF INLET &
CZ3CU3140 PART 3 CONSTRUCTION OF INLET & OUT LET NO 26 05-Sep-15 07-Oct-15 69 PART 3 CONSTRUCTION OF INL
CZ3CU3150 PART 3 CONSTRUCTION OF INLET & OUT LET NO 26 08-Oct-15 08-Nov-15 76 PART 3 CONSTRUCTION OF
INTERCHANGE RAWDAH
RAW & HUMAIDAH 402 06-Dec-14 02-Apr-16 68 02-Apr-16
INTERCHANGE AT A RAWDAH PART 1 [FROM MAHDAH TO RAWDAH] 203 06-Dec-14 05-Aug-15 43 05-Aug-15, INTERCHANGE AT RAWDAH PA
INT. RAW P 1 G
GEOTECHNICAL INVESTIGATION 33 06-Dec-14 13-Jan-15 23 13-Jan-15, INT. RAW P 1 GEOTECHNICAL INVESTIGATION
CZ3IN1000 INT. RAW P 1 MOBILIZATION 7 06-Dec-14 13-Dec-14 23 INT. RAW P 1 MOBILIZATION
CZ3IN1010 INT. RAW P 1 SOIL INVESTIGATION 14 14-Dec-14 29-Dec-14 23 INT. RAW P 1 SOIL INVESTIGATION
CZ3IN1020 INT. RAW P 1 ANALYSIS AND SUBMISSION 6 30-Dec-14 06-Jan-15 23 INT. RAW P 1 ANALYSIS AND SUBMISSION

Actual Work Critical Remaining Work Summary Page 46 of 57 TASK filter: All Activities

Remaining Work Milestone © Oracle Corporation


DUALIZATION OF MAHDAH - AL RAWDAH ROAD PROJECT Classic Schedule Layout 25-May-14 16:51

Activity ID Activity Name Original Start Finish Total Float Critical 2014 2015 2016
Duration
S Oct N D J F M Apr M J Jul A S Oct N D Jan F M Apr M J Jul A S Oct N D J F M Apr M J
CZ3IN1030 INT. RAW P 1 APPROVAL 6 07-Jan-15 13-Jan-15 23 INT. RAW P 1 APPROVAL
INT. RAW P 1 C
CONSTRUCTION 170 14-Jan-15 05-Aug-15 43 05-Aug-15, INT. RAW P 1 CONSTRUCTION
CZ3IN1040 INT. RAW P-1 SURVEY & SETTING OUT 3 14-Jan-15 17-Jan-15 23 INT. RAW P-1 SURVEY & SETTING OUT
CZ3IN1050 INT. RAW P-1 CLEARING AND GRUBBING 4 18-Jan-15 21-Jan-15 23 INT. RAW P-1 CLEARING AND GRUBBING
CZ3IN1060 INT. RAW P-1 STRUCTURAL EXACAVATION FOR F 15 22-Jan-15 08-Feb-15 23 INT. RAW P-1 STRUCTURAL EXACAVATION FOR FOUNDATION
CZ3IN1070 INT. RAW P-1 PCC FOR FOUNDATION 15 26-Jan-15 11-Feb-15 23 INT. RAW P-1 PCC FOR FOUNDATION
CZ3IN1080 INT. RAW P-1 CONCRETING FOR ABUTMENT (AB 15 03-Feb-15 19-Feb-15 23 INT. RAW P-1 CONCRETING FOR ABUTMENT (AB1, AB2) FOUND
CZ3IN1090 INT. RAW P-1 CONCRETING FOR ABUTMENT (AB 24 21-Feb-15 19-Mar-15 38 INT. RAW P-1 CONCRETING FOR ABUTMENT (AB1, AB2) WA
CZ3IN1100 INT. RAW P-1 CONCRETING FOR PIER FOUNDAT 9 16-Feb-15 25-Feb-15 23 INT. RAW P-1 CONCRETING FOR PIER FOUNDATION
CZ3IN1110 INT. RAW P-1 CONCRETING FOR PIERS 17 26-Feb-15 17-Mar-15 23 INT. RAW P-1 CONCRETING FOR PIERS
CZ3IN1120 INT. RAW P-1 STAGING FOR BOX GIRDERS 17 18-Mar-15 06-Apr-15 23 INT. RAW P-1 STAGING FOR BOX GIRDERS
CZ3IN1130 INT. RAW P-1 FIXING OF BEARING 5 07-Apr-15 12-Apr-15 23 INT. RAW P-1 FIXING OF BEARING
CZ3IN1140 INT. RAW P-1 SOFFIT FORMWORK ALONG WITH 12 05-Apr-15 18-Apr-15 23 INT. RAW P-1 SOFFIT FORMWORK ALONG WITH WING
CZ3IN1150 INT. RAW P-1 REINFORCEMENT FIXING FOR SOF 13 19-Apr-15 03-May-15 23 INT. RAW P-1 REINFORCEMENT FIXING FOR SOFFIT
CZ3IN1160 INT. RAW P-1 POST TENSIONING DUCT PROFILIN 8 29-Apr-15 07-May-15 23 INT. RAW P-1 POST TENSIONING DUCT PROFILING
CZ3IN1170 INT. RAW P-1 CONCRETING OF SOFFIT 1 09-May-15 09-May-15 23 INT. RAW P-1 CONCRETING OF SOFFIT
CZ3IN1180 INT. RAW P-1 REINFORCEMENT FIXING FOR WEB 4 10-May-15 13-May-15 23 INT. RAW P-1 REINFORCEMENT FIXING FOR WEB &
CZ3IN1190 INT. RAW P-1 FORMWORK FIXING FOR WEB & DI 9 14-May-15 24-May-15 23 INT. RAW P-1 FORMWORK FIXING FOR WEB & DIA
CZ3IN1200 INT. RAW P-1 CONCRETING FOR WEB & DIAPHAR 1 25-May-15 25-May-15 43 INT. RAW P-1 CONCRETING FOR WEB & DIAPHARG
CZ3IN1210 INT. RAW P-1 STAGING & FO RMWORK FOR DECK 13 26-May-15 09-Jun-15 43 INT. RAW P-1 STAGING & FO RMWORK FOR DEC
CZ3IN1220 INT. RAW P-1 REINFORCEMENT FIXING FOR DEC 10 10-Jun-15 21-Jun-15 43 INT. RAW P-1 REINFORCEMENT FIXING FOR D
CZ3IN1230 INT. RAW P-1 CONCRETING FOR DECK SLAB 1 22-Jun-15 22-Jun-15 43 INT. RAW P-1 CONCRETING FOR DECK SLAB
CZ3IN1240 INT. RAW P-1 THREADING OF STRANDS 10 23-Jun-15 04-Jul-15 43 INT. RAW P-1 THREADING OF STRANDS
CZ3IN1260 INT. RAW P-1 STRESSING & GROUTING 6 05-Jul-15 11-Jul-15 43 INT. RAW P-1 STRESSING & GROUTING
CZ3IN1270 INT. RAW P-1 DRAINAGE PIPE FIXING 7 12-Jul-15 25-Jul-15 53 INT. RAW P-1 DRAINAGE PIPE FIXING
CZ3IN1280 INT. RAW P-1 APPROACH SLAB 10 12-Jul-15 28-Jul-15 43 INT. RAW P-1 APPROACH SLAB
CZ3IN1290 INT. RAW P-1 EXPANSION JO INT 8 25-Jul-15 02-Aug-15 43 INT. RAW P-1 EXPANSION JO INT
CZ3IN1300 INT. RAW P-1 REMOVAL OF STAGING 7 12-Jul-15 25-Jul-15 53 INT. RAW P-1 REMOVAL OF STAGING
CZ3IN1310 INT. RAW P-1 DIRT WALL & CONCRETE BARRIER 17 12-Jul-15 05-Aug-15 43 INT. RAW P-1 DIRT WALL & CONCRETE B
INTERCHANGE AT A RAWDAH PART 2 [FROM RAWDAH TO MAHDAH] 281 30-Dec-14 06-Dec-15 31 06-Dec-15, INTERCHANG
INT. RAW P 2 G
GEOTECHNICAL INVESTIGATION 48 30-Dec-14 24-Feb-15 92 24-Feb-15, INT. RAW P 2 GEOTECHNICAL INVESTIGATION
CZ3IN1320 INT. RAW P 2 SOIL INVESTIGATION 24 30-Dec-14 27-Jan-15 92 INT. RAW P 2 SOIL INVESTIGATION
CZ3IN1330 INT. RAW P 2 ANALYSIS AND SUBMISSION 10 28-Jan-15 08-Feb-15 92 INT. RAW P 2 ANALYSIS AND SUBMISSION
CZ3IN1340 INT. RAW P 2 APPROVAL 14 09-Feb-15 24-Feb-15 92 INT. RAW P 2 APPROVAL
INT. RAW P 2 C
CONSTRUCTION 164 17-May-15 06-Dec-15 31 06-Dec-15, INT. RAW P 2 C
CZ3IN1350 INT. RAW P-2 SURVEY & SETTING OUT 3 17-May-15 19-May-15 23 INT. RAW P-2 SURVEY & SETTING OUT
CZ3IN1360 INT. RAW P-2 CLEARING AND GRUBBING 4 20-May-15 24-May-15 23 INT. RAW P-2 CLEARING AND GRUBBING
CZ3IN1370 INT. RAW P-2 STRUCTURAL EXACAVATION FOR F 15 25-May-15 10-Jun-15 23 INT. RAW P-2 STRUCTURAL EXACAVATION FOR
CZ3IN1380 INT. RAW P-2 PCC FOR FOUNDATION 10 02-Jun-15 13-Jun-15 23 INT. RAW P-2 PCC FOR FOUNDATION
CZ3IN1390 INT. RAW P-2 CONCRETING FOR ABUTMENT (AB 16 04-Jun-15 22-Jun-15 23 INT. RAW P-2 CONCRETING FOR ABUTMENT (A
CZ3IN1400 INT. RAW P-2 CONCRETING FOR ABUTMENT (AB 22 23-Jun-15 22-Jul-15 35 INT. RAW P-2 CONCRETING FOR ABUTMEN
CZ3IN1410 INT. RAW P-2 CONCRETING FOR PIER FOUNDAT 8 18-Jun-15 27-Jun-15 23 INT. RAW P-2 CONCRETING FOR PIER FOUND
CZ3IN1420 INT. RAW P-2 CONCRETING FOR PIERS 17 28-Jun-15 16-Jul-15 23 INT. RAW P-2 CONCRETING FOR PIERS
CZ3IN1430 INT. RAW P-2 STAGING FOR BOX GIRDERS 15 15-Jul-15 06-Aug-15 23 INT. RAW P-2 STAGING FOR BOX GIRDER
CZ3IN1440 INT. RAW P-2 FIXING OF BEARING 5 08-Aug-15 12-Aug-15 23 INT. RAW P-2 FIXING OF BEARING
CZ3IN1450 INT. RAW P-2 SOFFIT FORMWORK ALONG WITH 12 05-Aug-15 18-Aug-15 23 INT. RAW P-2 SOFFIT FORMWORK ALO
CZ3IN1460 INT. RAW P-2 REINFORCEMENT FIXING FOR SOF 13 19-Aug-15 02-Sep-15 23 INT. RAW P-2 REINFORCEMENT FIXIN
CZ3IN1470 INT. RAW P-2 POST TENSIONING DUCT PROFILIN 8 29-Aug-15 06-Sep-15 23 INT. RAW P-2 POST TENSIONING DU
CZ3IN1480 INT. RAW P-2 CONCRETING OF SOFFIT 1 07-Sep-15 07-Sep-15 23 INT. RAW P-2 CONCRETING OF SOF
CZ3IN1490 INT. RAW P-2 REINFORCEMENT FIXING FOR WEB 4 08-Sep-15 12-Sep-15 23 INT. RAW P-2 REINFORCEMENT FIX
CZ3IN1500 INT. RAW P-2 FORMWORK FIXING FOR WEB & DI 10 13-Sep-15 23-Sep-15 23 INT. RAW P-2 FORMWORK FIXING

