You are on page 1of 11

Automation in Construction 112 (2020) 103084

Contents lists available at ScienceDirect

Automation in Construction
journal homepage: www.elsevier.com/locate/autcon

3D printing of a post-tensioned concrete girder designed by topology T


optimization

Gieljan Vantyghema, , Wouter De Cortea, Emad Shakourb, Oded Amirb
a
Department of Structural Engineering, Ghent University, Valentin Vaerwyckweg 1, 9000 Ghent, Belgium
b
Faculty of Civil and Environmental Engineering, Technion – Israel Institute of Technology, Haifa, Israel

A R T I C LE I N FO A B S T R A C T

Keywords: In this paper, the digital design and manufacturing of a post-tensioned concrete girder is presented. We bring
3D concrete printing together two emerging technologies that show great potential for realizing highly-efficient concrete structures:
Topology optimization topology optimization for simulation-driven design and 3D concrete printing (3DCP) for manufacturing of op-
Prestressed concrete timized shapes. While this is not the first-ever 3D-printed concrete structure, it is the first demonstration of how
Bridge design
topological design in combination with 3D concrete extrusion printing allows for creating efficient structures
with reduced use of materials. As the implementation of a specific optimization procedure for post-tensioned
concrete structures is so far available in 2D only, some design post-processing was necessary, and a 3D finite
element analysis was performed. After realization of the 3DCP element (i.e. printing and assembly), the girder's
structural performance was experimentally verified using digital image correlation. The deflection of the girder
was compared with the numerical results. The manuscript includes thorough discussions on the manufacturing
challenges – including printing setup, assembly and integration of reinforcement.

1. Introduction However, as with any new technology, it also presents new chal-
lenges and complications [9]. A structural element that is well-designed
The purpose of this paper is to present a novel design and manu- according to traditional production methods and current standards may
facturing process that combines 3D concrete printing, topology opti- behave unexpectedly or even suffer damage as a result of the produc-
mization, and post-tensioning of concrete structures. In this section, we tion process, i.e. 3DCP. The reason is mainly that the effect of the
provide the essential background for each of the building blocks. printing process itself on the final structural response as well as the
Additive manufacturing techniques have become popular effective macroscopic material properties is not fully explained today
throughout recent years, and 3D printing of concrete is no exception. It [4,10]. Consequently, the result from the topology optimization study
is a new tool in the toolbox of architects and construction companies could not perform as expected and fail to stand the test of time.
and offers a quick and cost-efficient way of building large-scale en- Topology optimization is a class of computational tools that can be
gineering structures [1–3]. As defined by Buswell et al. [4]: “3D con- used to optimize the layout of materials in a certain design domain, so
crete printing (3DCP) works by precisely placing, or solidifying, specific that an objective function is optimized subject to design and behavioral
volumes of material in sequential layers by a computer-controlled po- constraints. There are several distinct approaches for obtaining opti-
sitioning process.” Autonomous or semi-autonomous 3D printers re- mized topologies. In this paper, we rely on the density-based approach
quire minimal human surveillance, as such this could answer to the [11], where the structural topology is represented by a collection of
growing shortages of skilled workers [5]. Another outcome of the density values that can vary between 0 (void) and 1 (material) at dis-
technique is that it disposes the need for conventional molding and crete points in the design domain.
allows for the creation of unique and complex shapes that were un- Topology optimization has gained popularity as a computational
attainable through conventional fabrication. By reducing the cost as- design tool for weight reduction of structural parts in automotive and
sociated with nonstandard shapes, 3DCP gives virtual free rein to ar- aerospace applications [12]. Despite its origin in classical structural
chitects, designers and structural engineers enabling non-traditional optimization methodologies, let alone several research efforts that de-
design methods such as topology optimization [6–8]. monstrate the role of topology optimization within emerging digital


Corresponding author.
E-mail addresses: Gieljan.Vantyghem@UGent.be (G. Vantyghem), Wouter.DeCorte@UGent.be (W. De Corte), semad@campus.technion.ac.il (E. Shakour),
odedamir@technion.ac.il (O. Amir).

https://doi.org/10.1016/j.autcon.2020.103084
Received 29 April 2019; Received in revised form 3 January 2020; Accepted 8 January 2020
0926-5805/ © 2020 Elsevier B.V. All rights reserved.
G. Vantyghem, et al. Automation in Construction 112 (2020) 103084

