You are on page 1of 223

LARSEN & TOUBRO CONSTRUCTION PROCEDURE NO:

Power Transmission & Distribution T&C/T& C P/AIS-GIS/001

TESTING AND COMMISSIONING PROCEDURE Page 1 of 223

TESTING & COMMISSIONING PROCEDURE FOR


SWITCHYARD EQUIPMENTS & SWITCHGEARS
LARSEN & TOUBRO CONSTRUCTION PROCEDURE NO:
Power Transmission & Distribution T&C/T& C P/AIS-GIS/001

TESTING AND COMMISSIONING PROCEDURE Page 2 of 223

TABLE OF CONTENTS

CONTENT PAGE
SL NO DESCRIPTION
NO NO
CURRENT TRANSFORMERS
1. 1.0 Scope 29
2. 2.0 Purpose 29
3. 3.0 Pre-requisites 29
4. 3.1 System requirements 29
5. 4.0 Requirements of Testing Kits 29
6. 5.0 Requirements of Testing Instruments 29
7. 6.0 Hazards and precautions 30
8. 7.0 Post installation checks 30
9. 8.0 Test to be conducted 30
10. 8.1 Insulation Resistance Test 30
11. 8.2 Continuity Test 32
12. 8.3 Secondary Winding Resistance Test 32
13. 8.4 Polarity Test 33
14. 8.5 Tan Delta & Capacitance Test 34
15. 8.6 Primary Injection Test Kit 35
16. 8.7 Magnetizing Current Characteristic Test 35
17. 8.8 Contact Resistance Measurement Test For Connectors 36
18. 8.9 Secondary Injection Test 37
19. An – 1 Annexure – 1 – Format for Equipment Data 38
20. An – 2 Annexure – 2 – Post Installation Check list 39
21. An – 3 Annexure – 3 – Insulation Resistance Test 41
22. An – 4 Annexure – 4- Insulation Resistance Test 42
23. An – 5 Annexure – 5- Insulation Resistance Test 42
24. An – 6 Annexure – 6 – Continuity Test 43
25. An – 7 Annexure – 7 – Secondary Winding Resistance Test 44
26. An – 8 Annexure – 8 – Polarity Test 45
27. An – 9 Annexure – 9 – Tan Delta & Capacitance Test 46
28. An – 10 Annexure – 10- Primary Injection Test 47
29. An – 11 Annexure – 11- Magnetizing Current Characteristic Test 49
30. An – 12 Annexure – 12- Contact Resistance Test For Connectors 50
31. An – 13 Annexure – 13- Secondary Injection Test 50
32. An – 14 Annexure – 14- Calibration Status Table 51
CAPACITIVE VOLTAGE TRANSFORMER
33. 1.0 Scope 53
34. 2.0 Purpose 53
35. 3.0 Pre-requisites 53
LARSEN & TOUBRO CONSTRUCTION PROCEDURE NO:
Power Transmission & Distribution T&C/T& C P/AIS-GIS/001

TESTING AND COMMISSIONING PROCEDURE Page 3 of 223

36. 3.1 System requirements 53


37. 4.0 Requirements of Testing Kits 53
38. 5.0 Requirements of Testing Instruments 53
39. 6.0 Hazards and precautions 53
40. 7.0 Post installation checks 54
41. 8.0 Test to be conducted 54
42. 8.1 Insulation Resistance Test 54
43. 8.2 Continuity Test 56
44. 8.3 Secondary Winding Resistance Test 56
45. 8.4 Polarity Test 56
46. 8.5 Tan Delta & Capacitance Test 57
47. 8.6 Ratio Test 58
48. 8.7 Contact Resistance Measurement Test For Connectors 59
49. 8.8 Secondary Injection Test 59
50. An – 1 Annexure – 1 – Format for Equipment Data 60
51. An – 2 Annexure – 2 – Post Installation Check list 60
52. An – 3 Annexure – 3 – Insulation Resistance Test 61
53. An – 4 Annexure – 4- Insulation Resistance Test 62
54. An – 5 Annexure – 5- Insulation Resistance Test 62
55. An – 6 Annexure – 6 – Continuity Test 62
56. An – 7 Annexure – 7 – Secondary Winding Resistance Test 63
57. An – 8 Annexure – 8 – Polarity Test 63
58. An – 9 Annexure – 9 – Tan Delta & Capacitance Test 64
59. An – 10 Annexure – 10- Ratio Test 64
60. An – 11 Annexure – 11- Contact Resistance Test For Connectors 65
61. An – 12 Annexure – 12- Secondary Injection Test 65
62. An – 13 Annexure – 13- Calibration Status Table 65
TRANSFORMERS
63. 1.0 Scope 67
64. 2.0 Purpose 67
65. 3.0 Pre-requisites 67
66. 3.1 System requirements 67
67. 4.0 Requirements of Testing Kits 67
68. 5.0 Requirements of Testing Instruments 67
69. 6.0 Hazards and precautions 67
70. 7.0 Post installation checks 68
71. 8.0 Test to be conducted 68
72. 8.1 Insulation Resistance Test(Polarization Index) 69
73. 8.2 Core Insulation Test 70
74. 8.3 Magnetic Balance Test 70
75. 8.4 Floating Neutral Test 71
76. 8.5 Winding Resistance Test 71
77. 8.6 Ratio Test 71
78. 8.7 Tan Delta & Capacitance Test 72
79. 8.8 Vector Group Test Magnetizing Current Characteristic Test 73
LARSEN & TOUBRO CONSTRUCTION PROCEDURE NO:
Power Transmission & Distribution T&C/T& C P/AIS-GIS/001

TESTING AND COMMISSIONING PROCEDURE Page 4 of 223

80. 8.9 Magnetizing Current Characteristic Test 74


81. 8.10 Short Circuit Test 74
82. 8.11 Sweep Frequency Analysis Test 75
83. 8.12 Test On Oil Sample 76
84. 8.13 Operational Checks on Protection System 76
85. 8.14 Operational Checks on OLTC 77
86. An – 1 Annexure – 1 – Format for Equipment Data 78
87. An – 2 Annexure – 2 – Post Installation Check list 79
88. An – 3 Annexure – 3 – Insulation Resistance Test(Polarization Index) 80
89. An – 4 Annexure – 4- Core Insulation Test 81
90. An – 5 Annexure – 5- Magnetic Balance Test 81
91. An – 6 Annexure – 6 – Floating Neutral Test 82
92. An – 7 Annexure – 7 –Winding Resistance Test 82
93. An – 8 Annexure – 8 – Ratio Test 83
94. An – 9 Annexure – 9 – Tan Delta & Capacitance Test 85
95. An – 10 Annexure – 10- Vector Group Test 86
96. An – 11 Annexure – 11- Magnetizing Current Characteristic Test 87
97. An – 12 Annexure – 12- Short Circuit Test 87
98. An – 13 Annexure – 13- Dissolved Gas Analysis Test 88
99. An – 14 Annexure – 14- Test On OLTC 89
100. An – 15 Annexure – 15 - Test Other Systems 89
101. An – 16 Annexure – 16 - Oil Characteristics 90
102. An – 17 Annexure – 17- Calibration Status Table 91
CIRCUIT BREAKER
103. 1.0 Scope 93
104. 2.0 Purpose 93
105. 3.0 Pre-requisites 93
106. 3.1 System requirements 93
107. 4.0 Requirements of Testing Kits 93
108. 5.0 Requirements of Testing Instruments 93
109. 6.0 Hazards and precautions 93
110. 7.0 Post installation checks 94
111. 8.0 Test to be conducted 94
112. 8.1 SF6 Gas Lockout/Low Alarm Test 94
113. 8.2 Dew Point Test 95
114. 8.3 Insulation Resistance Measurement Test 96
115. 8.4 Trip Coil/Close Coil Resistance Measurement Test 96
116. 8.5 Operating Time Measurement Test 97
117. 8.6 Contact Resistance Measurement Test 97
118. An – 1 Annexure – 1 – Format for Equipment Details 99
119. An – 2 Annexure – 2 – Post Installation Check list 99
120. An – 3 Annexure – 3 –Dew Point Test 100
121. An – 4 Annexure – 4- SF6 Gas Lockout/Low Alarm Test 100
122. An – 5 Annexure – 5- Insulation Resistance Test 100
123. An – 6 Annexure – 6 –Operating Time Measurement Test 101
LARSEN & TOUBRO CONSTRUCTION PROCEDURE NO:
Power Transmission & Distribution T&C/T& C P/AIS-GIS/001

TESTING AND COMMISSIONING PROCEDURE Page 5 of 223

124. An – 7 Annexure – 7 – Contact Resistance Test 101


125. Pre-Commissioning Checks for Hydraulic Operating System 101
126. Pre-Commissioning Checks for Pneumatic Operating System 103
127. Pre-Commissioning Checks for Spring Charge Operating
105
System
128. SF6 Gas Leakage Checks 105
129. Circuitry/Operational Checks 105
130. Breaker Counter Reading Checks 106
131. Check for annunciation in control room as per the following
106
formats and record the reading
132. Calibration Status Table 107
ISOLATORS
133. 1.0 Scope 109
134. 2.0 Purpose 109
135. 3.0 Pre-requisites 109
136. 3.1 System requirements 109
137. 4.0 Requirements of Testing Kits 109
138. 5.0 Requirements of Testing Instruments 109
139. 6.0 Hazards and precautions 109
140. 7.0 Post installation checks 110
141. 8.0 Test to be conducted 110
142. 8.1 Insulation Resistance Measurement Test 110
143. 8.2 Contact Resistance Measurement Test 111
144. An – 1 Annexure – 1 – Format for Equipment Details 112
145. An – 2 Annexure – 2 – Post Installation Check list 112
146. An – 3 Annexure – 3 – Insulation Resistance Test 113
147. An – 4 Annexure – 4- Contact Resistance Test 114
148. Operational Checks on Isolators 114
149. Motor Operation Current Measurement Format 114
150. Operating Time Measurement Format 115
151. Auxiliary Contacts checking Format 115
152. Operation on under voltage condition check Format 115
153. Operation of Isolators & Inter Lock Check Format 115
154. Calibration Status Table 118
WAVE TRAP
155. 1.0 Scope 120
156. 2.0 Purpose 120
157. 3.0 Pre-requisites 120
158. 3.1 System requirements 120
159. 4.0 Requirements of Testing Kits 120
160. 5.0 Requirements of Testing Instruments 120
161. 6.0 Hazards and precautions 120
162. 7.0 Post installation checks 121
163. 8.0 Test to be conducted 121
164. 8.1 Insulation Resistance Measurement Test 121
LARSEN & TOUBRO CONSTRUCTION PROCEDURE NO:
Power Transmission & Distribution T&C/T& C P/AIS-GIS/001

TESTING AND COMMISSIONING PROCEDURE Page 6 of 223

165. 8.2 Contact Resistance Measurement Test 122


166. An – 1 Annexure – 1 – Format for Equipment Details 123
167. An – 2 Annexure – 2 – Post Installation Check list 123
168. An – 3 Annexure – 3 – Insulation Resistance Test 124
169. An – 4 Annexure – 4- Contact Resistance Test 124
170. Calibration Status Table 124
LIGHTNING ARRESTORS
171. 1.0 Scope 126
172. 2.0 Purpose 126
173. 3.0 Pre-requisites 126
174. 3.1 System requirements 126
175. 4.0 Requirements of Testing Kits 126
176. 5.0 Requirements of Testing Instruments 126
177. 6.0 Hazards and precautions 126
178. 7.0 Post installation checks 127
179. 8.0 Test to be conducted 127
180. 8.1 Insulation Resistance Measurement Test 127
181. 8.2 Third Harmonic Resistance Leakage Current Measurement
128
Test
182. 8.3 Surge Counter operation check 129
183. An – 1 Annexure – 1 – Format for Equipment Details 130
184. An – 2 Annexure – 2 – Post Installation Check list 130
185. An – 3 Annexure – 3 – Insulation Resistance Test 131
186. An – 4 Annexure – 4- THRCM Test 131
187. An – 5 Annexure – 5 -Calibration Status Table 131
CABLES
HV CABLES
188. 1.0 Scope 133
189. 2.0 Purpose 133
190. 3.0 Pre-requisites 133
191. 3.1 System requirements 133
192. 4.0 Requirements of Testing Kits 133
193. 5.0 Requirements of Testing Instruments 133
194. 6.0 Hazards and precautions 133
195. 7.0 Post installation checks 134
196. 8.0 Test to be conducted 134
197. 8.1 Insulation Resistance Measurement Test 134
198. 8.2 High Voltage Test 135
199. An – 1 Annexure – 1 – Format for Cable Details 136
200. An – 2 Annexure – 2 – Post Installation Check list 136
201. An – 3 Annexure – 3 – Insulation Resistance Test 137
202. An – 4 Annexure – 4- High Voltage Test 137
203. Annexure – 5 - Calibration Status Table 138
EHV CABLES
204. 1.0 Scope 140
LARSEN & TOUBRO CONSTRUCTION PROCEDURE NO:
Power Transmission & Distribution T&C/T& C P/AIS-GIS/001

TESTING AND COMMISSIONING PROCEDURE Page 7 of 223

205. 2.0 Purpose 140


206. 3.0 Pre-requisites 140
207. 3.1 System requirements 140
208. 4.0 Requirements of Testing Kits 140
209. 5.0 Requirements of Testing Instruments 140
210. 6.0 Hazards and precautions 140
211. 7.0 Post installation checks 141
212. 8.0 Test to be conducted 141
213. 8.1 Insulation Resistance Measurement Test 141
214. 8.2 Phase verification Test 142
215. 8.3 DC Sheath Test 10KV 143
216. 8.4 Very Low Frequency Test 143
217. 8.5 No Load Test At Rated Voltage 144
218. 8.6 Power Loss Measurement 144
219. An – 1 Annexure – 1 – Format for Cable Details 146
220. An – 2 Annexure – 2 – Post Installation Check list 146
221. An – 3 Annexure – 3 – Insulation Resistance Test 147
222. An – 4 Annexure – 4- Phase verification Test 147
223. An – 5 Annexure – 5 - DC Sheath Test 10KV 147
224. An – 6 Annexure – 6 – VLF Test 148
225. An - 7 Annexure – 7 – Power Loss Measurement 148
226. An – 8 Annexure – 8 – Calibration Status Table 148
SWITCHGEARS
227. 1.0 Scope 150
228. 2.0 Purpose 150
229. 3.0 Pre-requisites 150
230. 3.1 System requirements 150
231. 4.0 Requirements of Testing Kits 150
232. 5.0 Requirements of Testing Instruments 150
233. 6.0 Hazards and precautions 150
234. 7.0 Post installation checks 151
235. 8.0 Test to be conducted 151
236. 8.1 Insulation Resistance Measurement Test 151
237. 8.2 Trip Coil/Close Coil Resistance Measurement Test 152
238. 8.3 Operating Time Measurement Test 152
239. 8.4 Contact Resistance Measurement Test 153
240. 8.5 Test on switchgear CT 154
241. 8.6 Test on switchgear PT 154
242. 8.7 Insulation Resistance Measurement for busbar 154
243. 8.8 Contact resistance measurement for busbar 155
244. 8.9 High voltage test for busbar 155
245. An – 1 Annexure – 1 – Format for Switchgear Details 156
246. An – 2 Annexure – 2 – Post Installation Check list 156
247. An – 3 Annexure – 3 - Switchgear CB Test Report 157
248. An – 4 Annexure – 4 - Switchgear CT Test Report 158
LARSEN & TOUBRO CONSTRUCTION PROCEDURE NO:
Power Transmission & Distribution T&C/T& C P/AIS-GIS/001

TESTING AND COMMISSIONING PROCEDURE Page 8 of 223

249. An – 5Annexure – 5 - Switchgear PT Test Report 160


250. An – 6Annexure – 6 – Insulation resistance test for busbar 161
251. An – 7Annexure – 7 – Contact resistance measurement for busbar 161
252. An – 8Annexure – 8 – High voltage test for busbar 162
253. Circuitry/Operational & Interlock Checks 162
254. Calibration Status Table 162
Commissioning Procedure For Air insulated sub-station
258. 1.0 Scope 164
259. 2.0 Purpose 164
260. 3.0 Pre-requisites 164
261. 4.0 Requirements of Testing equipment & Instruments 165
262. 5.0 Hazards & Precautions 165
263. 6.0 General Checks 166
264. 7.0 Energisation & Post Energisation Checks 166
265. 8.0 Work plans 167
266. An-1 Annexure – 1 - Final check list 168
267. An-1A Annexure - 1A - C & R Panel related 172
268. An-1B Annexure - 1B - SCADA related 173
269. An-2 Annexure - 2- Post Energisation Check sheet 173
270 An-3 Annexure – 3 - Verification sheet 175
Testing & Commissioning Procedure For Air insulated sub-station
271. 1.0 Scope 177
272. 2.0 Purpose 177
273. 3.0 Pre-requisites 177
274. 4.0 Requirements of Testing equipment & Instruments 178
275. 5.0 Hazards & Precautions 178
276. 6.0 Pre-commissioning checks 179
277. 7.0 Energisation & Post Energisation Checks 186
278. 8.0 Work plans 186
298. An – 1 Annexure - 1 checklist for earthing 189
299. An – 2 Annexure - 2 final checklist 191
300. An – 3 Annexure-3 Post Energisation Check sheet 196
301. An – 4 Annexure-4- Verification sheet 198
RELAY TESTING PROCEDURES
DIFFERENTIAL RELAY TESTING
302. 1.0 Scope 201
303. 2.0 Purpose 201
304. 3.0 Pre-Requisites 201
305. 3.1 System Requirements 201
306. 4.0 Requirement of testing kit 201
307. 5.0 Requirement of testing instruments 201
308. 6.0 Hazards and precautions 201
309. 7.0 Commissioning test notes 202
310. 8.0 Auxillary supply tests 203
311. 9.0 Tests to be conducted 203
LARSEN & TOUBRO CONSTRUCTION PROCEDURE NO:
Power Transmission & Distribution T&C/T& C P/AIS-GIS/001

TESTING AND COMMISSIONING PROCEDURE Page 9 of 223

312. 9.1 Phase compensation 203


313. 9.2 Specific checks 204
314. 9.3 Sensitivity checks 204
315. 9.4 Bias checks 204
316. 9.5 Harmonic restraint 205
317. 9.6 Over flux protection 205
318. 9.7 REF protection 205
319. 9.8 Selective logics 206
320. 9.9 Overcurrent & Earth fault test 206
321. 9.10 Directional feature test 206
322. 9.11 Auxillary relay test 207
323. An-1 Annexure – I – Name Plate details 208
324. An – 2 Annexure – II – Post installation checks 208
325. An – 3 Annexure – III – Sensitivity Checks 209
326. An – 4 Annexure – IV – Bias Checks 209
327. An – 5 Annexure – V – Harmonic restraint check 209
328. An – 6 Annexure – VI – Overcurrent / Earth fault protection 210
329. An – 7 Annexure – VII – Directional overcurrent / earth fault 210
330. An – 8 Annexure – VIII – Auxillary relays 210
331. An – 9 Annexure – IX – Binary inputs 211
332. An – 10 Annexure – X – Binary outputs 211
333. An – 11 Annexure – XI – LED 212
334. An – 12 Annexure – XII – Calibration status table 212
DISTANCE PROTECTION
335. 1.0 Scope 214
336. 2.0 Purpose 214
337. 3.0 Pre-Requisites 214
338. 3.1 System Requirements 214
339. 4.0 Requirement of testing kit 214
340. 5.0 Requirement of testing instruments 214
341. 6.0 Hazards and precautions 214
342. 7.0 Post installation checks 215
343. 8.0 Test to be conducted 215
344. 8.1 Zone verification check 215
345. 8.2 Auto enclosure check 216
346. 8.3 Aided trip 216
347. 8.4 SOTF 217
348. 8.5 Power swing detection 217
349. 8.6 Broken conductor detection 217
350. 8.7 VT fuse fail 217
351. 8.8 Under voltage protection 218
352. 8.9 Over voltage protection 218
353. 8.10 Overcurrent protection 218
354. 8.11 Earth fault protection 218
355. 8.12 Directional OC/EF protection 219
356. An – 1 Annexure – I – Name Plate Details 220
LARSEN & TOUBRO CONSTRUCTION PROCEDURE NO:
Power Transmission & Distribution T&C/T& C P/AIS-GIS/001

TESTING AND COMMISSIONING PROCEDURE Page 10 of 223

357. An – 2 Annexure – II – Post installation check list 220


358. An – 3 Annexure – III – Current inputs 221
359. An – 4 Annexure – IV – voltage Inputs 221
360. An – 5 Annexure – V – Settings Checks 221
361. An – 6 Annexure – VI – Zone Verification 221
362. An – 7 Annexure – VII – Autoreclosure check 222
363. An – 8 Annexure – VIII – Overcurrent protection 223
364. An – 9 Annexure – IX – Earth fault protection 223
365. An – 10 Annexure – X – Directional OC/EF protection 224
366. An – 11 Annexure – XI – Binary Inputs 224
367. An – 12 Annexure – XII – Binary outputs 224
368. An – 13 Annexure – XIII – LED checks 225
369. An – 14 Annexure – XIV – Under voltage protection 225
370. An – 15 Annexure – XV – Over voltage protection 225
371. An – 16 Annexure – XVI – Auxiliary Relay /Tc Supervision Relay/ Fuse Failure
225
Relay
372. An – 17 Annexure – XVII – Supervision relay 226
373. An – 18 Annexure – XVIII – Final checks 227
374. An – 19 Annexure – XIX – Calibration status table 227
BUSBAR PROTECTION
375. 1.0 Scope 229
376. 2.0 Purpose 229
377. 3.0 Pre-Requisites 229
378. 3.1 System Requirements 229
379. 4.0 Requirement of testing kit 229
380. 5.0 Requirement of testing instruments 229
381. 6.0 Hazards and precautions 229
382. 7.0 Post installation checks 230
383. 8.0 Test to be conducted 230
384. 9.0 Other protections 231
385. 9.1 Under frequency protection 231
386. 9.2 Over frequency protection 231
387. 9.3 Rate of change of frequency 231
388. An – 1 Annexure – I – Name plate details 232
389. An – 2 Annexure – II – Post installation checks 232
390. An – 3 Annexure – III – Busbar protection 232
391. An – 4 Annexure – IV – LBB protection 232
392. An – 5 Annexure – V – Frequency protection 234
393. An – 6 Annexure – VI – Calibration status table 235
394. BCU Inputs and outputs 236
395. BCU TO SCADA 240
LARSEN & TOUBRO CONSTRUCTION PROCEDURE NO:
Power Transmission & Distribution T&C/T& C P/AIS-GIS/001

TESTING AND COMMISSIONING PROCEDURE Page 11 of 223

PRE COMMISSIONING TEST PROCEDURE FOR CURRENT TRANSFORMERS


LARSEN & TOUBRO CONSTRUCTION PROCEDURE NO:
Power Transmission & Distribution T&C/T& C P/AIS-GIS/001

TESTING AND COMMISSIONING PROCEDURE Page 12 of 223

1.0 SCOPE
This procedure covers the Pre commissioning Test for current Transformers and the test
report format covers CT’s which is having 5 cores on its secondary.

2.0 PURPOSE
This procedure is prepared to carry out various pre- commissioning tests to be conducted in
systematic manner for Current Transformers to ensure the healthiness of the equipment.

3.0 PRE-REQUISITES
SYSTEM REQUIREMENTS
1. Relevant Drawings and layouts.
2. 415 V AC, 3 Ph power supply is available for Testing.
3. All Cables pertaining to current transformers were laid & terminated.
4. Make sure that the equipment erected is as per approved drawings & Layouts.
5. Check the Name Plate & Rating Plate Of the equipment Erected.

4.0 REQUIREMENTS OF TESTING KITS

S.No Test Kit Range


1 Tan Delta Test Kit with test leads 0 – 12kV
2 Primary Injection Kit with test leads 0-2000A / 5V (AIS)
0-3000 / 5V (GIS)
3 High Voltage Transformer with test leads 0 -5kV
4 Contact Resistance Kit with test leads 0-2000 milliohm
5 Secondary injection kit with test leads 0 – 100A

5.0 REQUIREMENT OF TESTING INSTRUMENTS


1. Digital Multi meter.
2. 500 V, 5000 V Insulation Tester
3. Polarity Tester.
4. Clamp Meters (200mA – 2000A)
5. 3 Ph- A.C Supply Extension Board with MCB Protection.
LARSEN & TOUBRO CONSTRUCTION PROCEDURE NO:
Power Transmission & Distribution T&C/T& C P/AIS-GIS/001

TESTING AND COMMISSIONING PROCEDURE Page 13 of 223

6.0 HAZARDS AND PRECAUTIONS


1. Unauthorized persons should not be allowed to enter Testing Area.
2. Barricade the Testing Area With Warning Tape
3. There should not be any temporary (hooking of supply) arrangement for Testing. Proper A.C
Supply extension board should be used
4. Ensure protection MCB is provided in the circuit of AC supply used for testing
5. Ensure Proper Tools & Tackles are Available for carrying out Tests.
6. Ensure Proper PPE ( Personal Protective Equipments) are used
7. Ensure the Healthiness of the test leads (Check for any insulation Damages).
8. Competent Authority to maintain shutdown & Work permit system in existing Live Bay
works.
9. Any conducting element should be carried horizontally at waist level in the area used for
pre-commissioning tests.

7.0 POST INSTALLATION CHECKS


Post installation check list should be done according to the annexure enclosed.

8.0 TESTS TO BE CONDUCTED


1. Insulation Resistance measurement Test.
2. Continuity Test.
3. Secondary Winding Resistance Test.
4. Polarity Test.
5. Tan Delta & Capacitance Test.
6. Primary Injection Test.
7. Magnetizing Current Characteristic Test (Knee Point Voltage Test).
8. Contact Resistance Measurement Test for Connectors.
9. Secondary Injection Test.
8.1 INSULATION RESISTANCE MEASUREMENT TEST
Aim:
To ensure the insulation healthiness of the primary and secondary circuits by measuring
insulation resistances.
Equipment Required:
The major equipment required for performing IR measurement test is,
i) 0-10kV Meggar.
ii) Test Leads.
LARSEN & TOUBRO CONSTRUCTION PROCEDURE NO:
Power Transmission & Distribution T&C/T& C P/AIS-GIS/001

TESTING AND COMMISSIONING PROCEDURE Page 14 of 223

Test Procedure:
The above test to be conducted at following points,
a) Primary to Earth
b) Primary to Secondary
c) Secondary to Earth
d) Between Secondary Cores

Note: a) Remove the connected earthing to system involving CT under test


b) Disconnect the connected terminals of CT M. Box.
c) Permissible values for 400 kV > 400 MΩ and for 220 kV > 200 MΩ

a. Primary to earth
1) Connect the line terminal of the Meggar (5000V) to either P1 (or) P2 of the Current
Transformers
2) Connect the Earth terminal of the Meggar to the earth stud provided at the equipment
3) Switch on the Meggar
4) Take down the readings (It should be in Mega Ohms).

b. Primary to Secondary
1) Connect the line terminal of the Meggar(5000V) to either P1 (or) P2 of the Current
transformers
2) Connect the Earth terminal of the Meggar to the S1 (or) S2 of the Current transformers
3) Switch on the Meggar

4) Take down the readings( It should be in Mega Ohms)

c. Secondary to Earth
1) Connect the line terminal of the Meggar(500V) to either S1 (or) S2 of the Current
transformers
2) Connect the Earth terminal of the Meggar to the earth stud provided at the equipment
3) Switch on the Meggar.

4) Take down the readings (It should be in Mega Ohms).

d. Between Secondary cores


1) Connect the line terminal of the Meggar(500V) to either S1 (or) S2 of one core of the Current
transformers
LARSEN & TOUBRO CONSTRUCTION PROCEDURE NO:
Power Transmission & Distribution T&C/T& C P/AIS-GIS/001

TESTING AND COMMISSIONING PROCEDURE Page 15 of 223

2) Connect the Earth terminal of the Meggar(500V) to either S1 (or) S2 of the other cores of
the Current transformers
3) Switch on the Meggar
4) Take down the readings (It should be in Mega Ohms).

Fig 1 : Insulation Resistance Measurement Setup


Test Format For the above test is enclosed in Annexure –III, IV & V.

8.2 CONTINUITY TEST


Aim:
To show that there is a continuity of supply in primary and secondary winding without any
open circuit in the current path.
Equipments Required:
The equipments required for performing continuity test are,
i) Digital Multimeter.
ii) Test Leads.
Test Procedure:
a) Select the Multi meter in continuity Mode.
b) Connect the Multi meter across the secondary terminals of various cores.
c) Check for the ‘Beep’ sound.
Test Format For the above test are enclosed in Annexure –VI
8.3 SECONDARY WINDING RESISTANCE TEST
Aim:
To check for the winding resistance on the secondary side value, so that the value matches
with the factory test values.
Equipments Required:
The Secondary winding resistance test can be performed with the following equipments,
i) Milli ohm meter.
ii) Test Leads.
LARSEN & TOUBRO CONSTRUCTION PROCEDURE NO:
Power Transmission & Distribution T&C/T& C P/AIS-GIS/001

TESTING AND COMMISSIONING PROCEDURE Page 16 of 223

Test Procedure:
a) Select the Multi meter in Resistance Mode.
b) Connect the Multi meter across the secondary terminals of various cores.
c) Note down the readings
d) Compare the test results with Factory Test Report (If available)
Test Format For the above test are enclosed in Annexure –VII

8.4 POLARITY TEST

Aim:
To check for the correct sequence of polarity on the primary and secondary side of the
current transformer. (For eg. When P1 is positive w.r.t. P2, then S1 also must be positive w.r.t S2,
according to the scheme requirement).
Equipments Required:
The equipments required for polarity tests are as follows,
i) Battery of suitable rating or Polarity tester.
ii) Analog Multimeter / Galvanometer.
iii) Connecting leads.
Test Procedure:

i) Connect battery + Ve to P1(Primary) Terminal of CT


ii) Connect battery - Ve to P2 (Primary) Terminal of CT
iii) Connect Multi meter (Analog) + Ve to S1 (Secondary) Terminal of CT
iv) Connect Multi meter (Analog) - Ve to S2 (Secondary) Terminal of CT
v) Momentarily apply the D.C Voltage across the Primary terminals of CT
If the meter deflects forward then the polarity is O.K.

Fig 2: Polarity Test Setup

Test Format For the above test are enclosed in Annexure – VIII
LARSEN & TOUBRO CONSTRUCTION PROCEDURE NO:
Power Transmission & Distribution T&C/T& C P/AIS-GIS/001

TESTING AND COMMISSIONING PROCEDURE Page 17 of 223

8.5 TAN DELTA & CAPACITANCE TEST


Aim:
To check the capacitances and tan delta value of the CT bushings and ensure that it
corresponds to the equipment data value given during the time of factory test.

Equipments Required:
The equipments required for carrying out Tan Delta Capacitance test are as follows,
i) Tan Delta Test Kit.
ii) Connecting cables.
Test Procedure:
Note: When the CT’s are provided with taps then the measurement of capacitance can be done
between the tests taps, else the capacitance should be measured from one terminal to grounded
terminal. (As per the connections shown in the diagram).
a) Connect the kit across the test terminals provided in the equipment for Tan Delta
Measurement.
b) Initially apply 2 KV and note down the readings
c) Then apply 10 KV and note down the readings
d) Compare with the test results obtained at the manufacturer test report (If Available)
For CT’s With Test Taps:

For CT’s Without Test Taps:

Fig 3: Tan Delta Measurement


Test Format For the above test are enclosed in Annexure –IX
LARSEN & TOUBRO CONSTRUCTION PROCEDURE NO:
Power Transmission & Distribution T&C/T& C P/AIS-GIS/001

TESTING AND COMMISSIONING PROCEDURE Page 18 of 223

8.6 PRIMARY INJECTION (RATIO) TEST


Aim:
To check the ratio of the primary turns to the secondary turns and compare it with the given
rated values.
Equipments Required:
The equipments required for primary injection test or ratio test are as follows,
i) Primary injection test kit / Loading Transformer.
ii) Clamp Meter.
iii) Connecting cables.
Test Procedure:
a) Connect the Primary injection kit across the primary terminals (P1, P2)
b) Initially apply 20% of rated current
c) Then Raise the current to 40%, 60% and 80%
d) Note down the corresponding Secondary current at various cores.
e) Repeat the test for all the ratios mentioned in the rating plate

Fig 4 : Typical Primary Injection Test Setup


Test Format For the above test are enclosed in Annexure – X
8.7 MAGNETIZING CURRENT CHARACTERISTIC (KNEE POINT VOLTAGE) TEST
Aim:
To prove that the CT cores do not saturate during the application of peak voltage and ensure
that the saturation of the core is avoided at knee point voltage.
Equipments required:
The following are the equipments required for performing magnetizing current characteristics,
i) High Voltage Transformer test kit.
ii) Digital Multimeter.
iii) Clamp Meter.
iv) Connecting cables.
Test Procedure:
LARSEN & TOUBRO CONSTRUCTION PROCEDURE NO:
Power Transmission & Distribution T&C/T& C P/AIS-GIS/001

TESTING AND COMMISSIONING PROCEDURE Page 19 of 223

Note: a) CT should not saturate at 110% of KVp


b) If knee point voltage is not mentioned the knee point current may be taken into
consideration
c) Magnetization of Metering core should not been done.
i) Connect the Hi-voltage Transformer across the secondary terminals of PS Class core
ii) Apply 25% of Knee point Voltage mentioned in rating plate
iii) Then Raise the voltage to 50%, 75%, 100% and 110%
iv) Note down the Magnetizing Current.
v)Repeat the test for all PS class cores.