Actual Work Critical Remaining Work Summary Page 47 of 57 TASK filter: All Activities

Remaining Work Milestone © Oracle Corporation


DUALIZATION OF MAHDAH - AL RAWDAH ROAD PROJECT Classic Schedule Layout 25-May-14 16:51

Activity ID Activity Name Original Start Finish Total Float Critical 2014 2015 2016
Duration
S Oct N D J F M Apr M J Jul A S Oct N D Jan F M Apr M J Jul A S Oct N D J F M Apr M J
CZ3IN1510 INT. RAW P-2 CONCRETING FOR WEB & DIAPHAR 1 24-Sep-15 24-Sep-15 31 INT. RAW P-2 CONCRETING FOR W
CZ3IN1520 INT. RAW P-2 STAGING & FO RMWORK FOR DECK 9 29-Sep-15 08-Oct-15 31 INT. RAW P-2 STAGING & FO RMW
CZ3IN1530 INT. RAW P-2 REINFORCEMENT FIXING FOR DEC 10 10-Oct-15 21-Oct-15 31 INT. RAW P-2 REINFORCEMEN
CZ3IN1540 INT. RAW P-2 CONCRETING FOR DECK SLAB 1 22-Oct-15 22-Oct-15 31 INT. RAW P-2 CONCRETING FO
CZ3IN1550 INT. RAW P-2 THREADING OF STRANDS 10 24-Oct-15 03-Nov-15 31 INT. RAW P-2 THREADING OF
CZ3IN1560 INT. RAW P-2 STRESSING & GROUTING 6 04-Nov-15 10-Nov-15 31 INT. RAW P-2 STRESSING &
CZ3IN1570 INT. RAW P-2 DRAINAGE PIPE FIXING 8 11-Nov-15 19-Nov-15 43 INT. RAW P-2 DRAINAGE PI
CZ3IN1580 INT. RAW P-2 APPROACH SLAB 12 11-Nov-15 24-Nov-15 31 INT. RAW P-2 APPROACH S
CZ3IN1590 INT. RAW P-2 EXPANSION JO INT 9 21-Nov-15 02-Dec-15 31 INT. RAW P-2 EXPANSION
CZ3IN1600 INT. RAW P-2 REMOVAL OF STAGING 11 11-Nov-15 23-Nov-15 40 INT. RAW P-2 REMOVAL OF
CZ3IN1610 INT. RAW P-2 DIRT WALL & CONCRETE BARRIER 19 12-Nov-15 06-Dec-15 31 INT. RAW P-2 DIRT WALL
INTERCHANGE AT
A HUMAIDAH 357 28-Jan-15 02-Apr-16 68 02-Apr-16
INT. HUM GEOTECHNICAL
GEO INVESTIGATION 48 28-Jan-15 24-Mar-15 168 24-Mar-15, INT. HUM GEOTECHNICAL INVESTIGATION
CZ3IN1620 INT. HUM SOIL INVESTIGATION 24 28-Jan-15 24-Feb-15 168 INT. HUM SOIL INVESTIGATION
CZ3IN1630 INT. HUM ANALYSIS AND SUBMISSION 10 25-Feb-15 08-Mar-15 168 INT. HUM ANALYSIS AND SUBMISSION
CZ3IN1640 INT. HUM APPROVAL 14 09-Mar-15 24-Mar-15 168 INT. HUM APPROVAL
INT. HUM CONSTRUCTION
CON 164 16-Sep-15 02-Apr-16 68 02-Apr-16
CZ3IN1650 INT. HUM SURVEY & SETTING OUT 3 16-Sep-15 19-Sep-15 23 INT. HUM SURVEY & SETTING OUT
CZ3IN1660 INT. HUM CLEARING AND GRUBBING 4 20-Sep-15 23-Sep-15 23 INT. HUM CLEARING AND GRUBBIN
CZ3IN1670 INT. HUM STRUCTURAL EXACAVATION FOR FOUN 13 24-Sep-15 12-Oct-15 23 INT. HUM STRUCTURAL EXACAV
CZ3IN1680 INT. HUM PCC FOR FOUNDATION 10 03-Oct-15 14-Oct-15 23 INT. HUM PCC FOR FOUNDATIO
CZ3IN1690 INT. HUM CONCRETING FOR ABUTMENT (AB1, AB 15 05-Oct-15 22-Oct-15 23 INT. HUM CONCRETING FOR A
CZ3IN1700 INT. HUM CONCRETING FOR ABUTMENT (AB1, AB 24 24-Oct-15 19-Nov-15 35 INT. HUM CONCRETING FO
CZ3IN1710 INT. HUM CONCRETING FOR PIER FOUNDATION 9 18-Oct-15 27-Oct-15 23 INT. HUM CONCRETING FOR
CZ3IN1720 INT. HUM CONCRETING FOR PIERS 17 28-Oct-15 16-Nov-15 23 INT. HUM CONCRETING FO
CZ3IN1730 INT. HUM STAGING FOR BOX GIRDERS 15 17-Nov-15 06-Dec-15 23 INT. HUM STAGING FOR
CZ3IN1740 INT. HUM FIXING OF BEARING 5 07-Dec-15 12-Dec-15 23 INT. HUM FIXING OF BEA
CZ3IN1750 INT. HUM SOFFIT FORMWORK ALONG WITH WIN 12 05-Dec-15 17-Dec-15 23 INT. HUM SOFFIT FORM
CZ3IN1760 INT. HUM REINFORCEMENT FIXING FOR SOFFIT 12 19-Dec-15 02-Jan-16 23 INT. HUM REINFORC
CZ3IN1770 INT. HUM POST TENSIONING DUCT PROFILING 8 29-Dec-15 06-Jan-16 23 INT. HUM POST TENS
CZ3IN1780 INT. HUM CONCRETING OF SOFFIT 1 07-Jan-16 07-Jan-16 23 INT. HUM CONCRET
CZ3IN1790 INT. HUM REINFORCEMENT FIXING FOR WEB & D 4 09-Jan-16 12-Jan-16 23 INT. HUM REINFORC
CZ3IN1800 INT. HUM FORMWORK FIXING FOR WEB & DIAPH 9 13-Jan-16 23-Jan-16 23 INT. HUM FORMW
CZ3IN1810 INT. HUM CONCRETING FOR WEB & DIAPHARGM 1 24-Jan-16 24-Jan-16 23 INT. HUM CONCRE
CZ3IN1820 INT. HUM STAGING & FORMWORK FOR DECK SLA 13 25-Jan-16 08-Feb-16 23 INT. HUM STAGI
CZ3IN1830 INT. HUM REINFORCEMENT FIXING FOR DECK S 10 09-Feb-16 20-Feb-16 23 INT. HUM REIN
CZ3IN1840 INT. HUM CONCRETING FOR DECK SLAB 1 21-Feb-16 21-Feb-16 23 INT. HUM CON
CZ3IN1850 INT. HUM THREADING OF STRANDS 11 22-Feb-16 05-Mar-16 23 INT. HUM TH
CZ3IN1860 INT. HUM STRESSING & GROUTING 6 06-Mar-16 12-Mar-16 23 INT. HUM ST
CZ3IN1870 INT. HUM DRAINAGE PIPE FIXING 8 13-Mar-16 21-Mar-16 33 INT. HUM D
CZ3IN1880 INT. HUM APPROACH SLAB 10 13-Mar-16 23-Mar-16 23 INT. HUM A
CZ3IN1890 INT. HUM EXPANSION JOINT 12 17-Mar-16 30-Mar-16 23 INT. HUM
CZ3IN1900 INT. HUM REMOVAL OF STAGING 11 13-Mar-16 24-Mar-16 75 INT. HUM R
CZ3IN1910 INT. HUM DIRT WALL & CONCRETE BARRIER 21 09-Mar-16 02-Apr-16 23 INT. HUM
UNDER PASS AT 44+240
44+ 194 14-Jan-15 02-Sep-15 48 02-Sep-15, UNDER PASS AT 44+240
UNP. 44+240 GEOTECHNICAL
GEO INVESTIGATION 38 14-Jan-15 26-Feb-15 48 26-Feb-15, UNP. 44+240 GEOTECHNICAL INVESTIGATION
CZ3UN1230 UNP. 44+240 SOIL INVESTIGATION 20 14-Jan-15 05-Feb-15 48 UNP. 44+240 SOIL INVESTIGATION
CZ3UN1240 UNP. 44+240 ANALYSIS AND SUBMISSION 10 07-Feb-15 17-Feb-15 48 UNP. 44+240 ANALYSIS AND SUBMISSION
CZ3UN1250 UNP. 44+240 APPROVAL 8 18-Feb-15 26-Feb-15 48 UNP. 44+240 APPROVAL
UNDER PASS AT 44+240 CONSTRUCTION 156 28-Feb-15 02-Sep-15 48 02-Sep-15, UNDER PASS AT 44+240 CO
CZ3UN1000 UNP. 44+240 SURVEY & SETTING OUT 3 28-Feb-15 02-Mar-15 48 UNP. 44+240 SURVEY & SETTING OUT

Actual Work Critical Remaining Work Summary Page 48 of 57 TASK filter: All Activities

Remaining Work Milestone © Oracle Corporation


DUALIZATION OF MAHDAH - AL RAWDAH ROAD PROJECT Classic Schedule Layout 25-May-14 16:51

