CONSTRUCTION DEPARTMENT
ERECTION METHODOLOGY
Prepared by:
Rolando V. Santiago
Project-in-Charge
Noted by:
Cesar E. Romero
OIC – Operation
Approved By:
Alfred S. Tiu
President/General Manager
Cc/file
ERECTION METHODOLOGY: METRO GAISANO - BAY
INTRODUCTION
The purpose of this erection methodology is to provide written guidelines for the
Project In-Charge, Site Supervisors and Inspectors to implement the correct and safe
installation of structural members for the project METRO GAISANO – BAY.
Note:
Whenever required, this procedure shall be adjusted or updated based on the degree
of complexity of the project to be undertaken and / or instructed by the client or its
authorized representative(s) based on actual site condition.
A. Control.
B. Geometric Control
The method statement requires and allows provision for transferring the
surveying control stations up through the structure to areas allocated for
these purposes. Some local ground settlement may be anticipated
during the early stage of erection, possibly causing certain displacement
of the surveying stations established both inside and outside the
hoarding.
IV. BOLTING
A. General
1. Always store bolts under cover until they are needed and keep
them clean. Don’t abuse the bolts during handling and
installation.
2. Prior to final tightening, all connections shall be cleaned to bring
connecting members to close contract.
3. When tightening a connection, always work from the center to the
free edges.
4. Projecting ends of bolts shall not exceed five threads on visible
steel work unless it is specified on plan.
5. Install lock nuts on slip connections and nick threads.
V. FIELD WELDING
A. General
Shielded metal arc welding using low hydrogen electrodes for all site
welding works;
2. Welding procedures.
The welding procedures shall be in accordance with AWS D1.1-96.
A. GENERAL
The construction site office, storage area, warehouse and other facilities
required should be established to ensure safety and security of materials
and personnel.
A. GENERAL
1. Mobilization of the erection crew with the necessary equipment.
a. Prepare and install all necessary power lines from the nearest
point of the power supply to the assembly area.
b. Match marking and proper storage of members and component
parts of the structure to ensure proper assembly and
positioning when final assembly commences.
Fig. 1
b. Use template with punchmark on its center that follows every gridline from
x-axis and y-axis. (See Fig. 2)
Fig. 2
Fig. 3
Fig. 4
e. Fix the template for alignment in x-axis and y-axis. Check elevation of anchor
bolts.
f. Check for the verticality and final elevation of Anchor Bolts before pouring.
(See Fig. 5)
Fig. 5
Fig. 7
Fig. 8
Install the Girders and Beams for GL 6-7/A-B’ making it a closed box
structure. (See Fig. 9)
Fig. 9
ERECTION METHODOLOGY: METRO GAISANO - BAY
Install columns @ GL 5/A-B. Complete beams and girders. Install Columns for second
floor in GL 5-7/A-B’. (See Fig. 10)
Fig. 10
Fig. 11
Continue erection for the roof deck @ GL 5-7/A-B’. (See Fig. 12)
Fig. 12
ERECTION METHODOLOGY: METRO GAISANO - BAY
Install columns @ GL 1-4/A-B. Complete erection of beams and girders. (See Fig. 13)
Fig. 13
Continue erection of columns, beams and girders @ GL 1-7/C-D. (See Fig. 14)
Fig. 14
Continue erection of columns, beams and girders @ GL 1-7/D-F. (See Fig. 15)
ERECTION METHODOLOGY: METRO GAISANO - BAY
MODULE 4. ERECTION @ GL 1-7/F-H
Continue erection of columns, beams and girders @ GL 1-7/F-H. (See Fig. 16)
h. Re-touching of paints
i. Punch list