You are on page 1of 12

500kV Muzaffargarh-Gatti Transmission Line Revision-1

Contract # MG-1 (Package-II) PROJECT TIME SCHEDULE


ID Task Name 2005 Start 2006
Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct
M E B M E B M E B M E B M E B M E B M E B M E B M E B M E B M E B
1 Contract Sign Nov 28 '05 11/28

2 Over All Project Completion Time Nov 28 '05


3 Mobilization Nov 28 '05

4 Project Office Nov 28 '05

5 Construction Office Dec 16 '05

6 Material Store Jan 15 '06

7 Site Camps Dec 16 '05

8 Mobilization Complete Apr 28 '06 4/28

9 Design & Engineering Nov 28 '05

10 Survey Nov 28 '05

11 Route Alignment Nov 28 '05

12 Route Alignment Approval Dec 30 '05

13 Detail Survey (2-Crews) Jan 12 '06

14 Detail Survey Approval Feb 24 '06

15 Tower Spotting Mar 3 '06

16 Tower Spotting Approval Mar 31 '06

17 Construction List Mar 31 '06

18 Construction List Approval Apr 28 '06

19 Survey Complete Jun 21 '06 6/21

20 Transposition Towers Apr 10 '06


21 Transposition Scheme Submission Apr 10 '06
22 Transposition Scheme Approval Apr 17 '06
23 Transposition Complete Apr 23 '06 4/23
24 Geotechnical Investigation Jan 27 '06

25 Field Drilling Jan 27 '06

26 Field Drilling for River Xing Feb 26 '06

27 Laboratory Testing Feb 11 '06

28 Geotechnical Report Jun 29 '06

Detail Construction Schedule Shall be given before the commencement of construction activity. Page 1
500kV Muzaffargarh-Gatti Transmission Line Revision-1
Contract # MG-1 (Package-II) PROJECT TIME SCHEDULE
ID Task Name 2005 Start 2006
Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct
M E B M E B M E B M E B M E B M E B M E B M E B M E B M E B M E B
29 Geotech Investigation Complete Jul 5 '06 7/5

30 Foundation Design Feb 26 '06

31 Selection of Foundation Types Feb 26 '06

32 Approval of Foundation Drawings Mar 5 '06

33 Selection of Pile Foundations May 15 '06

34 Approval of Pile Foundation Drawings May 22 '06

35 Foundation Design Complete Jul 18 '06 7/18

36 Steel Lattice Tower Nov 28 '05

37 Procure Tower Fab. Dwgs Nov 28 '05

38 Reproduction of Tower Fab. Dwgs Dec 13 '05

39 Approval of Tower Fab. Dwgs Jan 25 '06

40 ACD & Tower Signs Drawing Submission Mar 12 '06


41 ACD, Tower Signs Drawing Approval Mar 19 '06
42 Tower Design Complete Mar 25 '06 3/25

43 Overhead Line Material Dec 16 '05

44 Manufacturers Approval Dec 16 '05

45 Earthing Material Dec 16 '05

46 Tower Stubs Dec 16 '05

47 Lattice Steel Tower Dec 16 '05

48 Conductor Dec 16 '05

49 Shield Wire (OGW) Dec 16 '05

50 Shield Wire (OPGW) Dec 16 '05

51 Hardware Dec 16 '05

52 Spacer Dampers Dec 16 '05

53 Telecommunication Equipt Feb 4 '06

54 Manufacturer Approval Complete Mar 19 '06 3/19

55 Specific Goods Data (Schedule-D) Submission Jan 15 '06

Detail Construction Schedule Shall be given before the commencement of construction activity. Page 2
500kV Muzaffargarh-Gatti Transmission Line Revision-1
Contract # MG-1 (Package-II) PROJECT TIME SCHEDULE
ID Task Name 2005 Start 2006
Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct
M E B M E B M E B M E B M E B M E B M E B M E B M E B M E B M E B
56 Earthing Material Jan 15 '06
57 Tower Stubs Jan 15 '06
58 Lattice Steel Tower Feb 4 '06
59 Conductor Feb 4 '06
60 Shield Wire (OGW) Feb 4 '06
61 Shield Wire (OPGW) Feb 4 '06
62 Hardware Feb 4 '06
63 Spacer Dampers Feb 4 '06
64 Telecommunication Equipt Mar 20 '06
65 Specific Goods Data Submission Complete Mar 26 '06 3/26
66 Specific Goods Data (Schedule-D) Approval Jan 22 '06
67 Earthing Material Jan 22 '06
68 Tower Stubs Jan 22 '06
69 Lattice Steel Tower Feb 11 '06
70 Conductor Feb 11 '06
71 Shield Wire (OGW) Feb 11 '06
72 Shield Wire (OPGW) Feb 11 '06
73 Hardware Feb 11 '06
74 Spacer Dampers Feb 11 '06
75 Telecommunication Equipt Mar 27 '06
76 Specific Goods Data Approval Complete Apr 2 '06 4/2
77 Material Orders/Procurement Jan 29 '06

