You are on page 1of 71

Project Report on Summer training held at

JAYPEE GREENS SPORTS CITY (KASSIA block Residential Buildings)

Report Submitted by:-


Mohan Lal

B. Tech. Civil Engineering student of

SHRI JAGDISHPRASAD JHABARMAL TIBREWALA UNIVERSITY,


JHUNJHUNU,
RAJASTHAN
ACKNOWLEDGEMENT

As per our university syllabus we have to take summer training at an industry. We take training at JAYPEE
SPORTS CITY, Greater Noida. It is my pleasure to be indebted to various people, who directly or indirectly
contributed in the development of this work and who influenced my thinking, behavior, and acts during the
training. I express my sincere gratitude to Mr. B.L. Sahu (Vice- President), for providing me an opportunity
to undergo summer training at Jaypee Kassia block.
Great appreciation goes to Mr. Aashutosh Mishra (General Manager) who helps us from time to time during
the project. We are thankful to Mr. Prateek Shrivastva for his support, cooperation, and motivation
provided to me during the training for constant inspiration, presence and blessings. The supervision and
support that she gave truly help the progression and smoothness of the internship program. The co-operation
is much indeed appreciated. I also extend my sincere appreciation to my faculty members (Civil
Engineering Department), who provided there valuable suggestions and precious time in accomplishing my
project report.
Besides, this training program makes me realized the value of working together as a team and as a new
experience in working environment, which challenges us every minute. Lastly, I would like to thank the
almighty and my parents for their moral support and my friends with whom I shared my day-to-day
experience and received lots of suggestions that improved my quality of work.
CONTENTS

1. INTRODUCTION …………………………………………. ………...1.


2. INTRODUCTION OF PROJECT……………………………………..2.
3. ABOUT PROJECT…………………….……………………………...3-4.
4. LOCATION DETAILS………………………………………………..5.
5. TECHNICAL DETAILS………………………………………………6.
6. SITE PLAN & PLANING OF BULIDING……………………………7.
7. BUILDING MATERIALS ……………………………………………8-17.
8. THE EFFECT OF AGGREGATE PROPERTIES
ON CEMENT CONCRETE …………………………………………..18.
9. REINFORCED CEMENT CONCRETE ……………………………..19-20.
10.DESIGN PHILOSOPHY ……………………………………………..21-22.
11.CEMENT CONCRETE ………………………………………………23-24.
12.WORKABILITY …………………………………………………….. 25.
13.WATER CEMENT RATIO …………………………………………..26.
14.MANUFACTURING OF CONCRETE ……………………………....27-29.
15.FORMWORK …………………………………………………………30.
16.CURING OF CONCRETE ……………………………………………31.
17.REMOVAL OF CONCRETE …………………………………………32.
18.DEWATERING ……………………………………………………….33-34.
19.CONCRETE MIX DESIGN …………………………………………...35-36.
20.RETAINING WALL …………………………………………………..37-38.
21.SLUMP TEST ………………………………………………………….39-41.
22.CONCRETE CUBE TEST ……………………………………………..42-45.
23.GENERAL NOTES …………………………………………………….46-48.
24.CONCLUSION ………………………………………………………….49.
INTRODUCTION

The building is defined as any structure what so ever purpose and of whatsoever materials
constructed and ever part thereof whether used as human habitation or not.

For this practical training , I reported at Jaypee Greens Sports City, at construction of KASSIA
Personal Suits ( Residential Buildings , Tower & Non –Tower , in response to Mr. B.L.Sahoo
(Vice- President) dated In connection with same, I have reported to Mr. Aashutosh Mishra
(General Manager) at Jaypee Greens Sports City , furthers ordered me to join project site. The
site incharge Mr. Prateek Shrivastva meet me at the site and gives me brief introduction of this
project as under.
Introduction of Project

The Jaypee Greens Sports City located on the Yamuna Expressway, spread over 5000 acres, is the latest
project launched by Jaypee Greens and comprises of India’s first International Motor racing track scheduled
to host India’s first F1 race in October, 2011, International standard cricket stadium, a 15.7 Kms long green
boulevard and much more. The development will be divided into various thematic districts offering
commercial, residential and institutional facilities. The Commercial zone will offer well defined areas for
elaborate financial and civic centers, along with this Residential Districts which will have a vast range of
products including villas, town homes, residential plots and mid to high rise apartment blocks, with regular
water supply and 24 hours electric power supply, to suit the requirements of all. A new residential
community of high rise apartments –. The luxurious apartments are set amidst a healthy and pollution free
neighborhood with numerous other facilities like a pitch & putt golf course, various themed gardens,
children play areas etc. Jaypee Greens Kassia are a limited edition personal suites amidst a fascinating
landscape parks. A home designed to value your own space, where style meets elegance and delights you
with a warm friendly living. Facing a serene water body and a boulevard running along to soothen your
senses, Kassia revolutionize your lifestyle with its unique architectural designs. Kassia comes as a marvel of
living in style where homes are available in the option of 1/2/3/4 bedroom personal floors as well as
breathtaking duplex apartments. Another classic feature of this city would surely be a 18 kms long Green
Boulevard spread across 215 acres with green landscapes and water bodies.

Fig. 1.1 Purposed view of KASSIA Personal Suites


About Project
Location:
Jaypee Greens Sports City
Concept:
The product has TROPICAL FEEL. The architecture style, landscaping is in sync with the theme.
 TROPICAL style outer façade of the towers.
 Use of tropical flora like Palm trees, mangroves all over the community.
 All the apartment towers will be surrounded by palm trees or face a water body.

Club House:
 Tropical architecture.
 Swimming pool designed with a tropical feel.
 Fully equipped fitness facility including a weight and cardio room and a trainer studio.
 Spa rooms.
 Massage room.
 Aerobics and yoga room.
 Media rooms for watching movies etc. 40-50 seats.
 Sports lounge.
 Catering kitchen and party room equipped with electric barbecue.
 Library.
 Kids play area.
 Party room.

Area:
Area (in sq
Sr.No. Type No. of Units per floor
ft.)
1. 1 BHK* 770 4

1 BHK + Study* 955 1

2. 2 BHK* 1100 2

3. 2 BHK + W* 1340 2

4. 3 BHK + W* 1690 2

5. 4 BHK + W**(Ground floor) 2015 1

6. 4 BHK + W** (1ST floor) 2140 1

* Simplex.
** Duplex.
Specification
Structure:
R.C.C Framed Structure
Air Conditioning:
Split AC as per design & apartment configuration
Living Room, Dining Room & Lounge:
Floors: Marble Flooring
External Doors and Windows: Window steel frame with wooden shutters doors.
Walls:
Internal: Oil Bound Distemper
External: Good Quality external grade paint.
Internal Doors: Enamel painted Flush doors.
Bedrooms & Dress:
Floors: Laminated Wooden flooring
External Doors and Windows: Window steel frame with wooden shutters Doors
Walls:
Internal: Oil Bound Distemper
External: Good Quality external grade paint.
Internal doors: Enamel painted Flush doors.
Wardrobes: Built-in wardrobe
Toilets:
Floors: Tiles
External Doors and Windows: Window steel frame with wooden shutters Doors.
Fixture and Fittings: All provided of Standard Company make Exhaust fan
Walls: Tiles in cladding up to 7’ in shower area and 3’-6” in balance areas.
Internal doors: Enamel painted Flush doors.
Kitchens:
Floors: Marble Flooring
External Doors and Windows: Window steel frame with wooden shutters Doors.
Fixture and Fittings: Stone Top with sink Exhaust fan
Walls: Ceramic Tiles 2’-6” above counter, Balance walls painted n Oil bound distemper.
Balconies & Verandah:
Floors: Tiles
Railings: MS Railing as per Design