Activity ID Activity Name Original Start Finish Total Float Critical 2014 2015 2016
Duration
S Oct N D J F M Apr M J Jul A S Oct N D Jan F M Apr M J Jul A S Oct N D J F M Apr M J
CZ3UN1010 UNP. 44+240 CLEARING AND GRUBBING 5 03-Mar-15 08-Mar-15 48 UNP. 44+240 CLEARING AND GRUBBING
CZ3UN1020 UNP. 44+240 EXCAVATION FOR FOUNDATION 6 09-Mar-15 15-Mar-15 48 UNP. 44+240 EXCAVATION FOR FOUNDATION
CZ3UN1030 UNP. 44+240 PCC FOR FOUNDATION 5 12-Mar-15 17-Mar-15 48 UNP. 44+240 PCC FOR FOUNDATION
CZ3UN1040 UNP. 44+240 RCC FOR FOUNDATION 39 17-Mar-15 30-Apr-15 48 UNP. 44+240 RCC FOR FOUNDATION
CZ3UN1050 UNP. 44+240 CONCRETING FOR WALL 48 19-Apr-15 13-Jun-15 84 UNP. 44+240 CONCRETING FOR WALL
CZ3UN1060 UNP. 44+240 STAGING FOR DECK SLAB 15 21-May-15 07-Jun-15 48 UNP. 44+240 STAGING FOR DECK SLAB
CZ3UN1070 UNP. 44+240 FORMWORK & REINFORCEMENT W 25 03-Jun-15 01-Jul-15 68 UNP. 44+240 FORMWORK & REINFORCEMENT
CZ3UN1080 UNP. 44+240 CONCRETING FOR DECK SLAB 9 23-Jun-15 02-Jul-15 68 UNP. 44+240 CONCRETING FOR DECK SLAB
CZ3UN1090 UNP. 44+240 DESHUTTERING FOR DECK SLAB 6 04-Aug-15 10-Aug-15 68 UNP. 44+240 DESHUTTERING FOR DECK
CZ3UN1100 UNP. 44+240 PRECAST FOR MSER WALL PANELS 30 02-May-15 04-Jun-15 63 UNP. 44+240 PRECAST FOR MSER WALL PANELS
CZ3UN1110 UNP. 44+240 PRECAST FOR MSER WALL PANELS 30 06-Jun-15 09-Jul-15 63 UNP. 44+240 PRECAST FOR MSER WALL PAN
CZ3UN1120 UNP. 44+240 EXCAVATION FOR MSER WALL PART 4 23-May-15 26-May-15 48 UNP. 44+240 EXCAVATION FOR MSER WALL PART 1
CZ3UN1130 UNP. 44+240 EXCAVATION FOR MSER WALL PART 4 27-May-15 31-May-15 50 UNP. 44+240 EXCAVATION FOR MSER WALL PART
CZ3UN1140 UNP. 44+240 PCC FOR MSER WALL PART 1 4 26-May-15 30-May-15 48 UNP. 44+240 PCC FOR MSER WALL PART 1
CZ3UN1150 UNP. 44+240 PCC FOR MSER WALL PART 2 3 31-May-15 02-Jun-15 48 UNP. 44+240 PCC FOR MSER WALL PART 2
CZ3UN1160 UNP. 44+240 FOUNDATION FOR MSER WALL PAR 6 03-Jun-15 09-Jun-15 48 UNP. 44+240 FOUNDATION FOR MSER WALL PAR
CZ3UN1170 UNP. 44+240 FOUNDATION FOR MSER WALL PAR 5 10-Jun-15 15-Jun-15 84 UNP. 44+240 FOUNDATION FOR MSER WALL PA
CZ3UN1180 UNP. 44+240 FIXING OF MSER WALL PANELS PAR 21 09-Jun-15 02-Jul-15 48 UNP. 44+240 FIXING OF MSER WALL PANELS P
CZ3UN1190 UNP. 44+240 FIXING OF MSER WALL PANELS PAR 21 04-Jul-15 02-Aug-15 48 UNP. 44+240 FIXING OF MSER WALL PANE
CZ3UN1200 UNP. 44+240 APPROACH SLAB 20 16-Jul-15 13-Aug-15 65 UNP. 44+240 APPROACH SLAB
CZ3UN1210 UNP. 44+240 CONCRETE BARRIER 27 27-Jun-15 02-Aug-15 48 UNP. 44+240 CONCRETE BARRIER
CZ3UN1220 UNP. 44+240 MEDIAN WORKS 27 03-Aug-15 02-Sep-15 48 UNP. 44+240 MEDIAN WORKS
INCIDENTAL CONSTRUCTION
CONSTRU 399 10-Feb-15 02-Jun-16 11 0
CONSTRUCTION OF SLOPE PROTECTION AND STABILIZATION 393 10-Feb-15 26-May-16 6 26
WADI PROTECTION
PROTECTIO WITH RETAINING WALL 81 10-Feb-15 14-May-15 91 14-May-15, WADI PROTECTION WITH RETAINING WA
WADI 4 [MAYDAH]
[MAYDA PROTECTION CH. 42+000 TO 44+000 81 10-Feb-15 14-May-15 91 14-May-15, WADI 4 [MAYDAH] PROTECTION CH. 42+0
WADI 4A MAHDAH
MA TO RAWDAH 46 10-Feb-15 04-Apr-15 113 04-Apr-15, WADI 4A MAHDAH TO RAWDAH
CZ3FI1000 WADI 4A EXCAVATION FOR RETAINING WALL 8 10-Feb-15 18-Feb-15 91 WADI 4A EXCAVATION FOR RETAINING WALL
CZ3FI1010 WADI 4A BLINDING FOR RETAINING WALL 8 12-Feb-15 21-Feb-15 91 WADI 4A BLINDING FOR RETAINING WALL
CZ3FI1020 WADI 4A FOUNDATION FOR RETAINING WALL 25 14-Feb-15 14-Mar-15 91 WADI 4A FOUNDATION FOR RETAINING WALL
CZ3FI1030 WADI 4A RCC WALL FOR RETAINING WALL 35 23-Feb-15 04-Apr-15 91 WADI 4A RCC WALL FOR RETAINING WALL
CZ3FI1040 WADI 4A GABION METRESS 12 07-Mar-15 19-Mar-15 126 WADI 4A GABION METRESS
WADI 4B RAWDAH
RA TO MAHDAH 73 19-Feb-15 14-May-15 91 14-May-15, WADI 4B RAWDAH TO MAHDAH
CZ3FI1050 WADI 4B EXCAVATION FOR RETAINING WALL 8 19-Feb-15 28-Feb-15 154 WADI 4B EXCAVATION FOR RETAINING WALL
CZ3FI1060 WADI 4B BLINDING FOR RETAINING WALL 8 22-Feb-15 02-Mar-15 154 WADI 4B BLINDING FOR RETAINING WALL
CZ3FI1070 WADI 4B FOUNDATION FOR RETAINING WALL 25 15-Mar-15 12-Apr-15 119 WADI 4B FOUNDATION FOR RETAINING WALL
CZ3FI1080 WADI 4B RCC WALL FOR RETAINING WALL 35 05-Apr-15 14-May-15 91 WADI 4B RCC WALL FOR RETAINING WALL
CZ3FI1090 WADI 4B GABION METRESS 12 16-Apr-15 29-Apr-15 91 WADI 4B GABION METRESS
MORTARED STONE
STON RIP RAP PROTECTION WITH DYKE 225 17-Jun-15 19-Mar-16 6 19-Mar-16,
CZ3FI1100 MORTARED STONE RIP RAP CH. FROM KM 40+00 25 17-Jun-15 15-Jul-15 0 MORTARED STONE RIP RAP CH. FROM KM
CZ3FI1110 MORTARED STONE RIP RAP CH. FROM KM 42+00 25 16-Jul-15 19-Aug-15 0 MORTARED STONE RIP RAP CH. FROM
CZ3FI1120 MORTARED STONE RIP RAP CH. FROM KM 44+00 25 20-Aug-15 17-Sep-15 0 MORTARED STONE RIP RAP CH. FR
CZ3FI1130 MORTARED STONE RIP RAP CH. FROM KM 46+00 25 19-Sep-15 21-Oct-15 0 MORTARED STONE RIP RAP C
CZ3FI1140 MORTARED STONE RIP RAP CH. FROM KM 48+00 25 22-Oct-15 19-Nov-15 0 MORTARED STONE RIP RA
CZ3FI1150 MORTARED STONE RIP RAP CH. FROM KM 50+00 25 21-Nov-15 21-Dec-15 0 MORTARED STONE RI
CZ3FI1160 MORTARED STONE RIP RAP CH. FROM KM 52+00 25 22-Dec-15 20-Jan-16 0 MORTARED STONE
CZ3FI1170 MORTARED STONE RIP RAP CH. FROM KM 54+00 25 21-Jan-16 18-Feb-16 6 MORTARED ST
CZ3FI1180 DYKE CONSTRUCTION CH. FROM KM 54+000 TO 20 25-Jan-16 16-Feb-16 8 DYKE CONSTR
CZ3FI1190 MORTARED STONE RIP RAP CH. FROM KM 56+00 25 20-Feb-16 19-Mar-16 6 MORTARED
CZ3FI1200 DYKE CONSTRUCTION CH. FROM KM 56+000 TO 25 17-Feb-16 16-Mar-16 8 DYKE CONS
LOOSE STONE R
RIPRAP PROTECTION 216 16-Jul-15 06-Apr-16 6 06-Apr-1

Actual Work Critical Remaining Work Summary Page 49 of 57 TASK filter: All Activities

Remaining Work Milestone © Oracle Corporation


DUALIZATION OF MAHDAH - AL RAWDAH ROAD PROJECT Classic Schedule Layout 25-May-14 16:51

