You are on page 1of 18

RATE ANALYSIS

Item Unit
Details 1. Filling in plinth with brought out murum Quantity 10 cum
Assumed
Item No. Item Head Calculations Quantity Unit Rate/Unit Amount
A. Material

1 Murum 10 cum + 2cum 12 cum 425.00 5100.00


(Add 20% compaction factor)

Total of A 5100.00

B. Wastage @ 5% 255.00

C. Plant, Machinery &


Equipments @ 1% 51.00
D. Water & Electricity
incl. curing @ 2% 102.00
E. Labour charge 10 cum 375.00 3750.00

Total of A 9258.00
F. Add for Profit &
Overheads @ 15% 1388.70
G. TOTAL AMOUNT INCL. P & O Rate for 10 cum 10646.70
Rate for 1 cum 1064.67
RATE ANALYSIS
Item Unit
Details 2. Rubble soling 230mm thick with murum blindage coarse Quantity 10 cum
Assumed
Item No. Item Head Calculations Quantity Unit Rate/Unit Amount
A. Material

1 Rubble 10 cum + 1 cum 11 cum 530.00 5830.00


(Add 10% dressing wastage)
2 Murum (for blindage 50mm loose murum layered
coarse) over rubble soling for filling the
same into soling gaps
50mm/230mm = 20%
10 cum x 20% = 2 cum 2 cum 425.00 850.00

Total of A 6680.00

B. Wastage @ 5% 334.00

C. Plant, Machinery &


Equipments @ 1% 66.80
D. Water & Electricity
incl. curing @ 2% 133.60
E. Labour charge 10 cum 530.00 5300.00

Total of A 12514.40
F. Add for Profit &
Overheads @ 15% 1877.16
G. TOTAL AMOUNT INCL. P & O Rate for 10 cum 14391.56
Rate for 1 cum 1439.16
RATE ANALYSIS
Item Unit
Details 3. PCC at Plinth top in concrete mix 1:3:6 Quantity 10 cum
Assumed
Item No. Item Head Calculations Quantity Unit Rate/Unit Amount
A. Material
Ratio between Wet mix to Dry
mix = 1cum : 1.52cum
For 10 cum:15.20cum
15.20/(Sum of Proportion)
15.20cum/(1+3+6)
Therefore, Value for 0ne (1) is
1.52

1 Cement 1.52 cum x 30 46 bag 280.00 12768.00


(1cum = 30 bags)
2 Crush Sand 1.52 cum x 3 4.56 cum 990.00 4514.40
(Fine aggregate)
3 Metal 1.52 cum x 6 9.12 cum 880.00 8025.60
(Coarse aggregate)
Total of A 25308.00

B. Wastage @ 5% 1265.40

C. Plant, Machinery &


Equipments @ 1%
253.08
D. Water & Electricity
incl. curing @ 2% 506.16
E. Labour charge 10 cum 1200 12000.00

Total of A
to E 39332.64
F. Add for Profit &
Overheads @ 15% 5899.90
G. TOTAL AMOUNT INCL. P & O Rate for 10 cum 45232.54
Rate for 1 cum 4523.25
RATE ANALYSIS
Item Unit
Details 4. PCC at foundation base in concrete mix 1:2:4 Quantity 10 cum
Assumed
Item No. Item Head Calculations Quantity Unit Rate/Unit Amount
A. Material
Ratio between Wet mix to Dry
mix = 1cum : 1.52cum
For 10 cum:15.20cum
15.20/(Sum of Proportion)
Therefore, 15.20cum/(1+2+4)
Therefore, Value for 0ne (1) is
2.17

1 Cement 2.17 cum x 30 65 bag 280.00 18228.00


(1cum = 30 bags)
2 Crush Sand 2.17 cum x 2 4.34 cum 990.00 4296.60
(Fine aggregate)
3 Metal 2.17 cum x 4 8.68 cum 880.00 7638.40
(Coarse aggregate)
Total of A 30163.00

