TPF GETINSA EUROESTUDIOS, S.L.

in association with
Segmental Consulting & Infrastructure Advisory (P) Ltd
Project Office: First Floor, The Legend, VPO Gutkar, District Mandi, Himachal Pradesh-175021
E-Mail: scia010.nerchowk@segmental.in. Ph. No.:01905-246662.
Project: Consultancy services for Authority’ Engineer for Supervision of project of Four laning of Nerchowk –
Pandoh including Pandoh bypass section of NH-21 (Package-I km 190.000 to km 221.305) (Design length –
26.290 km) under NHDP-IVB on EPC Mode in the state of Himachal Pradesh.
FCRN:F04460, CIN:U74140DL2009PTC188591

No: TPF-GE-SCIA/010/N-P/AE/KMC/ 0707 Date: 8th May 2019

To
KMC Construction Limited,
Opposite Sri Harihar Hospital,
Upstairs: Tata Motors,
VPO: Gutkar, Distt. Mandi, Pin. - 175021 (H.P.)
Kind Attention: Sh. Rajashekhar, Authorized Signatory
Subject: Consultancy services for Authority’ Engineer for Supervision of project of Four laning of
Nerchowk – Pandoh including Pandoh bypass section of NH-21 (Package-I km 190.000 to km 221.305)
(Design length – 26.290 km) under NHDP-IVB on EPC Mode in the state of Himachal Pradesh-
Commencement of construction in new work front (Between Ch. 202+500 & Ch. 203+800) without
implementing safety measures as per standard construction practice
Ref: 1. Regional Office letter no. NHAI/RO/HP/11011/73/RS/BS/2018/364 dated 18th May 2018
2. This office letter no. TPF-GE-SCIA/010/N-P/AE/KMC/ 0275 dated 7th May 2018
3. Contractor’s letter no. KMC/Mandi/Nerchowk/2018/097 dated 16th April 2018
Dear Sir,
Please refer to above subject and letter. During routine site visit by the undersigned on 07.05.2019, it
was observed that the sub-agency engaged by the Contractor for excavation works (Hill cutting) between
Ch. 202+500 & Ch. 203+800 has been progressing with the excavation without adhering to safety
measures. It is further observed with concern that no supervisor and labors were present at excavation
site posing serious threat to the safety of the road users (Photos attached).

Contractor’s attention is also drawn to ref. 2 above, vide which this office has specifically advised the
Contractor to submit work zone traffic safety management plan prior to taking up new construction
activity in any of the sections, specially hill cut sections.
Contractor is once again advised to submit work zone traffic management plan for each new sections to
be taken up well in advance and implement the same to avoid any untoward incidents, failing which
Contractor should be sole responsible for any issue arising out of such negligence.
For strict compliance please.
Thanking you.
Yours faithfully

Rajesh Kumar Bhatt


Team Leader

Attachment: As Above

Copy for information to:

1. Project Director, NHAI, PIU-Mandi,


2. Project Coordinator TPF GE-SCIA, Gurgaon,
3. Office File.

Corporate Office: Unit No. 419-421, Spaze IT Park, Tower B4, Sector 49, Sohna Road, Gurgaon -122002