Activity ID Activity Name Original Start Finish Total Float Critical 2014 2015 2016
Duration
S Oct N D J F M Apr M J Jul A S Oct N D Jan F M Apr M J Jul A S Oct N D J F M Apr M J
CZ3FI1210 LOOSE STONE RIP RAP CH. FROM KM 40+000 TO 16 16-Jul-15 09-Aug-15 80 LOOSE STONE RIP RAP CH. FROM KM 4
CZ3FI1220 LOOSE STONE RIP RAP CH. FROM KM 42+000 TO 16 20-Aug-15 07-Sep-15 76 LOOSE STONE RIP RAP CH. FROM K
CZ3FI1230 LOOSE STONE RIP RAP CH. FROM KM 44+000 TO 16 19-Sep-15 10-Oct-15 51 LOOSE STONE RIP RAP CH. FRO
CZ3FI1240 LOOSE STONE RIP RAP CH. FROM KM 46+000 TO 16 22-Oct-15 09-Nov-15 26 LOOSE STONE RIP RAP CH.
CZ3FI1250 LOOSE STONE RIP RAP CH. FROM KM 48+000 TO 16 21-Nov-15 10-Dec-15 1 LOOSE STONE RIP RAP
CZ3FI1260 LOOSE STONE RIP RAP CH. FROM KM 50+000 TO 16 22-Dec-15 10-Jan-16 77 LOOSE STONE RIP R
CZ3FI1270 LOOSE STONE RIP RAP CH. FROM KM 52+000 TO 16 21-Jan-16 08-Feb-16 52 LOOSE STONE R
CZ3FI1280 LOOSE STONE RIP RAP CH. FROM KM 54+000 TO 16 20-Feb-16 08-Mar-16 27 LOOSE STO
CZ3FI1290 LOOSE STONE RIP RAP CH. FROM KM 56+000 TO 16 20-Mar-16 06-Apr-16 6 LOOSE S
REINFORCED CONCRETE
CO FOR SLOPE PROTECTION 220 10-Aug-15 30-Apr-16 29 30-Ap
CZ3FI1300 REINF. CONC. FOR SLOPE PROTECTION CH. FRO 21 10-Aug-15 02-Sep-15 91 REINF. CONC. FOR SLOPE PROTECT
CZ3FI1310 REINF. CONC. FOR SLOPE PROTECTION CH. FRO 20 08-Sep-15 04-Oct-15 83 REINF. CONC. FOR SLOPE PROT
CZ3FI1320 REINF. CONC. FOR SLOPE PROTECTION CH. FRO 21 11-Oct-15 04-Nov-15 89 REINF. CONC. FOR SLOPE P
CZ3FI1330 REINF. CONC. FOR SLOPE PROTECTION CH. FRO 20 10-Nov-15 05-Dec-15 81 REINF. CONC. FOR SLOP
CZ3FI1340 REINF. CONC. FOR SLOPE PROTECTION CH. FRO 21 12-Dec-15 05-Jan-16 87 REINF. CONC. FOR S
CZ3FI1350 REINF. CONC. FOR SLOPE PROTECTION CH. FRO 20 11-Jan-16 02-Feb-16 79 REINF. CONC. FO
CZ3FI1360 REINF. CONC. FOR SLOPE PROTECTION CH. FRO 21 09-Feb-16 03-Mar-16 78 REINF. CONC
CZ3FI1370 REINF. CONC. FOR SLOPE PROTECTION CH. FRO 21 09-Mar-16 02-Apr-16 53 REINF. C
CZ3FI1380 REINF. CONC. FOR SLOPE PROTECTION CH. FRO 20 07-Apr-16 30-Apr-16 29 REIN
ROCK BOLTING & ANCHORING, SHORTSCRETE 144 10-Aug-15 01-Feb-16 80 01-Feb-16, ROCK
CZ3FI1390 ROCK BOLTING & ANCHORING,SHORTCRETE CH 16 10-Aug-15 27-Aug-15 80 ROCK BOLTING & ANCHORING,SHOR
CZ3FI1400 ROCK BOLTING & ANCHORING,SHORTCRETE CH 16 29-Aug-15 15-Sep-15 80 ROCK BOLTING & ANCHORING,SHO
CZ3FI1410 ROCK BOLTING & ANCHORING,SHORTCRETE CH 16 16-Sep-15 07-Oct-15 80 ROCK BOLTING & ANCHORING,S
CZ3FI1420 ROCK BOLTING & ANCHORING,SHORTCRETE CH 16 08-Oct-15 27-Oct-15 80 ROCK BOLTING & ANCHORING
CZ3FI1430 ROCK BOLTING & ANCHORING,SHORTCRETE CH 16 28-Oct-15 15-Nov-15 80 ROCK BOLTING & ANCHOR
CZ3FI1440 ROCK BOLTING & ANCHORING,SHORTCRETE CH 16 16-Nov-15 06-Dec-15 80 ROCK BOLTING & ANCHO
CZ3FI1450 ROCK BOLTING & ANCHORING,SHORTCRETE CH 16 07-Dec-15 26-Dec-15 80 ROCK BOLTING & ANC
CZ3FI1460 ROCK BOLTING & ANCHORING,SHORTCRETE CH 16 27-Dec-15 13-Jan-16 80 ROCK BOLTING & A
CZ3FI1470 ROCK BOLTING & ANCHORING,SHORTCRETE CH 16 14-Jan-16 01-Feb-16 80 ROCK BOLTING &
DITCH LINING / C
CHUTES 222 10-Aug-15 02-May-16 6 02-M
CZ3FI1480 DITCH LINING/CHUTES CH. FROM KM 40+000 TO 22 10-Aug-15 03-Sep-15 87 DITCH LINING/CHUTES CH. FROM KM
CZ3FI1490 DITCH LINING/CHUTES CH. FROM KM 42+000 TO 22 08-Sep-15 06-Oct-15 76 DITCH LINING/CHUTES CH. FRO
CZ3FI1500 DITCH LINING/CHUTES CH. FROM KM 44+000 TO 22 11-Oct-15 05-Nov-15 51 DITCH LINING/CHUTES CH. F
CZ3FI1510 DITCH LINING/CHUTES CH. FROM KM 46+000 TO 22 10-Nov-15 07-Dec-15 26 DITCH LINING/CHUTES C
CZ3FI1520 DITCH LINING/CHUTES CH. FROM KM 48+000 TO 22 12-Dec-15 06-Jan-16 1 DITCH LINING/CHUT
CZ3FI1530 DITCH LINING/CHUTES CH. FROM KM 50+000 TO 22 11-Jan-16 04-Feb-16 77 DITCH LINING/CH
CZ3FI1540 DITCH LINING/CHUTES CH. FROM KM 52+000 TO 22 09-Feb-16 05-Mar-16 52 DITCH LININ
CZ3FI1550 DITCH LINING/CHUTES CH. FROM KM 54+000 TO 22 09-Mar-16 03-Apr-16 27 DITCH LI
CZ3FI1560 DITCH LINING/CHUTES CH. FROM KM 56+000 TO 22 07-Apr-16 02-May-16 6 DITC
GABION WALLS 221 05-Sep-15 26-May-16 6 26
CZ3FI1570 GABION WALLS CH. FROM KM 40+000 TO 42+000 25 05-Sep-15 06-Oct-15 87 GABION WALLS CH. FROM KM 40
CZ3FI1580 GABION WALLS CH. FROM KM 42+000 TO 44+000 25 07-Oct-15 05-Nov-15 76 GABION WALLS CH. FROM K
CZ3FI1590 GABION WALLS CH. FROM KM 44+000 TO 46+000 25 07-Nov-15 07-Dec-15 51 GABION WALLS CH. FRO
CZ3FI1600 GABION WALLS CH. FROM KM 46+000 TO 48+000 25 08-Dec-15 06-Jan-16 26 GABION WALLS CH.
CZ3FI1610 GABION WALLS CH. FROM KM 48+000 TO 50+000 25 07-Jan-16 04-Feb-16 1 GABION WALLS
CZ3FI1620 GABION WALLS CH. FROM KM 50+000 TO 52+000 25 06-Feb-16 05-Mar-16 77 GABION WAL
CZ3FI1630 GABION WALLS CH. FROM KM 52+000 TO 54+000 25 06-Mar-16 03-Apr-16 52 GABION
CZ3FI1640 GABION WALLS CH. FROM KM 54+000 TO 56+000 25 04-Apr-16 02-May-16 27 GABI
CZ3FI1650 GABION WALLS CH. FROM KM 56+000 TO 58+594. 21 03-May-16 26-May-16 6 G
CONSTRUCTION OF SIDEWALKS,PAVED AREAS AND CURBS 130 04-Jan-16 02-Jun-16 0 0
CZ3FI1660 SIDE WALKS, PAVED AREAS & CURBS CH. FROM K 15 04-Jan-16 20-Jan-16 0 SIDE WALKS, PAVE

Actual Work Critical Remaining Work Summary Page 50 of 57 TASK filter: All Activities

Remaining Work Milestone © Oracle Corporation


DUALIZATION OF MAHDAH - AL RAWDAH ROAD PROJECT Classic Schedule Layout 25-May-14 16:51