Fig 5: Magnetization Current Measurement Setup

Fig 6: Typical Magnetization curve


Test Format For the above test are enclosed in Annexure – XI

8.8 CONTACT RESISTANCE MEASUREMENT TEST FOR CONNECTORS


Aim:
To check the CT terminals has least value of resistance which ultimately ensures the tightness
of the joints and connectors.
Equipments Required:
The equipments required for performing test are,
i) CRM test kit.
ii) Connecting leads.
Test Procedure:
LARSEN & TOUBRO CONSTRUCTION PROCEDURE NO:
Power Transmission & Distribution T&C/T& C P/AIS-GIS/001

TESTING AND COMMISSIONING PROCEDURE Page 20 of 223

a) Connect the Micro Ohm Meter leads on the connectors of CT primary terminals
b) Switch ‘ON’ the test kit & apply the current up to 100Amps
c) Take Down the Readings.
d) It should be in Micro Ohms
Test Format For the above test are enclosed in Annexure – XII

8.9 SECONDARY INJECTION TEST


Aim:
To check the values of current injected to the secondary matches approximately with the
current measured at the C&R panel terminal point, without much deviation and ensures proper supply
of current to CR panel for controlling.
Equipments required:
The equipments required for performing secondary injection test are as follows,
i) Secondary injection test kit.
ii) Clamp Meter.
iii) Connecting leads.
Test Procedure:
a) Connect the secondary injection kit across the secondary terminals
b) Apply 0.5 Amps current.
c) Measure the current across the protective relay point & Metering point in the C & R panel (or)
In BCU.
d) Repeat Test for all the cores

Fig : Secondary Injection Test Setup


Test Format For the above test are enclosed in Annexure – XIII

ANNEXURE – I
LARSEN & TOUBRO CONSTRUCTION PROCEDURE NO:
Power Transmission & Distribution T&C/T& C P/AIS-GIS/001

TESTING AND COMMISSIONING PROCEDURE Page 21 of 223

DATA OF EQUIPMENT (Rating Plate)

Make :

Type: :

Sl. No. : R-Phase: Y-Phase: B-Phase:

Year of manufacture: R-Phase: Y-Phase: B-Phase:

Feeder /Bay Name :

V. Rated data and duty:

Core Ratio Class Burden KVp Protection / Metering

Winding I

Winding II

Winding III

Winding IV

Winding V

KVp: Knee point voltage in volts

ANNEXURE – II
LARSEN & TOUBRO CONSTRUCTION PROCEDURE NO:
Power Transmission & Distribution T&C/T& C P/AIS-GIS/001

TESTING AND COMMISSIONING PROCEDURE Page 22 of 223

Post Installation check list


S. No. Description Status Remarks, Record
Yes No discrepancies, if any
1. Equipment is cleaned and free from dust /
dirt, foreign materials etc.
2. Equipment is free from all visible defects on
physical inspection
3. Check CT tank has been provided with
double earthing
4. Check that CT junction box is earthed
5. All nuts and bolts are tightened correctly as
per specified torque
6. Check tightness of terminal connector
7. All fitting as per out line general
arrangement drawing
8. Leveling and alignment of structure and base
frame checked
9. Erection completion certificate along with
list of outstanding activities reviewed
10. Any paint removed / scratched in transit has
been touched up
11. Check primary polarity of CT erected as per
relevant drawing
12. Check hermetically sealing is intact
13. Check the oil level and leakage through any
joint / secondary terminals
14. Check oil drain valve is properly closed and
locked
15. Check oil level, nitrogen pressure and oil
sampling
16. Oil level in top chamber gauge glass
17. Check nitrogen pressure at Schrader valve
18. BDV of oil sample taken from tank bottom
drain valve (Only if nitrogen pressure
measured zero)
LARSEN & TOUBRO CONSTRUCTION PROCEDURE NO:
Power Transmission & Distribution T&C/T& C P/AIS-GIS/001

TESTING AND COMMISSIONING PROCEDURE Page 23 of 223

19. All the cable identification tags provided and


all cores are provided identification ferrules
at MB
20. Check secondary cable end box is properly
fixed and ensure cable entry at the bottom
and unused holes sealed.
21. Ensure interpose cabling is completed and
check the continuity
22.. Check the IR value of secondary cables
23. Check external cabling from junction box to
relay / control panel completed
24. Ensure unused secondary cores, if any, has
been shorted
25. Check star point has been formed properly
and grounded at one end only
26. Check spark gap setting in P1 terminal
27. Check permanent pole labelling and
identification marking made
LARSEN & TOUBRO CONSTRUCTION PROCEDURE NO:
Power Transmission & Distribution T&C/T& C P/AIS-GIS/001

TESTING AND COMMISSIONING PROCEDURE Page 24 of 223

ANNEXURE – III
Insulation Resistance Measurement test

Primary to Earth/ Secondary

Core Phase

R- Phase Y- Phase B-Phase

Primary – Core – I

Primary – Core – II

Primary – Core – III


Primary – Core – IV

Primary – Core – V

Primary – Earth

Primary – Tan Delta Point


LARSEN & TOUBRO CONSTRUCTION PROCEDURE NO:
Power Transmission & Distribution T&C/T& C P/AIS-GIS/001

TESTING AND COMMISSIONING PROCEDURE Page 25 of 223

ANNEXURE – IV
Insulation Resistance Measurement test
Secondary to Earth
Permissible value for 1kV is 1Mohm.
Phase
Core
R- Phase Y- Phase B-Phase

Secondary Core I - Earth

Secondary Core II - Earth

Secondary Core III - Earth

Secondary Core IV - Earth


Secondary Core V - Earth

ANNEXURE – V
Insulation Resistance Measurement test
Between Secondary Cores
Permissible value for 400 kV > 400 M Ω and for 220 kV > 220 M Ω

Core Phase
R- Phase Y- Phase B-Phase
Core I- Core II
Core I – Core III
Core I – Core IV
Core I – Core V
Core II – Core III
Core II – Core IV
Core II – Core V
Core III – Core IV
Core III – Core IV
Core IV – Core V
LARSEN & TOUBRO CONSTRUCTION PROCEDURE NO:
Power Transmission & Distribution T&C/T& C P/AIS-GIS/001

TESTING AND COMMISSIONING PROCEDURE Page 26 of 223

ANNEXURE – VI
Continuity Test
Core Between Phase
Terminal R- Phase Y- Phase B-Phase

1S1 – 1S2
Core I

1S1 – 1S3

1S1 – 1S4

2S1 – 2S2
Core II

2S1 – 2S3

2S1 – 2S4

3S1 – 3S2
Core III

3S1 – 3S3

3S1 – 3S4

4S1 – 4S2
Core IV

4S1 – 4S3

4S1 – 4S4

5S1 – 5S2
Core V

5S1 – 5S3

5S1 – 5S4
LARSEN & TOUBRO CONSTRUCTION PROCEDURE NO:
Power Transmission & Distribution T&C/T& C P/AIS-GIS/001

TESTING AND COMMISSIONING PROCEDURE Page 27 of 223

ANNEXURE – VII
Secondary Winding Resistance Test
Secondary winding resistance (In Ohms):

Core Terminal R- Phase Y- Phase B- Phase


Factory Site Factory Site Factory Site

1S1 – 1S2
Core I
1S1 – 1S3

1S1 – 1S4

2S1 – 2S2
Core II
2S1 – 2S3

2S1 – 2S4

3S1 – 3S2
Core III
3S1 – 3S3

3S1 – 3S4

4S1 – 4S2
Core IV
4S1 – 4S3

4S1 – 4S4

5S1 – 5S2
Core V
5S1 – 5S3

5S1 – 5S4
LARSEN & TOUBRO CONSTRUCTION PROCEDURE NO:
Power Transmission & Distribution T&C/T& C P/AIS-GIS/001

TESTING AND COMMISSIONING PROCEDURE Page 28 of 223

ANNEXURE – VIII
Polarity Test
Polarity Test: (With 1.5 Volt DC supply)
Connect + ve at P1 and –ve at P2
Core Between Phase
R-Phase Y-Phase B-Phase

1S1 (+ve) 1S2 (-ve)

Core I 1S1 (+ve) 1S3 (-ve)

1S1 (+ve) 1S4 (-ve)

2S1 (+ve) 2S2 (-ve)

Core II 2S1 (+ve) 2S3 (-ve)

2S1 (+ve) 2S4 (-ve)

3S1 (+ve) 3S2 (-ve)

Core III 3S1 (+ve) 3S3 (-ve)

3S1 (+ve) 3S4 (-ve)

4S1 (+ve) 4S2 (-ve)

Core IV 4S1 (+ve) 4S3 (-ve)

4S1 (+ve) 4S4 (-ve)

5S1 (+ve) 5S2 (-ve)

Core V 5S1 (+ve) 5S3 (-ve)

5S1 (+ve) 5S4 (-ve)


LARSEN & TOUBRO CONSTRUCTION PROCEDURE NO:
Power Transmission & Distribution T&C/T& C P/AIS-GIS/001

TESTING AND COMMISSIONING PROCEDURE Page 29 of 223

ANNEXURE – IX
Tan Delta & Capacitance Test
A.

Capacitance (Measured Value)


Y-Phase B-Phase
Voltage R -Phase Remarks
Site Factory Site Factory Site Factory

5 kV

10 kV

B.
Remarks
Voltage Tan Delta (Measured Value)
Y-Phase B-Phase
R -Phase
Site Factory Site Factory Site Factory

5 kV

10 kV
LARSEN & TOUBRO CONSTRUCTION PROCEDURE NO:
Power Transmission & Distribution T&C/T& C P/AIS-GIS/001

TESTING AND COMMISSIONING PROCEDURE Page 30 of 223

ANNEXURE – X
Primary Injection Test

CORE PRIMARY CURRENT SECONDARY THEORETICAL ACTUAL % OF


S1 - S2 % ACTUAL CURRENT RATIO RATIO ERROR
CORE I 20%

(1S1 - 1S2) 40%

60%

80%

CORE II 20%

(2S1 - 2S2) 40%

60%

80%

CORE III 20%

(3S1 - 3S2) 40%

60%

80%

CORE IV 20%

(4S1 - 4S2) 40%

60%

80%

CORE V 20%

(5S1 - 5S2) 40%

60%

80%

CORE I 20%

(1S1 - 1S3) 40%

60%

80%

CORE II 20%

(2S1 - 2S3) 40%

60%

80%

CORE III 20%

(3S1 - 3S3) 40%


LARSEN & TOUBRO CONSTRUCTION PROCEDURE NO:
Power Transmission & Distribution T&C/T& C P/AIS-GIS/001

TESTING AND COMMISSIONING PROCEDURE Page 31 of 223

60%

80%

CORE IV 20%

(4S1 - 4S3) 40%

60%

80%

CORE V 20%

(5S1 - 5S3) 40%

60%

80%

CORE I 20%

(1S1-1S4) 40%

60%

80%

CORE II 20%

(2S1 - 2S4) 40%

60%

80%

CORE III 20%

(3S1 - 3S4) 40%

60%

80%

CORE IV 20%

(4S1 - 4S4) 40%

60%

80%

CORE V 20%

(5S1 - 5S4) 40%

60%

80%
LARSEN & TOUBRO CONSTRUCTION PROCEDURE NO:
Power Transmission & Distribution T&C/T& C P/AIS-GIS/001

TESTING AND COMMISSIONING PROCEDURE Page 32 of 223

ANNEXURE – XI
Magnetizing Current Characteristic (Knee Point Voltage) Test
R – Phase
Voltage Current Measurement
To be applied Actual Value Core - I Core II Core IV Core V
1S1 – 1S2 2S1 – 2S2 4S1 – 4S2 5S1 – 5S2
0.25 X KVp
0.50 X KVp
0.75 X KVp
1.00 X KVp
1.10 X KVp

Y- Phase
Voltage Current Measurement
To be applied Actual Value Core - I Core II Core IV Core V
1S1 – 1S2 2S1 – 2S2 4S1 – 4S2 5S1 – 5S2
0.25 X KVp
0.50 X KVp
0.75 X KVp
1.00 X KVp
1.10 X KVp

B-Phase
Voltage Current Measurement
To be applied Actual Value Core - I Core II Core IV Core V
1S1 – 1S2 2S1 – 2S2 4S1 – 4S2 5S1 – 5S2
0.25 X KVp
0.50 X KVp
0.75 X KVp
1.00 X KVp
1.10 X KVp
LARSEN & TOUBRO CONSTRUCTION PROCEDURE NO:
Power Transmission & Distribution T&C/T& C P/AIS-GIS/001

TESTING AND COMMISSIONING PROCEDURE Page 33 of 223

ANNEXURE – XII
Contact Resistance Measurement (For Connectors) Test

Contact Resistance R-Phase Y-Phase B-Phase


Micro
Across terminal P1 Ω
Micro
Across terminal P2 Ω
The value of contact resistance should not be more than 5 micro Ω per joint per connector

ANNEXURE – XIII
Secondary Injection Test

Core Terminal R- Phase Y- Phase B- Phase


Current Current Current Current Current Current
Injected Measured Injected Measured Injected Measured

1S1 – 1S2
Core I
1S1 – 1S3

1S1 – 1S4

2S1 – 2S2
Core II
2S1 – 2S3

2S1 – 2S4

3S1 – 3S2
Core III
3S1 – 3S3

3S1 – 3S4

4S1 – 4S2
Core IV
4S1 – 4S3
LARSEN & TOUBRO CONSTRUCTION PROCEDURE NO:
Power Transmission & Distribution T&C/T& C P/AIS-GIS/001

TESTING AND COMMISSIONING PROCEDURE Page 34 of 223

4S1 – 4S4

5S1 – 5S2
Core V
5S1 – 5S3

5S1 – 5S4

ANNEXURE – XIV
Calibration Status Table
TEST INSTRUMENT DETAILS:
Sr no Instrument description Range Calibration status
LARSEN & TOUBRO CONSTRUCTION PROCEDURE NO:
Power Transmission & Distribution T&C/T& C P/AIS-GIS/001

TESTING AND COMMISSIONING PROCEDURE Page 35 of 223

PRE COMMISSIONING TEST PROCEDURE FOR VOLTAGE TRANSFORMERS

1.0 SCOPE
LARSEN & TOUBRO CONSTRUCTION PROCEDURE NO:
Power Transmission & Distribution T&C/T& C P/AIS-GIS/001

TESTING AND COMMISSIONING PROCEDURE Page 36 of 223

This procedure covers the Pre commissioning Test for Voltage Transformers

2.0 PURPOSE
This procedure is prepared to carry out various pre- commissioning tests to be conducted in
systematic manner for Voltage Transformers to ensure the healthiness and performance of
the equipment.

3.0 PRE-REQUISITES
SYSTEM REQUIREMENTS
1. Relevant Drawings and layouts.
2. 415 V AC, 3 Ph power supply is available for Testing.
3. All Cables pertaining to Voltage transformers were laid & terminated.
4. Make sure that the equipment erected is as per approved drawings & Layouts.
5. Check the Name Plate & Rating Plate Of the equipment Erected.

4.0 REQUIREMENTS OF TESTING KITS


S.No Test Kit Range
1 Tan Delta Test Kit with test leads 0 – 12kV
2 High voltage test kit with test leads 0-10kV (AIS)
3 Variac with test leads 0 -230V
4 Contact Resistance Kit with test leads 0-2000 milliohm

5.0 REQUIREMENT OF TESTING INSTRUMENTS


1. Digital Multi meter.
2. 500 V, 5000 V Insulation Tester
3. Polarity Tester.
4. 3 Ph- A.C Supply Extension Board with MCB Protection.

6.0 HAZARDS AND PRECAUTIONS


1. Unauthorized persons should not be allowed to enter Testing Area.
2. Barricade the Testing Area With Warning Tape
3. There should not be any temporary (hooking of supply) arrangement for Testing. Proper A.C
Supply extension board should be used
4. Ensure protection MCB is provided in the circuit of AC supply used for testing
5. Ensure Proper Tools & Tackles are Available for carrying out Tests.
LARSEN & TOUBRO CONSTRUCTION PROCEDURE NO:
Power Transmission & Distribution T&C/T& C P/AIS-GIS/001

TESTING AND COMMISSIONING PROCEDURE Page 37 of 223

6. Ensure Proper PPE ( Personal Protective Equipments) are used


7. Ensure the Healthiness of the test leads (Check for any insulation Damages).
8. Competent Authority to maintain shutdown & Work permit system in existing Live Bay works.
9. Any conducting element should be carried horizontally at waist level in the area used for pre-
commissioning tests.

7.0 POST INSTALLATION CHECKS


Post installation checks should be done according to the annexure enclosed.

8.0 TESTS TO BE CONDUCTED


1. Insulation Resistance measurement Test.
2. Continuity Test
3. Secondary Winding Resistance Test.
4. Polarity Test.
5. Tan Delta & Capacitance Test.
6. Ratio Test
7. Contact Resistance Measurement Test for Connectors.
8. Secondary Injection / Annunciation Test.
8.1 INSULATION RESISTANCE MEASUREMENT TEST
Aim :
To ensure the insulation healthiness of the primary and secondary windings by measuring the
insulation resistance value.
Equipment Required:
o Insulation Tester.
o Test leads.
Test Procedure:
The Above test to be conducted at following points
e) Primary to Earth
f) Primary to Secondary
g) Secondary to Earth
h) Between Secondary Cores
Note: a) Remove the connected earthing to system involving CVT/PT under test
b) Disconnect the connected terminals of CVT/PT M. Box.
c) Permissible values for 400 kV > 400 MΩ and for 220 kV > 200 MΩ
a. Primary to earth
LARSEN & TOUBRO CONSTRUCTION PROCEDURE NO:
Power Transmission & Distribution T&C/T& C P/AIS-GIS/001

TESTING AND COMMISSIONING PROCEDURE Page 38 of 223

1) Connect the line terminal of the Meggar(5000V) to either P1 (or) P2 of the Voltage
Transformers
2) Connect the Earth terminal of the Meggar to the earth stud provided at the equipment
3) Switch on the Meggar
4) Take down the readings (It should be in Mega Ohms).

b. Primary to Secondary
1. Connect the line terminal of the Meggar(5000V) to either P1 (or) P2 of the Voltage
transformers
2. Connect the Earth terminal of the Meggar to the a (or) n of the Voltage transformers
3. Switch on the Meggar
4. Take down the readings( It should be in Mega Ohms)

c. Secondary to Earth
1. Connect the line terminal of the Meggar(500V) to either a (or) n of the Voltage transformers
2. Connect the Earth terminal of the Meggar to the earth stud provided at the equipment
3. Switch on the Meggar
4. Take down the readings( It should be in Mega Ohms)

d. Between Secondary cores


1. Connect the line terminal of the Meggar(500V) to either a (or) n of one core of the Voltage
transformers
2. Connect the Earth terminal of the Meggar(500V) to either a (or) n of the other cores of the
Voltage transformers
3. Switch on the Meggar
4. Take down the readings( It should be in Mega Ohm
Test Format For the above test are enclosed in Annexure –III, IV & V

Fig 1: Insulation Resistance Measurement

8.2 CONTINUITY TEST


LARSEN & TOUBRO CONSTRUCTION PROCEDURE NO:
Power Transmission & Distribution T&C/T& C P/AIS-GIS/001

TESTING AND COMMISSIONING PROCEDURE Page 39 of 223

Aim:
This test is done in order to ensure that the flow of power is not interrupted in between due
to damages. This test assures that the flow of power is continuous.
Equipments Required:
o Multimeter.
o Test Leads.
Test Procedure:
a) Select the Multi meter in continuity Mode.
b) Connect the Multi meter across the secondary terminals of various cores.
c) Check for the ‘Beep’ sound
Test Format For the above test is enclosed in Annexure –VI.

8.3 SECONDARY WINDING RESISTANCE TEST


Aim:
This test is mainly done in order to calculate the winding resistance value and compare it with
the factory test report and approve if the values are found satisfactory.
Equipments Required:
o Multimeter.
o Test Leads.
Test Procedure:
a) Select the Multi meter in Resistance Mode.
b) Connect the Multi meter across the secondary terminals of various cores.
c) Note down the readings
d) Compare the test results with Factory Test Report (If available)
Test Format For the above test is enclosed in Annexure –VII.
8.4 POLARITY TEST
Aim:
To find the polarity of the terminals. This ensures that the terminals are marked with correct
polarity as manufactured.
Equipments Required:
o Battery supply.
o Multimeter.
o Test Leads.
Test Procedure:
LARSEN & TOUBRO CONSTRUCTION PROCEDURE NO:
Power Transmission & Distribution T&C/T& C P/AIS-GIS/001

TESTING AND COMMISSIONING PROCEDURE Page 40 of 223

i) Connect battery + Ve to S2 (Secondary) Terminal of CVT/PT

ii) Connect battery - Ve to S1 (Secondary) Terminal of CVT/PT

iii) Connect Multi meter (Analog) + Ve to ‘P1’ (Primary) Terminal of CVT/PT

iv) Connect Multi meter (Analog) - Ve to ‘P2’ (Primary) Terminal of CVT/PT

v) Momentarily apply the D.C Voltage across the Secondary terminals of CVT

If the meter deflects forward then the polarity is O.K.


Test Format For the above test are enclosed in Annexure – VIII

Fig 2: Polarity Test

8.5 TAN DELTA & CAPACITANCE TEST


Aim:
To calculate the value of capacitance and tangent delta angle and find the values to be
satisfactory in comparison with the factory test reports.
Equipments Required:
o Tandelta test kit.
o Trolley.
o Test Leads.
Test Procedure:
a) Connect the kit across the test terminals provided in the equipment for Tan Delta
Measurement.
b) Initially apply 2 KV and note down the readings
c) Then apply 10 KV and note down the readings
d) Compare with the test results obtained at the manufacturer test report (If Available)
LARSEN & TOUBRO CONSTRUCTION PROCEDURE NO:
Power Transmission & Distribution T&C/T& C P/AIS-GIS/001

TESTING AND COMMISSIONING PROCEDURE Page 41 of 223

Test Format For the above test are enclosed in Annexure –IX

Fig 3: Tan Delta Test Setup

8.6 RATIO TEST


Aim:
To calculate the value of the turns ratio and compare it with the name plate details and
approve it, if the values are found to be satisfactory.
Equipments Required:
o Ratio test kit.
o Test Leads.
Test Procedure:
a) Connect the Ratio Test kit across the primary terminals (P1, P2)
b) Apply 2000V (For220 KV), 4000V (For 400 KV)
c) Note down the corresponding Secondary Voltage at various cores.
d) Compare the ratio with Factory Test Reports (If available)

Fig 4 : Ratio Test


Test Format For the above test are enclosed in Annexure-X

8.7 CONTACT RESISTANCE MEASUREMENT TEST FOR CONNECTORS


LARSEN & TOUBRO CONSTRUCTION PROCEDURE NO:
Power Transmission & Distribution T&C/T& C P/AIS-GIS/001

TESTING AND COMMISSIONING PROCEDURE Page 42 of 223

Aim:
To calculate the value of the contact resistances and compare it with the factory test report
and find the values to be in acceptable limits.
Equipments Required:
o Micro ohm meter.
o Test Leads.
Test Procedure:
a) Connect the Micro Ohm Meter leads on the connectors of CVT/PT primary terminals
b) Switch ‘ON’ the test kit & apply the current up to 100Amps
c) Take Down the Readings.
d) It should be in Micro Ohms
Test Format For the above test is enclosed in Annexure – XI.

8.8 SECONDARY INJECTION TEST


Aim:
To find that the continuity of supply from the secondary to the load end do not very much in
order to ensure that the protection and metering is done accurately.
Equipments Required:
o Single phase variac.
o Test Leads.
o Multimeter.
Test Procedure:
a) Connect the Variac across the secondary terminals
b) Apply 110V A.C Supply.
c) Measure the Voltage across the protective relay point & Metering point in the C & R panel
(or)
In BCU.
d) Remove the Fuses and check for the annunciations.

Fig 5 : Secondary Injection Test


Test Format For the above test are enclosed in Annexure – XII.
LARSEN & TOUBRO CONSTRUCTION PROCEDURE NO:
Power Transmission & Distribution T&C/T& C P/AIS-GIS/001

TESTING AND COMMISSIONING PROCEDURE Page 43 of 223

ANNEXURE – I

DATA OF EQUIPMENT (Rating Plate)

Make :

Type: :

Sl. No. : R-Phase: Y-Phase: B-Phase:

Year of manufacture: R-Phase: Y-Phase: B-Phase:

Feeder /Bay Name :

V. Rated data and duty:

Core Ratio Class Burden Protection / Metering

Winding I

Winding II

Winding III

ANNEXURE – II
Post Installation check list

S. No. Description Status Remarks, Record


Yes No discrepancies, if any
1. Equipment is cleaned and free from dust / dirt,
foreign materials etc.
2. Equipment is free from all visible defects on
physical inspection
3. Check CVT/PT tank has been provided with
double earthing
4. Check that CVT/PT junction box is earthed
5. All nuts and bolts are tightened correctly as per
specified torque
6. Check tightness of terminal connector
7. All fitting as per out line general arrangement
drawing
8. Leveling and alignment of structure and base
frame checked
9. Labelling and identification marking is carried out

10. Erection completion certificate along with list of


outstanding activities reviewed
LARSEN & TOUBRO CONSTRUCTION PROCEDURE NO:
Power Transmission & Distribution T&C/T& C P/AIS-GIS/001

TESTING AND COMMISSIONING PROCEDURE Page 44 of 223

11. Any paint removed / scratched in transit has been


touched up
12. Sl. No. of HV capacitor identical to the Sl. No.
mentioned on rating plate
13. Ensure brass vent plug between stacks of CVT is
removed.
14. Check the oil level and leakage through any joints
/ terminals
15. Check oil drain valve is properly closed and
locked
16. Oil level in top chamber gauge glass
17. BDV of oil sample taken from tank bottom drain
valve
18. Check secondary cable end box is properly fixed
and ensure cable entry at the bottom.
19. Ensure HF terminal of unused phases has been
earthed and no load on HF terminal bushing.
20. Check rating / healthiness of fuses at CVT MB and
CVT terminal box.
21. Check rating / healthiness of fuses at CVT MB and
CVT terminal box.
22. Check that the neutral point is earthed.
23. Check the IR value of secondary cables> 1M Ω for
outdoor cables and>10 M Ω for indoor cables.
24. Check external cabling from junction box to relay /
control panel completed
25. All the cable identification tags provided and all
cores are provided with identification ferrules at
MB

ANNEXURE – III

Insulation Resistance Measurement test

Primary to Earth/ Secondary

Core Phase
R- Phase Y- Phase B-Phase

Primary – Core – I MΩ

Primary – Core – II MΩ

Primary – Core – III MΩ

Primary – Earth MΩ
LARSEN & TOUBRO CONSTRUCTION PROCEDURE NO:
Power Transmission & Distribution T&C/T& C P/AIS-GIS/001

TESTING AND COMMISSIONING PROCEDURE Page 45 of 223

ANNEXURE – IV

Insulation Resistance Measurement test


Secondary to Earth

Permissible value for 1kV is 1 M Ω

Phase
Core
R- Phase Y- Phase B-Phase

Secondary Core I - Earth

Secondary Core II - Earth

Secondary Core III - Earth

ANNEXURE – V

Insulation Resistance Measurement test

Between Secondary Cores

Permissible value for 400 kV > 400 M Ω and for 220 kV > 220 M Ω

Core Phase
R- Phase Y- Phase B-Phase

Core I- Core II

Core I – Core III

Core II – Core III

ANNEXURE – VI

Continuity Test

Core Between Phase


Terminal R- Phase Y- Phase B-Phase
Core I 1a – 1n
Core II 2a – 2n
Core III 3a – 3n
LARSEN & TOUBRO CONSTRUCTION PROCEDURE NO:
Power Transmission & Distribution T&C/T& C P/AIS-GIS/001

TESTING AND COMMISSIONING PROCEDURE Page 46 of 223

ANNEXURE – VII

Secondary Winding Resistance Test

Secondary winding resistance (In Ohms):

Core Terminal R- Phase Y- Phase B- Phase


Factory Site Factory Site Factory Site

Core I 1a – 1n

Core II 2a – 2n

Core III 3a – 3n

ANNEXURE – VIII

Polarity Test

Polarity Test: (With 1.5 Volt DC supply)

Connect + ve at P1 and –ve at P2

Core Between Phase


R-Phase Y-Phase B-Phase

Core I 1a (+ve) 1n (-ve)

Core II 2a (+ve) 2n (-ve)

Core III 3a (+ve) 3n (-ve)


LARSEN & TOUBRO CONSTRUCTION PROCEDURE NO:
Power Transmission & Distribution T&C/T& C P/AIS-GIS/001

TESTING AND COMMISSIONING PROCEDURE Page 47 of 223

ANNEXURE – IX
Tan Delta & Capacitance Test

Capacitance (Measured Value)


Y-Phase B-Phase
Voltage Across R -Phase Remarks
Site Factory Site Factory Site Factory

2 KV C1
10KV C1
2 KV C2
10KV C2
2 KV C3
10KV C3
2 KV C1+C2+C3
10KV C1+C2+C3

B.

Tan Delta(Measured Value)


Y-Phase B-Phase
Voltage Across R -Phase Remarks
Site Factory Site Factory Site Factory

2 KV C1
10KV C1
2 KV C2
10KV C2
2 KV C3
10KV C3
2 KV C1+C2+C3
10KV C1+C2+C3

ANNEXURE – X
Ratio Test

Phas e Primary Se condary Voltage The ore tical Actual ratio % Error
Voltage Be twe e n Value ratio Factory Site
R 1a-1n
R 2a-2n
R 3a-3n
Y 1a-1n
Y 2a-2n
Y 3a-3n
B 1a-1n
B 2a-2n
B 3a-3n
LARSEN & TOUBRO CONSTRUCTION PROCEDURE NO:
Power Transmission & Distribution T&C/T& C P/AIS-GIS/001

TESTING AND COMMISSIONING PROCEDURE Page 48 of 223

ANNEXURE – XI
Contact Resistance Measurement (For Connectors) Test

Contact Resistance R-Phase Y-Phase B-Phase


Micro
Across terminal P1 Ω

The value of contact resistance should not be more than 5 micro Ω per joint per connector

ANNEXURE – XII
Secondary Injection Test

S.No. Description of the Source of initiation Window Result Remarks


test Description OK / Not
OK
A Remove all the fuse Apply 110 v AC through
in R, Y, B Phase in 3 Phase variac in the
CVT secondary CVT secondary circuit
junction box towards C & R Panels
(i) Remove R – Phase CR Panel CVT Fuse CVT Fuse failure
fuse in the control
panel
(ii) Remove Y – Phase CR Panel CVT Fuse CVT Fuse failure
fuse in the control
panel
(iii) Remove B – Phase CR Panel CVT Fuse CVT Fuse failure
fuse in the control
panel

ANNEXURE – XIII
Calibration Status Table
TEST INSTRUMENT DETAILS:
Sr no Instrument description Range Calibration status
LARSEN & TOUBRO CONSTRUCTION PROCEDURE NO:
Power Transmission & Distribution T&C/T& C P/AIS-GIS/001

TESTING AND COMMISSIONING PROCEDURE Page 49 of 223

PRE COMMISSIONING TEST PROCEDURE FOR TRANSFORMERS


LARSEN & TOUBRO CONSTRUCTION PROCEDURE NO:
Power Transmission & Distribution T&C/T& C P/AIS-GIS/001

TESTING AND COMMISSIONING PROCEDURE Page 50 of 223

1.0 SCOPE
This procedure covers the Pre commissioning Test for Transformers.

2.0 PURPOSE
This procedure is prepared to carry out various pre- commissioning tests to be conducted in
systematic manner for Transformers to ensure the healthiness and performance of the
equipment.

3.0 PRE-REQUISITES
3.1 SYSTEM REQUIREMENTS
1. Relevant Drawings and layouts.
2. 415 V AC, 3 Ph power supply is available for Testing.
3. All Cables pertaining to Transformers were laid & terminated.
4. Make sure that the equipment erected is as per approved drawings & Layouts.
5. Check the Name Plate & Rating Plate of the equipment Erected.

4.0 REQUIREMENTS OF TESTING KITS


S.No Testing Kit Range
1 Tan Delta Test kit with test leads 0-12kV
2 Primary injection test kit with test leads 0 – 2000A
3 High voltage transformer with test leads 0 -5kV
4 Contact resistance test kit with test leads 0 – 2000milliohm
5 Secondary injection test kit with test leads 0 -100A
6 Transformer winding resistance kit with test leads 0 – 100milliohm
7 Transformer ratio kit with test leads 0 – 2000 turns
8 Sweep frequency analyzer kit with test leads 1kHz – 1MHz (-90dB min)

5.0 REQUIREMENT OF TESTING INSTRUMENTS


1. Digital Multi meter.
2. 500 V, 5000 V Insulation Tester
3. Polarity Tester.
4. Clamp Meters (200mA – 2000A)
5. 3 Ph- A.C Supply Extension Board with MCB Protection.

6.0 HAZARDS AND PRECAUTIONS:


LARSEN & TOUBRO CONSTRUCTION PROCEDURE NO:
Power Transmission & Distribution T&C/T& C P/AIS-GIS/001

TESTING AND COMMISSIONING PROCEDURE Page 51 of 223

1. Unauthorized persons should not be allowed to enter Testing Area.


2. Barricade the Testing Area With Warning Tape
3. There should not be any temporary (hooking of supply) arrangement for Testing. Proper A.C
Supply extension board should be used
4. Ensure protection MCB is provided in the circuit of AC supply used for testing
5. Ensure Proper Tools & Tackles are Available for carrying out Tests.
6. Ensure Proper PPE ( Personal Protective Equipments) are used
7. Ensure the Healthiness of the test leads (Check for any insulation Damages).
8. Competent Authority to maintain shutdown & Work permit system in existing Live Bay works.
9. Any conducting element should be carried horizontally at waist level in the area used for pre-
commissioning tests.

7.0 POST INSTALLATION CHECKS


Post installation checks should be done according to the annexure enclosed.

8.0 TESTS TO BE CONDUCTED


1. Polarization Index Test (Insulation Resistance measurement Test).
2. Core Insulation Test.
3. Magnetic Balance Test.
4. Floating Neutral Point Test
5. Winding Resistance Test.
6. Turns Ratio Test.
7. Tan Delta & Capacitance Test for Bushings & Windings.
8. Vector Group Test.
9. Magnetizing Current Measurement.
10. Short Circuit Impedance measurement Test.
11. Sweep Frequency Analysis Test.(ONLY FOR 220kV AND ABOVE)
12. Pre-Commissioning Test on Bushing CT’s.
13. Contact Resistance Measurement Test for Connectors.
14. Operational Checks on OLTC.
15. Operational Checks on Protection System.
LARSEN & TOUBRO CONSTRUCTION PROCEDURE NO:
Power Transmission & Distribution T&C/T& C P/AIS-GIS/001

TESTING AND COMMISSIONING PROCEDURE Page 52 of 223

8.1 POLARIZATION INDEX TEST (INSULATION RESISTANCE MEASUREMENT TEST)


Aim:
To find the value of insulation resistance and ensure that the insulation resistance value is
within the acceptable limit.
Equipments Required:
o Insulation Tester.
o Test leads.
Test Procedure:
The Polarization Index is nothing but the Ratio of Insulation Resistance Measured at 10 Minutes
to the 1 Minute. The above test is to be conducted at following points.
a) Windings of Transformer to Earth.
b) Between HV and LV winding.
a. Windings to earth
1) Connect the line terminal of the Meggar (5000V) to winding (s) of the Transformer.
2) Connect the Earth terminal of the Meggar to the earth stud provided at the equipment.
3) Switch on the Meggar.
4) Take down the readings (It should be in Mega Ohms).

b. Between Windings
1) Connect the line terminal of the Meggar (5000V) to one winding of the Transformer.
2) Connect the Earth terminal of the Meggar to the other winding of Transformer
3) Switch on the Meggar.
4) Take down the readings (It should be in Mega Ohms).

Fig 1: Insulation Resistance Measurement Setup

Test Format For the above test are enclosed in Annexure –III

8.2 CORE INSULATION TEST


LARSEN & TOUBRO CONSTRUCTION PROCEDURE NO:
Power Transmission & Distribution T&C/T& C P/AIS-GIS/001

TESTING AND COMMISSIONING PROCEDURE Page 53 of 223

Aim:
To ensure that the insulation resistance value between the core and tank is in acceptable
limits.
Equipments Required:
Insulation Tester.
Test leads.
Test Procedure:
a) Apply 2 KV D.C between Core and Frame/Tank. Take down the IR value.
b) Apply 2 KV D.C between Frame and Core/Tank. Take down the IR value.
Test Format For the above test are enclosed in Annexure –IV

8.3 MAGNETIC BALANCE TEST


Aim:
To ensure that the transformer is balanced magnetically so that there is no net flow of
unbalance current under normal operation.
Equipments Required:
o Multimeter.
o Test leads.
Test Procedure:
a) Keep The Tap in Normal Position.
b) Apply single phase A.C supply across one phase of the windings.
c) Measure the Voltage on the other two phases of the winding.
d) Measure the Voltage on the voltage induced on the other windings.