B. Wastage @ 5% 1508.15

C. Plant, Machinery &


Equipments @ 1%
301.63
D. Water & Electricity
incl. curing @ 2% 603.26
E. Labour charge 10 cum 1500 15000.00

Total of A
to E 47576.04
F. Add for Profit &
Overheads @ 15% 7136.41
G. TOTAL AMOUNT INCL. P & O Rate for 10 cum 54712.45
Rate for 1 cum 5471.24
RATE ANALYSIS
Item Unit
Details 5. RCC column/beam/slab in concrete mix 1:1.5:3 Quantity 10 cum
Assumed
Item No. Item Head Calculations Quantity Unit Rate/Unit Amount
A. Material
Ratio between Wet mix to Dry
mix = 1cum : 1.52cum
For 10 cum:15.20cum
15.20/(Sum of Proportion)

Therefore, 15.20cum/(1+1.5+3)
Therefore, Value for 0ne (1) is
2.76

1 Cement 2.76 cum x 30 83 bag 280.00 23184.00


(1cum = 30 bags)
2 Crush Sand 2.76 cum x 1.5 4.14 cum 990.00 4098.60
(Fine aggregate)
3 Metal 2.76 cum x 3 8.28 cum 880.00 7286.40
(Coarse aggregate)
Total of A 34569.00

B. Wastage @ 5% 1728.45

C. Plant, Machinery &


Equipments @ 1%
345.69
D. Water & Electricity
incl. curing @ 2% 691.38
E. Labour charge 10 cum 3200 32000.00

Total of A
to E 69334.52
F. Add for Profit &
Overheads @ 15% 10400.18
G. TOTAL AMOUNT INCL. P & O Rate for 10 cum 79734.70
Rate for 1 cum 7973.47
RATE ANALYSIS
Item Unit
Details 6. RCC footing/raft in concrete mix 1:1:2 Quantity 10 cum
Assumed
Item No. Item Head Calculations Quantity Unit Rate/Unit Amount
A. Material
Ratio between Wet mix to Dry
mix = 1cum : 1.52cum
For 10 cum:15.20cum
15.20/(Sum of Proportion)
Therefore, 15.20cum/(1+1+2)
Therefore, Value for 0ne (1) is
3.80

1 Cement 3.80 cum x 30 114 bag 280.00 31920.00


(1cum = 30 bags)
2 Crush Sand 3.80 cum x 1 3.8 cum 990.00 3762.00
(Fine aggregate)
3 Metal 3.80 cum x 2 7.6 cum 880.00 6688.00
(Coarse aggregate)
Total of A 42370.00

B. Wastage @ 5% 2118.50

C. Plant, Machinery &


Equipments @ 1%
423.70
D. Water & Electricity
incl. curing @ 2% 847.40
E. Labour charge 10 cum 2700 27000.00

Total of A
to E 72759.60
F. Add for Profit &
Overheads @ 15% 10913.94
G. TOTAL AMOUNT INCL. P & O Rate for 10 cum 83673.54
Rate for 1 cum 8367.35
RATE ANALYSIS
Item Unit
Details 7. Reinforcement steel work in RCC work Quantity 1000 kg
Assumed
Item No. Item Head Calculations Quantity Unit Rate/Unit Amount
A. Material

1
Reinforcement steel 1000 kg 44.00 44000.00

2 Binding wire (10kg per 1000kg) 10 kg 65.00 650.00

Total of A 44650.00

B. Wastage @ 5% 2232.50

C. Plant, Machinery &


Equipments @ 1%
446.50
D. Water & Electricity
incl. curing @ 2% 0.00
E. Labour charge 1000 kg 6.00 6000.00