Activity ID Activity Name Original Start Finish Total Float Critical 2014 2015 2016
Duration
S Oct N D J F M Apr M J Jul A S Oct N D Jan F M Apr M J Jul A S Oct N D J F M Apr M J
CZ3FI1670 SIDE WALKS, PAVED AREAS & CURBS CH. FROM K 14 21-Jan-16 06-Feb-16 0 SIDE WALKS, PAV
CZ3FI1680 SIDE WALKS, PAVED AREAS & CURBS CH. FROM K 14 07-Feb-16 22-Feb-16 0 SIDE WALKS, P
CZ3FI1690 SIDE WALKS, PAVED AREAS & CURBS CH. FROM K 14 23-Feb-16 09-Mar-16 0 SIDE WALKS
CZ3FI1700 SIDE WALKS, PAVED AREAS & CURBS CH. FROM K 14 10-Mar-16 26-Mar-16 0 SIDE WAL
CZ3FI1710 SIDE WALKS, PAVED AREAS & CURBS CH. FROM K 14 27-Mar-16 11-Apr-16 0 SIDE WA
CZ3FI1720 SIDE WALKS, PAVED AREAS & CURBS CH. FROM K 14 12-Apr-16 27-Apr-16 0 SIDE W
CZ3FI1730 SIDE WALKS, PAVED AREAS & CURBS CH. FROM K 14 28-Apr-16 14-May-16 0 SID
CZ3FI1740 SIDE WALKS, PAVED AREAS & CURBS CH. FROM K 17 15-May-16 02-Jun-16 0 S
SAFETY BARRIERS AND FENCING WORKS. 219 14-Sep-15 02-Jun-16 11 0
ROAD SIDE BARRIERS
BARR - GUARDRAILS 143 10-Dec-15 25-May-16 11 25
CZ3FI1750 GUARDRAILS FROM KM 40+000 TO 42+000 16 10-Dec-15 29-Dec-15 3 GUARDRAILS FROM K
CZ3FI1760 GUARDRAILS FROM KM 42+000 TO 44+000 16 30-Dec-15 17-Jan-16 3 GUARDRAILS FROM
CZ3FI1770 GUARDRAILS FROM KM 44+000 TO 46+000 16 18-Jan-16 04-Feb-16 11 GUARDRAILS FR
CZ3FI1780 GUARDRAILS FROM KM 46+000 TO 48+000 16 06-Feb-16 23-Feb-16 11 GUARDRAILS
CZ3FI1790 GUARDRAILS FROM KM 48+000 TO 50+000 15 24-Feb-16 12-Mar-16 11 GUARDRAIL
CZ3FI1800 GUARDRAILS FROM KM 50+000 TO 52+000 15 13-Mar-16 29-Mar-16 11 GUARDRA
CZ3FI1810 GUARDRAILS FROM KM 52+000 TO 54+000 15 30-Mar-16 16-Apr-16 11 GUARD
CZ3FI1820 GUARDRAILS FROM KM 54+000 TO 56+000 15 17-Apr-16 03-May-16 11 GUA
CZ3FI1830 GUARDRAILS FROM KM 56+000 TO 58+594.604 19 04-May-16 25-May-16 11 G
PRECAST FOR CONCRETE
C BARRIERS 200 14-Sep-15 11-May-16 30 11-M
CZ3FI1840 PRECAST FOR CONCRETE BARRIERS FROM KM 22 14-Sep-15 12-Oct-15 30 PRECAST FOR CONCRETE BAR
CZ3FI1850 PRECAST FOR CONCRETE BARRIERS FROM KM 22 14-Oct-15 08-Nov-15 30 PRECAST FOR CONCRETE B
CZ3FI1860 PRECAST FOR CONCRETE BARRIERS FROM KM 22 09-Nov-15 06-Dec-15 30 PRECAST FOR CONCRE
CZ3FI1870 PRECAST FOR CONCRETE BARRIERS FROM KM 22 07-Dec-15 02-Jan-16 30 PRECAST FOR CONC
CZ3FI1880 PRECAST FOR CONCRETE BARRIERS FROM KM 22 03-Jan-16 27-Jan-16 30 PRECAST FOR CO
CZ3FI1890 PRECAST FOR CONCRETE BARRIERS FROM KM 22 28-Jan-16 22-Feb-16 30 PRECAST FOR
CZ3FI1900 PRECAST FOR CONCRETE BARRIERS FROM KM 22 23-Feb-16 19-Mar-16 30 PRECAST F
CZ3FI1910 PRECAST FOR CONCRETE BARRIERS FROM KM 22 20-Mar-16 13-Apr-16 30 PRECAS
CZ3FI1920 PRECAST FOR CONCRETE BARRIERS FROM KM 24 14-Apr-16 11-May-16 30 PRE
CONCRETE BARRIERS
BARR 144 17-Dec-15 02-Jun-16 11 0
CZ3FI1930 CONCRETE BARRIERS FROM KM 40+000 TO 42+0 17 17-Dec-15 06-Jan-16 19 CONCRETE BARRIER
CZ3FI1940 CONCRETE BARRIERS FROM KM 42+000 TO 44+0 17 06-Jan-16 25-Jan-16 3 CONCRETE BARR
CZ3FI1950 CONCRETE BARRIERS FROM KM 44+000 TO 46+0 17 25-Jan-16 13-Feb-16 29 CONCRETE BAR
CZ3FI1960 CONCRETE BARRIERS FROM KM 46+000 TO 48+0 17 13-Feb-16 02-Mar-16 90 CONCRETE B
CZ3FI1970 CONCRETE BARRIERS FROM KM 48+000 TO 50+0 17 01-Mar-16 20-Mar-16 75 CONCRET
CZ3FI1980 CONCRETE BARRIERS FROM KM 50+000 TO 52+0 17 19-Mar-16 06-Apr-16 60 CONCRE
CZ3FI1990 CONCRETE BARRIERS FROM KM 52+000 TO 54+0 17 05-Apr-16 24-Apr-16 45 CONC
CZ3FI2000 CONCRETE BARRIERS FROM KM 54+000 TO 56+0 17 23-Apr-16 11-May-16 30 CON
CZ3FI2010 CONCRETE BARRIERS FROM KM 56+000 TO 58+5 17 15-May-16 02-Jun-16 11 C
HIGHWAY SIGN,ROA
SIGN,ROAD STUDS AND ROAD MARKING WORKS 108 30-Jan-16 02-Jun-16 11 0
CZ3FI2020 HIGHWAY SIGN, ROAD STUDS & MARKINGS CH. F 11 30-Jan-16 10-Feb-16 20 HIGHWAY SIGN
CZ3FI2030 HIGHWAY SIGN, ROAD STUDS & MARKINGS CH. F 11 11-Feb-16 23-Feb-16 20 HIGHWAY SIG
CZ3FI2040 HIGHWAY SIGN, ROAD STUDS & MARKINGS CH. F 11 24-Feb-16 07-Mar-16 20 HIGHWAY SI
CZ3FI2050 HIGHWAY SIGN, ROAD STUDS & MARKINGS CH. F 11 08-Mar-16 20-Mar-16 20 HIGHWAY
CZ3FI2060 HIGHWAY SIGN, ROAD STUDS & MARKINGS CH. F 11 21-Mar-16 02-Apr-16 20 HIGHWAY
CZ3FI2070 HIGHWAY SIGN, ROAD STUDS & MARKINGS CH. F 11 03-Apr-16 14-Apr-16 20 HIGHW
CZ3FI2080 HIGHWAY SIGN, ROAD STUDS & MARKINGS CH. F 11 16-Apr-16 27-Apr-16 20 HIGHW
CZ3FI2090 HIGHWAY SIGN, ROAD STUDS & MARKINGS CH. F 11 28-Apr-16 10-May-16 20 HIG
CZ3FI2100 HIGHWAY SIGN, ROAD STUDS & MARKINGS CH. F 11 22-May-16 02-Jun-16 11 H
UTILITIES - SERVICE PROTECTION WORKS 292 13-Apr-15 31-Mar-16 65 31-Mar-16
SERVICE DUCTS/ SPLIT PIPES 283 13-Apr-15 21-Mar-16 65 21-Mar-16,

Actual Work Critical Remaining Work Summary Page 51 of 57 TASK filter: All Activities

Remaining Work Milestone © Oracle Corporation


DUALIZATION OF MAHDAH - AL RAWDAH ROAD PROJECT Classic Schedule Layout 25-May-14 16:51

Activity ID Activity Name Original Start Finish Total Float Critical 2014 2015 2016
Duration
S Oct N D J F M Apr M J Jul A S Oct N D Jan F M Apr M J Jul A S Oct N D J F M Apr M J
CZ3UT1050 SERVICE DUCTS/ SPLIT PIPES CH. FROM KM 40+0 32 13-Apr-15 19-May-15 38 SERVICE DUCTS/ SPLIT PIPES CH. FROM KM 40+00
CZ3UT1060 SERVICE DUCTS/ SPLIT PIPES CH. FROM KM 42+0 31 20-May-15 24-Jun-15 38 SERVICE DUCTS/ SPLIT PIPES CH. FROM KM 4
CZ3UT1070 SERVICE DUCTS/ SPLIT PIPES CH. FROM KM 44+0 31 25-Jun-15 05-Aug-15 38 SERVICE DUCTS/ SPLIT PIPES CH. FROM
CZ3UT1080 SERVICE DUCTS/ SPLIT PIPES CH. FROM KM 46+0 31 06-Aug-15 10-Sep-15 38 SERVICE DUCTS/ SPLIT PIPES CH. F
CZ3UT1090 SERVICE DUCTS/ SPLIT PIPES CH. FROM KM 48+0 31 12-Sep-15 21-Oct-15 65 SERVICE DUCTS/ SPLIT PIPES
CZ3UT1100 SERVICE DUCTS/ SPLIT PIPES CH. FROM KM 50+0 31 22-Oct-15 26-Nov-15 65 SERVICE DUCTS/ SPLIT P
CZ3UT1110 SERVICE DUCTS/ SPLIT PIPES CH. FROM KM 52+0 31 30-Nov-15 05-Jan-16 65 SERVICE DUCTS/ SP
CZ3UT1120 SERVICE DUCTS/ SPLIT PIPES CH. FROM KM 54+0 31 06-Jan-16 10-Feb-16 65 SERVICE DUCTS
CZ3UT1130 SERVICE DUCTS/ SPLIT PIPES CH. FROM KM 56+0 34 11-Feb-16 21-Mar-16 65 SERVICE D
MEDIAN INLETS 269 05-May-15 27-Mar-16 65 27-Mar-16
CZ3UT1140 MEDIAN INLETS CH. FROM KM 40+000 TO 42+000 18 05-May-15 25-May-15 88 MEDIAN INLETS CH. FROM KM 40+000 TO 42+000
CZ3UT1150 MEDIAN INLETS CH. FROM KM 42+000 TO 44+000 18 10-Jun-15 30-Jun-15 57 MEDIAN INLETS CH. FROM KM 42+000 TO 44+
CZ3UT1160 MEDIAN INLETS CH. FROM KM 44+000 TO 46+000 18 16-Jul-15 11-Aug-15 69 MEDIAN INLETS CH. FROM KM 44+000 T
CZ3UT1170 MEDIAN INLETS CH. FROM KM 46+000 TO 48+000 18 27-Aug-15 16-Sep-15 38 MEDIAN INLETS CH. FROM KM 46+0
CZ3UT1180 MEDIAN INLETS CH. FROM KM 48+000 TO 50+000 18 06-Oct-15 27-Oct-15 79 MEDIAN INLETS CH. FROM KM
CZ3UT1190 MEDIAN INLETS CH. FROM KM 50+000 TO 52+000 18 12-Nov-15 05-Dec-15 69 MEDIAN INLETS CH. FRO
CZ3UT1200 MEDIAN INLETS CH. FROM KM 52+000 TO 54+000 18 21-Dec-15 11-Jan-16 80 MEDIAN INLETS CH.
CZ3UT1210 MEDIAN INLETS CH. FROM KM 54+000 TO 56+000 18 27-Jan-16 16-Feb-16 99 MEDIAN INLETS
CZ3UT1220 MEDIAN INLETS CH. FROM KM 56+000 TO 58+594 18 07-Mar-16 27-Mar-16 65 MEDIAN IN
CONCRETE IN MEDIAN
ME AREA 267 12-May-15 31-Mar-16 65 31-Mar-16
CZ3UT1230 CONCRETE IN MEDIAN AREA CH. FROM KM 40+00 16 12-May-15 30-May-15 88 CONCRETE IN MEDIAN AREA CH. FROM KM 40+00
CZ3UT1240 CONCRETE IN MEDIAN AREA CH. FROM KM 42+00 16 17-Jun-15 05-Jul-15 57 CONCRETE IN MEDIAN AREA CH. FROM KM 4
CZ3UT1250 CONCRETE IN MEDIAN AREA CH. FROM KM 44+00 16 29-Jul-15 16-Aug-15 69 CONCRETE IN MEDIAN AREA CH. FROM
CZ3UT1260 CONCRETE IN MEDIAN AREA CH. FROM KM 46+00 16 03-Sep-15 21-Sep-15 38 CONCRETE IN MEDIAN AREA CH. F
CZ3UT1270 CONCRETE IN MEDIAN AREA CH. FROM KM 48+00 16 14-Oct-15 01-Nov-15 79 CONCRETE IN MEDIAN AREA
CZ3UT1280 CONCRETE IN MEDIAN AREA CH. FROM KM 50+00 16 19-Nov-15 09-Dec-15 69 CONCRETE IN MEDIAN A
CZ3UT1290 CONCRETE IN MEDIAN AREA CH. FROM KM 52+00 16 29-Dec-15 16-Jan-16 80 CONCRETE IN MED
CZ3UT1300 CONCRETE IN MEDIAN AREA CH. FROM KM 54+00 16 03-Feb-16 21-Feb-16 99 CONCRETE IN
CZ3UT1310 CONCRETE IN MEDIAN AREA CH. FROM KM 56+00 16 14-Mar-16 31-Mar-16 65 CONCRE
ROAD LIGHTING AND ELECTRICAL INSTALLATIONS 267 09-Jul-15 29-May-16 4 2
CIVIL WORKS FOR E
ELECTRICAL INSTALLATION 189 09-Jul-15 28-Feb-16 64 28-Feb-16, CIV
CZ3EL1000 CIVIL WORKS FOR ELECTRICAL INSTALLATION C 21 09-Jul-15 08-Aug-15 33 CIVIL WORKS FOR ELECTRICAL INSTALL
CZ3EL1010 CIVIL WORKS FOR ELECTRICAL INSTALLATION C 21 09-Aug-15 01-Sep-15 34 CIVIL WORKS FOR ELECTRICAL INST
CZ3EL1020 CIVIL WORKS FOR ELECTRICAL INSTALLATION C 21 02-Sep-15 29-Sep-15 34 CIVIL WORKS FOR ELECTRICAL IN
CZ3EL1030 CIVIL WORKS FOR ELECTRICAL INSTALLATION C 21 30-Sep-15 25-Oct-15 64 CIVIL WORKS FOR ELECTRICA
CZ3EL1040 CIVIL WORKS FOR ELECTRICAL INSTALLATION C 21 26-Oct-15 18-Nov-15 64 CIVIL WORKS FOR ELECTR
CZ3EL1050 CIVIL WORKS FOR ELECTRICAL INSTALLATION C 21 19-Nov-15 15-Dec-15 64 CIVIL WORKS FOR ELE
CZ3EL1060 CIVIL WORKS FOR ELECTRICAL INSTALLATION C 21 16-Dec-15 10-Jan-16 64 CIVIL WORKS FOR E
CZ3EL1070 CIVIL WORKS FOR ELECTRICAL INSTALLATION C 21 11-Jan-16 03-Feb-16 64 CIVIL WORKS FO
CZ3EL1080 CIVIL WORKS FOR ELECTRICAL INSTALLATION C 21 04-Feb-16 28-Feb-16 64 CIVIL WORKS
SUB STATIONS & FE
FEEDER PILLARS 163 26-Jul-15 08-Feb-16 81 08-Feb-16, SUB S
CZ3EL1090 SUB STATION & FEEDER PILLARS CH. FROM KM 4 18 26-Jul-15 15-Aug-15 67 SUB STATION & FEEDER PILLARS CH. F
CZ3EL1100 SUB STATION & FEEDER PILLARS CH. FROM KM 4 18 16-Aug-15 05-Sep-15 67 SUB STATION & FEEDER PILLARS CH
CZ3EL1110 SUB STATION & FEEDER PILLARS CH. FROM KM 4 18 06-Sep-15 29-Sep-15 67 SUB STATION & FEEDER PILLARS
CZ3EL1120 SUB STATION & FEEDER PILLARS CH. FROM KM 4 18 30-Sep-15 21-Oct-15 67 SUB STATION & FEEDER PILLA
CZ3EL1130 SUB STATION & FEEDER PILLARS CH. FROM KM 4 18 22-Oct-15 11-Nov-15 70 SUB STATION & FEEDER PIL
CZ3EL1140 SUB STATION & FEEDER PILLARS CH. FROM KM 5 18 12-Nov-15 05-Dec-15 73 SUB STATION & FEEDER
CZ3EL1150 SUB STATION & FEEDER PILLARS CH. FROM KM 5 18 06-Dec-15 27-Dec-15 76 SUB STATION & FEED
CZ3EL1160 SUB STATION & FEEDER PILLARS CH. FROM KM 5 18 28-Dec-15 17-Jan-16 79 SUB STATION & FEE
CZ3EL1170 SUB STATION & FEEDER PILLARS CH. FROM KM 5 19 18-Jan-16 08-Feb-16 81 SUB STATION &
HIGH TENSION OVE
OVERHEAD ELECTRICAL LINE 121 27-Aug-15 23-Jan-16 95 23-Jan-16, HIGH TE