Lift Lobbies & Corridors:


Floors: Ceramic / Mosaic Tiles / Marble / Kota or equivalent.
Location Details

 The project site will be well connected with the Yamuna Expressway along its east boundary,
Eastern Expressway on its west & ring road to South east.
 Proposed metro link would run parallel to the Yamuna Expressway. The main railway between Delhi
& Agra runs along the west boundary.
 0 Points (Greater Noida) – The time taken is 15 min (approx.)
 Noida/Greater Noida Expressway – The time taken is 25 min (approx.)
 South Delhi – the time taken is 35 – 42 min (approx.)

Fig. 1.1 Location Map of Jaypee Greens Sports City


Technical Report

1. GENERAL
1.1 Name of work Construction of Residential building (Tower & Non-Tower).

1.2 Name of zone Greater Noida

1.3 Name of division Greater Noida, Uttar Pradesh

2. LOCATION OF THE LAND

2.1 Location Runway between Delhi & Agra.

3. BRIEF SPECIFICATION As received from Chief Architect

3.1 Foundation concrete: Design mix concrete M-25


3.2 Foundation: R.C.C. Raft foundation having slab thickness 700 mm.

3.3 Wall:
(a) Basement outer wall of R.C.C. Retaining type in cement concrete M-25.
(b) Ground floor & first floor other wall of R.C.C. in cement concrete M-25 &
Brick masonry in cement mortar.

3.4 Structure
The complete structure is of RCC frame structure in M-25 concrete.

4. Other specifications
(a) Expansion &Contraction joint are provided.
(b) Bitumen treatment are provided at the roof.
(c) Water proofing is done by using chemical water proofing
materials e.g. Penybar etc.

5. ESTIMATED COST
The estimate cost of above Building comes to ` 180 crores of basements

& Six floors


6. PLINTH AREA RATE ` 3200 per Sq. Ft.
SITE PLAN AND PLANING OF BUILDING

The planning of the building has the most important role in the civil engineering
because well designed building has the comfort and good working conditions
for the people who live and work in it.

The project on which I take training it is a construction of residential


buildings. This building is designed very carefully by keeping the
following views:

 Swimming pool.
 Aerobics and yoga room.
 Media rooms for watching movies etc. 40-50 seats.
 Sports lounge.
 Catering kitchen and party room equipped with electric barbecue.
 Library.
 Kids play area.
 Car Parking.

.
This building is situated in the Jaypee Greens sports city, Kassia village. There are
the environmental condition is sun shiny and hot arid zone, good rain fall,
good neighboring conditions. The facing of the building is south.
BUILDING MATERIALS

A building structure is composed of different types of the material these materials


are either called as building material. The material use in the building on basis of
the avaibility and cost. For construct a building the essential
building material are as follow:

Cement
The cement often called the magic power is a fine ground material
consisting of compound of lime ,silica alumina and iron. When mixed with
water it forms a paste which hardened and bind the aggregates (sand, gravel,
crushed rock, etc.) together to form a durable mass called the Concrete.
Cement is the binder that holds concrete and mortars together. Which is why it
play the most critical role in giving strength and durability to your building.

Cement uses for domestic building such as home are basically of three types.

Portland Slag Cement: Portland slag cement (PSC) conforming to


IS:455 A combination of good quality blast furnace slag (from the iron steel industry)
with clinker (which makes the OPC) and gypsum.

Portland Pozzolana Cement: Portland pozzolana cement (PCC) conforming to


IS: 1489 A combination of flyash (from thermal power plant) with clinker and gypsum.
pozzolana cement is prepared by grinding Portland cement clinker with pozzolana. This

type of cement is largely used in marine structure.


Ordinary Portland Cement: Ordinary Portland cement (OPC) 33 grade
conforming to IS: 269, 43 grade conforming to IS: 8112 and 53 grade conforming to IS:
12269 A combination of clinker and gypsum of good quality. Ordinary Portland cement
is manufactured by first burning at a very high temperature the mixture of calcareous
(mainly calcium carbonate) and argillaceous (mainly clay) and then grinding the calcined
product (i.e. clinker) with small amount of gypsum in to a fine power known as

ordinary Portland cement.

Good quality cement has the following features:


Reduced water requirement
Improve Workability
Less permissible to moisture
Improved resistance to acid and chlorides
Reduced heat of hydration
Easier to finish
Reduced shrinkage
Reduced leaching problems because it is low as
Free lime
Sand

These are cohesion less aggregates of either, rounded sub rounded, angular, sub
angular or flat fragments of more or less unaltered rock of minerals consisting of
90% of particles of size greater than 0.06 mm and less than 2 mm.
Alternatively, these are coarse grained cohesion less particles of silica derived
from the disintegration of rock.
These are of three types:

Coarse sand: It is one which contains 90% of particles of size greater than 0.6
mm and less than 2 mm.

Medium sand: It is one, which contains 90 & of particles of particles size greater
than 0.2 mm and less than 0.6 mm.

Fine sand: It is one, which contains 90% of particles of size greater than 0.06 mm
and less than 0.2 mm.
Proper selection of sand is critical in the durability and performance of concrete
mixture. It should be:

Clear, angular and hard


Free from clay, mica and soft, flaky material
Graded, which means it should be a mix of fine, medium and coarse sand
Fee from contaminates like sea salt
Consistent in moisture (water) content which should not exceed 7%. When
mixing concrete the moisture
Content must be taken in to consideration.
The price of sand includes three or four components- base cost,
transportation, handling and number of Intermediaries. Procuring sand in bulk
directly from the source will be cheaper. Your neighborhood dealer in this case is
likely to be costlier, except when you need smaller quantities.

Building Stone

Building stones are obtained from the rocks occurring in nature. The stones are
used into construct the foundation, super structure and many of the building
components. The various stones derived from these types of rocks are as follows:

Principal stones from igneous rocks: Granite, Basalt and Trap


Principal stones from sedimentary rocks : Sand stone, Shale,
Lime stone
Principal stones from metamorphic rocks: Quartzite, slate and
marble

Properties or requirement of good building stone:


A good building stone should posses several characteristics such as high
strength (crushing strength>1000kg/cm ), high durability, sufficient hardness
(coefficient of hardness>14), high resistance to wear, good fire resistance,
specific gravity more than 2.7, crystalline structure, high impact value
(toughness index> 13) low water absorption (percentage absorption after 24
hour less than 0.6), weather resistance and better appearance.
Bricks

Bricks are distinguished by their base (row) material and size. Standard brunt clay
bricks come in the size 10" x 5" x 3". Modular bricks, rarely used because they
are not easily available, come in the size 200mm x 100mm x 100mm
(including mortar thickness) Fly ash bricks, sometimes also come in modular
form.
Conventional bricks have a frog (depressed / raised portion) on one of the
larger surface bearing the Manufacturer’s brand. These also provide a good
mechanical key for bonding (lock ability) with mortar.
The modular bricks do not have the frog on them. Fly ash bricks exhibit almost
similar mechanical properties as brunt clay bricks. Exposed brickwork with
precise pointing is possible if the shapes are perfect

Fig. 1.2 BRICKS


The four board categories of bricks used in construction:

Ist Class Brick IInd Class Brick IIIrd Class Brick Over burnet
Bricks
1. Perfect in Not so uniform as Ist Much interior to Absolutely out
Size/shape/ class bricks in IInd class bricks shape of size,
quality of Size/shape/ quality of in terms of over burnet.
burning burning Size/shape/ quality Fused with more
of bricks with a
burning honey comb
texture
2. Red to cherry Red in color . Dark red in color. Black in color.
red in color.