Total of A
to E 53329.00
F. Add for Profit &
Overheads @ 15% 7999.35
G. TOTAL AMOUNT INCL. P & O Rate for 1000kg 61328.35
Rate for 1kg 61.33
RATE ANALYSIS
8. BB masonary 230mm thick in CM 1:5
Material Factor calculations
a) Brick
Brick size 225mm x 110mm x 65mm
Sample 1m x 1m x a) No. brick in one layer with 10mm mortor joint = 1m/0.235 = 4.25nos x 2 lines
0.23m = 0.23 cum >> = 8.50 nos
b) No. layers vertically with 10mm mortor joint = 1m/0.075 = 13.35 nos
No of bricks per 0.23 8.50 no x 13.35 no = 113.45 no
cum >>
No. of bricks/cum 113.45 no / 0.23 cum = 493 nos say 500 nos per cum
b) Mortor
Qty. of mortor/cum Qty. of whole masonary - Qty. of bricks = qty. of mortor
1 cum - (493 no x 0.225 x 0.11 x 0.065) = 0.21cum
Dry vol of mortor >> Wet volume + 20% Bulkage factor
0.21 cum + 0.04 cum = 0.25 cum
Item Unit
Details 8. BB masonary 230mm thick in CM 1:5 Quantity 10 cum
Assumed
Item No. Item Head Calculations Quantity Unit Rate/Unit Amount
A Material
1 Bricks 10 cum x 500 no 5000 No 7.00 35000.00
2 Mortor For 1 cum = 0.25 cum
for 10 cum = 2.50 cum
Therefore, 2.50/(Sum of proportion)
Therefore, 2.50 cum/(1+5)
Therefore, Value for One (1) is
0.42
a Cement 0.42 cum x 30 13 bag 280.00 3528.00
(1cum = 30 bags)
b Crush Sand 0.42 cum x 5 2.1 cum 990.00 2079.00
(Fine aggregate)
Total of A 40607.00

B. Wastage @ 5% 2030.35

C. Scaffolding @ 1% 406.07
D. Water & Electricity
incl. curing @ 2% 812.14
E. Labour charge 10 cum 880.00 8800.00

Total of A
to E 52655.56
F. Add for Profit &
Overheads @ 15% 7898.33
G. TOTAL AMOUNT INCL. P & O Rate for 10 cum 60553.89
Rate for 1 cum 6055.39
RATE ANALYSIS
9. Half thick (115mm thick) BB masonary in CM 1:4 excluding RCC band
Material Factor calculations
a) Brick
Brick size 225mm x 110mm x 65mm
Sample 1m x 1m a) No. brick in one layer with 10mm mortor joint = 1m/0.235 = 4.25nos
b) No. layers vertically with 10mm mortor joint = 1m/0.075 = 13.35 nos
Bricks per 1 Sq.m >> 4.25 no x 13.35 no = 57 no say 60 nos per Sq.m

b) Mortor
Qty. of mortor/cum Qty. of whole masonary - Qty. of bricks = Qty. of mortor
0.11 cum - (57 no x 0.225 x 0.11 x 0.065) = 0.018cum
Dry vol of mortor >> Wet volume + 20% Bulkage factor
0.018 cum + 0.0036 cum = 0.0216 cum per Sq.m
Say 0.022 cum per Sq. m
Item Unit
Details 9. Half thick (115mm thick) BB masonary in CM 1:4 excluding RCC band Quantity 100 Sqm
Assumed
Item No. Item Head Calculations Quantity Unit Rate/Unit Amount
A Material
1 Bricks 100 Sqm x 60 no 6000 No 7.00 42000.00
2 Mortor For 1 Sqm = 0.022 cum
for 100 Sqm = 2.20 cum
Therefore, 2.20/(Sum of proportion)
Therefore, 2.20 cum/(1+4)
Therefore, Value for One (1) is
0.44
a Cement 0.44 cum x 30 13 bag 280.00 3696.00
(1cum = 30 bags)
b Crush Sand 0.44 cum x 4 1.76 cum 990.00 1742.40
(Fine aggregate)
Total of A 47438.40

B. Wastage @ 5% 2371.92

C. Scaffolding @ 1% 474.38
D. Water & Electricity
incl. curing @ 2% 948.77
E. Labour charge 100 Sqm 160.00 16000.00

Total of A
to E 67233.47
F. Add for Profit &
Overheads @ 15% 10085.02
G. TOTAL AMOUNT INCL. P & O Rate for 100 Sqm 77318.49
Rate for 1 Sqm 773.18
RATE ANALYSIS
10. Neeru finish (Sanala) plaster 8mm to 10mm thick for ceiling in CM 1:3
Material Factor calculations

