You are on page 1of 26

Chap 6

MATERIAL HANDLING

Luu Van Thanh


Lecture outline
1. Introduction
2. Material handling principles
3. Designing material handling systems
4. Unit load design
5. Material handling equipment
6. Estimating material handling costs
7. Safety considerations

2
I. Introduction
• Material Handling accounts for:
– 25% of all employees,
– 55% of all factory space,
– 87% of production time
– 15-70% of the total cost of a manufactured product

• 3-5% of all material handled becomes damaged


– “Totally eliminate”
– However, handling less is not the answer.

3
Definitions:
• Material handling (MH) is the art and science of moving, storing,
protecting, and controlling of goods and materials.
– Moving: Required to create time and place utility. The value of
having the material at the right time and the right place.
– Storing: Provides a buffer between operations, facilitates the
efficient use of people and machines.
– Protecting: Includes the packaging, packing against damage
and theft.
– Controlling: Physical: Orientation, sequence and space
between material.
Status: Real-time awareness of the location, amount,
destination, origin, ownership, and schedule of material.

4
Definitions:
• MH means providing the right amount of the right material, in
the right condition, at the right place, in the right position, in
the right sequence, and for the right cost, by the right
methods.
- Right amount: how much inventory is needed?
- Right material
- Right condition: state in which customer desires the material
- Right sequence
- Right place: address both transportation and storage
- Right time: on-time delivery
- Right cost: not necessary the lowest cost
- Right method.
II. MH Principles

1. Planning
9. Environmental 10. Life Cycle Cost

2. Standardization
8. Automation

MH
7. System 3. Work principle

6. Space Utilization 4. Ergonomic


5. Unit load

6
Conditions for improvement
System not capable Idle production
No pre-kitting of of change or equipment due to
work expansion material shortage

Material piled
Automatic data
directly on floor
collection system
not used
MH
Backtracking of In-plant containers
material not standardized

Operators travel
Misdirected material excessively for
materials and
Excessive
supplies
demurrage
7
III. Designing material handling systems (MHS)

Six-step engineering design process:


1. Define the objectives and scope for the material handling system.
2. Analyze the requirements for moving, storing, protecting, and
controlling material.
3- Generate alternative designs for meeting material handling
system requirements.
4. Evaluate alternative material handling system designs.
5. Select the preferred design for moving, storing, protecting, and
controlling material.
6. Implement the preferred design, including the selection of
suppliers, training of personnel, installation, debug and startup of
equipment, and periodic audits of system performance.
8
1. Developing Alternative MHS Designs

NADLER’s IDEALS approach:

1. Aim for the theoretical ideal system.


2. Conceptualize the ultimate ideal system.
3. Design the technologically workable ideal system.
4. Install the recommended system.

9
2. The MHS equation & questions
The MHS equation:
Materials + Moves +
Methods =
Recommended systems

The What Question The How Question


1. What are the types of material to be moved? 1. How is the material moved or stored? How should
2. What are their characteristics? material be moved or stored? What are the alternative
3. What are the amounts moved and stored? ways of moving or storing the material?
2. How much inventory should be maintained?
The Where Question 3- How is the material tracked? How should the material
be tracked?
• Where is the material coming from? Where should it 4. How should the problem be analyzed?
come from?
• Where is the material delivered? Where should it be The Who Question
delivered? 1. Who should be handling material? What are the
• Where is the material stored? Where should it be required skills to perform the material handling tasks?
stored? 2. Who should be trained to service and maintain the
• Where can material handling tasks be eliminated, material handling system?
combined or simplified? 3. Who should be involved in designing the system?
• Where can you apply mechanization or automation? The Which Question
The When Question 1. Which material handling operations are necessary?
1. When is material needed? When should it be moved? 2. Which type of material handling equipment, if any,
2. When is it time to mechanize or automate? should be considered?
3. When should we conduct a material handling 3. Which material handling system is cost effective?
performance audit? 4. Which alternative is preferred? 10
3. MH planning chart

Fig 05_02: MH planning chart for an air flow regulator.