78 Earthing Material Jan 29 '06

79 Tower Stubs Jan 29 '06

80 Lattice Steel Tower Feb 18 '06

81 Conductor (Local & Off-Shore) Feb 18 '06

82 Shield Wire (OGW) Feb 18 '06

83 Shield Wire (OPGW) Feb 18 '06

84 Insulator Apr 25 '06

85 Hardware Feb 18 '06

86 Spacer Dampers Feb 18 '06

87 Telecommunication Equipment Apr 3 '06

Detail Construction Schedule Shall be given before the commencement of construction activity. Page 3
500kV Muzaffargarh-Gatti Transmission Line Revision-1
Contract # MG-1 (Package-II) PROJECT TIME SCHEDULE
ID Task Name 2005 Start 2006
Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct
M E B M E B M E B M E B M E B M E B M E B M E B M E B M E B M E B
88 Material Orders Complete May 24 '06 5/24

89 Manufacturing Feb 28 '06

90 Earthing Material (Lot-1) Feb 28 '06

91 Earthing Material (Lot-2) Mar 30 '06

92 Tower Stubs (Lot-1) Feb 28 '06

93 Tower Stubs (Lot-2) Mar 30 '06

94 Lattice Steel Tower (Lot-1) Apr 4 '06

95 Lattice Steel Tower (Lot-2) Apr 4 '06

96 Lattice Steel Tower (Lot-3) Apr 4 '06

97 Conductor-Local (Lot-1) Apr 4 '06

98 Conductor-Local (Lot-2) Jun 18 '06

99 Conductor (Imported) Apr 4 '06

100 Shield Wire (OGW) Apr 4 '06

101 Shield Wire (OPGW) Jun 3 '06

102 Hardware Apr 4 '06

103 Spacer Dampers Apr 4 '06

104 Telecommunication Equipment May 25 '06

105 Manufacturing Complete Aug 31 '06 8/31

106 Material Inspection/Testing Mar 30 '06

107 Stubs (Lot-1) Mar 30 '06

108 Stubs (Lot-2) Apr 29 '06

109 Lattice Steel Tower (Lot-1) Jul 3 '06

110 Lattice Steel Tower (Lot-2) Jul 3 '06

111 Lattice Steel Tower (Lot-3) Sep 1 '06

112 Conductor-Local (Lot-1) Jun 18 '06

113 Conductor-Local (Lot-2) Sep 1 '06

Detail Construction Schedule Shall be given before the commencement of construction activity. Page 4
500kV Muzaffargarh-Gatti Transmission Line Revision-1
Contract # MG-1 (Package-II) PROJECT TIME SCHEDULE
ID Task Name 2005 Start 2006
Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct
M E B M E B M E B M E B M E B M E B M E B M E B M E B M E B M E B
114 Conductor (Imported) Jun 3 '06

115 Shield Wire (OGW) Jul 3 '06

116 Shield Wire (OPGW) Sep 1 '06

117 Hardware Jul 3 '06

118 Spacer Dampers Jul 3 '06

119 Inspection/Testing Complete Oct 15 '06 1

120 Material Shipping (Imported) Mar 30 '06

121 Earthing Material (Lot-1) Mar 30 '06

122 Earthing Material (Lot-2) Apr 29 '06

123 Stubs (Lot-1) Apr 9 '06

124 Stubs (Lot-2) May 9 '06

125 Lattice Steel Tower (Lot-1) Jul 13 '06

126 Lattice Steel Tower (Lot-2) Jul 13 '06

127 Lattice Steel Tower (Lot-3) Sep 11 '06

128 Conductor (Imported) Jul 18 '06

129 Shield Wire (OGW) Aug 17 '06

130 Shield Wire (OPGW) Oct 16 '06

131 Hardware Aug 17 '06

132 Spacer Dampers Aug 17 '06

133 Telecommunication Equipment May 25 '06

134 Material Shipping Complete Nov 14 '06

135 Custom Clearance/Site Delivery Apr 29 '06

136 Earthing Material (Lot-1) Apr 29 '06

137 Earthing Material (Lot-2) May 29 '06

138 Stubs (Lot-1) May 9 '06

139 Stubs (Lot-2) Jun 8 '06

Detail Construction Schedule Shall be given before the commencement of construction activity. Page 5
500kV Muzaffargarh-Gatti Transmission Line Revision-1
Contract # MG-1 (Package-II) PROJECT TIME SCHEDULE
ID Task Name 2005 Start 2006
Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct
M E B M E B M E B M E B M E B M E B M E B M E B M E B M E B M E B
140 Lattice Steel Tower (Lot-1) Aug 12 '06

