You are on page 1of 6

Energy efficiency in steam and

condensate savings

Mr Lauri Suomalainen
Senior Consultant, Energy Efficiency in Industry
Motiva Oy
P.O. Box 489 (Urho Kekkosen katu 4–6 A)
FI-00101 Helsinki
Finland
lauri.suomalainen@motiva.fi

Ms Hille Hyytiä
Head of Unit, Energy Efficiency in Industry
Motiva Oy
P.O. Box 489 (Urho Kekkosen katu 4–6 A)
FI-00101 Helsinki
Finland
hille.hyytia@motiva.fi

Keywords
energy analysis, monitoring, industrial steam systems, indus- for experts on how to improve energy efficiency in steam and
trial energy saving, condensate system, maintenance condensate pipelines.

Abstract Introduction
In our country industry has long experience in co-operating The energy-intensive industry uses large quantities of steam,
in energy efficiency issues. Industrial steam and condensate and it is of utmost importance that all parts of the system work
system project is one of such programmes. The purpose of this efficiently. Steam and condensate pipelines between the steam
industrial steam and condensate pipeline system study was generation plant and processes using steam are often neglected.
to learn what can be done in the plant to improve energy ef- People working at a steam generation plant work to produce
ficiency and how to spread the results and auditing methods steam as efficiently as possible. People working in the produc-
to other industrial plants. Only the distribution of the steam tion lines want to ensure the quality and quantity of the proc-
and condensate return system was studied. The results from esses. Both of these parties are seldom interested in steam and
the study showed that much can be achieved even with simple condensate pipelines and how they are working.
and low cost actions. Representatives of the energy-intensive industry in Fin-
A case study was carried out in a paper mill with two paper land, the Aalto University, the Ministry of Employment and
machines. It revealed several encouraging findings. The results the Economy, leading equipment suppliers of steam in Fin-
affected not only the steam and condensate pipelines, but the land and Motiva Oy established a project group and drew up a
whole steam system. The purpose was not only to stop leak- project plan on how to improve the energy-efficiency of steam
ages, but also to present good maintenance and installation and condensate pipelines. A consultant company was selected
practices. The saving potential found was 1.9 % of the steam to carry out most of the field work and to draw up the audit
consumption of the plant with payback time of approximately guide.
0.4 year. In energy costs, this means a saving of some 2.4 % and The most important goal of the project was to find how to
an approximately 3 % reduction of CO2 emissions. achieve savings in steam and condensate systems in enterprises
As a result of the study a report was published. The report has and to improve their performance. Motiva had previously esti-
multiple parts and it deals with different aspects of steam and mated that the saving potential in the Finnish industry was in
condensate pipeline energy-efficiency and how to improve it. the region of 1.9 TWh/year, which equals to 3 % of the use of
In addition, a separate measurement guide was also pre- steam in Finnish industrial plants.
pared. This guide has two targets: a) How to measure and avoid The second goal was to find out, collect and develop infor-
pitfalls, and b) How monitoring should be done. mation and knowledge of industrial steam and condensate sys-
There are many basic issues described in the report and the tems and to spread the information for the benefit of industrial
measurement guide, which also include useful reading material plants.

ECEEE 2012 SUMMER STUDY on Energy efficiency in industry  617


4-142-12 Suomalainen, Hyytiä 4. UNDERTAKING HIGH IMPACT ACTIONS: TECHNOLOGY AND …

