REKAPITULASI

PERENCANAAN DED MINI DEPO


DAUR ULANG LIMBAH ELEKTRONIK
BBLM (BALAI BESAR LOGAM DAN MESIN)
BANDUNG
2018

HARGA/ITEM PEKERJAAN
NO. DESKRIPSI
(Rp.)
(1) (2) (3)

A. PREPARATION WORK

B ARCHITECTURAL WORK

B.1 ARCHITECTURAL WORK - 1ST FLOOR


1 WALL AND FINISHING WORK
2 FLOOR WORK
3 CEILING WORK
4 DOOR WORK
5 WINDOW WORK
6 SANITARY WORK
7 PAINTING WORK
8 RAILING WORK
9 SERVICES STAIR WORK
10 CANOPY ROOF WORK

B.2 ARCHITECTURAL WORK - 2ND FLOOR


1 WALL AND FINISHING WORK
2 FLOOR WORK
3 CEILING WORK
4 DOOR WORK
5 WINDOW WORK
6 SANITARY WORK
7 PAINTING WORK
8 STAIR RAILING WORK
9 SERVICES STAIR WORK

B.3 ARCHITECTURAL WORK - 3RD FLOOR


1 WALL AND FINISHING WORK
2 FLOOR WORK
3 WINDOW WORK
4 RAILING WORK

B.4 ROOF ARCHITECTURAL WORK


1 PEKERJAAN ATAP

C SPECIAL WORK
1 SUN SHADING WORK
2 PEKERJAAN PLANG WIREMESH
3 PEKERJAAN SIGNAGE HURUF
4 PEKERJAAN ENTRANCE GATE

D PEKERJAAN LANSEKAP
D.1 PEKERJAAN HARDSCAPE
D.2 PEKERJAAN SOFTSCAPE

E PEKERJAAN STRUKTUR GEDUNG


E.1 Preparation Work
E.2 Soil Work
E.3 Sand Bedding & Lean Concrete
E.4 Concrete Work
E.5 Steel Structure
E.6 Stair Steel Structure
E.7 Machine Foundation Structure
E.8 Steel Roof Structure & Cover

F PEKERJAAN MEKANIKAL PLUMBING DAN ELEKTRIKAL (MEP)


F.1 Electrical Work
F.2 Roof Vertical Drain
F.3 Clean & Waste Water (Plumbing) Installation
F.4 Fire Prevention & Protection

JUMLAH
PAJAK PPN
JUMLAH TOTAL
PEMBULATAN
IN)

SUB JUMLAH LUAS HARGA/m2


(Rp.) (m2) (Rp.)
(4) (5) (6)
-
-
-
-
RENCANA ANGGARAN BIAYA (RAB)
PERENCANAAN DED MINI DEPO
DAUR ULANG LIMBAH ELEKTRONIK
BBLM (BALAI BESAR LOGAM DAN MESIN)
BANDUNG
2018

NO. DESKRIPSI VOL SAT

(1) (2) (3) (4)

A. PEKERJAAN PERSIAPAN
1 Direksi Keet 12.00 m2
2 Gudang bahan & Bedeng Pekerja 15.00 m2
3 Mob./demob. peralatan dan tenaga kerja 1.00 ls
4 Pasang Papan Nama Proyek 1.00 bh
5 Pagar pengaman proyek 141.00 m'
6 Pekerjaan Tes Sondir dan Boring 1.00 ls
7 Pengurusan Izin Lingkungan 1.00 ls
8 Pengurusan Izin Mendirikan Bangunan (IMB) 1.00 ls
9 As built drawing, shop drawing dan dokumen 1.00 ls
10 Pekerjaaan marking dan bowplank 66.28 m'
11 Penyediaan listrik kerja 4.00 bln
12 Penyediaan air kerja 4.00 bln
13 K3 (asuransi, rambu-rambu dan properti proyek, APD, Jaring Proyek) 1.00 ls
14 Keamanan 4.00 bln

