Samsung EGCB

PD PD
SM SM
Weekly Meeting # 30 PCM Fichtner
DPM
Between EGCB and SCT on 16 July 18

Agenda Action by Due date


Safety
1 HSE Weekly Report
- Man-Hours & Lost Time Injury Rate Information (From 13 Sep 2017) * Date of Issue: 28 Jun 2018
Up to Last Week This Week Total Remarks
Man-Day 106,518 3,653 111,439 Daily average:614
Man-Hours 1,065,180 36,530 1,114,390
LTIR 0 0 0

- HSE Activities * Date of Issue: 28 Jun 2018

· Control high risk activities with PTW and JSA


· Site basic safety induction and special training for Samsung staff and sub-contractor
· Special inspection to site of STG area for the steel structure and Overhead crane
· Check condition of PPE and working clothes at site
· Regularly executing site walk down on every day
· Walk through with sub-con to avoid fall and fall object
Content This week Total Remarks
Hot work 34 503
Working at Height 12 371
Excavation 1 61
Lifting 7 113
PTW Confined space 1 74
Lock out Tag out - 92
Radiography 1 73
Pressure Test 10 79
Total 54 1,366
Induction 102/11 2,275/ 238
Special training 103/12 1,221 / 154 Attendees /
Training
Etc. 35/ 2 291/ 29 No. of Training
Total 240/ 25 3,787 /421
Near miss 4 132
Behavior Based Safety
28 677
Inspection / Observation
Observation S-CAR 6 106
Violation 2 62
Total 40 977
Subcontractor HSE Meeting 1 54
Meeting Security Meeting - 7
Total 1 61
Major Issues
1 Schedule of planned shutdown for rectification
Expected Required Required
Area Item
On-Site Period Outage Period
Aux TR. GT Aux TR Erection 30 Sep 2018 30 days
TR Replacement of CVT to IVT 30 Jul 2018 30 days Oct 2018
TR Additional CT Installation 30 Jul 2018 30 days
*Above schedule might be adjusted according to the site condition.

1
Agenda Action by Due date
2 ST Rectification Plan
Targeted date for the remedial actions [Tentative & For Information only]
SCT Cont.
- LP-IP rotor / diaphragms / packing head, casing, ring / oil deflectors / bearing
#1~3
1) ST LP Rotor Repair:
LSB reassembly & L-0 finger dovetail hole reaming and fitting : 17th June ~ 23rd July
2018, GE informed that special reamers is under manufacturing and expected by
20th July 2018. Therefore, HSB activities are re-planned in last week of July 2018.
2) Rotor journal & Thrust:
Journal & Thrust Collar Machining : 8th June ~ 19th June [Completed]
According to journal machined size, bearing pads modification is required.
GE engineering review is in progress.
3) Diaphragms / packing head, casing, ring / oil deflectors / bearing #1~3:
Transportation from GE India shop: 21 June 2018
On Site: Middle of August 2018
(Total 42 Packages, excluding 4 Journal bearing #1, 2, 3 and LP-IP Rotor).
- HP turbine (Rotor, blade carrier) Rectification Works
· New York Port to GE(Bangor) Shop: 25 ~ 29 May 2018 [Completed]
· Rotor & Carrier Inspection and Repair : 31 May ~ 18 July 2018 [In Progress]
· Inspection Report has been submitted to EGCB via letter SID-SCT-EGC-LT-0451-
NRR dated on 23 June 2018.
1) HP Rotor : Final cleaning and preparation of packing is in progress
2) Blade carrier : Abradable coating is in progress SCT
3) HP Packing Ring : Ordered new packing rings 29 June 2018
· Transportation from GE Bangor shop (USA): 18 July 2018 [Planned]
· On Site: Last week of September 2018 [Planned]

