ETERNA project is composed of five buildings (Capital, Centra, Cure, Arc, and ETERNA
hospital), each building has ground, first, second, third, and roof floors, besides two
outdoor areas; Plaza and the Garden. Also, the project has another part called
“Parking” which contains 3 floors; second basement, first basement, and lower ground
floors. The two basements are mainly used for parking, while the lower ground floor
contains clinics, medical centers, and hospitals.
The provided package of electrical works does not include the Electrical Design
Drawings (EDDs) of ETERNA hospital, Plaza, and the Garden. So, after reviewing the
EDDs & BOQs of the other buildings, we have the following comments:-
2. Lighting:
The used luminaires on roof are not identified in legend.
Luminaires wiring is not found in (CLC-1, CLC-5, CLA-6, CLA-7, CLA-8, CLB-1,
& CLB-2) clinics, ground floor, ARC building.
3. Power outlets:
Neither layout of furniture nor legend found.
4. HVAC:
The legend is not found.
A/C Controllers and isolating switches were not used in any clinic.
1|Page
ETERNA – Health Care City
2|Page
ETERNA – Health Care City
Transformer data (type, KVA, rated voltage, and tape changer steps) is not
included.
No clear reason for setting the generator on roof.
No need to motorize the main CB of main emergency panel in this design
case.
7. BOQ:
Main low voltage panel and main emergency panel are not included.
Quantity of panels is not correct.
Names of panels are different than SLD and design drawings.
DB-SH, included in BOQ, has no details and not found in design drawings.
Types and quantities of cables and cables trays are not correct.
Quantities of luminaires, switches, and sockets are not correct.
3|Page