B PEKERJAAN ARSITEKTUR

B.1 PEKERJAAN ARSITEKTUR LANTAI 1

1 PEKERJAAN DINDING DAN FINISHING


- Pekerjaan Pasangan Bata Ringan 399.89 m2
- Pekerjaan Plesteran + Acian Halus Ekspose [2] 799.78 m2
- Pekerjaan Dinding .Metal Cladding Bluescope Steel Clean Colorbond Gull Grey [1] 192.57 m2
- Pekerjaan Dinding Bata Tempel Merah [4] 15.38 m2
- Pekerjaan Dinding Keramik 30x30 t=150 cm (6) 30.50 m2
- Pekerjaan Dinding Roster 20x20 (8) 72.00 unit

2 PEKERJAAN LANTAI
- Pekerjaan Lantai Floor Hardener 201.70 m2
- Pekerjaan Lantai Ex. Keramik Roman 30x30 cream matter 4.49 m2
- Pekerjaan Plint Lantai 0.90 m'
- Pekerjaan Plat Checkered Lantai Tangga 14.22 m2
- Pekerjaan Ramp
a. Pekerjaan Galian Tanah 9.93 m3
b. Pekerjaan Pemadatan Tanah 49.63 m2
c. Pekerjaan Urugan Tanah 79.90 m3
d. Pekerjaan Lantai Kerja t=5cm 1.89 m3
e. Pekerjaan Beton K-250 3.79 m3
- Pekerjaan Tangga Teras
a. Pekerjaan Urugan Tanah 3.60 m3
b. Pekerjaan Pasangan Bata Merah 9.32 m2
c. Pekerjaan Plesteran + Acian 18.64 m2
d. Pekerjaan Lantai Screed 0.35 m3
e. Pekerjaan Pas.Batu Sikat 7.03 m2
3 PEKERJAAN PLAFOND
- Pekerjaan Plafond Indoor gypsum board t.9mm ex. Jayaboard + Rangka Hollow 6.26 m2
- Pekerjaan Plafond kalsiboard/GRC t.3,5mm + Rangka Hollow 4.19 m2
- Pekerjaan Plafond Expanded Metal Mesh + Rangka Hollow 10x5 + Siku 5x5 16.50 m2

4 PEKERJAAN PINTU
- Pemasangan Pintu Type P1 1.00 unit
- Pemasangan Pintu Type P2 1.00 unit
- Pemasangan Pintu Type P3 1.00 unit
- Pemasangan Pintu Type P4 2.00 unit
- Pemasangan Pintu Type P5 2.00 unit
- Pemasangan Pintu Type P6 2.00 unit
- Pemasangan Pintu Type P7 1.00 unit

5 PEKERJAAN JENDELA
- Pemasangan Jendela Type J4 3.00 unit
- Pemasangan Jendela Type J6 1.00 unit
- Pemasangan Jendela Type J7 1.00 unit
- Pemasangan Jendela Type J8 1.00 unit

6 PEKERJAAN SANITARY
- Pemasangan Closet duduk ex Toto SW784JP 2.00 bh
- Pemasangan Wastafel ex. Toto LW340CJ 1.00 bh
- Pemasangan Floor Drain ex Toto TX1DA 2.00 bh
- Pemasangan Kran Tembok ex Toto 2.00 bh
- Pemasangan Kitchen Zinc ex Toto SK508 1.00 bh
- Pemasangan Jet Washer ex Toto THX20CRB 2.00 bh
- Pemasangan Tempat Sabun 2.00 bh
- Pemasangan Tissue Holder ex Toto TS116R 2.00 bh
7 PEKERJAAN PENGECATAN
- Pengecatan Pengecatan plafond ex. Vinile Superwhite 10.45 m2
- Pengecatan Zincromate Baja IWF 1,014.76 m2

8 PEKERJAAN RAILING
a Pekerjaan Railing Area Ramp
- Pekerjaan Railing Besi Behel dia. 1/2 inch 26.40 m'
- Pekerjaan Pas. Besi Pipa Dia.2 inch 13.20 m'
- Pekerjaan Pas. Besi Siku 50.50.10 13.50 m'
b Pekerjaan Railing Tangga
- Pekerjaan Railing Besi Pipa dia. 2 inch 21.38 m'
- Pekerjaan Railling Hollow 40.40 17.50 m'
- Pekerjaan Railling Hollow 50.50 21.00 m'
- Pekerjaan Railing Besi Pipa dia. 1/2 inch 42.00 m'
- Pekerjaan Pas. Besi Hollow 5.5 13.20 m'

