Professional Documents
Culture Documents
net/publication/3151921
CITATIONS READS
26 4,424
3 authors, including:
A. A. Sallam
Port Said University
47 PUBLICATIONS 1,090 CITATIONS
SEE PROFILE
Some of the authors of this publication are also working on these related projects:
Clinicopathological and Immunological Evaluation of Garilc Extracts Treatment on Eimeria Vermiformis infected mice. View project
All content following this page was uploaded by A. A. Sallam on 17 August 2015.
Abdelhay A. Sallam, Member IEEE System security which involves the ability of the system to
University of Suez Canal,Port Said respond suitably to disturbances arising within the system,
Mohamed Desouky eg, generator or transformer failure. The redundancy of lines
University of Suez Canal,Port Said is one of the methods to keep the security of the distribution
Hussien Desouky system at a specific level when line interruptions occur.+
University of Tanta, Tanta
The distribution network is usually compensated by either
series or shunt capacitors as an effective &-economic& tool.
Series capacitors increase the maximum power limit while shunt
Key WO& - Reliability improvement, Shunt capacitor,
Distribution system, State-space method capacitors have several effects:
reduce lagging component of circuit current,
Reader Aids - increase voltage level at the load and power factor of source
General purpose: Demonstrate a reliability-prediction model
generators,
Special math needed for explanation: Probability theory
Sj&al math needed to use r e s u h Same
improve voltage regulation if the capacitoi units are proper-
Results useful to: Reliability & power analysts ly switched,
reduce direct & reactive power loss in the system,
Summary & Conclusions - To improve the security & decrease kVA loading on source generators and circuits to
reliability of a distributionsystem, as much power as feasible must relieve an over-loaded condition or release capacity for ad-
go through a given transmission Line. This can be achievedby using ditional load growth.
shunt capacitors as compensators.These shunt capacitive compen-
sators improve the load Carrying capability of the h e by controll- Additional kW loading may be placed on the generators, viz,
ing the reactive power flow. Consequently, the capacitor existence reduce demand kVA where power is purchased,
can not be ignored in evaluating system reliability. The paper a p
reduce investment in system facilities per kW of load sup-
plies the state-space method to calculate the reliability indices for
plied. 4
compensated & uncompensated systems with different success
criteria. The importanceof using shunt capacitorsto improve the Therefore, the transmission & distribution system at some
level of distribution system reliability is illustrated in addition to nodes or load points can be connected with shunt capacitors to
t h e i r ~ ~ a s r e a e t i v e p o w e r c o n t r o l l e r sO. u r p ” ,
control the reactive power, aiming to:
based on a Markov process, is applied to a numerical example,
and indicates that system reliability is improved when using shunt reduce system losses,
capacitors. restore the stability margin,
improve supply quality [6].
Other, standard notation is given in "Information for Readers Figure 2 illustrates the effects of shunt capacitors on
& Authors" at the rear of each issue. the loadability. oa represents the load kVA at power factor
f. Angle f is decreased to to improve the power factor
at constant load kVA, ob = oa. This improvement can
2. PROBLEM FORMULATION be obtained by inserting shunt capacitors feeding the system
with reactive power cb kVAR. This increases transmitted
Reliability indices are calculated for a distribution system active power by ef kW while load carrying capability is
with and without shunt capacitors, viz, compensated and un- increased by ac kVA. If the power factor is improved to
compensated systems. Figure 1 shows the ties representing unity (f=O), the maximum increase in both active power
the s-independent paths which connect the supply with one of (eg kw) and load rating (ad kVA) is obtained. This maximum
many electric distribution load points. These ties have, in increase of tie loadability requires adding shunt capacitors
general, different loading conditions, and each tie contains a providing the system with the total required reactive power
shunt capacitor. The size of these capacitors is determined dg kVAR.
originally in the system subjected to minimizing the reactive For an integrated power system, the loadability increase
power flow or increasing the line capability. When an inter- can be computed by load-flow techniques. Accordingly, the
ruption occurs at any tie, the shunt capacitors for the uninter- system reliability is assessed by calculating:
rupted ties are switched on. So, the interrupted kVA can be com-
pensated partially or completely. These capacitors increase the probability of success,
loadability of the uninterrupted ties, as shown in figure 2. probability of failure,
durations of success & failure.
3. SOLUTION TECHNIQUE
-I-
I -
i
3.1 Example 1
[AI = fi = A2Pl(~I+&)/D
From To state
state 0 1 2 3 h = AlA2(Pl+P2)/D
0 -(A,+A2) A1 A2 0
If the system contained 4 ties, it would be described by 16 states.