Fig 2 : Magnetic Balance Test


Test Format For the above test are enclosed in Annexure – V
LARSEN & TOUBRO CONSTRUCTION PROCEDURE NO:
Power Transmission & Distribution T&C/T& C P/AIS-GIS/001

TESTING AND COMMISSIONING PROCEDURE Page 54 of 223

8.4 FLOATING NEUTRAL POINT TEST.


Aim:
To ensure that the voltages when applied to the winding are always balanced and there is
only negligible voltage at neutral.
Equipments Required:
o Multimeter.
o Test Leads.
Test Procedure:
a) Remove the Ground/Earth connection From Neutral Point of Transformer.
b) Apply three Phase A.C Supply across HV windings / IV windings.
c) Measure the voltage between Neutral and Ground. It should be Zero (or) Very Negligible.
Test Format For the above test are enclosed in Annexure – VI

8.5 WINDING RESISTANCE TEST


Aim:
To find the value of the winding resistance and ensure that the values are similar to the
factory test reports.
Equipments Required:
o Transformer winding resistance meter.
o Test leads.
Test Procedure:
a) Connect the kit across the one phase of the HV windings. Measure the resistance.
b) Then connect the kit across the other phase of HV windings. Measure the resistance.
c) Repeat the test for all taps provided in the transformer.
d) Connect the Kit across one Phase of the IV Windings. (only for autotransformer)
e) Connect the kit across the other phases of the IV windings.
F) Repeat the Test for LV Windings also.
Compare with the test results obtained at the manufacturer test report (If Available)
Test Format For the above test are enclosed in Annexure – VII

8.6 TURNS RATIO TEST


Aim:
LARSEN & TOUBRO CONSTRUCTION PROCEDURE NO:
Power Transmission & Distribution T&C/T& C P/AIS-GIS/001

TESTING AND COMMISSIONING PROCEDURE Page 55 of 223

To calculate the value of the turn’s ratio and compare it with the factory test reports and
ensure the correctness of the values obtained.
Equipments Required:
o Transformer turns ratio meter.
o Test leads.
Test Procedure:
a) Connect the ratio kit across the HV and IV winding of the transformer at 1st Tap.
b) Measure the turn’s ratio obtained.
c) Repeat the test at all Taps.
d) Repeat the Test between HV and LV windings also.
Compare the results obtained with actual ratios.

Fig 3: Turns Ratio Test


Test Format For the above test are enclosed in Annexure – VIII

8.7 CAPACITANCE & TAN DELATA TEST ON BUSHINGS & WINDINGS.


Aim:
To measure the capacitance and tan delta value and ensure that the values are within the
acceptable limits.
Equipments Required:
o Tan delta Test Kit
o Test Leads.
Test Procedure:
Bushings
a) Short all the bushings together. Remove earth connection from Neutral.
b) Connect HV Lead to the one bushing of Transformer & LV lead to the Test tap provided
in the bushings. This Value will be recorded as C1.
c) Connect the HV lead to the Test tap of Bushing and LV lead to the Ground. This will be
recorded as C2.
LARSEN & TOUBRO CONSTRUCTION PROCEDURE NO:
Power Transmission & Distribution T&C/T& C P/AIS-GIS/001

TESTING AND COMMISSIONING PROCEDURE Page 56 of 223

Windings
a) Connect the HV & LV test lead of the kit across the windings in one phase.
b) Repeat the test for other phases of the windings.
c) Repeat the test between windings & Earth.

Fig 4: Tan Delta Measurement


Test Format For the above test are enclosed in Annexure – IX

8.8 VECTOR GROUP TEST


Aim:
To ensure that the windings in the transformer are of same vector group as that mentioned
in the name plate.

Equipments Required:
o Multimeter.
LARSEN & TOUBRO CONSTRUCTION PROCEDURE NO:
Power Transmission & Distribution T&C/T& C P/AIS-GIS/001

TESTING AND COMMISSIONING PROCEDURE Page 57 of 223

o Test leads.
Test Procedure:
This test is to confirm the Vector group of Transformer. This more crucial in sub-station where
transformers are paralleled together.
The vector group test for Yd11 Transformer (Widely used in all sub-stations)

1B1 – N > 3B1 -N


1Y1 –N > 3Y1 –N

1R1 –N = 3R1 -N

Fig 5: Vector Group Representation


Test Format For the above test are enclosed in Annexure – X

8.9 MAGNETIZING CURRENT TEST


Aim:
To calculate the value of the magnetizing current flow in each phase and compare the value
with the factory results.
Equipments Required:
o Milliammeter.
o Test leads.
Test Procedure:
a) Apply single phase 5KV (or) 10 KV across one phase of the HV winding. Take down
Magnetizing current.
b) Repeat the test for other phases of the HV windings & other (IV & LV) windings of the
transformers.
c) The readings to be similar for all the phases of the windings.
Test Format For the above test are enclosed in Annexure – XI

8.10 SHORT CIRCUIT IMPEDENCE TEST


LARSEN & TOUBRO CONSTRUCTION PROCEDURE NO:
Power Transmission & Distribution T&C/T& C P/AIS-GIS/001

TESTING AND COMMISSIONING PROCEDURE Page 58 of 223

Aim:
To ensure that the percentage impedance given in the factory test report is similar to that
measured value.
Equipments Required:
o Multimeter.
o Clamp meter.
o Test leads.
Test Procedure:
a) Apply Single Phase voltage across one phase of HV windings. Short the IV side winding
of that phase. Measure the Current at IV side. Note down the voltage applied.
b) Apply Single Phase voltage across one phase of IV windings. Short the LV side winding
of that phase. Measure the Current at LV side. Note down the voltage applied.
c) Apply Single Phase voltage across one phase of HV windings. Short the LV side winding
of that phase. Measure the Current at LV side. Note down the voltage applied.
This Test should be done at Nominal Tap, Minimum & Maximum Tap positions

The test format for the above test are enclosed in Annexure - XII

8.11 SWEEP FREQUENCY RESPONSE ANALYSIS TEST


Aim:
Frequency response analysis (FRA) is conducted to assess the mechanical integrity of the
transformer which may get disturbed due to transportation shocks or short circuit forces experienced
in service. FRA signatures will be taken after assembly and oil filling and compared with factory
testing’s to ensure the healthiness of core/coil assembly during transportation. These signatures will
be benchmark for future reference. The FRA signatures should be analyzed in conjunction with impact
recorder readings. Report of impact recorder readings is to be obtained from manufacturer.
Equipments Required:
o SFRA Test kit.
o Test leads.
Test Procedure:
It is recommended to follow the standard procedure for the SFRA measurement as
per the Table-1. It should be done on maximum, normal and minimum tap.

Table-1
TEST TYPE TEST 3 – PHASE 1-PHASE
LARSEN & TOUBRO CONSTRUCTION PROCEDURE NO:
Power Transmission & Distribution T&C/T& C P/AIS-GIS/001

TESTING AND COMMISSIONING PROCEDURE Page 59 of 223

Test 1 H! – X1
Series winding (OC)
Test 2 H2 – X2 H1-X1
All other terminals floating
Test 3 H3 –X3
Test 4 X1 – H0X0
Common winding (OC)
Test 5 X2 – H0X0 X1 – H0X0
All other terminals floating
Test 6 X3 – H0X0
Test 7 Y1 – Y3
Tertiary winding (OC) Y1 – Y2
Test 8 Y2 – Y1
All other terminals floating (Y1 – Y0)
Test 9 Y3 – Y2
Short circuit (SC) Test 10 H1-H0X0
H1-H0X0
High (H) to Low (L) Test 11 H2-H0X0
Short (X1-H0X0)
Short (X1-X2-X3) Test 12 H3-H0X0
Short Circuit (SC) Test 13 H1-H0X0
H1-H0X0
High (H) to Tertiary (Y) Test 14 H2-H0X0
Short (Y1-Y2)
Short (Y1-Y2-Y3) Test 15 H3-H0X0
Short Circuit (SC) Test 16 X1-H0X0
X1-H0X0
Low (L) to Tertiary (Y) Test 17 X2-H0X0
Short (Y1-Y2)
Short (Y1-Y2-Y3) Test 18 X3-H0X0

8.12 TESTS ON OIL SAMPLE

Dissolved gas analysis (DGA) is a powerful diagnostic tool to detect any incipient fault
developing inside the oil-filled equipment. The oil sample is to be taken after oil filling (before
commissioning) as a benchmark and there after 24hrs of charging, 7 days, 15 days, one month
and three months after charging to monitor the gas build up if any. The oil samples are to be
sent to CIOTL/IOTL/STL for DGA and first two samples for oil parameter testing also.

The test format for the above test are enclosed in Annexure - XIII

8.13 OPERATIONAL CHECKS ON PROTECTION SYSTEM

a. Operational checks on breathers ( Conventional Silcagel or Drycol as supplied with the


transformers)
b. Visual check of MOG of Main Conservator.
c. Marshalling box & kiosk checks.
d. Valve operational checks.
1. Checks in cooling fans-rotation, speed & control (Manual/temp/load) setting checks.
2. Checks on cooling pumps-rotation, vibration/noise, oil flow direction.
e. Checks on temperature gauges (OTI/WTI-calibration and cooler control, alarm & trip setting
tests).
LARSEN & TOUBRO CONSTRUCTION PROCEDURE NO:
Power Transmission & Distribution T&C/T& C P/AIS-GIS/001

TESTING AND COMMISSIONING PROCEDURE Page 60 of 223

f. Checks on gas actuated (SPRs/PRDs/Buchholz) relays – Operational checks by simulation as


well as shorting the respective contacts as applicable.
g. Checks on tightness of terminal connectors – micro-ohm measurement of each connection.
h. Checks on transformer/Reactor protection (differential, REF, Over-current & stability tests
etc.)

8.14 OPERATIONAL CHECKS ON OLTC

Following checks should be carried out during pre-commissioning:


Before applying voltage to the transformer, the mechanical operation of tap changer and
motor drive for step by step operation to be checked as follows:
a) Manual operation: The tap changer has to be run manually by the hand crank through the
total operating cycle. In each operating position, the position indicators of motor drive and
tap changer (On TC head) show the same position.
b) Motor drive for step by step tap changing operation: Push button to be kept pressed till the
motor stops i.e. driving motor should be automatically switched off when the tap changer
has performed one switching operation.

(Note: At the time of change over selector operation (i.e. 9b to 10 & vice-versa), higher
torque is required. Tap changer end position should be checked that the same is not overrun
to avoid any failure during operation. Same can be seen through the inspection glass in the
tap changer head cover.
With the tap-changer fully assembled on the transformer the following sequence of
operations shall be performed:
a) With the transformer un-energized, one complete cycles of operations (a cycle of
operation goes from one end of the tapping range to the other, and bach again). Check
continuity of winding during this test. Ensure that the voltmeter does not deflect to Zero.
b) With the transformer un-energized, and with the auxiliary voltage reduced to 85% of its
rated valve, one complete cycle of operation.
c) With the transformer energized at rated voltage and frequency at no load, one complete
cycle of operation.

The following additional check points/guide lines for OLTC is recommended in


consultation with OLTC manufacturer to ensure the absence of problems and proper
operation:
a) Function of control switches.
LARSEN & TOUBRO CONSTRUCTION PROCEDURE NO:
Power Transmission & Distribution T&C/T& C P/AIS-GIS/001

TESTING AND COMMISSIONING PROCEDURE Page 61 of 223

b) OLTC stopping on position.


c) Fastener tightness.
d) Signs of moisture such as rusting, oxidation or free standing water and leakages.
e) Mechanical clearances as specified by manufacturer’s instruction booklet.
f) Operation and condition of tap selector, changeover selector and arcing transfer
switches.
g) Drive mechanism operation.
h) Counter operation, position indicator operation and its co-ordination with mechanism and
tap selector positions.
i) Limit switch operation.
j) Mechanical block integrity.
k) Proper operation of hand-crank and its interlock switch.
l) Physical condition of tap selector.
m) Freedom of movement of external shaft assembly.
n) Extent of arc erosion on stationary and moveable arcing contacts.
o) Inspect barrier board for tracking and cracking.
p) After filling with oil, manually crank throughout entire range.
q) Oil BDV and moisture content (PPM) to be measured and recorded (Min BDV should be
60kV and moisture content should be less than 10 PPM).

The test format for the above test are enclosed in Annexure - XIV

ANNEXURE – I
DETAILS OF EQUIPMENT

Make :

Type:

Rating :

SL No :

Voltage Ratio :

Cooling Type :

Type of Neutral Grounding :

Year of Manufacture :

Oil Quantity :
LARSEN & TOUBRO CONSTRUCTION PROCEDURE NO:
Power Transmission & Distribution T&C/T& C P/AIS-GIS/001

TESTING AND COMMISSIONING PROCEDURE Page 62 of 223

Quantity of Main Tank :


Quantity of Radiator :

Oil Make &Type :


Specify oil type inhibited/uninhibited/standard

ANNEXURE – II
Post Installation check list

S. No. Description Status Remarks, Record


Yes No discrepancies, if any
1. ICT and its auxiliaries are free from visible
defects on physical inspection.
2. All fittings as per out line general arrangement
drawings.
3. Check main tank has been provided with double
earthing.
4. Check neutral is grounded through separate
connections. Ensure metallic requirements as per
specification (e.g. Cu.) in earthing strips used.
5. Check that marshaling box, T/C driving gear,
diverter, radiator bank pump & fan motor ETC
has been earthed.
6. All nuts and bolts are tightened correctly as per
specified torque (as per manufactures
recommendation).
7. Check tightness of terminal connectors.
8. Check leveling of transformer and its accessories.
9. Erection completion certificate along with list of
outstanding activities reviewed.
10. Any paint removed/scratched in transit has been
touched up.
11. Bushings are clean and free from physical
damages.
12. Oil level is correct on all bushings.
13. Check hermetically sealing is intact in all
bushings.
14. Check oil leakage through any joints/valves etc.
15. Check oil drain valves are properly closed and
locked.
16. Check oil level in MAIN/OLTC conservator tank.
17. Check oil level at conservator matches with oil
temperature of transformer.
18. Check gear box oil level in OLTC.
19. Check OTI and WTI pockets and replenish the
oil, if required.
21. Check the color of breather silica gel (blue when
dry).
22.. Check availability of oil in the breather cup.
23. Check all rollers are locked and tack welded with
rails (wherever applicable).
LARSEN & TOUBRO CONSTRUCTION PROCEDURE NO:
Power Transmission & Distribution T&C/T& C P/AIS-GIS/001

TESTING AND COMMISSIONING PROCEDURE Page 63 of 223

24. Check bushings test tap is grounded.


25. Check no debris, loose T & P and oil strains on
and around the transformer.
26. Check that pressure relief valve is correctly
mounted.
27. Check that pressure relief valve is correctly
mounted.
28. Ensure unused secondary cores of bushing CT’s,
if any, has been shorted.
29. Check star point has been formed properly and
grounded at one end only as per scheme.
30. Check that permanent and adequate lighting
arrangements are ready.
31. Check that labeling and identification is
permanent and satisfactory.
32. Check that bushels relay is correctly mounted
with arrow pointing towards conservator.
33. Check cables are properly fixed and ensure cable
entry at the bottom.
34. Ensure all power and control cable terminals are
tightened.
35. Check all cables and ferrules are provided with
number as per cable schedule (cross feruling to be
checked).
36. Check that all cables are correctly glanded.
37. Check external cabling from junction box to
relay/control panel completed.
38. Check that air has been released from the
radiators and their HEADERS/OLTC
BUCHHOLZ RELAY/MAIN
TANK/TANK/BUSHING TURRETS ETC.
39. Check fire protection system & emulsifier system
is adequate & ready.
40. Check that CC-CL&G are shorted.
41. Check that all radiator bank valves on top and
bottom headers are open.
42. Change over operation of AC supply from
source-I to source-II checked.
43. Check the flanges of bushings & OLTC for any
crack after fixing
LARSEN & TOUBRO CONSTRUCTION PROCEDURE NO:
Power Transmission & Distribution T&C/T& C P/AIS-GIS/001

TESTING AND COMMISSIONING PROCEDURE Page 64 of 223

ANNEXURE – III
Insulation Resistance Measurement: Using _____________ Megger

Make: Range: Sl.No: Calib due date:


IR Value
Main Winding Temperature
15 Sec 60 Sec 600 Sec PI
HV/E + LV
IV/E+HV+LV
LV/E+HV+IV
HV/LV

IV/LV

HV/LV

ANNEXURE – IV
Core Insulation test

APPLY 1.0 KV DC BETWEEN CL & CC+G

INSULATION VALUE
BETWEEN CC-G
BETWEEN CL-G
BETWEEN CC-CL

RECOMMENDED VALUE > 10 Mohm

ANNEXURE – V
Magnetic Balance Test
(Using Equipment Details)
Equipment: Make: Range: Sl.No: Calib due date:

HV Side at Normal Tap

Applied Voltage Measured Voltage


1R-N 1Y-N 1B-N 1R-N 1Y-N 1B-N

IV Side at Normal Tap (only for autotransformer)

Applied Voltage Measured Voltage


2R-N 2Y-N 2B-N 2R-N 2Y-N 2B-N
LARSEN & TOUBRO CONSTRUCTION PROCEDURE NO:
Power Transmission & Distribution T&C/T& C P/AIS-GIS/001

TESTING AND COMMISSIONING PROCEDURE Page 65 of 223

LV Side at Normal Tap

Applied Voltage Measured Voltage


3R-N 3Y-N 3B-N 3R-N 3Y-N 3B-N

ANNEXURE – VI
FLOATING NEUTRAL VOLTAGE MEASUREMENT

Note: Disconnect the transformer neutral from the ground. Apply 3 Phase 415 Volts to the high
voltage winding and make the measurement in the IV winding with respect to neutral point to
ground.

PRIMARY VOLTAGE IV VOLTAGE REMARKS, IF


TAP
WINDING APPLIED WINDING MEASURED ANY

Apply 3 Phase 415Volts to the intermediate voltage winding and make the measurement in the
tertiary winding with respect to neutral and neutral point to ground.

PRIMARY VOLTAGE IV VOLTAGE REMARKS, IF


TAP
WINDING APPLIED WINDING MEASURED ANY

ANNEXURE – VII
MEASURMENT OF WINDING RESISTANCE (IN OHM)
Testing Instrument details : _______________________________
Testing Equipment Calibration Valid or not : _______________________________
Ambient temperature at the time of test : _______________________________
Temperature of oil : _______________________________
WTI reading : _______________________________
LARSEN & TOUBRO CONSTRUCTION PROCEDURE NO:
Power Transmission & Distribution T&C/T& C P/AIS-GIS/001

TESTING AND COMMISSIONING PROCEDURE Page 66 of 223

Winding Resistance (HV-N)


Resistance 75 deg C Factory Value
Tap
Remarks
Position 1Y1-
1R1-2R1 1B1-2B1 R Y B R Y B
2Y1
1
2
3
4
5
6
7
8
9b
10
11
12
13
14
15
16
17
Reverse order
Tap No
Tap No
Tap No
Tap No
Tap No
Tap No
Factory Test Report Ref No: ________________________________
B INTERMEDIATE VOLTAGE SIDE
Between Resistance Resistance at 75 deg C
Remark
Winding Site Value Factory Site
2R1-N
2Y1-N
2B1-N

C LOW VOLTAGE SIDE


Between Resistance Resistance at 75 deg C
Remark
Winding Site Value Factory Site
3R1-3B1
3Y1-3R1
3B1-3Y1

NOTE: LV winding resistance at factory measured without formation of delta. However


measurements carried out at site are after formation of delta. Hence a correction factor of 1.5 times
to be applied in site results.
LARSEN & TOUBRO CONSTRUCTION PROCEDURE NO:
Power Transmission & Distribution T&C/T& C P/AIS-GIS/001

TESTING AND COMMISSIONING PROCEDURE Page 67 of 223

ANNEXURE – VIII
VOLTAGE RATIO TEST

Testing Instrument Details : ___________________________________


Testing Equipment Calibration Valid or not : ___________________________________
Ambient temperature at the time of test : ___________________________________
Temperature at the time of test : ___________________________________

a) RATIO : HV/IV

Tap Voltage Applied Voltage Measures Ratio Factory ratio


Position 1R-N 1Y-N 1B-N 2R-N 2Y-N 2B-N R Y B R Y B

1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16

REVERSE SIDE:

Tap
Voltage Applied Voltage Measures Ratio Factory ratio
Position
Tap Posi

Tap Posi
Tap Posi

Tap Posi

Remarks if any: ___________________________________________________________

b) Ratio: HV/LV

Tap Voltage Applied Voltage Measures Ratio Factory ratio


Position 1R-N 1Y-N 1B-N 3R-3Y 3Y-3B 3R-3B R Y B R Y B
LARSEN & TOUBRO CONSTRUCTION PROCEDURE NO:
Power Transmission & Distribution T&C/T& C P/AIS-GIS/001

TESTING AND COMMISSIONING PROCEDURE Page 68 of 223

Lowest

Normal
Highest

Remarks if any: ___________________________________________________________

c) Ratio: IV/LV (only for autotransformer)

Tap Voltage Applied Voltage Measures Ratio Factory ratio


Position 2R-N 2Y-N 2B-N 3R-3Y 3Y-3B 3R-3B R Y B R Y B

Remarks if any: ___________________________________________________________

ANNEXURE – IX
TAN DELTA & CAPACITANCE MEASUREMENT OF BUSHING

Testing Instrument details : _________________________________


Testing Equipment calibration valid or not : _________________________________
Ambient temperature at the time of test : _________________________________
Temperature of Oil : _________________________________

a) High Voltage Side


Capacitance (Measured Value) Remarks
Voltage R Phase Y Phase B Phase
Site Factory Site Factory Site Factory
Measurement of C1 Capacitance
2 kV
10kV
Measurement of C2 Capacitance
1kV

Tan Delta (Measured Value) Remarks


Voltage R Phase Y Phase B Phase
Site Factory Site Factory Site Factory
Measurement of C1 Capacitance
2 kV
10kV
Measurement of C2 Capacitance
1kV
LARSEN & TOUBRO CONSTRUCTION PROCEDURE NO:
Power Transmission & Distribution T&C/T& C P/AIS-GIS/001

TESTING AND COMMISSIONING PROCEDURE Page 69 of 223

b) Intermediate Voltage Side


Capacitance (Measured Value) Remarks
Voltage R Phase Y Phase B Phase
Site Factory Site Factory Site Factory
Measurement of C1 Capacitance
2 kV
10kV
Measurement of C2 Capacitance
1kV

Tan Delta (Measured Value) Remarks


Voltage R Phase Y Phase B Phase
Site Factory Site Factory Site Factory
Measurement of C1 Capacitance
2 kV
10kV
Measurement of C2 Capacitance
1kV

c) Low Voltage Side

Capacitance (Measured Value) Remarks


Voltage R Phase Y Phase B Phase
Site Factory Site Factory Site Factory
Measurement of C1 Capacitance
2 kV
10kV
Measurement of C2 Capacitance
1kV

Tan Delta (Measured Value) Remarks


Voltage R Phase Y Phase B Phase
Site Factory Site Factory Site Factory
Measurement of C1 Capacitance
2 kV
10kV
Measurement of C2 Capacitance
1kV

Factory Test Report Ref No: _________________________________


** Note: C2 Values shall be only for record purpose.
LARSEN & TOUBRO CONSTRUCTION PROCEDURE NO:
Power Transmission & Distribution T&C/T& C P/AIS-GIS/001

TESTING AND COMMISSIONING PROCEDURE Page 70 of 223

ANNEXURE – X
VECTOR GROUP TEST & POLARITY CHECKING

Connect neutral point with earth.


Join 1R1 & 3R1 terminals.
-Apply 415V, 3-Phase supply to HV terminals.

Terminals Voltage Measured Remarks

ANNEXURE – XI
MAGNETISATION CURRENT TEST

Testing Instrument details : _________________________________


Testing Equipment calibration valid or not : _________________________________
Ambient temperature at the time of test : _________________________________
Temperature of Oil : _________________________________

a) Apply 1-Phase AC Supply on HV terminals and keep IV & LV Open

Tap Position Voltage Applied Current Measured Remarks


R-N V R-Ph m AMP
Lowest ( ) Y-N V Y-Ph m AMP
B-N V B-Ph m AMP
R-N V R-Ph m AMP
Normal ( ) Y-N V Y-Ph m AMP
B-N V B-Ph m AMP
R-N V R-Ph m AMP
Highest( ) Y-N V Y-Ph m AMP
B-N V B-Ph m AMP
LARSEN & TOUBRO CONSTRUCTION PROCEDURE NO:
Power Transmission & Distribution T&C/T& C P/AIS-GIS/001

TESTING AND COMMISSIONING PROCEDURE Page 71 of 223

b) Apply 1-Phase AC Supply on IV terminals and keep HV & LV Open

Tap Position Voltage Applied Current measured ( in LV side)


Between volts
2R-N Volts R – PH m AMP
Normal ( )
2Y-N Volts Y – PH m AMP
2B-N Volts B – PH m AMP

ANNEXURE – XII
SHORT CIRCUIT IMPEDANCE TEST
Testing Instrument details : _________________________________
Testing Equipment calibration valid or not : _________________________________
Ambient temperature at the time of test : _________________________________
Temperature of Oil : _________________________________

a. MV to LV
Tap 1U1 ( R ) 1V1 ( Y ) 1W1 ( B )
Number (IV of R Ph & N shorted, LV (IV of Y Ph & N shorted, (IV of B Ph & N shorted,
Open) LV Open) LV Open)
Voltage Current Voltage Current Voltage Current

b. IV to LV
Supply Short all 3 LV bushing, Short all 3 LV bushing, Short all 3 LV bushing, HV
HV open HV open open

c. HV to LV
Tap No: ______

Supply Short all 3 LV bushing, IV Short all 3 LV bushing, IV Short all 3 LV bushing, IV
open open open
LARSEN & TOUBRO CONSTRUCTION PROCEDURE NO:
Power Transmission & Distribution T&C/T& C P/AIS-GIS/001

TESTING AND COMMISSIONING PROCEDURE Page 72 of 223

Tap No: ______

Supply Short all 3 LV bushing, IV Short all 3 LV bushing, IV Short all 3 LV bushing, IV
open open open

ANNEXURE – XIII
DISSOLVE GAS ANALYSIS

Oil Sample Schedule


Dissolve Just 15 days 01 month 03 months
24 Hrs after 7 days after
Gases before after after after
charging charging
charging charging charging charging
Total Gas
(%)
H2
CH4
C2H4
C2H6
C2H2
CO
CO2
O2
N2

ANNEXURE – XIV
TEST ON OLTC

Status Remarks
S. No Description
OK NOT OK
1 Visual inspection of equipment
Manual operation on all taps (local) with
2 confirmation of the No. of revolutions and
locking at extreme taps.
3 Over load device of driving motor.
4 Local operation (Electrical)
5 Remote operation (Electrical)
6 Tap position indicator
Check operation with master follower
7
scheme (parallel operation)
8 Out of step relay.
LARSEN & TOUBRO CONSTRUCTION PROCEDURE NO:
Power Transmission & Distribution T&C/T& C P/AIS-GIS/001

TESTING AND COMMISSIONING PROCEDURE Page 73 of 223

9 Step by step relay


10 Limit switch
11 Winding resistance at all taps
Continuity test of winding during one
12
complete cycle of operation

ANNEXURE – XV
OPERATIONAL TEST ON OTHER EQUIPMENTS

i) Rotation direction of Pumps OK NOT OK

ii) Rotation direction of Fans OK NOT OK

Eqpmt Setting Valve Pickup Valve Single Phasing Prevention


Fan no Check
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
Pump
No
1
2
3
4

ANNEXURE – XVI
OIL CHARACTERISTICS

MOISTURE TAN DELTA RESISTIVITY INTERFACIAL


OIL B.D.V
(MAX) (MAX) 90 (MIN) OHM- TENSION AT 27 REMARKS
SAMPLE (MIN) KV
PPM deg C CM deg (MIN) N/m
LARSEN & TOUBRO CONSTRUCTION PROCEDURE NO:
Power Transmission & Distribution T&C/T& C P/AIS-GIS/001

TESTING AND COMMISSIONING PROCEDURE Page 74 of 223

ANNEXURE – XVII

Calibration Status Table


TEST INSTRUMENT DETAILS:
Sr Instrument description Range Calibration status
no
LARSEN & TOUBRO CONSTRUCTION PROCEDURE NO:
Power Transmission & Distribution T&C/T& C P/AIS-GIS/001

TESTING AND COMMISSIONING PROCEDURE Page 75 of 223

PRE COMMISSIONING TEST PROCEDURE FOR CIRCUIT BREAKERS


LARSEN & TOUBRO CONSTRUCTION PROCEDURE NO:
Power Transmission & Distribution T&C/T& C P/AIS-GIS/001

TESTING AND COMMISSIONING PROCEDURE Page 76 of 223

1.0 SCOPE
This procedure covers the Pre commissioning Test for Circuit Breakers

2.0 PURPOSE
This procedure is prepared to carry out various pre- commissioning tests to be conducted in
systematic manner for Circuit Breakers to ensure the healthiness and performance of the
equipment.

3.0 PRE-REQUISITES
SYSTEM REQUIREMENTS
1. Relevant Drawings and layouts.
2. 415 V AC, 3 Ph power supply is available for Testing.
3. All Cables pertaining to Circuit Breakers were laid & terminated.
4. Make sure that the equipment erected is as per approved drawings & Layouts.
5. Check the Name Plate & Rating Plate Of the equipment Erected.

4.0 REQUIREMENTS OF TESTING KITS


S.No Testing Kit Range
1 Contact resistance kit with test leads 0 – 2000milliohm
2 Three pole timer with test leads 0 – 99sec
3 DCRM kit with test leads 100A
4 Dew point test kit with connector and cable 20 deg C to -110 deg C

5.0 REQUIREMENT OF TESTING INSTRUMENTS


1. Digital Multi meter.
2. 500 V, 5000 V Insulation Tester
3. 3 Ph- A.C Supply Extension Board with MCB Protection.

6.0 HAZARDS AND PRECAUTIONS


1. Unauthorized persons should not be allowed to enter Testing Area.
2. Barricade the Testing Area With Warning Tape
3. There should not be any temporary (hooking of supply) arrangement for Testing. Proper A.C
supply extension board should be used
4. Ensure protection MCB is provided in the circuit of AC supply used for testing
LARSEN & TOUBRO CONSTRUCTION PROCEDURE NO:
Power Transmission & Distribution T&C/T& C P/AIS-GIS/001

TESTING AND COMMISSIONING PROCEDURE Page 77 of 223

5. Ensure Proper Tools & Tackles are Available for carrying out Tests.
6. Ensure Proper PPE ( Personal Protective Equipments) are used
7. Ensure the Healthiness of the test leads (Check for any insulation Damages).
8. Competent Authority to maintain shutdown & Work permit system in existing Live Bay works.
9. Any conducting element should be carried horizontally at waist level in the area used for pre-
commissioning tests.

7.0 POST INSTALLATION CHECKS


1. Equipment is cleaned and free from dust / dirt, foreign materials etc.
2. Equipment is free from all visible defects on physical inspection.
3. Support structures, marshaling box has been provided with double earth.
4. All nuts and bolts are tightened correctly as per specified torque.
5. Equipment erection is complete in all respect.
6. Permanent pole labeling and identification is done.
7. Leveling and alignment of structure and base frame checked.
8. Control box / marshaling kiosk is free from Any physical defects
9. Tightness of nuts bolts of terminal connectors are checked
10. Auxiliary contacts and relays have been cleaned and free from rust / damage
11. Check all the valves in the SF6 pipe line are tightened and DILO coupling are tightened.
12. Erection completion certificate along with list of outstanding activities reviewed

8.0 TESTS TO BE CONDUCTED


1. SF6 Gas Lockout / Low Alarm Test.
2. Dew Point Test
3. Insulation Resistance Measurement Test.
4. Trip Coil/Close Coil Resistance Measurement
5. Opening/Closing Time Measurement Test
6. Main Circuit Contact Resistance Measurement Test.