Key: Operation – O, Transportation – T, Storage – S, Inspection – I. 11
IV. UNIT LOAD design
Larger unit load:
“Picked up and moved between two + fewer moves
locations as a single mass”
- bigger and heavier equipment
- wider aisles
Example:
- higher floor load capacities
1. a single item picked up and moved
- increased work-in-process inventory
manually between two locations
Smaller unit load:
2. Two tote pans with identical
components picked up moved by a + reduced work-in-process inventory
dolly from one machine to another + simple material handling methods
3. One pallet load of nonuniform-size (i.e., push carts)
cartons with different products + reduced completion time (How??)
picked up and moved by a lift truck - more moves
from the packaging area to the - increased material handling time
shipping dock
“Achieving single unit production
4. One full load of products delivered requires the materail handling time to
by a trucktrailer from a warehouse be shorter than the unit processing
to a customer store If the trailer is time.”
half full, it is still one unit load. 12
Fig 05_03
illustrates the effects
of the unit load size
on job completion
times

13
Fig 05_04
shows several
stages in the
material flow
process where
dimensional
relationships
play a major
role.

14
Fig 05_05
shows why
these two
features
play key
roles in
moving
and storing
containers

15
Efficiency of returnable containers
• Given the following dimensions of a plastic reusable containers:
– Inside dimensions: 18” x 11” x 11”
– Outside dimensions: 20” x 12” x 12”
– Each nested container: 20” x 12” x 2”
– The storage opening : 24” x 16” x 14”
A trailer with inside dimensions of 240” x 120” x 120” is used to transport these containers.
Assume no clearance is needed.

Determine the following:


1. Container space utilization: container efficiency: (18” x 11” x 11”)/(20” x 12” x 12”) = 0.76
2. Storage space efficiency : (18” x 11” x 11”)/(24” x 16” x 14”) = 0.45
3. Container nesting ratio: 12”/2” = 6: the ratio is 6:1
4. Trailer space utilization if all containers are stacked vertically in only one orientation
i. In the trailer length: 240”/20” = 12 containers
ii. In the trailer width: 120”/ 12’ = 10 containers
iii. In the stack vertically: 120”/ 12’ = 10 containers
iv. The total numbers of containers: 12x10x10 = 1200.
v. The trailer space utilization: (18” x 11” x 11”)(1200)/(240” x 120” x 120”) = 0.76
5. Trailer return ratio
i. Number empty containers of one stack 1 + (120” -12”)/2” = 55
ii. Total no. of empty containers per trailer : 55 x (240”/20”) x (120”/12”) = 6600
iii. The trailer return ratio: 6600/1200 = 5.5
16
Significant cost reduction may be achieved with higher trailer return ratios.
Fig 05_06
Shows a
container/pallet
system with
progressive
dimensions.

17
Unit load interactions with warehouse components

18
The pallet loading pattern for each carton-pallet pair must be prescribed
as shown in two above figures.

19
V. Material handling equipment
Categories of Material Handling Equipment
1. Containers and Unitizing Equipment
• Containers
• Unitizers
2. Material Transport Equipment
• Conveyors
• Industrial Vehicles
• Monorails, Hoists, and Cranes
3. Storage and Retrieval Equipment
• Unit Load Storage and Retrieval
• Unit Load Storage Equipment
• Unit Load Retrieval Equipment
• Small Load Storage and Retrieval
4. Automatic Data Collection and Communication Equipment
• Automatic Identification and Recognition
• Automatic Paperless Communication 20
Containers: Tote pans
Containers: Pallets

21
Unitizers: Palletizer Unitizers: Stretchwrapper

22
Conveyors Automatic
identification and
recognition

23
Industrial Vehicles Storage and Retrieval

Monorails, Hoists and Cranes


Stock to operator: Carousels
VI. Estimating material handling costs

• The development of MH design alternatives covers


not just the specification of the “right method of
handling”.
• The recommended alternative is at the “right cost”.
• Estimation of the cost of MH alternatives is not a
trivial task.
• That is a “roughcut” method through the use of
standard data and rules of thumb.

25
VII. Safety considerations
• The key to a safe facility is concentrating on the
interface between the workforce and the
equipment.
• The following table shows recommended aisle
widths for facility design.

26

You might also like