3. Do not absorb Do not absorb more Do not absorb


more than 15- than 22% water of more than 25%
17% water of their own weight , if water of their own
their own weight kept submerged for weight , if kept
, if kept one hour under water. submerged for one
submerged for hour under water
one hour under
water
4. Suitable for Used for internal Used for interior Not used in
floors & walls. construction works building
reinforced brick , where less construction
slabs. rainfall occurs works & used as
road metal, also
in foundations.
Aggregate

Aggregates is a general term applied to those inert (that chemically inactive)


material, which when bounded together by cement, form concrete. Most
aggregates used in this country are naturally occurring aggregates such as
Sand , crushed rock and gravel.

Fig. 1.3 Aggregates

Aggregates for concrete are divided into three categories:

Fine Aggregates: Most of which passes through 4.75 mm I.S. sieve


and retained on 150 micron.
Coarse Aggregates: Most of which passes through 63 mm I.S. sieve
and retained on 4.75 micron.
All in Aggregate: Mixed aggregate, as it comes from the pit or riverbed.
It is sometimes used for unimportant work without separating into different
sizes.
Properties of Natural Aggregates:

The properties should comply with the norms laid down in IS: 38-1970
Specification for C.A. and F.A. from natural sources for concrete. Aggregates
should be chemically inert, strong, hard, durable, of limited porosity (water
absorption when immersed in water for 24 hours should not be more than 10%.),
free from adherent coating, clay lumps, coal and coal residues and should
contain no organic or other admixture that may cause corrosion of the reinforcement
or impair the strength or durability of the concrete. The shape (rounded,
irregular, angular and flaky) and sizes of the aggregates should conform to the
strength and workability requirements.

Uses of the Aggregates:

1. Naturally occurring crushed stone aggregates can be used for producing


any type of good concrete or R.C.C. for construction purpose.
2. Broken brick aggregates is used to produce plain concrete but not suitable
for R.C.C. which is lighter than broken stone aggregate.
3. Air- cooled blast furnace slag, which is a by- product in the process of pig iron,
forms a stronger and durable concrete when mixed with sand, and has a high fire
resistance.
.
Reinforcement Steel

RCC stands for reinforced cement concrete. To enhance the load carrying capacity
of the concrete it is reinforced with steel bars of different diameters provided in an
appropriate manner. Such concrete is called reinforced concrete and the bars
are called the reinforcement. These bars are provided at various locations to
resist the internal forces, which are developed due to the loads acting on the
structure.

Fig. 1.4 Reinforcement Steel.

Reinforcing steel contributes to the tensile strength of the concrete. Concrete


has low tensile, but high compressive strength. The tensile deficiency is
compensated by reinforcing the concrete mass through insertion of plain or
twisted mild steel bars. Both branded and unbranded bars are available. It is
wise to buy good brands the names of which are marked on the steel. During
construction make sure that steel reinforcement is provided exactly as the
engineering design specification.
Precautions:

Steel bars/rods should be responsibly clean and free of rust.


Bars that cannot be easily bent manually or mechanically should be rejected.
Optimum length bars must not be chosen to reduce wastage in cutting.
To avoid laps, shorter bars must not be accepted
Welded length of the bars should not be accepted

Water

The strength and durability of concrete depends also on the amount of water mixed
with it. Too much or too little Water can adversely affect the strength of concrete.
After concrete is cast, water is used to cure it so that the temperature is
controlled and concrete matures slowly.
It is very important to use clean, potable water in quality concrete production.
Brackish or salty water must never be used. Contaminated water will produce
concrete mortars with lower durability, erratic set characteristics and inconsistent
colour.
THE EFFECT OF AGGREGATE PROPERTIES
ON CEMENT CONCRETE

Concrete is a mixture of cementious material, aggregate and water. Aggregate


is commonly considered inert filler, which accounts for 60 to 80% of the volume
and 70 to 85% of the weight of the concrete. Although aggregate is considered
inert filler, it is a necessary component that defines the concrete s thermal and
elastic properties and dimensional stability.

Physical and mineralogical properties of aggregate must be known before mixing


concrete to obtain a desirable mixture. These properties include shape and
texture, size gradation, moisture content, specific gravity, reactivity, soundness,
and bulk unit weight. These properties along with water /cementitious material
ratio determine the strength, workability and durability of the concrete.

The shape and texture of the aggregate affects the properties of fresh
concrete more than hardened concrete. Concrete ids more workable when
smooth and rounded aggregate is used instead of rough angular or elongated
aggregate. Crushed stone produces much more angular and elongated aggregate,
which have a higher surface to volume ratio better bond characteristics but
require more cement paste to produce a workable mixture.

The surface texture of the aggregate can be either smooth or rough. A smooth
surface can improve workability yet a rougher surface generates a stronger bond
between the paste and the aggregate creating a higher strength.

The grading or size distribution of aggregate is an important characteristic


because it determines the paste requirement for workable concrete. The required
amount of the concrete paste is dependent upon the amount of void space that
must be filled and the total surface area that must be covered. When the particles
are of uniform size the spacing is the greatest but when a range of sizes is used the
void spaces are filled, the less workable the concrete becomes, therefore, a
compromise between workability and economy is necessary.
The moisture content of an aggregate is an important factor when developing
the proper water/cementitious material ratio. The density of the aggregate is
required in mixture proportioning to establish weight- volume relationships
REINFORCEMENT CEMENT CONCRETE

Plain concrete is very strong in compression but its tensile strength is only
about 1/10 of the strength in the compression. So, the use of the plain concrete
is limited to the structure in pure compression. Steel being equally strong in
compression and tension, is, therefore, used to reinforce the concrete in a suitable
way so that it can be used to build supporting structure where tension also
develops . Concrete, thus reinforced is known as reinforced concrete .

This combination is made because long steel bars can develops its full
strength where it cannot carry equal amount of compressive force due to its
buckling which is caused by the slenderness. Thus, the combination of concrete
and steel bars has proved to be ideal, as the two material are used to resist the
stresses for which they are most suitable.