Mortor
Qty. of wet mortor 1m x 1m x 0.01m = 0.01cum
Dry vol of mortor >>
Wet volume + 20% Bulkage factor
0.01 cum + 0.002 cum = 0.012
cum per Sq.m

Item Unit
Details 10. Neeru finish (Sanala) plaster 8mm to 10mm thick for ceiling in CM 1:3 Quantity 100 Sqm
Assumed
Item No. Item Head Calculations Quantity Unit Rate/Unit Amount
A Material
Mortor For 1 Sqm = 0.012 cum
for 100 Sqm = 1.20 cum
Therefore, 1.20/(Sum of proportion)
Therefore, 1.20 cum/(1+3)
Therefore, Value for One (1) is
0.3

a Cement 0.3 cum x 30 9 bag 280.00 2520.00


(1cum = 30 bags)
b River Sand (0.3 cum x 3) + (0.225 cum)
Added 25% screening wastage 1.125 cum 2650.00 2981.25
(Fine aggregate)
Add for Sanala 100 sqm x 0.1 bag per Sqm 10 bag 130.00 1300.00

Total of A 6801.25

B. Wastage @ 5% 340.06

C. Scaffolding @ 1% 68.01
D. Water & Electricity
incl. curing @ 2% 136.03
E. Labour charge 100 Sqm 200.00 20000.00

Total of A
to E 27345.35
F. Add for Profit &
Overheads @ 15% 4101.80
G. TOTAL AMOUNT INCL. P & O Rate for 100 Sqm 31447.15
Rate for 1 Sqm 314.47
RATE ANALYSIS
11. Neeru finish (Sanala) plaster 12mm to 15mm thick for wall in CM 1:4
Material Factor calculations

Mortor
Qty. of wet mortor 1m x 1m x 0.015m = 0.015cum
Dry vol of mortor >>
Wet volume + 20% Bulkage factor
0.015 cum + 0.003 cum = 0.018
cum per Sq.m

Item Unit
Details 11. Neeru finish (Sanala) plaster 12mm to 15mm thick for wall in CM 1:4 Quantity 100 Sqm
Assumed
Item No. Item Head Calculations Quantity Unit Rate/Unit Amount
A Material
Mortor For 1 Sqm = 0.018 cum
for 100 Sqm = 1.80 cum
Therefore, 1.80/(Sum of proportion)
Therefore, 1.80 cum/(1+4)
Therefore, Value for One (1) is
0.36

a Cement 0.36 cum x 30 11 bag 280.00 3024.00


(1cum = 30 bags)
b River Sand (0.36 cum x 4) + (0.36 cum)
Added 25% screening wastage 1.8 cum 2650.00 4770.00
(Fine aggregate)
Add for Sanala 100 sqm x 0.1 bag per Sqm 10 bag 130.00 1300.00

Total of A 9094.00

B. Wastage @ 5% 454.70

C. Scaffolding @ 1% 90.94
D. Water & Electricity
incl. curing @ 2% 181.88
E. Labour charge 100 Sqm 220.00 22000.00

Total of A
to E 31821.52
F. Add for Profit &
Overheads @ 15% 4773.23
G. TOTAL AMOUNT INCL. P & O Rate for 100 Sqm 36594.75
Rate for 1 Sqm 365.95
RATE ANALYSIS
12. Sandfaced double coat plaster 18mm to 20mm thick for wall in CM 1:4
Material Factor calculations

Mortor
Qty. of wet mortor 1m x 1m x 0.020m = 0.020cum
Dry vol of mortor >>
Wet volume + 20% Bulkage factor
0.020 cum + 0.004 cum = 0.024
cum per Sq.m