design and manufacturing processes [13–16], topology optimization


has had an only minor impact on the construction industry so far.
Nevertheless, the negative environmental impact of concrete produc-
tion clearly motivates the use of topology optimization for reducing
material consumption in construction.
Topology optimization for concrete is not new; over the past two
decades, it was suggested as a method for generating optimal strut-and-
tie models [17]; for distributing material based on the different
strengths in tension and compression [18–20]; and for simultaneous
Fig. 1. Setup for topology optimization of a single-span beam subjected to a
optimization of concrete and rebars [21–24]. In a recent review paper
uniform load, utilizing symmetry. Gray represents the initial density value of
in Cement and Concrete Research [25], a slab element was topologi- 0.5 throughout the domain, while the density of the top surface is fixed to 1
cally optimized for a uniformly distributed load, and a formwork was (black) so that the loading area is not disturbed. The blue line represents the
3D printed using particle bed fusion and subsequently cast with initial tendon shape. (For interpretation of the references to color in this figure
UHPFRC. In another case, the same research group performed a topo- legend, the reader is referred to the web version of this article.)
logical optimization study for a concrete canoe competition, also using
a 3D printed formwork cast with UHPFRC [26].
min ϕ = (fText utotal )2
Our starting point for this paper is the conceptual designs as ob- [ρ, P ]
tained by [27]. In this paper, a new procedure was proposed for con- NE
current optimization of the concrete layout and the shape of a post- ∑ ρe ve
e=1
tensioning tendon embedded into it. This paper will focus on: a) the s. t. :g = NE
− V∗ ≤ 0
post-processing of the design; b) the segmental fabrication by 3D ∑ ve
e=1
printing; c) the assembly and post-tensioning; and d) the initial testing
0 ≤ ρe ≤ 1, e = 1, ..., NE
of a manufactured girder.
This paper presents a first proof-of-concept of the design and man- P≤P≤P
ufacturing process for prestressed concrete elements with concrete ex- Kutotal = f ext + f pre (1)
trusion technology as manufacturing process and a design that is based
on topology optimization. The remainder of the paper is organized as where ρ is the vector of density variables; P the vector of tendon co-
follows: In Section 2, we begin by reviewing the topology optimization ordinates; fext the vector of external forces; utotal the vector of total
formulation and results, for the sake of completeness. This is followed displacements, utotal = uext + upre; NE the number of finite elements
by a detailed presentation of the post-processing of the design, in- and density variables; ve the volume of the e-th finite element; V⋆ the
cluding finite element analysis and preparation for 3D printing. Section available volume fraction for the concrete in its dilated configuration; P
_
3 is dedicated to the manufacturing process, all the way from printing and P the lower and upper bounds for the tendon coordinate move-
of the segments to post-tensioning of the assembled girder. Experi- ments; K the stiffness matrix of the concrete domain, related to the
mental results and comparisons are presented in Section 4, followed by mathematical variables ρ and P via filtering and projection operations;
the conclusions in Section 5. and fpre the vector of prestress forces, that depends on P. We note that
the square of the work ϕ is used in the objective so to avoid the erro-
neous solution that magnifies the negative work of fext upon upre.
2. Design process For a standard beam with uniform cross-section, the required
M
tendon force can be estimated as TSTD = totalh , where Mtotal is the total
2.1. Topology optimization of the prestressed girder eT +
6
bending moment at the critical point (mid-span in the particular case);
The design of the prestressed 3D-printed concrete girder is based on eT the maximum eccentricity of the tendon; and h the beam height. The
computational results from [27]. As the design procedure has been design chosen for manufacturing and testing is the one obtained with
developed so far in 2D only and without precise design parameters, T = 0.8 × TSTD and a concrete volume equal to 50% of the rectangular
some adaptation of the design for the actual three-dimensional setting domain. The optimized concrete distribution and tendon layout are
and material properties is necessary. Hence, the results from [27] serve displayed in Fig. 2.
herein as a conceptual material distribution and tendon geometry, It should be emphasized that topology optimization of structures is a
whereas actual dimensioning is performed in a post-processing stage - well-established methodology and its development towards 3D concrete
described in the next section. printing applications can benefit from a vast body of knowledge. The
The particular design and manufacturing test case is that of a particular case of optimizing the tendon geometry is quite new but
simply-supported beam subjected to a uniform load. For topology op- results of several cases, including statically indeterminate beams, are
timization, we use a rectangular design domain with a length-to-height available in the referenced article. Moreover, ongoing work focuses on
ratio of 10:1 that is discretized into a grid of 300-by-30 square finite a more practical formulation that includes the tendon force as a design
elements, each element is associated with a density design variable. The variable; curvature constraints on the tendon; and stress constraints in
setup of the problem is presented in Fig. 1. Note that we utilize sym- the concrete.
metry, so only one half of the design domain is simulated and opti- As topology optimization typically generates complex geometries,
mized. At the beam's end, horizontal sliding supports are available its coupling to additive manufacturing is natural and has been the focus
through the complete height of the domain, so that the optimization of extensive research recently (see a recent review by [28] and refer-
procedure finds the best location of the supports that will meet the ences therein). The main challenge is to embed the printing limitations
tendon's anchor. and constraints into the optimization formulation. So far, overhang
The optimization seeks a design that minimizes the displacements at limitations have been receiving attention, primarily by using projection
the top surface of the beam, due to the combined action of the external or filtering operations [29,30]. As one of the limitations in concrete
loads and the post-tensioning tendon. In mathematical terms, this de- printing is the capacity to sustain self-weight during printing, for-
sign goal reads: mulations that embed gravity loads can be adapted to the particular
case of concrete [31,32].

2
G. Vantyghem, et al. Automation in Construction 112 (2020) 103084

Fig. 2. Results of the topology optimization proce-


dure for a single-span beam subjected to a uniform
load. Black represents concrete; white represents
void; cyan represents the tendon. (For interpretation
of the references to color in this figure legend, the
reader is referred to the web version of this article.)

Fig. 3. Computer-generated images of the 3D-printed design without (left) and with end blocks (right).