Fig. 1.5 Reinforced Cement Concrete


Properties of the reinforced cement concrete:
1) The concrete develops very good bond with the surface of the steel bars and ,
therefore the stresses are transferred from one material to the other which Cannot
resist individually.
2) The steel possesses a high tensile strength, a high modulus of elasticity
and same coefficients of expansion and contraction as concrete. Due to equal
linear coefficients, no internal stresses are set up within reinforced
concrete due to variation in temperature.
3) The coating of cement grout or paste on the surface of the reinforcement
protects it from corrosion and at the same time it does not chemically react
with the reinforcement.

Advantages of the reinforcement cement concrete:

1) It is overall economical in ultimate cost.


2) Its monolithic character provides more rigidity to the structure.

3) It is highly durable and fire resisting. It is not affected by the vermins termites
fungus or such other insects.
4) Well-compacted R.C.C. structure is impermeable to moisture penetration.
5) Care and cost of maintenance of R.C.C. structure are almost negligible.
6) The fluidity of the concrete and flexibility of reinforcement make it to
possible to mould the R.C.C. members into variety of shapes desired.
Design philosophy

R.C.C. design of building is being carried out mainly by three methods of design.
They are namely:
(1) Working stress method
(2) Ultimate load method and
(3) Limit state method.

The Limit state method is now is vogue in all government design offices
and premier private
consulting firms. The B.I.S. have published I.S.: 456-2000 incorporating the
use of the Limit state method of
design. The designer should therefore get well versed with the theory of Limit
state method.

Working Stress Method: In this method the design is based on the working
load and the criterion for the strength of the structure is its capacity to
sustain the loads and forces imposed on it.
Fig 1.6 Methods of RCC Design
Limit State Method is a judicious amalgamation of Working Stress Method and
Ultimate Stress Method, removing the drawback of both of the method but retaining
their good points. It is also based on sound scientific principles and backed by 25 year of
research.
The Limit State Method has proved to have an edge over the Working Stress Method
from the economic point of view. Consequently we need no stick to Working Stress
Method any more.

Besides analytical part of the structural design, following factors should also be kept in
mind while designing the structure.

a) Strength of structure.
b) Durability of structure.
c) Serviceability of structure during construction as well as during design
lifetime of structure.
d) Economy in building material and ease of constructions.
e) Economy in centering and formwork.
f) Aesthetics of structure
Cement concrete

Cement concrete is a composite material used for construction of various civil


engineering structures. It is obtained by mixing the basic ingredients such as
cement, Fine aggregate (normally sand) and coarse aggregate (normally stone
pieces) in required proportions. Water is added in the required measure and the
mixture is put into a mechanical mixer to achieve concrete. Concrete is poured
into the formwork (mould made up of plywood, steel plates and timber) to get the
desired shape. It is then vibrated to achieve proper compaction (uniform
denseness). High temperature is generated through chemical reaction in this
process. Curing (control of temperature) with water is essential to achieve the
desired strength of the concrete.

Concrete gains compressive strength progressively with time. The strength


achieved at the end of the 28 days is called the Characteristics Compressive
Strength of the concrete and is designed as a Grade. About 60% of this strength is
achieved at the end of the 7 days from the date of casting. Concrete continues to
gain strength even beyond 28 days, albeit marginally. The form is subsequently
removed. Different compressive strength of the concrete can be achieved by
mixing the basic ingredients in different proportions. Being a material
moulded at site, the durability of the concrete over a long period of time depends
on its mixing, placement, vibration and curing which together contribute to
its workmanship .
Fig 1.7 Cement – Concrete

Properties of Cement concrete

Strength of concrete:-
It should be have high compressive strength. The tensile and shear strengths are
generally about 8 to 12% and 8 To 10% of their compressive strength respectively.
The compressive strength of concrete is affected by several factors such as
(a) Quality of the material and grading of the aggregates
(b) Water
(c) Water cement ratio
(d) Cement content
(e) Age of the concrete
(f) Method of mixing placing compacting and curing
Workability of concrete
The concrete should have sufficient workability. The workability of the concrete
indicates the ease with which it can be mixed, placed and compacted. Generally
the strength decreases with increases of the workability.

Durability of concrete
The concrete possess a high durability value, as it is not much affected by
atmospheric action. On the contrary, with the age, the concrete goes on
hardening, thereby increase in the strength. It is this property, which gives
This material a distinct place among the building material.

Elasticity of concrete
The concrete is not a truly elastic material and elastic modulus is effect by
the strength, age, and moisture content of the concrete and the type of the
aggregate used. The concrete undergoes an extra strain in addition to instantaneous
strain on application of a load or stress, sufficient time. This extra strain is called
creep of concrete and is permanent in character not recovered on the removal of
load.

Shrinkage of concrete
The concrete has a tendency to shrink under following conditions:-
(a) There is initial shrinkage of cement concrete, which is mainly due to loss of
water through forms, absorption by surface of forms.
(b) The shrinkage of cement concrete occurs as it is hardened. This tendency
of shrinkage on one-hand causes cracks in concrete, while on the other, it grips
the reinforcement tightly and hence proper bond between concrete and
reinforcement when used in R.C.C. work
Fire resistance of concrete
Concrete is good insulator and has a fairly good fire resistance owing to the
presence of pores and also water.
Workability

Workability is the most elusive property of concrete. A concrete is said to be


workable if it can be easily mixed, handled, transported, placed in position and
compacted. A workable concrete should not show any segregation Or bleeding.
The segregation is said to occur when the coarse aggregate tries to separate
out from the finer material and
this result in concentration of coarse aggregate at one place and fine material
at another place in the mass concrete. The segregation creates larger voids
and reduces the durability and strength both.
The bleeding of concrete is said to occur when excess water comes up at the
surface of the concrete. This causes the undesirable small pores through the
mass of the concrete.

The workability of the concrete effected by many factors: -


(a) Shape of the aggregates
(b) grading and size of the aggregates
(c) ratio and coarse and fine aggregates
(d) efficiency of mixing
(e) quantity of water and use of any mixture.

For maximum strength, the desired workability of fresh concrete can be attained
by the following measure:

(i) The proportion of coarse aggregate may be reduced, because the


finer is the grading, the greater will be the workability.
(ii) The proportion of coarse aggregate may be reduced while on the
other hand corresponding increases may be made in that of the finer
aggregates.
(iii) The process of mixing concrete can be repeated second time by
use of the vibrator.
Water cement ratio

Water cement ratio is the ratio of the water in a mix (excluding water
absorbed already by the aggregate) to the weight of cement their in. water cement
ratio is the most important factor governing the strength of concrete. The
strength of the concrete depend mainly open the amount of cement and the amount
of water in it. The correct quantity Of water cement ratio required for a particular
mix depends upon various factors such as mix proportions, type and grading of
aggregate, method of compaction applied and weather condition.

Fig. 1.8 Water- Cement Ratio


On the other hand workability of a concrete mix increases as the water content
or water cement ratio of mix increased, because the water lubricate the mixture.
But, at the same time increases in water content deceases the strength. Excess
of water, further weaken the concrete, produces shrinkage cracks and decreases
density.
Manufacture of the concrete

In the manufacture of concrete, it is almost important to ensure that a


concrete of predetermined proportion is continuously placed in position in such
a way that each batch almost like the other batches as far as possible.

Batching of the concrete


After fixing the proportion of different ingredients of concrete for a particular
work, the material C.A., F.A., cement and water measured out in batches for
mixing. The process is known as Batching. This process of batching may be

carried out by weight or by volume.