8.1 SF6 GAS LOCKOUT/LOW ALARM TEST


The above test can be done while filling the SF6 Gas in to the Breaker Pole
a) Select the Multi meter in Resistance Mode.
b) Connect the Multi meter across the Lock out Contact Terminal of Density Monitor.
c) The Contact should open after the lock out pressure is reached
D) Connect the Multi meter across the Low alarm Contact Terminal of Density Monitor.
LARSEN & TOUBRO CONSTRUCTION PROCEDURE NO:
Power Transmission & Distribution T&C/T& C P/AIS-GIS/001

TESTING AND COMMISSIONING PROCEDURE Page 78 of 223

e) The Contact should open after the low pressure point is reached
Test Format For the above test are enclosed in Annexure-IV

8.2 DEW POINT TEST


DEW POINT MEASUREMENT OF SF6 GAS FOR CIRCUIT BREAKER
• Dew Point is the temperature at which moisture content in SF6 gas starts condensing.
• Dew Point at rated pressure of CB: Dew Point when measured keeping regulating valve in
service at the outlet of dew point kit to allow required flow rate of gas, is called at rated
pressure of CB. Inlet valve is opened completely.
• Dew Point at atmospheric pressure: Dew Point when measured by regulating the gas flow
at the inlet of dew point kit and keeping outlet regulating valve (if provided) in fully open
condition so that flow rate of gas is maintained as required, is called at atmospheric
pressure.
TESTING PROCEDURE
a) Make the connections to the kit from CB pole ensuring that regulating valve is fully closed
At the time of connections of the Dew Point kit.

b) By regulating the flow rate of SF6 gas (0.2 liter/min to 0.5 liter/min - ref. IEC 60480), the
Value of dew point is observed till it becomes stable.

c) If the regulating valve is provided at outlet of the dew point kit then values as given in
Doc. no. for rated pressure is to be monitored.
Dew Point of SF6 gas varies with pressure at which measurement is being carried out. This
Is due to the fact that Saturation Vapour Pressure decreases with increase in Pressure of the
SF6 gas. Hence, dew point of SF6 gas at higher pressure is lower than dew point at
Atmospheric pressure Therefore, it is to be ensured that if measurement has been done at a
Pressure other than the atmospheric pressure; same is to be converted to the atmospheric
Pressure as given in the table below used at the time of commissioning for various CB
Manufacturers: Method for converting dew point at different gas pressures, is
Given/described in IEC-60480.
Sl. Make of CB Dew point at Dew point at Atmospheric
rated pressure Pressure ( Limit )
No.
1 BHEL -15̊ C -36̊C

2 M&G -15̊ C -39̊C


LARSEN & TOUBRO CONSTRUCTION PROCEDURE NO:
Power Transmission & Distribution T&C/T& C P/AIS-GIS/001

TESTING AND COMMISSIONING PROCEDURE Page 79 of 223

3 CGL -15̊ C -35̊C


4 ABB -15̊ C -35̊C
5 NGEF -15̊ C -36̊C

Test Format For the above test are enclosed in Annexure-III

8.3 IR VALUE TEST


Aim:
To find the insulation resistance value of the equipments and ensure the performance of the
equipments based on the values obtained.
Equipments Required:
o Insulation tester.
o Test leads.
Test Procedure:
The above test is to be conducted at following points.
a) Control Circuit of Breakers
b) Main Circuit of Breakers (pole)
a) Control Circuit of Breakers
i) Connect the Megger across the various points on the control circuit
ii) Switch ‘ON’ the Meggar
iii) Take down the readings
Test Format For the above test are enclosed in Annexure-V
b) Main Circuit of Breakers (pole)
i) Connect the Meggar across the Interrupter while Breaker on ‘Open’ Condition
ii) Connect the Meggar across the Pole & Earth while Breaker on ‘Close’ Condition
iii) Switch ‘ON’ the Meggar
iv) Take down the readings
Test Format For the above test are enclosed in Annexure-V

8.4 TRIP COIL / CLOSE COIL RESISTANCE MEASUREMENT TEST


Aim:
To find the value of trip and coil resistance across the respective coils and compare with the
factory approved values.
LARSEN & TOUBRO CONSTRUCTION PROCEDURE NO:
Power Transmission & Distribution T&C/T& C P/AIS-GIS/001

TESTING AND COMMISSIONING PROCEDURE Page 80 of 223

Equipments Required:
o Multimeter.
o Test Leads.
Test Procedure:
a) Select the Multi meter in Resistance Mode.
b) Connect the Multi meter across the Trip/Close coils.
c) Note down the readings
Test Format For the above test are enclosed in Annexure-VI

8.5 OPENING / CLOSING TIME MEASUREMENT TEST


Aim:
To calculate the timing of the opening and closing of the breaker contacts and ensure that
the values are within acceptable limits.
Equipments Required:
o Single / three pole timer.
o Test leads.
Test Procedure:
a) Connect the Timer across the Breaks for the Opening Time
b) Connect the Timer across the Pole for the Closing Time/ “Close-Open” Time

Fig 1 : Opening & Closing time measurement


Test Format for the above Test in Enclosed in Annexure-VI

8.6 CONTACT RESISTANCE MEASUREMENT TEST


Aim:
To calculate the value of the contact resistance and compare the value with factory report
and approve the equipment for further use.
LARSEN & TOUBRO CONSTRUCTION PROCEDURE NO:
Power Transmission & Distribution T&C/T& C P/AIS-GIS/001

TESTING AND COMMISSIONING PROCEDURE Page 81 of 223

Equipments Required:
o Contact resistance meter.
o Test leads.
Test Procedure:
i. Connect the CRM kit across the contact while Breaker in Close Condition.
ii. Switch ON the test kit.

Fig 2 : Contact Resistance measurement


Test Format for the above Test in Enclosed in Annexure-VII
LARSEN & TOUBRO CONSTRUCTION PROCEDURE NO:
Power Transmission & Distribution T&C/T& C P/AIS-GIS/001

TESTING AND COMMISSIONING PROCEDURE Page 82 of 223

ANNEXURE – I
Details of Equipment

LOA No. :

Make :

Type:

Sl. No. :

Year of manufacture:

Feeder Name :

Operating Voltage:

Rated breaking capacity:

Control Voltage:

ANNEXURE – II
Post Installation check list

S. Description Status Remarks, Record


No. Yes No discrepancies, if any
1. Equipment is cleaned and free from dust /
dirt, foreign materials etc.
2. Equipment is free from all visible defects on
physical inspection
3. Support structures, marshalling box has been
provided with double earth
4. All nuts and bolts are tightened correctly as
per specified torque
5. Equipment erection is complete in all respect
6. Permanent pole labelling and identification
is done
7. Levelling and alignment of structure and
base frame checked
8. Control box / marshalling kiosk is free from
Any physical defects
9. Tightness of nuts bolts of terminal
connectors are checked
10. Auxiliary contacts and relays have been
cleaned and free from rust / damage
11 All spare wires terminated at the terminal
blocks
12 i Check all the valves in the SF 6 pipe line
are tightened and DILO coupling are
tightened.
13. Erection completion certificate along with
list of outstanding activities reviewed
LARSEN & TOUBRO CONSTRUCTION PROCEDURE NO:
Power Transmission & Distribution T&C/T& C P/AIS-GIS/001

TESTING AND COMMISSIONING PROCEDURE Page 83 of 223

ANNEXURE – III
Dew Point Test

Sl. No. Description Measured Value


A Dew point (Min Value -15 C)
B Air content (Max 0.05% by mass)

ANNEXURE – IV
SF6 Gas Lockout/ Low Alarm Test

Phase Details Blocking Unblocking SF 6 gas


Factory Site Factory Site filled at
R - Phase Refill Alarm ……Bar at
Operation Block ……Degre
Y – Phase Refill Alarm e on …/…/
Operation Block
B – Phase Refill Alarm
Operation Block

ANNEXURE – V
Insulation Resistance Measurement test

Caution: Isolate necessary DC for trip coils and closing coil before measuring

Control Circuit

Coil details Measured value


R-Phase trip coil - I MΩ
R-Phase trip coil – II MΩ
R-Phase closing coil MΩ
Y-Phase trip coil - I MΩ
Y-Phase trip coil – II MΩ
Y-Phase closing coil MΩ
B-Phase trip coil - I MΩ
B-Phase trip coil – II MΩ
B-Phase closing coil MΩ

Main Circuit
Breaker in Open Condition
Across Inteerupters Measured Value
R-Phase MΩ
Y-Phase MΩ
B-Phase MΩ

Breaker in Closed Condition


Between Measured Value
R-Phase and Earth MΩ
Y-Phase and Earth MΩ
LARSEN & TOUBRO CONSTRUCTION PROCEDURE NO:
Power Transmission & Distribution T&C/T& C P/AIS-GIS/001

TESTING AND COMMISSIONING PROCEDURE Page 84 of 223

B-Phase and Earth MΩ

ANNEXURE – VI
Operating Time Measurement Test

Phase Break Close Trip Close trip using Pole


Trip – I Trip – II Trip – I Trip - discrepancy
II clear time
R-Phase Main Break - I
contact
R-Phase PIR
R-Phase Main Break - II
contact
R-Phase PIR
Y-Phase Main Break - I
contact
Y-Phase PIR
Y-Phase Main Break - II
contact
Y-Phase PIR
B-Phase Main Break - I
contact
B-Phase PIR
B-Phase Main Break - II
contact
B-Phase PIR

ANNEXURE – VII
Contact Resistance Measurement Test

Sl. Phase Across each pole Across interrupter 1 Across interrupter 2


No. Factory Site Factory Site Factory Site
R
Y
B

Pre-Commissioning Checks For Hydraulic Operating System


Accumulator

R-Phase Y-Phase B-Phase


Make
Sl. No.
Type
Year of manufacture

Pump details

Make Volt
Sl. No. Amp.
Type HP/kW
LARSEN & TOUBRO CONSTRUCTION PROCEDURE NO:
Power Transmission & Distribution T&C/T& C P/AIS-GIS/001

TESTING AND COMMISSIONING PROCEDURE Page 85 of 223

Year of manufacture Oil setting

Details of relay / contractors used : Schematic Drawing No…………….

Circuit reference Make Sl. No. Type NO + NC


Oil pressure monitor
Closing lockout
Auto reclosing lockout
General lockout
Anti pumping contractor
Pole discrepancy timer
Auxiliary
Power contractor
Others

Operations check:

Date of filling hydraulic oil


Type of Hydraulic oil
Aero shell fluid 4
Other (Type…………….)
Venting of hydraulic system is done
(i) Pump
(ii) Pilot valve
(iii) Accumulator
(iv) Hydraulic mechanism

Pressurising hydraulic system

Factory Site Test


Test value Value
Pre filling pressure of N2 in accumulator (Bar / deg ….bar at ….bar at
C) …….deg …….deg
C C
Pump running time for charging hydraulic system Min
from initial pressure to working pressure
Checking safety valve (Open / close) Bar
Hydraulic pressure drop for 1 hour
Breaker ON position Bar
Breaker OFF position Bar
Oil pressure monitor
Pump ON/OFF Bar
Pump running time Sec
Auto reclosing lockout (Oil)
Pressure contact…… make / Break Bar
Factory Site Test
Test value Value
Closing lockout (Oil)
Pressure contact…… make / Break Bar
General lockout (Oil)
Pressure contact…… make / Break Bar
Checking anti pumping contactor
LARSEN & TOUBRO CONSTRUCTION PROCEDURE NO:
Power Transmission & Distribution T&C/T& C P/AIS-GIS/001

TESTING AND COMMISSIONING PROCEDURE Page 86 of 223

Pressure contact…… make / Break Bar


Checking loss of nitrogen
Pressure contact…… make / Break Bar
Factory test report ref. No.

Oil pressure drop during operations and pump running time in seconds

Factory Test Value Site Test Value


(i) Pressure before operation Bar
Pressure after closing operation Bar
Pump running time Sec

(ii) Pressure before operation Bar


Pressure after opening operation Bar
Pump running time Sec

(iii) Pressure before operation Bar


Pressure after close / open operation Bar
Pump running time Sec

(iv) Pressure before operation Bar


Pressure after O-C-O operation Bar
Pump running time Sec

Pre-Commissioning Checks for Pneumatic Operating System

Operating system details:

R - Phase Y - Phase B - Phase


Air receiver No.
Control block No.
Pneumatic drive No.
Magnetic ventile No.

Motor details:

Make Volt
Sl. No. Amp.
Type HP / kW
Year of manufacture Setting (Thermal
overload)

ICU details:

Make
Sl. No.
Type
Discharge
Capacity
LARSEN & TOUBRO CONSTRUCTION PROCEDURE NO:
Power Transmission & Distribution T&C/T& C P/AIS-GIS/001

TESTING AND COMMISSIONING PROCEDURE Page 87 of 223

Year of manufacture

Details of relays / contactors used: Schematic drawing No.:………………………..

Circuit reference Make Sl. No. Type NO + NC


Air pressure monitor
Closing lockout
Auto reclosing lockout
General lockout
Pole discrepancy timer
Auxiliary
Power contactor in ICU
Others

Pressure switch setting:

Circuit Reference Factory setting Site setting Make Remarks


Block Unblock Block Unblock
Tripping circuit - I
Tripping circuit - II
Closing circuit
Auto reclosing circuit
Low / High pressure
alarm circuit
ICU auto setting
ICU safety valve
operations

Pressure drop during operation: (In bar)

S. No. Description Factory setting value Site setting value


A Tripping through TC-
B Tripping through TC-II
C Closing circuit
D Close – Open operation
E Open – close – open operation

Number of operation from local:


Tank pressure ………. Bar

Breaker initially close:

Factory Test O-C ] Please keep pneumatic valve


Site Test O-C closed in these operation

Breaker initially open:


LARSEN & TOUBRO CONSTRUCTION PROCEDURE NO:
Power Transmission & Distribution T&C/T& C P/AIS-GIS/001

TESTING AND COMMISSIONING PROCEDURE Page 88 of 223

Factory Test C-O ] Please keep pneumatic valve


Site Test C-O closed in these operation

Leakage check:
Air pressure drop in 24 hours:

Breaker ON drop in pressure: Bar


Breaker OFF, drop in pressure: Bar

Pre-Commissioning Checks for Spring Charge Operating System

Spring operating system:

Motor details:

Make Volt
Sl. No. Amp.
Type HP / kW
Year of manufacture Setting (Thermal
overload)

Spring operating time:

Time taken by the spring to charge fully after closing of breaker


Details R – Phase Y – Phase B – Phase
Factory Site Factory Site Factory Site
Charging Time

SF6 Gas Lekage Checks

A Initial filling of SF 6 gas at ….deg C Bar


B Drop in SF 6 gas pressure in 24 hours Bar
C Final SF 6 gas pressure at …… deg C after all testing Bar

Circuitry/Operational Checks

S. No. Circuit reference Circuitary checks Operational checks


Local Remote Local Remote
A Tripping through TC – I
B Tripping through TC – II
C Closing circuit
D Anti hunting feature (Close
open operation)
E Pole discrepancy feature
F Breaker position indication
G Heater in switch cubicle
H Heater in control cubicle
I Illumination in switch cubicle
LARSEN & TOUBRO CONSTRUCTION PROCEDURE NO:
Power Transmission & Distribution T&C/T& C P/AIS-GIS/001

TESTING AND COMMISSIONING PROCEDURE Page 89 of 223

J Illumination in control cubicle

Breaker operation counter reading

Counter Type Sl. No. Phase Reading Date


A
Electrical B
Mechanical C

Check for annunciation in control room as per the following formats and record the
reading
S. Description of test Source of Window description Result Remarks
No. initiation
A Switch off the Dc switch in Control cubicle Source I / II DC fail /
control cubicle DC switch ON / AC fail
OFF
B Switch off the AC switch in Control cubicle Source I / II DC fail /
control cubicle AC switch ON / AC fail
OFF
C Short the alarm contacts of SF 6 Density Monitor SF 6 gas density low
gas density monitor (R-Phase)

D Short the alarm contacts of SF 6 Density Monitor SF 6 gas density low


gas density monitor (Y-Phase)
E Short the alarm contacts of SF 6 Density Monitor SF 6 gas density low
gas density monitor (B-Phase)
F Remove the cable connected to Density Monitor Operation / closing
Density monitor (R-Phase) lockout
G Remove the cable connected to Density Monitor Operation / closing
Density monitor (Y-Phase) lockout
H Remove the cable connected to Density Monitor Operation / closing
Density monitor (B-Phase) lockout
I Give tripping command to R-Ph Pole discrepancy Breaker pole
only and check the operation of relay at breaker discrepancy
pole discrepancy relay cubicle
J Give tripping command to Y-Ph Pole discrepancy Breaker pole
only and check the operation of relay at breaker discrepancy
pole discrepancy relay cubicle
K Give tripping command to B-Ph Pole discrepancy Breaker pole
only and check the operation of relay at breaker discrepancy
pole discrepancy relay cubicle
L Check other alarms as per plant
circuit diagram
M Close the breaker and trip Protective relay Breaker auto trip
through protection which are as per scheme
applicable
i) Main – I Breaker auto trip
ii) Main – II Breaker auto trip
iii) Over Voltage Breaker auto trip
LARSEN & TOUBRO CONSTRUCTION PROCEDURE NO:
Power Transmission & Distribution T&C/T& C P/AIS-GIS/001

TESTING AND COMMISSIONING PROCEDURE Page 90 of 223

iv) LBB Breaker auto trip


v) Bus bar Breaker auto trip
vi) Differential Breaker auto trip
vii) Carrier inter tripping Breaker auto trip
viii) Back up O/C & E/F Breaker auto trip
ix) Restricted earth fault Breaker auto trip
S. Description of test Source of Window description Result Remarks
No. initiation
x) Over fluxing Breaker auto trip
xi) OTI trip Breaker auto trip
xii) WTI trip Breaker auto trip
xiii) Buchholz trip Breaker auto trip
xiv) PRD Breaker auto trip
xv) TEE differential Breaker auto trip

Calibration Status Table


TEST INSTRUMENT DETAILS:
Sr Instrument description Range Calibration status
no
LARSEN & TOUBRO CONSTRUCTION PROCEDURE NO:
Power Transmission & Distribution T&C/T& C P/AIS-GIS/001

TESTING AND COMMISSIONING PROCEDURE Page 91 of 223

PRE COMMISSIONING TEST PROCEDURE FOR ISOLATORS


LARSEN & TOUBRO CONSTRUCTION PROCEDURE NO:
Power Transmission & Distribution T&C/T& C P/AIS-GIS/001

TESTING AND COMMISSIONING PROCEDURE Page 92 of 223

1.0 SCOPE
This procedure covers the Testing for Isolators.

2.0 PURPOSE
This procedure is prepared to carry out various pre- commissioning tests to be conducted in
systematic manner for Isolators to ensure the healthiness and performance of the equipment.

3.0 PRE-REQUISITES
SYSTEM REQUIREMENTS
1. Relevant Drawings and layouts.
2. 415 V AC, 3 Ph power supply is available for Testing.
3. All Cables pertaining to Isolators were laid & terminated.
4. Make sure that the equipment erected is as per approved drawings & Layouts.
5. Check the Name Plate & Rating Plate Of the equipment Erected.

4.0 REQUIREMENTS OF TESTING KITS

S.No Testing Kit Range


1 Contact Resistance kit with test leads 0 – 2000milliohm

5.0 REQUIREMENT OF TESTING INSTRUMENTS


1. Digital Multi meter.
2. 500 V, 5000 V Insulation Tester
3. Clamp Meter
4. 3 Ph- A.C Supply Extension Board with MCB Protection.

6.0 HAZARDS AND PRECAUTIONS


1. Unauthorized persons should not be allowed to enter Testing Area.
2. Barricade the Testing Area With Warning Tape
3. There should not be any temporary (hooking of supply) arrangement for Testing. Proper A.C
Supply extension board should be used
4. Ensure protection MCB is provided in the circuit of AC supply used for testing
5. Ensure Proper Tools & Tackles are Available for carrying out Tests.
LARSEN & TOUBRO CONSTRUCTION PROCEDURE NO:
Power Transmission & Distribution T&C/T& C P/AIS-GIS/001

TESTING AND COMMISSIONING PROCEDURE Page 93 of 223

6. Ensure Proper PPE ( Personal Protective Equipments) are used


7. Ensure the Healthiness of the test leads (Check for any insulation Damages).
8. Competent Authority to maintain shutdown & Work permit system in existing Live Bay works.
9. Any conducting element should be carried horizontally at waist level in the area used for pre-
commissioning tests.

7.0 POST INSTALLATION CHECKS


Post installation checks should be done according to the annexure enclosed.

8.0 TESTS & CHECKS TO BE CONDUCTED


1. Insulation Resistance Measurement Test.
2. Contact Resistance Measurement.
3. Motor Operation Current Measurement Checks
4. Opening/Closing Time Measurement Checks
5. Operational & Lockout Checks.

8.1 IR VALUE TEST


Aim:
To find the insulation resistance value of the equipments and ensure the performance of the
equipments based on the values obtained.
Equipments Required:
o Insulation tester.
o Test leads.
Test Procedure:
The above test is to be conducted at following points.
a) Motor Windings(Main Switch & Earth Switch) of Isolators
b) Main Circuit of Isolators (Fixed & Moving Contacts)
a) Across Motor Windings (using 500V Meggar)
i) Connect the Meggar across the motor Winding & Earth
ii) Switch ‘ON’ the Meggar
iii) Take down the readings
Test Format For the above test are enclosed in Annexure
b) Main Circuit of Isolators (Fixed & Moving Contacts)
i) Connect the Meggar across the Contacts & Earth while Isolator on ‘Open’ Condition
ii) Connect the Meggar across the Main Circuit & Earth while Isolator on ‘Close’ Condition
LARSEN & TOUBRO CONSTRUCTION PROCEDURE NO:
Power Transmission & Distribution T&C/T& C P/AIS-GIS/001

TESTING AND COMMISSIONING PROCEDURE Page 94 of 223

iii) Switch ‘ON’ the Meggar


iv) Take down the readings
Test Format For the above test are enclosed in Annexure – III

8.2 CONTACT RESISTANCE MEASUREMENT TEST


Aim:
To calculate the value of the contact resistance and compare the value with the factory
reports and approve the equipment for further use.
Equipments Required:
o Contact resistance meter.
o Test leads.
Test Procedure:
i. Connect the CRM kit across the Moving & Fixed Contacts of Isolators while Isolator in Close
Condition.
ii. Switch ON the CRM kit. Note down the reading.
iii. Connect the CRM kit across the Connectors of Isolators while Isolator in Open condition
iv. Switch ON the CRM kit. Note down the reading.
Test Format For the above test are enclosed in Annexure-IV
The various checks need to be conducted for Isolators & Formats for this are furnished in this
Procedure
LARSEN & TOUBRO CONSTRUCTION PROCEDURE NO:
Power Transmission & Distribution T&C/T& C P/AIS-GIS/001

TESTING AND COMMISSIONING PROCEDURE Page 95 of 223

ANNEXURE – I

Details of Equipment

LOA No. :

Make :

Type: :

Sl. No. :

Year of manufacture:

Feeder Name :

Operating Voltage:

Rated Current :

Control Voltage :

ANNEXURE – II
Post Installation check list

S. Description Status Remarks, Record


No. Yes No discrepancies, if any
1. Equipment is cleaned and free from dust /
dirt, foreign materials etc.
2. Equipment is free from all visible defects on
physical inspection
3. Support structure, marshalling box has been
provided with two earthing points
4. All nuts and bolts are tightened correctly as
per specified torque
5. Equipment erection is complete in all respect
as per instruction manual (Attach remaining
activities, if any)
6. Labelling and identification marking is
carried out
7. Levelling and alignment of structure and
base frame is checked
8. Control box / marshalling box is free from
any physical damage
9. Tightness of nut bolts of terminal
connectors are checked
10. Auxiliary contacts and relays have been
cleaned and free from rust / damage
11. Corona rings are provided and properly
fixed
LARSEN & TOUBRO CONSTRUCTION PROCEDURE NO:
Power Transmission & Distribution T&C/T& C P/AIS-GIS/001

TESTING AND COMMISSIONING PROCEDURE Page 96 of 223

12. Cable termination and tightness checked and


unused holes sealed
13. External cabling completed in all respect.
14. All the cable identification tags provided and
all cores are provided with identification
ferrules at MB
15. All moving parts lubricated
16. Alignment of isolator already made and
locking bolt provided, if any
17. Freeness of manual operation is O.K.
18. Greasing has been made on the main
contacts according to the manufacture’s
instruction
19. Functional checking of auxiliary contacts for
indications and interlocks

20. Erection completion certificate along with


list of outstanding activities reviewed
21. All spare wires are terminated at the
terminal box.
22. Earth switch connected to earth through
braided wires
23.. Ensure interpole cabling is completed and
check the continuity

ANNEXURE – III
IR VALUE TEST
Insulation resistance value of motor winding :

(Using a 500 volt megger measure resistance between the winding of motor and earth)
Isolator MB:

Between Phase
R- Phase Y- Phase B-Phase
Winding to earth MΩ

Ground Switch MB:


Between Phase
R- Phase Y- Phase B-Phase
Winding to earth MΩ

Insulation resistance test:

A. Isolator close condition


Between Phase
R- Phase Y- Phase B-Phase
Moving Contact to ground
Fixed contact 1 to ground
Fixed contact 2 to ground
LARSEN & TOUBRO CONSTRUCTION PROCEDURE NO:
Power Transmission & Distribution T&C/T& C P/AIS-GIS/001

TESTING AND COMMISSIONING PROCEDURE Page 97 of 223

B. Isolator open condition`


Between Phase
R- Phase Y- Phase B-Phase
Moving Contact to ground
Fixed contact 1 to ground
Fixed contact 2 to ground

ANNEXURE – IV
Contact Resistance Measurement Test

PHASE
ACROSS
R PHASE Y PHASE B PHASE
CONNECTOR(MALE SIDE) MICRO OHM
CONNECTOR (FEMALE SIDE) MICRO OHM
MAIN CONTACT(Male&female) MICRO OHM

Various Operational Checks to be conducted on Isolators

Motor details:
Isolator Ground switch
R-Phase Y-Phase B-Phase R-Phase Y-Phase B-Phase
Make
Sl. No.
Type
Volt
Amp.
HP/ kW
Year of
manufacture
Overload setting

Motor Operation Current Measurement

Operate the Isolator & Record the Current

R PHASE Y PHASE B PHASE


EQUIPMENT OPERATION FACTORY SITE FACTORY SITE FACTORY SITE
CLOSE in Amps
Isolator
OPEN in Amps
CLOSE in Amps
Earth Switch
OPEN in Amps
LARSEN & TOUBRO CONSTRUCTION PROCEDURE NO:
Power Transmission & Distribution T&C/T& C P/AIS-GIS/001

TESTING AND COMMISSIONING PROCEDURE Page 98 of 223

MEASUREMENT OF OPERATING TIME

PHASE (Vaules in Sec)


OPERATION
EQUIPMENT R PHASE Y PHASE B PHASE
OPENING
TIME
Isolator
CLOSING
TIME
OPENING
TIME
Earth switch
CLOSING
TIME
AUXILLARY CONTACTS CHECKING

ISOLATOR OPERATION TIME (Sec)


EQUIPMENT OPERATION R Y B
CLOSE 'NO'
CLOSE 'NC'
Isolator
OPEN 'NO'
OPEN 'NC'
CLOSE 'NO'
CLOSE'NC'
Earth switch
OPEN 'NO'
OPEN 'NC'

OPERATION ON UNDER VOLATGE CONDITION (VALUES IN DC VOLTS) :

EQUIIPMENT CONDITION COIL R Y B


CLOSING
PICK UP
VOLTAGE OPENING
INTERLOCK
Isolator
CLOSING
DROP
VOLTAGE OPENING
INTERLOCK
CLOSING
PICK UP
VOLTAGE OPENING
INTERLOCK
Earth switch
CLOSING
DROP
VOLTAGE OPENING
INTERLOCK

OPERATION OF ISOLATOR FROM LOCAL / REMOTE

CONTROL PANEL
OPERATION
EQUIPMANT LOCAL REMOTE
CLOSE
Isolator
OPEN
CLOSE
Earthswitch
OPEN
LARSEN & TOUBRO CONSTRUCTION PROCEDURE NO:
Power Transmission & Distribution T&C/T& C P/AIS-GIS/001

TESTING AND COMMISSIONING PROCEDURE Page 99 of 223

Checking of interlocks

Typical circuit

52
89A 89B

89AE 89BE

Typical Local / Remote Operational Checks

Interlock Condition Initiation Result Remark


object Equipment Location Close /
Open
Local / Remote Local / Remote Isolator 89A Local Close
operation switch in the control Open
control box in Remote Close
local control Open*
89A Opened
89B Opened
52 Opened
Local / Remote Isolator 89A Remote Close
switch in the control Open
control box in Local Close
remote control Open*
89A Opened
89B Opened
52 Opened
Local / Remote Isolator 89B Local Close
switch in the control Open
control box in Remote Close
local control Open*
89A Opened
89B Opened
52 Opened
Local / Remote Isolator 89B Remote Close
switch in the control Open
control box in Local Close
remote control Open*
89A Opened
89B Opened
52 Opened
89B closed Isolator 89B Local Open
89A Opened
52 Open
Ground switch Local / remote Ground Local Close
LARSEN & TOUBRO CONSTRUCTION PROCEDURE NO:
Power Transmission & Distribution T&C/T& C P/AIS-GIS/001

TESTING AND COMMISSIONING PROCEDURE Page 100 of 223

operation switch position in switch 89AE Open


control box in Ground Local Close
local switch 89BE Open
89A opened
89B opened
52 Opened
Interlock 89A Opened 89AE Local Close
between ground 89B Closed
switch and 52 Opened
isolator 89A Closed 89BE Local Close
89B Opened
52 Opened
89A Closed 89AE Local Close
89B NA
52 NA
89A NA 89BE Local Close
89B Closed
52 NA
Interlocking 89A Opened 89B Local Close
between 89AE Closed Remote Close
isolators 52 NA
89B Opened 89A Local Close
89BE Closed Remote Close
52 NA
Interlocking 89A Opened 89A Local Close
between breaker 89B Opened Remote Close
and isolator 52 Closed 89B Local Close
Remote Close
89A Closed 52 Local Close
89B Opened Remote Close
52 Opened
89A Opened 52 Local Close
89B Closed Remote Close
52 Opened
89A Closed 89A Local Open
89B Closed Remote Open
52 Closed
89A Closed 89B Local Open
89B Closed Remote Open
52 Closed

Normal 89A Closed 52 Local Close


operation 89B Closed Open
52 Opened
89A Closed 52 Remote Close
89B Closed Open
52 Opened
LARSEN & TOUBRO CONSTRUCTION PROCEDURE NO:
Power Transmission & Distribution T&C/T& C P/AIS-GIS/001

TESTING AND COMMISSIONING PROCEDURE Page 101 of 223

Calibration Status Table


TEST INSTRUMENT DETAILS:
Sr Instrument description Range Calibration status
no
LARSEN & TOUBRO CONSTRUCTION PROCEDURE NO:
Power Transmission & Distribution T&C/T& C P/AIS-GIS/001

TESTING AND COMMISSIONING PROCEDURE Page 102 of 223

PRE COMMISSIONING TEST PROCEDURE FOR WAVE TRAP


LARSEN & TOUBRO CONSTRUCTION PROCEDURE NO:
Power Transmission & Distribution T&C/T& C P/AIS-GIS/001

TESTING AND COMMISSIONING PROCEDURE Page 103 of 223

1.0 SCOPE
This procedure covers the Pre commissioning Test for Isolators

2.0 PURPOSE
This procedure is prepared to carry out various pre- commissioning tests to be conducted in
systematic manner for Isolators to ensure the healthiness and performance of the equipment.

3.0 PRE-REQUISITES
SYSTEM REQUIREMENTS
1. Relevant Drawings and layouts.
2. 415 V AC, 3 Ph power supply is available for Testing.
3. Make sure that the equipment erected is as per approved drawings & Layouts.
4. Check the Name Plate & Rating Plate Of the equipment Erected.

4.0 REQUIREMENTS OF TESTING KITS


S.No Testing Kit Range
1 Contact Resistance kit with test leads 0 – 2000milliohm

5.0 REQUIREMENT OF TESTING INSTRUMENTS


1. Digital Multi meter.
2. 500 V, 5000 V Insulation Tester`
3. Clamp Meter
4. 3 Ph- A.C Supply Extension Board with MCB Protection.

6.0 HAZARDS AND PRECAUTIONS


1. Unauthorized persons should not be allowed to enter Testing Area.
2. Barricade the Testing Area With Warning Tape
3. There should not be any temporary (hooking of supply) arrangement for Testing. Proper A.C
Supply extension board should be used
4. Ensure protection MCB is provided in the circuit of AC supply used for testing
5. Ensure Proper Tools & Tackles are Available for carrying out Tests.
6. Ensure Proper PPE ( Personal Protective Equipments) are used
7. Ensure the Healthiness of the test leads (Check for any insulation Damages).
8. Competent Authority to maintain shutdown & Work permit system in existing Live Bay works.
LARSEN & TOUBRO CONSTRUCTION PROCEDURE NO:
Power Transmission & Distribution T&C/T& C P/AIS-GIS/001

TESTING AND COMMISSIONING PROCEDURE Page 104 of 223

9. Any conducting element should be carried horizontally at waist level in the area used for pre-
commissioning tests.

7.0 POST INSTALLATION CHECKS


Post installation checks should be done according to the annexure enclosed.

8.0 TESTS & CHECKS TO BE CONDUCTED


1. Insulation Resistance Measurement Test.
2. Contact Resistance Measurement.

8.1 IR VALUE TEST


Aim:
To find the value of the insulation resistance across various terminals and find that the values
are found acceptable.
Equipments Required:
o Insulation Tester.
o Test Leads.
Test Procedure:
The above test is to be conducted at following points.
a) Across the upper Terminals of Wave Trap & Earth
b) Across LA of Wave trap & Earth.
a) Across Upper Terminal & Earth
i) Connect the Meggar across the upper Terminals & Earth
ii) Switch ‘ON’ the Meggar
iii) Take down the readings
Test Format For the above test are enclosed in Annexure – III

b) Across LA of Wave trap & Earth.


i) Connect the Meggar across the LA of Wave Trap & Earth
ii) Switch ‘ON’ the Meggar
iii) Take down the readings
Test Format For the above test are enclosed in Annexure -III
LARSEN & TOUBRO CONSTRUCTION PROCEDURE NO:
Power Transmission & Distribution T&C/T& C P/AIS-GIS/001

TESTING AND COMMISSIONING PROCEDURE Page 105 of 223

8.2 CONTACT RESISTANCE MEASUREMENT TEST


Aim:
To find the value of the contact resistance of the terminals and find that the values are within
acceptable limits.
Equipments Required:
o Contact Resistance Test kit.
o Test Leads.
Test Procedure:
i. Connect the CRM kit across the Terminal Connectors of Wave Trap.
ii. Switch ON the CRM test kti.
iii. Note down the reading.

Test Format For the above test are enclosed in Annexure-IV


LARSEN & TOUBRO CONSTRUCTION PROCEDURE NO:
Power Transmission & Distribution T&C/T& C P/AIS-GIS/001

TESTING AND COMMISSIONING PROCEDURE Page 106 of 223

ANNEXURE – I
Details of Equipment

LOA No. :

Make :

Type: :

Sl. No. : R-Phase: Y-Phase: B-Phase:

Year of manufacture: R-Pahse: Y-Phase: B-Phase:

Feeder Name:

Rating :

Voltage Rating:
mH Rating :
Current rating:
Bandwidth:

ANNEXURE – II
Post Installation check list

S. No. Description Status Remarks, Record


Yes No discrepancies, if any
1. Equipment is cleaned and free from dust /
dirt, foreign materials etc.
2. Equipment is free from all visible defects on
physical inspection
3. Support structure has been provided with
double earth
4. All nuts and bolts are tightened correctly as
per specified torque
5. Permanent Labelling and identification is
done.
6. Levelling and alignment of structure and
base frame is checked
7. All insulators are free from any physical
defect
8. Tightness of nuts bolts of terminal
connectors are checked
9. Erection completion certificate along with
list of outstanding activities reviewed
10. Check that the tuning unit and arrestor are
properly tightened and free from any
damage.
LARSEN & TOUBRO CONSTRUCTION PROCEDURE NO:
Power Transmission & Distribution T&C/T& C P/AIS-GIS/001

TESTING AND COMMISSIONING PROCEDURE Page 107 of 223

ANNEXURE – III
IR VALUE TEST
Insulation resistance measurement:

S. Between Megger Phase Permissible


No. R- Phase Y-Phase B-Phase Value
1. Upper terminal and 5000V 1000 M Ω
earth
2. LA of the wave trap 500V 1MΩ

ANNEXURE – IV

Contact Resistance Measurement Test

Sl. No. Across Phase


R- Phase Y- Phase B-Phase
1 Upper terminal
2 Bottom terminal

ANNEXURE – V

Calibration Status Table


TEST INSTRUMENT DETAILS:
Sr Instrument description Range Calibration status
no
LARSEN & TOUBRO CONSTRUCTION PROCEDURE NO:
Power Transmission & Distribution T&C/T& C P/AIS-GIS/001

TESTING AND COMMISSIONING PROCEDURE Page 108 of 223

PRE COMMISSIONING TEST PROCEDURE FOR LIGHTNING ARRESTORS /


SURGE ARRESTORS
LARSEN & TOUBRO CONSTRUCTION PROCEDURE NO:
Power Transmission & Distribution T&C/T& C P/AIS-GIS/001

TESTING AND COMMISSIONING PROCEDURE Page 109 of 223

1.0 SCOPE
This procedure covers the Pre commissioning Test for Lightning Arrestors / Surge
arrestors.

2.0 PURPOSE
This procedure is prepared to carry out various pre- commissioning tests to be conducted in
systematic manner for Lightning arrestors / Surge arrestors to ensure the healthiness and
performance of the equipment.

