FORTIS CHEMICALS PVT LTD

MONTHLY PREVENTIVE MAINTENANCE SCHEDULE FOR EQUIPMENTS


SLNO EQUIPMENT DATE
1 ACM 4-Aug 11-Aug 18-Aug 25-Aug WEEKLY
2 TFH-1/2 5-Aug 19-Aug 30-Aug EVERY 10 DAYS
4 RV-1 (3KL) 6-Aug 16-Aug 27-Aug EVERY 10 DAYS
5 RV-2(5KL) 7-Aug 18-Aug 28-Aug EVERY 10 DAYS
6 RV-3(10KL) 8-Aug 19-Aug 29-Aug EVERY 10 DAYS
7 BV1 9-Aug 20-Aug 30-Aug EVERY 10 DAYS
8 BV2 10-Aug 21-Aug 31-Aug EVERY 10 DAYS
9 BV3 11-Aug 22-Aug 30-Aug EVERY 10 DAYS
10 BV4/MELTER 12-Aug 26-Aug 31-Aug EVERY 10 DAYS
12 COOLING TOWER 1 13-Aug 23-Aug 3-Sep EVERY 10 DAYS
13 COOLING TOWER 2 14-Aug 24-Aug 4-Sep EVERY 10 DAYS
14 ALL PUMP OLEO/FO DAILY DAILY DAILY DAILY DAILY
15 ALL PUMP RASIN DAILY DAILY DAILY DAILY DAILY
16 ALL PUMP LOADING/UNLOADING DAILY DAILY DAILY DAILY DAILY
17 HOIST 1 & HOIST 2 15-Aug 25-Aug 5-Sep EVERY 10 DAYS

NOTE
ABOVE SCHEDULE IS MADE ASSUMING THE AVALIABLITY OF EQUIPMENT S FROM PROCESS
DEPT.ON MENTION DATES.THE SCHEDULE MAY BE RESUFFLED ACCORDING TO AVAILIABILITY
OF EQUIPMENTS FROM PROCESS DEPT.