(i) Weight batching: - The unit of weight, for material of concrete, is usually
Kilogram. The batching of material by weight is absolutely straightforward,
the cement, sand and coarse aggregate being all weighed directly in Kilogram.
(ii) Volume batching: - In batching by volume, all ingredient i.e. water, cement,
sand and coarse aggregate are measured in liters, where the resulting concrete
(being) solid measured in cubic meters.

Mixing of concrete
Mixing of concrete may be carried out by hand or machine (by using a mechanical
mixture) but the mixing by machine is always preferred.

(i) Mixing by hand :- In this, mixing carried out by hand on a clean, hard
and water tight platform. Firstly cement, sand, aggregate are mixed by hand with
the help of the shovel and a desired quantity of the water added to it and mix
properly. This type of mixing carried out in the small work and unimportant work.
(ii) Mixing in machine: - The machine used for mixing concrete is known as
mechanical concrete mixer. There are two main type of concrete mixer is
commonly use namely:
Continuous mixers are used in massive construction such as dams, bridges,
etc., which involve the use of large masses of concrete and also required
the continuous flow of concrete.

Batch mixer is most commonly used and consisting of a revolving drum with
blades or baffles inside it. In batch mixer, all the material of desired
proportioned mix are fed into the hopper of the revolving drum on being
rotated at a certain speed mixes the material with the aid of a series of blades
providing inside, the resulting mix is finally discharged from the drum and
conveyed for used

Transporting the concrete

Transporting the concrete mix is defined as the transferring of concrete from the
mixing plant to the construction site. Keep in mind that not all concrete is
mixed on the actual construction site and could require some significant travel.
This is most common for ready mixed concrete. The main objective in transporting
concrete is to ensure that the water cement ratio, slump or consistency, air
content, homogeneity are not modified from there intended states.
The concrete transport commonly by the steel pipes

Placing and finishing of concrete


Mixing, transporting, and handling of concrete should be carefully coordinated
with placing and finishing operations. Concrete should not be deposited more rapidly
than it can be spread, struck off, consolidation, and bull floated. Concrete
should be deposited continuously as near as possible to its final position. In
slab construction, placing should be started along the perimeter at one end of
the work with each batch placed against previously dispatched concrete. Concrete
should not be dumped in separate piles and then leveled and worked together; nor
should the concrete be deposited in large piles and moved horizontally into final

position.

Consolidation
In some types of construction, the concrete is placed in forms, and then
consolidated. The consolidation compacts fresh concrete to mold it within the
forms and around embedded items and reinforcement and to eliminate stone
pockets, honeycomb and entrapped air. It should not remove significant amount
of intentionally entrained air.

Vibration either internal or external is the most widely used method for
consolidating concrete. When concrete is vibrated, the internal friction between
the aggregate particles is temporarily destroyed and the concrete behave like
a liquid; it settles in the forms under the action of gravity and the large
entrapped air voids rise more easily to the surface. Internal friction is
reestablished as soon as vibration stops.
Finishing

Concrete that will be visible, such as slab like driveway, highway or patios often
need finishing. Concrete slabs can be finished in many ways, depending on the
intended service use. Options include various colors and textures, such as exposed
aggregate or a patterned stamped surface. Some surface may require only
strike off and screeding to proper contour and elevation, while for other
surface a broomed, floated, or troweled finish may be specified. In slab
construction screeding or strike off is the process of cutting off excess concrete to
bring the top surface of the slab to proper grade. A straight edge is moved across
the concrete with a sawing motion and advanced forward a short distance with
each movement.
Bull floating eliminates high and low spots and embeds large aggregate particles
immediately after strike off.
This look like a long handled straight edge pulled across the concrete. Joining is
required to eliminate unsightly random cracks. Construction joints are made
with a groover or by inserting strips of plastic, wood, metal, or performed joints
material into the unhardened concrete. Saw cut joints can be made after the
concrete is sufficiently hard or strong enough to prevent the reveling. After
the concrete has been jointed it should be floated with a wood or metal hand
float or with a finishing machine using float blades. This embeds aggregate
particles just beneath the surface; removes slight imperfections, humps, and
voids; and compacts the mortar at the surface in preparation for addition finishing
operations. Where a smooth, hard, dense surface is desired, floating should
be followed by steel troweling. Troweling should not be done on a

Surface that has not been floated; troweling after only bull floating is not an
adequate finish procedure. A slip resistant surface can be produced by brooming
before the concrete has thoroughly hardened but it should be sufficient hard
to retain the scoring impression.
FORMWORK

‘Temporary Supporting Structure’ is those structures, which are temporarily required in


building construction either for supporting the laying of concrete till it gets matured, such as
formwork or forms or shuttering. As fresh concrete is in a plastic state, when it is placed
for construction purposes, so it becomes necessary to provide some temporary structure to
confine and support the concrete, till it gains sufficient strength for selfsupporting.
The temporary structure is known as Formwork or shuttering.

Requirement of the formwork

God forms for concrete structure should satisfy the following requirements;
(1) It should be strong enough to resist the pressure or the weight of the fresh concrete and
the superimposed loads due to equipment, men etc. This requires careful design of formwork,
because the consideration of overloads will affects the economy whereas of under loads may
cause failure of the forms work.
(2) It should be rigid enough to retain the shape without undue deformation.
(3) It must be made or constructed so light that it does not allow the cement paste to leak
through the joints.
(4) The inside surface of the formwork should be smooth so as to give good appearance to the
resulting concrete surface. To achieve this, the inside surface of formwork is usually applied
with crude oil or soft soap solution. This also facilitates the removal of the formwork.
(5) The entire formwork should be so made that it can be removed easily without causing the
least injury to the surface or edges of the concrete.
(6) It should be made economical by reducing the cost through proper design, construction
and use of formwork.
Curing of concrete

Curing is one of the most important steps in concrete construction, because proper curing
greatly increase concrete strength and durability. Concrete hardened as a result of hydration:
the chemical reaction between cement and water. However, hydration occurs only if
water is available and if the concrete temperature stays within a suitable range. During the
curing period from five to seven days after placement for conventional concrete the concrete
surface needs to be kept moist to permit the hydration process. New concrete can be wet with
soaking hoses, sprinklers or covered with wet burlap, or can be coated with commercially
available curing compounds, which seal in moisture.
After concrete is placed, a satisfactory moisture contents and temperature (between 50º F and
75º F) must be maintained, process called curing. Adequate curing is vital to quality concrete.
Curing has a strong influence on the properties of hardened concrete such as durability,
strength, water tightness, abrasion resistance, volume, stability and resistance to freezing and
thawing and deicer salts. Exposed slab surfaces are especially sensitive to curing. Surface
strength development can be reduced significantly when curing is defective.
Curing the concrete aids the chemical reaction called hydration. Most freshly mixed concrete
contains considerably more water than is required for complete hydration of the cement;
however, any appreciable loss of water by evaporation or by otherwise will delay or prevent
the hydration. If temperature are favorable, hydration is relatively rapid the first few days
after concrete I s placed; retaining water during this period is important. Good curing means
evaporation should be prevented or reduced.
Removal of the formwork

