PSM - Plan Schedule Management CS - Control Schedule
DA - Define Actvites
A = Actvity(ies)
SA - Sequence Actvites
EAD - Est. Actvity Duratons
SCH - DS - Develop Schedule 6
Schedule Management
3 1
PCM - Plan Cost Management CC - Control Costs
COS - EC - Estmate Costs 4
Cost Management DB - Determine Budget
1 1 1
PQM - Plan Quality Management MQ - Manage Quaility CQ - Control Quality
QUA - (Process Focus) (Product Focus)
Quality Management 3
2 3 1
PRM - Plan Resource Management AR - Aquire Resources CR - Control Resources
RES - EAR - Est. Actvity Resources DT - Develop Team
Resource Management 6
MT - Manage Team
1 1 1
PCM - Plan Communicatons Management MC - Manage Communicatons MC - Monitor Communicatons
COM -
Communication Management 3
5 1 1
PRM - Plan Risk Management IRP - Implement Risk Responses MR - Monitor Risks
IR - Identfy Risk
P = Perform; Plan
PQRA - Perform Qualitatve Risk Analysis
PQRA - Perform Quanttatve Risk Analysis
R = Risk
RIS - PRR - Plan Risk Responses 7
Risk Management
1 1 1
PRO - PPM - Plan Procurement Management CP - Conduct Procurements CP - Control 3
Procurement Management Procurements
1 1 1 1
STM - IS: Identfy PSE - Plan Stakeholder Engagement MSE - Manage Stakeholder Engagement MSE - Monitor Stakeholder Engagement 4
Stakeholder Management Statekeholders
Total Processes 2 24 10 12 1 49
Plan Scope Management Collect Requirements Define Scope Create WBS Validate Scope Control Scope
- PSM - PL - CR - PL - DS - PL - CW - PL - VS - MC - CS - MC
Inputs: Inputs: Inputs: Inputs: Inputs: Inputs:
.1 Project Management Plan(PM Plan) .1 Project Management Plan(PM Plan) .1 Project Management Plan(PM Plan) .1 Project Management Plan(PM Plan) .1 Project Management Plan(PM Plan) .1 Project Management Plan(PM Plan)
a. Quality Management Plan a. Scope Management Plan a. Scope Management Plan a. Scope Management Plan a. Scope Management Plan a. Scope Management Plan
b. Project Life Cycle Descripton b. Requirements Management Plan .2 Project Charter .2 Project Documents b. Requirements Management Plan b. Requirements Management Plan
c. Development Approach c. Stakeholder Engagement Plan .3 Project Documents a. Project Scope Statement c. Scope Baseline c. Scope Baseline
.2 Project Charter .2 Project Documents a. Assumpton Log b. Requirements Documentaton .2 Project Documents d. Change Management Plan
.3 Enterprise Environmental Factors (EEF) a. Assumpton Log b. Risk Register .3 Enterprise Environmental Factors (EEF) a. Lessons Learned Register e. Confirguraton Management Plan
.4 Organizatonal Process Assets(OPA) b. Lessons Learned Register c. Requirements Documentaton .4 Organizatonal Process Assets(OPA) b. Quality Reports f. Performance Measurement Baseline
c. Stakeholder Register .4 Enterprise Environmental Factors (EEF) c. Requirements Documentaton .2 Project Documents
.3 Project Charter .5 Organizatonal Process Assets(OPA) d. Requirements Tracebility Matrix a. Lessons Learned Register
.4 Business Documents .3 Work Performance Data b. Requirements Documentaton
a. Business Case .4 Verified Deliverables c. Requirements Tracebility Matrix
.5 Agreements .3 Work Performance Data
.6 Enterprise Environmental Factors (EEF) .4 Organizatonal Process Assets(OPA)
.7 Organizatonal Process Assets(OPA)
6 Processes
Scope
Tools: Tools: Tools: Tools: Tools: Tools:
.1 Expert Judgment .1 Expert Judgment .1 Expert Judgment .1 Expert Judgment .1 Inspecton .1 Data Analysis
.2 Data Analysis .2 Data Gathering .2 Decision Making .2 Decompositon .2 Decision Making a. Variance Analysis
a. Alternatves Analysis a. Brainstorming a. Multcriteria Decision Analysis a. Votng b. Trend Analysis
.3 Meetngs b. Interviews .3 Data Analysis
c. Focus Groups a. Alternatves Analysis
d. Questonnaires and Surveys .4 Interpersonnal and Team Skills
