JINDAL STEEL & POWER LIMITED

ANGUL

Questions on SMP Of Conveyors


Date:

Name: ______________________ Agency/Department: ____________________ Empl. No: ____________

Pre test Please put tick ( ) mark on the correct answer. Each question carries 1 mark.
Post test
1. On Site Emergency plan shall be approved by:

a) Chief Labor Commissioner b) District Magistrate. c) Chief Inspector of Factories d) Non of the above

2. The number of hazardous industries included in Factory Act?

a) 27 b) 28 c) 29 d) 30

3. Anyone noticing Emergency shall immediately inform to:

a) HOD b) Plant Manager c) Safety Department d) Shift In charge

4. How many Emergency Assembly points are there in your Department?

a) 1 b) 2 c) 3 d) 4

5. In case of chlorine leakage, siren will be activated continuously for:

a) 3 min b) 4 min c) 5 min d) 6 min

6. In case of Fire /Explosion emergency, intermittent siren will be blown:

a) 10 second up and 5 seconds down for 3 minutes b) 20 second up and 20 seconds for 3 minutes
c) 25 second up and 25 seconds for 3 minutes d) All of the above

7. Rule no. ----- of “The Orissa Factories (Control of Major Accident Hazard) Rules, 2001” gives details in the On-
site Emergency Plan:

a) 10 b) 11 c) 12 d) 13

8. In case of chlorine leakage, one should move:

a) In the direction of wind b) to the shallow areas c) to the higher elevation d) All of the above

9. The Onsite Emergency Plan must be rehearsaled @ ----- months:

a)6 b) 12 c) 18 d) Non of the above

10. Which of the following is an emergency response team?

a) Operation Team b) Maintenance Team c) Security Team d) Combat Team