The period for which forms should be left in place depends upon the temperature of air, the
shape and position of structural member (i.e. horizontal vertical or inclined), the nature of the
loads likely to come and the character of the cement and cement paste. Generally, the use of
rapid hardening cement, higher temperatures, low water cement ratio and lighter loads, will
permit early removal of formwork. Under normal conditions where temperature is above
20ºC and ordinary cement is use, forms may be removed after the expiry of the period given
below:

Particulars of the structural period of member removing of formwork


(a) Vertical slides of slabs, beams 24 to 48 hours columns and wall
(b) Slabs (props or vertical supporting 3 days member left under)
(c) Beams soffits (props left under) 7 days
(d) Bottom of slabs up to a span 7 days of 4.5 m.
(e) Bottom of slabs above 4.5 m 14 days span, bottom of the beams up to 6 m span, and
bottom of arch ribs up to 6 m span
(f) Bottom of beams over 6 m span 21 days and bottom of arch ribs over 6 m span
DEWATERING

Dewatering is the removal of water from solid material or soil by wet classification,
centrifugation, filtration or similar solid-liquid separation processes, such as removal of
residual liquid from a filter cake by a filter press as part of various industrial processes.

Construction dewatering, unwatering, or water control are common terms used to describe
removal or draining groundwater or surface water from a riverbed, construction site, caisson
or mine shaft, by pumping or evaporation. On a construction site, this dewatering may be
implemented before subsurface excavation for foundations, shoring, or cellar space to lower
the water table. This frequently involves the use of submersible "dewatering" pumps,
centrifugal ("trash") pumps, eductors, "dewatering" by electro osmosis, or application
of vacum to well points.
Dewatering by horizontal drainage

The installation of horizontal dewatering systems is relative easy. A trencher installs first an
unperformed pipe followed by a synthetic or organic wrapped perforated pipe. The drain
length is determined by the drain diameter, soil-conditions and the water table. In general
drain lengths of 50 meter is common. After installation of the drainpipe a pump is connected
to the drain and water can be pumped out. After the water table has been lowered the
intended construction can start. After the construction is finished the pumps are stopped and
the water table will rise again. Installation depths up to 6 meter are common.

Fig. 1.9 Dewatering by Horizontal drainage.


CONCRETE MIX DESIGN

Introduction
Concrete is the basic engineering material used in most of the civil engineering structures.
Its popularity as basic building material in construction is because of, its economy of use,
good durability and ease with which it can be manufactured at site. The ability to mould it
into any shape and size, because of its plasticity in green stage and its subsequent hardening
to achieve strength, is particularly useful.
Concrete like other engineering materials needs to be designed for properties like strength,
durability, workability and cohesion. Concrete mix design is the science of deciding
relative proportions of ingredients of concrete, to achieve the desired properties in the
most economical way.
With advent of high-rise buildings and pre-stressed concrete, use of higher grades of
concrete is becoming more common. Even the revised IS 456-2000 advocates use of higher
grade of concrete for more severe conditions of exposure, for durability considerations.
With advent of new generation admixtures, it is possible to achieve higher grades of concrete
with high workability levels economically. Use of mineral admixtures like fly ash, slag, meta
kaolin and silica fume have revolutionised the concrete technology by increasing strength and
durability of concrete by many folds. Mix design of concrete is becoming more relevant in
the above-mentioned scenario.
However, it should be borne in mind that mix design when adopted at site should be
implemented with proper understanding and with necessary precautions.
Durocrete mix design manual is an attempt to increase the awareness among the
users, about concrete mix design. It is made with intention of serving as ready
reckoner for personnel, implementing mix design at site.

Advantages of mix design


Mix design aims to achieve good quality concrete at site economically.
I. Quality concrete means
• Better strength
• Better imperviousness and durability
• Dense and homogeneous concrete
II. Economy
a) Economy in cement consumption
It is possible to save up to 15% of cement for M20 grade of concrete with the
help of concrete mix design. In fact higher the grade of concrete more are the
savings. Lower cement content also results in lower heat of hydration and hence
reduces shrinkage cracks.
b) Best use of available materials:
Site conditions often restrict the quality and quantity of ingredient materials.
Concrete mix design offers a lot of flexibility on type of aggregates to be used in
mix design. Mix design can give an economical solution based on the available
materials if they meet the basic IS requirements. This can lead to saving in
transportation costs from longer distances.
c) Other properties:
Mix design can help us to achieve form finishes, high early strengths for early
deshuttering, concrete with better flexural strengths.
What is mix design?
Concrete is an extremely versatile building material because, it can be designed for strength
ranging from M10 (10Mpa) to M100 (100 Mpa) and workability ranging from 0 mm slump
to 150
mm slump. In all these cases the basic ingredients of concrete are the same, but it is their
relative proportioning that makes the difference.
Basic Ingredients of Concrete: -
1. Cement – It is the basic binding material in concrete.
2. Water – It hydrates cement and also makes concrete workable.
3. Coarse Aggregate – It is the basic building component of concrete.
4. Fine Aggregate – Along with cement paste it forms mortar grout and fills the voids in the
coarse aggregates.
5. Admixtures – They enhance certain properties of concrete e.g. gain of strength,workability,
setting properties, Imperviousness etc.
Concrete needs to be designed for certain properties in the plastic stage as well as in the
hardened stage.
Properties desired from concrete in plastic stage: -
• Workability
• Cohesiveness
• Initial set retardation

Properties desired from concrete in hardened stage: -


• Strength
• Imperviousness
• Durability

Concrete mix design is the method of correct proportioning of ingredients of concrete, in


order to optimize the above properties of concrete as per site requirements.
In other words, we determine the relative proportions of ingredients of concrete to achieve
desired strength & workability in a most economical way.
Retaining Wall

Definition

A retaining wall is a structure designed and constructed to resist the lateral pressure of soil
when there is a desired change in ground elevation that exceeds the angle of repose of the
soil.

A basement wall is thus one kind of retaining wall. But the term usually refers to a cantilever
retaining wall, which is a freestanding structure without lateral support at its top. These are
cantilevered from a footing and rise above the grade on one side to retain a higher level grade
on the opposite side. The walls must resist the lateral pressures generated by loose soils or, in
some cases, water pressures.

Fig.1.10 Retaining Wall

Every retaining wall supports a “wedge” of soil. The wedge is defined as the soil which
extends beyond the failure plane of the soil type present at the wall site, and can be calculated
once the soil friction angle is known. As the setback of the wall increases, the size of the
sliding wedge is reduced. This reduction lowers the pressure on the retaining wall.

The most important consideration in proper design and installation of retaining walls is to
recognize and counteract the tendency of the retained material to move downslope due
to gravity. This creates lateral earth pressure behind the wall which depends on the angle of
internal friction (phi) and the cohesive strength (c) of the retained material, as well as the
direction and magnitude of movement the retaining structure undergoes.

Lateral earth pressures are zero at the top of the wall and - in homogenous ground - increase
proportionally to a maximum value at the lowest depth. Earth pressures will push the wall
forward or overturn it if not properly addressed. Also, any groundwater behind the wall that
is not dissipated by adrainage system causes hydrostatic pressure on the wall. The total
pressure or thrust may be assumed to act at one-third from the lowest depth for lengthwise
stretches of uniform height.

