You are on page 1of 5

HALFAYAOIL FIELD

SURFACE FACILITY PROJECT


PETROCHINA HALFAYA

PRID No.: 3250

PROJECT NAME:PH III Roads and Bridges Package 1

Minutes of Meeting

Phase : 3
Doc. No. : HFY3-3250-PCH-GTH-M-0049 Meeting Date : 4 Feb 2016
Location : PCH-Base Camp-Meeting Room 207 Meeting Time : 02:00 PM
Chaired by : Mr. Elkheir Ali Prepared By: Mohammed Naqqash
Subject : Weekly Meeting
ATTENDEES
CONTRACTOR PMC- PETROCHINA HALFAYA
Name Position Name Position

Note : Refer to attached Attendance record Note : Refer to attached Attendance record
( AL-GTH/PMC/PMT ) ( AL-GTH/PMC/PMT )

AGREED BY:
CONTRACTOR: PMC:
AL-GAYATH CO. EXIDA SP
_____________ _____________________________
Name: Abd AlKareem Abd Ali Name: Abdulhalim Doka
Designation: PM Designation: Sr. Civil Engineer
Date: 4 Feb 2016 Date: 4 Feb 2016
COMPANY
PETROCHINA – Halfaya

___________________________
Name: Elkheir Ali
Designation: PCH-TL
Date: 4 Feb 2016

Template No: HFY-PMT-DC-TMP-0004 Revision 2 Page1 / 5


Issue Date: 22/02/15
HALFAYAOIL FIELD
SURFACE FACILITY PROJECT
PETROCHINA HALFAYA

The minutes are hereby duly recorded as follows:

ITEM ACTION
DESCRIPTION DATE
NO. BY

1.0 HSE

PMC/PMT remind the contractor to conduct equipment


1.1 periodical inspection prior to mobilization at site. Tracking GTH Info
record to be submitted every 1 months.
PMC/PMT remind contractor to ensure that site personnel are
1.2 mandatory using PPE such as Helmet, Safety shoes, Cover all GTH Regular
and Safety glass.
PMC/PMT request contractor to obtain PTW from PMC/PMT
authority prior to start their site work execution.
1.3 GTH Info
GTH is requested to follow PCH excavation procedure and use
the new excavation authorization form.
PMT/PMCRequest contractor to communicate with Mr.Mustafa
50260,Ali Sabeh (50922) and Mr.Ja’far Kareem (51233) for
any work stoppage and other security issues from (local
1.4 farmer/s), a preliminary incident report has to be submitted GTH Ongoing
within 24 Hours.Mr.Shafa Rizal for HSE (50535).
Contractor is requested to use the new PIR format for any
incident submission.
PMT/PMC reminds contractor to submit their monthly & weekly
1.5 GTH Info
statistics reports and tracking records.
Tool box shall be conducted daily prior to start the work.
1.6 PMC/PMT reminding GTH about Fire Safety to including inside GTH Ongoing
the TBT.
PMT/PMC remind GTH on housekeeping to be collected at the
1.7 end of the activity. GTH Info
Housekeeping to be conduct on daily basis.

1.8 PMT/PMC request GTH to provide gloves for the workers. GTH Info

PMT/PMC remind GTH to notify PMC/HSE about any incident GTH


1.9 Info
within 24 hours by Email or by Phone follow by PIR.
PMT/PMC Highlighted that any Contractor cannot use GTH
1.10 Vehicles without Plates and Valid Registration. Info
All the drivers must have a driving license.
PMT/PMC request GTH to submit Fire Safety Inspection Twice
1.11 GTH Info
per month (refer to the schedule).
Template No: HFY-PMT-DC-TMP-0004 Revision 2 Page2 / 5
Issue Date: 22/02/15
HALFAYAOIL FIELD
SURFACE FACILITY PROJECT
PETROCHINA HALFAYA

ITEM ACTION
DESCRIPTION DATE
NO. BY
PMT/PMC request GTH to submit Security Inspection by
1.13 GTH Info
monthly.
PMT/PMC informed GTH that in case of issuing of HSE NCR,
1.14 work will stop for 7 days at the site as per the last updated GTH Info
NCR procedure.
2.0 QA/QC

PMC/PMT reminds contractor to utilize competent Quality


2.1 Control personnel on site so as to avoid compromise with GTH Ongoing
regards to QC.
Summary of RFIs status to be mentioned in the weekly
meeting and to be updated every week.
Accepted 547
2.2 Rejected 51 Closed = 619 GTH Ongoing
Cancel 21
Open 12
Total 630
QSR Status :
2.3 Open Closed Total
3 14 17
NCR Status :
NCR Number Date Department Corrective Date Closing Date Current Status Action By Status
HFY3-PMC3-HSE-NCR-0004 9/13/2015 HSE 9/15/2015 9/15/2015 Verification Action Approved Closed
HFY3-3250-PMC3-GTH-NCR-0001 9/14/2015 QC 9/21/2015 9/22/2015 Verification Action Approved Closed
HFY3-3250-PMC3-GTH-NCR-0002 10/23/2015 QC 10/29/2015 12/19/2015 Verification Action Approved Closed
HFY3-3250-PMC3-GTH-NCR-0003 10/28/2015 QC 11/3/2015 12/8/2015 Verification Action Approved Closed
HFY3-3250-PMC3-GTH-NCR-0004 11/15/2015 QC 11/22/2015 1/5/2016 Verification Action Approved Closed
HFY3-3250-PMC3-GTH-NCR-0005 11/16/2015 QC 11/22/2015 12/17/2015 Verification Action Approved Closed
HFY3-3250-PMC3-GTH-NCR-0006 1/26/2016 QC 1/30/2016 Corrective Action Sent PCH Open

