GTG E&C WORK COMPLETION PROGRAMME AS ON 25/11/20

Total Duration
S.No. ACTIVITY DESCRIPTION START FINISH (Days)

1 GTG ERECTION
Gas Turbine & Generator Unloading at
site

1.1 11/10/2019 11/14/2019 4


1.2 GTG sole plate blue matching & Grouting 11/25/2019 12/10/2019 14
1.1 Turbine and Generator Placement 12/11/2019 12/31/2019 20

Turbine and Generator Erection including


Piping erection
1.2 1/1/2020 3/21/2020 80

Inlet Air Filter Erection including structure


1.3 2/1/2019 3/12/2020 40
1.4 Exhaust System including Dampers 12/21/2019 2/19/2020 60
1.5 Erection of Fuel Skids & Piping 1/1/2020 3/1/2020 60
1.6 Erection of Enclosure 3/4/2020 4/18/2020 45

3 GTG COMMISSIONING
3.1 Lube Oil Flushing & Normalization 5/1/2020 5/22/2020 21
3.2 Fuel Oil System readiness 5/15/2020 5/30/2020 15
3.3 GTG Connected C&I System Readiness 2/21/2020 5/21/2020 90
3.4 Cranking 5/23/2020 5/26/2020 3
3.5 FSNL 5/27/2020 5/30/2020 3
E AS ON 25/11/2019

REMARKS

GTG foundation handover on


08/11/2019 by Civil . Unloading from
trailor on 11/11/2019 and 14/11/2019
respectively for GT and Generator.
GTG AND STG E&C WORK COMPLETION PROGRAMME AS ON 07/12/2019

S.No. ACTIVITY DESCRIPTION START FINISH

1 GTG ERECTION

1.1 Turbine & Generator Unloaded at site 11/10/2019 11/14/2019


1.2 GTG sole plate blue matching & Grouting 11/5/2019 11/18/2019
1.1 Turbine and Generator Placement 12/20/2019 1/5/2020

Turbine and Generator Erection including


Piping erection
1.2 1/5/2020 3/20/2020

Inlet Air Filter Erection including structure


1.3 2/1/2019 3/10/2020
1.4 Exhaust System including Dampers 12/20/2019 2/19/2020
1.5 Erection of Fuel Skids & Piping 1/1/2020 2/2/2020
1.6 Erection of Enclosure 3/4/2020 4/20/2020

2 STG ERECTION

Generator Placement & Erection

2.1 1/1/2019 1/31/2019


2.2 Turbine Placement 2/1/2020 2/9/2020
Turbine Placement & Box-up including
2.3 Blue matching, Levelling
,Alingment,Coupling,CRO,Readiness for
OF activity including pedesstal box up.
2/10/2020 4/10/2020
2.4 Erection of Lube oil Console 3/1/2020 4/2/2020
2.5 Erection of GSC/SJAE 2/15/2020 6/14/2020
2.6 Lube Oil Piping & Intergal Piping 4/15/2020 6/24/2020

3 GTG COMMISSIONING
3.1 Lube Oil Flushing & Normalization 5/1/2020 5/22/2020
3.2 Fuel Oil System readiness 5/15/2020 5/30/2020
3.3 GTG Connected C&I System Readiness 2/21/2020 5/21/2020
3.4 Cranking 5/23/2020 5/26/2020
3.5 FSNL 5/27/2020 5/30/2020
4 STG COMMISSIONING
4.1 Lube Oil Flushing & Normalization 7/1/2020 8/15/2020
Mounting of Instrument-TSI & Interlock
4.2 Checking 8/16/2020 9/10/2020
4.3 TG on Turning Gear 9/12/2020 9/19/2020
4.4 Steam Blowing & Normalization 9/20/2020 10/5/2020
4.5 Vacuum Pulling 10/7/2020 10/9/2020
4.6 TG Rolling 10/10/2020 10/12/2020
4.7 Elecrical Testing 9/13/2020 10/14/2020
4.8 Synchronization 10/15/2020 10/22/2020
ME AS ON 07/12/2019

REMARKS

GTG foundation
handover on
dt.08/11/2019 by Civil
deppt.

Assumption: STG Deck


availabilty from Civil
To Mechanical by
30/12/2019