3.0 PRE-REQUISITES
SYSTEM REQUIREMENTS
1. Relevant Drawings and layouts.
2. 415 V AC, 3 Ph power supply is available for Testing.
3. Make sure that the equipment erected is as per approved drawings & Layouts.
4. Check the Name Plate & Rating Plate Of the equipment Erected.

4.0 REQUIREMENTS OF TESTING KITS


S.No Testing Kit Range
1 Third harmonic leakage kit with test leads 0 – 10mA

5.0 REQUIREMENT OF TESTING INSTRUMENTS


1. Digital Multi meter.
2. 5000 V Insulation Tester`
3. Clamp Meter
4. 3 Ph- A.C Supply Extension Board with MCB Protection.
6.0 HAZARDS AND PRECAUTIONS
1. Unauthorized persons should not be allowed to enter Testing Area.
2. Barricade the Testing Area With Warning Tape
3. There should not be any temporary (hooking of supply) arrangement for Testing. Proper A.C
Supply extension board should be used
4. Ensure protection MCB is provided in the circuit of AC supply used for testing
5. Ensure Proper Tools & Tackles are Available for carrying out Tests.
6. Ensure Proper PPE ( Personal Protective Equipments) are used
7. Ensure the Healthiness of the test leads (Check for any insulation Damages).
LARSEN & TOUBRO CONSTRUCTION PROCEDURE NO:
Power Transmission & Distribution T&C/T& C P/AIS-GIS/001

TESTING AND COMMISSIONING PROCEDURE Page 110 of 223

8. Competent Authority to maintain shutdown & Work permit system in existing Live Bay works.
9. Any conducting element should be carried horizontally at waist level in the area used for pre-
commissioning tests.

7.0 POST INSTALLATION CHECKS


Post installation checks should be done according to the annexure enclosed.

8.0 TESTS & CHECKS TO BE CONDUCTED


1. Insulation Resistance Measurement Test.
2. Third Harmonic Resistance Leakage Current Measurement Test.
3. Surge Counter Reading Checks.

8.1 IR VALUE TEST


Aim:
This test is done in order to find out that the value of the insulation resistance is found within
acceptable limits.
Equipments Required:
o Insulation Tester.
o Test Leads.
Test Procedure:
The above test is to be conducted at following points.
• Between Various stacks & Earth
i) Connect the Meggar across Various Stacks & Earth
ii) Switch ‘ON’ the Meggar
iii) Take down the readings

Fig 1: Insulation Resistance Test


Test Format For the above test are enclosed in Annexure- III
LARSEN & TOUBRO CONSTRUCTION PROCEDURE NO:
Power Transmission & Distribution T&C/T& C P/AIS-GIS/001

TESTING AND COMMISSIONING PROCEDURE Page 111 of 223

8.2 THIRD HARMONIC RESISTANCE LEAKAGE CURRENT MEASUREMENT TEST


Aim:
This test is done to calculate the value of third harmonic leakage current across the stack and
find that the value is found within the acceptable limits.
Equipments Required:
• Third harmonic leakage detector.
• Test leads.
Test Procedure:
a. Make the connections as per the diagram given below (Fig.18)
b. The kit should be properly earthed.
c. Clamp On type CT should be placed above the surge monitor to pick up the total leakage
Current.
d. Carryout the measurements as per standard procedure supplied by the test kit
Manufacturer.
e. Note down the system voltage and ambient temperature along with the test current value.
f. Avoid measurement during monsoon.

Fig 2 : Third Harmonic Current Measurement

EVALUATION OF TEST RESULTS

A. ZnO Surge Arrester continuously conducts a small leakage current (Fig.19). The resistive
Component of this leakage current may increase with time due to different stresses causing
Ageing and finally cause arrester failure.
LARSEN & TOUBRO CONSTRUCTION PROCEDURE NO:
Power Transmission & Distribution T&C/T& C P/AIS-GIS/001

TESTING AND COMMISSIONING PROCEDURE Page 112 of 223

B. If Harmonics are present in the system voltage, it affects the value of measured third
Harmonic current. Compensating device provided to be used to nullify the effect. The value
Of Third Harmonic Resistive current shall be less than 30 μA

Test Format For the above test are enclosed in Annexure- IV

8.3 SURGE COUNTER OPERATION CHECK


Aim:
To calculate the value of surge counter according to the surges applied and compare that the
operation of the surge counter is found acceptable.
Equipments Required:
o Single phase supply with variac.
o Counter.
Test Procedure:
a. Note initial Reading of the counter
b. Give single phase supply (ph lead) through a MCB to the surge counter.
c. Counter operates on each pulse given.
d. Note the final counter reading
LARSEN & TOUBRO CONSTRUCTION PROCEDURE NO:
Power Transmission & Distribution T&C/T& C P/AIS-GIS/001

TESTING AND COMMISSIONING PROCEDURE Page 113 of 223

ANNEXURE – I
DETAILS OF EQUIPMENT:
LOA No. :

Make :

Type: :

Sl. No. : R-Phase: Y-Phase: B-Phase:

Year of manufacture: R-Pahse: Y-Phase: B-Phase:

Feeder Name:

Voltage Rating :

ANNEXURE – II
Post Installation check list
S. Description Status Remarks, Record
No. Yes No discrepancies, if any
1. Equipment is cleaned and free from dust /
dirt, foreign materials etc.
2. Equipment is free from all visible defects on
physical inspection
3. Support structure and surge counter has been
provided with double earth
4. All nuts and bolts are tightened correctly as
per specified torque
5. Equipment erection is complete in all respect
6. Permanent Labelling and identification is
done
7. Levelling and alignment of structure and
base frame is checked
8. All insulators and surge counter are free
from any physical defect
9. Tightness of nuts bolts of terminal
connectors are checked
10. Erection completion certificate along with
list of outstanding activities reviewed
11. Check one end of surge counter is connected
to the bottom of LA stack and one end of
surge counter has been earthed
12. The direction of the exhaust vent ports away
from the protected equipment and other
arrester poles
13. Clearance from the arrester to earthed
objects and from the arrester pole to another
arrester pole maintained as per outline
drawing and all erection has been done as
per drawing issued by Engg. Deptt.
LARSEN & TOUBRO CONSTRUCTION PROCEDURE NO:
Power Transmission & Distribution T&C/T& C P/AIS-GIS/001

TESTING AND COMMISSIONING PROCEDURE Page 114 of 223

ANNEXURE – III
IR VALUE TEST

Insulation resistance measurement using 5 kV Megger: (min. >1000M Ω )

Sl. No. Between Phase


R- Phase Y- Phase B-Phase
1 1st stack and Earth MΩ
2 2nd stack and Earth MΩ
3 3rd stack and Earth MΩ
4 4th stack and Earth MΩ
5 5th stack and Earth MΩ
6 6th stack and Earth MΩ

ANNEXURE – IV

THIRD HARMONIC RESISTANCE LEKAGE CURRENT MEASUREMENT TEST

Sl. No. Leakage Phase


current in mA R- Phase Y- Phase B-Phase
1 IR
2 IC

Surge counter reading:

Sl. No. Reading Phase


R-Phase Y-Phase B-Phase

1 Counter Reading

Annexure-V
CALIBRATION STATUS TABLE
TEST INSTRUMENT DETAILS:
Sr Instrument description Range Calibration status
no
LARSEN & TOUBRO CONSTRUCTION PROCEDURE NO:
Power Transmission & Distribution T&C/T& C P/AIS-GIS/001

TESTING AND COMMISSIONING PROCEDURE Page 115 of 223

PRE COMMISSIONING TEST PROCEDURE FOR HV CABLES


LARSEN & TOUBRO CONSTRUCTION PROCEDURE NO:
Power Transmission & Distribution T&C/T& C P/AIS-GIS/001

TESTING AND COMMISSIONING PROCEDURE Page 116 of 223

1.0 SCOPE
This procedure covers the Pre commissioning Test for Power Cables

2.0 PURPOSE
This procedure is prepared to carry out various pre- commissioning tests to be conducted in
systematic manner for power cables to ensure the healthiness and performance of the cables.

3.0 PRE-REQUISITES
SYSTEM REQUIREMENTS
1. Relevant Drawings and layouts.
2. 415 V AC, 3 Ph power supply is available for Testing.
3. Make sure that the cable is laid as per approved drawings & Layouts.
4. Check the rating of the cable laid.

4.0 REQUIREMENTS OF TESTING KITS


S.No Testing Kit Range
1 High voltage test kit 0 – 70kV

5.0 REQUIREMENT OF TESTING INSTRUMENTS


1. Digital Multi meter.
2. 5000 V Insulation Tester`
3. Clamp Meter
4. 3 Ph- A.C Supply Extension Board with MCB Protection.
6.0 HAZARDS AND PRECAUTIONS
1. Unauthorized persons should not be allowed to enter Testing Area.
2. Barricade the Testing Area With Warning Tape
3. There should not be any temporary (hooking of supply) arrangement for Testing. Proper A.C
Supply extension board should be used
4. Ensure protection MCB is provided in the circuit of AC supply used for testing
5. Ensure Proper Tools & Tackles are Available for carrying out Tests.
6. Ensure Proper PPE ( Personal Protective Equipments) are used
7. Ensure the Healthiness of the test leads (Check for any insulation Damages).
8. Competent Authority to maintain shutdown & Work permit system in existing Live Bay works.
LARSEN & TOUBRO CONSTRUCTION PROCEDURE NO:
Power Transmission & Distribution T&C/T& C P/AIS-GIS/001

TESTING AND COMMISSIONING PROCEDURE Page 117 of 223

9. Any conducting element should be carried horizontally at waist level in the area used for pre-
commissioning tests.

7.0 POST INSTALLATION CHECKS


1. Check for the proper termination of cable.
2. Ensure that all straight through joints were made and cable is ready for testing.
3. Support structures, cable armours, link boxes have been provided with double earth.
4. Cable Termination is free from moisture & Dust.
5. Erection completion certificate along with list of outstanding activities reviewed.

8.0 TESTS & CHECKS TO BE CONDUCTED


1. Insulation Resistance Measurement Test.
2. High Voltage Test.

8.1 IR VALUE TEST


Aim:
To find the value of insulation resistance of the cable, and ensure that the value is in
acceptable limit.
Equipments Required:
o Insulation tester.
o Test leads.
Test Procedure:
i) Connect the Meggar across conductor & Earth
ii) Switch ‘ON’ the Meggar
iii) Take down the readings
iv) Repeat the test for other phases of the cable

FIG 1: INSULATION RESISTANCE MEASUREMENT


Test Format For the above test are enclosed in Annexure- III
LARSEN & TOUBRO CONSTRUCTION PROCEDURE NO:
Power Transmission & Distribution T&C/T& C P/AIS-GIS/001

TESTING AND COMMISSIONING PROCEDURE Page 118 of 223

8.2 HIGH VOLTAGE TEST


Aim:
To ensure that the power cables are withstanding the high voltage and to spot out minute
defects in cables and approve the performance of the cables under operation.
Equipments Required
o High voltage test kit.
o Test leads.
Test Procedure:
i) Connect the Hi-Pot test kit across the conductor and cable armour
ii) Connect the other conductors (other phases) and connect it to the earth
iii) Switch “on” the kit for 15 Minutes.
iv) Repeat the test for other phases of the cable
Take down the leakage current reading
LARSEN & TOUBRO CONSTRUCTION PROCEDURE NO:
Power Transmission & Distribution T&C/T& C P/AIS-GIS/001

TESTING AND COMMISSIONING PROCEDURE Page 119 of 223

ANNEXURE – I

Details of Cable

LOA No. :

Make :

Type: :

Feeder Name:

Voltage Rating :

ANNEXURE – II
Post Installation check list

S. Description Status Remarks, Record


No. Yes No discrepancies, if any
1. Check for the proper termination of
cable.
2. Ensure that all straight through joints
were made and cable is ready for testing
3. Support structures, cable armours, link
boxes have been provided with double
earth.
4. Cable Termination is free from moisture
& Dust.
5. Erection completion certificate along
with list of outstanding activities
reviewed.
LARSEN & TOUBRO CONSTRUCTION PROCEDURE NO:
Power Transmission & Distribution T&C/T& C P/AIS-GIS/001

TESTING AND COMMISSIONING PROCEDURE Page 120 of 223

ANNEXURE – III

IR VALUE TEST
Voltage grade of cable Voltage rating of IR tester
1.1Kv 500v
3.3Kv 1000v
6.6Kv 1000v
11Kv 1000v
22Kv 2.5Kv *
33Kv 2.5Kv *
33 Kv & Above 5 Kv *

*Motorized Meggar should be used for long feeders

Insulation resistance measurement

Sl. No. Between Phase


R- Phase Y- Phase B-Phase
1 Conductor & Earth

ANNEXURE – IV

HIGH VOLTAGE TEST

Rated voltage of Test Voltage Test Voltage Duration in Minutes


cable. Between Conductor Between Conductor
KV & Armor & Conductor
KV KV
0.6/1.1 3 3 15
1.9/3.3 5 9 15
3.3/3.3 9 9 15
3.8/6.6 10.5 18 15
6.6/6.6 18 18 15
6.35/11 18 30 15
11/11 30 30 15
12.7/22 37.5 - 15
19/33 60 - 15

Sl No Between Leakage Current Remarks


Y & B Phases &
1 R Phase & Earth
Earthed
R & B Phases &
2 Y Phase & Earth
Earthed
R & Y Phases &
3 B Phase & Earth
Earthed
LARSEN & TOUBRO CONSTRUCTION PROCEDURE NO:
Power Transmission & Distribution T&C/T& C P/AIS-GIS/001

TESTING AND COMMISSIONING PROCEDURE Page 121 of 223

Note:

The cable cores must be discharged on completion of DC high voltage test and the cable should be
Earthed until it is put into service.

DC test for old cable is 1.5 times rated voltage or less depending on the life of cables. But the test
Voltage should not be less than the rated voltage.

Frequent high voltage test must not be carried out on the cable, which will reduce the life of the
Cable.

During high voltage test all other electrical equipments related to the cable installation such as
Switches, Instrument Transformers, Bus-bar etc., must be earthed and clearance should be
maintained from the other equipment and framework to prevent flashover.

Annexure-V

Calibration Status Table


TEST INSTRUMENT DETAILS:
Sr Instrument description Range Calibration status
no
LARSEN & TOUBRO CONSTRUCTION PROCEDURE NO:
Power Transmission & Distribution T&C/T& C P/AIS-GIS/001

TESTING AND COMMISSIONING PROCEDURE Page 122 of 223

PRE COMMISSIONING TEST PROCEDURE FOR EHV CABLES


LARSEN & TOUBRO CONSTRUCTION PROCEDURE NO:
Power Transmission & Distribution T&C/T& C P/AIS-GIS/001

TESTING AND COMMISSIONING PROCEDURE Page 123 of 223

1.0 SCOPE
This procedure covers the Pre commissioning Test for EHV Cables as per IEC 62067 &
SEC- COA standards.

2.0 PURPOSE
This procedure is prepared to carry out various pre- commissioning tests to be conducted in
systematic manner for EHV Cables to find its Healthiness

3.0 PRE-REQUISITES
SYSTEM REQUIREMENTS
1. Relevant Drawings and layouts.
2. 415 V AC, 3 Ph power supply is available for Testing.
3. Make sure that the equipment erected is as per approved drawings & Layouts.
4. Check the Rating Of the Cables Erected.

4.0 REQUIREMENTS OF TESTING KITS


S.No Testing Kit Range
1 D.C Sheath kit 10kV

5.0 REQUIREMENT OF TESTING INSTRUMENTS


1. 500 V, 5000 V Insulation Tester`
2. Clamp Meter.
3. 3 Ph- A.C Supply Extension Board with MCB Protection.

6.0 HAZARDS AND PRECAUTIONS


1. Unauthorized persons should not be allowed to enter Testing Area.
2. Barricade the Testing Area With Warning Tape
3. There should not be any temporary (hooking of supply) arrangement for Testing. Proper A.C
Supply extension board should be used
4. Ensure protection MCB is provided in the circuit of AC supply used for testing
5. Ensure Proper Tools & Tackles are Available for carrying out Tests.
6. Ensure Proper PPE ( Personal Protective Equipments) are used
7. Ensure the Healthiness of the test leads (Check for any insulation Damages).
8. Competent Authority to maintain shutdown & Work permit system in existing Live Bay works.
LARSEN & TOUBRO CONSTRUCTION PROCEDURE NO:
Power Transmission & Distribution T&C/T& C P/AIS-GIS/001

TESTING AND COMMISSIONING PROCEDURE Page 124 of 223

9. Any conducting element should be carried horizontally at waist level in the area used for pre-
commissioning tests.
10. Both the ends of the cable require human supervision.

7.0 POST INSTALLATION CHECKS


Post installation checks should be done according to the annexure enclosed.
8.0 TESTS & CHECKS TO BE CONDUCTED
1. Insulation Resistance Measurement Test.
2. Phase checking test.
3. DC Sheath test 10KV.
4. VLF Test.
5. High voltage AC test.
6. Power loss measurement.

8.1 INSULATION RESISTANCE MEASUREMENT TEST


Aim:
To find the value of insulation resistance of the cable, and ensure that the value is in
acceptable limit.
Equipments Required:
o Insulation tester.
o Test leads.
Test Procedure:
The above test is conducted at following points,
a) Across conductor and sheath
a)Across conductor and sheath:
i) Connect line terminal of the meggar(0 – 5KV) to the conductor of the cable under test.
ii) Connect the sheath to the earth terminal of the meggar. Also earth all other cables
(conductor and sheath) of three phase cables.
iii) Switch ON the meggar.
iv) Note down the readings in Annuxure-III.
LARSEN & TOUBRO CONSTRUCTION PROCEDURE NO:
Power Transmission & Distribution T&C/T& C P/AIS-GIS/001

TESTING AND COMMISSIONING PROCEDURE Page 125 of 223

Fig 1 : INSULATION RESISTANCE TEST SETUP

8.2 PHASING VERIFICATION TEST


Aim:
This test is done in order to ensure that the cables are in exact same phase, so that there is
no fault during operation.
Equipments Required:
o Insulation Tester.
o Test leads.
Test Procedure:
The phase verification test is carried out by the following steps,
i)Connect one end of the cable to line terminal of meggar(0-5KV).
ii)Connect the other end of the cable and earth terminal of meggar to the ground.
iii)Keep all the other phases OPEN.
iv)Switch on the Meggar.
v)Note down the results in the Annuxure-IV.

FIG 2: PHASE VERIFICATION SETUP


LARSEN & TOUBRO CONSTRUCTION PROCEDURE NO:
Power Transmission & Distribution T&C/T& C P/AIS-GIS/001

TESTING AND COMMISSIONING PROCEDURE Page 126 of 223

8.3 DC SHEATH TEST


Aim:
This test is done in order to ensure that the leakage current flow due to the application of DC
high voltage is well within acceptable limits.
Equipments Required:
o High voltage DC test kit.
o Test leads.
Test Procedure:
The DC Sheath test is conducted by the following way,
i)The sheath of the other phases not under test is earthed.
ii)Connect the metallic sheath of the cable to line terminal of the test kit.
iii)Connect the earth terminal of the kit to ground. [Connect the negative terminal to the
graphite coated portion if the cable is not covered with soil or buried in ground or else connect the
negative to ground if the cable is fully buried].
iv)Switch on the test kit and apply voltage and note down readings as per the Annexure-V.
v)On completion of the test discharge the cable fully and note down the discharge time.

Fig 3: DC Sheath test setup

8.4 VERY LOW FREQUENCY TEST (VLF)


Aim:
This test is done in order to ensure that the insulation of the cable remains same after
passing rated voltage capacity which ultimately determines the performance of the EHV cables.
Equipments Required:
o VLF test kit / High voltage test kit.
o Test leads.
Test Procedure:
The VLF test must be conducted before conducting high voltage test / No load test.
i)The connections are given as per the diagram below for the test.
LARSEN & TOUBRO CONSTRUCTION PROCEDURE NO:
Power Transmission & Distribution T&C/T& C P/AIS-GIS/001

TESTING AND COMMISSIONING PROCEDURE Page 127 of 223

Fig 4 : VLF Test


ii)Apply 60kV at 0.1HZ for a duration of 15 minutes.
iii)The test report for the same is given in Annexure-VI.

8.5 HIGH VOLTAGE AC TEST


Aim:
To ensure that the power cables are withstanding the high voltage and to spot out minute
defects in cables and approve the performance of the cables under operation.
Equipments Required
o High voltage test kit.
o Test leads.
Test Procedure:
The high voltage AC test is conducted by the following way,’
i)Apply the rated system voltage to the cable.
ii) Apply the voltage for 24 hours .
iii)Observe the cable system throughout.

8.6 POWER LOSS MEASUREMENT


Aim:
To measure the power loss of EHV cables and to ensure that the losses are within permissible
limits.
Equipments Required:
Power analyzer.
Energy meter.
Test leads.
Test Procedure:
Connect the power analyzer voltage points across PT secondary circuit of sending end.
LARSEN & TOUBRO CONSTRUCTION PROCEDURE NO:
Power Transmission & Distribution T&C/T& C P/AIS-GIS/001

TESTING AND COMMISSIONING PROCEDURE Page 128 of 223

Connect the current points of the power analyzer to the CT secondary circuit of the sending
end cable.
Switch ON the supply and note down the readings according to Annexure – VII.
The sending end parameters are noted down.
Connect the power analyzer voltage points across PT secondary circuit of receiving end cable.
Connect the current points of the power analyzer to the CT secondary circuit of the receiving
end cable.
Switch ON the supply and note down the readings according to Annexure – VII.
The receiving end parameters are also noted down.
Now the power loss can be calculated as per Annexure – VII.
LARSEN & TOUBRO CONSTRUCTION PROCEDURE NO:
Power Transmission & Distribution T&C/T& C P/AIS-GIS/001

TESTING AND COMMISSIONING PROCEDURE Page 129 of 223

ANNEXURE-I
CABLE DETAILS
DATE OF TEST :

PROJECT :

CABLE TYPE USED :

CABLE LENGTH :

AMBIENT TEMPERATURE :

HUMIDITY :
ANNEXURE – II
POST INSTALLATION CHECK LIST

S. Description Status Remarks, Record


No. Yes No discrepancies, if any
1. Check for the proper termination of
cable.
2. Ensure that all straight through joints
were made and cable is ready for testing
3. Support structures, cable armours, link
boxes have been provided with double
earth.
4. Cable Termination is free from moisture
& Dust.
5. Erection completion certificate along
with list of outstanding activities
reviewed.
LARSEN & TOUBRO CONSTRUCTION PROCEDURE NO:
Power Transmission & Distribution T&C/T& C P/AIS-GIS/001

TESTING AND COMMISSIONING PROCEDURE Page 130 of 223

ANNEXURE –III
INSULATION RESISTANCE MEASUREMENT

Apply ______KV for a duration of _______ minutes.

Sl No Between RESISTENCE in ohm Remarks


Y & B Phases &
1 R Phase & Earth
Earthed
R & B Phases &
2 Y Phase & Earth
Earthed
R & Y Phases &
3 B Phase & Earth
Earthed

ANNEXURE-IV
PHASE VERIFICATION TEST
Sl No Phase Remarks Test Result
R-Earthed ; Y & B -
1 R Phase
Unearthed
Y-Earthed ; R & B -
2 Y Phase
Unearthed
B-Earthed ; Y & R -
3 B Phase
Unearthed

ANNEXURE –V
DC SHEATH TEST
Voltage Applied : …………………KV
Duration : …………………..sec

Sl No Phase Leakage Current in Remarks Test Result


mA
Y & B Phases &
1 R Phase
Earthed
R & B Phases &
2 Y Phase
Earthed
R & Y Phases &
3 B Phase
Earthed
LARSEN & TOUBRO CONSTRUCTION PROCEDURE NO:
Power Transmission & Distribution T&C/T& C P/AIS-GIS/001

TESTING AND COMMISSIONING PROCEDURE Page 131 of 223

ANNEXURE – VI
VLF TEST
Tested from ________________________________at 60KV AC with VLF testing equipment

Resistance – (megohms)

Before AC HV Test After AC HV Test 60KV AC at 0.1


(MΩ) (MΩ) cycles per sec.

Red to Earth

Yellow to Earth

Blue to Earth

ANNEXURE – VII
POWER LOSS MEASUREMENT
Sending End Receiving End Power Loss
Parameter R- Y- B- R- Y- B- R- Y- B-
Phase Phase Phase Phase Phase Phase Phase Phase Phase
Current, A
Voltage, V
Power
Factor
Active
Power,
Watt

ANNEXURE-VIII
CALIBRATION STATUS TABLE
TEST INSTRUMENT DETAILS:
Sr Instrument description Range Calibration status
no
LARSEN & TOUBRO CONSTRUCTION PROCEDURE NO:
Power Transmission & Distribution T&C/T& C P/AIS-GIS/001

TESTING AND COMMISSIONING PROCEDURE Page 132 of 223

PRE COMMISSIONING TEST PROCEDURE FOR SWITCH GEAR


LARSEN & TOUBRO CONSTRUCTION PROCEDURE NO:
Power Transmission & Distribution T&C/T& C P/AIS-GIS/001

TESTING AND COMMISSIONING PROCEDURE Page 133 of 223

1.0 SCOPE
This procedure covers the Pre commissioning Test for Switchgears

2.0 PURPOSE
This procedure is prepared to carry out various pre- commissioning tests to be conducted in
systematic manner for Switchgears to ensure the healthiness and performance of the
Switchgear.

3.0 PRE-REQUISITES
3.1 SYSTEM REQUIREMENTS
1. Relevant Drawings and layouts.
2. 415 V AC, 3 Ph power supply is available for Testing.
3. All Cables pertaining to switch gear were laid & terminated.
4. Make sure that the Switchgear erected is as per approved drawings & Layouts.
5. Check the Name Plate & Rating Plate Of the Switchgear.

4.0 REQUIREMENTS OF TESTING KITS


S.No Testing Kit Range
1 Contact resistance kit with test leads 0 – 2000milliohm
2 Secondary injection kit with test leads 0 – 100A
3 Three pole timer with test leads 0 – 99sec
4 Primary injection test kit with test leads 0 – 2000A
5 High voltage transformer with test kit 0 – 5kV

5.0 REQUIREMENT OF TESTING INSTRUMENTS


1. Digital Multi meter.
2. 500 V, 1000 V Insulation Tester
3. Milli amp meter
4. 3 Ph- A.C Supply Extension Board with MCB Protection.

6.0 HAZARDS AND PRECAUTIONS


1. Unauthorized persons should not be allowed to enter Testing Area.
2. Barricade the Testing Area With Warning Tape
LARSEN & TOUBRO CONSTRUCTION PROCEDURE NO:
Power Transmission & Distribution T&C/T& C P/AIS-GIS/001

TESTING AND COMMISSIONING PROCEDURE Page 134 of 223

3. There should not be any temporary (hooking of supply) arrangement for Testing. Proper A.C
Supply extension board should be used
4. Ensure protection MCB is provided in the circuit of AC supply used for testing
5. Ensure Proper Tools & Tackles are Available for carrying out Tests.
6. Ensure Proper PPE ( Personal Protective Switchgears) are used
7. Ensure the Healthiness of the test leads (Check for any insulation Damages).
8. Competent Authority to maintain shutdown & Work permit system in existing Live Bay works.
9. Any conducting element should be carried horizontally at waist level in the area used for pre-
commissioning tests.

7.0 POST INSTALLATION CHECKS


Post installation checks should be done according to the annexure enclosed.

8.0 TESTS TO BE CONDUCTED


1. Insulation Resistance Measurement Test.
2. Trip Coil/Close Coil Resistance Measurement of CB.
3. Opening/Closing Time Measurement Testof CB.
4. Main Circuit Contact Resistance Measurement Test for CB.
5. Pre commissioning Tests for Switchgear CT
6. Pre commissioning Tests for Switchgear PT.
7. Insulation resistance test for bus bar.
8. Contact resistance test for bus bar.
9. High voltage test for bus bar.

8.1 IR VALUE TEST


Aim:
To find the insulation resistance value of the equipments and ensure the performance of the
equipments based on the values obtained.
Equipments Required:
o Insulation tester.
o Test leads.
Test Procedure:
The above test is to be conducted at following points.
c) Control Circuit of switchgear Breakers
d) Main Circuit of Switchgear Breakers (pole)
LARSEN & TOUBRO CONSTRUCTION PROCEDURE NO:
Power Transmission & Distribution T&C/T& C P/AIS-GIS/001

TESTING AND COMMISSIONING PROCEDURE Page 135 of 223

a) Control Circuit of Breakers


i) Connect The Meggar across the various points on the control circuit after removing control coils
from circuit.
ii) Switch ‘ON’ the Meggar
iii) Take down the readings
Test Format For the above test are enclosed in Annexure-III

b) Main Circuit of Breakers (pole)


i) Connect the Meggar across the Pole & Earth while Breaker on ‘Close’ Condition
ii) Switch ‘ON’ the Meggar
iii) Take down the readings

8.2 TRIP COIL / CLOSE COIL RESISTANCE MEASUREMENT TEST


Aim:
To find the value of trip and coil resistance across the respective coils and compare with the
factory approved values.
Equipments Required:
Multimeter.
Test Leads.
Test Procedure:
a) Select the Multi meter in Resistance Mode.
b) Connect the Multi meter across the Trip/Close coils.
c) Note down the readings
Test Format For the above test are enclosed in Annexure-III

8.3 OPENING / CLOSING TIME MEASUREMENT TEST


Aim:
To calculate the timing of the opening and closing of the breaker contacts and ensure that
the values are within acceptable limits.
Equipments Required:
o Single / three pole timer.
o Test leads.
Test Procedure:
a) Connect the Timer across the Breaks for the Opening Time
LARSEN & TOUBRO CONSTRUCTION PROCEDURE NO:
Power Transmission & Distribution T&C/T& C P/AIS-GIS/001

TESTING AND COMMISSIONING PROCEDURE Page 136 of 223

b) Connect the Timer across the Pole for the Closing Time/ “Close-Open” Time

Test Format For The above Test In Enclosed in Annexure-III

8.4 CONTACT RESISTANCE MEASUREMENT TEST


Aim:
To calculate the value of the contact resistance and compare the value with the factory
reports and approve the equipment for further use.
Equipments Required:
o Contact resistance meter.
o Test leads.
Test Procedure:
i. Connect the CRM kit across the contact while Breaker in Close Condition.
iii. Switch ON the test kit.

Fig 1 : Contact Resistance measurement


Test Format For The above Test In Enclosed in Annexure-III
LARSEN & TOUBRO CONSTRUCTION PROCEDURE NO:
Power Transmission & Distribution T&C/T& C P/AIS-GIS/001

TESTING AND COMMISSIONING PROCEDURE Page 137 of 223

8.5 TESTS FOR SWITCHGEAR CT


1. Test Procedure for the above test can be obtained from CT testing
procedures.(Whichever applicable)
Test Format For The above Test In Enclosed in Annexure-IV

8.6 TESTS FOR SWITCHGEAR PT


1. Test Procedure for the above test can be obtained from PT testing procedures.
(Whichever applicable)
Test Format For The above Test In Enclosed in Annexure-V

8.7 INSULATION RESISTANCE TEST FOR BUS BAR


Aim:
To find the insulation resistance value of the equipments and ensure the performance of the
equipments based on the values obtained.
Equipments Required:
o Insulation tester.
o Test leads.
Test Procedure:
The above test is conducted at the following points,
a) Each phase and earth.
b) Between phase and phase.
a)Each phase and earth:
i. Connect the positive terminal of the meggar(5000V) to one phase.
ii. Connect the earth terminal of the meggar to the common earth terminal.
iii. Switch ON the meggar .
iv. Note down the reading in the annexure-VI
v. Similarly note down the reading for all phases and earth.
b)Between one phase to other:
i. Connect the positive terminal of the meggar(5000V) to one phase.
ii. Connect the earth terminal of the meggar to the other phase.
iii. Switch ON the meggar .
iv. Note down the reading in the annexure-VI
v. Similarly note down the reading for all phases.
LARSEN & TOUBRO CONSTRUCTION PROCEDURE NO:
Power Transmission & Distribution T&C/T& C P/AIS-GIS/001

TESTING AND COMMISSIONING PROCEDURE Page 138 of 223

8.8 CONTACT RESISTANCE MEASUREMENT OF BUS BAR


Aim:
To calculate the value of the contact resistance and compare the value with the factory
reports and approve the equipment for further use.
Equipments Required:
o Contact resistance meter.
o Test leads.
Test Procedure:
The contact resistance measurement of each of the busbar is measured by the following
method.
5) Ensure the required tightness of each bus.
6) Short one end of any two phases.
7) Now connect the CRM kit across the other end of the shorted phases.
8) Note down the reading in annexure –VII.
9) Repeat the test for other phases and ensure that the value is found similar in all the cases.

8.9 HIGH VOLTAGE TEST FOR BUS BAR


Aim:
To ensure that the bus bar withstands high voltage and to spot out minute defects in the
busbar and approve the bus for usage.
Equipments Required:
High voltage test kit.
Test leads.
Test Procedure:
The test is done by the following way.
i. Connect the positive terminal of the test kit to one phase.
ii. Short the other two phases to earth.
iii. Connect the earth terminal of the kit to the same earth point.
iv. Supply the rated high voltage to the bus.
v. Note down the reading in annexure – VIII.
LARSEN & TOUBRO CONSTRUCTION PROCEDURE NO:
Power Transmission & Distribution T&C/T& C P/AIS-GIS/001

TESTING AND COMMISSIONING PROCEDURE Page 139 of 223

ANNEXURE – I

Details of Switchgear

LOA No. :

Make :

Type: :

Sl. No. :

Year of manufacture:

Operating Voltage:

Feeder details :

Control Voltage:

ANNEXURE – II
Post Installation check list

S. Description Status Remarks, Record


No. Yes No discrepancies, if any
1. Switchgear is cleaned and free from dust /
dirt, foreign materials etc.
2. Switchgearf is free from all visible defects
on physical inspection
3. Switchgear Panel has been provided with
double earth
4. All nuts and bolts are tightened correctly as
per specified torque
5. Switchgear erection is complete in all
respect
6. Permanent labelling and identification is
done
7. Levelling and alignment of switchgear and
base frame checked
8. Tightness of nuts bolts of Bus Bar are
checked
9. Auxiliary contacts and relays have been
cleaned and free from rust / damage
10 All spare wires terminated at the terminal
blocks
11. Erection completion certificate along with
list of outstanding activities reviewed
LARSEN & TOUBRO CONSTRUCTION PROCEDURE NO:
Power Transmission & Distribution T&C/T& C P/AIS-GIS/001

TESTING AND COMMISSIONING PROCEDURE Page 140 of 223

ANNEXURE – III

Circuit Breaker Test Report

Board Name Feeder


Description/No:
Rated Voltage Rated Current
Sl. No. Year of mfg.
Make Closing Coil
Rating
Trip Coil Rating

i) Insulation Resistance Test –

Instrument Details Make


Calibration valid Instrument Sl. No.
upto

Phase Measured Between Insulation Resistance in MΩs


R–E
R R`– E
R – R`
Y–E
Y Y`– E
Y – Y`
B–E
B B`– E
B – B`

ii) CB Operation Time Measurement –

Operation Pole
R Y B
Closing Time (msec)
Opening Time (msec)
Close-open Time (msec)

iii) Coil Resistance Measurement –

Instrument Details Make


Calibration valid Instrument Sl. No.
upto

Description Resistance in Ωs
Closing Coil
Trip Coil
LARSEN & TOUBRO CONSTRUCTION PROCEDURE NO:
Power Transmission & Distribution T&C/T& C P/AIS-GIS/001

TESTING AND COMMISSIONING PROCEDURE Page 141 of 223

iv) Contact Resistance Measurement –

Instrument Details Make


Calibration valid Instrument Sl. No.
upto

Description Resistance in Milli Ωs


R Pole
Y Pole
B Pole

v) Mechanical Checks –

Description Remarks
CB rack in / out operation
CB rack in / out indications
Manual spring charging operation
Spring charged Indication
Manual ON / OFF operation
CB ON / OFF indication
Emergency Trip operation
Power contact alignment with panel contacts

vi) Electrical Checks -

Description Remarks
Spring Charging operation time (Secs)
Test / Service position switch
ON / OFF operation in Local / Remote
Spring charged Indication
CB ON / OFF indication
Lamp Indications

ANNEXURE – IV
Metering / Protection CT Test Report

Board Name Feeder Description


CT Details Make / Class
Core-1 Details Core-2 Details

CT Serial No.
R Ph Y Ph B Ph
LARSEN & TOUBRO CONSTRUCTION PROCEDURE NO:
Power Transmission & Distribution T&C/T& C P/AIS-GIS/001

TESTING AND COMMISSIONING PROCEDURE Page 142 of 223

i) CT Insulation Resistance Test –

Instrument Details Make


Calibration valid upto Instrument Sl. No.

