Professional Documents
Culture Documents
ASME code
revisions 2019.
Key Changes – Section I
Every two years the American Society of Mechanical Engineers (ASME) issues an
update to the ASME Boiler and Pressure Vessel Code (BPVC).
Part/Paragraph Change/Revision
PG-31.4 / PW-17
Revised PG-31.4 to add reference to PW-17 for illustration (a), (b-1) and (b-2).
- 2017
o Last sentence under PG-31 illustration (b-2): The hub may be formed by machining a
forged blank or by direct forging action. This illustration shall not be used with plate,
bar, or rod. The welding shall meet all requirements for circumferential joints in
Part PW.
- 2019
o REVISED
• Last sentence revised under PG-31 illustration (b-2): “The forged head shall meet
the requirements of PW-17.”
o ADDED
• Last sentence added for PG-31 illustrations (a) and (b-1): “The forged head shall meet
the requirements of PW-17.”
o ADDED
• Revised PW-17 by adding: “The hub shall be integrally forged with the flat head by
direct forging action or machined from a forging. Plate, bar, or rod shall not be used
in lieu of a forging. The hub shall have minimum dimensions in accordance with
Figure PW-17.”
PG-106 / PG-106.4 Revised PG-106.1 and PG-106.4 to allow alternative marking methods for the Code required stamp-
ing and publish enabling code case.
- 2019
o Sentence added at the end of PG-106.1
• “Application of the ASME Certification Mark and Designator may be by stamping or
by alternate methods that comply with Mandatory Appendix VII.”
o Sentence added at the end of PG-106.4
• In addition to the Certification Mark, the following items shall also be stamped with
letters and figures at least 5/16 in. (8 mm) high [5/32 in. (4 mm) on miniature boilers
if necessary], arranged as shown in Figure PG-106. “Marking of the required items may
be by stamping or by alternate methods that comply with Mandatory Appendix VII.”
PW-53 Test Plates Revised by adding final part of sentence in PW-53.1(a). Deleted “cylindrical” in PW-53.1(b).
- 2019
o PW-53.1 Vessel Test Plates. Cylindrical pressure parts such as drums and shells and
all noncylindrical pressure parts that are subject to internal pressure and are fabricated
by fusion welding, shall meet the test requirements in PW-53.2 through PW-53.9. The
following are exempt from these requirements:
• ADDED
• (a) cylindrical pipe, tubes, and headers subject to internal pressure, “including
heads attached by welding to these pressure parts.”
• DELETED
• (b) all cylindrical pressure parts constructed of P-No. 1 materials
• (c) all attachment welds
Lloyd’s Register
Part/Paragraph Change/Revision
PW-53.2 Welded Test Plates Added two new paragraphs in PW-53.2 – Welded Test Plates
- 2019
o ADDED
• “The weld consumables used to weld the test plate shall be from the same
manufacturer and lot(s), control or heat number(s) as that to be used for each
weld process in production.”
o ADDED
• “If weld consumables are purchased with a Certified Material Test Report based
on Schedule 4 or I level of testing as defined in Section II, Part C, SFA-5.01/
SFA-5.01M, then the requirement to make a test plate is exempted.”
PW-39
PW-39 Post Weld Heat Treatment
- Revised PW-39.2 to clarify that the exemptions contained within the General Notes of the
PW-39 tables are applicable only to materials of their respective P-No. groupings.
o 2019
• PW-39.2 When pressure parts of two different P-Number groups are joined by
welding, the postweld heat treatment shall be that specified in Tables PW-39-1
through PW-39-14 and applicable notes for the material requiring the higher
postweld heat treatment temperature…
• ADDED: “If one of the materials in the joint is exempt from postweld heat
treatment, then the time and temperature shall be that of the material
requiring postweld heat treatment. For the weld to be exempt from postweld
heat treatment, each material must satisfy the exemptions applicable to its
respective P-Number and Group Number in Tables PW-39-1 through PW-39-14.”
Part/Paragraph Change/Revision
PG-33 PG-33 Compensation Required for Openings in Shell and Dished Heads
- Revised x-axis title in Figure PG-33.3 and added sketch to the Figure depicting the angle theta
used for determining the F factor.
- 2017
– Fig. PG-33.3 - X-Axis Title - Angle With Plane With Longitudinal Axis, deg
- 2019
– X-Axis Title - Angle 0, deg. of plane with Longitudinal Axis
Longitudinal
0 shell axis
PG-112.2.5 Revised PG-112.2.5 to state that the organization certifying Form P-4A or P-4B retains the
responsibility for the Code design.
- 2019
o PG-112.2.5 - ADDED
• Form P-4A, Manufacturer’s Data Report for Fabricated Piping, shall be used to record
all shop or field-welded boiler external piping that falls within the scope of this Section
but is not furnished by the boiler Manufacturer. Form P-4B, Manufacturer’s Data Report
for Field-Installed Mechanically Assembled Piping, shall be used to record all
field-installed mechanically assembled boiler external piping. Form P-4B shall be used
only for piping that contains no joints brazed or welded by the field installer. “The
organization certifying Form P-4A or P-4B retains the responsibility for the Code design”
PG-113.4
Revised PG-113.4 for retention requirements of form P-4A
- 2019
o PG-113.4 – ADDED
• When boiler external piping is furnished by an organization not contractually
responsible to the Manufacturer [see PG-104.1, Note (1)], the organization responsible
for the fabrication and installation of this piping shall have the responsibility for
distributing copies of Form P-4A to the inspection agency and proper authorities.
