Weekly Report
Overview
Plant site visited on daily basis. On Monday 16-12-2019 GT 1,2,3, Turning Gear Engaged for two hours and
Complex full load demand initiated by NPCC on 17 DEC 2019 but due to unavailability of Fuel, Start-up
command was not executed and informed to NPCC. Whole Complex remained on standby during the week.
Regarding Maintenance All major activities observed as mentioned in Morning meeting Report some major
activities during week are listed below:
GT-1 annual shutdown calibration of Transmitters and Pressure switches (Auxiliary Compartment) work in
progress. Lube Oil Level Transmitter calibration were in progress as shown in picture.
II
Weekly Report
GT-1 CCCW Heat Exchanger B Cleaning was in progress. Plates were dipped in chemical for cleaning. After
Cleaning All the plates assembled back and bolts tightening were performed
III
Weekly Report
IV
Weekly Report
V
Weekly Report
UAT Oil and winding Temperature Meter calibration work was observed. By Applying Current through
external source and oil temperature sensor was dipped in hot water just to check existing point of
alarm and tripping command of transformer, then after setting the gauge again testing was
performed.
VI
Weekly Report
VII
Weekly Report
Steam Turbine Turning Gear Box Mechanical work is in progress. Faulty unit were replaced with
another Turning Gear and old one shifted to mechanical work shop for bearing dismantling. Some
Picture from ST Hall are attached below.