Name of the Project :- Development of NH-31 to 4 lane configuration from km 551.360 to km 563.260 (Ghoshpukur to Bihar More, Bagdogra) in Darjeeling District,West Bengal under EPC Mode'' (Project length-11.90 km.) RFI SUMMARY DATE : Submission Chainage Chainage Proposed Proposed Sl No. RFI No. Side Description of Work Submitted By Status Date (Km) (Km) Inspection Inspection 5957 TIPPLGRDJV/NH-31/HW/ 5931 7-Dec-19 LHS HIGHWAY BC Tack Coat MR. SATYAKI SARKAR 9-Dec-19 11:30 5958 TIPPLGRDJV/NH-31/HW/ 5932 7-Dec-19 LHS HIGHWAY BC BC MR. SATYAKI SARKAR 9-Dec-19 12:30 5959 TIPPLGRDJV/NH-31/HW/ 5933 7-Dec-19 LHS HIGHWAY MEDIAN Kerb Laying MR. SATYAKI SARKAR 9-Dec-19 12:30 5960 TIPPLGRDJV/NH-31/HW/ 5934 7-Dec-19 RHS HIGHWAY BUS BYE Laying 1st MR. SATYAKI SARKAR 9-Dec-19 01:30 5961 TIPPLGRDJV/NH-31/HW/ 5935 7-Dec-19 RHS HIGHWAY BUS BYE wmm 1st MR. SATYAKI SARKAR 9-Dec-19 02:30 5962 TIPPLGRDJV/NH-31/STR/ 5936 7-Dec-19 552+480 LHS Reinforcement checking of RE Pannel STRUCTURE RE PANNEL concreting of RE Pannel MR. ARINDAM SINHA 9-Dec-19 12:30 5963 TIPPLGRDJV/NH-31/STR/ 5937 7-Dec-19 552+480 LHS Concreting of RE Pannel STRUCTURE RE PANNEL PCC MR. ARINDAM SINHA 9-Dec-19 01:30 Reinforcement and shuttering RETAINING 5964 TIPPLGRDJV/NH-31/STR/ 5938 7-Dec-19 553+870 553+940 70 RHS STRUCTURE reinf. Of raft of ret. Wall MR. ARINDAM SINHA 9-Dec-19 02:30 checking of raft of ret. Wall WALL RETAINING concreting of raft of ret. 5965 TIPPLGRDJV/NH-31/STR/ 5939 7-Dec-19 553+870 553+940 70 RHS Concreting of raft of ret. Wall STRUCTURE MR. ARINDAM SINHA 9-Dec-19 02:45 WALL Wall Reinforcement & Shuttering checking 5966 TIPPLGRDJV/NH-31/STR/ 5940 7-Dec-19 553+697 RHS of Abutment Shaft 2nd Lift of A-2 STRUCTURE Minor Bridge Reinf. Of shaft 2nd lift MR. ARINDAM SINHA 9-Dec-19 03:00 (MCW) Concreting of Abutment -2 Shaft 2nd Concreting of shaft 2nd 5967 TIPPLGRDJV/NH-31/STR/ 5941 7-Dec-19 553+697 RHS STRUCTURE Minor Bridge MR. ARINDAM SINHA 9-Dec-19 03:15 lift of MCW lift. Reinforcement & Shuttering Checking 5968 TIPPLGRDJV/NH-31/STR/ 5942 7-Dec-19 554+050 RHS STRUCTURE LVUP reinf. Of deck slab MR. ARINDAM SINHA 9-Dec-19 04:15 of Deck Slab with Bracket of LVUP Concreting of Deck slab with bracket CONCRETING OF DECK 5969 TIPPLGRDJV/NH-31/STR/ 5943 7-Dec-19 554+050 RHS STRUCTURE LVUP MR. ARINDAM SINHA 9-Dec-19 04:20 of LVUP SLAB RETAINING 5970 TIPPLGRDJV/NH-31/STR/ 5944 7-Dec-19 555+066 555+086 20 RHS Excavation for PCC of Ret. Wall STRUCTURE Excavation MR. ARINDAM SINHA 9-Dec-19 04:15 WALL RETAINING 5971 TIPPLGRDJV/NH-31/STR/ 5945 7-Dec-19 555+066 555+086 20 RHS PCC of Ret. Wall STRUCTURE PCC MR. ARINDAM SINHA 9-Dec-19 04:20 WALL Excavation for foundation A-2 of 5972 TIPPLGRDJV/NH-31/STR/ 5946 7-Dec-19 559+982 LHS STRUCTURE Minor Bridge Excavation MR. ARINDAM SINHA 9-Dec-19 02:15 MNB Reinforcement and Shuttering RETAINING 5973 TIPPLGRDJV/NH-31/STR/ 5947 7-Dec-19 560+654 LHS STRUCTURE reinf. Of ret. wall 2nd lift MR. ARINDAM SINHA 9-Dec-19 02:40 checking of ret. Wall 2nd lift WALL RETAINING concreting of ret. wall 2nd 5974 TIPPLGRDJV/NH-31/STR/ 5948 7-Dec-19 560+654 LHS Concreting of ret. Wall 2nd lift STRUCTURE MR. ARINDAM SINHA 9-Dec-19 03:15 WALL lift Level checking of PCC and Layout of 5975 TIPPLGRDJV/NH-31/STR/ 5949 7-Dec-19 562+020 562+030 10 LHS STRUCTURE DRAIN Layout of raft MR. ARINDAM SINHA 9-Dec-19 03:50 Raft of side DRAIN Reinforcement and shuttering 5976 TIPPLGRDJV/NH-31/STR/ 5950 7-Dec-19 562+020 562+030 10 LHS STRUCTURE DRAIN Reinf. Of raft MR. ARINDAM SINHA 9-Dec-19 04:15 checking of raft of side Drain 5977 TIPPLGRDJV/NH-31/STR/ 5951 7-Dec-19 562+020 562+030 10 LHS Concreting of raft of side drain STRUCTURE DRAIN Concreting of raft MR. ARINDAM SINHA 9-Dec-19 04:40 Reinforcement and shuttering 5978 TIPPLGRDJV/NH-31/STR/ 5952 7-Dec-19 553+697 LHS checking of Pedestal of B-3 Type STRUCTURE Minor Bridge Reinf. Of Pedestal MR. ARINDAM SINHA 9-Dec-19 05:00 Bearing Abutment 1&2 Concreting of Pedestal of B-3 type 5979 TIPPLGRDJV/NH-31/STR/ 5953 7-Dec-19 553+697 LHS STRUCTURE Minor Bridge Concreting of Pedestal MR. ARINDAM SINHA 9-Dec-19 05:15 Bearing of Abutment-1&2