Weekly Meeting # 30 PCM Fichtner
DPM
Between EGCB and SCT on 16 July 18
1
Agenda Action by Due date
2 ST Rectification Plan
Targeted date for the remedial actions [Tentative & For Information only]
SCT Cont.
- LP-IP rotor / diaphragms / packing head, casing, ring / oil deflectors / bearing
#1~3
1) ST LP Rotor Repair:
LSB reassembly & L-0 finger dovetail hole reaming and fitting : 17th June ~ 23rd July
2018, GE informed that special reamers is under manufacturing and expected by
20th July 2018. Therefore, HSB activities are re-planned in last week of July 2018.
2) Rotor journal & Thrust:
Journal & Thrust Collar Machining : 8th June ~ 19th June [Completed]
According to journal machined size, bearing pads modification is required.
GE engineering review is in progress.
3) Diaphragms / packing head, casing, ring / oil deflectors / bearing #1~3:
Transportation from GE India shop: 21 June 2018
On Site: Middle of August 2018
(Total 42 Packages, excluding 4 Journal bearing #1, 2, 3 and LP-IP Rotor).
- HP turbine (Rotor, blade carrier) Rectification Works
· New York Port to GE(Bangor) Shop: 25 ~ 29 May 2018 [Completed]
· Rotor & Carrier Inspection and Repair : 31 May ~ 18 July 2018 [In Progress]
· Inspection Report has been submitted to EGCB via letter SID-SCT-EGC-LT-0451-
NRR dated on 23 June 2018.
1) HP Rotor : Final cleaning and preparation of packing is in progress
2) Blade carrier : Abradable coating is in progress SCT
3) HP Packing Ring : Ordered new packing rings 29 June 2018
· Transportation from GE Bangor shop (USA): 18 July 2018 [Planned]
· On Site: Last week of September 2018 [Planned]
- MSCV and CRV Actuators (6EA) & ST Lube Oil Hydraulic Pumps + Motors (2EA)
Delivery Schedule to Korea : 7th June ~ 22nd of June 2018
Delivery to Boschrexroth : 26th of June 2018
Cleaning and Inspection is in progress, after inspection detail schedule will be shared
with EGCB.
- Steam line pipe two (2) flanges surface has heavy pittings due to corrosion, it is
required to send workshop for rectification works.
3 Agreed by EGCB to SCT
- Samsung will provide certificate of public university as per requirement of SRO73. SCT
- EGCB inspected the maintenance tools. After handover the temporary container
EGCB will be responsible for Maintenance tools custody.
4 Request by SCT to EGCB
- Letter of Credit to be extended. SCT sent official letter in this regard on 27 May 2018
(Letter ref: SID-SCT-EGC-LT-0379-RR). EGCB is requested to reply by 2 Jun 2018. EGCB ASAP
- EGCB already sent Extension request to Sonali Bank and Sonali Bank sent swift
message to negotiating bank on 28 June 2018.
Quality
1 NCR
< as of 01 July. ’18>
- Current status of NCR’s received from EGCB is as follows; SCT QC
Total: 125 / Closed: 88 / Open 37
2 Commissioning Punch List (Simple Cycle)
< as of 01 July. ’18>
- Total Punch List SCT QC
1) Electrical - Total: 27 / Closed: 2 / Open 25
2) Instrument - Total : 58 / Closed : 4 / Open 54
2
Agenda Action by Due date
3 Erection Dossiers (Simple Cycle)
< as of 01 July. ’18>
- Current status of erection dossiers submitted by EPC is as follows SCT QC
Total: 107 / Document submitted: 107 / Pending: 0
(Approved: 85 / Under review: 22)
4 Pre-commissioning and Commissioning Dossier (Simple Cycle)
< as of 01 July. ’18>
- Current status of pre-comm. &comm. dossiers submitted by EPC is as follows SCT QC/
Total: 36 / Document submitted: 36 / Pending: 0 Comm.
(Under Reviewing : 22 / Reviewed with Comments : 14)
Engineering
1 Engineering document
- As built drawing documents for Simple Cycle has been submitted to EGCB/OE on
EGCB ASAP
01 June 2018. (Transmittal ref: SID-SCT-EGC-TR-0095). Also SCT replied EGCB’s
letter (Letter ref: SID-EGC-SCT-LT-192) on 27 June 2018 (Letter ref: SID-SCT-EGC-
LT-0459-RR). EGCB to review.