(In MΩs)
Description R Ph Y Ph B Ph
Primary to Earth
Primary to Secondary Core-1
Primary to Secondary Core-2
Secondary Core-1 to Earth
Secondary Core-2 to Earth
Secondary Core-1 to Core-2

ii) CT Secondary Winding Resistance Measurement –

Instrument Details - Make -


Calibration valid upto - Instrument Sl. No. -

(In Ωs)
Description Terminal Nos. R Ph Y Ph B Ph
Secondary Core-1 1S1-1S2
Secondary Core-2 2S1-2S2

iii) CT Polarity Check –

Description Terminal Nos. R Ph Y Ph B Ph


Secondary Core-1 1S1-1S2
Secondary Core-2 2S1-2S2

iv) CT Ratio Test –

Description Ratio Primary Current Measured Secondary Current


Injected R Ph Y Ph B Ph
Secondary Core-1

Secondary Core-2
LARSEN & TOUBRO CONSTRUCTION PROCEDURE NO:
Power Transmission & Distribution T&C/T& C P/AIS-GIS/001

TESTING AND COMMISSIONING PROCEDURE Page 143 of 223

CT Check List

Sl. Check Point Remarks


No.
1 All CT quantity, rating, type & make are as per approved drawings.
2 No physical damage to any of the CT.
3 Inter-panel wiring from CTs to disconnector Terminal blocks in panel is as per
approved drawing.
4 CT secondary star point terminals are properly earthed at disconnector terminal
blocks.
5 CT wiring ferrules are as per drawing.
6 All CT connections are properly tightened.

ANNEXURE – V

PT Test Report

Board Name Feeder Description/No:


PT Details Make / Class
Core-1 Details Core-2 Details

PT Serial No.
R Ph Y Ph B Ph

i) PT Insulation Resistance Test –

Instrument Details Make


Calibration valid upto Instrument Sl. No.

(In MΩs)
Description R Ph Y Ph B Ph
Primary to Earth
Primary to Secondary Core-1
Primary to Secondary Core-2
Secondary Core-1 to Earth
Secondary Core-2 to Earth
Secondary Core-1 to Core-2

ii) PT Polarity Check –

Description Terminal Nos. R Ph Y Ph B Ph


Secondary Core-1
Secondary Core-2
LARSEN & TOUBRO CONSTRUCTION PROCEDURE NO:
Power Transmission & Distribution T&C/T& C P/AIS-GIS/001

TESTING AND COMMISSIONING PROCEDURE Page 144 of 223

iii) PT Ratio Test –

Description Ratio Primary Voltage Measured Secondary Voltage


Applied R Ph Y Ph B Ph
Secondary
Core-1

Secondary
Core-2

PT Check List

Sl. Check Point Remarks


No.
1 All PT quantity, rating, type & make are as per approved drawings.
2 No physical damage to any of the PT.
3 Inter-panel wiring from PTs to disconnector Terminal blocks in panel is as per
approved drawing.
4 PT primary neutral terminals are properly earthed.
5 PT wiring ferrules are as per drawing.
6 All PT connections are properly tightened.
7 Primary Fuse rating is as per the drawing and fuses are healthy.

ANNEXURE – VI
INSULATION RESISTANCE TEST FOR BUSBAR

a)Phase to earth:

Connection R–E Y–E B–E


Resistance

b)Phase to Phase:

Connection R – Y Phase Y – B Phase R – B Phase


Resistance
LARSEN & TOUBRO CONSTRUCTION PROCEDURE NO:
Power Transmission & Distribution T&C/T& C P/AIS-GIS/001

TESTING AND COMMISSIONING PROCEDURE Page 145 of 223

ANNEXURE – VII
CONTACT RESISTANCE MEASUREMENT

Resistance of the lead used for shorting =__________

Connection R & Y Phase Y & B Phase R & B Phase


Resistance

ANNEXURE – VIII
HIGH VOLTAGE TEST

Rated voltage Test Voltage Test Voltage Duration in


KV Between Conductor Between Minutes
& Earth Conductor &
KV Conductor
KV
0.6/1.1 3 3 15
1.9/3.3 5 9 15
3.3/3.3 9 9 15
3.8/6.6 10.5 18 15
6.6/6.6 18 18 15
6.35/11 18 30 15
11/11 30 30 15
12.7/22 37.5 - 15
19/33 60 - 15

Sl No Between Leakage Current Remarks


Y & B Phases &
1 R Phase & Earth
Earthed
R & B Phases &
2 Y Phase & Earth
Earthed
R & Y Phases &
3 B Phase & Earth
Earthed

Circuitry/Operational Checks

S. No. Circuit reference Circuitary checks Operational checks


Local Remote Local Remote
A Tripping of CB
B Closing of CB
C Breaker position indication
D Heater in switchgear
E Illumination in switchgear
F Incomer & Bus coupler
Interlock

Calibration Status Table


TEST INSTRUMENT DETAILS:
Sr Instrument description Range Calibration status
no
LARSEN & TOUBRO CONSTRUCTION PROCEDURE NO:
Power Transmission & Distribution T&C/T& C P/AIS-GIS/001

TESTING AND COMMISSIONING PROCEDURE Page 146 of 223

COMMISSIONING PROCEDURE FOR


AIR INSULATED SUB-STATION
LARSEN & TOUBRO CONSTRUCTION PROCEDURE NO:
Power Transmission & Distribution T&C/T& C P/AIS-GIS/001

TESTING AND COMMISSIONING PROCEDURE Page 147 of 223

1.0 SCOPE:
This procedure will cover the guidelines for Commissioning checks, energisation and post
energisation checks on outdoor equipments for all bays. Interface outdoor equipment to CRP,
SCADA, DCDB, and ACDB is also covered by the procedure.

2.0 PURPOSE:
This procedure is prepared for carrying out the commissioning checks, energisation and post
energisation checks on all outdoor equipments.

3.0 PRE-REQUISITES:
3.1 REQUIREMENT OF OTHER SYSTEM:
1. Control & Relay panels with mimic display / semaphore indication are installed, tested and
commissioned in switchyard relay and control panel building, in control equipment room &
main control room.
2. 415V 3phase power supply from 415V ACDB are commissioned and available.
3. 220 V DC source 1 & 2 from DCDB power supply for protection and control system are
commissioned and available.
4. Installation, testing and commissioning of fire fighting system, EOT crane, ventilation system
and DG set ,submersible pumps for cable trench connected sump drainage system in
switchyard is completed.
5. System energy metering system is installed, tested and commissioned.
6. All civil works and mechanical services in the building and adjacent area are completed.
7. SCADA is commissioned and available (preferably).

3.2 SYSTEM REQUIREMENTS:


1. Installation and wiring of substation is completed as per approved drawings and clearance
certificate is obtained.
2. Installation related checks like resistance checks of main circuit, cable continuity checks, SF6
leakage checks, gas pressure monitoring and oil pressure monitoring switch calibration
checks, coil resistance checks are completed.
3. Installation of CT, Isolator, Wave Trap, Circuit Breaker, LAs & CVTs in the conventional part
of switchyard and power connection is completed.
LARSEN & TOUBRO CONSTRUCTION PROCEDURE NO:
Power Transmission & Distribution T&C/T& C P/AIS-GIS/001

TESTING AND COMMISSIONING PROCEDURE Page 148 of 223

4. Wave trap installation and PLCC (supplied / installed by other) equipments wherever
applicable are completed.
5. Firefighting system is available, completely installed and tested.
6. Ventilation system is functional and available.
7. Switchyard cable trenches are completed and are completely covered. The water sumps
connected to cable trench should be completed and the dewatering pumps and system
should be functional.
8. 3 phase 415 V power supply is available for testing.
9. Electrical inspectors clearance is obtained.
10. Telephone system is available near the equipment.
11. Relevant drawings, documents, PO copies, approved settings of relays are available.
12. Availability of auxiliary power with all protection is ensured.
13. Switchyard illumination is available on a permanent basis.
14. Earthing grid of switchyard is completed and all equipments and structures are connected to
earth.
4.0 REQUIREMENTS OF INSTRUMENTS:-
1. 250V, 500V, 5 KV & 10kV meggar.
2. Earth tester.
3. Multimeter.
4. Leakage current tester(AC/DC).
5. Clamp meter.(0-2000A)
6. DC power pack for (0 - 220V DC).
7. Micro – Ohmmeter.

5.0 HAZARDS AND PRECAUTIONS:


1. Unauthorized persons should not be allowed to enter switchyard area
2. Any conducting element should be carried horizontally at waist level.
3. All under ground cable trenches should be kept in dry state and should be covered
properly.
4. Growth of weeds, shrubs etc should be prevented in switchyard area.
5. Local control cabinet / marshalling boxes / junction boxes should be kept in locked
condition.
6. Adequate illumination must be maintained in switchyard area.
7. Ensure that switchyard area is clean.
8. Ensure that no CT secondary is left open circuited during testing.
LARSEN & TOUBRO CONSTRUCTION PROCEDURE NO:
Power Transmission & Distribution T&C/T& C P/AIS-GIS/001

TESTING AND COMMISSIONING PROCEDURE Page 149 of 223

9. Ensure that no earthing or discharge rod is left connected and that they are cleared
before charging.
10. Ensure proper ventilation and exhaust system is ON when installation is being done and
clean room conditions should be followed.
11. Do not operate the CB with SF6 gas pressure less than Recommended pressure.
12. Do not exceed the duty cycle of the CB for repeated operations.
13. Emergency operation of CB is not subjected to any condition of interlock, this has to be
checked before any emergency operation.
14. Do not operate the isolator and earth switch mechanism more than rated duty cycle.
Allow for cooling time of motor if repeated operations are to be performed.
15. Do not leave CVT neutral terminals disconnected from earth, connect them to PLCC
equipment or earth as per scheme.
16. Do not leave PT primary neutral terminals disconnected from earth.
17. Confirm the relative polarities of CT , line CVT and bus PT. These are particularly critical
for synchronising.

6 GENERAL CHECKS

In line with the pre-commissioning check list all checks shall be carried out
7 ENERGISATION AND POST ENERGISATION CHECKS
1. Check sheet is enclosed in annexure – 11.
2. Record on hourly basis as per the annexure the below mentioned values.
3. Record no load charging current on drawn by the line for 24 hrs.
4. Record current flow in the CT secondaries at regular intervals.
5. Record voltages on main buses and on line at regular intervals for 24 hrs.
6. Record the SF6 gas pressure readings of CB on an hourly basis.
7. Record the hydraulic oil pressure/ pneumatic pressure of CB on an hourly basis.
8. Check for any visible corona in the conventional part of switchyard.
9. Record the reading at LA surge monitor for counter and leakage current.
LARSEN & TOUBRO CONSTRUCTION PROCEDURE NO:
Power Transmission & Distribution T&C/T& C P/AIS-GIS/001

TESTING AND COMMISSIONING PROCEDURE Page 150 of 223

8 WORK PLANS
Confirming the status of other
systems

Confirming the status of


switchyard system

Confirming the availability of


manpower

Confirming the availability of


test instruments

Confirming the availability of


outside agencies

Identifying the hazards and


taking necessary precautions

Checks for completeness and


correctness of switchyard &
line installation

Checks for completeness and


correctness of power circuit of
switchyard
LARSEN & TOUBRO CONSTRUCTION PROCEDURE NO:
Power Transmission & Distribution T&C/T& C P/AIS-GIS/001

TESTING AND COMMISSIONING PROCEDURE Page 151 of 223

Checks for interfacing with


other systems controlling,
protecting and monitoring the
switchyard

Interlocking, indication and


annunciation checks of
switchyard equipments

CB tripping checks by
simulating protection system

General checks on switchyard

Commissioning of switchyard as
per procedure

Energisation and post


energisartion checks

Consolidation of commissioning
documentation

Handing over the system to


Client
LARSEN & TOUBRO CONSTRUCTION PROCEDURE NO:
Power Transmission & Distribution T&C/T& C P/AIS-GIS/001

TESTING AND COMMISSIONING PROCEDURE Page 152 of 223

ANNEXURE – 1
FINAL CHECK SHEET

Sr no Description of final check Observations Remarks


1 Testing checks of all SF6 density monitors done and all monitors
are connected in alarm and lockout circuit and they show a
healthy status for CB
2 Testing checks of all CB hydraulic/pneumatic pressure switches
done and all switches are connected in alarm, lockout and pump
operation circuit and they show a healthy status for CB
mechanism
3 Safety value operating correctly for all CB hydraulic mechanisms
5 CB trip and close timings in the specified control voltage range
are checked and are found acceptable
6 CB pole discrepancy function is operational
7 CB cannot be closed when due to fall in hydraulic pressure
/pneumatic pressure & spring dis charged the close/open lock
outs have operated respectively
8 CB mechanical indicators show correct position
9 CB auxiliary switch is correctly connected as per scheme
10 CB is correctly interlocked from other equipments for its
closing/opening
11 Other equipments are correctly interlocked from CB for their
closing/opening
12 CB is tripping from all tripping relays / hand trip (from C&R
Panel) directly connected to its trip coil is checked. Also it is
confirmed that there is no mixing of DC for TC-1 & TC-2. trip
circuit supervision relays show healthiness of trip coils in pre-
close, post-close and post trip position of CB.
13 CB closing and tripping from bay controller is checked
14 CB closing from remote is checked
15 Signals emanating from CB are getting registered at local and
remote annunciator and at SCADA.
LARSEN & TOUBRO CONSTRUCTION PROCEDURE NO:
Power Transmission & Distribution T&C/T& C P/AIS-GIS/001

TESTING AND COMMISSIONING PROCEDURE Page 153 of 223

16 ISOLATOR mechanical indicators show correct position


17 ISOLATOR auxiliary switch is correctly connected as per scheme
18 ISOLATOR is correctly interlocked from other equipments for its
closing/opening
19 Other equipments are correctly interlocked from ISOLATOR for
their closing/opening
21 ISOLATOR neither open nor close position gets registered in
alarm annunciator
22 ISOLATOR timing checks are performed and are acceptable
23 ISOLATOR local and remote indications for position are true
24 E/S mechanical indicators show correct position
25 E/S auxiliary switch is correctly connected as per scheme
26 E/S is correctly interlocked from other equipments for its
closing/opening
27 Other equipments are correctly interlocked from E/S for their
closing/opening
29 E/S neither open nor close position gets registered in alarm
annunciator
30 E/S timing checks are performed and are acceptable
31 E/S local and remote indications for position are true
32 Local bay controller is fully checked for all functions as per
scheme
33 Bay controller counter for all equipments is functional
34 Mimic at bay controller shows correct circuit condition
35 Alarm of bay are correctly registered at bay controller
36 Interlock of bay equipments among themselves and with other
bays through bay controller is as per scheme
37 Metering of bay is checked at bay controller
38 CTs are tested and their secondaries are connected to burdens
correctly
39 No CT secondary is left open circuited
40 Correct CT ratio tapping is adopted
41 Earth continuity across CT, CVT, LA, Breaker, Isolator & wave
trap are provided
LARSEN & TOUBRO CONSTRUCTION PROCEDURE NO:
Power Transmission & Distribution T&C/T& C P/AIS-GIS/001

TESTING AND COMMISSIONING PROCEDURE Page 154 of 223

45 PTs are tested and their secondaries are connected to burdens


correctly
46 Neutral ends of PT primary and secondary are connected to
earth as per scheme
47 CVTs are tested and their secondaries are connected to burdens
correctly
48 Neutral ends of CVTs, primary and secondary are connected to
earth as per scheme and / or to PLCC equipment as per scheme
49 Corona rings are connected to CVT line terminal
50 Earth connection of CVT to station grid is completed
51 IR value of CVT is checked and found acceptable
52 LA surge counter readings are taken
53 LA connection to HV lead is checked
54 LA connection to station earth grid via surge counter is checked
also LA supporting structure is earthed
55 LA insulation resistance value is found acceptable
56 Wave traps (if any) are checked to be mounted and connected
as per the drawing
57 Jumper and dropper connections at line terminations is checked
with drawing and are found correctly connected
58 PLCC equipments if any are connected to system as per scheme
(by other agencies)
59 Connection tightness of terminations at CT, Breaker, Isolator,
wavetrap, CVT, LA & is checked and found OK
60 Clearance between phase to earth and phase to phase is
checked and is found OK
61 Ground clearance of live parts is found OK
62 Orientation of LA with respect to pressure relief diaphragm is
checked to be correct
63 Stress ring is mounted on LA line terminal
LARSEN & TOUBRO CONSTRUCTION PROCEDURE NO:
Power Transmission & Distribution T&C/T& C P/AIS-GIS/001

TESTING AND COMMISSIONING PROCEDURE Page 155 of 223

A. C&R Panel RELATED


SR DESCRIPTION OF FINAL CHECK OBSERVATIONS REMARKS
NO
1 Check that C&R Panel installation is completed in all
respects
2 Check that C&R Panel commissioning for AIS system is
completed as per procedure.
3 Checked that CB of each bay can be tripped with tripping
relays as per the scheme
4 Checked that there is no mixing of DC control sources
and panel internal wiring is correct as per scheme
5 Checked all termination of control and power cable at
C&R Panel are found correct
6 All relays in C&R Panel are tested and set to operate as
per relay setting chart. Further all relay are free to
operate and all mechanical locking is removed.
7 Checked the operation of all bay equipments from
remote and verified that interlocking scheme of bay
equipments is functional from remote
8 Checked that the bus bar protection scheme for zone
1&2 is functioning correctly and local breaker back up
protection is functional
9 Checked that bus bar check zone protection scheme is
functioning as per scheme.
10 Checked that all CT, CVT and PT circuits are connected to
burdens in C&R Panel.
11 Checked the operation of main and backup protection of
each bay
13 Checked interfacing with PLCC equipments
14 Checked interfacing with SCADA equipments
15 Checked that synchronizing scheme is functional
16 Checked that DC failure alarm and alarm annunciator
circuits are functioning as per scheme
LARSEN & TOUBRO CONSTRUCTION PROCEDURE NO:
Power Transmission & Distribution T&C/T& C P/AIS-GIS/001

TESTING AND COMMISSIONING PROCEDURE Page 156 of 223

B. SCADA RELATED
SR DESCRIPTION OF FINAL CHECK OBSERVATIONS REMARKS
NO
1 Check that SCADA panel installation is completed in all
respects
2 Check that SCADA system is commissioned as per
procedures.
3 Checked the operation of bay equipments from SCADA
panel
4 Checked that bay equipment interlocking is functioning
as per scheme from SCADA operations also
5 Checked that status of equipment is correctly getting
registered at SCADA panel
6 Checked that various signals emanating from relay
contacts are getting registered at SCADA panel

PERFORMED BY CHECKED BY WITNESSED BY

M/S L&T (CONST) M/S L&T (QA) CLIENT


LARSEN & TOUBRO CONSTRUCTION PROCEDURE NO:
Power Transmission & Distribution T&C/T& C P/AIS-GIS/001

TESTING AND COMMISSIONING PROCEDURE Page 157 of 223

ANNEXURE – 2
POST ENERGISATION CHECK SHEET
SR POST ENERGISATION CHECKS OBSERVATION INFERENCE REMARK
NO / VALUE
1 Bus A voltage (in Volts) and frequency (in Hz)
2 Bus B voltage (in Volts) and frequency (in Hz)
3 SF6 pressure in all CBs (in bars)
4 Hydraulic oil pressure in all CBs (in bars)
5 Check for any visual corona discharge in the
switchyard
6 Check for any other abnormal noise from
equipments
7 Check the surge counter at LA and record the
leakage current, ensure leakage current is in
acceptable limit.
8 Line voltage in control room

PERFORMED BY CHECKED BY WITNESSED BY

M/S L&T (CONST) M/S L&T (QA) CLIENT


LARSEN & TOUBRO CONSTRUCTION PROCEDURE NO:
Power Transmission & Distribution T&C/T& C P/AIS-GIS/001

TESTING AND COMMISSIONING PROCEDURE Page 158 of 223

ANNEXURE – 3
VERIFICATION SHEET
S no Activity Acceptance Verific Certification by verifying agency
verified criteria ation Procedure Inspection Functional Results
agency certification tests
1 Pre As per check list/
commissioni acceptance list
ng checks
2 Switch yard As per check list/
checks and acceptance list
testing
3 Interfacing As per set points
with CR
Panel,
relaying,
relay setting
4 Control and Logics as per
logic of annexure
switchyard
equipments
5 Line and As per checklist/
remote end acceptance list
checks
LARSEN & TOUBRO CONSTRUCTION PROCEDURE NO:
Power Transmission & Distribution T&C/T& C P/AIS-GIS/001

TESTING AND COMMISSIONING PROCEDURE Page 159 of 223

TESTING & COMMISSIONING PROCEDURE


FOR GAS INSULATED SUB-STATION
LARSEN & TOUBRO CONSTRUCTION PROCEDURE NO:
Power Transmission & Distribution T&C/T& C P/AIS-GIS/001

TESTING AND COMMISSIONING PROCEDURE Page 160 of 223

1.0 SCOPE

This procedure will cover the guidelines for Commissioning checks, energisation and post
energisation checks on GIS system and outdoor equipments for all bays up to first gantry
tower. Interface checks from GIS / outdoor equipment to CRP, SCADA, DCDB, and ACDB is
also covered by the procedure.

2.0 PURPOSE:
This procedure is prepared for carrying out the commissioning checks, energisation and post
energisation checks on GIS System.

3.0 PRE-REQUISITES:
3.1 REQUIREMENT OF OTHER SYSTEM:
1. Control & Relay panels with mimic display / semaphore indication are installed, tested and
commissioned in switchyard relay and control panel building, in control equipment room &
main control room.
2. 415V 3phase power supply from 415V ACDB are commissioned and available.
3. 220 V DC source 1 & 2 from DCDB power supply for protection and control system are
commissioned and available.
4. Installation, testing and commissioning of fire fighting system, EOT crane, ventilation system
and DG set ,submersible pumps for cable trench connected sump drainage system in
switchyard is completed.
5. System energy metering system is installed, tested and commissioned.
6. All civil works and mechanical services in the building and adjacent area are completed.
7. SCADA is commissioned and available (preferably).

3.2 SYSTEM REQUIREMENTS:


1. Installation and wiring of GIS is completed as per approved drawings and clearance
certificate is obtained.
2. Installation related checks like resistance checks of main circuit, cable continuity checks,
SF6 leakage checks, gas pressure monitoring and oil pressure monitoring switch
calibration checks, coil resistance checks are completed.
3. HV and partial discharge test on the completely assembled GIS is carried out and the
results are acceptable.
LARSEN & TOUBRO CONSTRUCTION PROCEDURE NO:
Power Transmission & Distribution T&C/T& C P/AIS-GIS/001

TESTING AND COMMISSIONING PROCEDURE Page 161 of 223

4. Installation of LAs & CVTs in the conventional part of switchyard and power connection is
completed.
5. Wave trap installation and PLCC (supplied / installed by other) equipments wherever
applicable are completed.
6. Fire fighting system is available, completely installed and tested.
7. Ventilation system is functional and available.
8. Switchyard illumination is available on a permanent basis.
9. Earthing grid of switchyard is completed and all equipments and structures are connected to
earth.
10. Switchyard cable trenches are completed and are completely covered. The water sumps
connected to cable trench should be completed and the dewatering pumps and system
should be functional.
11. 3 phase 415 V power supply is available for testing.
12. Electrical inspectors clearance is obtained.
13. Telephone system is available near the equipment.
14. Relevant drawings, documents, PO copies, approved settings of relays are available.
15. Availability of SF 6 gas maintenance unit and adequate quantity of SF 6 gas cylinders for make
up is available.
16. Availability of auxiliary power with all protection is ensured.

4.0 REQUIREMENTS OF INSTRUMENTS:-


1. 250V, 500V, 5 KV & 10kV meggar.
2. Earth tester.
3. Multimeter.
4. Leakage current tester(AC/DC).
5. Clamp meter.(0-2000A)
6. DC power pack for (0 - 220V DC).
7. Micro – Ohmmeter.

5.0 HAZARDS AND PRECAUTIONS:


1. Unauthorized persons should not be allowed to enter switchyard area.
2. Any conducting element should be carried horizontally at waist level.
3. All under ground cable trenches should be kept in dry state and should be covered properly.
4. Growth of weeds, shrubs etc should be prevented in switchyard area.
5. Local control cabinet / marshalling boxes / junction boxes should be kept in locked condition.
LARSEN & TOUBRO CONSTRUCTION PROCEDURE NO:
Power Transmission & Distribution T&C/T& C P/AIS-GIS/001

TESTING AND COMMISSIONING PROCEDURE Page 162 of 223

6. Adequate illumination must be maintained in switchyard area and GIS building.


7. Ensure that switchyard area and GIS building is clean.
8. Ensure that no CT secondary is left open circuited during testing.
9. Ensure that no earthing or discharge rod is left connected and that they are cleared before
charging.
10. Ensure proper ventilation and exhaust system is ON when installation/SF6 gas filling is being
done and clean room conditions should be followed.
11. Do not operate the CB with SF6 gas pressure less than 6 bars.
12. Do not exceed the duty cycle of the CB for repeated operations.
13. Do not operate the CB with oil tank cover open since this can lead to air entrapment in
mechanism.
14. Emergency operation of CB is not subjected to any condition of interlock, this has to be
checked before any emergency operation.
15. Do not operate the disconnector and earth switch mechanism more than rated duty cycle.
Allow for cooling time of motor if repeated operations are to be performed.
16. Do not leave CVT neutral terminals disconnected from earth, connect them to PLCC
equipment or earth as per scheme.
17. Do not leave PT primary neutral terminals disconnected from earth.
18. Confirm the relative polarities of line CVT and bus PT. These are particularly critical for
synchronising.

6 PRE-COMMISSIONING CHECKS

BAY EQUIPMENT CHECKS:


CHECKS ON CIRCUIT BREAKER
1. Power supply, perform test for rated operating sequence starting from pump cut in pressure.
If test is to be repeated keep 15 minutes gap between the cycles.

6.1 CB TIME MEASUREMENT CHECKS


1. CB operating time checks are carried out at pump shut down pressure and at the range of DC
fed to operating coils.
2. CB timing test kit is used to measure the operation time of each pole. Two leads each, per
phase are connected from the kit across the fixed and moving contact of each CB pole. The
CB close and trip coil 1 & 2 are connected to the kit and their operation is controlled by the
push buttons on the kit.
3. The access to the CB poles in GIS for connecting the leads of time measurement kit is
achieved by closing of earth switch on sides of CB and opening the earthing shunt links of
LARSEN & TOUBRO CONSTRUCTION PROCEDURE NO:
Power Transmission & Distribution T&C/T& C P/AIS-GIS/001

TESTING AND COMMISSIONING PROCEDURE Page 163 of 223

earth switch to GIS enclosure. Now the leads from the kit can be connected on the bushing
terminals of earth switch.
4. Carry out the time measurement checks for simultaneous closing operation of CB and note
down the closing time of each pole. Check that the difference between closing time is with in
acceptable limit. These measurements are to be done when the control DC voltage is at 85%,
100%, and 110% of rated 220 V DC.
5. Carry out the time measurement checks for simultaneous opening operation of CB and note
down the opening time of each pole for opening through trip coil 1. Check that the difference
in opening time in between the poles is with in acceptable limit. These measurements are to
be done when the control DC voltage is at 70%, 100%, and 110% of rated 220 V DC.
6. Carry out the time measurement checks for simultaneous opening operation of CB and note
down the opening time of each pole for opening through trip coil 2 Check that the difference
in opening time in between the poles is with in acceptable limit. These measurements are to
be done when the control DC voltage is at 70%, 100%, and 110% of rated 220 V DC.
7. Carry out simultaneous closing on a fault and check the anti pumping system. Keeping the
tripping circuit energized through NO auxiliary contact of CB (with CB initially open), apply
closing order for a couple of seconds. The time during which the CB stays closed during
closing/opening cycle is measured. Also the CB should not close back after tripping, even
though closing order is continuously present. This confirms the anti pumping feature of CB.
8. RESTORE THE TRIP & CLOSE COIL WIRES AS PER SCHEME.
9. Also check the trip free feature of the CB mechanism.

6.1.1 CB FUNCTIONAL CHECKS


1. Check the nameplate of CB and compare it with nameplate drawing.
2. CB closing/opening coil resistances and IR values are taken at installation stage and the
results are enclosed
3. Check the closing of CB at lock out pressure: keep the hydraulic pump shut down, reduce the
operating mechanism pressure till it reaches the value corresponding to closing lockout. Now
attempt a closing operation, the CB should not close. Record the pressure at which closing
lock out of circuit happens.
4. Check the opening of CB at lock out pressure: keep the hydraulic pump shut down, reduce
the operating mechanism pressure till it reaches the value corresponding to opening lockout.
Now attempt an opening operation, the CB should not open. Record the pressure at which
opening lock out of circuit happens.
5. Perform test to confirm operation of pole discrepancy circuit. Set the pole discrepancy relay
timer to about 5 seconds. Connect DC supply for close and trip coil 1 circuit only. With CB in
open position remove close coil wire of R pole. Close the CB. Check that Y and B pole have
closed, while R pole remains open. Now after elapse of time set on pole discrepancy timer,
check that the Y and B poles open by the initiation from pole discrepancy relay. Similarly
LARSEN & TOUBRO CONSTRUCTION PROCEDURE NO:
Power Transmission & Distribution T&C/T& C P/AIS-GIS/001

TESTING AND COMMISSIONING PROCEDURE Page 164 of 223

check for Y and B pole. Repeat the above test with DC supply connected to close coil and trip
coil 2 only. RESTORE THE TRIP & CLOSE COIL WIRES AS PER SCHEME.
6. Check that the mechanical open and close indicators for each pole of CB are operating
correctly.
7. Check that the operation counters for CB operation are recording each operation of CB. From
the start of pre commissioning activity, maintain a record of CB operation and counter
increments.
8. Check the local operation of CB.
9. Check the emergency operation of CB
10. Check the operation of CB through bay controller.
11. Check the remote closing of CB from control panel manual closing, auto reclose closing as
applicable (including 1 phase and 3 phase auto reclosure), and SCADA.
12. Check the operation of CB auxiliary contacts for correctness and their being correctly wired
up as per scheme to various other locations.
13. Check the various signals emanating from CB and getting connected to bay controller, alarm
annunciation and SCADA for the following conditions:
a) CB SF6 internal leakage.
b) CB general failure.
c) CB close/open status monitoring.
d) CB pole discrepancy.
e) CB in rescue trip mode.
f) Heating power supply fail.
g) Hydraulic oil pump supply fail.
h) CB hydraulic oil pump motor excessive starts.
i) CB tripping lock out.
j) CB in local or maintenance position.
k) CB SF6 stage 1 alarm.
l) CB SF6 stage 2 alarm and lock out.

DISCONNECTOR CHECKS
6.1.2 CHECKS IN ERECTION STAGE ON DISCONNECTOR
1. Check for the correct operation of auxiliary switches. Also check that these auxiliary switches
are connected to various other equipments / systems as per the scheme.
2. Check the operation of limit switches for close and open position.
3. Check the IR value and winding resistance of mechanism motor are taken during installation
stage.
4. Check for lubrication of mechanism.
LARSEN & TOUBRO CONSTRUCTION PROCEDURE NO:
Power Transmission & Distribution T&C/T& C P/AIS-GIS/001

TESTING AND COMMISSIONING PROCEDURE Page 165 of 223

6.1.2.1 OPERATION CHECKS ON DISCONNECTOR

1. Keep the disconnector selector switch in manual control mode. Check that electrical operation
cannot be performed. Press the push button for manual operation and check that the shutter
for hand crank is released (this is subject to interlock conditions being satisfied). Connect the
hand crank to the switch drive and operate the switch manually. Check for smoothness of
operation and note down the no of revolutions it takes to complete the closing and opening
operation.
2. Keep the disconnector selector switch in electrical control mode. Check shutter covering the
hand crank connecting point is locked. Press the push button on the mechanism and confirm
that the shutter still remains closed.
3. Check the operation of limit switches for closing and opening position. Ensure that close limit
switch is in closing circuit and open is in opening circuit. Also ensure that the phase sequence
for closing and opening supplies is correct, before commencing electrical operation.
4. Check the operation of the disconnector by operating it from the bay controller and also from
remote control panel and SCADA panel. (this is subject to interlock conditions being satisfied)
5. Keep the disconnector selector switch in locked mode. Check that neither electrical nor
manual operation is possible on the disconnector even if the interlocking conditions are
satisfied.
6. Measure the currents absorbed by operating motor during operation.
7. Check the operation of auxiliary contacts changeover.
8. Check the operation of limit switches for closing and opening position.

6.1.2.2 TIME MEASUREMENT CHECKS ON DISCONNECTOR

1. Measure the time of operation of the disconnector for closing and opening. Check that the
closing and opening times and the maximum difference between poles are as per
manufacturers specifications.
2. Using the timer and connecting it across the fixed and moving contact of isolator perform
time measurement.
3. Access to the isolator contacts is available at earth switch bushing on the enclosure (after
removing shunt link to earthed enclosure), by closing the earth switches on either side of
disconnector. RESTORE THE SHUNT LINKS AFTER TEST.