- MSCV and CRV Actuators (6EA) & ST Lube Oil Hydraulic Pumps + Motors (2EA)
Delivery Schedule to Korea : 7th June ~ 22nd of June 2018
Delivery to Boschrexroth : 26th of June 2018
Cleaning and Inspection is in progress, after inspection detail schedule will be shared
with EGCB.
- Steam line pipe two (2) flanges surface has heavy pittings due to corrosion, it is
required to send workshop for rectification works.
3 Agreed by EGCB to SCT
- Samsung will provide certificate of public university as per requirement of SRO73. SCT
- EGCB inspected the maintenance tools. After handover the temporary container
EGCB will be responsible for Maintenance tools custody.
4 Request by SCT to EGCB
- Letter of Credit to be extended. SCT sent official letter in this regard on 27 May 2018
(Letter ref: SID-SCT-EGC-LT-0379-RR). EGCB is requested to reply by 2 Jun 2018. EGCB ASAP
- EGCB already sent Extension request to Sonali Bank and Sonali Bank sent swift
message to negotiating bank on 28 June 2018.
Quality
1 NCR
< as of 01 July. ’18>
- Current status of NCR’s received from EGCB is as follows; SCT QC
Total: 125 / Closed: 88 / Open 37
2 Commissioning Punch List (Simple Cycle)
< as of 01 July. ’18>
- Total Punch List SCT QC
1) Electrical - Total: 27 / Closed: 2 / Open 25
2) Instrument - Total : 58 / Closed : 4 / Open 54

2
Agenda Action by Due date
3 Erection Dossiers (Simple Cycle)
< as of 01 July. ’18>
- Current status of erection dossiers submitted by EPC is as follows SCT QC
Total: 107 / Document submitted: 107 / Pending: 0
(Approved: 85 / Under review: 22)
4 Pre-commissioning and Commissioning Dossier (Simple Cycle)
< as of 01 July. ’18>
- Current status of pre-comm. &comm. dossiers submitted by EPC is as follows SCT QC/
Total: 36 / Document submitted: 36 / Pending: 0 Comm.
(Under Reviewing : 22 / Reviewed with Comments : 14)
Engineering
1 Engineering document
- As built drawing documents for Simple Cycle has been submitted to EGCB/OE on
EGCB ASAP
01 June 2018. (Transmittal ref: SID-SCT-EGC-TR-0095). Also SCT replied EGCB’s
letter (Letter ref: SID-EGC-SCT-LT-192) on 27 June 2018 (Letter ref: SID-SCT-EGC-
LT-0459-RR). EGCB to review.
Procurement
1 Vendor TFA Dispatch Schedule
Vendor Equipment Description Expected Dispatch Date
ABB ST GSUT Mid of July 2018
Amiantit GRP Pipe 27 July 2018

2 Transportation Status
ETA IP/Auth. Letter to EGCB On-
Vendor Item Remark
Port Submission Approval Site
PVC Fitting & pipe
Hidroambiente 5/28 6/14 - TBC*
(SID-167)
Chemical(HAZDS) Pending in
Hidroambiente TBC 6/11 6/12 TBC*
(SID-123) MPEMR
Piping & Fitting On Customs
Saliran 4/9 4/9 5/5 TBC*
(SID-178) clearnace
Instrument
Hylok 6/28 6/21 - TBC*
(SID-195)
* To be checked
**MPEMR: Ministry of Power Energy and Mineral Resources process
- Outstanding import documents will be reported to EGCB separately.
3 Auxiliary Transformer FAT
- EGCB informed three Electrical Engineers from EGCB will attend the FAT on 17 ~ SCT ASAP
20 July 2018. (Letter ref: SID-EGC-SCT-LT-214).
- Official invitation from Schneider, Indonesia will be send to EGCB by 02 July 2018.
Construction
Civil
1 Civil
- Chemical Dosing & Gantry Crane foundation Structure work. SCT Ongoing
- Urbanization & underground network. SCT Ongoing
- Pretreatment area DAF wall leakage rectification work ongoing.
SCT Ongoing
- CB 1 Rebar work ongoing
SCT Ongoing
- CB 6 Lean concrete work ongoing
- Cooling Tower GRP foundation modification work ongoing SCT Ongoing
- Boundary Wall
SCT Ongoing
· Temporary fencing & Excavation work ongoing.
- River intake Pump Bain A modification work preparation