Procurement
1 Vendor TFA Dispatch Schedule
Vendor Equipment Description Expected Dispatch Date
ABB ST GSUT Mid of July 2018
Amiantit GRP Pipe 27 July 2018
2 Transportation Status
ETA IP/Auth. Letter to EGCB On-
Vendor Item Remark
Port Submission Approval Site
PVC Fitting & pipe
Hidroambiente 5/28 6/14 - TBC*
(SID-167)
Chemical(HAZDS) Pending in
Hidroambiente TBC 6/11 6/12 TBC*
(SID-123) MPEMR
Piping & Fitting On Customs
Saliran 4/9 4/9 5/5 TBC*
(SID-178) clearnace
Instrument
Hylok 6/28 6/21 - TBC*
(SID-195)
* To be checked
**MPEMR: Ministry of Power Energy and Mineral Resources process
- Outstanding import documents will be reported to EGCB separately.
3 Auxiliary Transformer FAT
- EGCB informed three Electrical Engineers from EGCB will attend the FAT on 17 ~ SCT ASAP
20 July 2018. (Letter ref: SID-EGC-SCT-LT-214).
- Official invitation from Schneider, Indonesia will be send to EGCB by 02 July 2018.
Construction
Civil
1 Civil
- Chemical Dosing & Gantry Crane foundation Structure work. SCT Ongoing
- Urbanization & underground network. SCT Ongoing
- Pretreatment area DAF wall leakage rectification work ongoing.
SCT Ongoing
- CB 1 Rebar work ongoing
SCT Ongoing
- CB 6 Lean concrete work ongoing
- Cooling Tower GRP foundation modification work ongoing SCT Ongoing
- Boundary Wall
SCT Ongoing
· Temporary fencing & Excavation work ongoing.
- River intake Pump Bain A modification work preparation
3
Agenda Action by Due date
- Admin Building
· All Furniture had been inspected and handed over to EGCB. EGCB already
shifted from Project office to Admin Building
· SCT will start cleaning and renovation from 01 July 2018.
Steel Structure
1 ST Building
- Structural Erection work is ongoing.
- Grouting work ongoing. SCT Ongoing
2 River Water Intake Area
- Balance platform work. SCT Ongoing
3 HRSG Area
- Structural Erection for DCS panel is ongoing. SCT Ongoing
4 Workshop and Warehouse Building
- Structural erection work will resume from 03 July 2018. SCT 01 Jul 18
Mechanical
1 HRSG
- Preparing work for HRSG inside cleaning. SCT Ongoing
- Balance material arrived on 13 June and working start 5 July 2018
2 Pre-Water / Water Treatment Plant
- For PT Area
· Remain punch, surface preparation and paint repair works ongoing. SCT Ongoing
- For WTP Area
. Piping pressure test is ongoing. (test packages) SCT Ongoing
3 Cooling Tower
- Pre-assembly of clean flow (infill) & drift eliminator & FRP structure are ongoing at
Laydown 3 area and in front of office SCT Ongoing
4 ST Building Overhead Crane
- OHC rail work is ongoing. It is planned to install OHC on 4 Jul 2018.
5 Piping
- Utility (SW/IA/SA) piping and support installation work ongoing.
SCT Ongoing
- Steam drain line and Low steam line installation work ongoing
- Main steam line(Alloy) installation ongoing
- Circulating water line installation ongoing
- Hydro-test of Fire fighting for WTP is ongoing.
- Transformer(ST) Firefighting installation on going
- HVAC of CCR AHU-1 maintenance work is ongoing
Electrical
1 Electrical
- WTP Area
· Lighting Conduit & Fixture Installation work is ongoing. SCT 30 Jun 18
- STG Area
· Cable Tray Installation work is ongoing. SCT 31 Jul. 18
- BOP Area
SCT 30 Jun 18
· Chemical Dosing Skid Grounding work is ongoing.
- River Intake Line
· Cable tray cover installation will start from 01 July 2018 SCT 01 July 18
I&C
1 I&C
- HRSG Area
· Installation of Conduit for I & C. SCT 30 Jul 18
· Installation of Tubing and Instrument for HP, IP, LP Drum SCT 30 Jul 18
· Installation of Air Supply Tubing SCT 30 Jul 18
4
Agenda Action by Due date
- CCW Area SCT 05 Jul 18
· Installation of fitting as welding.
- CCR Area SCT 05Jul 18
· Installation of NLDC Panel and Junction Box.
Project Control
1 Project Schedule
- SCT will report only for Construction & Commissioning progress weekly basis.
Last Week (22 June 2018) This Week (29 June 2018)
Description
Plan Actual Var. Plan Actual Var. Incremental