Professional Documents
Culture Documents
DRILLING OPTIMIZATION
maximum drilling efficiency. The process involves the post appraisal of offset
Which include mud type, hydraulics, bit type, weight on bit and rotary speed.
The variables that offer the best potential for improving the drilling process
are identified. A final optimized drilling program is prepared and then will be
implemented in the field. Flexibility should be built into the program to allow
field application changes that may be dictated when unexpected problems are
encountered.
compromises must be made because of limitations beyond our control that result
in something less than optimum. Perhaps it can be explained this way; for years
it has been known that rate of penetration could be increased by drilling with
water, by rotating the bit faster, and by increasing flow velocity through jets in
the bit. Lack of sufficient mechanical and hydraulic horsepower, however, often
on bit, and pump rate does little or no good. New technology has raised these
limits, but they are still there. The limits set for drilling variables are all
influenced by the resulting bit life, the first major factor. Some are set by the
Although water is the fastest drilling liquid, in many areas some colloidal
solids in the fluid are necessary to provide hole stability. In other areas, weight
and pump pressure are generally limited by equipment capability and resulting
maintenance costs. Therefore, the lowest cost drilling will result when limits are
imposed that maximize not only drilling rate but also equipment life and well-
bore stability. In some cases, if well-bore stability and equipment life are
today without the hard work of numerous researchers who have spent
considerable time studying the effects of drilling variables and how they relate
to each other.
From 1937 to 1947 researchers worked on the composition and control of
drilling mud. Very little attention was given to penetration rate. The objective
was simply to get the hole drilled cased completed and production.
mud systems for effectiveness in producing desired viscosity and fluid loss
properties and to establish minimum specifications for mud materials. They also
effectiveness.
By the late 1950’s mud chemistry had advanced to the stage where mud
products available at the rig. However, mud researchers noted that even with
effective control mud properties hole conditions often were aggravated instead
become unstable even though mud properties were within the specified
guidelines. The observations that perfect mud don’t necessarily mean perfect
In 1959, through a series of 100 wells drilled it was shown that clay solids
had a significant effect on drilling rate number of bits and rig days. The great
Cost calculations are necessary when comparing less expensive milled tooth
bits with tungsten carbide insert bits. The basic cost per foot equation can be
presented as follows:
equal cost per foot and rate of penetration, involves the following equation:
variables: rate of penetration, bit life, rig rental cost, bit cost, and non-drilling
time. Other related costs not included in the above equation are mud cost
R = W k N R D f / T P
Df = drillability constant
assumptions:
-All drilling variables are interrelated; changes in one variable affect all the
others.
-The type amount and colloidal size of clay solids are the factors on which all
following order:
-Bit type
unalterable.
Alterable Unalterable
Mud Weather
Type Location
Weight-on-bit Depth
Rotary Speed
The classification is not strict, as some of the unalterable ones may be
altered by a change in the alterable ones. For example, changes in bit type,
the drilling fluid and bit type has altered the compressive and tensile strength
variables. For instance, the type and amount of solids considerably influence mud
in one may necessitate a reduction in the other for smooth economical operation.
experience and research suggest six: four alterable ones and two unalterable
ones.
Alterable Unalterable
Hydraulics Depth
Bit Type
Weight-rpm
The most important factors, which affect the cost of drilling fluids, are as
follows:
-Hole size
-Total depth
-Logistics
Special drilling fluid systems are available either for reducing the severity
fluid is, however, increased as result. For example, the use of oil-base drilling
fluid in place of water base mud completely eliminates the problems of cement
and salt contaminations; however, it is very costly to change (“switch”) the mud
type.
The cost of drilling fluid increases with increasing size and depth of the well
because of the higher volume of fluid required. Logistics is also responsible for
high drilling fluid cost, because materials, which have to be transported long
distance, will cost more than those that are available locally will. Consequently,
there are no typical drilling fluid costs. For example, drilling fluid costs alone for
different wells in the west Texas area drilled to the same depths (15,000 ft)
-Trained personnel must be used to supervise and direct any operations involving
viscosity or not. Trained mud engineers, on the other hand, can properly
diagnose the situation and prescribe correct treatment. This will reduce
x2)/(x3-x1)*(x3-x2)
Given the following table of x and y values find the value of y which
Chose the points 20, 1.1134; 35, 1.2160; 50, 1.3350 to substitute into
LaGrange’s interpolation formula . Note that the points 14, 20, and 35, could
y = 1,1134 * (26 - 35) * (26 - 50) / (20 - 35) * (20 - 50) + 1,2160 * (26 - 20) *
(26 - 50) / (35 - 20) * (35 - 50) + 1,3350 * (26 - 20) * (26 - 35) / (50 - 20) * (50
- 35)
1,1525
alternative, which is not associated at all with multiple regression and is very
a popular engineering equation. Compute k, a and b with the least squares method
b c
y = kx z
Begin by putting the equation into linear form by
taking logarithms.