Actual Work Critical Remaining Work Summary Page 52 of 57 TASK filter: All Activities

Remaining Work Milestone © Oracle Corporation


DUALIZATION OF MAHDAH - AL RAWDAH ROAD PROJECT Classic Schedule Layout 25-May-14 16:51

Activity ID Activity Name Original Start Finish Total Float Critical 2014 2015 2016
Duration
S Oct N D J F M Apr M J Jul A S Oct N D Jan F M Apr M J Jul A S Oct N D J F M Apr M J
CZ3EL1180 HIGH TENSION OVERHEAD ELECTRICAL LINE CH 13 27-Aug-15 10-Sep-15 4 HIGH TENSION OVERHEAD ELECTR
CZ3EL1190 HIGH TENSION OVERHEAD ELECTRICAL LINE CH 13 12-Sep-15 29-Sep-15 17 HIGH TENSION OVERHEAD ELEC
CZ3EL1200 HIGH TENSION OVERHEAD ELECTRICAL LINE CH 13 30-Sep-15 15-Oct-15 21 HIGH TENSION OVERHEAD ELE
CZ3EL1210 HIGH TENSION OVERHEAD ELECTRICAL LINE CH 13 17-Oct-15 31-Oct-15 67 HIGH TENSION OVERHEAD E
CZ3EL1220 HIGH TENSION OVERHEAD ELECTRICAL LINE CH 13 01-Nov-15 15-Nov-15 67 HIGH TENSION OVERHEAD
CZ3EL1230 HIGH TENSION OVERHEAD ELECTRICAL LINE CH 13 16-Nov-15 02-Dec-15 75 HIGH TENSION OVERHEA
CZ3EL1240 HIGH TENSION OVERHEAD ELECTRICAL LINE CH 13 03-Dec-15 17-Dec-15 83 HIGH TENSION OVERH
CZ3EL1250 HIGH TENSION OVERHEAD ELECTRICAL LINE CH 13 19-Dec-15 03-Jan-16 91 HIGH TENSION OVER
CZ3EL1260 HIGH TENSION OVERHEAD ELECTRICAL LINE CH 17 04-Jan-16 23-Jan-16 95 HIGH TENSION OV
CABLING WORKS 153 02-Sep-15 06-Mar-16 58 06-Mar-16, CA
CZ3EL1270 CABLING WORKS CH. FROM KM 40+000 TO 42+00 17 02-Sep-15 21-Sep-15 4 CABLING WORKS CH. FROM KM 40
CZ3EL1280 CABLING WORKS CH. FROM KM 42+000 TO 44+00 17 22-Sep-15 15-Oct-15 4 CABLING WORKS CH. FROM KM
CZ3EL1290 CABLING WORKS CH. FROM KM 44+000 TO 46+00 17 17-Oct-15 04-Nov-15 4 CABLING WORKS CH. FROM
CZ3EL1300 CABLING WORKS CH. FROM KM 46+000 TO 48+00 17 05-Nov-15 24-Nov-15 50 CABLING WORKS CH. FRO
CZ3EL1310 CABLING WORKS CH. FROM KM 48+000 TO 50+00 17 25-Nov-15 16-Dec-15 51 CABLING WORKS CH. F
CZ3EL1320 CABLING WORKS CH. FROM KM 50+000 TO 52+00 17 17-Dec-15 06-Jan-16 52 CABLING WORKS CH
CZ3EL1330 CABLING WORKS CH. FROM KM 52+000 TO 54+00 17 07-Jan-16 26-Jan-16 53 CABLING WORKS
CZ3EL1340 CABLING WORKS CH. FROM KM 54+000 TO 56+00 17 27-Jan-16 15-Feb-16 54 CABLING WOR
CZ3EL1350 CABLING WORKS CH. FROM KM 56+000 TO 58+59 17 16-Feb-16 06-Mar-16 58 CABLING WO
ROAD LIGHTING MASTS,
MA COLUMNS AND LUMINAIRES 168 22-Oct-15 08-May-16 4 08-M
CZ3EL1360 ROAD LIGHTING MASTS, COLUMNS & LUMINARIE 19 22-Oct-15 12-Nov-15 4 ROAD LIGHTING MASTS, CO
CZ3EL1370 ROAD LIGHTING MASTS, COLUMNS & LUMINARIE 19 14-Nov-15 07-Dec-15 4 ROAD LIGHTING MASTS
CZ3EL1380 ROAD LIGHTING MASTS, COLUMNS & LUMINARIE 19 08-Dec-15 30-Dec-15 4 ROAD LIGHTING MAS
CZ3EL1390 ROAD LIGHTING MASTS, COLUMNS & LUMINARIE 18 31-Dec-15 20-Jan-16 4 ROAD LIGHTING M
CZ3EL1400 ROAD LIGHTING MASTS, COLUMNS & LUMINARIE 18 21-Jan-16 10-Feb-16 4 ROAD LIGHTING
CZ3EL1410 ROAD LIGHTING MASTS, COLUMNS & LUMINARIE 18 11-Feb-16 02-Mar-16 4 ROAD LIGHT
CZ3EL1420 ROAD LIGHTING MASTS, COLUMNS & LUMINARIE 18 03-Mar-16 23-Mar-16 4 ROAD LIG
CZ3EL1430 ROAD LIGHTING MASTS, COLUMNS & LUMINARIE 18 24-Mar-16 13-Apr-16 4 ROAD L
CZ3EL1440 ROAD LIGHTING MASTS, COLUMNS & LUMINARIE 21 14-Apr-16 08-May-16 4 ROA
LIGHTING - TESTING AND COMMISSIONING 167 14-Nov-15 29-May-16 4 2
CZ3EL1450 LIGHTING - TESTING & COMMISSIONING CH. FRO 18 14-Nov-15 06-Dec-15 153 LIGHTING - TESTING & C
CZ3EL1460 LIGHTING - TESTING & COMMISSIONING CH. FRO 18 08-Dec-15 29-Dec-15 134 LIGHTING - TESTING
CZ3EL1470 LIGHTING - TESTING & COMMISSIONING CH. FRO 18 31-Dec-15 20-Jan-16 115 LIGHTING - TESTIN
CZ3EL1480 LIGHTING - TESTING & COMMISSIONING CH. FRO 18 21-Jan-16 10-Feb-16 97 LIGHTING - TES
CZ3EL1490 LIGHTING - TESTING & COMMISSIONING CH. FRO 18 11-Feb-16 02-Mar-16 79 LIGHTING - T
CZ3EL1500 LIGHTING - TESTING & COMMISSIONING CH. FRO 18 03-Mar-16 23-Mar-16 61 LIGHTING
CZ3EL1510 LIGHTING - TESTING & COMMISSIONING CH. FRO 18 24-Mar-16 13-Apr-16 43 LIGHTIN
CZ3EL1520 LIGHTING - TESTING & COMMISSIONING CH. FRO 18 14-Apr-16 04-May-16 25 LIGH
CZ3EL1530 LIGHTING - TESTING & COMMISSIONING CH. FRO 18 09-May-16 29-May-16 4 L
HANDING OVER AND SNAG
S ATTENDING 105 20-Feb-16 20-Jun-16 0
CZ1CO1010 PART 1 (FROM KM 0+000 to KM 20+000 ) 15 20-Feb-16 07-Mar-16 65 PART 1 (FRO
CZ2CO1010 PART 2 (FROM KM 20+000 to KM 40+000 ) 15 31-May-16 16-Jun-16 3
CZ3CO1010 PART 3 (FROM KM 40+000 to KM 58+594.604) 15 04-Jun-16 20-Jun-16 0
Activity ID Activity Name Start Finish