e. Benchmarking a. Facilitaton
.3 Decision Making .5 Product Analysis
a. Votng
b. Multcriteria Decision Analysis
6 Processes
Scope
a. Votng
Cost
Plan Resource Management Estimate Activities Resources Acquire Resources Develop Project Team Manage Project Team Control Resources
- PRM - PL - EAR - PL - AR - EX - DPT - EX - MPT - EX - CR - MC
Inputs: Inputs: Inputs: Inputs: Inputs: Inputs:
.1 Project Management Plan(PM Plan) .1 Project Management Plan(PM Plan) .1 Project Management Plan(PM Plan) .1 Project Management Plan(PM Plan) .1 Project Management Plan(PM Plan) .1 Project Management Plan(PM Plan)
a. Quality Management Plan a. Resource Management Plan a. Resource Management Plan a. Resource Management Plan a. Resource Management Plan a. Resource Management Plan
b. Scope Baseline b. Scope Baseline b. Procurement Management Plan .2 Project Documents .2 Project Documents .2 Project Documents
.2 Project Charter .2 Project Documents .2 Project Documents a. Lessons Learned Register a. Lessons Learned Register a. Lessons Learned Register
.3 Project Documents a. Actvity List a. Project Schedule b. Project Schedule b. Issue Log b. Issue Log
a. Project Schedule b. Actvity Attributes b. Resource Requirements c. Resource Calendars c. Project Team Assignments c. Physical Resource Assignments
b. Requirements Documentaton c. Assumpton Log c. Resource Calendars d. Project Team Assignments d. Team Charter d. Project Schedule
c. Risk Register d. Cost Estmates d. Stakeholder Register e. Team Charter .3 Enterprise Environmental Factors (EEF) e. Resource Breakdown Structure
d. Stakeholder Register e. Resource Calendars .3 Enterprise Environmental Factors (EEF) .3 Enterprise Environmental Factors (EEF) .4 Organizatonal Process Assets(OPA) f. Resource Requirements
.4 Enterprise Environmental Factors (EEF) f. Risk Register .4 Organizatonal Process Assets(OPA) .4 Organizatonal Process Assets(OPA) .5 Work Performance Reports g. Risk Register
.5 Organizatonal Process Assets(OPA) .3 Enterprise Environmental Factors (EEF) .6 Team Performance Assessments .3 Work Performance Data
.4 Organizatonal Process Assets(OPA) .4 Organizatonal Process Assets(OPA)
.5 Agreements
.4 Organizatonal Theory .7 Data Analysis e. Team Building d. Emotonal Intelligence .4 Data Analysis
a. Alternatves Analysis .3 Recogniton and Rewards e. Leadership a. Alternatves Analysis
.4 Virtual Teams b. Cost Benefit Analysis
.5 Training c. Performance Reviews
.6 Individual and Team Assessments d. Trend Analysis
.7 Meetngs
.8 Communicaton Technology
Plan Risk Management Identify Risk Perform Qualitative Risk Analysis Perform Quantitative Risk Analysis Plan Risk Responses Implement Risk Responses Monitor Risks
- PRM - PL - IR - PL - PQlRA - PL - PQnRA - PL - PRR - PL - IRR - EX - MR - MC
Inputs: Inputs: Inputs: Inputs: Inputs: Inputs: Inputs:
.1 Project Management Plan(PM Plan) .1 Project Management Plan(PM Plan) .1 Project Management Plan(PM Plan) .1 Project Management Plan(PM Plan) .1 Project Management Plan(PM Plan) .1 Project Management Plan(PM Plan) .1 Project Management Plan(PM Plan)
a. All Components a. Resource Management Plan a. Risk Management Plan a. Risk Management Plan a. Risk Management Plan a. Risk Management Plan a. Risk Management Plan
.2 Project Charter b. Requirements Management Plan .2 Project Documents b. Scope Baseline b. Resource Management Plan .2 Project Documents .2 Project Documents
.3 Project Documents c. Schedule Management Plan a. Assumpton Log c. Schedule Baseline c. Cost Baseline a. Lessons Learned Register a. Lessons Learned Register
a. Stakeholder Register d. Cost Management Plan b. Stakeholder Register d. Cost Baseline .2 Project Documents b. Risk Register b. Risk Register