Item Unit
Details 12. Sandfaced double coat plaster 18mm to 20mm thick for wall in CM 1:4 Quantity 100 Sqm
Assumed
Item No. Item Head Calculations Quantity Unit Rate/Unit Amount
A. Material
Mortor For 1 Sqm = 0.024 cum
for 100 Sqm = 2.40 cum
Therefore, 2.40/(Sum of proportion)
Therefore, 2.40 cum/(1+4)
Therefore, Value for One (1) is
0.48

a Cement 0.48 cum x 30 14 bag 280.00 4032.00


(1cum = 30 bags)
b River Sand (0.48 cum x 4) + (0.48 cum)
Added 25% screening wastage
2.4 cum 2650.00 6360.00
(Fine aggregate)

Total of A 10392.00

B. Wastage @ 5% 519.60

C. Scaffolding @ 1% 103.92
D. Water & Electricity
incl. curing @ 2% 207.84
E. Labour charge 100 Sqm 270.00 27000.00

Total of A
to E 38223.36
F. Add for Profit &
Overheads @ 15% 5733.50
G. TOTAL AMOUNT INCL. P & O Rate for 100 Sqm 43956.86
Rate for 1 Sqm 439.57
RATE ANALYSIS
13. Kota stone flooring (Hand dressed/machine cut) on 50mm thick sub base in CM 1:5 with Cement Paste
backing
Material Factor calculations
Mortor
Qty. of wet mortor 1m x 1m x 0.050m = 0.050cum
Dry vol of mortor >>
Wet volume + 20% Bulkage factor
0.050 cum + 0.010 cum = 0.060
cum per Sq.m
Item Unit
13. Kota stone flooring (Hand dressed/machine cut) on 50mm thick sub
Details Quantity 100 Sqm
base in CM 1:5 with Cement Paste backing
Assumed
Item No. Item Head Calculations Quantity Unit Rate/Unit Amount
A Material
1 Kota stone Considering 20% hand dressing /
cutting wastage
100 Sqm + 20 Sqm 120 Sqm 280.00 33600.00
2 Mortor For 1 Sqm = 0.060 cum
for 100 Sqm = 6.00 cum
Therefore, 6.00/(Sum of proportion)
Therefore, 6.00 cum/(1+5)
Therefore, Value for One (1) is
1
a Cement 1 cum x 30 30 bag 280.00 8400.00
(1cum = 30 bags)
b Crush Sand 1 cum x 5 5 cum 990.00 4950.00
(Fine aggregate)
c Add extra cement for
backing paste 0.1 bag per Sqm x 100 sqm 10 bag 280.00 2800.00

Total of A 49750.00

B. Wastage @ 5% 2487.50
C. Plant, Machinery &
Equipments @ 1%
497.50
D. Water & Electricity
incl. curing @ 2% 995.00
E. Labour charge (Incl Dressing & fixing) 100 Sqm 380.00 38000.00

Total of A
to E 91730.00
F. Add for Profit &
Overheads @ 15% 13759.50
G. TOTAL AMOUNT INCL. P & O Rate for 100 Sqm 105489.50
Rate for 1 Sqm 1054.90
RATE ANALYSIS
14. Vitrified tile flooring 35mm thick sub base in CM 1:5 with Cement slurry
Material Factor calculations
Mortor
Qty. of wet mortor 1m x 1m x 0.050m = 0.035cum
Dry vol of mortor >>
Wet volume + 20% Bulkage factor
0.0350 cum + 0.007 cum = 0.042
cum per Sq.m
Item Unit
Details 14. Vitrified tile flooring 35mm thick sub base in CM 1:5 with Cement slurry Quantity 100 Sqm
Assumed
Item No. Item Head Calculations Quantity Unit Rate/Unit Amount
A Material
1 Vitrified tile 100 Sqm 550.00 55000.00