141 Lattice Steel Tower (Lot-2) Aug 12 '06

142 Lattice Steel Tower (Lot-3) Oct 11 '06

143 Conductor-Local (Lot-1) Jul 18 '06

144 Conductor-Local (Lot-2) Oct 1 '06

145 Conductor (Imported) Aug 17 '06

146 Shield Wire (OGW) Sep 16 '06

147 Shield Wire (OPGW) Sep 16 '06

148 Insulator May 1 '06

149 Hardware Sep 16 '06

150 Spacer Damper Sep 16 '06

151 Telecommunication Equipment Jun 24 '06

152 Material Delivery at Site Complete Nov 9 '06

153 Construction of Overhead Line Jun 8 '06

154 Foundations (2-Crews) Jun 8 '06

155 Foundations (3-Crews) Jul 8 '06

156 Pile Foundations (2-Crews) Jul 12 '06

157 River Crossing Pile Foundations (1Crew) Sep 5 '06

158 Pile Caps and Beams (2-Crews) Sep 10 '06

159 Tower Erection (3-Crews) Sep 11 '06

160 Conductor Stringing (2-Crews) Oct 26 '06

161 Supply of ACD/Tower Signs Apr 4 '07


162 Installation of ACD/Tower Signs Jul 3 '07
163 Test & Commission Sep 1 '07

164 Project Complete Sep 18 '07

Detail Construction Schedule Shall be given before the commencement of construction activity. Page 6
500kV Muzaffargarh-Gatti Transmission Line Revision-1
Contract # MG-1 (Package-II) PROJECT TIME SCHEDULE
ID Task Name 2006 2007
Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct
B M E B M E B M E B M E B M E B M E B M E B M E B M E B M E B M E B M E B M
1 Contract Sign
2 Over All Project Completion Time
3 Mobilization
4 Project Office
5 Construction Office
6 Material Store
7 Site Camps
8 4/28
Mobilization Complete
9 Design & Engineering
10 Survey
11 Route Alignment
12 Route Alignment Approval
13 Detail Survey (2-Crews)
14 Detail Survey Approval
15 Tower Spotting
16 Tower Spotting Approval
17 Construction List
18 Construction List Approval
19 Survey Complete 6/21
20 Transposition Towers
21 Transposition Scheme Submission
22 Transposition Scheme Approval
23 4/23
Transposition Complete
24 Geotechnical Investigation
25 Field Drilling
26 Field Drilling for River Xing
27 Laboratory Testing
28 Geotechnical Report
Detail Construction Schedule Shall be given before the commencement of construction activity. Page 7
500kV Muzaffargarh-Gatti Transmission Line Revision-1
Contract # MG-1 (Package-II) PROJECT TIME SCHEDULE
ID Task Name 2006 2007
Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct
B M E B M E B M E B M E B M E B M E B M E B M E B M E B M E B M E B M E B M
29 7/5
Geotech Investigation Complete
30 Foundation Design
31 Selection of Foundation Types
32 Approval of Foundation Drawings
33 Selection of Pile Foundations
34 Approval of Pile Foundation Drawings
35 7/18
Foundation Design Complete
36 Steel Lattice Tower
37 Procure Tower Fab. Dwgs
38 Reproduction of Tower Fab. Dwgs
39 Approval of Tower Fab. Dwgs
40 ACD & Tower Signs Drawing Submission
41 ACD, Tower Signs Drawing Approval
42 3/25 Tower Design Complete
43 Overhead Line Material
44 Manufacturers Approval
45 Earthing Material
46 Tower Stubs
47 Lattice Steel Tower
48 Conductor
49 Shield Wire (OGW)
50 Shield Wire (OPGW)
51 Hardware
52 Spacer Dampers
53 Telecommunication Equipt
54 3/19 Manufacturer Approval Complete
55 Specific Goods Data (Schedule-D) Submission

Detail Construction Schedule Shall be given before the commencement of construction activity. Page 8
500kV Muzaffargarh-Gatti Transmission Line Revision-1
Contract # MG-1 (Package-II) PROJECT TIME SCHEDULE
ID Task Name 2006 2007
Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct
B M E B M E B M E B M E B M E B M E B M E B M E B M E B M E B M E B M E B M
56 Earthing Material
57 Tower Stubs
58 Lattice Steel Tower
59 Conductor
60 Shield Wire (OGW)
61 Shield Wire (OPGW)
62 Hardware
63 Spacer Dampers
64 Telecommunication Equipt
65 3/26 Specific Goods Data Submission Complete
66 Specific Goods Data (Schedule-D) Approval
67 Earthing Material
68 Tower Stubs
69 Lattice Steel Tower
70 Conductor
71 Shield Wire (OGW)
72 Shield Wire (OPGW)
73 Hardware
74 Spacer Dampers
75 Telecommunication Equipt
76 4/2 Specific Goods Data Approval Complete
77 Material Orders/Procurement
78 Earthing Material
79 Tower Stubs
80 Lattice Steel Tower
81 Conductor (Local & Off-Shore)
82 Shield Wire (OGW)
83 Shield Wire (OPGW)
84 Insulator
85 Hardware
86 Spacer Dampers
87 Telecommunication Equipment