6.1.2.3 INTERLOCK CHECKS ON DISCONNECTOR


1. Check that the disconnector is inoperable when the CB of the bay is closed.
2. Check that the disconnector can operate only when CB of the bay is open.
LARSEN & TOUBRO CONSTRUCTION PROCEDURE NO:
Power Transmission & Distribution T&C/T& C P/AIS-GIS/001

TESTING AND COMMISSIONING PROCEDURE Page 166 of 223

3. Check for prolonged closing of both isolator (bus isolators paralled) alarm initiated after time
delay.
4. Check that the disconnector cannot close when any of the earth switch on its side is closed.
5. Check further interlocks as per the approved interlocking scheme.
6.1.3 EARTH SWITCH CHECKS
6.1.3.1 CHECKS IN ERECTION STAGE ON EARTH SWITCH
1. Check for the correct operation of auxiliary switches. Also check that these auxiliary switches
are connected to various other equipments / systems as per the scheme.
2. Check the operation of limit switches for close and open position.
3. Check the IR value and winding resistance of mechanism motor.
4. Check for lubrication of mechanism.

6.1.3.2 OPERATION CHECKS ON EARTH SWITCH


1. Test format is enclosed in annexure –14
2. Keep the E/S selector switch in manual control mode. Check that electrical operation cannot
be performed. Press the push button for manual operation and check that the shutter for
hand crank is released (this is subject to interlock conditions being satisfied). Connect the
hand crank to the switch drive and operate the E/S manually. Check for smoothness of
operation and note down the no of revolutions it takes to complete the closing and opening
operation.
3. Keep the E/S selector switch in electrical control mode. Check shutter covering the hand
crank connecting point is locked. Press the push button on the mechanism and confirm that
the shutter still remains closed.
4. Check the operation of limit switches for closing and opening position. Ensure that close limit
switch is in closing circuit and open is in opening circuit. Also ensure that the phase sequence
for closing and opening supplies is correct, before commencing electrical operation.
5. Check the operation of the E/S by operating it from the bay controller and also from remote
control panel and SCADA panel. (This is subject to interlock conditions being satisfied).
6. Keep the E/S selector switch in locked mode. Check that neither electrical nor manual
operation is possible on the E/S even if the interlocking conditions are satisfied
7. Measure the currents absorbed by operating motor during operation/spring charging.
8. Check the operation of auxiliary contacts changeover.
9. Check the operation of limit switches for closing and opening position.

6.1.3.3 TIME MEASUREMENT CHECKS ON EARTH SWITCH


1. Measure the time of operation of the E/S for closing and opening. Check that the closing and
opening times and the maximum difference between poles are as per manufacturers
specifications.
LARSEN & TOUBRO CONSTRUCTION PROCEDURE NO:
Power Transmission & Distribution T&C/T& C P/AIS-GIS/001

TESTING AND COMMISSIONING PROCEDURE Page 167 of 223

2. Using the timer and connecting it across the fixed and moving contact of E/S, perform time
measurement.
3. Access to the E/S contacts is available on one side (for moving contact), at earth switch
bushing on the enclosure (after removing shunt link to earthed enclosure). For other side
(fixed contact) close the disconnector(s) & other earth switches connected to other side of
E/S under test. Remove the shunt link from the bushing to the enclosure of the (nearest
other) earth switch. Fixed contact of the E/S under test is now accessed at the bushing of the
(nearest other) earth switch. RESTORE THE SHUNTS AFTER THE TEST.

6.1.3.4 INTERLOCK CHECKS ON EARTH SWITCH


1. Check that the E/S is inoperable when the CB of the bay is closed.
2. Check that the E/S can operate only when CB & disconnectors of the bay connected with E/S
are open.
3. Check that the line side E/S is inoperable when the line is charged (simulating through line no
volt relay).
4. Check that the bus side E/S is inoperable when the bus is charged (simulating through line no
volt relay).
5. Check further interlocks as per the approved interlocking scheme.
6.1.4 CT CHECKS
1. Current transformer primary is accessed by earth switches on its either side. The earth
switches are closed and the earthing shunt from the bushing to enclosure is removed. Now
the connections for CT primary can be done at the E/S bushings for the purpose of test.
Further keep the disconnectors on either side of CT open.
2. Polarity check is performed on the CT. A polarity tester is used and it applies a positive pulse
across P1 to P2 terminal. The galvanometer connected across the S1 to S2 terminal should
show a positive deflection, then it is concluded that the polarity is correct. This is checked for
all secondaries.
3. IR value check on secondary is performed using a 1000V insulation tester. This is checked for
all secondaries.
4. Winding resistance of secondary windings are checked using a suitable bridge circuit. This is
checked for all secondaries.
5. Knee point voltage and current absorbed by CT secondary at half the knee point voltage is
inferred from the magnetization characteristics of CT for P and PS class CTs. This is done by
impressing increasing values of AC voltage across the CT secondary and keep measuring the
magnetizing current absorbed by the secondary. When for increase of 10% of impressed
voltage, the increase in current is 50%, then the voltage being impressed is equal to knee
point voltage. A graph is to be plotted for the same.
6. Ratio test is conducted on CT to check the ratio of primary current to secondary current is
same as nameplate ratio. Primary injection test kit is used to inject high currents into the CT
LARSEN & TOUBRO CONSTRUCTION PROCEDURE NO:
Power Transmission & Distribution T&C/T& C P/AIS-GIS/001

TESTING AND COMMISSIONING PROCEDURE Page 168 of 223

primary and corresponding secondary currents are noted using an ammeter. RESTORE THE
SHUNT AFTER THE TEST.

6.1.5 CVT CHECKS


1. CVT line terminal is accessible and is connected to outgoing overhead conductor.
2. Polarity of secondary winding with respect to primary is checked using a polarity tester.
3. IR value of secondary windings is checked using a 250 V megger.
4. Winding resistance of secondary windings is measured using bridge method.
5. Ratio of CVT is checked by impressing 1 phase 240V AC supply across the primary and
measuring the induced voltage in the secondary. This is compared with the nameplate ratio.
6. Measure the capacitance of the CVT capacitors.
7. When all tests are completed, ensure to connect the earthing links of primary and
secondary terminals which are meant to be earthed. In case of PLCC equipments
connected to CVT, ensure correctness of connections as per scheme.

6.1.6 PT CHECKS
1. Potential Transformer (PT) primary line terminal is accessed at the earth bushing of closed
earth switch.
2. Polarity of secondary winding with respect to primary is checked using a polarity tester.
3. IR value of secondary windings is checked using a 250 V megger.
4. Winding resistance of secondary windings is measured using bridge method.
5. Ratio of PT is checked by impressing 1 phase 240V AC supply across the primary and
measuring the induced voltage in the secondary. This is compared with the nameplate ratio.
6. When all test are completed ensure to connect the earthing links of primary 1N terminal and
secondary 2n terminals.

6.1.7 LA CHECKS
1. Insulation resistance of surge arrester is measured using a 5 KV megger.
2. Completeness of installation with respect to GA and DD drawings is checked.
3. Leakage current milli ampere meter of surge monitor is checked by passing current through
it. Surge counter is checked for incrementing the count by discharging a charged capacitor
across it.
4. Check that the surge counter is connected firmly between the LA and the earth. Check that
the supporting structure of LA is separately earthed.
5. Check the orientation of LA with respect to the pressure relief diaphragm.

6.1.8 WAVE TRAP CHECKS


1. Check for correct installation of wave trap as per drawing on its post insulators.
2. Check for correct incoming and outgoing jumper connections for wave trap.
LARSEN & TOUBRO CONSTRUCTION PROCEDURE NO:
Power Transmission & Distribution T&C/T& C P/AIS-GIS/001

TESTING AND COMMISSIONING PROCEDURE Page 169 of 223

For Detailed Testing procedures please refer Pre-commissioning test of S/S


equipments

7. ENERGISATION AND POST ENERGISATION CHECKS


1. Check sheet is enclosed in annexure – 11.
2. Record on hourly basis as per the annexure the below mentioned values.
3. Record no load charging current on drawn by the line for 24 hrs.
4. Record current flow in the CT secondaries at regular intervals.
5. Record voltages on main buses and on line at regular intervals for 24 hrs.
6. Record the SF6 gas pressure readings of all enclosures of GIS on an hourly basis.
7. Record the SF6 gas pressure readings of CB on an hourly basis.
8. Record the hydraulic oil pressure/ pneumatic pressure of CB on an hourly basis.
9. Check for any visible corona in the conventional part of switchyard.
10. Record the reading at LA surge monitor for counter and leakage current.

8. WORK PLANS

Confirming the status of other


systems

Confirming the status of


switchyard system

Confirming the availability of


manpower

Confirming the availability of


test instruments
LARSEN & TOUBRO CONSTRUCTION PROCEDURE NO:
Power Transmission & Distribution T&C/T& C P/AIS-GIS/001

TESTING AND COMMISSIONING PROCEDURE Page 170 of 223

Confirming the availability of


outside agencies

Identifying the hazards and


taking necessary precautions

Checks for completeness and


correctness of switchyard &
line installation

Checks for completeness and


correctness of power circuit of
switchyard

Checks for interfacing with


other systems controlling,
protecting and monitoring the
switchyard

Electrical testing of individual


switchyard equipments

Primary/secondary injection
testing of switchyard
equipments with burdens
connected
LARSEN & TOUBRO CONSTRUCTION PROCEDURE NO:
Power Transmission & Distribution T&C/T& C P/AIS-GIS/001

TESTING AND COMMISSIONING PROCEDURE Page 171 of 223

Interlocking, indication and


annunciation checks of
switchyard equipments

CB tripping checks by
simulating protection system

General checks on switchyard


and HV & PD checks

Commissioning of switchyard as
per procedure

Energisation and post


energisartion checks

Consolidation of commissioning
documentation

Handing over the system to


Client
LARSEN & TOUBRO CONSTRUCTION PROCEDURE NO:
Power Transmission & Distribution T&C/T& C P/AIS-GIS/001

TESTING AND COMMISSIONING PROCEDURE Page 172 of 223

ANNEXURE – 1
CHECKLIST OF EARTHING: PHYSICAL CHECK

Sr Locations of earthing / Checked Checked Checked for Checked


no description of earthing for tightness of for
parameter provision fasteners to continuity
as per specified level to main
drawing earth
1 Soil resistivity of switchyard

2 Earth resistance of switchyard earth


grid

3 Shunts from bushings to enclosure


of all earth switches

4 Shunts across all CTs

5 Shunts across all compensation


joints

6 Connection of all enclosures earth


pads to switchyard earth pads.

7 Connection of all IPBD, LA, CVT


support structure earth pads to
switchyard earth pads.

8 Connection of all IPBD, LA, CVT


earth pads to switchyard earth pads.

9 Connection of switchyard earthing


grid to station earth grid
LARSEN & TOUBRO CONSTRUCTION PROCEDURE NO:
Power Transmission & Distribution T&C/T& C P/AIS-GIS/001

TESTING AND COMMISSIONING PROCEDURE Page 173 of 223

10 Connection of earth pits to earth grid

11 Connection of LA, PT and CVT earth


terminal

12 Connection of line supporting towers


to earth

13 Connection of line shield wire to


earth

14 Earthing of any other equipment as


per detailed drawing

TEST INSTRUMENT DETAILS:


Sr no Instrument description Range Calibration status

PERFORMED BY CHECKED BY WITNESSED BY

M/S L&T (CONST) M/S L&T (QA) CLIENT


LARSEN & TOUBRO CONSTRUCTION PROCEDURE NO:
Power Transmission & Distribution T&C/T& C P/AIS-GIS/001

TESTING AND COMMISSIONING PROCEDURE Page 174 of 223

ANNEXURE – 2
FINAL CHECK SHEET
1. 400KV GIS RELATED

Sr no Description of final check Observations Remarks


1 Testing checks of all SF6 density monitors done and all monitors
are connected in alarm and lockout circuit and they show a
healthy status for CB and enclosures
2 Testing checks of all CB hydraulic pressure switches done and all
switches are connected in alarm, lockout and pump operation
circuit and they show a healthy status for CB mechanism
3 Safety value operating correctly for all CB hydraulic mechanisms
4 All CB hydraulic mechanisms accumulators are healthy
5 CB trip and close timings in the specified control voltage range
are checked and are found acceptable
6 CB pole discrepancy function is operational
7 CB cannot be closed/opened when due to fall in hydraulic oil
pressure the close/open lock outs have operated respectively
8 CB mechanical indicators show correct position
9 CB auxiliary switch is correctly connected as per scheme
10 CB is correctly interlocked from other equipments for its
closing/opening
11 Other equipments are correctly interlocked from CB for their
closing/opening
12 CB is tripping from all tripping relays / hand trip (from C&R
Panel) directly connected to its trip coil is checked. Also it is
confirmed that there is no mixing of DC for TC-1 & TC-2. trip
circuit supervision relays show healthiness of trip coils in pre-
close, post-close and post trip position of CB.
13 CB closing and tripping from bay controller is checked
14 CB closing from remote is checked
15 Signals emanating from CB are getting registered at local and
remote annunciator and at SCADA.
LARSEN & TOUBRO CONSTRUCTION PROCEDURE NO:
Power Transmission & Distribution T&C/T& C P/AIS-GIS/001

TESTING AND COMMISSIONING PROCEDURE Page 175 of 223

16 D/S mechanical indicators show correct position


17 D/S auxiliary switch is correctly connected as per scheme
18 D/S is correctly interlocked from other equipments for its
closing/opening
19 Other equipments are correctly interlocked from D/S for their
closing/opening
20 D/S locks out for SF6 pressure at & below 2nd level alarm
21 D/S neither open nor close position gets registered in alarm
annunciator
22 D/S timing checks are performed and are acceptable
23 D/S local and remote indications for position are true
24 E/S mechanical indicators show correct position
25 E/S auxiliary switch is correctly connected as per scheme
26 E/S is correctly interlocked from other equipments for its
closing/opening
27 Other equipments are correctly interlocked from E/S for their
closing/opening
28 E/S locks out for SF6 pressure at & below 2nd level alarm
29 E/S neither open nor close position gets registered in alarm
annunciator
30 E/S timing checks are performed and are acceptable
31 E/S local and remote indications for position are true
32 Local bay controller is fully checked for all functions as per
scheme
33 Bay controller counter for all equipments is functional
34 Mimic at bay controller shows correct circuit condition
35 Alarm of bay are correctly registered at bay controller
36 Interlock of bay equipments among themselves and with other
bays through bay controller is as per scheme
37 Metering of bay is checked at bay controller
38 CTs are tested and their secondaries are connected to burdens
correctly
39 No CT secondary is left open circuited
40 Correct CT ratio tapping is adopted
LARSEN & TOUBRO CONSTRUCTION PROCEDURE NO:
Power Transmission & Distribution T&C/T& C P/AIS-GIS/001

TESTING AND COMMISSIONING PROCEDURE Page 176 of 223

41 Earth continuity shunts across CT enclosure are provided


42 Earth continuity shunts across adjustment compensation joints,
bus bar flanges of enclosure are provided
43 Earth continuity shunts between E/S bushing and enclosure are
provided
44 Earthing connection of enclosures, IPBD, IPBD supporting
structure to switchyard earth grid is done
45 PTs are tested and their secondaries are connected to burdens
correctly
46 Neutral ends of PT primary and secondary are connected to
earth as per scheme
47 GIS routine testing including resistance inspection, gas leakage
test, gas moisture content test, IR test is completed
48 GIS HV & PD testing are completed

2. CONVENTIONAL PART OF SWITCHYARD RELATED


Sr no Description of final check Observations Remarks
1 CVTs are tested and their secondaries are connected to burdens
correctly
2 Neutral ends of CVTs, primary and secondary are connected to
earth as per scheme and / or to PLCC equipment as per scheme
3 Corona rings are connected to CVT line terminal
4 Earth connection of CVT to station grid is completed
5 IR value of CVT is checked and found acceptable
6 LA surge counter readings are taken
7 LA connection to HV lead is checked
8 LA connection to station earth grid via surge counter is checked
also LA supporting structure is earthed
9 LA insulation resistance value is found acceptable
10 Wave traps (if any) are checked to be mounted and connected as
per the drawing
11 Jumper and dropper connections at line terminations is checked
with drawing and are found correctly connected
LARSEN & TOUBRO CONSTRUCTION PROCEDURE NO:
Power Transmission & Distribution T&C/T& C P/AIS-GIS/001

TESTING AND COMMISSIONING PROCEDURE Page 177 of 223

12 PLCC equipments if any are connected to system as per scheme


(by other agencies)
13 Connection tightness of terminations at wavetrap, CVT, LA &
SF6/air bushing is checked and found OK
14 Clearance between phase to earth and phase to phase is checked
and is found OK
15 Ground clearance of live parts is found OK
16 Orientation of LA with respect to pressure relief diaphragm is
checked to be correct
17 Stress ring is mounted on LA line terminal

3. C&R Panel RELATED

SR NO DESCRIPTION OF FINAL CHECK OBSERVATIONS REMARKS

1 Check that C&R Panel installation is completed in all


respects
2 Check that C&R Panel commissioning for GIS system is
completed as per procedure.
3 Checked that CB of each bay can be tripped with tripping
relays as per the scheme
4 Checked that there is no mixing of DC control sources and
panel internal wiring is correct as per scheme
5 Checked all termination of control and power cable at C&R
Panel are found correct
6 All relays in C&R Panel are tested and set to operate as per
relay setting chart. Further all relay are free to operate and
all mechanical locking is removed.
7 Checked the operation of all bay equipments from remote
and verified that interlocking scheme of bay equipments is
functional from remote
8 Checked that the bus bar protection scheme for zone 1&2
is functioning correctly and local breaker back up
protection is functional
LARSEN & TOUBRO CONSTRUCTION PROCEDURE NO:
Power Transmission & Distribution T&C/T& C P/AIS-GIS/001

TESTING AND COMMISSIONING PROCEDURE Page 178 of 223

9 Checked that bus bar check zone protection scheme is


functioning as per scheme.
10 Checked that all CT, CVT and PT circuits are connected to
burdens in C&R Panel.
11 Checked the operation of main and backup protection of
each bay
13 Checked interfacing with PLCC equipments
14 Checked interfacing with SCADA equipments
15 Checked that synchronizing scheme is functional
16 Checked that DC failure alarm and alarm annunciator
circuits are functioning as per scheme

4. SCADA RELATED

SR NO DESCRIPTION OF FINAL CHECK OBSERVATIONS REMARKS


1 Check that SCADA panel installation is completed in all
respects
2 Check that SCADA system is commissioned as per
procedures.
3 Checked the operation of bay equipments from SCADA
panel
4 Checked that bay equipment interlocking is functioning as
per scheme from SCADA operations also
5 Checked that status of equipment is correctly getting
registered at SCADA panel
6 Checked that various signals emanating from relay
contacts are getting registered at SCADA panel

PERFORMED BY CHECKED BY WITNESSED BY

M/S L&T (CONST) M/S L&T (QA) CLIENT


LARSEN & TOUBRO CONSTRUCTION PROCEDURE NO:
Power Transmission & Distribution T&C/T& C P/AIS-GIS/001

TESTING AND COMMISSIONING PROCEDURE Page 179 of 223

ANNEXURE – 3

POST ENERGISATION CHECK SHEET

SR POST ENERGISATION CHECKS OBSERVATION INFERENCE REMARK


NO / VALUE
1 Bus A voltage (in Volts) and frequency (in Hz)
2 Bus B voltage (in Volts) and frequency (in Hz)
3 SF6 pressure in all enclosures (in bars)
4 SF6 pressure in all CBs (in bars)
5 Hydraulic oil pressure in all CBs (in bars)
6 Check for any visual corona discharge in the
conventional part of switchyard
7 Check for any other abnormal noise from
enclosures, GIS and conventional equipments
8 Check the surge counter at LA and record the
leakage current, ensure leakage current is in
acceptable limit.
9 Line voltage in control room

PERFORMED BY CHECKED BY WITNESSED BY

M/S L&T (CONST) M/S L&T (QA) CLIENT


LARSEN & TOUBRO CONSTRUCTION PROCEDURE NO:
Power Transmission & Distribution T&C/T& C P/AIS-GIS/001

TESTING AND COMMISSIONING PROCEDURE Page 180 of 223

FORMAT FOR POST ENERGISATION CHECKS FOR A PERIOD OF 24 HRS


Sr Type of check Observations /remarks
no
Start 3hrs 6hrs 9hrs 12hrs 15hrs 18hrs 21hrs 24hrs
1 Bus A voltage (in Volts)
and frequency (in Hz)
2 Bus B voltage (in Volts)
and frequency (in Hz)
3 SF6 pressure in all
enclosures (in bars)
4 SF6 pressure in all CBs (in
bars)
5 Hydraulic oil pressure in all
CBs (in bars)
6 Check for any visual
corona discharge in the
conventional part of
switchyard
7 Check for any other
abnormal noise from
enclosures, GIS and
conventional equipments
8 Check the surge counter at
LA and record the leakage
current, ensure leakage
current is in acceptable
limit.
9 Line voltage in control
room

PERFORMED BY CHECKED BY WITNESSED BY

M/S L&T (CONST) M/S L&T (QA) CLIENT


LARSEN & TOUBRO CONSTRUCTION PROCEDURE NO:
Power Transmission & Distribution T&C/T& C P/AIS-GIS/001

TESTING AND COMMISSIONING PROCEDURE Page 181 of 223

ANNEXURE – 4
VERIFICATION SHEET
S Activity verified Acceptance Verificat Certification by verifying agency
no criteria ion Procedure Inspection Functional Results
agency certification tests
1 Pre As per check list/
commissioning acceptance list
checks
2 Switch yard As per check list/
checks and acceptance list
testing
3 Interfacing with As per set points
C&R Panel,
relaying, relay
setting
4 Control and Logics as per
logic of annexure
switchyard
equipments
5 Line and As per checklist/
remote end acceptance list
checks
LARSEN & TOUBRO CONSTRUCTION PROCEDURE NO:
Power Transmission & Distribution T&C/T& C P/AIS-GIS/001

TESTING AND COMMISSIONING PROCEDURE Page 182 of 223

TESTING OF RELAYS
LARSEN & TOUBRO CONSTRUCTION PROCEDURE NO:
Power Transmission & Distribution T&C/T& C P/AIS-GIS/001

TESTING AND COMMISSIONING PROCEDURE Page 183 of 223

PROCEDURE FOR TESTING


DIFFERENTIAL PROTECTION RELAYS
LARSEN & TOUBRO CONSTRUCTION PROCEDURE NO:
Power Transmission & Distribution T&C/T& C P/AIS-GIS/001

TESTING AND COMMISSIONING PROCEDURE Page 184 of 223

1.0 Scope:
The procedure covers pre commissioning test of differential relay which is to be done and test report formats are
enclosed.
2.0 Purpose:
This procedure is prepared to carry out various pre commissioning test in a systematic manner on differential
relays to ensure the healthiness of relays.
3.0 Pre-Requisites
3.1 System Requirement:
1. Final settings of the relay.
2. 220V DC power supply.
3. 230V AC, single phase supply with proper grounding.
4. All internal wirings are done according to the drawings.
5. Relay terminal drawing.
6. Make sure that the CT inputs are terminated according to the drawings.

4.0 Requirement of testing kits:


S.No Testing kit Range
1 Relay test kit ( Omicron/Ponovo/freja/SMRT or any 0-25A, AC from single channel
equivalent) 250V auxillary DC
300V AC
2 Laptop with testing kit software and relay software

5.0 Requirement of testing instruments:


1. Digital multimeter.
2. 500V Insulation tester.
3. Polarity tester.
4. Test plug, Ethernet cable, serial port connector and other test leads.

6.0 Hazards and precautions:


1. Unauthorized persons should not be allowed to enter the testing area.
2. Ensure proper grounding of the panel is done.
3. Ensure proper grounding of the testing kit.
4. Ensure that the auxillary supply given to the relay is proper and is according to the relay
manual.
LARSEN & TOUBRO CONSTRUCTION PROCEDURE NO:
Power Transmission & Distribution T&C/T& C P/AIS-GIS/001

TESTING AND COMMISSIONING PROCEDURE Page 185 of 223

5. Ensure that all the terminal connections are tight.


6. Availability of tester and other tools is ensured.

7. Commissioning engineer should get familiarized with local menu control and the software of
the relay.
8. Care should be taken to protect the relay from electrostatic discharge while handling of relay.
9. Inspect the relay by removing the polycarbonate front cover and by withdrawing the modules.
Examine the module and the case and check for any damages. Check that CT shorting
switches are in the case are wired into correct circuit and are closed when the module is
withdrawn.
10. Check the serial number of the module & case are identical and the model number and rating
information are correct.
11. Check that the external wiring is correct to relevant relay diagram.
12. With the relay removed from the case, check that it is isolated from voltage and current
transformer inputs and ensure using a continuity meter that the CT I/P terminals are closed.
13. Check for earthing of relay to the local earth bar.
14. Insulation checks: isolate all wiring from the earth and test the insulation with an electronic or
brushless tester at a DC voltage not exceeding 1000V. Terminals of same circuit shall be
temporarily strapped together.
15. There should be no temporary supply (hooking of supply) for testing.
16. Ensure healthiness of test leads.
17. Ensure that the supply used is with MCB protection.

7.0 Commissioning test notes


1. This relay takes the CT inputs from HV and LV side of power transformer directly and
corrects the input for CT ratio, current transformation from HV to LV and for any phase shift
due to transformation. Its internal phase compensator does this.
2. Set the internal transformer phase compensation for the purpose of testing the relay with
single-phase currents. Check that the CT secondary setting is 1A. (Out of selection of 1A or
5A).
3. Commission the relay with calculated application settings after the auxiliary supply test is
completed.
4. Commission the relay with selective logic function required for a particular application.
LARSEN & TOUBRO CONSTRUCTION PROCEDURE NO:
Power Transmission & Distribution T&C/T& C P/AIS-GIS/001

TESTING AND COMMISSIONING PROCEDURE Page 186 of 223

5. Check that when the relay trips and red LED is illuminated, pressing the appropriate key can
reset this. Also check that LED and the fault display can be reset only when the fault condition
has been removed.
6. Check the configuration of output contacts is done as per setting sheet.

8.0 Auxillary supply tests:


1. Check that specified auxiliary supply is available to the specified terminals of the relay. Do not
energise the relay with battery charger with the battery disconnected.
2. Check for energisation of relay from auxiliary voltage supply. Check the status of watchdog
contacts when the auxiliary supply is connected and when it is disconnected.
3. Check the field voltage generated by the relay at the appropriate terminals.

8.0 Post installation checks:


Post installation checks should be done according to the annexure enclosed.
9.0 Test to be conducted:
1. Sensitivity check (or Pick up test).
2. Bias check.
3. Harmonic restraint check.

9.1 Phase Compensation:


I. Checks on internal phase compensation function: inject the current through A phase of HV
and LV 1 winding. Set the phase compensation for both these windings to the same value.
This will result in no differential currents if the magnitude of the injected currents is equal.
The differential currents can be monitored using the measurements menu.
II. While injecting the currents ensure that they are in phase opposition (180 degree). Once
checks are completed set the phase compensation to carry out further testing.
III. For Yy0 = inject with no phase compensation.
IV. For Dy1 = Inject on secondary with 30 degree lag.(i.e, Primary = 0 degree ; Secondary =
150 degree for stable condition)
V. For Dy11 = Inject on secondary with 30 degree lead. .(i.e, Primary = 0 degree ; Secondary =
210 degree for stable condition)
VI. One of the compensation factor on one of the winding is then changed which will result in
differential current. Using the measurements menu the resultant differential current can be
noted and compared with the values as per relay manual annexure.
LARSEN & TOUBRO CONSTRUCTION PROCEDURE NO:
Power Transmission & Distribution T&C/T& C P/AIS-GIS/001

TESTING AND COMMISSIONING PROCEDURE Page 187 of 223

9.2 Specific Checks:


I. INJECTED CURRENT MEASUREMENT CHECK: Set the phase compensation
factor. Inject a current of known value into each phase input. Check the CT ratios entered into
the relay and check the primary and secondary current displayed by the relay. Inject current
into the HV and LV terminals. Check the values displayed in the measurement menu and
confirm that it is with in +\- 10% of the values as given in relay manual.
II. FREQUENCY MEASUREMENT CHECKS: inject a current of known frequency to the
appropriate terminals of the relay. The frequency should be in the range of 15-65Hz. Check
that the displayed value is within +/- 2%.

9.3 Sensitivity Check (or Pick up test):


I. The following connections are given to check the differential relays.
a. Two current inputs to the analog channels assigned in the relay.
b. Auxillary input is connected to the relay according to the relay manual.
c. The binary output terminal of the relay is given to the testing kit in order to record the
tripping time.
II. Connect the current input from the testing kit to the test plug.
III. After connecting the testing kit with the above connections switch on the testing kit.
IV. Ensure the communication of the relay and test kit with the laptop according to the annexure
enclosed.
V. Load the relay with the final setting file.
VI. Now inject current I < Idmin of the relay on HV or LV side.
VII. Increase the magnitude of current I and record the trip value of the relay.
VIII. Repeat the test for other side and enter the values in the annexure enclosed.

9.4 Bias check:


I. With the above connections bias check can be done by the following steps.
II. Note down the slope value of each section.
III. Now inject current I (magnitude in slope section 1) in both the HV and LV section.
IV. Now increase the current I.
V. The relay will trip at a particular value. Note down the value in the annexure enclosed and
compare the slope value in the setting file.
LARSEN & TOUBRO CONSTRUCTION PROCEDURE NO:
Power Transmission & Distribution T&C/T& C P/AIS-GIS/001

TESTING AND COMMISSIONING PROCEDURE Page 188 of 223

VI. Continue the procedure for slope section 2 (if available). And enter the reading the reading in
the annexure enclosed.

9.5 Harmonic restraint:


I. Note down the Ix/I1 ratio.
II. Now connect two current channels of the testing kit to the same analog input of the relay.
III. Change the frequency of one of the current channel.
IV. This condition is similar to the harmonic inrush condition.
V. On injecting the current of magnitude such that the ratio Ix/I1 is exceeded of the setting value,
the LED assigned for harmonic block will be ON.
VI. Now increase the value of I1 and note down the trip value in the annexure enclosed.

9.6 Overfluxing protection


I. Testing the over fluxing alarms sensitivity: enable the overflux alarm relay and its output
relay. Disable all other protections.
II. Configure the equipment so that an AC voltage can be applied to appropriate relay input
terminal and timer can be started when the voltage is applied while it stops when the relay
operates.
III. Apply a voltage V= settings x f x 0.95 and check that the relay does not trip for a duration
greater than the set time.
IV. Now apply V= setting x f x 1.05 volts and ensure that the output relay operates in +/- 20% of
the set time.
V. Testing the over fluxing trip sensitivity: check this function in a similar manner as above.
Check the time for DT & IDMT characteristics for over fluxing (if any).
VI. Test for over flux fifth harmonic blocking on the low set differential protection if the feature
is used in scheme.
VII. Test for over fluxing fifth harmonic relay operating time if the feature is used in scheme.

9.7 Restricted Earth Fault Protection:


I. REF CURRENT SENSITIVITY : By going into the appropriate menu, select the REF
protection relay and enable it. Disable other protections. Adjust the series resistor to the given
value.Now apply given set voltage and note down the tripping time.
LARSEN & TOUBRO CONSTRUCTION PROCEDURE NO:
Power Transmission & Distribution T&C/T& C P/AIS-GIS/001

TESTING AND COMMISSIONING PROCEDURE Page 189 of 223

II. REF CURRENT STABILITY : Now inject a calculated value of current (3Io) into the
neutral terminal and also inject equal current (Io), in all the phases, and check that the relay
does not trip. This proves that the relay is stable for through fault.
III. REF ELEMENT OPERATING TIME: Connect the relay contacts to trip the test kit and
stop the timer. Configure the test set so that when current is applied the timer starts. Inject 5
times set voltage into the relay and ensure that the operating time is within 10-20 ms.

9.8 Selective Logics


I. OPTO INPUT CHECKS: Connect the negative terminal of the field output to the
appropriate relay terminals. Energise the opto isolated inputs by impressing the +ve of the
field voltage to the appropriate terminals as per annexure and check the status of inputs by
monitoring appropriate cell in the system menu data and enter the checks in annexure.
II. Test the auxiliary timers for relays, which are to be used in the intended application.
III. Change of setting group: check that the setting groups can be changed from settings1 &
settings2 by going into the appropriate menu (if feature is required).
IV. Remote control of transformer tap changer: check the function of tap changing locally using
the relay menu if the function is intended and wired (if feature is required).

9.9 Overcurrent & Earth fault relays:


I. Enter the as built settings in the relay.
II. Enable overcurrent protection and disable all other protections in the relay.
III. Now inject current at the specified terminal by the secondary injection test kit.
IV. For the specified amount of current injected note down the time taken for the relay to trip.
V. Similarly check for various values of current and note down the readings in the annexure.
VI. Also note down the trip time for definite time (if the feature is enabled) and also for
instantaneous trip time.
VII. Similarly follow the procedure for earth fault protection relays.

9.10 Directional Feature test:


I. This method of testing can be done on overcurrent/ Earthfault protection if directional feature
is enabled.
II. Now apply voltage (i.e, polarizing voltage) to the relay at specified input.
III. When the directional feature is being tested, apply voltage as shown in the table below,
LARSEN & TOUBRO CONSTRUCTION PROCEDURE NO:
Power Transmission & Distribution T&C/T& C P/AIS-GIS/001

TESTING AND COMMISSIONING PROCEDURE Page 190 of 223

Phase tested Polarizing voltage

R Phase V y-b

Y Phase V b-r

B Phase V r-y

IV. Apply rated line voltage across the phases as shown in the table, and inject current in the
phase to be tested.
V. Now apply current with respective phase angle (i.e, in tripping region) as shown in the figure.
VI. Check for the trip time as per the settings and note it in the annexure.
VII. Now vary the phase angle (180 degree apart) of the current (i.e, in the non operating region),
and check that the relay does not trip for the current injected.
VIII. In case of directional earth fault relays, if open delta connection is used for voltage input, the
only specified quantity of voltage can be applied irrespective of the phases.

