Professional Documents
Culture Documents
Elect Installation Dependabiliy Studies - Schneider PDF
Elect Installation Dependabiliy Studies - Schneider PDF
electrical
installation
dependability
studies
Sylvie LOGIACO
general
The voltage at the terminals of a current standard EN 50160 low voltage supply
consumer can be affected by frequency 50 Hz ± 1% for 95% of a week
phenomena originating in the distributor's 50 Hz + 4%, - 6% for 100% of a week
network, the electrical installation of a voltage amplitude for each one week period, 95% of the average effective values
subscriber connected to that network or over 10 minutes must be within the range of Un ± 10%
the electrical installation of the user who rapid voltage from 5% to 10% of Un
is suffering the disturbance. variations (4 to 6% in medium voltage)
Disturbances in the electricity voltage drops c amplitude: between 10% and 99% of Un
product (indicative values) most voltage drops are <60% of Un
c the main characteristics of the c duration: between 10 ms and 1 minute,
most voltage drops < 1s
voltage supplied by both the MV and
c number: several tens to 1 thousand per year
LV public distribution network are those
defined by European standard brief loss of power c amplitude: 100% of Un
(indicative values) c duration: up to 3 minutes,
EN 50160. This details the tolerances
70% are less than 1s
that must be guaranteed for both c number: several tens to several hundreds per year
voltage and frequency as well as the
long loss of power c amplitude: 100% of Un
disturbance levels that are usually
(indicative values) c duration: over 3 minutes,
encountered; e.g. harmonic distortion. c number: between 10 and 50 per year
The table in figure 1 details the
standard's recommended values. fig. 1: network disturbances : values found in the standard.
At any moment in time therefore, the
quality of the energy supplied to the
current consumers in an installation can frequency variations and overvoltages is duration of the loss of power that is
be affected by various disturbances, achieved by installing equipment suited acceptable to the installation.
either imposed by the external supply to each case. The design and choice of These studies enable the best suited
network or self-generated within the connection points for such equipment configuration and equipment to be
internal distribution network. are decided by performing detailed determined for the operator's
The operations of current consumers studies that are outside the scope of this requirements. They generally require
that are either independent or federated document (see bibliography). the current consumers or systems to be
in systems are affected by these classed according to their sensitivity
Loss of power
disturbances. level as well as distinguishing between:
For industrial processes and low
c malfunctions and the type and cost of v current consumers that accept
voltage systems this is increasingly
the damage incurred depend both on prolonged stoppage: 1 or more hours
difficult to tolerate since it generates
the type of current consumers and on (non priority),
unacceptable costs.
the installation's criticality level. Thus, a v current consumers accepting
momentary break in supply to a critical c immunity to loss of power requires stoppages of several minutes long
current consumer can have serious dedicated equipment such as (priority),
consequences on the installation's uninterruptible power supplies and v current consumers which must have
operation without it being intrinsically independent generator sets. This the power restored to them after
affected. equipment is generally not enough to several seconds (essential)
resolve all the problems. The network v current consumers not accepting any
c in all cases, a study detailing the
configuration, automatic power break in supply (vital),
effects of the suspected disturbances
restoring control devices, the level of
must be performed. Measures must be As an example, figure 3 shows the
reliability of the equipment, the
taken to limit their consequences. simplified diagram of a network in which
selectivity of protection devices as well
c the table in figure 2 shows the as the maintenance policy, all play an this distinction has been performed:
disturbances that can usually be found important role in reducing and v vital current consumers not tolerating
in electrical networks, their causes and eliminating down time. the slightest break in supply, are
the solutions that are possible to Minimising loss of power requires supplied power through an
reduce their effects. reliability / dependability studies to be uninterruptible power supply.
c the reduction of the effects of performed that take account of all these v power is restored to essential current
harmonics, Flicker, voltage imbalances, factors as well as the frequency and consumers a few seconds after network
fig. 4: definitions.
MTTR
MTBF
fig. 5: relations between the various values that characterise the reliability, maintainability and availability of a machine.
current current
consumer n°1 consumer n°2 * SC= Static contactor
process
dependability criteria 2
assessment calculations 1P=probability of P=probability of
start-up of GE's GE's not starting up
Two different techniques can be used.
c analytical resolution:
v for states graphs,
v for fault tree diagrams.
When systems are large or complex,
analytical resolution may be
impossible.
failure of GE's 3
c system component behaviour in operation
simulation (operation or failure):
v for Petri networks,
v for fault tree diagrams.
To achieve accuracy, a large number of
simulations must be carried out and the
calculation time may be prohibitive if fig. 20: modelling using a Petri network.
comparing two electrical R1b,…, R6b for plant n° 2 - the probability of losing electrical
network configurations in a R1c,…, R6c for plant n° 3 supply to current consumers n°3.