9 PEKERJAAN TANGGA SERVIS (PENYIMPANAN BARANG)


- Pekerjaan Tangga Besi Hollow dia.2 inc 5.00 m'

10 PEKERJAAN ATAP KANOPI


- Pemasangan Kanopi Onduvilla 230.00 m2
- Pekerjaan Rangka Kanopi Onduvilla Hollow 5.10 160.25 m2
- Pekerjaan Rangka Kanopi Onduvilla Hollow 10.10 160.25 m2
- Pemasangan Talang Air Galvalume 1/2 + Rangka Hollow 4x4 55.66 m'
- Pemasangan Talang Air Siku 35.52 m'

B.2 PEKERJAAN ARSITEKTUR LANTAI 2

1 PEKERJAAN DINDING DAN FINISHING


- Pekerjaan Pasangan Bata Ringan 172.42 m2
- Pekerjaan Plesteran + Acian Halus Ekspose [2] 344.85 m2
- Pekerjaan Dinding .Metal Cladding Bluescope Steel Clean Colorbond Gull Grey [1] 100.61 m2
- Pekerjaan Dinding Bata Tempel Merah [4] 4.80 m2
- Pekerjaan Partisi Gypsum Fin. Cat Putih [5] 21.60 m2
- Pekerjaan Dinding Keramik 30x30 t=150 cm (6) 31.05 m2
- Pekerjaan Partisi Besi Hollow 50.50 Fin. Cat (7) 15.95 m2
- Pekerjaan Selimut Kolom Metal Cladding + Rangka Hollow (9) 181.40 m2

2 PEKERJAAN LANTAI
- Pekerjaan Lantai Ex. Keramik Roman 30x30 cream matter 7.10 m2
- Pekerjaan Lantai Ex.Keramik Roman 60x50 grey 147.61 m2
- Pekerjaan Plint Lantai 29.52 m'

3 PEKERJAAN PLAFOND
- Pekerjaan Plafond Gypsum Board t.9mm ex. Jayaboard + Rangka Hollow 100.57 m2
- Pekerjaan Plafond Kalsiboard/GRC t.3,5mm, Rangka Hollow 4.19 m2
- Pekerjaan Rangka Plafond Alluminium Wood Hollow 10x5 73.15 m'
- Pekerjaan Pas Shadow Line 202.54 m'
- Pekerjaan Plafond Outdoor Alumunium Wood U-Shape 30x60 mm (Rangka by Supplier) 48.02 m2

4 PEKERJAAN PINTU
- Pemasangan Pintu Type PJ-1 1.00 unit
- Pemasangan Pintu Type PJ-1' 1.00 unit
- Pemasangan Pintu Type PJ-2 1.00 unit
- Pemasangan Pintu Type P5 2.00 unit

5 PEKERJAAN JENDELA
- Pemasangan Jendela Type J1 1.00 unit
- Pemasangan Jendela Type J2 3.00 unit
- Pemasangan Jendela Type J2' 1.00 unit
- Pemasangan Jendela Type J3 1.00 unit
- Pemasangan Jendela Type J6 1.00 unit
- Pemasangan Jendela Type J9 2.00 unit
- Pemasangan Jendela Type J10 2.00 unit
- Pemasangan Jalusi Aluminium AL 36.00 m2

6 PEKERJAAN SANITARY
- Pemasangan Closet duduk ex Toto SW784JP 2.00 bh
- Pemasangan Wastafel ex. Toto LW340CJ 2.00 bh
- Pemasangan Floor Drain ex Toto TX1DA 2.00 bh
- Pemasangan Kran Tembok ex Toto 3.00 bh
- Pemasangan Kitchen Zinc ex Toto SK508 2.00 bh
- Pemasangan Jet Washer ex Toto THX20CRB 2.00 bh
- Pemasangan Tempat Sabun 2.00 bh
- Pemasangan Tissue Holder ex Toto TS116R 2.00 bh

7 PEKERJAAN PENGECATAN
- Pengecatan Pengecatan Plafond ex. Vinile Superwhite 104.76 m2
- Pengecatan Interior Dinding ex. Vinile 77.34 m2
- Pengecatan Zincromate Baja IWF 465.60 m2