Detail Construction Schedule Shall be given before the commencement of construction activity. Page 9
500kV Muzaffargarh-Gatti Transmission Line Revision-1
Contract # MG-1 (Package-II) PROJECT TIME SCHEDULE
ID Task Name 2006 2007
Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct
B M E B M E B M E B M E B M E B M E B M E B M E B M E B M E B M E B M E B M
88 5/24 Complete
Material Orders
89 Manufacturing
90 Earthing Material (Lot-1)
91 Earthing Material (Lot-2)
92 Tower Stubs (Lot-1)
93 Tower Stubs (Lot-2)
94 Lattice Steel Tower (Lot-1)
95 Lattice Steel Tower (Lot-2)
96 Lattice Steel Tower (Lot-3)
97 Conductor-Local (Lot-1)
98 Conductor-Local (Lot-2)
99 Conductor (Imported)
100 Shield Wire (OGW)
101 Shield Wire (OPGW)
102 Hardware
103 Spacer Dampers
104 Telecommunication Equipment
105 Manufacturing Complete 8/31

106 Material Inspection/Testing


107 Stubs (Lot-1)
108 Stubs (Lot-2)
109 Lattice Steel Tower (Lot-1)
110 Lattice Steel Tower (Lot-2)
111 Lattice Steel Tower (Lot-3)
112 Conductor-Local (Lot-1)
113 Conductor-Local (Lot-2)

Detail Construction Schedule Shall be given before the commencement of construction activity. Page 10
500kV Muzaffargarh-Gatti Transmission Line Revision-1
Contract # MG-1 (Package-II) PROJECT TIME SCHEDULE
ID Task Name 2006 2007
Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct
B M E B M E B M E B M E B M E B M E B M E B M E B M E B M E B M E B M E B M
114 Conductor (Imported)
115 Shield Wire (OGW)
116 Shield Wire (OPGW)
117 Hardware
118 Spacer Dampers
119 Inspection/Testing Complete 10/15

120 Material Shipping (Imported)


121 Earthing Material (Lot-1)
122 Earthing Material (Lot-2)
123 Stubs (Lot-1)
124 Stubs (Lot-2)
125 Lattice Steel Tower (Lot-1)
126 Lattice Steel Tower (Lot-2)
127 Lattice Steel Tower (Lot-3)
128 Conductor (Imported)
129 Shield Wire (OGW)
130 Shield Wire (OPGW)
131 Hardware
132 Spacer Dampers
133 Telecommunication Equipment
134 Material Shipping Complete 11/14

135 Custom Clearance/Site Delivery


136 Earthing Material (Lot-1)
137 Earthing Material (Lot-2)
138 Stubs (Lot-1)
139 Stubs (Lot-2)

Detail Construction Schedule Shall be given before the commencement of construction activity. Page 11
500kV Muzaffargarh-Gatti Transmission Line Revision-1
Contract # MG-1 (Package-II) PROJECT TIME SCHEDULE
ID Task Name 2006 2007
Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct
B M E B M E B M E B M E B M E B M E B M E B M E B M E B M E B M E B M E B M
140 Lattice Steel Tower (Lot-1)
141 Lattice Steel Tower (Lot-2)
142 Lattice Steel Tower (Lot-3)
143 Conductor-Local (Lot-1)
144 Conductor-Local (Lot-2)
145 Conductor (Imported)
146 Shield Wire (OGW)
147 Shield Wire (OPGW)
148 Insulator
149 Hardware
150 Spacer Damper
151 Telecommunication Equipment
152 Material Delivery at Site Complete 11/9

153 Construction of Overhead Line


154 Foundations (2-Crews)
155 Foundations (3-Crews)
156 Pile Foundations (2-Crews)
157 River Crossing Pile Foundations (1Crew)
158 Pile Caps and Beams (2-Crews)
159 Tower Erection (3-Crews)
160 Conductor Stringing (2-Crews)
161 Supply of ACD/Tower Signs
162 Installation of ACD/Tower Signs
163 Test & Commission
164 Project Complete 9/18

Detail Construction Schedule Shall be given before the commencement of construction activity. Page 12