.4 Enterprise Environmental Factors (EEF) e. Quality Management Plan c. Risk Register .2 Project Documents a. Lessons Learned Register c. Risk Report c. Risk Report
.5 Organizatonal Process Assets(OPA) f. Risk Management Plan .3 Enterprise Environmental Factors (EEF) a. Assumpton Log b. Project Schedule .3 Organizatonal Process Assets(OPA) d. Issue Log
g. Scope Baseline .4 Organizatonal Process Assets(OPA) b. Basis of Estmates c. Project Team Assignments .3 Work Performance Data
h. Schedule Baseline c. Cost Estmates d. Risk Register .5 Work Performance Reports
i. Cost Baseline d. Risk Register e. Resource Calendars
.2 Agreements e. Milestone List f. Stakeholder Register
.3 Project Documents f. Costs Forecasts g. Risk Report
a. Assumpton Log g. Resource Requirements .3 Enterprise Environmental Factors (EEF)
b. Stakeholder Register h. Duraton Estmates .4 Organizatonal Process Assets(OPA)
c. Cost Estmates i. Risk Report
d. Lessons Learned Register j. Schedule Forecasts
e. Issue Log .3 Enterprise Environmental Factors (EEF)
f. Requirements Documentaton .4 Organizatonal Process Assets(OPA)
g. Resource Requirements
h. Duraton Estmates
.4 Enterprise Environmental Factors (EEF)
.5 Organizatonal Process Assets(OPA)
.6 Procurement Documentaton
Identify Stakeholders Plan Stakeholder Engagement Manage Stakeholder Engagement Monitor Stakeholder Engagement
- IS - IN - PSM - PL - MSE - EX - MSEN - MC
er
Inputs: Inputs: Inputs: Inputs:
.1 Project Management Plan(PM Plan) .1 Project Management Plan(PM Plan) .1 Project Management Plan(PM Plan) .1 Project Management Plan(PM Plan)
a. Communicaton Management Plan a. Communicatons Management Plan a. Communicatons Management Plan a. Communicatons Management Plan
b. Stakeholder Engagement Plan b. Resource Management Plan b. Stakeholder Engagement Plan b. Stakeholder Engagement Plan
.2 Project Charter c. Risk Management Plan c. Risk Management Plan c. Resource Management Plan
.3 Project Documents .2 Project Charter d. Change Management Plan .2 Work Performance Data
a. Change Log .3 Project Documents .2 Project Documents .3 Project Documents
b. Issue Log a. Change Log a. Change Log a. Project Communicatons
c. Requirements Documentaton b. Issue Log b. Issue Log b. Issue Log
.4 Organizatonal Process Assets(OPA) c. Assumpton Log c. Lessons Learned Register c. Lessons Learned Register
.5 Business Documents d. Project Schedule d. Stakeholder Register d. Stakeholder Register
a. Business Case e. Risk Register .3 Organizatonal Process Assets(OPA) e. Risk Register
b. Benefits Management Plan f. Stakeholder Register .4 Enterprise Environmental Factors .4 Organizatonal Process Assets(OPA)
.6 Agreements .4 Organizatonal Process Assets(OPA) .5 Enterprise Environmental Factors
.7 Enterprise Environmental Factors .5 Agreements
.6 Enterprise Environmental Factors
varun.anand@eduhubspot.com
services@eduhubspot.com
Varun Anand, PMP
+1-833-338-7768 Project Management Institute, A Guide to the Project Management Body of Knowledge,
www.eduhubspot.com (PMBOK® Guide) – Sixth Edition, Project Management Institute Inc., 2013, Table 4-1,
Page 89
varun.anand@eduhubspot.com
services@eduhubspot.com Materials in this class are based on the A Guide to the Proje
Sixth Edition, Project Management Institute Inc., 2017
ment Body of Knowledge, Project Management Institute, A Guide to the Project Management Body of Knowledge, Project Management Institute, A Guide
te Inc., 2013, Table 4-1, (PMBOK® Guide) – Sixth Edition, Project Management Institute Inc., 2013, Table 5-1, (PMBOK® Guide) – Sixth Edition, Proj
Page 155 1
Cost Eastimations
CPI = EV / AC CV = 0 AS OnS BS
Cost
SPI = EV / PV CPI = 0 OnB OnB OnB
TCPI = (BAC - EV) / (BAC - AC) CV < 0 AS OnS BS
TCPIE = (BAC - EV) / (EAC - AC) CPI < 1 OvB OvB OB
Buyer-Seller Risk