2.2. Design post-processing Table 1


Material properties used in the FE-model.
The topology-optimized result from Fig. 2 was adopted and trans- Material Young's modulus Poisson's ratio Density (kg/m3)
formed to 3D using Fusion 360 – Autodesk ©. The idea was to have a (MPa) (−)
circular lower chord, so that the post-tension cable was evenly sur-
rounded by a reasonable amount of concrete, thus avoiding local Concrete (C30/37) 32,800 0.2 2500
Steel 190,000 0.3 7800
failure. Secondly, the upper chord of the girder was widened to allow
for humans crossing the girder. We refer to this part as the deck side, as
we purposely envisioned a small bridge. Attention was paid not to make Table 2
the deck too wide, since this would introduce unsafe transverse tensile Strand properties.
forces in the top fibers of the upper chord. Taking these matters into
Type 3/8″
account, a dynamic shape was finally created, see Fig. 3. As can be
Diameter (mm) 9.3
observed, the 3D printing process was only used for the manufacturing Ap (mm2) 52
of the contour shape of the girder; thereafter, the 3D-printed parts were fpk (N/mm2) 1860
assembled between two pre-fabricated end blocks, and the inner cavity Max. prestress force (kN) 77.4
was injected with a grout material. The function of the end blocks is
two-fold. Primarily, they anchor the transverse bursting forces in-
troduced by the post-tension force, and secondly, they are used to keep nature of the structure. The ratio between the 3D-printed segments and
the separate parts together during the assembly and grouting process. the internal cavity volume is quite large ( ± 85%), therefore, the
Finally, as the project was meant to serve as a proof-of-concept, the equivalent material properties depend not only on the grout material
girder was designed with a limited span width of 4.0 m, and the post- that will fill the internal cavity, but also the material of the 3D-printed
tensioning cable consisted of one 7-wire strand. segments and the effects of the printing process itself. In the end, a well-
The analysis of the 3D-printed girder cannot be based on the 2D considered choice had to be made; and an equivalent concrete grade of
calculation. Since the optimization analysis is purely 2D, its stress re- C30/37 was chosen for the dimensioning of the girder. Concerning the
sults are not valid. Therefore, the model was studied using 3D finite validation part, several other concrete grades were added and dis-
element analysis, and the structural response under different load cussed. Based on this concrete grade with a characteristic cylinder
conditions was analyzed. The considered load cases were: self-weight compressive strength of 30 MPa (C30/37), the following design limits
(g), self-weight + post-tensioning force (g + fpre), and self- were extracted conforming with EN 1992-1-1: the design compressive
weight + post-tensioning force + live load (g + fpre + fext). For strength of the concrete was constrained to 20 MPa and the design
symmetry reasons, only half of the girder was modeled. The domain tensile strength was limited to 1.35 MPa.
was discretized using C3D4 and C3D6 elements (4-node linear tetra- The results of a linear elastic analysis based on the aforementioned
hedrons and 6-node linear triangular prisms) and comprises 125,555 geometry, loads and material properties can be found in Fig. 4. The first
elements. The use of complex quadratic elements was not deemed cri- study (Fig. 4a) only considers the self-weight of the girder. Results show
tical at this stage, since the differences in results are likely neglectable that the maximum principal stresses in the girder are mostly below
for design purposes. Also, included in the FE study is the post-ten- these ultimate stress states. The average tensile stress in the lower chord
sioning cable in the lower chord and the end blocks. These were is only 1 MPa. The second result (Fig. 4b) presents the girder when the
modeled using linear elements and connected using a tie constraint. A live load is also applied. This load case (without the post-tensioning)
diameter of 8.2 mm was used for the cable, and surface-to-surface will not occur in reality but is included to assess certain risks. The live
contact properties were defined to model the unbonded interaction load is set equal to 17 kN distributed equally across the top surface (i.e.,
with the concrete girder. The sliding formulation was defined as small fext = 10 kN/m2). The tensile stress in the girder now exceeds the de-
with hard normal contact properties, and frictionless tangential beha- sign tensile strength.
vior [33]. The material properties used in the FE-study can be found in The third result (Fig. 4c) considers the self-weight and the post-
Table 1 and the characteristics of the post-tensioning strand in Table 2. tensioning. Due to the prestress force, the lower chord of the girder is
For clarification, the shape of the end blocks was not optimized. loaded in compression, while tensile forces arise in the top part of the
It should be noted that the Young's modulus and its associated girder. The prestress force was set at 50 kN. As can be observed, the
concrete grade were difficult to determine because of the ‘hybrid’ occurring stresses are mostly within the design limits of the material;
except for a peak stress concentration in one of the struts. The

3
G. Vantyghem, et al. Automation in Construction 112 (2020) 103084

g
3 MPa

(a)
fext

g
3 MPa 6 MPa

(b)

3.5 MPa
g
fpre

(c)
fext

g
fpre 2 MPa

(d)

Ø9.4 mm tendons Ø12 mm rebars

(e)
Fig. 4. Principal stress plots for the different load cases. (a) self-weight, (b) self-weight + live load, (c) self-weight + prestress force, (d) self-weight + prestress
force + live load, and (e) dimensioning of the reinforcements.