2 Mortor For 1 Sqm = 0.042 cum


for 100 Sqm = 4.20 cum
Therefore, 4.20/(Sum of proportion)
Therefore, 4.20 cum/(1+5)
Therefore, Value for One (1) is
0.7
a Cement 0.7 cum x 30 21 bag 280.00 5880.00
(1cum = 30 bags)
b Crush Sand 0.7 cum x 5 3.5 cum 990.00 3465.00
(Fine aggregate)
c Add extra cement for
backing paste 0.1 bag per Sqm x 100 sqm 10 bag 280.00 2800.00

Total of A 67145.00

B. Wastage @ 5% 3357.25
C. Plant, Machinery &
Equipments @ 1%
671.45
D. Water & Electricity
incl. curing @ 2% 1342.90
E. Labour charge 100 Sqm 280.00 28000.00

Total of A
to E 100516.60
F. Add for Profit &
Overheads @ 15% 15077.49
G. TOTAL AMOUNT INCL. P & O Rate for 100 Sqm 115594.09
Rate for 1 Sqm 1155.94
15. Vitrified tile for wall (Dado) 15mm thick backing CM 1:2
Material Factor calculations
Mortor
Qty. of wet mortor 1m x 1m x 0.015m = 0.015cum
Dry vol of mortor >>
Wet volume + 20% Bulkage factor
0.0150 cum + 0.003 cum = 0.018
cum per Sq.m

Item Unit
Details 15. Vitrified tile for wall (Dado) 15mm thick backing CM 1:2 Quantity 100 Sqm
Assumed
Item No. Item Head Calculations Quantity Unit Rate/Unit Amount
A Material
1 Vitrified tile 100 Sqm 450.00 45000.00

2 Mortor For 1 Sqm = 0.018 cum


for 100 Sqm = 1.80 cum
Therefore, 1.80/(Sum of proportion)
Therefore, 1.80 cum/(1+2)
Therefore, Value for One (1) is
0.6
a Cement 0.6 cum x 30 18 bag 280.00 5040.00
(1cum = 30 bags)
b Screened Sand (0.6 cum x 2 ) + (0.30 cum) 1.5 cum 2650.00 3975.00
(Fine aggregate) add 25% screening wastage

Total of A 54015.00

B. Wastage @ 5% 2700.75

C. Plant, Machinery &


Equipments @ 1%
540.15
D. Water & Electricity
incl. curing @ 2% 1080.30
E. Labour charge 100 Sqm 280.00 28000.00

Total of A
to E 86336.20
F. Add for Profit &
Overheads @ 15% 12950.43
G. TOTAL AMOUNT INCL. P & O Rate for 100 Sqm 99286.63
Rate for 1 Sqm 992.87
RATE ANALYSIS
16. Brick bat waterproof treatment 100mm thick in CM 1:3 with smooth surface finish
Material Factor calculations
a) Brick
Brick size 225mm x 110mm x 65mm
Sample 1m x 1m a) Bricks in one direction with 15mm mortor joint = 1m/0.24 = 4.17nos
b) Bricks in another direction with 15mm mortor joint = 1m/0.125 = 8 nos
Bricks per 1 Sq.m >> 4.17 no x 8 no = 35 no per Sq.m

b) Mortor
Qty. of mortor/cum Qty. of whole mass - Qty. of bricks = Qty. of mortor
0.10 cum - (35 no x 0.225 x 0.11 x 0.065) = 0.044cum
Dry vol of mortor >> Wet volume + 20% Bulkage factor
0.044 cum + 0.009 cum = 0.053 cum per Sq.m
Item Unit
16. Brick bat waterproof treatment 100mm thick in CM 1:4 with smooth
Details Quantity 100 Sqm
surface finish
Assumed
Item No. Item Head Calculations Quantity Unit Rate/Unit Amount
A Material
1 Bricks 100 Sqm x 35 no 3500 No 7.00 24500.00

2 Mortor For 1 Sqm = 0.053 cum


for 100 Sqm = 5.30 cum
Therefore, 5.30/(Sum of proportion)
Therefore, 5.30 cum/(1+3)
Therefore, Value for One (1) is
1.06
a Cement 1.32 cum x 30 40 bag 280.00 11088.00
(1cum = 30 bags)
b Crush Sand 1.32 cum x 3 3.96 cum 990.00 3920.40
(Fine aggregate)
Total of A 39508.40