8 PEKERJAAN RAILING KORIDOR


- Pekerjaan Railing Besi Pipa dia. 2 inch 20.64 m'
- Pekerjaan Railing Besi Behel dia. 1 cm 38.38 m'

9 PEKERJAAN TANGGA SERVIS


- Pekerjaan Tangga Besi Pipa dia.2 inc 6.50 m'
B.3 PEKERJAAN ARSITEKTUR LANTAI 3 (AREA SERVICE)

1 PEKERJAAN DINDING DAN FINISHING


- Pekerjaan Pasangan Bata Ringan 23.52 m2
- Pekerjaan Plesteran + Acian Halus Ekspose [2] 47.05 m2
- Pekerjaan Dinding Metal Cladding Bluescope Steel Clean Colorbond Gull Grey [1] 72.34 m2

2 PEKERJAAN LANTAI (DAK BETON)


- Pekerjaan Water Proofing 25.78 m2

3 PEKERJAAN JENDELA
- Pemasangan Jalusi Aluminium [AL] 43.97 m2

4 PEKERJAAN RAILING TANGGA SERVIS (TORN)


- Pekerjaan Railing Besi Pipa dia. 2 inch 10.83 m'
- Pekerjaan Railing Besi Behel dia. 1 cm 16.40 m'

B.4 PEKERJAAN ARSITEKTUR ATAP

1 PEKERJAAN ATAP
- Pemasangan Atap Onduline tipe Classic warna hitam + Tripleks 342.00 m2
- Pemasangan Talang Air 22.50 m'
- Pekerjaan Rangka Kanopi Onduline Hollow 5.5 67.10 m'
- Pekerjaan Rangka Kanopi Onduline Hollow 5.10 67.10 m'

C PEKERJAAN KHUSUS

1 PEKERJAAN SUNSHADING
- Pekerjaan Rangka Hollow 8x10 108.44 m1
- Pekerjaan Plat Besi + Baud Angkur 24.00 unit
- Pekerjaan Panel Sunshading Alluminium Wood 2.5x20 92.83 m2

2 PEKERJAAN PLANG WIREMESH


- Pekerjaan Pondasi Batu Kali 1.59 m3
- Pekerjaan Plat Besi + Baud Angkur 17.00 unit
- Pekerjaan Wiremesh M8 58.04 m2
- Pekerjaan Kolom Besi Hollow Galvanis 30.80 m'

3 PEKERJAAN SIGNAGE HURUF


- Pekerjaan Stainless Steel 6.90 m'

4 PEKERJAAN ENTRANCE GATE


- Pekerjaan Pondasi Batu Kali 0.19 m3
- Pekerjaan Plat Besi + Baud Angkur 2.00 unit
- Pekerjaan ACP 11.80 m2
- Pekerjaan Balok Cremona Besi Hollow Galvanis 54.00 m'
- Pekerjaan Kolom Baja IWF 150.150 79.98 kg

D PEKERJAAN LANSEKAP

D.1 PEKERJAAN HARDSCAPE


1 Pekerjaan Jalan Entrance
- Pekerjaan Galian 7.08 m3
- Pekerjaan Pemadatan Tanah 3.54 m2
- Pekerjaan Urugan Pasir Bawah Lantai t=10cm 7.08 m3
- Pekerjaan Pas Karpet Geotextile Woven 70.78 m2
- Pekerjaan Pas Abu Batu 3.54 m3
- Pekerjaan Pas Paving Blok 70.78 m2
2 Pekerjaan Area Parkir
- Pekerjaan Kolom Baja IWF 300 891.00 kg
- Pekerjaan Rangka Lantai Plat Checker Baja IWF 300 2,076.43 kg
- Pekerjaan Pas Lantai Plat Checker 8mm 5.34 m3
3 Pekerjaan Railing Area Parkir
- Pekerjaan Railing Besi Pipa dia. 1/2 inch 41.56 m'
- Pekerjaan Pas. Besi Pipa Dia.2 inch 20.78 m'
- Pekerjaan Pas. Besi Siku 50.50.10 13.50 m'