R1d,…, R6d for plant n° 4 c functional analysis
factory To ensure operation at off-peak times, General considerations concerning the
c presentation of the factory: only one plant is required ; during peak network operation:
A drinking water production plant times, two plants are required. v the site is supplied by two
supplies 100 000 m3/day at off peak c analysis of the enquiry, the independent power supply feeders.
times, 300 jours/year and requirements Two generator sets are there on stand-
200 000 m3/day at peak times, 65 days After two meetings with the customer, by in the case of failure of the power
a year. the specialists have determined: supply feeders,
Production of water is performed using v that the following was required: v in normal operation, the site is
4 production plants, each capable of - a proposal for a new LV electrical supplied by the power supply feeder A.
supplying 100 000 m3/day. network configuration, the configuration If this feeder fails, then the system
Each plant is associated with six of the MV (5.5 kV) should change very switches to power supply feeder B. If
types of current consumers : R1, R2, little, both power supply feeders fail, the
R3, R4, R5 and R6 (pumps, - proof that the proposed layout was at generator sets start up,
disinfectors, etc.) which must work least as good as the old in terms of v there are two levels of production, off-
simultaneously in order to ensure certain dependability criteria. peak and peak. In the case of peak
production (ref. fig. 22). v that the dependability criteria to be production, the power of the generator
The current consumers ensuring the assessed were: sets is not sufficient to ensure
operation of each plant can be - the probability of simultaneously production.
distinguished in the following manner: losing electrical supply to current v the power supply split between current
R1a,…, R6a for plant n° 1 consumers n°1 and n°6, consumers is such that the availability is
MV MV
switchboard 1 switchboard 2
20 kV 20 kV
T1 T2
5,5 kV 5,5 kV
fig. 22: functional diagram of the original installation. Certain penalising common modes are not shown.
transformer transformer
20 kV/5.5 kV 20 kV/5.5 kV
current current
protection coupling protection
consumers consumers
devices devices
n°7 n°7
current current
consumers T5 T3 T6 T4 consumers
n°8 n°8
console
level 2
communication
network
sorties
on/off
TORoutputs on/off outputs level 1
central
unité centrale entrées TOR
on/off inputs central on/off inputs
processor processor
entrées
analogical
analogiques
inputs analogical inputs
automate
PLC* (*Programmable Logic Controller) PLC*
to level 3
central
processor
console level 2
communication communication
network
sorties
on/off
TORoutputs on/off outputs
level 1
central
unité centrale entrées TOR
on/off inputs central on/off inputs
processor processor
entrées analogiques
analogical inputs analogical inputs
automate
PLC* (*Programmable Logic Controller) PLC*
fig. 27: monitoring and control configuration of an EHV substation with access and remote work station.
dependability study
packages tool modelling calculation main features
Certain tools automatically generate a name technique resolution technique
dependability study from the functional Adélia fault tree c analytical tool developed by Schneider Electric
analysis of the system and the failure c simulation to model the malfunctions in
electrical network components. It
modes of its components.
integrates an electrical network
A model is generated which enables malfunction database. The
evaluation of the dependability criteria. description of the network and of the
These tools are useful for complex undesirable event automatically
systems and/or repetitive systems. generates the corresponding
They enable a database to be created fault tree.
on the failure modes of the components Sofia fault tree c analytical tool developed by SGTE Sofrenten.
and on the consequences of these (logical polynomial) Automatic generation of a fault
tree and associated FMEA, by a
failures when possible. (see. fig. 30).
functional description of the system
and the creation of an associated
modelling tools malfunction database.
Two types of tools (see. fig. 31): fig. 30 : two types of tools regularly used by Schneider Electri for dependability study.
c simulation tools,
c analytical calculation tools.
modelling type simulation tool analytical calculation tool
Comment: a Markov graph can very
easily be transformed into a Pétri Markov graph super Cab
developed by ELF AQUITAINE
network and be used for simulation. As
opposed to a Pétri network, a graph Petri network MOCA-RD
developed by Microcab
can be associated, but in this case the
transitions must be «Markovised»: in a fig. 31: the modelling tools.
Markov graph the frequency of
occurrence of the transitions are
necessarily constant.
Schneider currently has a PC graphical
interface called PCDM which
automatically generates the file defining
the Markov graph or the Pétri network
that has been drawn (ref. fig. 32).
This provides time savings and
improved reliability of data entry.
The Petri network modelling technique
is that which currently best approaches
the real behaviour of the system. The
acceleration of the simulation of Petri
networks, notably using MOCA-RP
software, is the subject of a thesis
whose initial findings have been
presented at the ESREL 96 congress
(European Safety Reliability).
In the near future, the use of Petri
networks will no longer be limited by
the simulation time they require.
Dependability can be broken down in Requirements have progressed in c of the monitoring and control system,
terms of: terms of quality of electricity supply. c of the maintenance policy.
c safety, Taking account of the considerable They enable solutions to be chosen
c reliability, improvements that have been made in that are tailored to achieve the required
c availability, methods and equipment, users are availability threshold as cost effectively
c maintainability. entitled today to demand a high level of as possible.
Safety requirements initially imposed availability. Often the study can be limited to a key
dependability studies on hazardous To achieve this objective with justified point in the installation, responsible for
applications : rail and air transport, confidence, dependability studies are the major part of the global
nuclear power stations, etc. If we add necessary. unavailability.
the requirements of reliability, They enable optimisation of In many cases, it is interesting to call in
availability and maintainability, many c the configuration of the electrical a specialist. The advice they may
other sectors are concerned. network, provide could prove decisive.