B. Wastage @ 5% 1975.42

C. Scaffolding @ 1% 395.08
D. Water & Electricity
incl. curing @ 2% 790.17
E. Labour charge 100 Sqm 280.00 28000.00
Total of A
to E 70669.07
F. Add for Profit &
Overheads @ 15% 10600.36
G. TOTAL AMOUNT INCL. P & O Rate for 100 Sqm 81269.43
Rate for 1 Sqm 812.69
SUMMARISED WORKING FACTORS FOR DIFFERENT ITEMS
Item No Item Head Factor for calculation Qty per Comments
Unit

1 Murum filling Add 20% in basic quantity 1 cum Addition for compaction factor
Therefore, 1 cum + 0.2 cum 1.2 cum

2 Rubble Soling 1 cum


a) Rubble Add 10% in basic quantity Addition for Dressing wastage
Therefore, 1 cum + 0.1 cum 1.1 cum
b) Murum Add 20% quantity against 0.2 cum 50mm layer is 20% of 230mm
blindage course soling layer.

3 All concrete items 1 cum


PCC & RCC
a) Cement 1 cum = 30 bags Conversion factor
b) Concrete Add 52% in basic quantity 1.52 Considering 52% Bulkage factor
1 cum of Wet mix = 1.52 cum of
Dry mix
c) Working out
ingradients 1.52 cum/ (Sum of Proportion)

4 230mm thick Brick 1 cum


masonary
a) Bricks 500 nos per cum
b) Mortor Dry mortor = 0.25 cum/ 1 cum
1 cum of wet mix = 1.20 cum of Considering 20% Bulkage factor
dry mix

5 115mm thick Brick 1 sqm


masonary
a) Bricks 60 nos per Sqm
b) Mortor Dry mortor = 0.022 cum/ 1 Sqm Considering 20% Bulkage factor

6 Neeru plaster for 1 Sqm


ceiling 8 to 10mm
thick
a) Mortor Dry mortor = 0.012 cum/ 1 Sqm Considering 20% Bulkage factor
Add 25% more for sand only Screening wastage
b) Neeru 0.1 bag per Sqm

7 Neeru plaster for 1 sqm


wall 12 to 15mm
thick
a) Mortor Dry mortor = 0.018 cum/ 1 Sqm Considering 20% Bulkage factor
Add 25% more for sand only Screening wastage
b) Neeru 0.1 bag per Sqm
Item No Item Head Factor for calculation Qty per Comments
Unit

8 Sandfaced double 1 Sqm


coat plaster to wall
18 to 20mm thick
a) Mortor Dry mortor = 0.024 cum/ 1 Sqm Considering 20% Bulkage factor
Add 25% more for sand only Screening wastage

9 Kota stone flooring 1 Sqm


on 50mm thick sub
base
a) Kota stone Add 20% on basic quantity 20% for Dressing wastage
Therefore, 1 Sqm + 0.2 Sqm
b) Mortor Dry mortor = 0.06 cum/ 1 Sqm Considering 20% Bulkage factor
c) Extra Cement 0.1 bag per 1 Sqm For cement paste backing

10 Vitrified flooring 1 Sqm


on 35mm thick sub
base
a) Vitrified tile No any addition
b) Mortor Dry mortor = 0.042 cum/ 1 Sqm Considering 20% Bulkage factor
c) Extra Cement 0.1 bag per 1 Sqm For cement slurry backing

11 Vitrified wall tiles 1 sqm


on 15mm thick
backing mortor
a) Vitrified tile No any addition
b) Mortor Dry mortor = 0.018 cum/ 1 Sqm Considering 20% Bulkage factor

12 100mm thick Brick 1 sqm


bat waterproof
treatment
a) Bricks 35 nos per Sqm
b) Mortor Dry mortor = 0.053 cum/ 1 Sqm Considering 20% Bulkage factor

You might also like