Unless the wall is designed to retain water, It is important to have proper drainage behind the
wall in order to limit the pressure to the wall's design value. Drainage materials will reduce or
eliminate the hydrostatic pressure and improve the stability of the material behind the
wall. Drystone retaining walls are normally self-draining.

As an example, the International Building Code requires retaining walls to be designed to


ensure stability against overturning, sliding, excessive foundation pressure and water uplift;
and that they be designed for a safety factor of 1.5 against lateral sliding and overturning.
SLUMP TEST

The slump test is the most well-known and widely used test method to characterize the
workability of fresh concrete. The inexpensive test, which measures consistency, is used on
job sites to determine rapidly whether a concrete batch should be accepted or rejected. The
test method is widely standardized throughout the world, including in ASTM C143 in the
United States and EN 12350-2 in Europe.
The apparatus consists of a mold in the shape of a frustum of a cone with a base
diameter of 8 inches, a top diameter of 4 inches, and a height of 12 inches. The mold is filled
with concrete in three layers of equal volume. Each layer is compacted with 25 strokes of a
tamping rod. The slump cone mold is lifted vertically upward and the change in height of the
concrete is measured.
Four types of slumps are commonly encountered, as shown in Figure 3. The only type of
slump permissible under ASTM C143 is frequently referred to as the “true” slump, where the
concrete remains intact and retains a symmetric shape. A zero slump and a collapsed slump
are both outside the range of workability that can be measured with the slump test.
Specifically, ASTM C143 advises caution in interpreting test results less than ½ inch and
greater than 9 inches. If part of the concrete shears from the mass, the test must be repeated
with a different sample of concrete. A concrete that exhibits a shear slump in a second test is
not sufficiently cohesive and should be rejected.

Fig. 1.11 Four Types Of Slumps

The slump test is not considered applicable for concretes with a maximum coarse aggregate
size greater than 1.5 inches. For concrete with aggregate greater than 1.5 inches in size, such
larger particles can be removed by wet sieving.
Additional qualitative information on the mobility of fresh concrete can be obtained
after reading the slump measurement. Concretes with the same slump can exhibit different
behavior when tapped with a tamping rod. A harsh concrete with few fines will tend to fall
apart when tapped and be appropriate only for applications such as pavements or mass
concrete. Alternatively, the concrete may be very cohesive when tapped, and thus be suitable
for difficult placement conditions.

Slump is influenced by both yield stress and plastic viscosity; however, for most cases the
effect of plastic viscosity on slump is negligible. Equations have been developed for
calculating yield stress in terms of slump, based on either analytical or experimental analyses.
Since different rheometers measure different absolute values for the yield stress of identical
samples of concrete, the experimental equations are largely depended on the specific device
used to measure yield stress.
SLUMP TEST PROCEDURE (FIELD TESTING)

1 To obtain a representative sample, take samples from two or more regular intervals
throughout the discharge of the mixer or truck. DO NOT take samples at the beginning or the
end of the discharge.
2 Dampen inside of cone and place it on a smooth, moist, non-absorbent, level surface large
enough to accommodate both the slumped concrete and the slump cone.Stand or, foot pieces
throughout the test procedure to hold the cone firmly in place.
3 Fill cone 1/3 full by volume and rod 25 times with 5/8-inchdiameter x 24-inch-long
hemispherical tip steel tamping rod. (This is a specification requirement which will produce
nonstandard results unless followed exactly.) Distribute rodding evenly over the entire cross
section of the sample.
4 Fill cone 2/3 full by volume. Rod this layer 25 times with rod penetrating into, but not
through first layer. Distribute rodding evenly over the entire cross section of the layer.
5 Fill cone to overflowing. Rod this layer 25 times with rod penetrating into but not through,
second layer. Distribute rodding evenly over the entire cross section of this layer.
6 Remove the excess concrete from the top of the cone, using tamping rod as
a screed. Clean overflow from base of cone.
7 Immediately lift cone vertically with slow, even motion. Do not jar the concrete or
tilt the cone during this process. Invert the withdrawn cone, and place next to, but not
touching the slumped concrete. (Perform in 5-10 seconds with no lateral or torsional
motion.)
8 Lay a straight edge across the top of the slump cone. Measure the amount of slump in
inches from the bottom of the straight edge to the top of the slumped concrete at a point over
the original center of the base. The slump operation shall be completed in a maximum
elapsed time of 2 1/2 minutes. Discard concrete. DO NOT use in any other tests.
Fig. 1.12 Slumped concrete

Advantages:
• The slump test is the most widely used device worldwide. In fact, the test is so well known
that often the terms workability and slump are used interchangeably, even though they have
different meanings.
• The slump test is simple, rugged, and inexpensive to perform. Results are obtained
immediately.
• The results of the slump test can be converted to yield stress in fundamental units based on
various analytical treatments and experimental studies of the slump test.
• Compared to other commonly used concrete tests, such as for air content and
compressive strength, the slump test provides acceptable precision.
Disadvantages:
• The slump test does not give an indication of plastic viscosity.
• The slump test is a static, not dynamic, test; therefore, results are influenced by concrete
thixotropy. The test does not provide an indication of the ease with which concrete can be
moved under dynamic placing conditions, such as vibration.
• The slump test is less relevant for newer advanced concrete mixes than for more
conventional mixes.
CONCRETE CUBE TEST

Making cubes
Collect a composite sample to the standard method described above.Concrete sampled using
the alternative spot method must not be used to make cubes.
Step 1
• Check that the moulds are clean and lightly oiled with all bolts tightened so that there
will be no leakage
• Ensure that the correct halves of the moulds are used and that the corner lifting pins are
correctly located
• Thoroughly remix the sample as described for the slump test

Fig. 1.12 Checking the mould’s bolts.


Step 2

• Fill the mould with concrete in 50mm layers using the tamping bar, compact the concrete
with no fewer than 25 tamps for each of the two layers in a 100mm mould and no fewer than
35 tamps for for each of the three layers in a 150mm mould
• For very high workability concrete you may not need the minimum number of tamps
Fig. 1.13 Temping the mould with temping bar.

Step 3
• After tamping of each layer, tap the sides of the mould with the hide hammer until large
bubbles of air cease to appear on the surface and the holes left by the tamping bar are closed

Fig. 1.14 Taping the sides of mould with hide hammer


Step 4
• Remove surplus concrete and smooth over with a float
• Wipe clean the mould edges
• Number the moulds for identification and record details and immediately place where they
are to be stored overnight

Fig. 1.15 Clearing the mould edges.

Step 5
• Cover each mould with a damp cloth and plastic sheet
• Store inside at room temperature (15-250C) e.g. on top of the curingtank
• Protect the cube moulds at all times from high and low temperature (especially sub-zero
temperatures) and drying winds
• Complete the sampling and cube making certificates

Fig. 1.16 Covering the mould by damp cloth.


Storing cubes

Having stored the moulds at between 15_250C the cubes should be removed from the moulds
no earlier than 16 hours and no later than 72 hours after casting.
Step 1
• Record the maximum/minimum overnight storage temperatures on the certificate
Step 2
• Slacken all nuts
• Part the sides of the mould, tapping gently with the hide hammer
• Lift off carefully
• Remember new cubes are easily damaged unless handled carefully

Fig. 1.17 Lifting off the mould.