Case study Steam is used in a paper machine and to heat up process


A typical paper mill was selected as the pilot plant for several water, ventilation air and the buildings. The average total power
reasons. The mill had two paper machines and all the usual of steam by the paper machine was approximately 56 MW. Low
departments and heat consumption sections of a paper mill. pressure steam (2.2 bar) was the normal back pressure steam
At the site, there were low and middle pressure pipelines and of the turbine. Middle pressure steam (12 bar) was taken from
the turbines’ tap-off. There was some middle pressure usage in
respective condensate pipe lines, and therefore it was possible
some +places due to the location of an instrument that needed
to study every relevant aspect. Steam for the plant and for the
low pressure steam.
backpressure turbine for electricity generation was produced in
Condensate from the paper machine was recovered and
a steam power plant, which was not included in the audit. The
gathered in a tank; the condensate was pumped back to the
production of the paper machine that was on the consump-
power station’s main condensate tank. About 80 % of the con-
tion side of the steam lines totalled 300,000 t/year of printing
densate was returned to the paper mill (Figure 2).
paper. Some figures of the steam demand in the paper plant are
Maintenance was carried out by an outside company. Moni-
presented in Table 1.
toring of the steam and condensate during operating hours was
The boundary line of the audit in the production side was the
performed by the company itself. There was no regular main-
main steam manifold and the main condensate tank. On the
tenance programme. Faults were repaired as and when they
consumption side, the boundary line was the main steam valve
occurred.
of the paper machine. The steam and condensate systems of the All steam and condensate measurements from every paper
paper machine were not included in the audit. machine were connected to process automation. Monthly con-
sumption of heat and electricity was reported to the people in
Steam and condensate systems charge of paper production. The energy group of the mill had a
The power plant produces steam and electricity only to the pa- meeting every 3 months to review energy efficiency and to give
per mill. Generation of steam at the power station was quite instructions on how to improve operations.
steady throughout the year with the exception of two occasions
(holiday, maintenance). Average use of middle pressure steam Field studies
amounted to 10 MW and low pressure steam 70 MW. The dura- The field studies were carried out by experts of the steam equip-
tion curve is steady (Figure 1). This made it easy to estimate the ment suppliers. More than 120 steam traps were studied. The
losses and savings in a reliable and accurate way. methods used were surface temperature measurements, use

Table 1. Power and consumption of steam at the paper mill.

Element Power, MW Consumption, GWh/year


Total steam in the paper plant 80 700
- low pressure steam 70 600
- middle pressure steam 10 100
Paper machine 56 490
- low pressure steam 49 430
- middle pressure steam 7 60

Figure 1. Steam consumption of the paper mill over a year.

618  ECEEE 2012 SUMMER STUDY on Energy efficiency in industry


4. UNDERTAKING HIGH IMPACT ACTIONS: TECHNOLOGY AND … 4-142-12 Suomalainen, Hyytiä

Figure 2. Distribution of the condensate in the paper machine.

Table 2. Results of the steam trap studies.

Number of Percentage of the


Observation faults steam traps studied, %
Condensate to waste 41 34
Inadequate installation 52 43
Steam trap not working properly 22 18
Wrong steam trap type 31 26

   

Figure 3. A thermal and a normal picture of a steam trap.

of ultrasound devices and thermal cameras, and also separate ing of the steam trap. The bypass valve should be installed so
tests to identify the status of each steam trap. The experts also that the dirt builds up in front of it and not in the steam trap.
estimated if the steam trap used was of the appropriate type for In the best case, dirt is led into a drain so that it does not cause
that specific place and purpose. further problems in the pipeline.
Thermal cameras give very good and accurate readings when During the study, experts found several bypass valves that
used in the appropriate way. The use of such cameras provides were open, as well as broken steam traps. They also found leaks
good evidence of the steam trap’s condition. In thermal pic- in the lines and discovered that process condensate had been
tures, important temperature readings can be pointed out. It is wasted. The big problem with even a small leak is that it will
also a rather quick way to obtain reliable results. accrue high costs when the running hours are long, such as
Great attention was paid to faults in installations. It is impor- 8,000 h/year. Every leak and fault should be repaired as soon
tant that dirt in the pipeline does not disturb proper function- as possible.

ECEEE 2012 SUMMER STUDY on Energy efficiency in industry  619


4-142-12 Suomalainen, Hyytiä 4. UNDERTAKING HIGH IMPACT ACTIONS: TECHNOLOGY AND …

Bad Better Best

Figure 4. An example of the installation of steam traps.

Table 3. Faults in the condensate pipelines.

Steam leaks kg/h Recovered Wasted


Bypass valve open (15 pcs) 1,050 100 % 0%
Broken steam trap (22 pcs) 300 40 % 60 %
Leakage in the line 165 0% 100 %
Process condensate wasted 720 0% 100 %