9.11 Auxillary relays:


I. Note down the relay details in the annexure enclosed.
II. Now apply 0.5 times the setting voltage of the relays.
III. Now increase the voltage gradually and check for the tripping condition.
IV. After the relay trips now decrease the voltage from 1.2 times the setting voltage and note
down the drop off value of the relay.
V. Similarly repeat the procedure for all the auxillary relays.
LARSEN & TOUBRO CONSTRUCTION PROCEDURE NO:
Power Transmission & Distribution T&C/T& C P/AIS-GIS/001

TESTING AND COMMISSIONING PROCEDURE Page 191 of 223

Annexure –I
Name plate Details
Relay make :
Relay serial No. :
Test kit make :
Test kit serial no. :
Protection to :
Protected object details:-
1. Rating :
2. HV Side :
3. LV Side :
4. Other :
5. HV side CT Ratio :
6. LV Side CT Ratio :
7. Neutral CT Ratio :

Annexure – II
Post Installation Check List:
S.No Description Status Remarks, record
Yes No discrepancies, if any
1 Equipment is cleaned and free from dust / dirt, foreign
materials etc.
2 Auxillary DC is proper
3 All the settings are done as per the approved settings
received
4 The logic file for input/ output/ LED configuration is
loaded according to the approved as built drawing
5 Binary inputs assigned are checked
6 Binary outputs assigned are checked
7 LED assigned are checked
LARSEN & TOUBRO CONSTRUCTION PROCEDURE NO:
Power Transmission & Distribution T&C/T& C P/AIS-GIS/001

TESTING AND COMMISSIONING PROCEDURE Page 192 of 223

Annexure – III
Sensitivity Check
Idmin =
Phase HV Side LV Side
Trip value ,Amp Trip time, ms Trip value, Amp Trip time, ms
R
Y
B

Annexure – IV
Bias check
End section 1 =
Slope 1 =
Phase HV Side, Amp LV Side, Amp Trip time, ms
R
Y
B
Calculated slope 1 value =
End section 2 =
Slope 2 =
Phase HV Side, Amp LV Side, Amp Trip time, ms
R
Y
B

Calculated slope 2 value =


Annexure – V
Harmonic restrain Check
Ix/I1 ratio =
S.No Ix, Amp I1, Amp Trip time, ms
1 No trip
2
*Initially apply value current such that the ratio is exceeded and check for blocking condition and then check for
tripping condition.
LARSEN & TOUBRO CONSTRUCTION PROCEDURE NO:
Power Transmission & Distribution T&C/T& C P/AIS-GIS/001

TESTING AND COMMISSIONING PROCEDURE Page 193 of 223

Annexure – VI
Overcurrent Test / Earth fault Test
Relay S.No :
Relay Make :
Curve used :
Definite time setting :
Instantaneous setting :
S.No Current Applied, in Amps Trip time, in sec

*The table can be modified according to the number of readings taken.


Annexure – VII
Directional Overcurrent / Earthfault
Relay S.No :
Relay Make :
Voltage Input Current Input
S.No Region Polarizing voltage, Phase angle, degree Current, amp Phase,
volt degree

Tripping

Non - Tripping
*The table can be modified according to the number of readings taken.
Annexure – VIII
Auxillary Relays
S.No Auxillary Relay number Relay purpose Pick up, volt Drop off value, in
volt
LARSEN & TOUBRO CONSTRUCTION PROCEDURE NO:
Power Transmission & Distribution T&C/T& C P/AIS-GIS/001

TESTING AND COMMISSIONING PROCEDURE Page 194 of 223

Annexure – IX
Binary inputs
S.no Binary input Description Status Remarks
no.
1
2
3
4
5
6
7
8

*Enter all the binary inputs assigned for the relay and check whether the respective output is high in the system
menu. If corresponding output is obtained mark as OK, else note down the remark.

Annexure – X
Binary outputs
S.no Binary output Description Status Remarks
no.
1
2
3
4
5
6
7
*Give high inputs for the binary inputs assigned for the relay and check whether the respective output is high in
the system menu. If corresponding output is obtained mark as OK, else note down the remark.
LARSEN & TOUBRO CONSTRUCTION PROCEDURE NO:
Power Transmission & Distribution T&C/T& C P/AIS-GIS/001

TESTING AND COMMISSIONING PROCEDURE Page 195 of 223

Annexure – XI
LED
S.No LED No. Description Status Remarks
1
2
3
4
5
*Perform the respective LED operation in the relay by giving DC input to the appropriate input and check
whether the respective LED in glowing.

Annexure – XII
Calibration status table
S. no Instrument description Range Calibration status
LARSEN & TOUBRO CONSTRUCTION PROCEDURE NO:
Power Transmission & Distribution T&C/T& C P/AIS-GIS/001

TESTING AND COMMISSIONING PROCEDURE Page 196 of 223

PROCEDURE FOR TESTING DISTANCE


PROTECTION RELAYS
LARSEN & TOUBRO CONSTRUCTION PROCEDURE NO:
Power Transmission & Distribution T&C/T& C P/AIS-GIS/001

TESTING AND COMMISSIONING PROCEDURE Page 197 of 223

1.0 Scope:
The procedure covers pre commissioning test of distance relay and busbar relay along with the scheme checking
which is to be done and test report formats are enclosed.
2.0 Purpose:
This procedure is prepared to carry out various pre commissioning test in a systematic manner on distance relays
and busbar relays as per scheme to ensure the healthiness of relays.
3.0 Pre-Requisites
3.1 System Requirement:
1. Final settings of the relay.
2. 220V DC power supply.
3. 230V AC, single phase supply with proper grounding.
4. All internal wirings are done according to the drawings.
5. Relay terminal drawing.
6. Make sure that the CT and PT inputs are terminated according to the drawings.

4.0 Requirement of testing kits:


S.No Testing kit Range
1 Relay test kit ( Omicron/Ponovo/freja/SMRT or any 0-25A, AC from single channel
equivalent) 250V auxillary DC
300V AC
2 Laptop with testing kit software and relay software

5.0 Requirement of testing instruments:


1. Digital multimeter.
2. 500V Insulation tester.
3. Polarity tester.
4. Test plug, Ethernet cable, serial port connector and other test leads.

6.0 Hazards and precautions:


1. Unauthorized persons should not be allowed to enter the testing area.
2. Ensure proper grounding of the panel is done.
3. Ensure proper grounding of the testing kit.
4. Ensure that the auxillary supply given to the relay is proper and is according to the relay
manual.
LARSEN & TOUBRO CONSTRUCTION PROCEDURE NO:
Power Transmission & Distribution T&C/T& C P/AIS-GIS/001

TESTING AND COMMISSIONING PROCEDURE Page 198 of 223

5. Ensure that all the terminal connections are tight.


6. Availability of tester and other tools is ensured.
7. There should be no temporary supply (hooking of supply) for testing.
8. Ensure healthiness of test leads.
9. Ensure that the supply used is with MCB protection.

7.0 Post installation checks:


Post installation checks should be done according to the annexure enclosed.
8.0 Test to be conducted:
1. Zone verification.
2. Auto-reclose check.
3. Aided tripping (if available).
4. SOTF (if available).
5. Power swing block (if available).
6. Broken conductor detection (if available).
7. VT fuse failure (if available).
8. Undervoltage protection.
9. Over voltage protection.
10. Over current protection.
11. Earth fault protection.
12. Directional protection.

8.1 Zone verification:


I. Enter the as built setting in the relay. Disable all other protection.
II. Insert the test plug and connect the current and voltage inputs to the specific points.
III. Draw the matching characteristics for testing in the test kit (The procedure for drawing the
characteristics depends upon the type of kit used).
IV. Disable all other protection in the relay setting.
V. Now select various points on the characteristics.
VI. Start the test and check for the trip time.
VII. Note down the trip time in the annexure or enclose the test report from the test kit (if
available).
LARSEN & TOUBRO CONSTRUCTION PROCEDURE NO:
Power Transmission & Distribution T&C/T& C P/AIS-GIS/001

TESTING AND COMMISSIONING PROCEDURE Page 199 of 223

8.2 Auto-Reclose Check:


I. Ensure that single pole tripping is available in the scheme.
II. Check that the pole discrepancy relay setting is greater than dead time of A/R function.
III. Enter the approved setting in the relay.
IV. Now create a single phase to ground fault (in zone1) from the test kit. This initiates the A/R
start from the protection panel to the internal same relay/BCU/ external AR relay of the
particular bay.
V. Check for the auto reclose function noting down the dead time and reclaim time.
VI. Again initiate a fault (in zone1) during the reclaim time (this can be done by removing the
feedback from the binary output to the test kit) and check for auto-reclose lockout
condition.(in the BCU)
VII. Also check for
• ph-ph,
• 3-ph fault,
• busbar operated,
• carrier switch in ‘out’ position,
• backup protection operated,
• CB status unhealthy, the A/R is in block condition.
VIII. Also check for CB healthy status (SF6 gas pressure, Hydraulic pressure, Spring charged, air
pressure) for A/R check.
IX. Note down the proper LED is ON and note down the conditions in the annexure enclosed.

8.3 Aided trip:


I. Enter the as built setting in the relay and enable the aided trip condition.
II. Now apply a high DC to the binary input assigned for carrier receive(CR).
III. Now apply a fault in 80% to 100% of the line.
IV. Note down the trip time. The relay should trip in zone1 timing with trip in zone1 extended
(i.e. Aided tripping condition).
V. This condition is for carrier receive.
VI. Now similarly the carrier send condition can be simulated.
VII. Create a fault in zone1 and remove the feedback wire to the test kit.
VIII. Now check the binary output assigned for carrier send is high.
IX. This ensures that the carrier send is initiated from the relay.
LARSEN & TOUBRO CONSTRUCTION PROCEDURE NO:
Power Transmission & Distribution T&C/T& C P/AIS-GIS/001

TESTING AND COMMISSIONING PROCEDURE Page 200 of 223

8.4 SOTF:
I. This is switch on to fault condition. Disable all other protection.
II. Ensure that the settings entered are approved setting.
III. Now create a fault immediately on test run. This can be done by changing the prefault time
delay in the test kit to “0”.
IV. If no such option is available, hold the TNC switch in Trip position and Inject a calculated
quantity of voltage and current.
V. Now check that the relay trips under the SOFT condition without and time delay.

8.5 Power swing detection:


I. Enter the as built settings in the relay. Disable all other protection.
II. Now the condition can be simulated by varying the voltage. Inject rated quantity of current
and voltage in the CT and PT terminals.
III. Now decrease the voltage in steps of 2V for every 200ms keeping current at rated value. Or
increase current in steps of 0.5A for every 200ms keeping voltage at rated value. This
condition holds true for power swing.
IV. Check that the power swing condition is detected. (LED is ON, if assigned).
V. Check that the tripping is blocked for only the zones where power swing block is enabled.

8.6 Broken Conductor Detection:


I. Enter the setting in the relay. Disable all other protection.
II. Now inject current in the current channels.
III. Suddenly reduce one of the current to zero.
IV. Now check that the binary output / LED assigned for broken conductor detection is high. If
tripping logic is provided for broken conductor, check for the tripping of master trip relay.

8.7 VT fuse fail:


I. Enter the as built setting in the relay. Disable all other protection.

II. Connect a 3 phase supply to the terminals.


III. Now apply rated voltage to the voltage terminals of the relay.
IV. Now immediately reduce voltage in one of the phases to zero. This condition is similar to
fuse fail condition.
V. Now check for the LED indication assigned for VT fuse fail is ON.
LARSEN & TOUBRO CONSTRUCTION PROCEDURE NO:
Power Transmission & Distribution T&C/T& C P/AIS-GIS/001

TESTING AND COMMISSIONING PROCEDURE Page 201 of 223

8.8 Under Voltage Relay:


I. Now enable under voltage protection and disable all other protections.
II. Now supply 1.1 times the rated secondary voltage across the relay through the test kit.
III. Gradually decrease the voltage till the relay trips.
IV. If second stage for over voltage protection is given, apply the specified quantity of voltage
and note down the trip time as per the settings
V. Note down the trip time in the annexure enclosed.

8.9 Over Voltage Relay:


I. Now enable over voltage protection and disable all other protections.
II. Now supply 0.9 times the rated secondary voltage across the relay through the test kit.
III. Gradually increase the voltage till the relay trips.
IV. If second stage for over voltage protection is given, apply the specified quantity of voltage
and note down the trip time as per the settings
V. Note down the trip time in the annexure enclosed.

8.10 Overcurrent protection:


I. Enter the approved settings in the relay. Disable all other protection.
II. Inject the set quantity of the current in one phase, and gradually increase the current and note
down the trip time of the relay from the test kit feedback.
III. Repeat the procedure for other phases and note down the trip time.
IV. If any IEC curve is used, then note down the trip time for every current value(in times of rated
current).

8.11 Earthfault protection:


I. Enter the approved settings in the relay. Disable all other protection.
II. Inject the set quantity of the current in one phase, and gradually increase the current and note
down the trip time of the relay from the test kit feedback.
III. Note down the trip time.
IV. If any IEC curve is used, then note down the trip time for every current value(in times of rated
current).
LARSEN & TOUBRO CONSTRUCTION PROCEDURE NO:
Power Transmission & Distribution T&C/T& C P/AIS-GIS/001

TESTING AND COMMISSIONING PROCEDURE Page 202 of 223

8.12 Directional protection:


I. Enter the approved setting in the relay and disable all other protection.
II. Now apply voltage in all the phases at rated value. To create fault in any of the phases, reduce
the voltage by 20V in the faulty phase. Remaining phases are all with rated voltage.
III. Now apply current in the negative RCA angle given in the setting. (i.e., if RCA is given as 60
degree, apply current with an angle of -60 degree).
IV. This will produce trip from which time can be noted down.
V. Similarly inject current in the opposite region with 180 degree apart from previous injected
angle. This does not initiate trip signal. Hence directional feature is proved in the relay.
LARSEN & TOUBRO CONSTRUCTION PROCEDURE NO:
Power Transmission & Distribution T&C/T& C P/AIS-GIS/001

TESTING AND COMMISSIONING PROCEDURE Page 203 of 223

Annexure –I
Name Plate Details
Relay make :
Relay serial No. :
Test kit make :
Test kit serial no. :
Protection to :

Annexure – II
Post Installation Check List
S.No Description Status Remarks, record
Yes No discrepancies, if any
1 Equipment is cleaned and free from dust / dirt, foreign
materials etc.
2 Auxillary power supply is proper
3 All the settings are done as per the approved settings
received
4 Check that earthing bus continuity inside the panel &
connection of earth bus to station grounding mat is
completed
5 The logic file for input/ output/ LED configuration is
loaded according to the approved as built drawing
6 Binary inputs assigned are checked
7 Binary outputs assigned are checked
8 LED assigned are checked
9 Check factory test certificates are available and are as
per specifications for all relays, meters etc
10 Check that no unwanted tools or material are left near
the panel
11 Check that all cables are connected as per schedule and
interconnection chart
12 Check that all temporary loops & connections provided
for the purpose of conducting any test are removed
each time at the end of each test.
LARSEN & TOUBRO CONSTRUCTION PROCEDURE NO:
Power Transmission & Distribution T&C/T& C P/AIS-GIS/001

TESTING AND COMMISSIONING PROCEDURE Page 204 of 223

ANNEXURE III
CURRENT INPUTS
Displayed current
Phase CT ratio
IA, applied current / measured current
IB, applied current / measured current
IC, applied current / measured current
ANNEXURE IV
VOLTAGE INPUTS
Displayed voltage
Main VT ratio
Va, applied voltage / measured voltage
Vb applied voltage / measured voltage
Vc, applied voltage / measured voltage
ANNEXURE V
SETTINGS CHECK
Application specific function setting applied
Application specific programmable scheme logic
settings applied. If settings are applied using a
portable PC, then which software and version was
used
Application specific function setting verified
Application specific programmable scheme logic
tested
Protection function timing tested

Annexure – VI
Zone verification
Phase – Earth Fault:
S.No Phase Zone Impedance, in ohm Trip time, in ms
1
2
3
4
LARSEN & TOUBRO CONSTRUCTION PROCEDURE NO:
Power Transmission & Distribution T&C/T& C P/AIS-GIS/001

TESTING AND COMMISSIONING PROCEDURE Page 205 of 223

5
6
*Every tested point is enclosed along with the test report generated by the test kit.
Phase – Phase Fault:
S.No Phase Zone Impedance, in ohm Trip time, in ms
1
2
3
4
5
6
*Every tested point is enclosed along with the test report generated by the test kit.
3 Phase Fault:
S.No Phase Zone Impedance, in ohm Trip time, in ms
1
2
3
4
5
6
*Every tested point is enclosed along with the test report generated by the test kit.
Annexure – VII
Auto-Reclose Check
A/R trip : 1ph or 3ph
Dead time : Reclaim time :
Fault impedance =………………………… (in reclaim time)
A/R Lockout status =………………………….
CB Healthy status : YES / NO
A/R BLOCK for STATUS (YES/NO)
Busbar protection operated
Carrier switch in ‘out’ position
PH – PH
3 PH fault
CB Unhealthy
Backup protection operated
LARSEN & TOUBRO CONSTRUCTION PROCEDURE NO:
Power Transmission & Distribution T&C/T& C P/AIS-GIS/001

TESTING AND COMMISSIONING PROCEDURE Page 206 of 223

Annexure –VIII
Over current Protection
Definite time:
 Set current =
 Set time =
 Injected current =
 Actual time =

TOC type:
Set current = Time dial =
Injected current, Amp Theoretical time, sec Actual trip time, sec

Annexure –IX
Earth fault Protection
Definite time:
 Set current =
 Set time =
 Injected current =
 Actual time =

TOC type:
Set current = Time dial =
Injected current, Amp Theoretical time, sec Actual trip time, sec
LARSEN & TOUBRO CONSTRUCTION PROCEDURE NO:
Power Transmission & Distribution T&C/T& C P/AIS-GIS/001

TESTING AND COMMISSIONING PROCEDURE Page 207 of 223

Annexure – X
Directional overcurrent/ earthfault protection
Phase Applied Phase angle Injected Phase angle Set Trip Actual trip
voltage current time time
R - Phase
Y - Phase
B - Phase

Annexure – XI
Binary inputs
S.no Binary input Description Status Remarks
no.
1
2
3
4
5
6
7
8
*Enter all the binary inputs assigned for the relay and check whether the respective function is high/enabled. If
corresponding output is obtained mark as OK, else note down the remark.
Annexure – XII
Binary outputs
S.no Binary output Description Status Remarks
no.
1
2
3
4
5
6
7
*Give high inputs for the binary inputs assigned for the relay and check whether the respective output is high. If
corresponding output is obtained mark as OK, else note down the remark.
LARSEN & TOUBRO CONSTRUCTION PROCEDURE NO:
Power Transmission & Distribution T&C/T& C P/AIS-GIS/001

TESTING AND COMMISSIONING PROCEDURE Page 208 of 223

Annexure XIII
LED
S.No LED No. Description Status Remarks
1
2
3
4
5
*Perform the respective LED operation in the relay by giving high DC input and check whether the respective
LED in glowing.

Annexure – XIV
Undervoltage protection
• Set voltage =
• Set time =
• Applied voltage =
• Actual time =

Annexure – XV
Overvoltage protection
• Set voltage =
• Set time =
• Applied voltage =
• Actual time =

ANNEXURE XVI
AUXILIARY RELAY /TC SUPERVISION RELAY/ FUSE FAILURE RELAY

S. NO CHECK DESCRIPTION OBSERVATION / INFERENCE


VALUE
1 Relay type and name plate details
2 Relay coil rated voltage
3 Relay checked physically and no
LARSEN & TOUBRO CONSTRUCTION PROCEDURE NO:
Power Transmission & Distribution T&C/T& C P/AIS-GIS/001

TESTING AND COMMISSIONING PROCEDURE Page 209 of 223

damages found
4 Internal wiring of relay checked
5 IR test for all terminals of relay and AC
to DC terminals
6 Pick up voltage
7 Drop off voltage
8 Checked the operation of
electrical/mechanical targets and flags
9 Checked the operation of relay contacts

ANNEXURE XVII
SUPERVISION RELAY
PANEL NO: _________________________ LOCATION: _________________________
S. NO CHECK DESCRIPTION OBSERVATION / INFERENCE
VALUE
1 Relay type and name plate details
2 Relay coil rated voltage
3 Relay checked physically and no
damages found
4 Internal wiring of relay checked
5 IR test for all terminals of relay and AC
to DC terminals
6 Pick up voltage “A coil’
“B coil”
“C coil”
7 Drop off voltage “A coil’
“B coil”
“C coil”
8 Checked the operation of
electrical/mechanical targets and flags
9 Checked the operation of relay contacts
10 Coils picked up in pre-close supervision.
Coils picked up in post-close supervision
LARSEN & TOUBRO CONSTRUCTION PROCEDURE NO:
Power Transmission & Distribution T&C/T& C P/AIS-GIS/001

TESTING AND COMMISSIONING PROCEDURE Page 210 of 223

ANNEXURE XVIII
FINAL CHECKS
Test wiring removed
Disturbed customer wiring rechecked
Circuit breaker operation counter reset
Current counters reset
Event recorder reset
Fault record reset
Disturbance record reset
Alarm reset
LEDs reset

Annexure – XIX
Calibration status table
S. No Instrument description Range Calibration status
LARSEN & TOUBRO CONSTRUCTION PROCEDURE NO:
Power Transmission & Distribution T&C/T& C P/AIS-GIS/001

TESTING AND COMMISSIONING PROCEDURE Page 211 of 223

PROCEDURE FOR TESTING BUSBAR


PROTECTION RELAYS
LARSEN & TOUBRO CONSTRUCTION PROCEDURE NO:
Power Transmission & Distribution T&C/T& C P/AIS-GIS/001

TESTING AND COMMISSIONING PROCEDURE Page 212 of 223

1.0 Scope:
The procedure covers pre commissioning test of busbar relay along with the scheme checking which is to be
done and test report formats are enclosed.
2.0 Purpose:
This procedure is prepared to carry out various pre commissioning test in a systematic manner on distance relays
and busbar relays as per scheme to ensure the healthiness of relays.

3.0 Pre-Requisites
3.1 System Requirement:
1. Final settings of the relay.
2. 220V DC power supply.
3. 230V AC, single phase supply with proper grounding.
4. All internal wirings are done according to the drawings.
5. Relay terminal drawing.
6. Make sure that the CT and PT inputs are terminated according to the drawings.

4.0 Requirement of testing kits:


S.No Testing kit Range
1 Relay test kit ( Omicron/Ponovo/freja/SMRT or any 0-25A, AC from single channel
equivalent) 250V auxillary DC
300V AC
2 Laptop with testing kit software and relay software

5.0 Requirement of testing instruments:


1. Digital multimeter.
2. 500V Insulation tester.
3. Polarity tester.
4. Test plug, Ethernet cable, serial port connector and other test leads.

6.0 Hazards and precautions:


1. Unauthorized persons should not be allowed to enter the testing area.
2. Ensure proper grounding of the panel is done.
3. Ensure proper grounding of the testing kit.
4. Ensure that the auxillary supply given to the relay is proper and is according to the relay
manual.
LARSEN & TOUBRO CONSTRUCTION PROCEDURE NO:
Power Transmission & Distribution T&C/T& C P/AIS-GIS/001

TESTING AND COMMISSIONING PROCEDURE Page 213 of 223

5. Ensure that all the terminal connections are tight.


6. Availability of tester and other tools is ensured.
7. There should be no temporary supply (hooking of supply) for testing.
8. Ensure healthiness of test leads.
9. Ensure that the supply used is with MCB protection.

7.0 Post installation checks:


Post installation checks should be done according to the annexure enclosed.

8.0 Testing procedure:


Busbar scheme containing Main-I and Main-II for protection (for double bus transfer scheme). Each of the
protection is given separate CT core. If Main-II is not available then check zone is included via logic in the same
Main-I relay. But testing procedure is same.
The testing of the busbar protection contains the following tests,
Pickup test for every bay:
o Keep all the bays at one (same) isolator position.
o Connect the relay test kit current channels to the CT point in the relay (Main-I).
o Also connect another current channel in CT point of another relay (Main-II).
o Now inject the pickup current in both the current channels for one phase, as per the settings
provided. Repeat the procedure for other phases.
o Check for the tripping of the all the bays with same isolator position.
o Now keep all the bays in another isolator position and repeat the procedure.
o Check the tripping in this position and repeat the procedure for other phases. Ensure the
tripping of all the bays as per the isolator position.

CT Supervision condition:
This check in the testing is done only for relays where Main-I and Main-II protection are provided.
o Connect the bays with one isolator position.
o Inject the set quantity of the current (50-500mA) in Main-I relay. Wait for the delay time for
the CT supervision to be operated in Main-I.
o Now inject pickup current in Main-II relay in the same phase in which CT supervision is
picked up. Check for the relay tripping for all the bays.
o Now repeat the procedure with other isolator position. Check the tripping by injecting current
in other phases also.
o Now create the condition of CT supervision alarm in Main-II relay by injecting set quantity of
current after certain time delay.
LARSEN & TOUBRO CONSTRUCTION PROCEDURE NO:
Power Transmission & Distribution T&C/T& C P/AIS-GIS/001

TESTING AND COMMISSIONING PROCEDURE Page 214 of 223

o Inject current in Main-I relay and repeat the above procedure for all the phases and isolator
position.

** Note that when testing the tripping of the bus coupler bay, If bus coupler bay is closed, then trip signal is
given for the bays with isolator position in which pickup current is injected and bus coupler. Check for the other
isolator position also. Ensure that the remaining bay with other isolator position does not trip.
If pickup test is done for bus coupler bay, then all the bays irrespective of the isolator position trips.
In all the conditions note down the trip time of the relay from the feedback given to the test kit.
LBB relay / initiation:
o Now inject current in any one of the bay at busbar panel, and trip the master trip relay of the particular
bay in the protection panel end. This produces the LBB initiation to the busbar relay as there is current
in the CT secondary.
o Once LBB initiation is given to the busbar relays, the busbar relay gives LBB trip signal tripping the
individual master trip relay in the busbar panel. If still current prevails in the channel the LBB
operates all the bays by operating the busbar according to the isolator position. At each time note
down the LBB trip time at the busbar relay end from the events list.

9.0 Other protections:


9.1 Under frequency protection:
i. Enter the approved setting in the relay.
ii. Disable all other protections, and now apply voltage at the voltage terminals at nominal frequency.
iii. Now decrease the frequency in steps of smaller value.
iv. Note down the trip time in the annexure, and verify it with the settings.

9.2 Over- frequency protection:


i. Enter the approved setting in the relay.
ii. Disable all other protections, and now apply voltage at the voltage terminals at nominal frequency.
iii. Now increase the frequency in steps of smaller value.
iv. Note down the trip time in the annexure, and verify it with the settings.

9.3 Rate of change of frequency protection:


i. Enter the approved setting in the relay.
ii. Now disable all other protections.
iii. Using the test kit, apply nominal voltage at nominal frequency.
iv. Now vary the frequency with some specified step size and step time. This simulates the condition of
rate of change of frequency.
v. Now note down the trip time and the end frequency at which the trip occurred.
LARSEN & TOUBRO CONSTRUCTION PROCEDURE NO:
Power Transmission & Distribution T&C/T& C P/AIS-GIS/001

TESTING AND COMMISSIONING PROCEDURE Page 215 of 223

Annexure –I
Name Plate Details
Relay make :
Relay serial No. :
Test kit make :
Test kit serial no. :
Protection to :

Annexure – II
Post Installation Check List
S.No Description Status Remarks, record
Yes No discrepancies, if any
1 Equipment is cleaned and free from dust / dirt, foreign
materials etc.
2 Auxillary power supply is proper
3 All the settings are done as per the approved settings
received
4 Check that earthing bus continuity inside the panel &
connection of earth bus to station grounding mat is
completed
5 The logic file for input/ output/ LED configuration is
loaded according to the approved as built drawing
6 Binary inputs assigned are checked
7 Binary outputs assigned are checked
8 LED assigned are checked
9 Check factory test certificates are available and are as
per specifications for all relays, meters etc
10 Check that no unwanted tools or material are left near
the panel
11 Check that all cables are connected as per schedule and
interconnection chart
12 Check that all temporary loops & connections
provided for the purpose of conducting any test
are removed each time at the end of each test.
LARSEN & TOUBRO CONSTRUCTION PROCEDURE NO:
Power Transmission & Distribution T&C/T& C P/AIS-GIS/001

TESTING AND COMMISSIONING PROCEDURE Page 216 of 223

Annexure – III
BUSBAR PROTECTION
Bay No. Set differential Operating Trip time, in sec Remarks /
current, in amp differential current, Conditions
in amp

ANNEXURE – IV
LOCAL BREAKER BACK UP RELAY
DESCRIPTION VALUE

Setting range
Model number
Auxiliary voltage
Serial number
External resister

LBB re-trip in particular bay:


Bay Current Set operating Actual operating time
No. injected, time Remarks
Amp R Y B
LARSEN & TOUBRO CONSTRUCTION PROCEDURE NO:
Power Transmission & Distribution T&C/T& C P/AIS-GIS/001

TESTING AND COMMISSIONING PROCEDURE Page 217 of 223

LBB backup trip:

Bay Current Set operating Actual operating time, in sec


no. injected, time, in sec Remarks
Amp R Y B

Annexure – V
FREQUENCY PROTECTION
Under frequency protection:
Phase Set frequency, in Hz Applied frequency, in Hz Trip time, in sec

Over frequency protection:


Phase Set frequency, in Hz Applied frequency, in Hz Trip time, in sec
LARSEN & TOUBRO CONSTRUCTION PROCEDURE NO:
Power Transmission & Distribution T&C/T& C P/AIS-GIS/001

TESTING AND COMMISSIONING PROCEDURE Page 218 of 223

Rate of change of frequency protection:


Phase Set RCF, in Applied Start frequency, Hz End frequency, Hz Trip time, in sec
Hz/s RCF, in Hz/s

Annexure – VI
Calibration status table
S. No Instrument description Range Calibration status
LARSEN & TOUBRO CONSTRUCTION PROCEDURE NO:
Power Transmission & Distribution T&C/T& C P/AIS-GIS/001

TESTING AND COMMISSIONING PROCEDURE Page 219 of 223

BCU inputs and outputs (For Line Bays)

Inputs
Outputs
• CB status
• Isolator status
• Earth switch status
• CB oil level low alarm • CB open command
• CB SF6 gas normal • CB close command
• CB motor circuit abnormal • Isolator open command
• CB hydraulic pressure alarm • Isolator close command
• CB pole discrepancy • Prepare 3PH trip (AR lockout)
• L/R switch in local • CB trip command for DT CH-1
• L/R switch in remote • CB trip command for DT CH-2
• N/M switch in normal
BCU • CB autoreclose command
• N/M switch in maintenance • 86A reset
• Busbar reset • 86B reset
• Islanding reset • Bus-1 selected
• Group A operated • Bus-2 selected
• Group B operated • Bus-1 MCB tripped
• Carrier CH-1 fail • Bus-2 MCB tripped
• Carrier CH-2 fail
• Incoming DC-1 fail
• Incoming DC-2 fail
• Autoreclosure start
• Autoreclosure block
• 3PH trip

*NOTE: Additional inputs for GIS -


i) 89A SF6 stage 1 low gas alarm
ii) 89A SF6 stage 2 low gas alarm
iii) 89B SF6 stage 1 low gas alarm
iv) 89B SF6 stage 2 low gas alarm
v) 89L SF6 stage 1 low gas alarm
vi) 89L SF6 stage 2 low gas alarm
vii) CB SF6 stage 1 low gas alarm and closing lockout.
viii) CB SF6 stage 2 low gas alarm and tripping lockout.
LARSEN & TOUBRO CONSTRUCTION PROCEDURE NO:
Power Transmission & Distribution T&C/T& C P/AIS-GIS/001

TESTING AND COMMISSIONING PROCEDURE Page 220 of 223

BCU inputs and outputs (For Transformer Bays)


Inputs
• CB status
• Isolator status
• Earth switch status
Outputs
• CB oil level low alarm
• CB SF6 gas normal
• CB open command
• CB motor circuit abnormal
• CB close command
• CB hydraulic pressure alarm
• CB pole discrepancy
• Isolator open command
• L/R switch in local • Isolator close command
• L/R switch in remote • Bus-1 selected
• N/M switch in normal • Bus-2 selected
• N/M switch in maintenance BCU • HV CB open position (for
• Busbar reset interlock)
• Islanding reset • HV CB closed position
• Group A operated (for interlock)
• Group B operated
• Tap raiser
• Running fan fail
• Tap lower
• Standby fan fail
• Control Supply in transformer
fail
• Common thermal OL trip
• Incoming DC-1 fail
• Incoming DC-2 fail
• Cooler supply change over
• LV CB open
• LV protection reset
• LV earth switch open
Analog Inputs
• Winding temperature
• Oil temperature
• Tap position
LARSEN & TOUBRO CONSTRUCTION PROCEDURE NO:
Power Transmission & Distribution T&C/T& C P/AIS-GIS/001

TESTING AND COMMISSIONING PROCEDURE Page 221 of 223

BCU inputs and outputs (For Generator Bays)


(*for Non GCB scheme, with control in SS)
Inputs
Outputs
• CB status
• Isolator status • CB open command
• Earth switch status • CB close command
• CB oil level low alarm • Isolator open command
• CB SF6 gas normal • Isolator close command
• CB motor circuit abnormal • Bus-1 selected
• CB hydraulic pressure alarm BCU • Bus-2 selected
• CB pole discrepancy
• Bus-1 MCB tripped
• L/R switch in local
• Bus-2 MCB tripped
• L/R switch in remote
• N/M switch in normal • CB close permissive
• N/M switch in maintenance
• Busbar reset
• Islanding reset
• Group-1 A/B/C operated
• Group-1 A/B/C operated
• Incoming DC-1 fail
• Incoming DC-2 fail
• LV ES open
• LV CB open
LARSEN & TOUBRO CONSTRUCTION PROCEDURE NO:
Power Transmission & Distribution T&C/T& C P/AIS-GIS/001

TESTING AND COMMISSIONING PROCEDURE Page 222 of 223

PROTECTION Inputs and Outputs (For line bays)


Inputs Outputs
• Carrier receive CH-1 • Carrier send CH-1
• Carrier receive CH-2 • Carrier send CH-2
• Carrier fail CH-1 • Earth fault trip
• Over voltage trip
• Carrier fail CH-2
• 3PH general trip
• Carrier switch in out position Protection • Line UV
main-1 Relay • CB RPH open
• Carrier switch in out position
• CB YPH open
main-2 • CB BPH open
• Carrier speech fail CH-1 • Broken conductor trip
• AR start • Busbar operated(AR block to
• AR block AR relay)
• 3PH trip • Islanding operated(AR block
to AR relay)

PROTECTION Inputs and Outputs (for


transformer bays)
Inputs Outputs

• Oil level low alarm from


conservator
• WTI alarm • OTI trip
• WTI trip • WTI trip
• OTI alarm Protection • Differential operated
• OTI trip Relay • Overcurrent operated
• PRD trip (main tank) • Earth fault operated
• OSR trip (OLTC) • REF trip
• Buchholz alarm
• Buchholz trip
• Fire protection trip
LARSEN & TOUBRO CONSTRUCTION PROCEDURE NO:
Power Transmission & Distribution T&C/T& C P/AIS-GIS/001

TESTING AND COMMISSIONING PROCEDURE Page 223 of 223

BCU to SCADA

i) All datas are available in soft logic in BCU from which it can be extracted to SCADA.
ii) The data packets are routed through Ethernet switches according to the addresses given.

Consider the below example,


Let there be 4 BCU’s with addresses of
BCU/RELAY 1 = 172.1.201.1
BCU/RELAY 2 = 172.1.202.1
BCU/RELAY 3 = 172.1.203.1
BCU/RELAY 4 = 172.1.204.1

Now the address of the master SCADA system is 172.1.200.0


This enables all the active devices to be in one group.

SCADA
172.1.200.0

Ethernet switch 1 Ethernet switch 2 Ethernet switch 3 Ethernet switch 4

Eg: CB
Status

BCU/RELAY 1 BCU/RELAY 2 BCU/RELAY 3 BCU/RELAY 4


172.1.201.1 172.1.202.1 172.1.203.1 172.1.204.1

Denotes the flow of data from BCU 1 to the SCADA system (CB
status).

Denotes the failure of the communication link which forces the data
to take other route as shown.

Denotes the communication ring formation.

You might also like