WORK BREAKDOWN STRUCTURE DICTIONARY

CONTROL ACCOUNT CODE ACTIVITY COST RESPONSIBLE RISKS


1.1 STEEL WORK $15 Million
Samsung Engineering Risk of height, wind pressure
1.2 BRAND SELECTION
1.3 Y SHAPE SOM, Chicago Change in design effect on cost, time
1.4 WELDING $6 Million
Risk of height, sun heat
1.5 DRILLING $7 Million Samsung Engineering
GREY STRUCTURE
1.6 CONCRETE WORK $20 Million
1.7 FOUNDATION $7 Million Brookfield multiplex
1.8 EXCAVATION $5 Million Baier and ME foundation Materials & their durability
1.9 LEVELLING $6 Million
Besix and Arbatec
1 10 CONCRETE PLACEMENT $15 Million
2.1 POWER WORK $18 Million
2.2 CONDUIT PIPING $10 Million
Change in design effect on cost, time
2.3 WIRES INSTALLATION $12 Million
2.4 SOCKETS, SWITCHES, A.C $30 Million
ELEVATORS Otis
2.5 LIFT DESIGN $20 Million Effect of gravity on tall buildings
2.6 LIFT CAPACITY $5 Million
2.7 LIFT SPEED $3 Million
2.8 INTERIOR $10 Million
3.1 WIND PRESSURE TESTING $0.5 Million
wind pressure, working at height
3.2 PANEL SELECTION
GLASS WORK 3.3 ALUMINUM/ UPVC $35 Million Al Ghurair Group Scaffolding failure
3.4 PANEL SELECTION Risk of collapse
3.5 GLASS INSTALLATION $17 Million Workers exposed to sun radiation at height
4.1 DESIGN
4.2 MATERIAL $20 Million Transport of material to such heights
4.3 SELECT WOOD
WOOD WORK Dorma
4.4 SELECT COLOR Workers working at height
ROOM HARDWARE,
4.5 $40 Million Objects falling from height
CUPBOARDS, CABINETS
5.1 CABLE TESTING $5 Million
Internal travel/transport within building

NETWORK INFRASTRUCTURE Hyder Consulting


Internal travel/transport within building
5.2 CABLE BRAND
5.3 CONDUIT PIPING $15 Million
Workers working at height
NETWORK INFRASTRUCTURE 5.4 WIRES INSTALLATION $10 Million Hyder Consulting
5.5 SURVEY $5 Million Escape route from height
5.6 CABLE NETWORK $16 Million Transport of material to such heights
5.7 DESIGN $5 Million Danger of site machinery
on at height