D.2 PEKERJAAN SOFTSCAPE


1 Pekerjaan Pohon Ketapang Kencana [KT] 6 unit
2 Pekerjaan Pohon Kiara Payung [KP] 7 unit
3 Pekerjaan Tanaman Calathea [CL] 85 unit
4 Pekerjaan Tanaman Puring [PU] 36 unit
5 Pekerjaan Tanaman Philodendron [PL] 35 unit
6 Pekerjaan Tanaman Keladi [KL] 60 unit
7 Pekerjaan Tanaman Rumput Gajah Mini [RG] 370 m2
8 Pekerjaan Tanaman Vertical Garden Ipomea Merah [I1] 42 unit
9 Pekerjaan Tanaman Vertical Garden Ipomea Biru [I2] 42 unit
10 Pekerjaan Tanaman Vertical Garden Ipomea Putih [I3] 38 unit
11 Pekerjaan Tanaman Rumput Gajah Mini [RG] 26 m2
12 Pekerjaan Tanaman Landep [LD] 25 m2
E PEKERJAAN STRUKTUR GEDUNG
E.1 Preparation Work
1 Mob. & Demob. Of Borepile Machine 1.00 Ls
2 Land Clearing & Grubing 1.00 Ls
3 Staking Out & Border Plank 90.00 M'

E.2 Soil Work


1 Excavation of Concrete Foundation 65.93 M3
2 Soil Fill & Compaction 54.45 M3

E.3 Sand Bedding & Lean Concrete


1 Sand Bedding t = 100 mm 1.91 M3
2 Lean Concrete t = 50 mm 3.83 M3

E.4 Concrete Work


1 Concrete Footing Foundation 11.48 M3
2 Concrete Bore Pile Dia. 300 mm 136.00 M'
3 Concrete Pedestal Column 6.31 M3
4 Concrete Practical Column (non structural) 3.78 M3
5 1st Concrete Slab include steel deck t = 0,7 mm 31.88 M3
6 2nd Concrete Slab include steel deck t = 0,7 mm 17.86 M3
7 3rd Concrete Slab include steel deck t = 0,7 mm 11.25 M3

E.5 Steel Structure


1 Tie Beam WF 400x150x6,5x9 4,406.40 Kg
2 Column WF 400x150x6,5x9 7,397.98 Kg
3 1st Floor Main Beam WF400x150x6,5x9 4,131.00 Kg
4 1st Floor Secondary Beam WF 200x100x5.5x8 2,875.50 Kg
5 2nd Floor Main Beam WF 400x150x6,5x9 4,131.00 Kg
6 2nd Floor Secondary Beam WF 200x100x5.5x8 2,401.58 Kg
7 3rd Floor Main Beam WF 400x400x150x6,5x9 4,222.80 Kg
8 3rd Floor Secondary Beam WF 200x100x5.5x8 414.50 Kg

E.6 Stair Steel Structure


1 Column WF 200x100x5.5x12 106.50 Kg
2 Beam WF 200x100x5.5x8 650.67 Kg
3 Steel Angle L 40x40x4 47.84 Kg
4 Chequer Plate t=3mm 287.25 Kg
5 UNP 100 99.68 Kg

E.7 Machine Foundation Structure


HARGA
TOTAL
SATUAN
(5) (6)

-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
###

-
-
-
-
-
-
-

-
-
-
-

-
-
-
-
-

-
-
-
-
-
-
-
-
-
-

-
-
-
-
-
-
-
-

-
-
-
-
-

-
-
-
-
-
-
-
-
-
-
-
-

-
-
-

-
-
-
-
-
-

-
-

-
-
-
-
-
-

-
-
-
-
-
-
-
-
-

-
-
-
-

-
-
-
-
-
-

-
-
-
-
-

-
-
-
-
-
-
-
-
-

-
-
-
-
-
-
-
-
-

-
-
-
-

-
-
-
###
-
-
-

-
-
-
-

-
-

-
-

-
-
-

-
-
-
-
-

-
-
-
-

-
-
-
-
-

-
-

-
-
-
-
-
-

-
-
-
-
-
-

-
-
-

-
-
-
-

-
-
-
-
-
-
-
-
-
-
-
-
-
-

-
-
-
-

-
-
-

-
-
-

-
-
-
-
-
-
-
-

-
-
-
-
-
-
-
-
-

-
-
-
-
-
-