This document outlines a work breakdown structure dictionary for a construction project. It lists 15 main work packages with over 50 sub-tasks and provides estimates for cost and responsibilities. Some key risks are also identified such as working at heights, wind pressure, scaffolding failure, and transporting materials to high levels. The total estimated cost is over $350 million with the largest shares going to concrete work, lifts, glass work, and wood work. Various contractors and consulting firms are assigned responsibility for the different tasks.
This document outlines a work breakdown structure dictionary for a construction project. It lists 15 main work packages with over 50 sub-tasks and provides estimates for cost and responsibilities. Some key risks are also identified such as working at heights, wind pressure, scaffolding failure, and transporting materials to high levels. The total estimated cost is over $350 million with the largest shares going to concrete work, lifts, glass work, and wood work. Various contractors and consulting firms are assigned responsibility for the different tasks.
This document outlines a work breakdown structure dictionary for a construction project. It lists 15 main work packages with over 50 sub-tasks and provides estimates for cost and responsibilities. Some key risks are also identified such as working at heights, wind pressure, scaffolding failure, and transporting materials to high levels. The total estimated cost is over $350 million with the largest shares going to concrete work, lifts, glass work, and wood work. Various contractors and consulting firms are assigned responsibility for the different tasks.
CONTROL ACCOUNT CODE ACTIVITY COST RESPONSIBLE RISKS
1.1 STEEL WORK $15 Million Samsung Engineering Risk of height, wind pressure 1.2 BRAND SELECTION 1.3 Y SHAPE SOM, Chicago Change in design effect on cost, time 1.4 WELDING $6 Million Risk of height, sun heat 1.5 DRILLING $7 Million Samsung Engineering GREY STRUCTURE 1.6 CONCRETE WORK $20 Million 1.7 FOUNDATION $7 Million Brookfield multiplex 1.8 EXCAVATION $5 Million Baier and ME foundation Materials & their durability 1.9 LEVELLING $6 Million Besix and Arbatec 1 10 CONCRETE PLACEMENT $15 Million 2.1 POWER WORK $18 Million 2.2 CONDUIT PIPING $10 Million Change in design effect on cost, time 2.3 WIRES INSTALLATION $12 Million 2.4 SOCKETS, SWITCHES, A.C $30 Million ELEVATORS Otis 2.5 LIFT DESIGN $20 Million Effect of gravity on tall buildings 2.6 LIFT CAPACITY $5 Million 2.7 LIFT SPEED $3 Million 2.8 INTERIOR $10 Million 3.1 WIND PRESSURE TESTING $0.5 Million wind pressure, working at height 3.2 PANEL SELECTION GLASS WORK 3.3 ALUMINUM/ UPVC $35 Million Al Ghurair Group Scaffolding failure 3.4 PANEL SELECTION Risk of collapse 3.5 GLASS INSTALLATION $17 Million Workers exposed to sun radiation at height 4.1 DESIGN 4.2 MATERIAL $20 Million Transport of material to such heights 4.3 SELECT WOOD WOOD WORK Dorma 4.4 SELECT COLOR Workers working at height ROOM HARDWARE, 4.5 $40 Million Objects falling from height CUPBOARDS, CABINETS 5.1 CABLE TESTING $5 Million Internal travel/transport within building
NETWORK INFRASTRUCTURE Hyder Consulting
Internal travel/transport within building 5.2 CABLE BRAND 5.3 CONDUIT PIPING $15 Million Workers working at height NETWORK INFRASTRUCTURE 5.4 WIRES INSTALLATION $10 Million Hyder Consulting 5.5 SURVEY $5 Million Escape route from height 5.6 CABLE NETWORK $16 Million Transport of material to such heights 5.7 DESIGN $5 Million Danger of site machinery on at height