maximum compression stress in the lower chord is around 5 MPa, and 2.1; thus, these were not considered. Additionally, the stress distribu-
the maximum tensile stress in the upper chord is 0.5 MPa. The final tion in the end blocks was removed from the results as they did not
analysis (Fig. 4d) shows the principal stresses of the girder when all accurately predict the internal stresses. The reason for this is the in-
loads are combined: the self-weight of the girder plus the prestressing accurate modeling of the anchorage zones and the simplifications in the
and external force. As expected in prestressed concrete design, the material model. Advanced FE models such as proposed by Van Meirv-
girder appears to be in a neutral state, where most of the tensile stresses enne et al. [35] could provide more insight. However, their in-
are eliminated. A small peak of tensile stresses does remain. corporation is beyond the scope of the current study. The amount of
The authors are aware that in bridge design engineering, asym- rebar in the end blocks was therefore calculated manually, and in ac-
metric design loads and concentrated convoy loads should be con- cordance to LRFD Bridge Design Specifications - AASHTO [36].
sidered as well. Although a topology optimization study concerning Finally, some additional safety measures were taken in the final
these additional load cases was performed by the authors [34], this design. Additional rebars were added to the structure to protect it from
approach was not yet combined with the algorithm described in Section unforeseen stress concentrations considering the segmentation in the

4
G. Vantyghem, et al. Automation in Construction 112 (2020) 103084

Part 1 Part 2 Part 3 Part 4 Part 9

Part 5 Part 6 Part 7 Part 8

(a)

(b)
Fig. 5. Generation of the printing path by visual scripting techniques in Rhinoceros & Grasshopper.

printing process (see further). Therefore, in every diagonal strut, two 3.1. Printing of the girder segments
rebars of Ø12 were added (Fig. 4e).
The 3D printing of the girder segments took place at the Magnel
2.3. Subdivision into parts and slicing algorithm Laboratory for concrete research and at Vertico [38]. Because both
setups are very similar, only the printing setup of the former is de-
As expected, the girder could not be 3D printed in one piece. A scribed (Fig. 6). The setup comprises: (i) a robot arm, (ii) a mortar
similar approach as observed in the production of the 3D-printed bi- (screw) pump for cementitious material, and (iii) a concrete 3D printing
cycle bridge in Gemert, The Netherlands [37] was adopted. In that mixture.
project, six identical pieces were individually printed, then rotated on The robot is of the type ABB IRB6650 – with a range of 3.2 m and
their sides and finally post-tensioned towards one another. Similar to payload of 125 kg – and has 6 degrees of freedom (DOFs), which enable
that approach, our topology-optimized design was subdivided into printing in almost every orientation and tool alignment. It is one of two
several parts (Fig. 5a) and for each of them the contour shape was 3D systems that is frequently used by researchers and companies in the
printed. Since, each element had a maximum height of 400 mm and a field of concrete 3D printing. In this experiment, the robot actuator
maximum total weight of 30 kg, they could be printed with a minimal remained perpendicular to the horizontal plane. The pump has a de-
amount of support material, where taller prints would collapse under livery rate between 2 and 29 L/min and can handle pressures up to
self-weight load. The subdivision of the 3D design was performed in 30 bar. The mortar recipe was based on the dehuizenprinters [39], and
Rhinoceros using the Grasshopper plugin. A custom Grasshopper script consists of 51.1% dried sand 0/2, 34.7% Portland cement CEM I 52.5 R,
was created to slice the volumes and to generate the RAPID code with 13.2% water, and 1.0% water retention agent (these percentages are in
robot control instructions. (Fig. 5b). Considering the symmetry of the mass, i.e. % of the total weight). The latter ensures that the water is
girder, nine RAPID files were created, each containing roughly 4000 more retained, and the mix gets its desired thixotropic behavior and
lines of code needed to control the ABB robotic arm. prevent the occurrence of pressurised bleeding. The print nozzle has a
Ø25 mm opening and is set to print at 80 mm/s. The total printing time
of the segments was estimated to be around 24 h. The actual printing
3. Manufacturing process
was performed in three working days and required at least three op-
erators simultaneously. The 3D-printed segments were allowed one
The manufacturing process of the girder was separated into three
night of settling, whereafter they could be removed from the printing
phases. First, the actual 3D printing of the eighteen girder segments and
bed and be transported.
the casting of the two end blocks is presented. Secondly, the assembly of
the different parts is discussed, including the grouting process and the
integration of rebars. Finally, the post-tensioning of the lower tendon.

5
G. Vantyghem, et al. Automation in Construction 112 (2020) 103084

Fig. 6. Concrete 3D printing set-up at the Magnel Laboratory for concrete research.

