Professional Documents
Culture Documents
T&C/T& C P/AIS-GIS/001
TESTING & COMMISSIONING PROCEDURE FOR
SWITCHYARD EQUIPMENTS &SWITHGEARS Page 76 of 187
1.0 SCOPE
This procedure covers the Pre commissioning Test for Circuit Breakers
2.0 PURPOSE
This procedure is prepared to carry out various pre- commissioning tests to be conducted in
systematic manner for Circuit Breakers to ensure the healthiness and performance of the
equipment.
3.0 PRE-REQUISITES
SYSTEM REQUIREMENTS
1. Relevant Drawings and layouts.
2. 415 V AC, 3 Ph power supply is available for Testing.
3. All Cables pertaining to Circuit Breakers were laid & terminated.
4. Make sure that the equipment erected is as per approved drawings & Layouts.
5. Check the Name Plate & Rating Plate Of the equipment Erected.
4. Ensure protection MCB is provided in the circuit of AC supply used for testing
5. Ensure Proper Tools & Tackles are Available for carrying out Tests.
6. Ensure Proper PPE ( Personal Protective Equipments) are used
7. Ensure the Healthiness of the test leads (Check for any insulation Damages).
8. Competent Authority to maintain shutdown & Work permit system in existing Live Bay works.
9. Any conducting element should be carried horizontally at waist level in the area used for pre-
commissioning tests.
b) Connect the Multi meter across the Lock out Contact Terminal of Density Monitor.
c) The Contact should open after the lock out pressure is reached
d) Connect the Multi meter across the Low alarm Contact Terminal of Density Monitor.
e) The Contact should open after the low pressure point is reached
b) By regulating the flow rate of SF6 gas (0.2 liter/min to 0.5 liter/min - ref. IEC 60480), the
value of dew point is observed till it becomes stable.
c) If the regulating valve is provided at outlet of the dew point kit then values as given in
Doc. no. for rated pressure is to be monitored.
Dew Point of SF6 gas varies with pressure at which measurement is being carried out. This
Is due to the fact that Saturation Vapour Pressure decreases with increase in Pressure of the
SF6 gas. Hence, dew point of SF6 gas at higher pressure is lower than dew point at
Atmospheric pressure Therefore, it is to be ensured that if measurement has been done at a
Pressure other than the atmospheric pressure; same is to be converted to the atmospheric
Pressure as given in the table below used at the time of commissioning for various CB
Manufacturers: Method for converting dew point at different gas pressures, is
LARSEN & TOUBRO LIMITED-ECC DIVISION PROCEDURE NO:
T&C/T& C P/AIS-GIS/001
TESTING & COMMISSIONING PROCEDURE FOR
SWITCHYARD EQUIPMENTS &SWITHGEARS Page 80 of 187
Given/described in IEC-60480.
Sl. Make of CB Dew point at Dew point at Atmospheric
rated pressure Pressure ( Limit )
No.
1 BHEL -15̊ C -36̊C
ANNEXURE – I
Details of Equipment
LOA No. :
Make :
Type: :
Sl. No. :
Year of manufacture:
Feeder Name :
Operating Voltage:
Control Voltage:
ANNEXURE – II
Post Installation check list
ANNEXURE – III
ANNEXURE – IV
ANNEXURE – V
Caution: Isolate necessary DC for trip coils and closing coil before measuring
Control Circuit
Main Circuit
ANNEXURE – VI
Operating Time Measurement Test
ANNEXURE – VII
Pump details
Make Volt
Sl. No. Amp.
Type HP/kW
Year of manufacture Oil setting
Operations check:
Oil pressure drop during operations and pump running time in seconds
Motor details:
Make Volt
Sl. No. Amp.
Type HP / kW
Year of manufacture Setting (Thermal
overload)
ICU details:
Make
Sl. No.
Type
Discharge
Capacity
Year of manufacture
Leakage check:
Air pressure drop in 24 hours:
Motor details:
Make Volt
Sl. No. Amp.
Type HP / kW
Year of manufacture Setting (Thermal
overload)
Circuitry/Operational Checks
Check for annunciation in control room as per the following formats and record the
reading
S. Description of test Source of Window description Result Remarks
No. initiation
A Switch off the Dc switch in Control cubicle Source I / II DC fail /
control cubicle DC switch ON / AC fail
OFF
B Switch off the AC switch in Control cubicle Source I / II DC fail /
control cubicle AC switch ON / AC fail
OFF
C Short the alarm contacts of SF6 Density Monitor SF6 gas density low
gas density monitor (R-Phase)
D Short the alarm contacts of SF6 Density Monitor SF6 gas density low
gas density monitor (Y-Phase)
LARSEN & TOUBRO LIMITED-ECC DIVISION PROCEDURE NO:
T&C/T& C P/AIS-GIS/001
TESTING & COMMISSIONING PROCEDURE FOR
SWITCHYARD EQUIPMENTS &SWITHGEARS Page 91 of 187
E Short the alarm contacts of SF6 Density Monitor SF6 gas density low
gas density monitor (B-Phase)
F Remove the cable connected to Density Monitor Operation / closing
Density monitor (R-Phase) lockout
G Remove the cable connected to Density Monitor Operation / closing
Density monitor (Y-Phase) lockout
H Remove the cable connected to Density Monitor Operation / closing
Density monitor (B-Phase) lockout
I Give tripping command to R-Ph Pole discrepancy Breaker pole
only and check the operation of relay at breaker discrepancy
pole discrepancy relay cubicle
J Give tripping command to Y-Ph Pole discrepancy Breaker pole
only and check the operation of relay at breaker discrepancy
pole discrepancy relay cubicle
K Give tripping command to B-Ph Pole discrepancy Breaker pole
only and check the operation of relay at breaker discrepancy
pole discrepancy relay cubicle
L Check other alarms as per plant
circuit diagram
M Close the breaker and trip Protective relay Breaker auto trip
through protection which are as per scheme
applicable
i) Main – I Breaker auto trip
ii) Main – II Breaker auto trip
iii) Over Voltage Breaker auto trip
iv) LBB Breaker auto trip
v) Bus bar Breaker auto trip
vi) Differential Breaker auto trip
vii) Carrier inter tripping Breaker auto trip
viii) Back up O/C & E/F Breaker auto trip
ix) Restricted earth fault Breaker auto trip
S. Description of test Source of Window description Result Remarks
No. initiation
x) Over fluxing Breaker auto trip
xi) OTI trip Breaker auto trip
xii) WTI trip Breaker auto trip
xiii) Buchholz trip Breaker auto trip
xiv) PRD Breaker auto trip
xv) TEE differential Breaker auto trip
LARSEN & TOUBRO LIMITED-ECC DIVISION PROCEDURE NO:
T&C/T& C P/AIS-GIS/001
TESTING & COMMISSIONING PROCEDURE FOR
SWITCHYARD EQUIPMENTS &SWITHGEARS Page 92 of 187