I PEMBONGKARAN, PENGADAAN MATERIAL DAN INSTALASI HEAT EXCHANGER TOURNAIRE MACHINE LINE DESTILASI UNIT V 81.49%
A. PEMBONGKARAN HEAT EXCHANGER MACHINE TOURNAIRE LINE DESTILASI UNIT V 1 LOT 26.25%
B. PENGADAAN MATERIAL DAN INSTALASI HEAT EXCHANGER MACHINE TOURNAIRE LINE DESTILASI UNIT V 1 LOT 55.24%
PENGADAAN MATERIAL, FABRIKASI DAN INSTALASI LINE PIPING STEAM CONDENSATE, LINE PIPING FRESH WATER, LINE PIPING
II 18.51%
HOT WATER DAN LINE PIPING AIR COMPRESSOR TO CUBICLE MC. ADMOIST UNIT V
A PENGADAAN DAN PEMASANGAN LINE PIPING STEAM CONDENSATE SUPPLY SERVICE CUBICLE 1 LOT 1.77%
B PENGADAAN DAN PEMASANGAN LINE PIPING AIR COMPRESSOR SUPPLY SERVICE CUBICLE ADMOIST 1 LOT 0.13%
C PENGADAAN DAN PEMASANGAN LINE PIPING FRESH WATER SUPPLY SERVICE CUBICLE 1 LOT 0.58%
D PENGADAAN DAN PEMASANGAN LINE. PIPING HOT WATER SUPPLY SERVICE CUBICLE 1 LOT 15.03%
E PENGADAAN, FABRIKASI, PAINTING DAN INSTALASI SUPPORT UNP 80 X 45 X 5MM 1 LOT 1.01%
SUB TOTAL
100.00%
DIBULATKAN
1 PROGRESS RENCANA 0.00%
2 PROGRESS RENCANA KUMULATIF 0.00%
3 PROGRESS REALISASI
4 PROGRESS REALISASI KUMULATIF