3.2. Casting of the end blocks Finally, four 30 mm holes were drilled in the girder. The first and last
hole were drilled 400 mm from the supports, and hole two and three
Traditional casting was used for the realization of the end blocks. A were drilled 1000 mm from the midspan. One of the center holes was
wooden formwork was made (Fig. 7a) and steel rebars and spirals were used as inlet for the grout material, while the other holes served as an
inserted (Fig. 7b). In each end block, three anchorage systems were air outlet. The same pumping system as for the 3D printing was used to
built in to fix the strands. Steel ducts were embedded in the concrete to transport the grout. The grouting material was a high-quality shrinkage
allow for the post-tension cables and their hoses running through the compensating high-strength seal mortar [40] (compressive strength
concrete mass. In addition, perpendicularly to the main duct, a steel ~60 MPa; tensile strength ~12 MPa). However, since the consistency of
reinforcing plate was embedded to transfer the post-tensioning force the mortar had to be adjusted during pumping by adding water, the
from the wedge into the concrete (Fig. 7c). quality of the material is not certain, but likely somewhat lower.
Whenever the mortar rose from one of the remaining holes, pumping
was paused, and the hole was sealed. A small amount of mortar leaked
3.3. Assembly, integration of reinforcements and grouting
though an unclosed gap in the mid-bottom section of the girder. Finally,
the girder was allowed two weeks of hardening.
After the 3D printing of the girder, the next step was to assemble all
parts, including the reinforcements, and to fill the inner cavity with a
grout mortar. This grout was injected after a sufficient hardening/set- 3.4. Post-tensioning
tling period of the 3D-printed segments (i.e., several weeks).
First, the printed elements (Fig. 8a) were positioned with their deck After a hardening period of 14 days, the girder was lifted from the
side flat on the ground. By positioning the parts this way, only a limited ground, and the main tendon was slightly tensioned (10 kN); next, the
amount of support structure was required. Foam blocks were used to girder was flipped in its upright position. During this elevation and
support the cylindrical sections in the mid part of the girder. The rotation process, the girder was supported by polyester lashing belts.
joining of the different parts was performed from one end to the other The final structure was placed on supports with a rubber slab below
to enable the insertion of the steel rebar (Fig. 8b). To keep them in each end block (Fig. 9a) and a preliminary verification of the girder's
place, traditional plastic spacers were used. The post-tensioning cables strength was performed by carefully allowing people on the girder
– surrounded by a plastic sheathing – were also brought in position. (estimated weight: 7 kN). Finally, the full post-tension force of 50 kN
Attention was given to the positioning of the main strand, which had to was applied, and the upward deflection was measured using several dial
run as centrically as possible to avoid secondary bending in the lower indicators and digital image processing (Fig. 9b). The upwards deflec-
chord. To close the gaps between the printed elements, the two deck tion of the upper chord was around 10 mm, while the lower chord's
strands were prestressed using a very small force (5 kN). Next, the joints maximum final deflection was around 18 mm. This (excessive) deflec-
were sealed with a foam gun to close off any remaining gaps (Fig. 8c). tion of the lower chord (especially in the mid-span) was more than what

Fig. 7. Manufacturing of the end blocks: (a) design - dimensions in [cm], (b) wooden formwork and added reinforcements, and (c) the resulting end block with a view
on the steel reinforcing plate.

6
G. Vantyghem, et al. Automation in Construction 112 (2020) 103084

Fig. 8. (a) 3D-printed segments, (b) positioning of reinforcement, and (c) assembly and grouting process.

Fig. 9. (a) Completed girder and (b) image correlation software capturing the deflection of the manufactured girder during post-tensioning.

7
G. Vantyghem, et al. Automation in Construction 112 (2020) 103084

Fig. 10. Experimental setup to monitor deformations.

Fig. 11. Registration of the displacements of the concrete girder by digital image correlation.

the FE-model predicted and could be attributed to secondary bending of manufactured girder. The goal was to verify the service load perfor-
the lower chord due to misalignment of the post-tensioning strand mance of the optimized shape. Since the original objective of the op-
within. This issue is further discussed in the next section. timization study was to seek a design that minimizes the displacements
at the top surface of the beam, the focus of the experiment was on the
4. Experimental testing upper chord. Digital image processing [41] was used to measure the
deflection of the girder, with the white markers being the area of in-
Finally, load/displacement tests were performed on the terest. The displacements of these markers were tracked, and the

8
G. Vantyghem, et al. Automation in Construction 112 (2020) 103084

Fig. 12. Registration of the displacements of the concrete girder compared to the numerical results for (a) the upper chord and (b) the lower chord.

measurements were verified using digital dial indicators (Figs. 10–11). 5. Conclusions
Both the upper and lower chord were registered. In the end, the ex-
perimental results were then compared to the original FE analysis. We presented a digital design-to-manufacture process that combines
In Fig. 12, the numerical results and marker are presented using topology optimization, 3D concrete printing and post-tensioning. As
lines and points, respectively. The upper chord (Fig. 12a) shows a good additive manufacturing in general offers relatively large design
fit between the experimental and numerical results. Most of the tracked freedom, it can promote the reduction of material consumption when
markers are within the gray area, which shows the numerical deflection coupled with techniques such as topology optimization. The complex
values for different concrete grades. The small deviations from the shapes that arise from topology optimization procedures challenge the
numerical values can be attributed to the sectional assembly, and the manufacturing techniques and material limitations of 3D concrete
use of linear elements in the FE analysis (these elements are known to printing – hence our main purpose was to demonstrate the feasibility of
be overly stiff hence will underestimate deflections). On the other hand, the process and to show a proof-of-concept in the form of a scaled
the lower chord (Fig. 12b) shows a much higher deviation from the girder. By careful segmentation of the design into printable parts, fol-
numerical result. The main deviation arises around the mid-section, lowed by joining them with post-tensioning tendons, we obtained a
indicating an effect of secondary bending in the lower chord. This can viable concrete girder that can sustain the loads for which it was de-
be attributed to tolerances in the position of the post-tensioning strand signed. The use of post-tensioning, with its geometry optimized si-
within the lower chord, as well as to the sectional assembly. During the multaneously with the concrete distribution, alleviated the difficulty of
post-tensioning phase, the upwards deflection of the mid-span was al- introducing steel reinforcement in 3D-printed concrete.
ready higher than what was expected. Therefore, when loading the Based on the performance of the optimized beam, in terms of mid-
structure, this upwards deflection is being relaxed and is adding to the span deflections under self-weight and live loads, we can predict ma-
deflection of the tracked markers. In larger structures, the positioning of terial savings of roughly 20%. This estimate is based on finding a T-
the post-tension strand should be easier to control and eliminate this section girder with the same flange size (585 mm by 97 mm) and the
problem. same overall depth (388 mm) as the optimized beam, giving the same
total deflection. The resulting volume of concrete is nearly 20% higher