WATER TANKER - 10000 G


WATE 10-Feb-14 16-Apr-16
CZ1EW EMBANKMENT FILLING CH. F 10-Feb-14 16-Mar-14
CZ1EW EMBANKMENT FILLING CH. F 17-Mar-14 20-Apr-14
CZ1EW EMBANKMENT FILLING CH. F 21-Apr-14 25-May-14
CZ1EW EMBANKMENT FILLING CH. F 26-May-14 30-Jun-14
CZ1EW EMBANKMENT FILLING CH. F 01-Jul-14 09-Aug-14

Actual Work Critical Remaining Work Summary Page 53 of 57 TASK filter: All Activities

Remaining Work Milestone © Oracle Corporation


DUALIZATION OF MAHDAH - AL RAWDAH ROAD PROJECT Classic Schedule Layout 25-May-14 16:51

Activity ID Activity Name Start Finish

CZ1EW EMBANKMENT FILLING CH. F 10-Aug-14 13-Sep-14


CZ1EW EMBANKMENT FILLING CH. F 14-Sep-14 21-Oct-14
CZ1EW EMBANKMENT FILLING CH. F 07-Dec-14 11-Jan-15
CZ1EW EMBANKMENT FILLING CH. F 12-Jan-15 15-Feb-15
CZ1EW EMBANKMENT FILLING CH. F 16-Feb-15 22-Mar-15
CZ1RW AGGREGATE BASE COURSE 03-Dec-14 06-Jan-15
CZ1RW AGGREGATE BASE COURSE 07-Jan-15 09-Feb-15
CZ1RW AGGREGATE BASE COURSE 10-Feb-15 15-Mar-15
CZ1RW AGGREGATE BASE COURSE 16-Mar-15 18-Apr-15
CZ1RW AGGREGATE BASE COURSE 01-May-14 04-Jun-14
CZ1RW AGGREGATE BASE COURSE 05-Jun-14 08-Jul-14
CZ1RW AGGREGATE BASE COURSE 09-Jul-14 16-Aug-14
CZ1RW AGGREGATE BASE COURSE 17-Aug-14 18-Sep-14
CZ1RW AGGREGATE BASE COURSE 20-Sep-14 27-Oct-14
CZ1RW AGGREGATE BASE COURSE 28-Oct-14 02-Dec-14
CZ1EW SUB GRADE PREPARATION IN 28-Apr-14 02-Jun-14
CZ1EW SUB GRADE PREPARATION IN 03-Jun-14 07-Jul-14
CZ1EW SUB GRADE PREPARATION IN 08-Jul-14 16-Aug-14
CZ1EW SUB GRADE PREPARATION IN 17-Aug-14 20-Sep-14
CZ1EW SUB GRADE PREPARATION IN 21-Sep-14 29-Oct-14
CZ1EW SUB GRADE PREPARATION IN 30-Oct-14 06-Dec-14
CZ1EW SUB GRADE PREPARATION IN 07-Dec-14 11-Jan-15
CZ1EW SUB GRADE PREPARATION IN 12-Jan-15 15-Feb-15
CZ1EW SUB GRADE PREPARATION IN 16-Feb-15 22-Mar-15
CZ1EW SUB GRADE PREPARATION IN 24-Mar-14 27-Apr-14
CZ1CU 7.02 CONSTRUCTION OF INL 05-May-14 17-May-14
CZ1CU 19.02 CONSTRUCTION OF IN 02-Jun-14 14-Jun-14
CZ1CU 21.03 CONSTRUCTION OF IN 05-Jun-14 11-Jun-14
CZ1CU 13.02 CONSTRUCTION OF IN 29-May-14 07-Jun-14
CZ1CU 9.02 CONSTRUCTION OF INL 08-May-14 20-May-14
CZ1CU 37.06 CONSTRUCTION OF IN 13-Nov-14 24-Nov-14
CZ1CU 16.02 CONSTRUCTION OF IN 26-May-14 08-Jun-14
CZ1CU 36.39 CONSTRUCTION OF IN 05-Jan-15 21-Jan-15
CZ1CU 44.02 CONSTRUCTION OF IN 22-Oct-14 01-Nov-14
CZ1CU 24.06 CONSTRUCTION OF IN 20-Aug-14 30-Aug-14
CZ1CU PART 1 CONSTRUCTION OF 28-May-14 07-Jul-14
CZ1CU PART 1 CONSTRUCTION OF 08-Jul-14 23-Aug-14
CZ1CU PART 1 CONSTRUCTION OF 24-Aug-14 07-Oct-14
CZ1CU PART 1 CONSTRUCTION OF 08-Oct-14 19-Nov-14
CZ1CU PART 1 CONSTRUCTION OF 20-Nov-14 04-Jan-15
CZ1CU PART 1 CONSTRUCTION OF 05-Jan-15 16-Feb-15
CZ1CU PART 1 CONSTRUCTION OF 17-Feb-15 31-Mar-15
CZ1CU PART 1 CONSTRUCTION OF 16-Apr-14 26-May-14
CZ1CU 20.03 CONSTRUCTION OF IN 24-Jun-14 05-Jul-14
CZ1CU 35.24 CONSTRUCTION OF IN 16-Nov-14 26-Nov-14
CZ1CU 43.02 CONSTRUCTION OF IN 19-Oct-14 28-Oct-14
CZ1CU 10.07 CONSTRUCTION OF IN 10-Jun-14 21-Jun-14
CZ1CU 45.03 CONSTRUCTION OF IN 26-Oct-14 05-Nov-14
CZ1CU 34.51 CONSTRUCTION OF IN 13-Jan-15 07-Feb-15
CZ1CU 22.02 CONSTRUCTION OF IN 19-Jun-14 28-Jun-14
CZ1CU 41.06 CONSTRUCTION OF IN 20-Nov-14 30-Nov-14

Actual Work Critical Remaining Work Summary Page 54 of 57 TASK filter: All Activities

Remaining Work Milestone © Oracle Corporation


DUALIZATION OF MAHDAH - AL RAWDAH ROAD PROJECT Classic Schedule Layout 25-May-14 16:51

Activity ID Activity Name Start Finish

CZ1CU 23.03 CONSTRUCTION OF IN 09-Jul-14 14-Jul-14


CZ1CU 12.06 CONSTRUCTION OF IN 14-Jul-14 24-Jul-14
CZ1CU 42.14 CONSTRUCTION OF IN 27-Dec-14 05-Jan-15
CZ1CU 32.06 CONSTRUCTION OF IN 27-Aug-14 06-Sep-14
CZ3RW AGGREGATE BASE COURSE 08-Apr-15 17-May-15
CZ3RW AGGREGATE BASE COURSE 18-May-15 25-Jun-15
CZ3RW AGGREGATE BASE COURSE 27-Jun-15 10-Aug-15
CZ3RW AGGREGATE BASE COURSE 11-Aug-15 19-Sep-15
CZ3RW AGGREGATE BASE COURSE 20-Sep-15 02-Nov-15
CZ3RW AGGREGATE BASE COURSE 03-Nov-15 14-Dec-15
CZ3RW AGGREGATE BASE COURSE 15-Dec-15 24-Jan-16
CZ3RW AGGREGATE BASE COURSE 25-Jan-16 03-Mar-16
CZ3RW AGGREGATE BASE COURSE 05-Mar-16 16-Apr-16
CZ3EW EMBANKMENT FILLING CH. F 22-Feb-15 28-Mar-15
CZ3EW EMBANKMENT FILLING CH. F 29-Mar-15 02-May-15
CZ3EW EMBANKMENT FILLING CH. F 03-May-15 04-Jun-15
CZ3EW EMBANKMENT FILLING CH. F 06-Jun-15 08-Jul-15
CZ3EW EMBANKMENT FILLING CH. F 18-Aug-15 20-Sep-15
CZ3EW EMBANKMENT FILLING CH. F 21-Sep-15 28-Oct-15
CZ3EW EMBANKMENT FILLING CH. F 29-Oct-15 03-Dec-15
CZ3EW EMBANKMENT FILLING CH. F 05-Dec-15 12-Jan-16
CZ3EW EMBANKMENT FILLING CH. F 09-Jul-15 17-Aug-15
CZ3EW SUB GRADE PREPARATION IN 06-Sep-15 18-Oct-15
CZ3EW SUB GRADE PREPARATION IN 19-Oct-15 25-Nov-15
CZ3EW SUB GRADE PREPARATION IN 26-Nov-15 06-Jan-16
CZ3EW SUB GRADE PREPARATION IN 07-Jan-16 14-Feb-16
CZ3EW SUB GRADE PREPARATION IN 18-Feb-16 27-Mar-16
CZ3EW SUB GRADE PREPARATION IN 24-Mar-15 30-Apr-15
CZ3EW SUB GRADE PREPARATION IN 04-May-15 10-Jun-15
CZ3EW SUB GRADE PREPARATION IN 15-Jun-15 28-Jul-15
CZ3EW SUB GRADE PREPARATION IN 29-Jul-15 05-Sep-15
CZ3CU 163.3 CONSTRUCTION OF IN 28-Jul-15 06-Aug-15
CZ3CU PART 3 CONSTRUCTION OF 25-Dec-14 26-Jan-15
CZ3CU PART 3 CONSTRUCTION OF 27-Jan-15 26-Feb-15
CZ3CU PART 3 CONSTRUCTION OF 28-Feb-15 30-Mar-15
CZ3CU PART 3 CONSTRUCTION OF 31-Mar-15 29-Apr-15
CZ3CU PART 3 CONSTRUCTION OF 30-Apr-15 30-May-15
CZ3CU PART 3 CONSTRUCTION OF 31-May-15 29-Jun-15
CZ3CU PART 3 CONSTRUCTION OF 30-Jun-15 04-Aug-15
CZ3CU PART 3 CONSTRUCTION OF 05-Aug-15 03-Sep-15
CZ3CU PART 3 CONSTRUCTION OF 05-Sep-15 07-Oct-15
CZ3CU PART 3 CONSTRUCTION OF 08-Oct-15 08-Nov-15
CZ3CU 110.2 CONSTRUCTION OF IN 08-Feb-15 18-Feb-15
CZ3CU 118.36 CONSTRUCTION OF I 16-May-15 06-Jun-15
CZ3CU 125.2 CONSTRUCTION OF IN 24-Mar-15 04-Apr-15
CZ3CU 126.6 CONSTRUCTION OF IN 30-Mar-15 09-Apr-15
CZ3CU 111.3 CONSTRUCTION OF IN 15-Feb-15 22-Feb-15
CZ3CU 167.6 CONSTRUCTION OF IN 09-Aug-15 18-Aug-15
CZ3CU 149.2 CONSTRUCTION OF IN 07-Jul-15 16-Jul-15
CZ3CU 153.2 CONSTRUCTION OF IN 07-Jul-15 16-Jul-15
CZ3CU 159.2 CONSTRUCTION OF IN 06-Jul-15 16-Jul-15