1 P1 +2+Pl> 0 A2 The states can be defined as success or failure according to the
(1) failure criterion.
2 P2 0 -(A,+&) A1 To simplify the calculations, the state-space diagram is
3 reduced to an equivalentlcombined success state S and an
0 P2 P1 --(PI+&)
equivalentlcombined failure state F; see figure 4.
Multiplying [A] by the vector of state probabilities:
SALLAM ET AL: SHUNT CAPACITOR EFFECT ON ELECTRICAL DISTRIBUTION SYSTEM RELIABILITY 173
A r
PF = Pi (9) Component (failurelyear) (hourslfailure)
iEF
13.8 kV circuit breakers 0.0036 2.1
6. System failure frequency, f F , is the frequency of F: cable terminations at 13.8 kV 0.0018 25.0
disconnected switches 0.0061 3.6
transformers 0.0030 130.0
iEF j€S
switchgear bus:
(connected to 2 CBs) 0.0068 26.8
7. The mean duration of system failure, tp* (connected to 4 CBs) 0.0136 26.8
3-phase cablekm 0.1283 1.09
fUSeS 0.0023 1.1
manual switches o.Ooo1 2.0
supply 0.005 12.0
The main steps of the problem solution for B specific distribution transformer 0.004 1.85
one kVAR capacitor 0.00162 3.6
criterion are illustrated by the flow chart in figure 6.
Given distribution system data 2. The reliability indices for the ties feeding the load point
The technique is applied to the reliability indices for the The power diagram is illustrated in figure 2, the increase in
electrical distribution network in figure 1. The number of ties loadability of ties TI, T2, T3, T4against the compensator size
n = 4. The steps of the solution according to figure 6 are: can be evaluated as in table 3.
1. The reliability data for the system are in table 1. 4. The following 3 criteria for success are to be examined.
The power (X of full load) delivered to the load point must be:
a. 100, b. 70, c. 50.
'The number of signifcant figures is not intended to imply any ac-
curacy in the estimates, but to illustrate the arithmetic. 5 . The state-space method is implemented as follows:
174 EEE TRANSACTIONS ON RELIABILITY, VOL. 43, NO. 1, 1994 MARCH
Success criterion
Stage State %Continuity
Notation no. probability (%cont.) 100% 70% 50%
i tie number 1 Po 100 S S S
j interrupted tie number
2 P1 100 S S S
kWi tie load 'z 90.43 F S S
P2
AkW, increase in kWi due to shunt capacitor insertion P3 79.10 F S S
AkWi,- maximum AkWi at unity power factor. P4 67.67 F F S
3 Pl2 79.23 F S S
Example P31 67.34 F S S
PI4 56.45 F F S
Let j = 2 , Akwi = 0.9 AkWi,-. Then - P23 56.52 F F S
P24 45.13 F F F
AkW1 = 0.9 AkWi,- = 0.9.10 = 9.0 kW P34 33.75 F F F
4 P123 45.31 F F F
AkW3 = 0.9 AkW3,- = 0.9.18 = 16.2 kW P234 11.21 F F F
P341 22.54 F F F
P412 33.91 F F F
AkW4 = 0.9 AkW4,- = 0.9.20 = 18.0 kW.
5 Pl234 0.0 F F F
The fraction of continuity for these conditions is:
ii. Using tables 4 & 5, the failure & success states can be
%cont = (437 - 85.0 + 43.2)/437 = 90.43% of full load defined in the state diagram:
SALLAM ET AL: SHUNT CAPACITOR EFFECT ON ELECTRICAL DISTRIBUTION SYSTEM RELIABILITY 175
Omit (15) and replace it by the solution of (13) & (14). The
result for case b (compensated; success criterion = 70%)is:
st.0. I
PF = 0.7142, p s = 0.2857
' L - ,-
Figure 8. Partition of States into Success & Failure Domains t~ = 0.5838, ts = 0.2835
[Uncompensated; Success criterion = 70%]
Similarly, the reliability indices for all cases (uncompensated
& compensated) can be calculated. The results are in table 6.
iii. The [A] derived from figure 7 consists of 16x16 Table 6 indicates the improvement of reliability indices due
elements; thus 16 equations are solved to get the probabilities to capacitor insertion (capacitor effectiveness). For example,
of all individual states. To reduce the dimension of [A], some at 50% success criterion the success probability is increased by
states can be combined. Figure 10 is the reduced state-space 0.011, and the failure probability is decreased by the same
graph- amount.
-
176 IEEE TRANSACTIONS ON RELIABILITY,VOL. 43, NO. 1, 1994 MARCH