9
G. Vantyghem, et al. Automation in Construction 112 (2020) 103084

than that of the optimized beam – hence clarifying the incentive to We would like to thank our colleagues: Prof. Geert De Schutter,
employ topology optimization and manufacture complex geometries. Prof. Kim Van Tittelboom, Prof. Veerle Boel, and Dr. Karel Lesage who
The manufacturing process described in the paper does not yet re- provided insight and expertise that greatly assisted the realization of
veal a clear economic benefit. Nevertheless, the focus was on the fea- this project. We would also like to express our gratitude to all students
sibility of the process, combining a computational-intensive design (Ghent University) who assisted in the realization: Victor Bulcke, Ticho
method and robotic 3D printing. The realistic economic benefits of 3D Ooms, Brenten Smekens, Cedric Van den Abeele, Maxim Vanderbeken,
printing over traditional manufacturing methods are still a matter of and Niels Venneman. Finally, we would like to express our sincere
research, not only in the context of concrete but also in more estab- gratitude to Volker Ruitinga and Lars Kooijman (Vertico).
lished technologies such as powder-based metal printing. Therefore, we
do not claim any immediate economical savings in the paper. However, References
as the technology improves and consolidates, the expected key benefits
will be: a) Reduction of concrete consumption, due to optimization and [1] D. Hwang, B. Khoshnevis, Concrete wall fabrication by contour crafting,
realization of complex geometry that is not necessarily feasible in tra- Proceedings of the 21st International Symposium on Automation and Robotics in
Construction, 2004, https://doi.org/10.22260/isarc2004/0057.
ditional manufacturing; b) No need of molding as in concrete casting; [2] S. Lim, R. Buswell, T. Le, R. Wackrow, S. Austin, A. Gibb, et al., Development of a
and c) Possibility of autonomous robotic manufacturing. viable concrete printing process, 28th International Symposium on Automation and
This study opens up many research topics that require further in- Robotics in Construction (ISARC 2011), 2011, https://doi.org/10.22260/
isarc2011/0124.
vestigations. At first, the deviations between the numerical model and [3] Y.W.D. Tay, B. Panda, S.C. Paul, M.N.A. Noor, M.J. Tan, K.F. Leong, 3D printing
the measured deflections at the lower chord need to be investigated. trends in building and construction industry: a review, Virtual and Physical
One possible explanation could be secondary bending moments due to Prototyping 12 (3) (2017) 261–276, https://doi.org/10.1080/17452759.2017.
1326724.
imperfections in the alignment of the tendon. Another factor of un-
[4] R. Buswell, W. Leal de Silva, S. Jones, J. Dirrenberger, 3D printing using concrete
certainty is the determination of the equivalent material characteristics extrusion: a roadmap for research, Cem. Concr. Res. 112 (2018) 37–49, https://doi.
of the hybrid structure (3DCP segments and grout infill). From the org/10.1016/j.cemconres.2018.05.006.
[5] R. de Laubier, M. Wunder, S. Witthöft, C. Rothballer, Will 3D printing remodel the
computational design perspective, full 3D topology optimization with
construction industry? [ONLINE] Available https://www.bcg.com/publications/
prestressing still needs to be addressed, while accounting for manu- 2018/will-3d-printing-remodel-construction-industry.aspx, (2018) , Accessed date:
facturing limitations and uncertainties poses further challenges. From 18 April 2019.
the manufacturing perspective, future work should focus on improving [6] C. Gosselin, R. Duballet, P. Roux, N. Gaudillière, J. Dirrenberger, P. Morel, Large-
scale 3D printing of ultra-high performance concrete – a new processing route for
the buildability of printable construction materials, i.e. the ability of architects and builders, Mater. Des. 100 (2016) 102–109, https://doi.org/10.1016/
extruded material to retain its shape under sustained loads. This may be j.matdes.2016.03.097.
achieved in the future using active rheology (or stiffening) control as [7] F. Bos, R. Wolfs, Z. Ahmed, T. Salet, Additive manufacturing of concrete in con-
struction: potentials and challenges of 3D concrete printing, Virtual and Physical
well as a setting-on-demand mix design approach. Progress in this field Prototyping 11 (3) (2016) 209–225, https://doi.org/10.1080/17452759.2016.
could increase the number of continuous layers that can be printed (or 1209867.
stacked) without failure and boost the maximum degree of overhang in [8] R. Duballet, O. Baverel, J. Dirrenberger, Classification of building systems for