Step 3
• Mark each cube with its identification number on two of its cast sides
Place the cubes in the curing tank with the water temperature controlled at 200C ± 20C and
the cubes covered by water.
Fig. 1.18 Placing the cubes in the curing tank.

Step 5

• Clean and reassemble the moulds


• Make sure the power supply is not switched off day or night
• Check the temperature range daily using the maximum/minimum thermometer
• Keep a record of the readings.
GENERAL NOTES

The general notes specify the quantities and quantities of materials, the proportion of the
mortar, workmanship. The method of preparation and execution and the methods of the
measurement. The company prepares the general notes of various items of work, and gets
them printed in the book from under the name of general notes. Some of the general notes are
given below related to Building Construction.

1. Earthwork in excavation in foundation:-



Excavation- Foundation trenches shall be dug out to the exact width of the
foundation concrete and the sides shall be vertical. If the soil is not good and does not permit
vertical sides, the sides should be sloped back or protected with timber shoring.

Finish and Trench- The bottom of the foundation trenches shall be perfectly
leveled both longitudinally and transversally and the sides of the trench shall be dressed
perfectly vertical from bottom up to least thickness of lose concrete may be laid to the exact
width as per design. The bed of the trench shall be tightly watered and well rammed. Soft or
defective spots shall be dug out excess digging if done through mistake shall be filled with
concrete.

Measurement- The measurement of the excavation shall be taken in cu m as for


rectangular trench, bottom width of concrete multiplied by the vertical depth of the
foundation from ground level and multiplied by the length of the trench.
2. Foundation

 The foundation of the building should be so planned and the lay out of the foundation
should be on the ground should be correct in the measurement.
 Should not place the concrete in the foundation before checked by the Engineer-in
charge.
 If building has the basement more than two raft foundations should be provided.
 In the P.C.C. it should be in the ratio of 1:4:8 and 75 mm thick 75 mm projected
beyond raft foundation.
 The concrete provided in the raft foundation should be M-25 grade conforming to
IS456.

 The design and thickness of the raft foundation provided by the soil testing.
3. Reinforcement Concrete Work
 All reinforcement shall be of tested quality high yield strength deformed bars
conforming to IS 1786 shall be used as reinforcement steel.
 The lap length of bars shall be equal to Ҟ (splice factor) X Dia of small bar. The value
of Ҟ shall be as per following table:-
 Grade of the value of the splice factor concrete for column for other
M-20 40 50
M-25 35 45
M30 35 45
M-35 30 40
M-40 30 40
Lapping of bars shall be suited staggered and in no case more than 50% bars shall be lapped
at any section.
 The chair to support the raft foundation bars can be provided at the distance of the one
meter.
 The length of the anchorage should be 300mm
 The reinforcement should be provided as per the detailed drawing specification.
 The bars of the reinforcement should straight not be in the zigzag manner.
 Check the slump of the concrete when concrete is placing.
 Clean cover to the main reinforcement shall be as follows:
Structural element Top Bottom Sides
1. Footing/raft 50 50 50
2. Column dimension - - 25
up to 230
3. Column dimension - - 40
up above 230
4. R.C.C. wall up to 25 25 25
150 thk.
5. R.C.C. wall above 40 40 40
150 thk.
6. Beams 25 25 25
7. Lintel up to 200 15 15 15
depth
8. Lintel above 200 25 25 40
depth
9. Slab & chhaja 15 15 25

4. Plastering
 The joints of the brick work shall raked out to a depth of 12 mm and the surface of the
wall washed and clean and kept wet for the two days before plastering. The material
of mortar should be of standard specification.
 The thickness of the plastering shall be of 12mm to ensure uniform thickness of
plaster; patches of 15 cm shall be applied first at about 2 m apart to act as guide. First
mortar shall be dashed and pressed over the surface and then brought to a true smooth
and uniform surface by means of float and trowel.
 Wall plastering shall be started from top and worked down towards floor,. Ceiling
plastering shall be completed before starting of wall plaster.
 All corner and edge shall be rounded. The plastered surface shall be kept wet for 10
days the surface should be protected from rain, sun, frost, etc.
 For wall plastering 1:5 cement mortar and for ceiling plastering 1:3 cement mortar
with coarse sand is used.
5. 25 cm Cement Concrete floor
 The cement concrete shall be of proportion 1:2:4 cement shall be fresh Portland
cement of standard specification. The coarse aggregate shall be hard and tough of 3
cm gauge, well graded and free from dust, dirt, etc. the sand shall be coarse of 5 mm
maximum size and down, well graded, clean and free from dust, direct and organic
matters.

 The floor shall be leveled and divided into panels or bays of maximums size or 1.2m
x1.2m and the sides of the panels shall be bounded with teak wood battens 2. cm thick
and 5 cm wide or flat iron of same thickness and fixed with weak mortar, or with nails
or hooks. Required camber or slope should be given in floor for draining wash water.
 Mixing of concrete shall be down by measuring with boxes to have the required
proportion as specified. First cement and sand mixed dry and the dry mix of
cement and sand mixed with ballast dry, and the mixed by adding water slowly
and gradually to the required quantity, and mixed thoroughly to have a uniform
plastic mix.
 Base – In ground floor the c.c. floor shall be laid on a 7.5cm base of weak cement
concrete as per standard specifications.

6. White washing

Fresh white lime slaked at site of work should be mixed with sufficient water to make a thin
cream. It shall then be screened through a coarse cloth, and gum in proportion of 100 gms of
gums to 16 liters of wash shall be added.
The surface should be dry and thoroughly cleaned from dust and dirt. The wash shall be
applied with Moonj or jute brush, vertically and horizontally. And the wash kept stirred in
container while using. Two or three coats shall be applied as specified, and each coat shall
perfectly dry before the succeeding coat is applied over it. Dry before the succeeding coat
shall be applied as specified, and each coat shall be perfectly dry before the succeeding coat
is applied as specified, and each coat shall be perfectly dry before the succeeding coat is
applied over it. After finishing the surface shall be of uniform color. In old surface, the
surface should be cleaned and repaired with cement mortar where necessary and allowed to
dry before white wash is applied.
CONCLUSION

The main aim of studies within this project was to investigate how a structure is constructed
within its desired properties. We get knowledge about the basic & advanced techniques of
building construction as well as saw the challenges which a civil engineer have to face during
construction i.e. labour problems, cost management, environmental challenges etc. We
cleared our many doubts regarding building construction. We had seen dewatering system at
project site for construction which is not used at our state anymore, so it was a new thing for
us..
Although are subjects more important for technicians, in the project we have been
Studied some mechanic or electro-mechanic machinery such as the ready mix plant because
basic knowledge about their working is important for an engineer but also because was the
opportunity to see and understand them.
Overhaul it must be said that the construction methods and quality control on a highway
Project needs a very good coordination and large quantities of man power, equipment and
funds.
During the period of one & half month all the company staff helped us a lot to provide all the
information about any query. So we are grateful to all the staff of JAYPEE KASSIA , as well
as we are so thankful to our Civil Engineering for their kind support.

You might also like