Summary Closed/Open
2.4 QC 6 Closed 6
HSE 1 Open 1
Planning 0
Management 0
DCC 0
Total 7
PMT/PMC requested GTH QC to pay more attention and
spend more time to check all activities and the qualities
2.6 documents. GTH Regular
GTH QA/QC to inspect the activities before sending the RFI to
the PCH, then PMC/GTH QC will attend the inspection.
FDT/ Concrete Results, shall be submitted weekly.
2.7 GTH Ongoing
Cut-off Date: Sunday, submission: Tuesday. After review in
Template No: HFY-PMT-DC-TMP-0004 Revision 2 Page3 / 5
Issue Date: 22/02/15
HALFAYAOIL FIELD
SURFACE FACILITY PROJECT
PETROCHINA HALFAYA

ITEM ACTION
DESCRIPTION DATE
NO. BY
special meeting.

PMT/PMC request GTH to update the Org. Chart and submit


2.8 GTH 21st Jan
new Rev. accordingly.
3.0 Project Management / General

PMT/pmc requested GTH to make sure updating the progress figures regulary
before entering into weekly meetings and informed that un upadeted figures are
unacceptable .
Last Week This Week
Work Package Weight Work
Revised Plan Actual Variance Revised plan Actual Variance
3.1 done this
Procurement 13.00% 100.00% 92.60% -7.40% 100.00% 92.60% -7.40% 0.00%

Construction 85.00% 92.17% 69.78% -22.39% 97.65% 72.08% -25.57% 2.31%

Commissioning & HO
2.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

Overall 100.00% 91.34% 71.35% -19.99% 96.00% 73.31% -22.70% 1.96%

PCH highlight the increasing variance from the revised base


line due to the delay in sub-base and asphalt paving. GTH is
3.2 PMT/GTH 31st / Jan
requested to prepare and submit a revised plan in which the
completion date will be on 15th March.
PMT/PMC agreed with GTH to hold weekly construction
3.3 meeting at GTH camp to monitor the weekly construction GTH Regular
activities.
4.0 Procurement

GTH confirmed that (1220 / 1220) PCs of Pipe culvert already


4.1 GTH Closed
arrived.
GTH Confirm that the sign board will arrive to site on 4th Feb
4.2 GTH 4th/Feb
PCH advised GTH to expedite.
Billboard Manufacturing will start 15th Feb, expected time of
dispatch from China is 15th Mar.
4.3 PCH advised GTH to expedite. GTH 15th Feb
PMT/PMC requested a progress report to be provided from
vendor.
PMT/PMC advise GTH to assign certified 3rd party to inspect
4.3 GTH Info
fabrication of billboard to avoid any acceptance dispute at site.

5.0 Construction

Template No: HFY-PMT-DC-TMP-0004 Revision 2 Page4 / 5


Issue Date: 22/02/15
HALFAYAOIL FIELD
SURFACE FACILITY PROJECT
PETROCHINA HALFAYA

ITEM ACTION
DESCRIPTION DATE
NO. BY
GTH confirms that 5 shovels 6 Compactors,30 Dump Trucks,4
Water Tanker,2 Excavator,0 Scrapers, 0 Dozer, 0 Mobile
Crane 30Ton and 4 Graders and available at site , 0 low
5.1 GTH Regular
loader, 0 Truck mixers , 0 concrete pumps , paver 2 and
bitumen tanker 1 .
GTH to update the status of equipment list weekly.

5.2 PCH informed GTH that Road 6 is first Priority. GTH Info

GTH casted the concrete of the 546/570 pre-cast slab for slab
culvert.
5.3 GTH 4th Feb
PMT/PMC request GTH to complete the remaining pieces for
the precast slabs.
GTH informed PCH that the Construction delay is due to
recent stoppages by land owners. Incident reports submitted
5.4 in this regard. GTH Info
GTH sent letter to PCH in this regard at 23/Oct for the
summary of all project stoppages.
GTH is requested to start shaping for road 5 and road 6 side
5.5 GTH Info
slopes.
PMT/PMC request GTH to keep road 6 accessible for
5.6 GTH Info
emergency to CPF3 during rainy season.
PCH advised daily paving productivity (400 m) is low, GTH to
5.7 GTH 2nd Feb
engage additional resources to maintain 800 – 1000 m/day.
PMT/PMC requested GTH to submit weekly schedule of
5.8 GTH Regular
activities for PMC to avail the required monitoring.
6.0 Others

Next meeting will be on 11th Feb 2016, venue: PCH Base


6.1 Info
Camp 03:00 PM O'clock.

Attachments:
1. Attendance Sheet

Template No: HFY-PMT-DC-TMP-0004 Revision 2 Page5 / 5


Issue Date: 22/02/15

You might also like