concrete 3D printing, Autom. Constr. 83 (2017) 247–258, https://doi.org/10.1016/
a design. j.autcon.2017.08.018.
Additionally, having a finite element-based virtual simulation [9] G. De Schutter, K. Lesage, V. Mechtcherine, V.N. Nerella, G. Habert, I. Agusti-Juan,
model for concrete 3D printing is valuable. Such model could predict Vision of 3D printing with concrete - technical, economic and environmental po-
tentials, Cem. Concr. Res. 112 (2018) 25–36, https://doi.org/10.1016/j.cemconres.
values of strength, internal stresses, critical locations, and initial de- 2018.06.001.
formations during the printing progress. Based on the outcome from a [10] R. Wolfs, F. Bos, T. Salet, Early age mechanical behaviour of 3D printed concrete:
FEM-based calculation, a particular design could be marked unfit for numerical modelling and experimental testing, Cem. Concr. Res. 106 (2018)
103–116, https://doi.org/10.1016/j.cemconres.2018.02.001.
printing, providing additional insight on process parameters that could
[11] M.P. Bendsøe, Optimal shape design as a material distribution problem, Structural
be tuned in order to increase the chance of success in printing the Optimization 1 (4) (1989) 193–202, https://doi.org/10.1007/BF01650949.
analyzed design; thus, avoiding costly physical experiments. Finally, if [12] J.H. Zhu, W.H. Zhang, L. Xia, Topology optimization in aircraft and aerospace
all these challenges can be overcome, the authors see great potential in structures design, Arch. Comput. Meth. Eng. 23 (4) (2015) 595–622, https://doi.
org/10.1007/s11831-015-9151-2.
using this design methodology for the manufacturing of large-scale [13] L. Frattari, The Structural from: Topology Optimization in Architecture and
post-tensioned concrete bridges. Industrial Design, Doctoral dissertation School of Advanced Studies, University of
Camerino, 2011 [ONLINE] Available https://altairatc.com/europe/EHTC2011-
Abstracts/EHTC-Presentations-2011/Session_09/Pres_ehtc_2001_03_Eng.pdf ,
Declaration of competing interest Accessed date: 15 July 2019.
[14] P. Dombernowsky, A. Søndergaard, Unikabeton prototype, Fabricate 2011 (2011)
The authors declare that they have no known competing financial 55–60, https://doi.org/10.2307/j.ctt1tp3c6d.14.
[15] K. Besserud, N. Katz, A. Beghini, Structural emergence: architectural and structural
interests or personal relationships that could have appeared to influ- design collaboration at SOM, Archit. Des. 83 (2) (2013) 48–55, https://doi.org/10.
ence the work reported in this paper. 1002/ad.1553.
[16] A. Søndergaard, J. Feringa, F. Stan, D. Maier, Robotic abrasive wire cutting of
polymerized styrene formwork systems for cost-effective realization of topology-
Acknowledgements optimized concrete structures, Construction Robotics 2 (1–4) (2018) 81–92,
https://doi.org/10.1007/s41693-018-0016-8.
This research project was supported by Ghent University, Vertico, [17] Q.Q. Liang, Y.M. Xie, G.P. Steven, Generating optimal strut-and-tie models in pre-
stressed concrete beams by performance-based optimization, ACI Struct. J. 98 (2)
and Technion - Israel Institute of Technology.
(2001) 226–232, https://doi.org/10.14359/10191.
The following partners were involved: [18] M. Bogomolny, O. Amir, Conceptual design of reinforced concrete structures using
topology optimization with elastoplastic material modeling, Int. J. Numer. Methods
- Topology optimization of the prestressed concrete girder: Technion - Eng. 90 (13) (2012) 1578–1597, https://doi.org/10.1002/nme.4253.
[19] Y. Luo, Z. Kang, Layout design of reinforced concrete structures using two-material
Israel Institute of Technology topology optimization with Drucker–Prager yield constraints, Struct. Multidiscip.
- 3D modeling and FE-analysis: Research Group Schoonmeersen - Optim. 47 (1) (2012) 95–110, https://doi.org/10.1007/s00158-012-0809-1.
Department of Structural Engineering - Ghent University [20] Y. Luo, M. Wang, M. Zhou, Z. Deng, Topology optimization of reinforced concrete
structures considering control of shrinkage and strength failure, Comput. Struct.
- Rheology mix design and manufacturing process: Mortar recipe 157 (1) (2015) 31–41, https://doi.org/10.1016/j.compstruc.2015.05.009.
from wiki.bouwkoppel.nl | dehuizenprinters - Vertico [21] A.T. Gaynor, J.K. Guest, C.D. Moen, Reinforced concrete force visualization and
- Assembly and post-tensioning: Magnel Laboratory for concrete re- design using bilinear truss-continuum topology optimization, J. Struct. Eng. 139
(2013) 607–618, https://doi.org/10.1061/(asce)st.1943-541x.0000692.
search - Department of Structural Engineering - Ghent University [22] O. Amir, A topology optimization procedure for reinforced concrete structures,

