You are on page 1of 2

Relining of Incinerator‐A & Repair of Oxidizer‐A

Bulletin No. : 12 Report Date : 29th  Oct. 2011, 08:00 hrs
Total Working /Execution Period (Days)    = 153
Execution Clock Completed Days   : 142 Remaining Days      : 11
Planned Start 10‐June‐17, 07:00 AM Planned Finish 10‐Nov.2011, 04:00 PM
Actual Start 10‐June‐11, 07:00 AM Expected Finish 02‐Nov.2011, 05:00 AM
Planned Duration  154 Days Expected Duration 56 Days
HIGHLIGHTS
Safety:
Last 1 Week Cumulative Status
Observations 0 56 ALL CLOSED
Near Misses 0 0
Property Damage 0 0
MT-Medical Treatment 0 0
RWC- Restricted Work Cases 0 0
LTI-Lost Time Incident 0 0
Fire Incident 0 0
First Aid Cases 0 0
Environmental Incidents 0 0
Fatality 0 0

Manpower
Plan Actual Variance Status
M i t (Manhours.)
Maint. (M h ) (YANSAB) 4 178
4,178 5 264
5,264 ‐‐‐‐‐‐‐
Contractors (Nos.) 16 10 ‐‐‐‐‐‐‐
Contractors (Manhours.) 16,800 16,292 ‐‐‐‐‐‐‐

Progress Curve

100
PLAN % AGE ACTUAL % AGE
80
% AGE COMPLETION

60

40

20

DATES 

Critical Path Overall Progress
Cumulative
Stages Status
Incinerator‐A Status Target Actual
As per the Revised 
Overall Schedule Overall 79.78% 98.05%
Schedule.

Major Activities Carried Out During Last Week
INCINERATOR ‐ A

Bricks installation at Top Area.

OXIDIZER ‐ A
Shuttering, Gunning of First & Second Layer.

Prepared By ‐ 
Yansab Planning Page 1 of 2
Planned Major Activities for Next 1 Week
INCINERATOR ‐ A
Shuttering removal and housekeeping for Final inspection. Removal of scaffolding, Blinds & Box up. Nozzle repair.

OXIDIZER ‐ A
Ramming final layer, Final inspection, Removal of Scaffolding & box up.
Mile Stones

Critical Activities

Reconstruction of Incinerator‐A Flash Report
Equipment Contract Awarded Major Material Ordered Material Delivered Logistics Remarks

Action Items: Responsibility

Slipping Tasks nearing critical path & Constraints, if any: Responsibility

Prepared By ‐ 
Yansab Planning Page 2 of 2

You might also like