Actual Work Critical Remaining Work Summary Page 55 of 57 TASK filter: All Activities

Remaining Work Milestone © Oracle Corporation


DUALIZATION OF MAHDAH - AL RAWDAH ROAD PROJECT Classic Schedule Layout 25-May-14 16:51

Activity ID Activity Name Start Finish

CZ3CU 150.2 CONSTRUCTION OF IN 06-Jul-15 16-Jul-15


CZ3CU 116.3 CONSTRUCTION OF IN 18-Feb-15 28-Feb-15
CZ3CU 143.4 CONSTRUCTION OF IN 06-Jun-15 15-Jun-15
CZ3CU 161.8 CONSTRUCTION OF IN 15-Jul-15 30-Jul-15
CZ3CU 138.12 CONSTRUCTION OF I 13-Jun-15 30-Jun-15
CZ3CU 142.7 CONSTRUCTION OF IN 07-Jul-15 29-Jul-15
CZ3CU 141.4 CONSTRUCTION OF IN 25-May-15 04-Jun-15
CZ3CU 127.3 CONSTRUCTION OF IN 05-Apr-15 13-Apr-15
CZ3CU 123.4 CONSTRUCTION OF IN 17-Mar-15 28-Mar-15
CZ3CU 129.2 CONSTRUCTION OF IN 22-Apr-15 03-May-15
CZ3CU 139.3 CONSTRUCTION OF IN 07-May-15 17-May-15
CZ3CU 117.14 CONSTRUCTION OF I 20-Apr-15 07-May-15
CZ3CU 160.3 CONSTRUCTION OF IN 11-Jul-15 27-Jul-15
CZ3CU 128.6 CONSTRUCTION OF IN 25-May-15 11-Jun-15
CZ3CU 151.4 CONSTRUCTION OF IN 06-Jul-15 16-Jul-15
CZ3CU 166.4 CONSTRUCTION OF IN 02-Aug-15 12-Aug-15
CZ2RW AGGREGATE BASE COURSE 17-Nov-14 01-Jan-15
CZ2RW AGGREGATE BASE COURSE 04-Jan-15 16-Feb-15
CZ2RW AGGREGATE BASE COURSE 02-Apr-15 16-May-15
CZ2RW AGGREGATE BASE COURSE 17-May-15 29-Jun-15
CZ2RW AGGREGATE BASE COURSE 30-Jun-15 17-Aug-15
CZ2RW AGGREGATE BASE COURSE 18-Aug-15 03-Oct-15
CZ2RW AGGREGATE BASE COURSE 04-Oct-15 16-Nov-15
CZ2RW AGGREGATE BASE COURSE 17-Nov-15 02-Jan-16
CZ2RW AGGREGATE BASE COURSE 03-Jan-16 14-Feb-16
CZ2RW AGGREGATE BASE COURSE 17-Feb-15 01-Apr-15
CZ2EW EMBANKMENT FILLING CH. F 19-Nov-14 11-Jan-15
CZ2EW EMBANKMENT FILLING CH. F 12-Jan-15 02-Mar-15
CZ2EW EMBANKMENT FILLING CH. F 03-Mar-15 21-Apr-15
CZ2EW EMBANKMENT FILLING CH. F 22-Apr-15 10-Jun-15
CZ2EW EMBANKMENT FILLING CH. F 11-Jun-15 05-Aug-15
CZ2EW EMBANKMENT FILLING CH. F 06-Aug-15 24-Sep-15
CZ2EW EMBANKMENT FILLING CH. F 29-Sep-15 18-Nov-15
CZ2EW EMBANKMENT FILLING CH. F 19-Nov-15 11-Jan-16
CZ2EW EMBANKMENT FILLING CH. F 05-Aug-14 24-Sep-14
CZ2EW EMBANKMENT FILLING CH. F 25-Sep-14 18-Nov-14
CZ2EW SUB GRADE PREPARATION IN 02-Sep-14 22-Oct-14
CZ2EW SUB GRADE PREPARATION IN 23-Oct-14 11-Dec-14
CZ2EW SUB GRADE PREPARATION IN 13-Dec-14 28-Jan-15
CZ2EW SUB GRADE PREPARATION IN 29-Jan-15 16-Mar-15
CZ2EW SUB GRADE PREPARATION IN 17-Mar-15 02-May-15
CZ2EW SUB GRADE PREPARATION IN 03-May-15 17-Jun-15
CZ2EW SUB GRADE PREPARATION IN 18-Jun-15 09-Aug-15
CZ2EW SUB GRADE PREPARATION IN 10-Aug-15 24-Sep-15
CZ2EW SUB GRADE PREPARATION IN 29-Sep-15 15-Nov-15
CZ2EW SUB GRADE PREPARATION IN 16-Nov-15 04-Jan-16
CZ2CU 48.2 CONSTRUCTION OF INL 28-Oct-14 06-Nov-14
CZ2CU 50.4 CONSTRUCTION OF INL 10-Nov-14 20-Nov-14
CZ2CU 80.2 CONSTRUCTION OF INL 11-Dec-14 22-Dec-14
CZ2CU 98.4 CONSTRUCTION OF INL 30-Mar-15 11-Apr-15
CZ2CU 82.2 CONSTRUCTION OF INL 15-Dec-14 24-Dec-14

Actual Work Critical Remaining Work Summary Page 56 of 57 TASK filter: All Activities

Remaining Work Milestone © Oracle Corporation


DUALIZATION OF MAHDAH - AL RAWDAH ROAD PROJECT Classic Schedule Layout 25-May-14 16:51

Activity ID Activity Name Start Finish

CZ2CU 63.4 CONSTRUCTION OF INL 27-Oct-14 06-Nov-14


CZ2CU 91.2 CONSTRUCTION OF INL 26-Jan-15 05-Feb-15
CZ2CU 104.3 CONSTRUCTION OF IN 12-Apr-15 22-Apr-15
CZ2CU 108.2 CONSTRUCTION OF IN 13-Apr-15 22-Apr-15
CZ2CU 73.2 CONSTRUCTION OF INL 17-Nov-14 29-Nov-14
CZ2CU 92.2 CONSTRUCTION OF INL 31-Jan-15 09-Feb-15
CZ2CU 93.2 CONSTRUCTION OF INL 03-Feb-15 14-Feb-15
CZ2CU 102.15 CONSTRUCTION OF I 18-May-15 02-Jun-15
CZ2CU 87.2 CONSTRUCTION OF INL 14-Jan-15 25-Jan-15
CZ2CU 90.2 CONSTRUCTION OF INL 22-Jan-15 02-Feb-15
CZ2CU 77.3 CONSTRUCTION OF INL 13-Jan-15 24-Jan-15
CZ2CU 86.2 CONSTRUCTION OF INL 11-Jan-15 20-Jan-15
CZ2CU 96.2 CONSTRUCTION OF INL 15-Feb-15 25-Feb-15
CZ2CU 95.3 CONSTRUCTION OF INL 11-Feb-15 21-Feb-15
CZ2CU 64.4 CONSTRUCTION OF INL 12-Nov-14 25-Nov-14
CZ2CU 101.5 CONSTRUCTION OF IN 12-Apr-15 27-Apr-15
CZ2CU 94.3 CONSTRUCTION OF INL 07-Feb-15 17-Feb-15
CZ2CU 46.2 CONSTRUCTION OF INL 26-Oct-14 03-Nov-14
CZ2CU 83.83 CONSTRUCTION OF IN 03-Mar-15 24-Mar-15
CZ2CU 85.26 CONSTRUCTION OF IN 16-Mar-15 05-Apr-15
CZ2CU PART 2 CONSTRUCTION OF 16-Nov-14 23-Dec-14
CZ2CU PART 2 CONSTRUCTION OF 24-Dec-14 29-Jan-15
CZ2CU PART 2 CONSTRUCTION OF 31-Jan-15 07-Mar-15
CZ2CU PART 2 CONSTRUCTION OF 08-Mar-15 12-Apr-15
CZ2CU PART 2 CONSTRUCTION OF 13-Apr-15 18-May-15
CZ2CU PART 2 CONSTRUCTION OF 19-May-15 23-Jun-15
CZ2CU PART 2 CONSTRUCTION OF 24-Jun-15 03-Aug-15
CZ2CU PART 2 CONSTRUCTION OF 04-Aug-15 07-Sep-15
CZ2CU PART 2 CONSTRUCTION OF 08-Sep-15 17-Oct-15
CZ2CU PART 2 CONSTRUCTION OF 18-Oct-15 21-Nov-15
CZ2CU 65.4 CONSTRUCTION OF INL 16-Nov-14 30-Nov-14
CZ2CU 74.3 CONSTRUCTION OF INL 09-Dec-14 20-Dec-14
CZ2CU 84.5 CONSTRUCTION OF INL 03-Feb-15 19-Feb-15
CZ2CU 88.2 CONSTRUCTION OF INL 19-Jan-15 28-Jan-15
CZ2CU 75.12 CONSTRUCTION OF IN 24-Jan-15 10-Feb-15
CZ2CU 99.9 CONSTRUCTION OF INL 28-Apr-15 17-May-15

Actual Work Critical Remaining Work Summary Page 57 of 57 TASK filter: All Activities