10
G. Vantyghem, et al. Automation in Construction 112 (2020) 103084

Comput. Struct. 114 (2013) 46–58, https://doi.org/10.1016/j.compstruc.2012.10. Comput. Phys. 351 (2017) 295–328, https://doi.org/10.1016/j.jcp.2017.09.041.
011. [32] O. Amir, Y. Mass, Topology optimization for staged construction, Struct.
[23] M. Bruggi, A numerical method to generate optimal load paths in plain and re- Multidiscip. Optim. 57 (4) (2017) 1679–1694, https://doi.org/10.1007/s00158-
inforced concrete structures, Comput. Struct. 170 (2016) 26–36, https://doi.org/ 017-1837-7.
10.1016/j.compstruc.2016.03.012. [33] ABAQUS, ABAQUS Documentation, Dassault Systèmes, Providence, RI, USA, 2011
[24] W.R. Leal da Silva, T.J. Andersen, A. Kudsk, K.F. Jørgensen, 3D concrete printing of [ONLINE] Available http://ivt-abaqusdoc.ivt.ntnu.no:2080/v6.14/books/usb/
post-tensioned elements, Proceedings of IASS 2018 – Creativity in Structural default.htm?startat=pt09ch38s01aus177.html [Accessed 15 July 2019].
Design, Boston, July 2018 [ONLINE] Available https://www.dti.dk/_/media/ [34] A. Jansseune, W. De Corte, The influence of convoy loading on the optimized to-
71860_IASS2018_Ref172.pdf [Accessed 15 July 2019]. pology of railway bridges, Struct. Eng. Mech. 64 (1) (2017) 45–58, https://doi.org/
[25] D. Lowke, E. Dini, A. Perrot, D. Weger, C. Gehlen, B. Dillenburger, Particle-bed 3D 10.12989/sem.2017.64.1.045.
printing in concrete construction – possibilities and challenges, Cem. Concr. Res. [35] K. Van Meirvenne, W. De Corte, V. Boel, L. Taerwe, Nonlinear analysis of the end
112 (2018) 50–65, https://doi.org/10.1016/j.cemconres.2018.05.018. zones of prestressed concrete girders, Proceedings of the PCI Convention and
[26] A. Jipa, M. Bernhard, B. Dillenburger, N. Ruffray, T. Wangler, R. Flatt, skelETHon National Bridge Conference 2017, 2017 http://hdl.handle.net/1854/LU-8512855.
formwork 3D printed plastic formwork for load-bearing concrete structures, [36] American Association of State Highway and Transportation Officials (AASHTO),
Blucher Design Proceedings (2017), https://doi.org/10.5151/sigradi2017-054. LRFD Bridge Design Specifications, 8th edition, (2017) Washington, DC. [ONLINE]
[27] O. Amir, E. Shakour, Simultaneous shape and topology optimization of prestressed Available https://app.knovel.com/web/toc.v/cid:kpAASHTO94 , Accessed date: 15
concrete beams, Struct. Multidiscip. Optim. 57 (2018) 1831–1843, https://doi.org/ July 2019.
10.1007/s00158-017-1855-5. [37] T. Salet, Z. Ahmed, F. Bos, H.L.M. Laagland, Design of a 3D printed concrete bridge
[28] J. Liu, A.T. Gaynor, S. Chen, Z. Kang, K. Suresh, A. Takezawa, L. Li, J. Kato, J. Tang, by testing, Virtual and Physical Prototyping 13 (2018) 222–236, https://doi.org/
C.C.L. Wang, L. Cheng, X. Liang, A.C. To, Current and future trends in topology 10.1080/17452759.2018.1476064.
optimization for additive manufacturing, Struct. Multidiscip. Optim. 57 (6) (2018) [38] Vertico, Pioneers in 3D concrete printing, [ONLINE] Available https://www.
2457–2483, https://doi.org/10.1007/s00158-018-1994-3. vertico.xyz/, (2019) , Accessed date: 15 July 2019.
[29] A.T. Gaynor, J.K. Guest, Topology optimization considering overhang constraints: [39] Wiki.bouwkoppel.nl, Hardware:our_setup, [Online]. Available, 2019. https://wiki.
eliminating sacrificial support material in additive manufacturing through design, bouwkoppel.nl/doku.php?id=hardware:our_setup.
Struct. Multidiscip. Optim. 54 (5) (2016) 1157–1172, https://doi.org/10.1007/ [40] SIKA, Technische fiches Sikagrout, [ONLINE] Available https://bel.sika.com/nl/
s00158-016-1551-x. oplossingen_producten/download-center/technische_fiches/pds_sikagrout.html,
[30] M. Langelaar, An additive manufacturing filter for topology optimization of print- (2019) , Accessed date: 15 July 2019.
ready designs, Struct. Multidiscip. Optim. 55 (3) (2016) 871–883 2016 https://doi. [41] GOM, GOM correlate evaluation software for 3D testing, [ONLINE] Available
org/10.1007/s00158-016-1522-2. https://www.gom.com/3d-software/gom-correlate.html, (2019) , Accessed date:
[31] G. Allaire, C. Dapogny, R. Estevez, A. Faure, G. Michailidis, Structural optimization 15 July 2019.
under overhang constraints imposed by additive manufacturing technologies, J.

11

You might also like