“The piping fabricator shall retain Form P-4A for a minimum of 5 years.”
Lloyd’s Register
Part/Paragraph Change/Revision
Table PW-39-1 Table PW-39-1 Revised General Note (a), added new (b)(2), changed CE equation to remove
silicon; removed CE requirement from P-No. 1 Group 1 ≤25mm thickness
PW-38 - 2017
o (a) PWHT is not required for P-No. 1 Group 1 materials when the calculated carbon
equivalent (CE) is less than or equal to 0.45, and the nominal thickness as defined in
PW-39.3 is 1.5 in. (38 mm) or less. When the nominal thickness is greater than 1.5 in.
(38 mm), PWHT is not required when the calculated CE is less than or equal to 0.45 and
a minimum preheat of 250°F (120°C) is applied. Electroslag welds shall follow the PWHT
requirements of PW-27.3 and PW-39.7
- 2019
(a) Postweld heat treatment is not mandatory for P-No. 1 Group 1 materials under the following conditions:
(1) when the nominal thickness as defined in PW-39.3 is 1 in. (25mm) or less.
(2) when the nominal thickness as defined in PW-39.3 exceeds 1 in. (25mm), postweld heat treatment is not required when
the calculated carbon equivalent, CE, of each base metal in the weld joint is less than or equal to 0.45 using the following
formula, and a minimum preheat of 200oF (95oC) is applied.
NOTE: The maximum chemical composition limit from the material specification or the actual values from a chemical analysis or material test report shall be used in
computing the CE. If the chemistry values required for the last two terms are not available, 0.14% shall be substituted for those two terms as follows:
Mn
CE = C + + 0.15
6
PG-59 Revised PG-59.3.2 to clarify that the maximum size limit of NPS 2-1/2 apply to surface blowoff
connections when they are provided. Revised PG-59.3.5 to clarify that the size requirements for
blowoff connections apply to bottom blowoff connections and added a reference to the size
exceptions provided in Part PEB.
- 2019
o PG-59.3.2 - ADDED
• “When” a surface blowoff connection “is provided, the size” shall not exceed NPS
2 ½ (DN 65), and the internal pipe and the terminal connection for the external
pipe, when used, shall form a continuous passage, but with clearance between
their ends and arranged so that the removal of either will not disturb the other.
A properly designed steel bushing, similar to or the equivalent of those shown in
Figure PG-59.1, or a flanged connection shall be used.
o PG-59.3.5 - ADDED
• Except as permitted for miniature boilers in Part PMB, “for electric boilers in Part
PEB”, and for boilers with 100 ft2 (9.3 m2) of heating surface or less, the minimum
size of “bottom” blowoff connections shall be NPS 1 (DN 25) and the maximum size
shall be NPS 2½ (DN 65). Boilers with 100 ft2 (9.3 m2) or less but more than 20 ft2
(1.9 m2) of heating surface may have a minimum size blowoff connection of NPS 3/4
(DN 20). Boilers with 20 ft2 (1.9 m2) or less of heating surface may have a minimum
size blowoff connection of NPS ½ (DN 15).
Part/Paragraph Change/Revision
PG-58.2.6 Added Fig. PG-58.2-6 for Code Jurisdictional Limit for Piping for Firetube Boiler
Figure PG-58.2-6
Code jurisdictional limits for piping - firetube boiler
Lloyd’s Register
Part/Paragraph Change/Revision
Non-mandatory appendix Revised Table A-360 to reference ASME B31.1-2018, revised Note (2), deleted Note (3), and
A – table A-360 renumbered subsequent notes.
ASME Standards
B16.1-2015 Gray iron pipe flanges and flanged fittings (classes 25, 125 and 250)
B16.15-2013 Cast copper alloy threaded fittings; classes 125 and 250
B16.20-2017 Metallic gaskets for pipe flanges : ring-joint, spiral wound, and jacketed
B16.24-2016 Cast copper alloy pipe flanges and flanged fittings: class 150, 300, 600, 900 1500, and 2500
B16.42-2016 Ductile iron pipe flanges and flanged fittings, classes 150 and 300
B16.47-2017 Large diameter steel flanges, NPS 26 through NPS 60
• Give advice on the procedures • Attend the ASME review, renewal If you’re looking to switch from another
required for you to obtain ASME reviews and surveys. Authorised Inspection Agency, we’ll
Certificates of Authorisation. • Provide authorised inspectors make that easy to do.
• Assist you in preparing and and supervisors to inspect
establishing Quality Assurance manufactured components.
(QA) Programmes and Quality • Arrange seminars to train your
Control (QC) Systems. personnel in the requirements of
• Help prepare your Quality Manuals. the ASME Code.
Globally recognised and accredited LR’s authorised inspectors can provide The profits we generate fund the Lloyd’s
Lloyd’s Register is a globally recognized first-hand insights into the requirements Register Foundation, a charity which
ASME Authorised Inspection Agency. of the ASME code the logic behind them. supports science and engineering-related
We are one of the world’s leading Our inspectors are chosen for their research, education and public
providers of ASME services, and have sector-specific knowledge and expertise, engagement around everything we do.
been since 1973. which means you can be confident that All of this helps us stand by the purpose
they’ll understand the manufacturing that drives us every single day: Working
We provide accreditation services* to challenges you face. together for a safer world.
all parts of the ASME BPVC including
Sections I, III, Divisions 1,2 & 3, IV, VIII
ivisions 1, 2 & 3, X, XI, and XII.
*All ASME Authorised Inspection Agency activities are performed under the accreditation held by Lloyd’s Register Verification Limited.