3
Agenda Action by Due date
- Admin Building
· All Furniture had been inspected and handed over to EGCB. EGCB already
shifted from Project office to Admin Building
· SCT will start cleaning and renovation from 01 July 2018.
Steel Structure
1 ST Building
- Structural Erection work is ongoing.
- Grouting work ongoing. SCT Ongoing
2 River Water Intake Area
- Balance platform work. SCT Ongoing
3 HRSG Area
- Structural Erection for DCS panel is ongoing. SCT Ongoing
4 Workshop and Warehouse Building
- Structural erection work will resume from 03 July 2018. SCT 01 Jul 18
Mechanical
1 HRSG
- Preparing work for HRSG inside cleaning. SCT Ongoing
- Balance material arrived on 13 June and working start 5 July 2018
2 Pre-Water / Water Treatment Plant
- For PT Area
· Remain punch, surface preparation and paint repair works ongoing. SCT Ongoing
- For WTP Area
. Piping pressure test is ongoing. (test packages) SCT Ongoing
3 Cooling Tower
- Pre-assembly of clean flow (infill) & drift eliminator & FRP structure are ongoing at
Laydown 3 area and in front of office SCT Ongoing
4 ST Building Overhead Crane
- OHC rail work is ongoing. It is planned to install OHC on 4 Jul 2018.
5 Piping
- Utility (SW/IA/SA) piping and support installation work ongoing.
SCT Ongoing
- Steam drain line and Low steam line installation work ongoing
- Main steam line(Alloy) installation ongoing
- Circulating water line installation ongoing
- Hydro-test of Fire fighting for WTP is ongoing.
- Transformer(ST) Firefighting installation on going
- HVAC of CCR AHU-1 maintenance work is ongoing
Electrical
1 Electrical
- WTP Area
· Lighting Conduit & Fixture Installation work is ongoing. SCT 30 Jun 18
- STG Area
· Cable Tray Installation work is ongoing. SCT 31 Jul. 18
- BOP Area
SCT 30 Jun 18
· Chemical Dosing Skid Grounding work is ongoing.
- River Intake Line
· Cable tray cover installation will start from 01 July 2018 SCT 01 July 18
I&C
1 I&C
- HRSG Area
· Installation of Conduit for I & C. SCT 30 Jul 18
· Installation of Tubing and Instrument for HP, IP, LP Drum SCT 30 Jul 18
· Installation of Air Supply Tubing SCT 30 Jul 18

4
Agenda Action by Due date
- CCW Area SCT 05 Jul 18
· Installation of fitting as welding.
- CCR Area SCT 05Jul 18
· Installation of NLDC Panel and Junction Box.
Project Control
1 Project Schedule
- SCT will report only for Construction & Commissioning progress weekly basis.
Last Week (22 June 2018) This Week (29 June 2018)
Description
Plan Actual Var. Plan Actual Var. Incremental

Construction 71.26% 69.94% △1.32% 72.19% 70.34% △1.86% 0.40%


Civil 82.38% 84.03% 1.66% 82.38% 84.06% 1.68% 0.02%
Architecture 79.77% 72.18% △7.58% 83.55% 73.58% △9.97% 1.39%
Mechanical 67.58% 65.23% △2.35% 68.36% 65.27% △3.09% 0.03%
Piping 72.34% 69.88% △2.46% 72.94% 70.62% △2.32% 0.74%
Painting/ Insulation 18.28% 18.28% 0.00% 18.28% 18.28% 0.00% 0.00%
Electrical 74.35% 73.65% △0.70% 75.09% 73.65% △1.44% 0.00%
I&C 38.80% 40.07% 1.27% 40.91% 41.47% 0.56% 1.40%
Fire Fighting 77.23% 79.67% 2.43% 77.52% 79.96% 2.44% 0.29%
HVAC 67.99% 65.59% △2.40% 69.19% 65.88% △3.31% 0.29%
Commissioning 50.00% 50.00% 0.00% 50.00% 50.00% 0.00% 0.00%

[Notes for this week]


- Overall site activity has been affected by Eid holiday.
1. Civil
- Civil work for Chemical Dosing completed.
2. Architecture
- Structural work for Internal platform and east side of ST building is ongoing.
- Preparing to commence Workshop and Warehouse building.
- Cladding work for ST building is delayed.
3. BOP Equipment
- Pre-assembly and material shifting work for Cooling Tower is ongoing.
- Remaining piping and electrical work for pre-treatment and water treatment plant is
ongoing.
4. Piping
- Steam turbine drain system, Main & cold reheat system, low steam system welding
and joint fit-up works ongoing
- Condensate water pipe, Closed cooling water pipe installation is ongoing.
- Clarified water pipe, Service water pipe installation for WTP building is ongoing.
5. E&I
- Scaffolding and electrical cable tray installation is ongoing
- Instrumentation installation for HRSG area is ongoing.
6. Fire Fighting & HVAC
- Firefighting and HVAC work for WTP building is ongoing.
2 Monthly Meeting # 08
- Meeting will be held on 10 July 2018. SCT/ 10 Jul 18
EGCB