Ln y = Ln k + b Ln x + c Ln z
Let x 1 = Ln yx2 = Ln x3 = Ln z a = Ln k
x1 = a+ bx2 + cx3
simultaneously
Σ x1 = a N + b Σ x2 + c Σ x3
D= det ( N x2 x3
x2 x2x2 x3 x2
x3 x2x3 x3x3 )
a = det ( x1 x2 x3
b = det ( N x1 x3
x2 x1x2 x3x2
x3 x1x3 x3x3) / D
c = det ( N x2 x1
x2 x2x2 x3x1
x2 x2x3 x3x1) / D
Example
y=k*xb*z c
Ln y = Ln k + b Ln x + c Ln z
x1 = Ln y * x2 = Ln x * x3 = Ln z * a = Ln k
Data computations
n = 6.00
Σ x1 = 38.34 D = 2.06
Σ x2 = 16.79 a = 0.74
Σ x3 = 17.22 b = 0.85
Example
Find: j and m
Linear form : Ln Pf = Ln j + m Ln q
Let: x1 = Ln Pf , x2 = Ln q n = Lnj
∑ x2x2 = 199,78
D = 5,89
a = -2,48
j = 0,084
Confidence Lines
Confidence lines area computed and drawn to provide the following type of
answer :
" If 7 " casing is selected 95 % of the pipe will have an expected maximum
diameter of 7.012 " and a minimum expected diameter of 6.889 " and an
expected diameter of 7.001".These are often called the maximum , minimum and
best values.
y=a+b*x
Begin by computing a,b and c
b = N ∑ xy - ∑ x * ∑ y / N ∑ x2 - (∑ x )2
a=∑y/ N–b∑x/N
χ=∑x/N
where:
Example
then Γ = 1 – 0,95
and then tn = 2,1 - Γ / 2 * 0.975 = 4.30 (value depends on number of data points)
Example
x data y data x * y x * x (x - c)2 (y – a – b x)2
N = 5,000 ∑ x = 22,372
x = 4,474 ∑ y = 22,057
y = 4,411 ∑ (x - x )2 = 12,830
3,180
x0 y0 y0+ Y 0- S
The cost per foot equation is used for the comparison of alternative equipments,
comparisons which are often called break-even calculations and are usually
EXAMPLES
C=
[1500 + 300 + 2500 + ((40 + 8 + 0.5) × (600 + 200 + 10))] = 72.6$ / ft
15 × 40
b) Calculate cost per foot if company use a bit costs $ 1000 more and
C=
[2500 + 300 + 4500 + ((46 + 8 + 0.5) × (600 + 200 + 10))] = 64.8$ / ft
17.25 × 46
Because interest is paid on savings, the value of money varies with time.
So the time value of money can be found by using the following formula.
n× q
r
F = P × 1 +
q
Find the value of $ 2000 after 10 years period if the rate of return or
n×q 10×3
r 0.25
F = P × 1 + = 2000 × 1 + = 22074$
q 3
EXAMPLE
Find the arte of return or interest rate if the future worth of the
present $ 1000 is $ 9000 after 15 years later and a) each year has one payment
n× q 15×1
r r
F = P × 1 + ⇒ 9000 = 1000 × 1 + ⇒ r = 16%
q 1
n× q 15× 2
r r
F = P × 1 + ⇒ 9000 = 1000 × 1 + ⇒ r = 15%
q 2
expected costs and the probability of their occurrence. The fundamental form
EV = Expected value $
EXAMPLE
Calculate the expected value of 4 inch and 5 inch DP by using given below
330 85
350 65
EV = (C1 × P1 ) + (C 2 × P2 )
EV4 = ((12000 300 )(850 24) × 0.15) + ((12000 330 )(850 24 ) × 0.85)
multiplier method can be applied in order to find the maximum and the minimum.
∂f ∂g ∂f ∂g
∂L ∂w − ∂w ∂L = 0
w = parameter to be determined
L = parameter to be determined
EXAMPLE
order to maximize the volume of the mud pit what should be the length, L and
width, w?
Objective equation f = 10 × w × L
∂f ∂g ∂f ∂g
Lagrange equation ∂L ∂w − ∂w ∂L = 0
∂f ∂f
Partial derivatives = 10w = 10 L
∂L ∂w
∂g ∂g
=2 =2
∂L ∂w
Width 2 w + 2 w = 160 ⇒ w = 40 ft
Maximum Volume V = 10 × w × L
V = 10 × 40 × 40
V = 16000 ft 3