Bulletin No. : 12 Report Date : 29th Oct. 2011, 08:00 hrs
Total Working /Execution Period (Days) = 153
Execution Clock Completed Days : 142 Remaining Days : 11
Planned Start 10‐June‐17, 07:00 AM Planned Finish 10‐Nov.2011, 04:00 PM
Actual Start 10‐June‐11, 07:00 AM Expected Finish 02‐Nov.2011, 05:00 AM
Planned Duration 154 Days Expected Duration 56 Days
HIGHLIGHTS
Safety:
Last 1 Week Cumulative Status
Observations 0 56 ALL CLOSED
Near Misses 0 0
Property Damage 0 0
MT-Medical Treatment 0 0
RWC- Restricted Work Cases 0 0
LTI-Lost Time Incident 0 0
Fire Incident 0 0
First Aid Cases 0 0
Environmental Incidents 0 0
Fatality 0 0
Manpower
Plan Actual Variance Status
M i t (Manhours.)
Maint. (M h ) (YANSAB) 4 178
4,178 5 264
5,264 ‐‐‐‐‐‐‐
Contractors (Nos.) 16 10 ‐‐‐‐‐‐‐
Contractors (Manhours.) 16,800 16,292 ‐‐‐‐‐‐‐
Progress Curve
100
PLAN % AGE ACTUAL % AGE
80
% AGE COMPLETION
60
40
20
DATES
Critical Path Overall Progress
Cumulative
Stages Status
Incinerator‐A Status Target Actual
As per the Revised
Overall Schedule Overall 79.78% 98.05%
Schedule.
Major Activities Carried Out During Last Week
INCINERATOR ‐ A
Bricks installation at Top Area.
OXIDIZER ‐ A
Shuttering, Gunning of First & Second Layer.
Prepared By ‐
Yansab Planning Page 1 of 2
Planned Major Activities for Next 1 Week
INCINERATOR ‐ A
Shuttering removal and housekeeping for Final inspection. Removal of scaffolding, Blinds & Box up. Nozzle repair.
OXIDIZER ‐ A
Ramming final layer, Final inspection, Removal of Scaffolding & box up.
Mile Stones
Critical Activities
Reconstruction of Incinerator‐A Flash Report
Equipment Contract Awarded Major Material Ordered Material Delivered Logistics Remarks
Action Items: Responsibility
Slipping Tasks nearing critical path & Constraints, if any: Responsibility
Prepared By ‐
Yansab Planning Page 2 of 2