Professional Documents
Culture Documents
Recommendations for
Tank No. 5111 FA Shell and Roof
Project: Rehabilitation of 83 storage tanks in QP refinery at Mesaieed.
Weld missing at the bottom side of gusset plate of roof tertiary rafter
General corrosion on internal surface of gauge hatch nozzle
Mechanical damage on roof internal surface Missing Nut at the Roof Primary Rafter
7. Inspection Findings
7.1 Visual Inspection shows the following:
7.1.1 All shell plates don’t show any mechanical degradation from both external and internal except
pitting corrosion observed on shell internal plate & shell internal horizontal and vertical butt
weld joints (Depth up to 2.5 mm). See below photos and visual inspection drawing # J198-
5111FA-016 Rev-0.
7.1.2 Open to surface pore was observed on shell horizontal and vertical butt weld joints (See below
photos).
7.1.3 Lack of side wall fusion and continuous under cut was observed on shell horizontal butt weld
joint from tank inside. See below photos and visual inspection drawing # J198-5111FA-016
Rev-0.
7.1.3.1 Localized corrosion was observed on over flow nozzle TP and around the vent hole of inlet
piping (Depth of corrosion up to 1.0 mm) (See below photos)
7.1.3.2 Mechanical damages, spatters and arc strikes were observed on shell plate internal. (See below
photos).
7.1.3.3 Localized corrosion was observed on Shell manhole (H3 & H4) cover plate.
7.1.3.4 Shell distortion was observed on shell plates at inlet nozzle pipe support and over flow pipe
support location. See attached plumbness and peaking & banding drawings. (See below
photos).
7.1.3.5 All supports and structural attachments were welded on directly to the Shell plates without RF
pad.
Pitting corrosion on shell plate & Pore Pores on shell vertical butt weld joint
on shell horizontal joint (internal) (internal)
Lack of Fusion on shell horizontal weld Under cut on shell horizontal weld joint
joint (internal) (internal)
8 Repair Methodology
The purpose of any repair or replacement of shell and its component is to maintain the tank
shell integrity and their fitness for continuous service up to next shutdown (internal inspection)
after10 years, without any perceived potential risk to the assets or operators.