Minutes of Meeting
Phase : 3
Doc. No. : HFY3-3250-PCH-GTH-M-0049 Meeting Date : 4 Feb 2016
Location : PCH-Base Camp-Meeting Room 207 Meeting Time : 02:00 PM
Chaired by : Mr. Elkheir Ali Prepared By: Mohammed Naqqash
Subject : Weekly Meeting
ATTENDEES
CONTRACTOR PMC- PETROCHINA HALFAYA
Name Position Name Position
Note : Refer to attached Attendance record Note : Refer to attached Attendance record
( AL-GTH/PMC/PMT ) ( AL-GTH/PMC/PMT )
AGREED BY:
CONTRACTOR: PMC:
AL-GAYATH CO. EXIDA SP
_____________ _____________________________
Name: Abd AlKareem Abd Ali Name: Abdulhalim Doka
Designation: PM Designation: Sr. Civil Engineer
Date: 4 Feb 2016 Date: 4 Feb 2016
COMPANY
PETROCHINA – Halfaya
___________________________
Name: Elkheir Ali
Designation: PCH-TL
Date: 4 Feb 2016
ITEM ACTION
DESCRIPTION DATE
NO. BY
1.0 HSE
1.8 PMT/PMC request GTH to provide gloves for the workers. GTH Info
ITEM ACTION
DESCRIPTION DATE
NO. BY
PMT/PMC request GTH to submit Security Inspection by
1.13 GTH Info
monthly.
PMT/PMC informed GTH that in case of issuing of HSE NCR,
1.14 work will stop for 7 days at the site as per the last updated GTH Info
NCR procedure.
2.0 QA/QC
Summary Closed/Open
2.4 QC 6 Closed 6
HSE 1 Open 1
Planning 0
Management 0
DCC 0
Total 7
PMT/PMC requested GTH QC to pay more attention and
spend more time to check all activities and the qualities
2.6 documents. GTH Regular
GTH QA/QC to inspect the activities before sending the RFI to
the PCH, then PMC/GTH QC will attend the inspection.
FDT/ Concrete Results, shall be submitted weekly.
2.7 GTH Ongoing
Cut-off Date: Sunday, submission: Tuesday. After review in
Template No: HFY-PMT-DC-TMP-0004 Revision 2 Page3 / 5
Issue Date: 22/02/15
HALFAYAOIL FIELD
SURFACE FACILITY PROJECT
PETROCHINA HALFAYA
ITEM ACTION
DESCRIPTION DATE
NO. BY
special meeting.
PMT/pmc requested GTH to make sure updating the progress figures regulary
before entering into weekly meetings and informed that un upadeted figures are
unacceptable .
Last Week This Week
Work Package Weight Work
Revised Plan Actual Variance Revised plan Actual Variance
3.1 done this
Procurement 13.00% 100.00% 92.60% -7.40% 100.00% 92.60% -7.40% 0.00%
Commissioning & HO
2.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
5.0 Construction
ITEM ACTION
DESCRIPTION DATE
NO. BY
GTH confirms that 5 shovels 6 Compactors,30 Dump Trucks,4
Water Tanker,2 Excavator,0 Scrapers, 0 Dozer, 0 Mobile
Crane 30Ton and 4 Graders and available at site , 0 low
5.1 GTH Regular
loader, 0 Truck mixers , 0 concrete pumps , paver 2 and
bitumen tanker 1 .
GTH to update the status of equipment list weekly.
5.2 PCH informed GTH that Road 6 is first Priority. GTH Info
GTH casted the concrete of the 546/570 pre-cast slab for slab
culvert.
5.3 GTH 4th Feb
PMT/PMC request GTH to complete the remaining pieces for
the precast slabs.
GTH informed PCH that the Construction delay is due to
recent stoppages by land owners. Incident reports submitted
5.4 in this regard. GTH Info
GTH sent letter to PCH in this regard at 23/Oct for the
summary of all project stoppages.
GTH is requested to start shaping for road 5 and road 6 side
5.5 GTH Info
slopes.
PMT/PMC request GTH to keep road 6 accessible for
5.6 GTH Info
emergency to CPF3 during rainy season.
PCH advised daily paving productivity (400 m) is low, GTH to
5.7 GTH 2nd Feb
engage additional resources to maintain 800 – 1000 m/day.
PMT/PMC requested GTH to submit weekly schedule of
5.8 GTH Regular
activities for PMC to avail the required monitoring.
6.0 Others
Attachments:
1. Attendance Sheet