Other observations level. No savings were found in insulation and no major faults
In addition to steam and condensate observations, the audi- were discovered.
tors noticed several deficiencies in energy efficiency that should Middle-pressure steam should be changed to low-pressure
be improved. For example, in the middle pressure steam line, steam as this would make it possible to increase the produc-
four measurements need to be added for comprehensive energy tion of electricity by 3.7 GWh/year and achieve fuel savings of
balance measurement. There was also unnecessary use of mid- 1.8 GWh/year.
dle pressure steam that could be substituted with low pressure
steam. The error in the steam balance was in accordance with
the findings of the field work.
Results of the case study
In the low-pressure network, three more steam meters need The case study was carried out in a typical paper mill with
to be added for a comprehensive steam energy balance. Several backpressure electricity production. The saving potential found
faults in the measurements were found during the field work. was 1.9 % of the steam consumption with approximate payback
The error in the steam balance was also in accordance with the time of 0.4 a. As for make-up water for the steam system, the
findings of the field work. savings were 6.3 %. In the power plant, electricity production
The average return rate of the condensate was over 80  %. can be increased by 970 MWh/year, which means a 0.8 % in-
There is some uncertainty as during the summer the return crease in production. If emission were included, the total sav-
rate of the condensate is smaller than the lower limit of the ings would be even greater.
condensate flow meter. The study revealed several encouraging findings. The results
affected not only the steam and condensate pipelines, but the
Efficiency measures entire steam system. The purpose was not only to stop leaks,
The most important efficiency measures found in the steam but also to present good maintenance and installation practices.
and condensate pipelines were closing the bypass valves that The conclusions found were in some cases contradictory. For
were found open and repairing the steam traps that were bro- example, steam production, steam consumption and mainte-
ken or leaking. These represent about 80 % of the findings in nance may often be represented by three different companies.
the heat energy saving potential. In some areas that were in- There may be differences in how problems should be dealt with
spected, no relevant savings were found, for example, the use of and solved.
flash steam, pressure level or losses in the steam and condensate The proposed saving measures can be contradictory for dif-
pipelines and pipe insulation. ferent parties. Direct saving in the use of steam (heat) means
Insulation of the pipelines, including valves, was inspected less produced steam; fuel and make-up water are saved. There
during the study. The thickness of the insulation was at a proper are also fewer emissions to the atmosphere. For the power

620  ECEEE 2012 SUMMER STUDY on Energy efficiency in industry


4. UNDERTAKING HIGH IMPACT ACTIONS: TECHNOLOGY AND … 4-142-12 Suomalainen, Hyytiä

plant, this means lower electricity production, which may be • efficiency measures in steam production
much more valuable than saved steam (heat).
• efficiency measures in steam consumption.
By changing unnecessary use of middle pressure steam to
low pressure steam means that more electricity can be pro- Basic data has to be gathered from the consumption side, the
duced. In addition, savings are achieved in fuel, emissions and steam and condensate pipelines and the production site. This
additional water. means close co-operation with the auditor and all three parties.
The saving potentials must be carried out and the faults re- In field work, the auditor has to clarify the structure of the
paired as soon as possible. Continuous use and incorrect tech- steam and condensate pipelines, inspect the condition of the
niques in the use of steam and condensate increase losses all pipelines and the steam traps and other equipment, and verify
the time. Investments taking place in the future will hardly be how they work.
cheaper than those carried out right now. The analysis is carried out in close co-operation with pro-
duction, maintenance and consumption personnel. The main
attention is directed towards finding savings and making the
Audit guide system work more energy-efficiently.
Based on the pilot plant findings, it was decided that a guide Reporting much depends on the target and the findings. Eve-
is needed for industrial enterprises using steam, maintenance rything must be presented in a reader-friendly way as everyone
service suppliers and energy auditors and for all those working reading the report is not an expert in steam and condensate
closely with these companies. The consulting company drew up matters.
the audit guide and the project group gave its comments and It is very important that the customer and the auditor agree
advice during the project (Motiva 2011). where the main focus is even if the whole area has to be cov-
ered. They must also agree on the terms and ways of acting
Audit model in the field so that the audit can be carried out smoothly. The
limits of the audit must be clear in order to have the agreed
The audit model consists of four sections, which form a guide
work done in an efficient way. Use of clear boundary lines is
to the steam and condensate line audit.
recommended and a field tour to clarify the limits is advisable
Part 1 defines the guidelines of the steam and condensate
(Figure 6).
pipeline audit. It also describes the purpose and principles of a
Part 2 describes how to carry out a steam and condensate
steam and condensate audit according to the Motiva principles
audit and to report findings. It also describes the main areas
(Figure 5). The following areas are included in the steam and
where the focus should be set. The contents of this section are
condensate pipeline audit:
written in general terms, and therefore it can be adapted widely
• steam and condensate pipelines to different industrial branches, equipment selections and plant

Figure 5. Principles of a steam and condensate pipeline audit. Figure 6. Typical boundary lines for a steam and condensate
pipeline audit.

