Detail Construction Schedule Shall be given before the commencement of construction activity. Page 1
500kV Muzaffargarh-Gatti Transmission Line Revision-1
Contract # MG-1 (Package-II) PROJECT TIME SCHEDULE
ID Task Name 2005 Start 2006
Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct
M E B M E B M E B M E B M E B M E B M E B M E B M E B M E B M E B
29 Geotech Investigation Complete Jul 5 '06 7/5
Detail Construction Schedule Shall be given before the commencement of construction activity. Page 2
500kV Muzaffargarh-Gatti Transmission Line Revision-1
Contract # MG-1 (Package-II) PROJECT TIME SCHEDULE
ID Task Name 2005 Start 2006
Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct
M E B M E B M E B M E B M E B M E B M E B M E B M E B M E B M E B
56 Earthing Material Jan 15 '06
57 Tower Stubs Jan 15 '06
58 Lattice Steel Tower Feb 4 '06
59 Conductor Feb 4 '06
60 Shield Wire (OGW) Feb 4 '06
61 Shield Wire (OPGW) Feb 4 '06
62 Hardware Feb 4 '06
63 Spacer Dampers Feb 4 '06
64 Telecommunication Equipt Mar 20 '06
65 Specific Goods Data Submission Complete Mar 26 '06 3/26
66 Specific Goods Data (Schedule-D) Approval Jan 22 '06
67 Earthing Material Jan 22 '06
68 Tower Stubs Jan 22 '06
69 Lattice Steel Tower Feb 11 '06
70 Conductor Feb 11 '06
71 Shield Wire (OGW) Feb 11 '06
72 Shield Wire (OPGW) Feb 11 '06
73 Hardware Feb 11 '06
74 Spacer Dampers Feb 11 '06
75 Telecommunication Equipt Mar 27 '06
76 Specific Goods Data Approval Complete Apr 2 '06 4/2
77 Material Orders/Procurement Jan 29 '06
Detail Construction Schedule Shall be given before the commencement of construction activity. Page 3
500kV Muzaffargarh-Gatti Transmission Line Revision-1
Contract # MG-1 (Package-II) PROJECT TIME SCHEDULE
ID Task Name 2005 Start 2006
Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct
M E B M E B M E B M E B M E B M E B M E B M E B M E B M E B M E B
88 Material Orders Complete May 24 '06 5/24
Detail Construction Schedule Shall be given before the commencement of construction activity. Page 4
500kV Muzaffargarh-Gatti Transmission Line Revision-1
Contract # MG-1 (Package-II) PROJECT TIME SCHEDULE
ID Task Name 2005 Start 2006
Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct
M E B M E B M E B M E B M E B M E B M E B M E B M E B M E B M E B
114 Conductor (Imported) Jun 3 '06
Detail Construction Schedule Shall be given before the commencement of construction activity. Page 5
500kV Muzaffargarh-Gatti Transmission Line Revision-1
Contract # MG-1 (Package-II) PROJECT TIME SCHEDULE
ID Task Name 2005 Start 2006
Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct
M E B M E B M E B M E B M E B M E B M E B M E B M E B M E B M E B
140 Lattice Steel Tower (Lot-1) Aug 12 '06
Detail Construction Schedule Shall be given before the commencement of construction activity. Page 6
500kV Muzaffargarh-Gatti Transmission Line Revision-1
Contract # MG-1 (Package-II) PROJECT TIME SCHEDULE
ID Task Name 2006 2007
Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct
B M E B M E B M E B M E B M E B M E B M E B M E B M E B M E B M E B M E B M
1 Contract Sign
2 Over All Project Completion Time
3 Mobilization
4 Project Office
5 Construction Office
6 Material Store
7 Site Camps
8 4/28
Mobilization Complete
9 Design & Engineering
10 Survey
11 Route Alignment
12 Route Alignment Approval
13 Detail Survey (2-Crews)
14 Detail Survey Approval
15 Tower Spotting
16 Tower Spotting Approval
17 Construction List
18 Construction List Approval
19 Survey Complete 6/21
20 Transposition Towers
21 Transposition Scheme Submission
22 Transposition Scheme Approval
23 4/23
Transposition Complete
24 Geotechnical Investigation
25 Field Drilling
26 Field Drilling for River Xing
27 Laboratory Testing
28 Geotechnical Report
Detail Construction Schedule Shall be given before the commencement of construction activity. Page 7
500kV Muzaffargarh-Gatti Transmission Line Revision-1
Contract # MG-1 (Package-II) PROJECT TIME SCHEDULE
ID Task Name 2006 2007
Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct
B M E B M E B M E B M E B M E B M E B M E B M E B M E B M E B M E B M E B M
29 7/5
Geotech Investigation Complete
30 Foundation Design
31 Selection of Foundation Types
32 Approval of Foundation Drawings
33 Selection of Pile Foundations
34 Approval of Pile Foundation Drawings
35 7/18
Foundation Design Complete
36 Steel Lattice Tower
37 Procure Tower Fab. Dwgs
38 Reproduction of Tower Fab. Dwgs
39 Approval of Tower Fab. Dwgs
40 ACD & Tower Signs Drawing Submission
41 ACD, Tower Signs Drawing Approval
42 3/25 Tower Design Complete
43 Overhead Line Material
44 Manufacturers Approval
45 Earthing Material
46 Tower Stubs
47 Lattice Steel Tower
48 Conductor
49 Shield Wire (OGW)
50 Shield Wire (OPGW)
51 Hardware
52 Spacer Dampers
53 Telecommunication Equipt
54 3/19 Manufacturer Approval Complete
55 Specific Goods Data (Schedule-D) Submission
Detail Construction Schedule Shall be given before the commencement of construction activity. Page 8
500kV Muzaffargarh-Gatti Transmission Line Revision-1
Contract # MG-1 (Package-II) PROJECT TIME SCHEDULE
ID Task Name 2006 2007
Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct
B M E B M E B M E B M E B M E B M E B M E B M E B M E B M E B M E B M E B M
56 Earthing Material
57 Tower Stubs
58 Lattice Steel Tower
59 Conductor
60 Shield Wire (OGW)
61 Shield Wire (OPGW)
62 Hardware
63 Spacer Dampers
64 Telecommunication Equipt
65 3/26 Specific Goods Data Submission Complete
66 Specific Goods Data (Schedule-D) Approval
67 Earthing Material
68 Tower Stubs
69 Lattice Steel Tower
70 Conductor
71 Shield Wire (OGW)
72 Shield Wire (OPGW)
73 Hardware
74 Spacer Dampers
75 Telecommunication Equipt
76 4/2 Specific Goods Data Approval Complete
77 Material Orders/Procurement
78 Earthing Material
79 Tower Stubs
80 Lattice Steel Tower
81 Conductor (Local & Off-Shore)
82 Shield Wire (OGW)
83 Shield Wire (OPGW)
84 Insulator
85 Hardware
86 Spacer Dampers
87 Telecommunication Equipment
Detail Construction Schedule Shall be given before the commencement of construction activity. Page 9
500kV Muzaffargarh-Gatti Transmission Line Revision-1
Contract # MG-1 (Package-II) PROJECT TIME SCHEDULE
ID Task Name 2006 2007
Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct
B M E B M E B M E B M E B M E B M E B M E B M E B M E B M E B M E B M E B M
88 5/24 Complete
Material Orders
89 Manufacturing
90 Earthing Material (Lot-1)
91 Earthing Material (Lot-2)
92 Tower Stubs (Lot-1)
93 Tower Stubs (Lot-2)
94 Lattice Steel Tower (Lot-1)
95 Lattice Steel Tower (Lot-2)
96 Lattice Steel Tower (Lot-3)
97 Conductor-Local (Lot-1)
98 Conductor-Local (Lot-2)
99 Conductor (Imported)
100 Shield Wire (OGW)
101 Shield Wire (OPGW)
102 Hardware
103 Spacer Dampers
104 Telecommunication Equipment
105 Manufacturing Complete 8/31
Detail Construction Schedule Shall be given before the commencement of construction activity. Page 10
500kV Muzaffargarh-Gatti Transmission Line Revision-1
Contract # MG-1 (Package-II) PROJECT TIME SCHEDULE
ID Task Name 2006 2007
Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct
B M E B M E B M E B M E B M E B M E B M E B M E B M E B M E B M E B M E B M
114 Conductor (Imported)
115 Shield Wire (OGW)
116 Shield Wire (OPGW)
117 Hardware
118 Spacer Dampers
119 Inspection/Testing Complete 10/15
Detail Construction Schedule Shall be given before the commencement of construction activity. Page 11
500kV Muzaffargarh-Gatti Transmission Line Revision-1
Contract # MG-1 (Package-II) PROJECT TIME SCHEDULE
ID Task Name 2006 2007
Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct
B M E B M E B M E B M E B M E B M E B M E B M E B M E B M E B M E B M E B M
140 Lattice Steel Tower (Lot-1)
141 Lattice Steel Tower (Lot-2)
142 Lattice Steel Tower (Lot-3)
143 Conductor-Local (Lot-1)
144 Conductor-Local (Lot-2)
145 Conductor (Imported)
146 Shield Wire (OGW)
147 Shield Wire (OPGW)
148 Insulator
149 Hardware
150 Spacer Damper
151 Telecommunication Equipment
152 Material Delivery at Site Complete 11/9
Detail Construction Schedule Shall be given before the commencement of construction activity. Page 12