BHEL Erection Procedure for ESP:TG& TC:202 01

HYD 32 Page 2 of 5
STG Sets REV.01 , DT 30 11 10

1.0 GENERAL:

The erection of TG sets involves the following activities:


1. Checking of foundation
2. Pecker plate grouting
3. Placement of equipment on the pecker plates
4. Leveling and alignment
5. Grouting of equipment

2.0 CHECKING OF FOUNDATION

Foundation checking involves

2.1 Dimensional checking of foundation as per drawing.


2.2 Certification from civil engineer concerned.
2.3 Marking of center lines of turbine, gear box and generator.
2.4 Position of foundation bolts pockets with respect to the center line.
2.5 Verticality of the pockets to be ensured.

3.0 PECKER PLATE GROUTING

3.1 Blue matching of pecker plates is to be done with respect to surface


plate. (70 to 80%).
3.2 Chip the foundation top to make it rough for better grouting effect.
3.3 Arrange the plates on the foundation as per pecker plated
arrangement drawing.
3.4 Transfer the elevation bench mark on the turbine floor.
3.5 Place the packer according to the required level allowance ±1.0 mm.
3.6 Individual plates can the leveled with the help of master level.
3.7 Make shuttering around the leveled plates and grout the plates with
non shrink cement.
3.8 The grouting thickness should be 50mm or as per drawing. Avoid
having excess thickness as it may result in cracking on the surfaces.
3.9 Have a record of make and batch number of the cement.

4.0 LEVELLIING AND ALIGNMENT

GEAR BOX (IF APPLICABLE)

4.1 Place the base plate under gear box and level it using shims and
tighten the foundation bolts

ISSUED BY: EXTERNAL SERVICES DEPARTMENT


BHEL Erection Procedure for ESP:TG& TC:202 01
HYD 32 Page 3 of 5
STG Sets REV.01 , DT 30 11 10

4.2 Place the gear box on the bed plate and blue match the surface with
respect to the Gear box bottom.
4.3 Place the gear box on bed plate keeping approximately 2 mm shims.
(the purpose of keeping shims at initial stages is to have provision of
alignment adjustment in future due to shrinkage)

TURBINE ERECTION (refer annex. 1 for details)

4.4 Place the assembled turbine on the grouted pecker plates


4.5 Keep the orientation as per the marked center on the foundation
4.6 Level the machine on pecker plate.
4.7 Tighten the foundation bolts.
4.8 Check centering of the turbine as per QC protocol.

GENERATOR ERECTION

4.9 Place bed plates under generator on grouted pecker plates and level.
4.10 Place generator on bed plates and assemble with holding down bolts.
4.11 Keep min 2 mm shims for future adjustment.
4.12 Check and adjust orientation as per foundation marking and tighten
the foundation bolts.
4.13 Lift the generator and weld pieces of foundation bed plate together.
4.14 Place generator back on the bed plate.
4.15 Assemble the generator rotor as per the details in rotor insertion and
withdrawal drawing.

ALIGNMENT

4.16 Complete alignment between turbine gear box generator. (refer


alignment protocol supplied by Engineering)
4.17 Maintain coupling distance between turbine gear box generator as
per the input and out put coupling drawing.

5.0 GROUTING OF SET

5.1 Tack weld the pecker plates (if the pecker plate are 9mm and above).
5.2 Fill the foundation holes with dry mixture of cement and sand (1:15).
5.3 Grout the machine with non shrink cement (Conbextra GP 2 or
equivalent).
5.4 Allow the curing of cement for5 7 days depending on the
specification provided by the cement supplier.

ISSUED BY: EXTERNAL SERVICES DEPARTMENT


BHEL Erection Procedure for ESP:TG& TC:202 01
HYD 32 Page 4 of 5
STG Sets REV.01 , DT 30 11 10

5.5 Tighten the foundation bolts and lock.


Annexure 1

Erection and assembly sequence for Steam Turbine.

Sr No. Activity
1. Foundation checks with respect to civil drawing.
2. Pecker plate and bed plate leveling, grouting and matching
3 Turbine front bearing pedestal positioning
4 Exhaust hood positioning.
5 Placement of Rear bearing housing in exhaust hood and centering.
6 Bearing housing center line checking.
7 Main casing placement on bearing pedestals.
8 Checking of Parting plane level and surface level.
9 Assembly of vertical joint of exhaust hood and casing
10 Placement of Top exhaust hood and casing.
11 Vertical joint of exhaust hood casing top half connection
12 Top casing removal and placement of bearings.
13 Rotor placement and centering checks.
14 Adjustment of bearing center lines by placing rotor in reference position.
15 Assembly of radial and axial keys of pedestal to casing
16 Take out the turbine rotor
17 Placement of bottom internals casing
18 Rotor placement and checking of axial and radial clearance
19 Assembly of top internal casings
20 Cleaning of internals after assembly, torque tightening of fasteners
21 Placement of top spherical washers. Maintain parting plane level as per design
values
22 Placement of top outer casing
23 Parting plane bolt torque tightening
24 Casing outer centering
25 Placement of thrust bearing and clearance checks.
26 Front and rear journal bearing clearance checking
27 Placement of oil glands, radial and axial clearance checking
28 Gear box leveling and maintaining the center distance
29 Turbine to gear box alignment

ISSUED BY: EXTERNAL SERVICES DEPARTMENT


BHEL Erection Procedure for ESP:TG& TC:202 01
HYD 32 Page 5 of 5
STG Sets REV.01 , DT 30 11 10

30 Placement of generator front bearing pedestal


31 Placement of generator stator
32 Generator rotor insertion
33 Rotor G value checking and bearing center line checking
34 Gear Box to generator alignment as per design values
35 Generator air gap adjustment
36 Exciter placement, air gap checking and dowelling
37 Bearing box up and clearance for grouting

Notes:
1. The above listed activities are to be carried for installation and assembly of turbine at
site.
2. Alignment between Turbine Gear Box – Generator has to be rechecked after grouting
is set.
3. Generator assembly to be carried out at site.

ISSUED BY: EXTERNAL SERVICES DEPARTMENT