ECEEE 2012 SUMMER STUDY on Energy efficiency in industry  621


4-142-12 Suomalainen, Hyytiä 4. UNDERTAKING HIGH IMPACT ACTIONS: TECHNOLOGY AND …

sizes. Technical details or specifications of steam and conden- The guide describes the basic construction of a steam and
sate equipment and systems are not included. condensate system and how to measure the flows in each part
Table of contents, summary: of the network. Special attention is paid to balance sheets, re-
porting, online measurements and energy efficiency. There
• Summary
must be a purpose for the measurements, such as defining spe-
• Basic information cial consumption. These numbers tell the process staff how they
are running the process.
• The present status of the steam and condensate pipelines
It is very important to choose the best meter type and the
• Results of the field work correct meter size to carry out the work. To be able to measure
energy from a steam and condensate flow, you must be able to
• Energy balance of the steam and condensate pipelines
measure the flow and the pressure.
• Operational saving potential Reliable measurements are the foundation of energy man-
agement decisions. That is why strict criteria must be followed
• Saving measures and economy
when installing flow, temperature and pressure meters. Meters
• Future actions. must be regularly maintained and calibrated. Reliable measure-
ments are only a part of the entire measurement process. The
Part 3 is an example report from an imaginary paper mill where
data transfer must also be reliable and faultless.
a steam and condensate audit has been carried out. This is a
complete report so the reader can follow the steps and actions
that were carried out and how the findings were reported. In Communications
smaller companies, the report can be more compact, but it The steam and condensate energy audit model is a new and
must follow the same principles. important tool to improve energy efficiency in industry. Now
It must always be kept in mind that every industrial site is that we have achieved promising results, it is very important to
one of a kind and must be treated like one. Attention must be spread the findings of the project and the auditing method. In
paid to variations in production, operating hours, type and age this case, the most important groups to be informed are indus-
of equipment, as well as to maintenance. Part 4 gives instruc- trial companies using steam in production, especially energy
tions and advice to the maintenance department and designers. managers and maintenance departments, and also companies
Details of good installation and operation practices are given to offering steam maintenance services and their personnel. The
designers and the maintenance department. third group consists of energy auditing companies and their
People working with steam and condensate systems are given auditors who now have a guide to use and exploit in their work.
advice on how to identify and deal with problems and how to
maintain good energy efficiency. Monitoring systems must be
reliable and up-to-date. The decision of who takes care of what Benefits of the project
must be made clear to everyone involved. During maintenance, The benefits of this project can be summarised as follows:
all three sections must be kept in mind: production, pipelines
• A systematic practice for the company personnel to ascer-
and consumption. In this part, advice is also given to design-
tain and maintain energy efficiency of the steam and con-
ers with regard to the areas they must pay attention to when
densate system in an industrial plant. Usability of the steam
designing or renovating steam and condensate system. The ad-
and condensate system will improve and become more en-
vice deals with all basic areas, for example, steam pressure and
ergy efficient.
dimensioning of pipes, insulation, selection of steam traps, use
of flash steam and, of course, measurements. Examples are also • The audit model presents a uniform way to document and
shown. One person must be appointed to be in charge of the report the results of steam and condensate pipeline audits.
steam and condensate system and to supervise the work. The It also offers a comprehensive model for industrial plants
person must also have appropriate staff, equipment and money to use as a project plan and when putting such an audit out
to manage the task. Steam traps must be inspected regularly, at to tender.
least once a year.
• The measurement guide gives recommendations on meas-
In addition, a slide show was created to be presented in com-
urements and their installation (location, meter type, etc.)
pany seminars for maintenance and other departments work-
for the industrial plant to monitor energy efficiency and en-
ing with steam and condensate systems.
ergy costs. Reliable metering is the only way to divide the
costs according to consumption, serving as a robust basis
Measurement guide for emissions trading.
In addition to the audit guide, measurements were found to be • More attention should be paid to steam and condensate
an extremely important part of energy efficiency in a steam and pipelines, which are often neglected.
condensate system. To improve a steam and condensate line sys-
tem in a cost-effective way, it must also be possible to measure
the flows in a reliable manner in order to see how everything is References
working. It must also be possible to verify changes in consump- Motiva Oy, Höyry-lauhde-siirtojärjestelmä, Energiakat-
tion after investments. That is the reason why the measurement selmuksen tarkennetut toteutusohjeet (Only in Finnish),
guide was seen as a very important part of the entire survey. 2011

622  ECEEE 2012 SUMMER STUDY on Energy efficiency in industry

You might also like