Professional Documents
Culture Documents
HYD 32 Page 2 of 5
STG Sets REV.01 , DT 30 11 10
1.0 GENERAL:
4.1 Place the base plate under gear box and level it using shims and
tighten the foundation bolts
4.2 Place the gear box on the bed plate and blue match the surface with
respect to the Gear box bottom.
4.3 Place the gear box on bed plate keeping approximately 2 mm shims.
(the purpose of keeping shims at initial stages is to have provision of
alignment adjustment in future due to shrinkage)
GENERATOR ERECTION
4.9 Place bed plates under generator on grouted pecker plates and level.
4.10 Place generator on bed plates and assemble with holding down bolts.
4.11 Keep min 2 mm shims for future adjustment.
4.12 Check and adjust orientation as per foundation marking and tighten
the foundation bolts.
4.13 Lift the generator and weld pieces of foundation bed plate together.
4.14 Place generator back on the bed plate.
4.15 Assemble the generator rotor as per the details in rotor insertion and
withdrawal drawing.
ALIGNMENT
5.1 Tack weld the pecker plates (if the pecker plate are 9mm and above).
5.2 Fill the foundation holes with dry mixture of cement and sand (1:15).
5.3 Grout the machine with non shrink cement (Conbextra GP 2 or
equivalent).
5.4 Allow the curing of cement for5 7 days depending on the
specification provided by the cement supplier.
Sr No. Activity
1. Foundation checks with respect to civil drawing.
2. Pecker plate and bed plate leveling, grouting and matching
3 Turbine front bearing pedestal positioning
4 Exhaust hood positioning.
5 Placement of Rear bearing housing in exhaust hood and centering.
6 Bearing housing center line checking.
7 Main casing placement on bearing pedestals.
8 Checking of Parting plane level and surface level.
9 Assembly of vertical joint of exhaust hood and casing
10 Placement of Top exhaust hood and casing.
11 Vertical joint of exhaust hood casing top half connection
12 Top casing removal and placement of bearings.
13 Rotor placement and centering checks.
14 Adjustment of bearing center lines by placing rotor in reference position.
15 Assembly of radial and axial keys of pedestal to casing
16 Take out the turbine rotor
17 Placement of bottom internals casing
18 Rotor placement and checking of axial and radial clearance
19 Assembly of top internal casings
20 Cleaning of internals after assembly, torque tightening of fasteners
21 Placement of top spherical washers. Maintain parting plane level as per design
values
22 Placement of top outer casing
23 Parting plane bolt torque tightening
24 Casing outer centering
25 Placement of thrust bearing and clearance checks.
26 Front and rear journal bearing clearance checking
27 Placement of oil glands, radial and axial clearance checking
28 Gear box leveling and maintaining the center distance
29 Turbine to gear box alignment
Notes:
1. The above listed activities are to be carried for installation and assembly of turbine at
site.
2. Alignment between Turbine Gear Box Generator has to be rechecked after grouting
is set.
3. Generator assembly to be carried out at site.